JP2010229761A - Construction device and construction method for base course reinforced concrete - Google Patents

Construction device and construction method for base course reinforced concrete Download PDF

Info

Publication number
JP2010229761A
JP2010229761A JP2009080316A JP2009080316A JP2010229761A JP 2010229761 A JP2010229761 A JP 2010229761A JP 2009080316 A JP2009080316 A JP 2009080316A JP 2009080316 A JP2009080316 A JP 2009080316A JP 2010229761 A JP2010229761 A JP 2010229761A
Authority
JP
Japan
Prior art keywords
concrete
section
work
base
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009080316A
Other languages
Japanese (ja)
Other versions
JP5355175B2 (en
Inventor
Shigeji Iwanaga
茂治 岩永
Akira Kimura
晃 木村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP2009080316A priority Critical patent/JP5355175B2/en
Publication of JP2010229761A publication Critical patent/JP2010229761A/en
Application granted granted Critical
Publication of JP5355175B2 publication Critical patent/JP5355175B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction device and a construction method for base course reinforced concrete which can reduce the amount of construction time of the base course reinforced concrete and which can reduce a period of construction. <P>SOLUTION: The construction device 1 of the base course reinforced concrete is used for constructing the base course reinforced concrete 100 in turn in a tunnel in the extension direction of the tunnel every predetermined section which is divided in the extension direction of the tunnel. The construction device 1 of the base course reinforced concrete includes a base truck 2, a concrete pouring pipe 3, and a passage. The base truck 2 is extended between the front end of the planned section for concrete pouring and the rear end of the section which follows in the rear along the side which is in the extension direction of the tunnel of the planned section for concrete pouring where assembly work of a form and reinforcements has completed and along the side which is along the extension direction of the tunnel of the rear section where concrete pouring work is performed after the planned section for concrete pouring. The concrete pouring pipe 3 is provided on the base truck 2, and the passage is provided on the base truck 2 so that it can be extended from the rear end to the front end of the base truck 2. <P>COPYRIGHT: (C)2011,JPO&INPIT

Description

本発明は、工期を短縮可能な路盤鉄筋コンクリートの施工装置及び施工方法に関する。   The present invention relates to a construction apparatus and construction method for roadbed reinforced concrete capable of shortening the construction period.

トンネルの延長方向に沿って区切られた所定区間毎にトンネルの延長方向に沿って順番にトンネル内に路盤鉄筋コンクリートを施工する際に、コンクリート打設予定区間までコンクリートミキサー車を移動してコンクリート打設予定区間にコンクリートを打設することが知られている(例えば、特許文献1等参照)。しかしながら、このようにトンネル内においてコンクリート打設予定区間まで車を運転して移動する場合は、種々の問題があった。例えば、車をトンネルの一方の坑口から出入りさせる場合、坑口からコンクリート打設予定区間までの距離が長い場合は、コンクリート打設予定区間から坑口までバック運転が必要になり、安全性に問題があった。
そこで、コンクリート打設台車を用い、このコンクリート打設台車を移動させてコンクリート打設予定区間にコンクリートを打設する方法が知られている(例えば、特許文献2等参照)。
When constructing subbase reinforced concrete in the tunnel in order along the tunnel extension direction for each predetermined section divided along the tunnel extension direction, move the concrete mixer truck to the concrete placement planned section and cast the concrete It is known to cast concrete in a planned section (see, for example, Patent Document 1). However, there are various problems when driving and moving to the concrete placement planned section in the tunnel. For example, when a vehicle is moved in and out from one tunnel entrance, if the distance from the tunnel entrance to the concrete placement section is long, back operation is required from the concrete placement section to the tunnel entrance, which is a safety issue. It was.
Therefore, there is known a method in which concrete is placed in a concrete placement planned section by using a concrete placement carriage and moving the concrete placement carriage (see, for example, Patent Document 2).

特開2003−138886号公報JP 2003-138886 A 特開2005−90077号公報Japanese Patent Laying-Open No. 2005-90077

しかしながら、コンクリート打設予定区間にコンクリートを打設するためには、コンクリート打設予定区間に鉄筋及び型枠を組み立てておく必要がある。特許文献2では、ある任意の区間に路盤鉄筋コンクリートを施工する場合に、ある任意の区間に鉄筋及び型枠を組み立ててコンクリート打設予定区間を形成し、その後、当該コンクリート打設予定区間にコンクリートを打設するので、ある任意の区間の路盤鉄筋コンクリートを施工する時間は、ある任意の区間での鉄筋及び型枠の組立作業時間+ある任意の区間でのコンクリート打設時間となる。この場合、1つ目の区間に対する型枠及び鉄筋の組立作業の開始から2つ目の区間に対するコンクリート打設作業の終了までにかかる総合時間は、(1つ目の区間での鉄筋及び型枠の組立作業時間)+(1つ目の区間に対するコンクリート打設時間)+(2つ目の区間での鉄筋及び型枠の組立作業時間)+(2つ目の区間に対するコンクリート打設時間)となる。この場合、各作業に1日かかるとすれば、上記総合時間は、4日間かかることになる。このように、施工時間が長くなり、工期が長期化するという問題点があった。
本発明は、上記問題点に鑑みてなされたもので、路盤鉄筋コンクリートの施工時間を短縮でき、工期を短縮できる路盤鉄筋コンクリートの施工装置及び施工方法を提供する。
However, in order to place concrete in the concrete placement planned section, it is necessary to assemble a reinforcing bar and a formwork in the concrete placement section. In patent document 2, when constructing roadbed reinforced concrete in a certain arbitrary section, a concrete placement schedule section is formed by assembling a reinforcing bar and a formwork in a certain arbitrary section, and then concrete is placed in the concrete placement section. Since the placement is performed, the time for constructing the roadbed reinforced concrete in a certain arbitrary section is the time for assembling the reinforcing bars and the formwork in the certain arbitrary section + the concrete placing time in the certain arbitrary section. In this case, the total time taken from the start of the assembly work of the formwork and rebar for the first section to the end of the concrete placement work for the second section is (rebar and formwork in the first section). Assembly time) + (concrete placement time for the first section) + (rebar and formwork assembly time for the second section) + (concrete placement time for the second section) and Become. In this case, if each work takes 1 day, the total time will take 4 days. As described above, there is a problem that the construction time becomes longer and the construction period becomes longer.
The present invention has been made in view of the above problems, and provides a roadbed reinforced concrete construction apparatus and method that can shorten the construction time of roadbed reinforced concrete and shorten the construction period.

