CN114017057B - Construction method for cast-in-situ concrete wind channel separator of plateau railway tunnel double-lane trackless transportation auxiliary tunnel - Google Patents

Construction method for cast-in-situ concrete wind channel separator of plateau railway tunnel double-lane trackless transportation auxiliary tunnel Download PDF

Info

Publication number
CN114017057B
CN114017057B CN202111333103.6A CN202111333103A CN114017057B CN 114017057 B CN114017057 B CN 114017057B CN 202111333103 A CN202111333103 A CN 202111333103A CN 114017057 B CN114017057 B CN 114017057B
Authority
CN
China
Prior art keywords
embedded
bars
steel bars
transverse
double
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111333103.6A
Other languages
Chinese (zh)
Other versions
CN114017057A (en
Inventor
李天胜
包烨明
马希平
温辉
刘军华
张绍俊
姜文涛
高云龙
李文灿
李福林
米瑞斌
潘俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
China Railway 12th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN202111333103.6A priority Critical patent/CN114017057B/en
Publication of CN114017057A publication Critical patent/CN114017057A/en
Application granted granted Critical
Publication of CN114017057B publication Critical patent/CN114017057B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides a construction method of a cast-in-situ concrete wind channel separator of a plateau railway tunnel double-lane trackless transportation auxiliary tunnel, which belongs to the technical field of tunnel engineering construction and comprises the following steps of S1, measuring the point position of an embedded drain pipe; s2, installing an embedded drain pipe; s3, measuring the point positions of the embedded channels; s4, installing an embedded channel and embedded bars; s5, pouring secondary lining concrete; s6, demolding the second lining and removing the embedded channel; s7, installing a bottom die; s8, installing partition plate reinforcing steel bars; s9, pouring partition plate concrete; s10, sealing treatment. The construction by adopting the method can follow the secondary lining construction, does not influence the passing of construction vehicles, greatly shortens the construction period and has extremely wide popularization value.

