CN104612694B - Freezing pipe processing method at a kind of chamber - Google Patents

Freezing pipe processing method at a kind of chamber Download PDF

Info

Publication number
CN104612694B
CN104612694B CN201510004265.3A CN201510004265A CN104612694B CN 104612694 B CN104612694 B CN 104612694B CN 201510004265 A CN201510004265 A CN 201510004265A CN 104612694 B CN104612694 B CN 104612694B
Authority
CN
China
Prior art keywords
pipe
freezing pipe
freezing
quick coupling
newborn
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510004265.3A
Other languages
Chinese (zh)
Other versions
CN104612694A (en
Inventor
吕涛
闫振斌
李天荣
谢洪波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Coal No 1 Construction Co Ltd
Original Assignee
China Coal No 1 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Coal No 1 Construction Co Ltd filed Critical China Coal No 1 Construction Co Ltd
Priority to CN201510004265.3A priority Critical patent/CN104612694B/en
Publication of CN104612694A publication Critical patent/CN104612694A/en
Application granted granted Critical
Publication of CN104612694B publication Critical patent/CN104612694B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/10Preparation of the ground
    • E21D1/12Preparation of the ground by freezing
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses freezing pipe processing method at a kind of chamber, after being drained by the water in freezing pipe, around the freezing pipe at excavated section 500mm, brush off rock with pneumatic pick, then cut off freezing pipe in excavated section position, in freezing pipe, put into polyethylene tube.The punching pipe of one band gingival cyst of mucous gland in the newborn of processing, by the punching pipe of band gingival cyst of mucous gland in the newborn and the following Plate Welding welding quick coupling I, and quick coupling I connection welded below with steel plate by the punching pipe of band gingival cyst of mucous gland in the newborn, welds a quick coupling II again in the side of freezing pipe.The punching pipe of band gingival cyst of mucous gland in the newborn is connected with the polyethylene tube putting into freezing pipe, then by moving on steel plate, with freezing pipe welded closure.Weld a steel pipe on steel plate outside freezing pipe, in the 200mm of steel pipe top, make floral tube, below steel plate, then weld the snap joint connected with steel pipe III, finally steel pipe is reached in the space of boring.This method has saved the sinking shaft duration, reduces security risk.