本発明に係る路盤鉄筋コンクリートの施工装置は、トンネルの延長方向に沿って区切られた所定区間毎にトンネルの延長方向に沿って順番にトンネル内に路盤鉄筋コンクリートを施工する路盤鉄筋コンクリートの施工装置において、型枠及び鉄筋の組立作業が終了したコンクリート打設予定区間のトンネルの延長方向に沿った横と当該コンクリート打設予定区間の後にコンクリート打設作業を行う後の区間のトンネルの延長方向に沿った横とに沿ってコンクリート打設予定区間の先端部と後の区間の後端部とに渡って延長するベース台車と、ベース台車の後端部から先端部まで延長するようにベース台車に設けられたコンクリート打設管と、ベース台車の後端部から先端部まで延長するようにベース台車上に設けられた通路とを備えたので、コンクリート打設管を用いてコンクリート打設予定区間に対するコンクリート打設作業を行えるとともに、ベース台車の後端部と先端部との間を通路を経由して通行できるので、後の区間での型枠及び鉄筋の組立作業に必要な資材の運搬や作業員の往来、前の区間での型枠撤去作業で撤去された型枠の回収運搬や作業員の往来が可能となるため、コンクリート打設予定区間に対するコンクリート打設作業と後の区間に対する型枠及び鉄筋の組立作業とを同時並行して行うことや、前の区間に対する型枠撤去作業とコンクリート打設予定区間に対するコンクリート打設作業と後の区間に対する型枠及び鉄筋の組立作業とを同時並行して行うことができるようになり、路盤鉄筋コンクリートの施工工期を短縮できる。
本発明の路盤鉄筋コンクリートの施工装置を使用する路盤鉄筋コンクリートの施工方法は、型枠及び鉄筋の組立作業が終了したコンクリート打設予定区間に対するコンクリート打設作業と、当該コンクリート打設予定区間の後にコンクリート打設作業を行う後の区間に対する型枠及び鉄筋の組立作業とを同時並行して行うので、路盤鉄筋コンクリートの施工時間を短縮でき、よって、路盤鉄筋コンクリートの施工工期を短縮できる。
既にコンクリート打設作業を終了してコンクリートが固化した上記コンクリート打設予定区間の前の区間に対する型枠撤去作業と、上記コンクリート打設予定区間に対するコンクリート打設作業と、後の区間に対する型枠及び鉄筋の組立作業とを同時並行して行うので、路盤鉄筋コンクリートの施工工期を短縮できる。
ベース台車の後端部と先端部との間を移動可能なようにベース台車上に設けられた資材運搬用台車を備えたので、資材運搬用台車を、後の区間での型枠及び鉄筋の組立作業に必要な資材の運搬作業や前の区間での型枠撤去作業で撤去された型枠の回収運搬作業に用いることにより、運搬作業が容易となる。
ベース台車の後端部から先端部まで延長するようにベース台車に設けられた水送管を備え、後端がコンクリート供給源に接続されたコンクリート打設管内を洗浄する際、水送管の後端が水供給源に接続され、コンクリート打設管の先端開口と水送管の先端口とが連通するように連結され、水供給源から水送管経由でコンクリート打設管内に供給されてコンクリート打設管内を洗浄した水がコンクリート供給源に送り出されるようにしたので、コンクリート打設管内を定期的に洗浄できるようになり、また、コンクリート打設管内を洗浄した水の排水処理が容易となる。
ベース台車は、複数の単位台車により構成され、単位台車は、両方の脚部と脚部の上端同士を連結する梁部とを有した門形フレームと、門形フレームの両方の脚部の下端に設けられた走行車輪とにより形成され、ベース台車は、所定間隔隔てて設けられた各単位台車の梁部同士が連結部材で連結されたことにより形成されたので、区間の長さに応じたベース台車を形成でき、区間の長さを自由に設定できるようになる。
A roadbed reinforced concrete construction device according to the present invention is a roadbed reinforced concrete construction device for constructing roadbed reinforced concrete in a tunnel in order along a tunnel extension direction for each predetermined section divided along a tunnel extension direction. The side along the extension direction of the tunnel in the planned concrete placement section where the assembly work of the frame and rebar is completed, and the side along the extension direction of the tunnel in the section after the concrete placement work is performed after the planned concrete placement section And a base carriage that extends from the rear end of the base carriage to the front end of the base section, and the base carriage that extends from the rear end of the base carriage to the front end. Since the concrete placement pipe and the passage provided on the base carriage so as to extend from the rear end portion to the front end portion of the base carriage, In addition to being able to perform concrete placement work on the concrete placement planned section using a concrete placement pipe, it is possible to pass between the rear end and the front end of the base carriage via a passage, so the formwork in the later section Also, it is planned to cast concrete because it will be possible to transport materials necessary for assembling of reinforcing bars and traffic of workers, and to collect and transport molds removed in the previous section and to transport workers. Perform concrete placement work for the section and formwork and rebar assembly work for the subsequent section at the same time, formwork removal work for the previous section and concrete placement work for the planned concrete placement section and later The formwork and rebar assembly work for the section can be performed in parallel, and the construction period of roadbed reinforced concrete can be shortened.
A roadbed reinforced concrete construction method using the roadbed reinforced concrete construction apparatus of the present invention includes a concrete placement operation for a concrete placement planned section after the assembly work of a formwork and a reinforcing bar, and a concrete placement operation after the concrete placement section. Since the formwork and rebar assembly work for the section after the installation work is performed simultaneously, the construction time of the roadbed reinforced concrete can be shortened, and therefore the construction period of the roadbed reinforced concrete can be shortened.
The formwork removal work for the section before the concrete placement section, the concrete has already solidified after the concrete placement work, the concrete placement work for the concrete placement section, the formwork for the subsequent section, and Since the rebar assembly work is performed in parallel, the construction period of roadbed reinforced concrete can be shortened.
Since the material transportation carriage provided on the base carriage so as to be movable between the rear end portion and the front end portion of the base carriage is provided, the material transportation carriage is attached to the formwork and the reinforcing bar in the later section. By using the material necessary for the assembly work for the work for carrying the material and for collecting and carrying the form removed by the work for removing the form in the previous section, the work for carrying becomes easy.
When the inside of the concrete placement pipe with the rear end connected to the concrete supply source is cleaned, the water supply pipe is provided on the base carriage so as to extend from the rear end to the front end of the base carriage. The end is connected to the water supply source, the tip opening of the concrete placement pipe and the tip end of the water feed pipe are connected to communicate with each other, and the concrete is supplied from the water supply source through the water feed pipe into the concrete placement pipe. Since the water in which the inside of the placing pipe has been washed is sent to the concrete supply source, the inside of the concrete placing pipe can be washed periodically, and the drainage treatment of the water in which the inside of the concrete placing pipe has been washed becomes easy. .
The base carriage is composed of a plurality of unit carriages. The unit carriage has a portal frame having both leg portions and a beam portion connecting the upper ends of the leg portions, and lower ends of both leg portions of the portal frame. The base carriage is formed by connecting the beam portions of each unit carriage provided at a predetermined interval with a connecting member, so that it corresponds to the length of the section. A base carriage can be formed, and the length of the section can be set freely.

路盤鉄筋コンクリートの施工方法の手順を示す図。The figure which shows the procedure of the construction method of a roadbed reinforced concrete. 路盤鉄筋コンクリートが施工されたトンネルの断面図。Sectional drawing of the tunnel where roadbed reinforced concrete was constructed. 路盤鉄筋コンクリートの施工装置の平面図。The top view of the construction equipment of a roadbed reinforced concrete. 路盤鉄筋コンクリートの施工装置の断面図。Sectional drawing of the construction equipment of a roadbed reinforced concrete. 路盤鉄筋コンクリートの施工装置の分解斜視図。The exploded perspective view of the construction equipment of a roadbed reinforced concrete. コンクリート打設管の洗浄方法の手順を示す図。The figure which shows the procedure of the washing | cleaning method of a concrete placement pipe.