Description

Construction method for cast-in-situ concrete wind channel separator of plateau railway tunnel double-lane trackless transportation auxiliary tunnel
Technical Field
The invention belongs to the technical field of tunnel engineering construction, and particularly discloses a construction method of a cast-in-situ concrete canal baffle of a double-lane trackless transportation auxiliary tunnel of a plateau railway tunnel.
Background
Along with the increasing expansion of railway construction scale, the proportion of the altitude tunnel is larger and larger, the tunnel setting length is longer and longer, the auxiliary tunnel needs to be arranged for construction, a plurality of working surfaces need to be constructed simultaneously after the auxiliary tunnel enters the main tunnel, and the ventilation with multiple working surfaces at a long distance needs to be realized. Aiming at the unique climate characteristics of the plateau and the existence of high-ground temperature sections in the tunnel, the auxiliary tunnel ventilation function is particularly necessary, and the choice of an economic and efficient ventilation mode greatly improves the construction environment in the tunnel of the plateau. The conventional wind belt type ventilation of the plateau tunnel has the problems of easiness in bending of the wind belt, high ventilation resistance, high air leakage rate, high wind belt loss, low ventilation efficiency and the like. The duct type ventilation is a ventilation mode capable of guaranteeing a ventilation section and extremely low air leakage rate, avoids the loss of a large amount of air belts in the traditional air belt type ventilation, and is an economical and efficient ventilation mode. The construction of the canal baffle is a foundation of canal ventilation, the construction efficiency of the foundation influences the whole construction period, but the construction of the canal baffle and construction vehicles influence each other, and the construction efficiency is influenced.
Disclosure of Invention
The invention aims to provide a construction method of a cast-in-situ concrete canal baffle of a double-lane trackless transportation auxiliary tunnel of a plateau railway tunnel, which can immediately follow secondary lining construction, does not influence the passing of construction vehicles and can greatly shorten the construction period.
In order to achieve the purpose, the invention provides a construction method of a cast-in-situ concrete canal baffle of a double-lane trackless transportation auxiliary tunnel of a plateau railway tunnel, which comprises the following steps:
s1, measuring the point position of a pre-buried drain pipe
The method comprises the steps that drainage pipes are arranged at equal height positions on two sides of the designed height of the air duct partition plate at equal intervals along the longitudinal direction of an auxiliary tunnel and used for drainage of air duct catchment, and after two lining trolleys are positioned, the design elevation of the top water inlet of each drainage pipe is determined on the two lining trolley panels through measurement;
s2, installing a pre-buried drain pipe
According to the measurement point position of the embedded drain pipe, the embedded drain pipe is installed on the surface of the secondary lining trolley, the distance between the drain pipe and the surface protection layer of the secondary lining trolley is not smaller than the preset thickness, a tunnel drain side ditch is introduced into the bottom of the drain pipe, and a switch valve is arranged at the lower part of the drain pipe;
s3, measuring the point positions of the embedded channels
Positioning the embedded channel according to the design elevation of the transverse steel bars of the air channel partition plates, reserving preset heights as operation spaces respectively at the upper and lower sides of the design elevation of the transverse steel bars of the two layers of air channel partition plates, and determining the height of the embedded channel;
s4, installing embedded channels and embedded bars
The embedded channels are made of wood plates, the embedded channels on two sides are arranged along the longitudinal through length of the auxiliary tunnel, and the embedded channels are grooved at the embedded bar passing positions;
double-layer annular embedded bars are arranged in the two liners at two sides of the design height of the wind tunnel partition board, the annular length of the double-layer annular embedded bars is larger than the thickness of the wind tunnel partition board, outer-layer steel bars of the double-layer annular embedded bars are positioned outside the embedded channel, inner-layer steel bars penetrate through the embedded channel, the double-layer annular embedded bars are provided with steel bar protection layers, and a plurality of groups of double-layer annular embedded bars are arranged at equal intervals along the longitudinal direction of the auxiliary tunnel;
longitudinal embedded bars I are arranged on the inner side of the outer layer steel bar and the outer side of the inner layer steel bar of the double-layer circumferential embedded bars, a plurality of groups of longitudinal embedded bars I are arranged at equal intervals along the circumferential direction of the two liners, two longitudinal embedded bars II are arranged at the designed elevation position of the transverse steel bar of the air duct partition plate, and the longitudinal embedded bars II are positioned on the outer side of the outer layer steel bar of the double-layer circumferential embedded bars;