Description

Freezing pipe processing method at a kind of chamber
Technical field
The present invention relates to the method that freezing pipe processes, be specifically related to freezing pipe processing method at a kind of chamber.
Background technology
Freezing shaft construction in the past does not the most use to be freezed entirely deeply, freezing pipe does not pass through the chamber relevant to pit shaft, therefore, in the past freezing pipe process general wait freeze to terminate after 3~in 5 months, carry out tube drawing and freezing pipe closure, closure typically uses injects the western dreg concrete of cement bonded sand pulp grinder in pipe on ground;As freezing pipe fails to extract, use carry out perforation slip casting closure in the face of freezing pipe.Along with the increasing of the shaft construction degree of depth, pit shaft discloses water-bearing layer to be increased, and the Northwest's Jurassic stratum is because containing pore water, grouting water blockoff difficulty, the most generally preferably freezing Jurassic stratum, therefore pit shaft deep freezeout entirely in the Northwest's is more.
Summary of the invention
The deficiency existed according to prior art, it is provided that one has saved the sinking shaft duration, reduces freezing pipe processing method at the chamber of security risk.
Technical solution of the present invention realizes by the following method:
Freezing pipe processing method at a kind of chamber, the method comprises the following steps:
A. after being drained by the water in freezing pipe, around the freezing pipe at 400mm~600mm at excavated section, brush off rock with pneumatic pick, then cut off freezing pipe in excavated section position, in freezing pipe, put into polyethylene tube.
B. the punching pipe of a band gingival cyst of mucous gland in the newborn is processed, by the punching pipe of band gingival cyst of mucous gland in the newborn and the following Plate Welding welding quick coupling I, and quick coupling I connection welded below with steel plate by the punching pipe of band gingival cyst of mucous gland in the newborn, welds a quick coupling II again in the side of freezing pipe.
C. the punching pipe of band gingival cyst of mucous gland in the newborn is connected with the polyethylene tube putting into freezing pipe, then by moving on steel plate, with freezing pipe welded closure.
D. weld a steel pipe on the steel plate outside freezing pipe, in mm~250mm of steel pipe top 150, make floral tube, below steel plate, then weld a quick coupling connected with steel pipe III, finally steel pipe is reached in the space of boring.
E. will be with joint, the mouth of pipe carries out after being connected with quick coupling equipped with the high-pressure hose of high-pressure ball valve pouring into a mould concrete.
F., after concrete cast, thaw from quick coupling I, quick coupling II below, by bleeding off with the water of pipe outer void in freezing pipe after defrosting, estimate grouting amount according to defrosting drillhole height, to Grouting Pipe and pipe outside borehole standoff slip casting reinforce.
A diameter of 75mm of described polyethylene tube, a length of 30mm.
The punching length of tube of described band gingival cyst of mucous gland in the newborn is 300mm.
Described steel plate thickness is 10mm.
Described quick coupling I is 3 cun of snap joints, and described quick coupling II is 3 cun of snap joints, and described quick coupling III is 2 cun of snap joints.
The a length of 200mm of described floral tube, wraps up filling with plastic bag under floral tube, prevents from being blocked by floral tube during cast.
The invention has the beneficial effects as follows:
By using this kind of construction method, successfully implement Chamber Construction during freezing and pass through freezing pipe, use down-hole treatment freezing pipe technology, saved the sinking shaft duration, reduced security risk.
Accompanying drawing explanation
Fig. 1 is skip bucket chamber freezing pipe distribution plane figure;
Fig. 2 is that freezing pipe processes schematic diagram;
1 skip loading pocket, 2 freezing pipes, 3 borings, 4 polyethylene tubes, the punching pipe of 5 band gingivals cyst of mucous gland in the newborn, 6 quick couplings II, 7 quick couplings I, 8 quick couplings III, 9 steel plates, 10 steel pipes, 11 floral tubes, 12 excavated sections.
Detailed description of the invention
Below in conjunction with accompanying drawing, by specific embodiment, technical solution of the present invention is described further.
As shown in Figure 1 and Figure 2, when using sequence construction method, i.e. shaft construction to chamber opening part when this pit shaft freezing degree of depth exceedes during skip loading pocket 1, shaft construction, proceed to Chamber Construction, after Chamber Construction, proceed to shaft construction again.Owing to lower wellbore freezes not yet to terminate during construction skip loading pocket 1, therefore tube drawing filling sealing of hole cannot be carried out as conventional after freezing to terminate.The arrangement and method for construction used is: the freezing pipe 2 in the range of Chamber Construction closes the brine recycling freezed, and after down-hole Chamber Construction exposure freezing pipe, the saline in blow-down pipe, cuts off freezing pipe, block freezing pipe 2 in down-hole.
Specifically comprise the following steps that
A. after being drained by the water in freezing pipe 2, around the freezing pipe 2 at the 500mm away from excavated section 12, brush off rock with pneumatic pick, then cut off freezing pipe 2 in excavated section 12 position, in freezing pipe 2, put into the polyethylene tube 4 of a diameter of 75mm, a length of 30mm.
B. the punching pipe 5 of the band gingival cyst of mucous gland in the newborn of one a length of 300mm of processing, the punching pipe 5 of band gingival cyst of mucous gland in the newborn is welded 3 cun of quick couplings I 7 with following, thickness is that the steel plate 9 of 10mm welds, and 3 cun of quick coupling I 7 connections welded below with steel plate 9 by the punching pipe 5 of band gingival cyst of mucous gland in the newborn, weld 3 cun of quick couplings II 6 again in the side of freezing pipe 2.
C. the punching pipe 5 of band gingival cyst of mucous gland in the newborn is connected with the polyethylene tube 4 putting into freezing pipe 2, then by moving on steel plate 9, with freezing pipe 2 welded closure.
D. weld a steel pipe 10 on the steel plate 9 outside freezing pipe 2, by making the floral tube 11 of a length of 200mm in steel pipe 10 top 200mm, under floral tube, wrap up filling with plastic bag, prevent from being blocked by floral tube during cast,
Then below steel plate 9, weld the 2 cun of snap joints III 8 connected with steel pipe 10, finally steel pipe 10 is reached in the space of boring 3.
E. will be with joint, the mouth of pipe carries out after being connected with quick coupling equipped with the high-pressure hose of high-pressure ball valve pouring into a mould concrete.
F. after concrete cast, thaw below I 7,3 cun of quick couplings II 6 of 3 cun of quick couplings, to bleed off with the water of pipe outer void in freezing pipe after defrosting, according to thawing, grouting amount is highly estimated in boring 3, to Grouting Pipe and pipe outside boring 3 gap slip casting reinforce.
By using this kind of construction method, successfully implement Chamber Construction during freezing and pass through freezing pipe, use down-hole treatment freezing pipe technology, saved the sinking shaft duration, reduced security risk.