本形態では、図2;3に示すように、トンネル延長方向Xに沿って区切られた所定区間毎にトンネル延長方向Xに沿って順番にトンネル内200に路盤鉄筋コンクリート100を施工する場合、施工装置1を用いる。本形態による路盤鉄筋コンクリートの施工装置1は、例えば、鉄道用トンネルの路盤鉄筋コンクリートを施工する際に用いられる。
例えば図2に示すように、トンネル内200の断面における下部にはインバートコンクリート205が形成され、インバートコンクリート205の上に置換コンクリート204が設けられる。置換コンクリート204の上面中央には、トンネル延長方向Xに沿って延長するように形成された中央水路81と、中央水路81より幅広で中央水路の上部に設けられた中央溝82とを備える。中央溝82は、中央水路81の上部開口83の側縁84より延長する側底路85と、側底路85より立ち上がる側壁86とを備える。中央水路81の上部開口83は水路蓋87で塞がれる。施工装置1は、トンネル延長方向Xに沿って移動可能なように中央溝82の側底路85上に設置される。路盤鉄筋コンクリート100は、中央溝82の上部開口88の両側部分、即ち、中央溝82の上部開口縁89とトンネルの壁部201との間に施工される。
In this embodiment, as shown in FIGS. 2 and 3, when the roadbed reinforced concrete 100 is constructed in the tunnel 200 in order along the tunnel extension direction X for each predetermined section divided along the tunnel extension direction X, 1 is used. The construction device 1 for roadbed reinforced concrete according to this embodiment is used, for example, when building roadbed reinforced concrete for a railway tunnel.
For example, as shown in FIG. 2, invert concrete 205 is formed in the lower part of the cross section of the tunnel 200, and replacement concrete 204 is provided on the invert concrete 205. At the center of the upper surface of the replacement concrete 204, a central water channel 81 formed so as to extend along the tunnel extension direction X and a central groove 82 that is wider than the central water channel 81 and provided at the upper part of the central water channel are provided. The central groove 82 includes a side bottom channel 85 extending from the side edge 84 of the upper opening 83 of the central water channel 81 and a side wall 86 rising from the side bottom channel 85. The upper opening 83 of the central water channel 81 is closed with a water channel cover 87. The construction apparatus 1 is installed on the side bottom path 85 of the central groove 82 so as to be movable along the tunnel extension direction X. The roadbed reinforced concrete 100 is applied to both sides of the upper opening 88 of the central groove 82, that is, between the upper opening edge 89 of the central groove 82 and the tunnel wall 201.

つまり、施工装置1は、図3に示すように、コンクリート打設予定区間91のトンネルの延長方向に沿った横と型枠及び鉄筋組立予定区間92のトンネルの延長方向に沿った横とに沿ってコンクリート打設予定区間91の先端部91aと型枠及び鉄筋組立予定区間92の後端部92aとに渡って延長する長さに形成される。
図3乃至図5に示すように、施工装置1は、ベース台車2、コンクリート打設管3、通路4、水送管5、資材運搬用台車6、資材資材運搬用台車走行レール7とを備える。
That is, as shown in FIG. 3, the construction apparatus 1 is along the side along the extension direction of the tunnel of the concrete placement scheduled section 91 and the side of the formwork and the reinforcing bar assembly scheduled section 92 along the extension direction of the tunnel. Thus, the length is formed to extend over the leading end portion 91a of the concrete placement planned section 91 and the rear end section 92a of the formwork and reinforcing bar assembly scheduled section 92.
As shown in FIGS. 3 to 5, the construction apparatus 1 includes a base carriage 2, a concrete placing pipe 3, a passage 4, a water feeding pipe 5, a material carrying carriage 6, and a material / material carrying carriage running rail 7. .

ベース台車2は、複数の単位台車21が連結部材22で連結されて形成される。図3に示すように、ベース台車2は、コンクリート打設予定区間91の横と型枠及び鉄筋組立予定区間92の横とに沿って延長する長さに形成され、中央溝82の側底路85上に設置される。つまり、コンクリート打設予定区間91と型枠及び鉄筋組立予定区間92とを足した合計区間長以上の長さに形成される。   The base carriage 2 is formed by connecting a plurality of unit carriages 21 with connecting members 22. As shown in FIG. 3, the base carriage 2 is formed to have a length extending along the side of the concrete placing scheduled section 91 and the side of the formwork and the reinforcing bar assembly scheduled section 92, and the side bottom path of the central groove 82. 85 is installed. That is, it is formed to have a length that is equal to or greater than the total section length obtained by adding the concrete placement scheduled section 91 and the formwork and reinforcing bar assembly scheduled section 92.

図5に示すように、単位台車21は、門形フレーム23と、門形フレーム23の両方の脚部24の下端部に設けられた走行車輪25とにより形成される。
門形フレーム23は、両方の脚部24;24と、脚部24;24の上端同士を連結する梁部26とを備える。ベース台車2は、複数の単位台車21の梁部26が所定間隔を隔てて互いに平行に位置され、互いに平行に位置された隣り合う梁部26と梁部26とが連結部材22で連結されて形成される。
As shown in FIG. 5, the unit carriage 21 is formed by a portal frame 23 and traveling wheels 25 provided at lower ends of both leg portions 24 of the portal frame 23.
The portal frame 23 includes both leg portions 24; 24 and a beam portion 26 that connects the upper ends of the leg portions 24; 24 to each other. In the base carriage 2, the beam portions 26 of the plurality of unit carriages 21 are positioned in parallel with each other at a predetermined interval, and the adjacent beam portions 26 and the beam portions 26 that are positioned in parallel with each other are connected by the connecting member 22. It is formed.

走行車輪25は、脚部24の下端に梁部26と直交する方向(トンネル延長方向X)に延長するように設けられた車輪取付体27の両端部の下端に取付けられる。即ち、単位台車21は、4個の走行車輪25と2個の側壁側車輪31とを備える。即ち、トンネル延長方向Xに転がる2つの走行車輪25;25がトンネル延長方向Xに沿って所定間隔を隔てて設けられる。このように、トンネル延長方向Xに延長する車輪取付体27の両端部の下端に走行車輪25を備えたので、自立する単位台車21となり、単位台車21同士を連結してベース台車2を組み立てる作業が容易となる。また、単位台車21が4個の走行車輪25を備えたので、走行車輪1個当たりの転がり摩擦が小さくなる。2個の側壁側車輪31は、両方の側壁86に接触して滑走するように両方の脚部24;24の側面に設置される。この側壁側車輪31を備えたので、施工装置1を坑内側から坑口側に正確に直進させることができる。   The traveling wheels 25 are attached to the lower ends of both ends of a wheel attachment body 27 provided at the lower end of the leg portion 24 so as to extend in a direction orthogonal to the beam portion 26 (tunnel extension direction X). That is, the unit carriage 21 includes four traveling wheels 25 and two sidewall wheels 31. That is, two traveling wheels 25; 25 that roll in the tunnel extension direction X are provided along the tunnel extension direction X at a predetermined interval. As described above, since the traveling wheels 25 are provided at the lower ends of both ends of the wheel attachment body 27 extending in the tunnel extending direction X, the unit carriage 21 becomes self-supporting, and the base carriage 2 is assembled by connecting the unit carriages 21 to each other. Becomes easy. Further, since the unit carriage 21 includes the four traveling wheels 25, the rolling friction per traveling wheel is reduced. The two side wall wheels 31 are installed on the side surfaces of both legs 24; 24 so as to slide in contact with both side walls 86. Since this side wall side wheel 31 is provided, the construction apparatus 1 can be made to go straight from the mine inner side to the pit side accurately.