binding the crossing positions of the double-layer circumferential embedded bars and the longitudinal embedded bars, and arranging stirrups at the crossing positions of the double-layer circumferential embedded bars and the longitudinal embedded bars I;
the transverse steel bars of the air duct partition plate comprise transverse embedded steel bars and transverse connecting steel bars, the transverse embedded steel bars are arranged in the second lining and are arranged at equal intervals along the longitudinal direction of the auxiliary tunnel, the transverse embedded steel bars penetrate through the embedded channel, the end parts outside the embedded channel are processed into hooks, the hooks are downwards connected with the longitudinal embedded steel bars II, the end parts inside the embedded channel are provided with thick straight threads, the wire heads wear protective caps, and the inside of the embedded channel is filled;
s5, pouring secondary lining concrete
S6, demolding and removing the embedded channel by using the second lining
The secondary lining concrete meets the demoulding requirement, the secondary lining trolley is demoulded, the elevation of the embedded channel is retested, and the embedded channel is cleaned to expose the transverse embedded bar wire opening;
s7, installing a bottom die
The construction of the wind canal baffle adopts a walkable rack provided with a door opening, the length of the walkable rack is not less than that of a two-lining trolley, the width and the height of the door opening are set according to the sizes of common mechanical equipment and vehicles, the walkable rack is provided with a hydraulic operating system and a walking track, the rack is lifted by a hydraulic jack, and the top of the walkable rack is provided with an operating platform;
arching is carried out on the bottom die of the air duct partition plate;
s8, installing partition plate reinforcing steel bars
The two ends of the transverse connecting steel bars are provided with thick straight threads, the transverse connecting steel bars are connected with the transverse embedded steel bars by adopting mechanical sleeves, cushion blocks are uniformly arranged at the bottoms of the transverse connecting steel bars, longitudinal connecting steel bars are arranged at the upper side and the lower side of the two layers of transverse connecting steel bars, the longitudinal connecting steel bars are arranged at equal intervals along the transverse direction of the auxiliary tunnel, and the crossing positions of the transverse connecting steel bars and the longitudinal connecting steel bars are bound and hooped;
s9, pouring partition plate concrete
S10, sealing treatment
Demoulding is carried out after the concrete strength of the partition plate meets the requirement, and sealing treatment is carried out on transverse construction joints between adjacent wind channel partition plates and joints between the two adjacent wind channel partition plates and the two lining concrete.
Further, in step S3, after determining the height of the embedded channel, the height point of the bottom of the embedded channel is measured at equal intervals.
Further, in step S7, the arch is formed by arranging square timber to form arch ribs, and the bottom die is fully laid by adopting bamboo plywood, and the arch ribs are longitudinally and equidistantly arranged.
Further, in step S9, after the installation of the steel bars is completed, a bamboo plywood closed end mould is used, and grooving treatment is adopted for the end mould to ensure that the extending length of the longitudinal connecting steel bars meets the lap welding length requirement;
after the concrete pouring is completed, the top surface is subjected to trowelling and surface finishing treatment, and water inlets of the drain pipes are reserved at the two sides to form water channels.
Further, in step S10, a water-neutral silicone weather-resistant sealant is used to seal the transverse construction joint between adjacent canal separators and the joint between the two lining concrete.
The invention has the following beneficial effects.
The construction method of the cast-in-situ concrete canal baffle of the plateau railway tunnel double-lane trackless transportation auxiliary tunnel can immediately follow secondary lining construction, does not influence the passing of construction vehicles, greatly shortens the construction period, has extremely wide popularization value, can form an economic and efficient canal type ventilation structure, has stable ventilation section, large ventilation quantity, small ventilation resistance, extremely low air leakage rate, high ventilation efficiency, avoids the loss of a wind band and extremely low later maintenance cost, and can be used as an operation ventilation channel compared with the traditional wind band type ventilation mode.
Drawings
FIG. 1 is a process flow diagram of a construction method of a cast-in-situ concrete duct diaphragm of a plateau railway tunnel double-lane trackless transportation auxiliary tunnel;