Claims (6)

1. freezing pipe processing method at a chamber, it is characterised in that: the method comprises the following steps:
A. after being drained by the water in freezing pipe, around the freezing pipe at 400mm~600mm of excavated section, brush off rock with pneumatic pick, then cut off freezing pipe in excavated section position, in freezing pipe, put into polyethylene tube;
B. the punching pipe of a band gingival cyst of mucous gland in the newborn is processed, by the punching pipe of band gingival cyst of mucous gland in the newborn and the following Plate Welding welding quick coupling I, and quick coupling I connection welded below with steel plate by the punching pipe of band gingival cyst of mucous gland in the newborn, welds a quick coupling II again in the side of freezing pipe;
C. the punching pipe of band gingival cyst of mucous gland in the newborn is connected with the polyethylene tube putting into freezing pipe, then by moving on steel plate, with freezing pipe welded closure;
D. weld a steel pipe on the steel plate outside freezing pipe, in mm~250mm of steel pipe top 150, make floral tube, below steel plate, then weld the snap joint connected with steel pipe III, finally steel pipe is reached in the space of boring;
E. will be with joint, the mouth of pipe carries out after being connected with quick coupling equipped with the high-pressure hose of high-pressure ball valve pouring into a mould concrete;
F., after concrete cast, thaw from quick coupling I, quick coupling II below, by bleeding off with the water of pipe outer void in freezing pipe after defrosting, estimate grouting amount according to defrosting drillhole height, to Grouting Pipe and pipe outside borehole standoff slip casting reinforce.
Freezing pipe processing method at a kind of chamber, it is characterised in that: a diameter of 75mm of described polyethylene tube, a length of 30mm.
Freezing pipe processing method at a kind of chamber, it is characterised in that: the punching length of tube of described band gingival cyst of mucous gland in the newborn is 300mm.
Freezing pipe processing method at a kind of chamber, it is characterised in that: described steel plate thickness is 10mm.
Freezing pipe processing method at a kind of chamber, it is characterised in that: described quick coupling I is 3 cun of snap joints, and described quick coupling II is 3 cun of snap joints, and described snap joint III is 2 cun of snap joints.
Freezing pipe processing method at a kind of chamber, it is characterised in that: a length of 200mm of described floral tube, wraps up filling with plastic bag under floral tube, prevents from being blocked by floral tube during cast.
CN201510004265.3A 2015-01-06 2015-01-06 Freezing pipe processing method at a kind of chamber Expired - Fee Related CN104612694B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510004265.3A CN104612694B (en) 2015-01-06 2015-01-06 Freezing pipe processing method at a kind of chamber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510004265.3A CN104612694B (en) 2015-01-06 2015-01-06 Freezing pipe processing method at a kind of chamber

Publications (2)

Publication Number Publication Date
CN104612694A CN104612694A (en) 2015-05-13
CN104612694B true CN104612694B (en) 2017-01-04