連結部材22は、例えば、断面L字形状のアングルと呼ばれるような棒状鋼材を用いる。例えば、隣り合う単位台車21の梁部26の中央部同士が第1の棒状鋼材22aで連結され、隣り合う単位台車21の梁部26の一端部同士が第2の棒状鋼材22bで連結され、隣り合う単位台車21の梁部26の他端部同士が第3の棒状鋼材22cで連結される。従って、複数の単位台車21が第1乃至第3の棒状鋼材22a乃至22cによって順次連結されることにより所定の長さのベース台車2が形成される。   The connecting member 22 is made of, for example, a rod-shaped steel material called an angle having an L-shaped cross section. For example, the central portions of the beam portions 26 of the adjacent unit carts 21 are connected by a first bar-shaped steel material 22a, and one end portions of the beam portions 26 of the adjacent unit carts 21 are connected by a second bar-shaped steel material 22b. The other ends of the beam portions 26 of the adjacent unit carriages 21 are connected by a third bar-shaped steel material 22c. Accordingly, the base carriage 2 having a predetermined length is formed by sequentially connecting the plurality of unit carriages 21 by the first to third rod-shaped steel members 22a to 22c.

コンクリート打設管3は、ベース台車2上における梁部26の一端と第2の棒状鋼材22bとの間(又は梁部26の他端と第3の棒状鋼材22cとの間)に、ベース台車2の全長に渡って連続するように設置されてベース台車2の梁部26に取付けられる。   The concrete placing pipe 3 is provided between the one end of the beam portion 26 on the base carriage 2 and the second rod-shaped steel material 22b (or between the other end of the beam portion 26 and the third rod-shaped steel material 22c). 2 is installed so as to be continuous over the entire length of 2 and attached to the beam portion 26 of the base carriage 2.

通路4は、ベース台車における第1の棒状鋼材22aと第2の棒状鋼材22bとの間、及び、第1の棒状鋼材22aと第3の棒状鋼材22cとの間に設置された足場板4aにより形成される。通路4は、複数の足場板4aがベース台車2の全長に渡って連続するように設置されることで形成される。   The passage 4 is formed by a scaffold plate 4a installed between the first bar-shaped steel material 22a and the second bar-shaped steel material 22b and between the first bar-shaped steel material 22a and the third bar-shaped steel material 22c in the base carriage. It is formed. The passage 4 is formed by installing a plurality of scaffolding plates 4 a so as to continue over the entire length of the base carriage 2.

水送管5は、ベース台車2上における梁部26の他端と第3の棒状鋼材22cとの間(又は梁部26の一端と第2の棒状鋼材22bとの間)に、ベース台車2の全長に渡って連続するように設置されてベース台車2の梁部26に取付けられる。   The water feed pipe 5 is disposed between the other end of the beam portion 26 on the base carriage 2 and the third rod-shaped steel material 22c (or between one end of the beam portion 26 and the second rod-shaped steel material 22b). And is attached to the beam portion 26 of the base carriage 2.

資材運搬用台車6は、例えば、矩形板状の資材置台6aと、資材置台6aの矩形の4角部の下面から下方に突出するように設けられた脚6bと、各脚6bの下端に設けられた走行用滑車6cとを備える。   The material carrying cart 6 is, for example, a rectangular plate-shaped material table 6a, a leg 6b provided so as to protrude downward from the lower surface of the rectangular four corners of the material table 6a, and a lower end of each leg 6b. And a traveling pulley 6c.

資材運搬用台車走行レール7は、第1の棒状鋼材22aと第2の棒状鋼材22bとにより形成されるか、あるいは、第1の棒状鋼材22aと第3の棒状鋼材22cとにより形成される。
つまり、資材運搬用台車6の左右の走行用滑車6c;6cの間隔と、第1の棒状鋼材22aと第2の棒状鋼材22bとの間隔、あるいは、第1の棒状鋼材22aと第3の棒状鋼材22cとの間隔とが一致するように構成され、資材運搬用台車6の左右の走行用滑車6c;6cが資材運搬用台車走行レール7上を滑走可能に形成される。
The material carrying bogie travel rail 7 is formed of the first bar-shaped steel material 22a and the second bar-shaped steel material 22b, or is formed of the first bar-shaped steel material 22a and the third bar-shaped steel material 22c.
That is, the distance between the left and right traveling pulleys 6c; 6c of the material transporting carriage 6 and the distance between the first bar-shaped steel material 22a and the second bar-shaped steel material 22b, or the first bar-shaped steel material 22a and the third bar-shaped It is comprised so that the space | interval with the steel material 22c may correspond, and the left and right traveling pulleys 6c; 6c of the material conveying cart 6 are formed to be slidable on the material conveying cart traveling rail 7.

図1に基いて、施工装置1を用いた路盤鉄筋コンクリート100の施工方法を説明する。
例えば、1日に施工するコンクリート打設予定区間の長さを施工装置1の長さの半分に設定する。例えば、1日のコンクリート打設予定区間の長さを60mとすれば、施工装置1は長さ120mのものを使用する。
Based on FIG. 1, the construction method of the roadbed reinforced concrete 100 using the construction apparatus 1 is demonstrated.
For example, the length of the concrete placement planned section to be constructed on one day is set to half the length of the construction apparatus 1. For example, when the length of the concrete placement schedule for one day is 60 m, the construction apparatus 1 is 120 m long.

まず、図1(a)に示すように、施工装置1の先端側半分に横に位置する中央溝82の上部開口88の両側部分を第1区間aとし、この第1区間aでの鉄筋及び型枠の組立作業を行う。この場合、資材運搬用台車6を利用して鉄筋や型枠などの資材を第1区間aに運搬し、かつ、通路4を利用して作業員が資材置場101と第1区間aとの間を往来する。第1区間aでの鉄筋及び型枠の組立作業が終了したならば、この第1区間aがコンクリート打設予定区間となる。   First, as shown to Fig.1 (a), the both sides of the upper opening 88 of the center groove | channel 82 located laterally in the front end side half of the construction apparatus 1 are made into the 1st area a, and the reinforcement in this 1st area a and Perform assembly work for the formwork. In this case, materials such as reinforcing bars and formwork are transported to the first section a using the material transporting carriage 6, and the worker uses the passage 4 between the material storage area 101 and the first section a. Come and go. If the rebar and formwork assembly work in the first section a is completed, the first section a becomes the concrete placement scheduled section.