FIG. 2 is a layout diagram of a construction method of a cast-in-situ concrete canal separator for a double-lane trackless transportation auxiliary tunnel of a plateau railway tunnel;
FIG. 3 is an enlarged view of the pre-buried channel portion of FIG. 2;
fig. 4 is a schematic arching view of the bottom die.
In the figure: the novel tunnel is characterized by comprising the following components of a 1-drain pipe, a 2-tunnel drain side ditch, a 3-switch valve, a 4-embedded channel, a 5-secondary lining, a 6-double-layer circumferential embedded bar, a 7-longitudinal embedded bar I, an 8-longitudinal embedded bar II, a 9-stirrup, a 10-transverse embedded bar, a 11-transverse connecting bar, a 12-mechanical sleeve, a 13-walkable bench, a 14-wind channel partition board, a 15-longitudinal connecting bar, a 16-arch rib and a 17-arch height.
Detailed Description
The following description of the embodiments of the present invention will be made apparent and fully in view of the accompanying drawings, in which some, but not all embodiments of the invention are shown. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
The embodiment takes a Sichuan line double-lane II type auxiliary tunnel as an example to describe the construction method of the cast-in-situ concrete canal baffle in detail, and the method comprises the following steps.
1. Measuring the point position of the embedded drain pipe
At equal height positions on two sides of the designed height of the canal diaphragm, a drain pipe 1 is arranged at intervals of 50m along the longitudinal direction of the auxiliary tunnel for draining the canal catchment. After the two lining trolleys are positioned, the design elevation of the top water inlet of each drain pipe 1 is determined on the two lining trolley panels through measurement.
2. Mounting pre-buried drain pipe
According to the measurement point position of the embedded drain pipe, a drain pipe 1 with the pre-specification of phi 100UPVC is installed on the surface of the secondary lining trolley, the distance between the drain pipe 1 and the surface protection layer of the secondary lining trolley is not less than 5cm, a tunnel drain side ditch 2 is introduced into the bottom of the drain pipe 1, and a switch valve 3 is arranged at the lower part of the drain pipe 1.
3. Measuring the point position of the embedded channel
The embedded channel 4 is positioned according to the design elevation of the transverse steel bars of the wind channel partition, 5cm is reserved up and down according to the design elevation of the transverse steel bars of the two layers of wind channel partition to serve as an operation space, the height of the embedded channel 4 is determined, and the height point position of the bottom of the embedded channel 4 is measured according to the 5m distance, so that the observation and the positioning are facilitated.
4. Installing embedded channel and embedded bar
The embedded channels 4 are made of wood plates with the depth of 2cm and the center depth of 20cm, the embedded channels 4 on two sides are arranged along the longitudinal through length of the auxiliary tunnel, and the embedded channels 4 are grooved at the embedded bar passing positions.
Double-layer annular embedded bars 6 are arranged in the two liners 5 at the two sides of the design height of the wind channel baffle, the annular length is about 1m, and the specification is that
Figure BDA0003349656970000041
22 steel bars, the outer layer steel bars of the double-layer circumferential embedded steel bars 6 are positioned outside the embedded channel 4, the inner layer steel bars penetrate through the embedded channel 4, the longitudinal spacing is 20cm, and the thickness of the steel bar protection layer is 5cm.
Longitudinal embedded bars I7 are arranged on the inner side of the outer layer steel bar and the outer side of the inner layer steel bar of the double-layer circumferential embedded bar 6, and the specification is that
Figure BDA0003349656970000042
14 steel bars with a circumferential spacing of 25cm. At the designed elevation position of the transverse steel bars of the canal baffle, two longitudinal embedded steel bars II 8 are arranged, the longitudinal embedded steel bars II 8 are positioned at the outer side of the outer layer steel bars of the double-layer annular embedded steel bars 6, and the specification is +.>
Figure BDA0003349656970000043
14 rebar.
Binding is carried out at the crossing position of the double-layer circumferential embedded bars 6 and the longitudinal embedded bars, hooping 9 is arranged at the crossing position of the double-layer circumferential embedded bars 6 and the longitudinal embedded bars I7, the specification of the hooping 9 is phi 8, the circumferential spacing is 25cm, and the longitudinal spacing is 20cm, and the hooping is arranged in a quincuncial shape.
The transverse steel bars of the canal baffle comprise transverse embedded steel bars 10 and transverse connecting steel bars 11, and the specification is that
Figure BDA0003349656970000051