Family

ID=53147319

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510004265.3A Expired - Fee Related CN104612694B (en) 2015-01-06 2015-01-06 Freezing pipe processing method at a kind of chamber

Country Status (1)

Country Link
CN (1) CN104612694B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577987B (en) * 2018-11-30 2024-05-10 陕西中能煤田有限公司 Construction method for penetrating freezing pipe of casing through inclined shaft wall
CN111119952A (en) * 2020-01-06 2020-05-08 中煤第一建设有限公司 Reinforcing and waterproof method for inclined shaft wall jointing composite steel cylinder

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202187765U (en) * 2011-08-17 2012-04-11 中煤矿山建设集团有限责任公司 Head structure of local freezer for double plastic tube
CN102418535A (en) * 2011-10-09 2012-04-18 陕西彬长胡家河矿业有限公司 Plugging and grouting method for exposing freezing pipes in underground engineering
CN103277103A (en) * 2013-05-20 2013-09-04 陕西彬长矿业集团有限公司 None-full-depth freezing method for penetrating through ultra-thick water-rich bed rock in shaft deepening
CN103912241A (en) * 2014-04-10 2014-07-09 西安博深煤矿安全科技有限公司 Refrigeration cooling system under mine

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202187765U (en) * 2011-08-17 2012-04-11 中煤矿山建设集团有限责任公司 Head structure of local freezer for double plastic tube
CN102418535A (en) * 2011-10-09 2012-04-18 陕西彬长胡家河矿业有限公司 Plugging and grouting method for exposing freezing pipes in underground engineering
CN103277103A (en) * 2013-05-20 2013-09-04 陕西彬长矿业集团有限公司 None-full-depth freezing method for penetrating through ultra-thick water-rich bed rock in shaft deepening
CN103912241A (en) * 2014-04-10 2014-07-09 西安博深煤矿安全科技有限公司 Refrigeration cooling system under mine

Also Published As

Publication number Publication date
CN104612694A (en) 2015-05-13

Similar Documents

Publication Publication Date Title
CN104675408B (en) High hydraulic pressure extra long distance large cross-section tunnel liquid nitrogen freezing system and shield shield tail brush quick change method
CN107605498B (en) Construction method for horizontal grouting reinforcement structure of end head of shield tunnel in water-rich sandy pebble stratum
CN107217691A (en) For city underground leak stopping and the method for strengthening construction
CN104895098A (en) Piping blocking structure outside deep foundation pit underground diaphragm wall and grouting treatment method thereof
CN104832196B (en) Pipe curtain freezing process supporting construction and its construction method
CN107237650A (en) A kind of drilling siphon drainage system and method for being used to handle the infiltration of Tunnel wall
CN205975649U (en) Freezing pipe curtain steel pipe supporting construction
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN103883797A (en) Construction method of steel wire mesh framework plastic composite pipe
CN104612694B (en) Freezing pipe processing method at a kind of chamber
CN106677198A (en) Well plugging method under dynamic water level state
CN109519150A (en) One kind being directed to the biggish plugging dewatering well device and method of water yield
CN113404430A (en) Safe embedding method of freezing pipe
CN204728353U (en) Piping plugging structure outside deep foundation ditch diaphragm wall
JP5443200B2 (en) Construction method of shaft
CN207862925U (en) A kind of slip casting casing device
JP2009068213A (en) Construction method for underground structure using caisson, and caisson with cut-off device
CN206800431U (en) A kind of sealing bottom type caisson wall
CN205077502U (en) A blowout preventer for holing gush sand and emit water
CN209444310U (en) A kind of plugging dewatering well structure
CN103527205A (en) Shield underwater oblique crossing hole entering construction method
CN207109745U (en) Contain high water head plugging structure in a kind of dam foundation water delivery bottom
JP2007154635A (en) Tunnel repairing method no. 2
CN107313437A (en) The shut-in well construction method of foundation ditch pressure-bearing dewatering well
CN205025499U (en) Subway contact passageway freezes to excavate guard gate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170104

Termination date: 20220106