次に、図1(b)に示すように、コンクリート供給源としてのコンクリートミキサー車(生コン車)110のコンクリート供給管111をポンプ車112に搭載されたコンクリート圧送ポンプ113の吸込口に繋ぎ、コンクリート圧送ポンプ113の吐出口とコンクリート打設管3の後端開口とを連結管114で連通可能に連結する。また、ポンプ車112で施工装置1を牽引できるように施工装置1のベース台車2の後端とポンプ車112とを牽引ロープ115で連結する。そして、コンクリート圧送ポンプ113を駆動してコンクリートミキサー車110からの生コンクリートをコンクリート打設管3の先端開口3tに圧送することにより、第1区間aであるコンクリート打設予定区間に対するコンクリート打設作業を行うとともに、当該コンクリート打設予定区間の後にコンクリート打設作業を行う後の区間である第2区間b、即ち、施工装置1の後端側半分に横に位置する第2区間bに対する型枠及び鉄筋の組立作業を行う。つまり、コンクリート打設予定区間91の先端部91aと型枠及び鉄筋組立予定区間92の後端部92aとに渡って延長するように施工装置1を設置し、第1区間a(コンクリート打設予定区間)に対するコンクリート打設作業と第2区間b(後の区間)に対する型枠及び鉄筋の組立作業とを同時並行して行う。尚、第1区間aに対するコンクリート打設作業は、ポンプ車112で施工装置1を少しずつ矢印f方向(坑内側から坑口側)に牽引することによってコンクリート打設管3の先端開口3t側を第1区間aの先端側a1から後端側a2に移動しながら行う。また、中央溝82の上部開口88の両側部分にある左右の第1区間aの領域にコンクリート打設管3の先端部分を首振りしながらコンクリートを打設するため、コンクリート打設管3の先端側は、可撓性(フレキブル)を有した管を用いる。   Next, as shown in FIG. 1 (b), a concrete supply pipe 111 of a concrete mixer truck (raw concrete car) 110 as a concrete supply source is connected to a suction port of a concrete pumping pump 113 mounted on a pump truck 112, and concrete is supplied. The discharge port of the pressure pump 113 and the rear end opening of the concrete placing pipe 3 are connected by a connecting pipe 114 so that they can communicate with each other. In addition, the rear end of the base carriage 2 of the construction device 1 and the pump vehicle 112 are connected by a tow rope 115 so that the construction device 1 can be pulled by the pump vehicle 112. Then, by driving the concrete pumping pump 113 and feeding the ready-mixed concrete from the concrete mixer truck 110 to the tip opening 3t of the concrete placing pipe 3, the concrete placing work for the concrete placing scheduled section which is the first section a. And a frame for the second section b, which is a section after the concrete placement work is performed, that is, the second section b located laterally on the rear end half of the construction apparatus 1 And rebar assembly work. That is, the construction apparatus 1 is installed so as to extend over the leading end portion 91a of the concrete placement scheduled section 91 and the rear end portion 92a of the formwork and reinforcing bar assembly scheduled section 92, and the first section a (concrete placing schedule) The concrete placing operation for the section) and the assembly work of the formwork and the reinforcing bar for the second section b (the subsequent section) are performed simultaneously. The concrete placing work for the first section a is performed by pulling the construction device 1 little by little in the direction of arrow f (from the inside of the mine to the side of the wellhead) with the pump car 112, so that the tip opening 3t side of the concrete placing pipe 3 is moved to the first side. It is performed while moving from the front end side a1 to the rear end side a2 of one section a. Further, in order to place concrete while swinging the tip portion of the concrete placement pipe 3 in the left and right first section a regions on both sides of the upper opening 88 of the central groove 82, the tip of the concrete placement pipe 3 is placed. On the side, a flexible tube is used.

そして、図1(c)に示すように、既にコンクリート打設作業を終了してコンクリートが固化した第1区間a(前の区間)に対する型枠撤去作業と、型枠及び鉄筋の組立作業を終了した第2区間bであるコンクリート打設予定区間に対するコンクリート打設作業と、当該コンクリート打設予定区間の後にコンクリート打設作業を行う第3区間c(後の区間)に対する型枠及び鉄筋の組立作業とを同時並行して行う。コンクリート打設予定区間91の先端部91aと型枠及び鉄筋組立予定区間92の後端部92aとに渡って延長するように施工装置1を設置し、第1区間aに対する型枠撤去作業と、第2区間bに対するコンクリート打設作業と、第3区間c(後の区間)に対する型枠及び鉄筋の組立作業とを同時並行して行う。   Then, as shown in FIG. 1 (c), the concrete placement work has been finished and the formwork removal work for the first section a (previous section) in which the concrete has solidified and the work of assembling the formwork and the rebar are finished. The concrete placement work for the concrete placement planned section, which is the second section b, and the assembly work of the formwork and the reinforcing bar for the third section c (the subsequent section) in which the concrete placement work is performed after the concrete placement planned section. And simultaneously. The construction apparatus 1 is installed so as to extend over the front end portion 91a of the concrete placement planned section 91 and the rear end portion 92a of the formwork and rebar assembly planned section 92, and the formwork removal work for the first section a, The concrete placing work for the second section b and the assembling work of the formwork and the reinforcing bar for the third section c (later section) are performed in parallel.

尚、コンクリート打設管3は、連続的にコンクリートを打設する際には、コンクリート打設管3内に付着したコンクリートを定期的に洗浄する必要がある。例えば、コンクリートミキサー車1台分のコンクリートを打設した後、図6に示すように、水供給源としての水貯留槽121の水排出口と水圧送ポンプ122の吸込口とを連結管123で繋ぎ、水圧送ポンプ122の吐出口と水送管5の後端開口5bとを連結管124で連通可能に連結し、さらに、コンクリート打設管3の先端開口3tと水送管5の先端開口5tとを連通可能に連結した後に、水圧送ポンプ122を駆動して水送管5経由でコンクリート打設管3内に水を供給するとともに、コンクリート圧送ポンプ113を逆回転駆動させる。これにより、コンクリート打設管3内に圧送され、コンクリート打設管3内を洗浄した水が、コンクリートミキサー車110のコンクリート収納タンク内に取り込まれる。これにより、コンクリート打設管3の洗浄が行えるとともに洗浄に使用した当該水をコンクリートミキサー車110でそのまま水処理場に運搬できる。   In addition, the concrete placement pipe 3 needs to wash | clean the concrete adhering in the concrete placement pipe 3 regularly, when placing concrete continuously. For example, after placing concrete for one concrete mixer truck, as shown in FIG. 6, a water discharge port of a water storage tank 121 as a water supply source and a suction port of a water pump 122 are connected by a connecting pipe 123. The discharge port of the water pressure feed pump 122 and the rear end opening 5b of the water feed pipe 5 are connected so as to be able to communicate with each other through a connecting pipe 124. Further, the tip opening 3t of the concrete placing pipe 3 and the tip opening of the water feed pipe 5 are connected. 5t is connected so that communication is possible, and then the water pressure pump 122 is driven to supply water into the concrete placing pipe 3 via the water pipe 5, and the concrete pressure pump 113 is driven to rotate in reverse. As a result, the water that has been pumped into the concrete placement pipe 3 and cleaned in the concrete placement pipe 3 is taken into the concrete storage tank of the concrete mixer truck 110. Thereby, the concrete placement pipe 3 can be cleaned and the water used for the cleaning can be transported to the water treatment plant as it is by the concrete mixer truck 110.