20 reinforcing bars, transverse embedded bars 10 are arranged inside a secondary lining 5 and are arranged at equal intervals along the longitudinal direction of an auxiliary tunnel, the thickness of a reinforcing bar protection layer is 5cm, the transverse embedded bars 10 penetrate through an embedded channel 4, the end parts outside the embedded channel 4 are processed into hooks of 135 degrees, the hooks are connected with a longitudinal embedded bar II downwards, in order to solve the problem that the lap joint length of transverse embedded bars 10 and a rear-mounted transverse connecting bar 11 is insufficient, the transverse embedded bars are connected with a mechanical sleeve 12 through pier thick straight threads, the end parts of the transverse embedded bars 10, which are located in the embedded channel, are required to be subjected to pier thick straight threads, a protective cap is worn by a wire head to prevent wire mouth pollution, and the inside of the embedded channel 4 is filled with foam.
All the crossing parts of the reinforcing steel bars are firmly bound by iron wires. The embedded channel 4, the embedded bars and the two lining trolley panels are fixed firmly to prevent displacement.
5. Pouring secondary lining concrete
In the process of pouring concrete, the embedded channel 4 and the embedded bar part are protected, and displacement caused by over vibration is prevented.
6. Two lining drawing of patterns and demold pre-buried channel
And the secondary lining concrete reaches 75% of the design strength, the secondary lining trolley is demolded, and the elevation of the embedded channel 4 is retested. Cleaning filling foam, removing the wood boards of the embedded channels 4 and cleaning transparent adhesive tapes to expose the wire openings of the embedded bars.
7. Mounting bottom die
The construction of the canal baffle adopts a walkable rack provided with a door opening, and the length of the walkable rack 13 is not less than that of the two lining trolleys, so as to ensure that the construction joint of the canal baffle 14 and the two lining construction joint are in the same ring. The width and the height of the door opening are set according to the sizes of common mechanical equipment and vehicles so as to meet the traffic of the vehicles such as the empty concrete tank truck and the like. The walkable gantry 13 is provided with a hydraulic operating system and a walking rail, and is lifted and lowered by a hydraulic jack. A 5cm thick wood plate is fully paved on the top of the walking bench 13 to serve as a working platform.
The bottom form of the canal diaphragm 14 arches at 3/1000 of the span, and arches by machining 5cm square lumber to form arching ribs 16 to eliminate the sagging of the form during the concrete casting process. The bottom die is fully laid by adopting a bamboo plywood with the thickness of 1.22 multiplied by 2.44 multiplied by 0.012m, and the arch rib 16 is arranged at intervals of 1m in the longitudinal direction.
8. Reinforcing steel bar for installing partition plate
The longitudinal distance between the transverse connection steel bars 11 is 20cm, the bottoms of the steel bars are provided with cushion blocks according to the weight of not less than 4/m 2 Setting, evenly distributing and binding firmly to ensure that the thickness of the bottom reinforcement protection layer is not less than 5cm. The transverse connecting steel bars 10 are connected with the transverse embedded steel bars 11 by adopting mechanical sleeves 12, other parts are connected in a lap joint mode by adopting welding, and the lap joint welding length meets the requirements of single-sided welding 10d and double-sided welding 5 d.
Longitudinal connecting bars 15 are arranged on the upper side and the lower side of the two layers of transverse connecting bars 11, and the specification is that
Figure BDA0003349656970000052
14 steel bars, wherein the transverse spacing is 25cm, the crossing position of the transverse connection steel bars 11 and the longitudinal connection steel bars 15 is firmly bound by iron wires, phi 8 stirrups 9 are arranged, the transverse spacing of the stirrups 9 is 25cm, and the longitudinal spacing is 20cm, and the stirrups are arranged in a quincuncial shape.
9. Pouring partition plate concrete
After the steel bar is installed, a bamboo plywood closed end mould is used, and grooving treatment is adopted for the end mould to ensure that the extending length of the longitudinal connecting steel bar 15 meets the lap welding length requirement. And pumping C35 concrete to pour the canal diaphragm 14, wherein in the process of pouring the diaphragm concrete, attention is paid to strengthening the vibration of the connection part with the secondary lining concrete, and over-vibration is avoided. And after the concrete pouring is finished, the top surface is subjected to trowelling and finishing treatment. Water inlets of the reserved drain pipes on two sides need to be reserved with water channels.
10. Sealing treatment
And demolding after the concrete strength of the partition plate reaches 75% of the design value. And sealing the transverse construction joint and the two-lining concrete joint between the adjacent canal baffles 14 by adopting 5mm thick water-neutral silicone weather-proof sealant.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solution of the present invention, and not for limiting the same; although the invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some or all of the technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit of the invention.

Claims (5)

1. The construction method of the cast-in-situ concrete canal baffle of the auxiliary tunnel for the double-lane trackless transportation of the plateau railway tunnel is characterized by comprising the following steps of:
s1, measuring the point position of a pre-buried drain pipe
The method comprises the steps that drainage pipes are arranged at equal height positions on two sides of the designed height of the air duct partition plate at equal intervals along the longitudinal direction of an auxiliary tunnel and used for drainage of air duct catchment, and after two lining trolleys are positioned, the design elevation of the top water inlet of each drainage pipe is determined on the two lining trolley panels through measurement;
s2, installing a pre-buried drain pipe
According to the measurement point position of the embedded drain pipe, the embedded drain pipe is installed on the surface of the secondary lining trolley, the distance between the drain pipe and the surface protection layer of the secondary lining trolley is not smaller than the preset thickness, a tunnel drain side ditch is introduced into the bottom of the drain pipe, and a switch valve is arranged at the lower part of the drain pipe;
s3, measuring the point positions of the embedded channels
Positioning the embedded channel according to the design elevation of the transverse steel bars of the air channel partition plates, reserving preset heights as operation spaces respectively at the upper and lower sides of the design elevation of the transverse steel bars of the two layers of air channel partition plates, and determining the height of the embedded channel;
s4, installing embedded channels and embedded bars
The embedded channels are made of wood plates, the embedded channels on two sides are arranged along the longitudinal through length of the auxiliary tunnel, and the embedded channels are grooved at the embedded bar passing positions;
double-layer annular embedded bars are arranged in the two liners at two sides of the design height of the wind tunnel partition board, the annular length of the double-layer annular embedded bars is larger than the thickness of the wind tunnel partition board, outer-layer steel bars of the double-layer annular embedded bars are positioned outside the embedded channel, inner-layer steel bars penetrate through the embedded channel, the double-layer annular embedded bars are provided with steel bar protection layers, and a plurality of groups of double-layer annular embedded bars are arranged at equal intervals along the longitudinal direction of the auxiliary tunnel;
longitudinal embedded bars I are arranged on the inner side of the outer layer steel bar and the outer side of the inner layer steel bar of the double-layer circumferential embedded bars, a plurality of groups of longitudinal embedded bars I are arranged at equal intervals along the circumferential direction of the two liners, two longitudinal embedded bars II are arranged at the designed elevation position of the transverse steel bar of the air duct partition plate, and the longitudinal embedded bars II are positioned on the outer side of the outer layer steel bar of the double-layer circumferential embedded bars;
binding the crossing positions of the double-layer circumferential embedded bars and the longitudinal embedded bars, and arranging stirrups at the crossing positions of the double-layer circumferential embedded bars and the longitudinal embedded bars I;
the transverse steel bars of the air duct partition plate comprise transverse embedded steel bars and transverse connecting steel bars, the transverse embedded steel bars are arranged in the second lining and are arranged at equal intervals along the longitudinal direction of the auxiliary tunnel, the transverse embedded steel bars penetrate through the embedded channel, the end parts outside the embedded channel are processed into hooks, the hooks are downwards connected with the longitudinal embedded steel bars II, the end parts inside the embedded channel are provided with thick straight threads, the wire heads wear protective caps, and the inside of the embedded channel is filled;
s5, pouring secondary lining concrete
S6, demolding and removing the embedded channel by using the second lining
The secondary lining concrete meets the demoulding requirement, the secondary lining trolley is demoulded, the elevation of the embedded channel is retested, and the embedded channel is cleaned to expose the transverse embedded bar wire opening;
s7, installing a bottom die
The construction of the wind canal baffle adopts a walkable rack provided with a door opening, the length of the walkable rack is not less than that of a two-lining trolley, the width and the height of the door opening are set according to the sizes of common mechanical equipment and vehicles, the walkable rack is provided with a hydraulic operating system and a walking track, the rack is lifted by a hydraulic jack, and the top of the walkable rack is provided with an operating platform;
arching is carried out on the bottom die of the air duct partition plate;
s8, installing partition plate reinforcing steel bars
The two ends of the transverse connecting steel bars are provided with thick straight threads, the transverse connecting steel bars are connected with the transverse embedded steel bars by adopting mechanical sleeves, cushion blocks are uniformly arranged at the bottoms of the transverse connecting steel bars, longitudinal connecting steel bars are arranged at the upper side and the lower side of the two layers of transverse connecting steel bars, the longitudinal connecting steel bars are arranged at equal intervals along the transverse direction of the auxiliary tunnel, and the crossing positions of the transverse connecting steel bars and the longitudinal connecting steel bars are bound and hooped;
s9, pouring partition plate concrete
S10, sealing treatment
Demoulding is carried out after the concrete strength of the partition plate meets the requirement, and sealing treatment is carried out on transverse construction joints between adjacent wind channel partition plates and joints between the two adjacent wind channel partition plates and the two lining concrete.
2. The construction method of the cast-in-situ concrete canal diaphragm for the auxiliary tunnel for the double-lane trackless transportation of the plateau railway tunnel according to claim 1, wherein in the step S3, after the height of the embedded channel is determined, the height point positions of the bottom of the embedded channel are measured at equal intervals.
3. The construction method of the cast-in-situ concrete canal diaphragm for the double-lane trackless transportation auxiliary tunnel of the plateau railway tunnel according to claim 2, wherein in the step S7, arching is formed by arranging square timber, the bottom die is fully laid by adopting bamboo plywood, and the arching ribs are longitudinally arranged at equal intervals.
4. The construction method of the cast-in-situ concrete canal separator for the double-lane trackless transportation auxiliary tunnels of the plateau railway tunnel according to claim 3, wherein in the step S9, after the installation of the reinforcing steel bars is completed, a bamboo plywood closed end mould is used, and the end mould adopts grooving treatment to ensure that the extension length of the longitudinal connecting reinforcing steel bars meets the lap welding length requirement;
after the concrete pouring is completed, the top surface is subjected to trowelling and surface finishing treatment, and water inlets of the drain pipes are reserved at the two sides to form water channels.
5. The construction method of the cast-in-situ concrete canal diaphragm of the auxiliary tunnel for the double-lane trackless transportation of the plateau railway tunnel according to claim 4, wherein in the step S10, water-neutral silicone weather-resistant sealant is adopted to seal the transverse construction joint between the adjacent canal diaphragm and the joint with the secondary lining concrete.
CN202111333103.6A 2021-11-11 2021-11-11 Construction method for cast-in-situ concrete wind channel separator of plateau railway tunnel double-lane trackless transportation auxiliary tunnel Active CN114017057B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111333103.6A CN114017057B (en) 2021-11-11 2021-11-11 Construction method for cast-in-situ concrete wind channel separator of plateau railway tunnel double-lane trackless transportation auxiliary tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111333103.6A CN114017057B (en) 2021-11-11 2021-11-11 Construction method for cast-in-situ concrete wind channel separator of plateau railway tunnel double-lane trackless transportation auxiliary tunnel