本形態の施工方法によれば、1つ目の区画に対する型枠及び鉄筋の組立作業の開始から2つ目の区画に対するコンクリート打設作業の終了までにかかる総合時間は、(1つ目の区間に対する鉄筋及び型枠の組立作業時間)+(1つ目の区間に対するコンクリート打設時間及び2つ目の区間に対する鉄筋及び型枠の組立作業時間のうち長い方の時間)+(2つ目の区間に対するコンクリート打設時間)となる。この場合、各作業時間がそれぞれ1日間であれば、1つ目の区画に対する型枠及び鉄筋の組立作業の開始から2つ目の区画に対するコンクリート打設作業の終了までにかかる総合時間は、3日間となるので、従来技術の4日間と比べて短くなる。
即ち、本形態1によれば、前後の区画を施工する場合において、前の区画に対するコンクリート打設作業と後の区間に対する鉄筋及び型枠の組立作業とを1日で行えるので、施工工期を短縮できるようになる。
また、第1区間aに対する型枠撤去作業と、第2区間bに対するコンクリート打設作業と、第3区間cに対する型枠及び鉄筋の組立作業とを同時並行して行うので、施工工期をさらに短縮できるようになる。尚、これら3つの作業を同時並行して行う場合には、第1区間a、第2区間b、第3区間cに渡って延長している長さの施工装置1を用いれば型枠撤去作業をより効率的に行うことができる。
According to the construction method of this embodiment, the total time taken from the start of the assembly work of the formwork and the reinforcing bar to the first section to the end of the concrete placing work for the second section is (the first section Reinforcing bar and formwork assembly time) + (Concrete placement time for the first section and rebar and formwork assembly time for the second section) + (Second time Concrete placement time for the section). In this case, if each work time is one day, the total time required from the start of the assembly work of the formwork and the reinforcing bar to the first section to the end of the concrete placing work for the second section is 3 Since it is a day, it is shorter than the four days of the prior art.
That is, according to the present embodiment 1, when constructing the front and rear sections, the concrete placing work for the previous section and the rebar and formwork assembly work for the rear section can be performed in one day, so the construction period is shortened. become able to.
Moreover, since the work for removing the formwork for the first section a, the concrete placing work for the second section b, and the work for assembling the formwork and reinforcing bars for the third section c are performed simultaneously, the construction period is further reduced. become able to. In addition, when these three operations are performed in parallel, if the construction device 1 having a length extending over the first section a, the second section b, and the third section c is used, the form removal work is performed. Can be performed more efficiently.

本形態の施工装置1によれば、ベース台車2と、ベース台車2の後端部から先端部まで延長するようにベース台車2に設けられたコンクリート打設管3と、ベース台車2の後端部から先頭部まで延長するようにベース台車2上に設けられた通路4とを備えたので、コンクリート打設管3を用いてコンクリート打設予定区間に対するコンクリート打設作業を行えるとともに、ベース台車2の後端部と先端部との間を通路4を経由して通行できる。従って、型枠及び鉄筋の組立予定区間に必要な資材の運搬や作業員の往来、型枠撤去区間での型枠撤去作業で撤去された型枠の回収運搬や作業員の往来が可能となるため、コンクリート打設予定区間に対するコンクリート打設作業と型枠及び鉄筋の組立予定区間に対する型枠及び鉄筋の組立作業とを同時並行して行うことや、型枠撤去区間(前の区間)に対する型枠撤去作業とコンクリート打設予定区間に対するコンクリート打設作業と型枠及び鉄筋の組立予定区間(後の区間)に対する型枠及び鉄筋の組立作業とを同時並行して行うことができるようになり、路盤鉄筋コンクリートの施工工期を短縮できる。
また、資材運搬用台車6を備えたので、資材運搬用台車6を、型枠及び鉄筋の組立作業に必要な資材の運搬作業や型枠撤去作業で撤去された型枠の回収運搬作業に用いることにより、運搬作業が容易となる。
また、ベース台車2の後端部から先端部まで延長するようにベース台車2に設けられた水送管5を備えたので、コンクリート打設管3内を容易に洗浄できるようになり、かつ、コンクリート打設管3内を洗浄した水の処理を容易に行えるようになる。
ベース台車2は、複数の単位台車21により構成され、単位台車21は、両方の脚部24;24と脚部24;24の上端同士を連結する梁部26とを有した門形フレーム23と、門形フレーム23の両方の脚部24;24の下端に設けられた走行車輪25とにより形成され、ベース台車2は、所定間隔隔てて設けられた各単位台車21の梁部26;26同士が連結部材22で連結されたことにより形成されたので、区間の長さに応じたベース台車2を形成でき、区間の長さを自由に設定できるようになる。
単位台車21が4個の走行車輪25を備えたので、走行車輪1個当たりの転がり摩擦を小さくでき、ベース台車2をスムーズに移動させることができる。
According to the construction apparatus 1 of the present embodiment, the base carriage 2, the concrete placing pipe 3 provided on the base carriage 2 so as to extend from the rear end portion of the base carriage 2 to the front end portion, and the rear end of the base carriage 2 Since the passage 4 provided on the base carriage 2 is provided so as to extend from the head to the head, the concrete placement work can be performed on the concrete placement planned section using the concrete placement pipe 3, and the base carriage 2 It is possible to pass between the rear end portion and the front end portion via the passage 4. Therefore, it is possible to transport materials necessary for the assembly section of the formwork and rebar and transport of workers, collect and transport the formwork removed by formwork removal work in the formwork removal section, and transport workers. Therefore, the concrete placement work for the concrete placement planned section and the formwork and rebar assembly work for the formwork and rebar assembly planned section are performed simultaneously, and the mold for the formwork removal section (previous section) The frame removal work and the concrete placement work for the concrete placement planned section and the formwork and reinforcement assembly work for the formwork and reinforcement assembly planned section (later section) can be performed simultaneously in parallel. The construction period of roadbed reinforced concrete can be shortened.
In addition, since the material transport cart 6 is provided, the material transport cart 6 is used for the material transport work necessary for assembling the formwork and the rebar and the formwork collected and transported by the formwork removal work. This facilitates the transportation work.
Moreover, since the water delivery pipe 5 provided in the base carriage 2 is provided so as to extend from the rear end portion to the front end portion of the base carriage 2, the inside of the concrete placing pipe 3 can be easily cleaned, and It becomes possible to easily treat the water in which the inside of the concrete placing pipe 3 is washed.
The base carriage 2 includes a plurality of unit carriages 21, and the unit carriage 21 includes a portal frame 23 having both leg portions 24; 24 and beam portions 26 that connect the upper ends of the leg portions 24; 24. The base carriage 2 is formed by running wheels 25 provided at the lower ends of both leg portions 24; 24 of the gate-shaped frame 23, and the base carriage 2 has beam portions 26; 26 of the unit carriages 21 provided at predetermined intervals. Is formed by being connected by the connecting member 22, the base carriage 2 corresponding to the length of the section can be formed, and the length of the section can be freely set.
Since the unit carriage 21 includes four traveling wheels 25, the rolling friction per traveling wheel can be reduced, and the base carriage 2 can be moved smoothly.

尚、上述した効果からわかるように、施工装置1は、ベース台車2とコンクリート打設管3と通路4とにより構成されたものでもよいし、ベース台車2とコンクリート打設管3と通路4とを備えた構成に加え、資材運搬用台車6、水送管5のうちの少なくとも1つを備えた構成としてもよい。
また、第1区間aに対する型枠撤去作業と、第2区間bに対するコンクリート打設作業と、第3区間c(後の区間)に対する型枠及び鉄筋の組立作業とを同時並行して行う場合には、施工装置1を、第1区間aと第2区間bと第3区間cとに渡って延長するように設置すれば、型枠撤去作業をより効率的に行える。
As can be seen from the above-described effects, the construction apparatus 1 may be configured by the base carriage 2, the concrete placing pipe 3 and the passage 4, or the base carriage 2, the concrete placing pipe 3 and the passage 4. It is good also as a structure provided with at least 1 of the trolley | bogie 6 for material conveyance and the water pipe 5 in addition to the structure provided with.
In addition, when performing the formwork removal work for the first section a, the concrete placing work for the second section b, and the work of assembling the formwork and rebar for the third section c (later section) in parallel. If the construction apparatus 1 is installed so as to extend over the first section a, the second section b, and the third section c, the mold removal work can be performed more efficiently.