Publications (2)

Publication Number Publication Date
CN114017057A CN114017057A (en) 2022-02-08
CN114017057B true CN114017057B (en) 2023-05-02

Family

ID=80063530

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111333103.6A Active CN114017057B (en) 2021-11-11 2021-11-11 Construction method for cast-in-situ concrete wind channel separator of plateau railway tunnel double-lane trackless transportation auxiliary tunnel

Country Status (1)

Country Link
CN (1) CN114017057B (en)

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1025890A (en) * 1963-05-08 1966-04-14 Kesting Lorenz Equipment for the production of wall-size prefabricated concrete building units
JPH033609A (en) * 1989-05-29 1991-01-09 Nippon Pressed Concrete Co Ltd Setting construction for separation plate in tubular body
JP2000064794A (en) * 1998-08-26 2000-02-29 Penta Ocean Constr Co Ltd Receiving block for shield-tunnel partition, partition using receiving block, and construction method thereof
JP2002327600A (en) * 2001-04-27 2002-11-15 Daiwa-Cres Co Ltd Retaining wall structure of tunnel watchman's passage and member for forming retaining wall
JP2010229761A (en) * 2009-03-27 2010-10-14 Kumagai Gumi Co Ltd Construction device and construction method for base course reinforced concrete
CN102031795A (en) * 2010-06-12 2011-04-27 中铁十六局集团有限公司 Short pile reinforcing technology in narrow space
CN102345461A (en) * 2011-07-23 2012-02-08 中铁十二局集团有限公司 Subsequent project and shield driving parallel construction method for long-distance railway tunnel
CN103643968A (en) * 2013-12-10 2014-03-19 中铁二十三局集团第一工程有限公司 Method for rapid construction of double-track tunnel ditch cable channel
CN104790969A (en) * 2015-03-04 2015-07-22 中铁二十四局集团福建铁路建设有限公司 Two-time positioning construction process for pre-buried channels of overhead line system of high-speed railway tunnel
CN106837397A (en) * 2017-03-20 2017-06-13 山东科技大学 A kind of device and method isolated for gob side entry retaining lane side with supporting
CN107100648A (en) * 2017-06-23 2017-08-29 中铁第四勘察设计院集团有限公司 Tunnel plain concrete lining construction auxiliary equipment and method
CN109209441A (en) * 2018-11-01 2019-01-15 中铁十八局集团有限公司 Mass concrete construction method under a kind of low temperature environment
CN111365018A (en) * 2020-03-25 2020-07-03 上海同岩土木工程科技股份有限公司 Cover arch reinforcement method suitable for small tunnel clearance
CN111411977A (en) * 2020-03-26 2020-07-14 中铁十二局集团有限公司 Construction method for connecting diaphragm in single-hole double-layer tunnel by mould building
CN111502689A (en) * 2020-04-05 2020-08-07 中铁二院工程集团有限责任公司 Upper and lower partition tunnel auxiliary tunnel structure and construction method thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NO335669B1 (en) * 2011-06-21 2015-01-19 Stabinor As Process for the preparation of a tunnel run, and structural element of concrete for use in the manufacture of tunnel sections for such a tunnel run.

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1025890A (en) * 1963-05-08 1966-04-14 Kesting Lorenz Equipment for the production of wall-size prefabricated concrete building units
JPH033609A (en) * 1989-05-29 1991-01-09 Nippon Pressed Concrete Co Ltd Setting construction for separation plate in tubular body
JP2000064794A (en) * 1998-08-26 2000-02-29 Penta Ocean Constr Co Ltd Receiving block for shield-tunnel partition, partition using receiving block, and construction method thereof
JP2002327600A (en) * 2001-04-27 2002-11-15 Daiwa-Cres Co Ltd Retaining wall structure of tunnel watchman's passage and member for forming retaining wall
JP2010229761A (en) * 2009-03-27 2010-10-14 Kumagai Gumi Co Ltd Construction device and construction method for base course reinforced concrete
CN102031795A (en) * 2010-06-12 2011-04-27 中铁十六局集团有限公司 Short pile reinforcing technology in narrow space
CN102345461A (en) * 2011-07-23 2012-02-08 中铁十二局集团有限公司 Subsequent project and shield driving parallel construction method for long-distance railway tunnel
CN103643968A (en) * 2013-12-10 2014-03-19 中铁二十三局集团第一工程有限公司 Method for rapid construction of double-track tunnel ditch cable channel
CN104790969A (en) * 2015-03-04 2015-07-22 中铁二十四局集团福建铁路建设有限公司 Two-time positioning construction process for pre-buried channels of overhead line system of high-speed railway tunnel
CN106837397A (en) * 2017-03-20 2017-06-13 山东科技大学 A kind of device and method isolated for gob side entry retaining lane side with supporting
CN107100648A (en) * 2017-06-23 2017-08-29 中铁第四勘察设计院集团有限公司 Tunnel plain concrete lining construction auxiliary equipment and method
CN109209441A (en) * 2018-11-01 2019-01-15 中铁十八局集团有限公司 Mass concrete construction method under a kind of low temperature environment
CN111365018A (en) * 2020-03-25 2020-07-03 上海同岩土木工程科技股份有限公司 Cover arch reinforcement method suitable for small tunnel clearance
CN111411977A (en) * 2020-03-26 2020-07-14 中铁十二局集团有限公司 Construction method for connecting diaphragm in single-hole double-layer tunnel by mould building
CN111502689A (en) * 2020-04-05 2020-08-07 中铁二院工程集团有限责任公司 Upper and lower partition tunnel auxiliary tunnel structure and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
童正洪 ; .特长隧道通风排烟系统之顶隔板技术研究.中国西部科技(学术).(第06期), *

Also Published As

Publication number Publication date
CN114017057A (en) 2022-02-08

Similar Documents

Publication Publication Date Title
CN107905254B (en) Construction method of comprehensive pipe gallery formwork supporting integrated hydraulic internal formwork trolley
CN102505708B (en) Construction method of tunnel at oversized cross section open cut area in track traffic
CN108487630B (en) Concrete sill prefabricated assembly construction method
CN104400898A (en) Vertical integral forming mould of novel prefabricated concrete segment and forming method thereof
CN202596743U (en) Formwork trolley for underground tunnel pull-rod-free side wall construction
CN108442405A (en) A kind of piping lane support construction based on Urban Underground pipe gallery
CN114017057B (en) Construction method for cast-in-situ concrete wind channel separator of plateau railway tunnel double-lane trackless transportation auxiliary tunnel
CN202528306U (en) Trough beam template
CN110886235B (en) Bridge construction method
CN103321153A (en) Construction method for medium and small span trough girder bridge
CN216043764U (en) Cast-in-place concrete wind channel formula ventilation structure of supplementary gallery in plateau railway tunnel
CN207846241U (en) Whole assembly overlapping box culvert
CN111411977A (en) Construction method for connecting diaphragm in single-hole double-layer tunnel by mould building
CN113635439B (en) Industrialized prefabrication construction method for immersed tube pipe joint
CN217974011U (en) Prefabricated piping lane strides sea bridge
CN108098978A (en) A kind of assembled underground pipe gallery epimere producing device and production method
CN208280166U (en) A kind of piping lane support construction based on Urban Underground pipe gallery
CN206972274U (en) A kind of tunnel circular construction joint expansion sealing strip installation mold
CN218713143U (en) Square-round window-type facing wall construction equipment
CN110450279B (en) Dry dock system for pouring full-section precast concrete and arrangement method
CN103114724A (en) Cast-in-place solid light polyphenyl pipe hollow floorslab construction method
CN210758422U (en) Dry dock system for pouring full-section precast concrete
CN203741988U (en) Large section girder and column joint construction joint processing structure
CN117513077B (en) Construction method of air cushion template of prefabricated short slab secondary pouring growth slab
CN220847057U (en) Hoisting construction railway simply supported beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231019

Address after: 030024 No. 130 West Mining street, Shanxi, Taiyuan

Patentee after: CHINA RAILWAY 12TH BUREAU GROUP Co.,Ltd.

Patentee after: SOUTHWEST JIAOTONG University

Patentee after: THE THIRD ENGINEERING CO., LTD. OF CHINA RAILWAY 12TH BUREAU Group

Address before: 030024 No. 130 West Mining street, Shanxi, Taiyuan

Patentee before: CHINA RAILWAY 12TH BUREAU GROUP Co.,Ltd.

Patentee before: THE THIRD ENGINEERING CO., LTD. OF CHINA RAILWAY 12TH BUREAU Group