1 施工装置、2 ベース台車、3 コンクリート打設管、4 通路、
5 水送管、6 資材運搬用台車、7 資材運搬用台車走行レール、21 単位台車、
22 連結部材、23 門形フレーム、24 脚部、25 走行車輪、26 梁部、
100 路盤鉄筋コンクリート。
1 construction equipment, 2 base carriage, 3 concrete placing pipe, 4 passage,
5 Water transport pipe, 6 Material transport cart, 7 Material transport cart travel rail, 21 Unit cart,
22 connecting members, 23 portal frame, 24 legs, 25 traveling wheels, 26 beams,
100 Roadbed reinforced concrete.

Claims (6)

トンネルの延長方向に沿って区切られた所定区間毎にトンネルの延長方向に沿って順番にトンネル内に路盤鉄筋コンクリートを施工する路盤鉄筋コンクリートの施工装置において、型枠及び鉄筋の組立作業が終了したコンクリート打設予定区間のトンネルの延長方向に沿った横と当該コンクリート打設予定区間の後にコンクリート打設作業を行う後の区間のトンネルの延長方向に沿った横とに沿ってコンクリート打設予定区間の先端部と後の区間の後端部とに渡って延長するベース台車と、ベース台車の後端部から先端部まで延長するようにベース台車に設けられたコンクリート打設管と、ベース台車の後端部から先端部まで延長するようにベース台車上に設けられた通路とを備えたことを特徴とする路盤鉄筋コンクリートの施工装置。   In a roadbed reinforced concrete construction device that constructs roadbed reinforced concrete in the tunnel in order along the tunnel extension direction for each predetermined section divided along the tunnel extension direction, the concrete casting after the formwork and rebar assembly work has been completed. The tip of the concrete placement section along the side along the extension direction of the tunnel of the planned installation section and the side of the section along the extension direction of the tunnel of the section after the concrete placement operation after the concrete placement section. Base trolley extending over the rear end of the base section and the rear section, a concrete placing pipe provided on the base trolley extending from the rear end of the base trolley to the front end, and the rear end of the base trolley A roadbed reinforced concrete construction apparatus comprising a passage provided on a base carriage so as to extend from a portion to a tip portion. 請求項1に記載の路盤鉄筋コンクリートの施工装置を使用した路盤鉄筋コンクリートの施工方法であって、型枠及び鉄筋の組立作業が終了したコンクリート打設予定区間に対するコンクリート打設作業と、当該コンクリート打設予定区間の後にコンクリート打設作業を行う後の区間に対する型枠及び鉄筋の組立作業とを同時並行して行うことを特徴とする路盤鉄筋コンクリートの施工方法。   A roadbed reinforced concrete construction method using the roadbed reinforced concrete construction apparatus according to claim 1, wherein the concrete placement work for the concrete placement planned section where the assembly work of the formwork and the reinforcing bar is completed, and the concrete placement schedule A method for constructing roadbed reinforced concrete, wherein the formwork and rebar assembly work for the section after performing the concrete placing work after the section are performed in parallel. 既にコンクリート打設作業を終了してコンクリートが固化した上記コンクリート打設予定区間の前の区間に対する型枠撤去作業と、上記コンクリート打設予定区間に対するコンクリート打設作業と、後の区間に対する型枠及び鉄筋の組立作業とを同時並行して行うことを特徴とする請求項2に記載の路盤鉄筋コンクリートの施工方法。   The formwork removal work for the section before the concrete placement section, the concrete has already solidified after the concrete placement work, the concrete placement work for the concrete placement section, the formwork for the subsequent section, and The construction method for roadbed reinforced concrete according to claim 2, wherein the rebar assembling work is performed in parallel. ベース台車の後端部と先端部との間を移動可能なようにベース台車上に設けられた資材運搬用台車を備えたことを特徴とする請求項1に記載の路盤鉄筋コンクリートの施工装置。   The construction apparatus for roadbed reinforced concrete according to claim 1, further comprising a material carrying carriage provided on the base carriage so as to be movable between a rear end portion and a front end portion of the base carriage. ベース台車の後端部から先端部まで延長するようにベース台車に設けられた水送管を備え、後端がコンクリート供給源に接続されたコンクリート打設管内を洗浄する際、水送管の後端が水供給源に接続され、コンクリート打設管の先端開口と水送管の先端口とが連通するように連結され、水供給源から水送管経由でコンクリート打設管内に供給されてコンクリート打設管内を洗浄した水がコンクリート供給源に送り出されるようにしたことを特徴とする請求項1又は請求項4に記載の路盤鉄筋コンクリートの施工装置。   When the inside of the concrete placement pipe with the rear end connected to the concrete supply source is cleaned, the water supply pipe is provided on the base carriage so as to extend from the rear end to the front end of the base carriage. The end is connected to the water supply source, the tip opening of the concrete placement pipe and the tip end of the water feed pipe are connected to communicate with each other, and the concrete is supplied from the water supply source through the water feed pipe into the concrete placement pipe. 5. The roadbed reinforced concrete construction apparatus according to claim 1, wherein water in which the inside of the placing pipe is washed is sent to a concrete supply source. ベース台車は、複数の単位台車により構成され、単位台車は、両方の脚部と脚部の上端同士を連結する梁部とを有した門形フレームと、門形フレームの両方の脚部の下端に設けられた走行車輪とにより形成され、ベース台車は、所定間隔隔てて設けられた各単位台車の梁部同士が連結部材で連結されたことにより形成されたことを特徴とする請求項1又は請求項4又は請求項5のいずれかに記載の路盤鉄筋コンクリートの施工装置。   The base carriage is composed of a plurality of unit carriages. The unit carriage has a portal frame having both leg portions and a beam portion connecting the upper ends of the leg portions, and lower ends of both leg portions of the portal frame. The base carriage is formed by connecting beam portions of each unit carriage provided at a predetermined interval with a connecting member. The construction device of the roadbed reinforced concrete according to any one of claims 4 and 5.
JP2009080316A 2009-03-27 2009-03-27 Construction equipment and construction method for roadbed reinforced concrete Active JP5355175B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009080316A JP5355175B2 (en) 2009-03-27 2009-03-27 Construction equipment and construction method for roadbed reinforced concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009080316A JP5355175B2 (en) 2009-03-27 2009-03-27 Construction equipment and construction method for roadbed reinforced concrete

Publications (2)

Publication Number Publication Date
JP2010229761A true JP2010229761A (en) 2010-10-14
JP5355175B2 JP5355175B2 (en) 2013-11-27

Family

ID=43045832

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009080316A Active JP5355175B2 (en) 2009-03-27 2009-03-27 Construction equipment and construction method for roadbed reinforced concrete

Country Status (1)

Country Link
JP (1) JP5355175B2 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102787848A (en) * 2011-05-17 2012-11-21 江南水利水电工程公司 Tunnel inverted arch sliding formwork concrete lining steel trolley
CN106930767A (en) * 2017-03-28 2017-07-07 中国五冶集团有限公司 Big cross section arcading tunnel construction method
CN106988764A (en) * 2017-05-19 2017-07-28 龚岗 Tunnel geotextiles waterproof cloth and two lined steel muscle are plated in technique
JP2020002528A (en) * 2018-06-25 2020-01-09 大成建設株式会社 Concrete placement system and concrete placement method
CN114017057A (en) * 2021-11-11 2022-02-08 中铁十二局集团有限公司 Construction method of cast-in-place concrete air duct partition plate for plateau railway tunnel double-lane trackless transportation auxiliary gallery
CN114033431A (en) * 2021-11-16 2022-02-11 中铁十二局集团有限公司 Irregular structure concrete pouring construction method
CN114233326A (en) * 2021-09-01 2022-03-25 中铁隧道局集团有限公司 Side wall foundation construction template installation device
CN114233003A (en) * 2021-12-30 2022-03-25 平煤神马建工集团有限公司 Automatic concrete pouring equipment for building construction
CN114857353A (en) * 2022-04-21 2022-08-05 中铁一局集团有限公司 Construction method of jacking pipe internally-penetrated steel sleeve steel steam pipeline

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105715282A (en) * 2016-03-25 2016-06-29 中国水利水电第十四工程局有限公司 Inverted arch simultaneous lining steel die trolley

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03129099A (en) * 1989-10-12 1991-06-03 Hitachi Zosen Corp Lining construction for tunnel in shield method and equipment thereof
JPH08284598A (en) * 1995-04-12 1996-10-29 Maeda Corp Method and equipment for placing concrete in tunnel
JP2003232196A (en) * 2002-02-06 2003-08-22 Kajima Corp Tunnel invert construction method and device for the same
JP2004137834A (en) * 2002-10-21 2004-05-13 Gifu Kogyo Co Ltd Tunnel invert construction method by moving pier and moving pier
JP2005171549A (en) * 2003-12-09 2005-06-30 Seisuke Okubo Tunnel construction method
JP2008308855A (en) * 2007-06-13 2008-12-25 Ohbayashi Corp Construction method for lining concrete, and lining concrete structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03129099A (en) * 1989-10-12 1991-06-03 Hitachi Zosen Corp Lining construction for tunnel in shield method and equipment thereof
JPH08284598A (en) * 1995-04-12 1996-10-29 Maeda Corp Method and equipment for placing concrete in tunnel
JP2003232196A (en) * 2002-02-06 2003-08-22 Kajima Corp Tunnel invert construction method and device for the same
JP2004137834A (en) * 2002-10-21 2004-05-13 Gifu Kogyo Co Ltd Tunnel invert construction method by moving pier and moving pier
JP2005171549A (en) * 2003-12-09 2005-06-30 Seisuke Okubo Tunnel construction method
JP2008308855A (en) * 2007-06-13 2008-12-25 Ohbayashi Corp Construction method for lining concrete, and lining concrete structure

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102787848A (en) * 2011-05-17 2012-11-21 江南水利水电工程公司 Tunnel inverted arch sliding formwork concrete lining steel trolley
CN106930767A (en) * 2017-03-28 2017-07-07 中国五冶集团有限公司 Big cross section arcading tunnel construction method
CN106930767B (en) * 2017-03-28 2019-01-08 中国五冶集团有限公司 Big cross section arcading tunnel construction method
CN106988764A (en) * 2017-05-19 2017-07-28 龚岗 Tunnel geotextiles waterproof cloth and two lined steel muscle are plated in technique
CN106988764B (en) * 2017-05-19 2019-05-21 龚岗 Tunnel geotextiles waterproof cloth and two lined steel muscle are plated in technique
JP2020002528A (en) * 2018-06-25 2020-01-09 大成建設株式会社 Concrete placement system and concrete placement method
JP7105439B2 (en) 2018-06-25 2022-07-25 大成建設株式会社 Concrete placing device and concrete placing method
CN114233326A (en) * 2021-09-01 2022-03-25 中铁隧道局集团有限公司 Side wall foundation construction template installation device
CN114017057A (en) * 2021-11-11 2022-02-08 中铁十二局集团有限公司 Construction method of cast-in-place concrete air duct partition plate for plateau railway tunnel double-lane trackless transportation auxiliary gallery
CN114017057B (en) * 2021-11-11 2023-05-02 中铁十二局集团有限公司 Construction method for cast-in-situ concrete wind channel separator of plateau railway tunnel double-lane trackless transportation auxiliary tunnel
CN114033431A (en) * 2021-11-16 2022-02-11 中铁十二局集团有限公司 Irregular structure concrete pouring construction method
CN114233003A (en) * 2021-12-30 2022-03-25 平煤神马建工集团有限公司 Automatic concrete pouring equipment for building construction
CN114233003B (en) * 2021-12-30 2023-07-14 平煤神马建工集团有限公司 Automatic concrete pouring equipment for building construction
CN114857353A (en) * 2022-04-21 2022-08-05 中铁一局集团有限公司 Construction method of jacking pipe internally-penetrated steel sleeve steel steam pipeline
CN114857353B (en) * 2022-04-21 2024-04-05 中铁一局集团有限公司 Construction method for penetrating steel sleeve steel steam pipeline in jacking pipe

Also Published As

Publication number Publication date
JP5355175B2 (en) 2013-11-27

Similar Documents

Publication Publication Date Title
JP5355175B2 (en) Construction equipment and construction method for roadbed reinforced concrete
JP2012180693A (en) Removal method and new construction method for bridge
JP5466527B2 (en) Concrete placement equipment
CN105041339B (en) Disengaging type formwork jumbo, chassis component and underpass concrete construction method
CN109333800A (en) A kind of prefabricated components production line
CN109129872B (en) Prefabricated component production line
CN207131969U (en) The rail-mounted concrete pump pipe carrier of solid concrete roabed cast-in-place construction in subway tunnel
CN109355983A (en) A kind of trackless construction method of city rail
KR101006462B1 (en) Railroad way concrete other opinion system and the method which are space-time on the tunnel inside
CN102704360B (en) Construction method for ballastless track base plate
CN104526862A (en) Integrated prefabricated part demolding machine
JP2006327015A (en) Manufacturing system for precast concrete product
CN207537980U (en) For building the template construction of tidal channel machinery
CN202248906U (en) Concrete transportation device for pouring lateral baffle block of ballast-free track of high-speed rail
CN109483717A (en) A kind of component production line
CN103510436A (en) Bed plate formwork rapid transferring device and technology
JP2018204303A (en) Reinforced cage positioning system
CN202702384U (en) Automatic circulating production system for wall plates
JPH0829542B2 (en) Manufacturing equipment for precast concrete products
CN218531459U (en) Integral automatic spraying device of tunnel lining platform truck template release agent
JP2005090077A (en) Invert concrete building method and invert concrete building device
JP5030740B2 (en) Reclaimer equipment
JP4442975B2 (en) Reinforcing bar mat transfer device in rebar mat manufacturing equipment for ALC panel
CN215038701U (en) Stair automation production unit and stair automation line
CN218713143U (en) Square-round window-type facing wall construction equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120117

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130226

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130611

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130703

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130827

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130827

R150 Certificate of patent or registration of utility model

Ref document number: 5355175

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350