JP2010031564A - Basement pillar installation method and construction method for underground structure - Google Patents

Basement pillar installation method and construction method for underground structure Download PDF

Info

Publication number
JP2010031564A
JP2010031564A JP2008195504A JP2008195504A JP2010031564A JP 2010031564 A JP2010031564 A JP 2010031564A JP 2008195504 A JP2008195504 A JP 2008195504A JP 2008195504 A JP2008195504 A JP 2008195504A JP 2010031564 A JP2010031564 A JP 2010031564A
Authority
JP
Japan
Prior art keywords
steel core
pillar
basement
foundation
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008195504A
Other languages
Japanese (ja)
Other versions
JP5140515B2 (en
Inventor
Yoshiki Yamamoto
佳城 山本
Hiroshi Jinnai
浩 陣内
Atsunari Motooka
功成 本岡
Tetsuji Miyata
哲治 宮田
Takahisa Aoyama
高久 青山
Naoya Inomata
直哉 猪又
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2008195504A priority Critical patent/JP5140515B2/en
Publication of JP2010031564A publication Critical patent/JP2010031564A/en
Application granted granted Critical
Publication of JP5140515B2 publication Critical patent/JP5140515B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a basement pillar installation method, hardly causing shift of an installation position of a basement pillar in a process performed after erecting, and reducing cleaning work before concrete is placed. <P>SOLUTION: This basement pillar installation method includes: a process of inserting the basement pillar 1 having a precast concrete-made pillar part 1a and a steel core material 1b extended downward from the pillar part 1a in an excavated hole A formed in the ground, and burying the steel core material 1b in a pile top part of a foundation pile 2; a process of feeding hard granular material 3 in the periphery of the steel core material 1b; and a process of feeding back filling material 4 on the upside of the hard granular material 3. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、地下階柱の設置方法および地中構造物の構築方法に関する。   The present invention relates to an installation method for underground floor pillars and a construction method for underground structures.

地中構造物(建物の地下階を含む)の柱の芯材となる構真柱を地中に設置した後に、構真柱の上部にトップスラブ(先行スラブ)を構築し、その後、トップスラブの下側を掘削して地中構造物を構築する方法(いわゆる逆打ち工法)が知られている。なお、構真柱は、多くの場合、H形鋼等の鉄骨からなる。   After installing the structural pillar that is the core of the pillar of the underground structure (including the basement floor of the building) in the ground, a top slab (advanced slab) is built on top of the structural pillar, and then the top slab A method (so-called reverse driving method) for constructing underground structures by excavating the lower side is known. In many cases, the structural pillar is made of a steel frame such as H-shaped steel.

一般的な逆打ち工法では、地盤を掘削して構真柱を露出させた後に、構真柱の周囲にコンクリートを打設することで柱を構築しているが、構真柱の一部をプレキャストコンクリート部材に置き換えたユニット(以下、「地下階柱」という。)を使用することで、コンクリートの打設作業を簡略化した逆打ち工法も知られている(特許文献1〜3参照)。   In the general reverse driving method, after excavating the ground to expose the structural pillar, the pillar is constructed by placing concrete around the structural pillar. There is also known a reverse casting method that simplifies the concrete placing work by using a unit (hereinafter referred to as “basement column”) replaced with a precast concrete member (see Patent Documents 1 to 3).

特開昭62−86242号公報JP-A-62-86242 特開昭63−67344号公報JP 63-67344 A 特開平8−68057号公報JP-A-8-68057

特許文献1,2の逆打ち工法では、地下階柱の周囲を掘削残土等で埋め戻した状態でその後の工程を行っている。ところが、特許文献1,2の地下階柱は、トップヘビーな構造であるが故に、床付け掘削時に所定の据付位置から移動してしまう虞がある。   In the reverse driving method disclosed in Patent Documents 1 and 2, the subsequent steps are performed in a state where the periphery of the underground floor column is backfilled with excavated residual soil or the like. However, since the underground floor pillars of Patent Documents 1 and 2 have a top heavy structure, they may move from a predetermined installation position during floor excavation.

また、特許文献1,2の地下階柱においても、鉄骨が剥き出しになった部分(すなわち、基礎躯体に埋設される部分)が存在しているので、基礎躯体用のコンクリートを打設する際には、鉄骨表面に固着した埋戻土(掘削残土)を念入りに清掃する必要がある。   In addition, in the underground floor pillars of Patent Documents 1 and 2, there is a portion where the steel frame is exposed (that is, a portion embedded in the foundation frame), so when placing concrete for the foundation frame Therefore, it is necessary to carefully clean up the backfill (excavated soil) that has adhered to the steel surface.

このような観点から、本発明は、プレキャストコンクリート部分を含む地下階柱の設置方法であって、建込み後に行われる工程において地下階柱の据付位置にズレが発生し難く、かつ、基礎躯体用コンクリートの打設前に行う清掃作業を軽減することが可能な地下階柱の設置方法を提供することを課題とし、さらには、この地下階柱の設置方法を含む地中構造物の構築方法を提供することを課題とする。   From this point of view, the present invention is a method for installing a basement column including a precast concrete part, and is difficult to cause a shift in the installation position of the basement column in a process performed after the construction, and for a foundation frame. An object of the present invention is to provide a method of installing an underground floor pillar that can reduce the cleaning work performed before placing concrete, and further, a method for constructing underground structures including the method of installing this underground floor pillar. The issue is to provide.

本発明に係る地下階柱の設置方法は、プレキャストコンクリート製の柱部と当該柱部から下方向に向って延出する鋼製芯材とを有する地下階柱を地盤に形成した掘削孔に挿入し、前記鋼製芯材の下端部を基礎杭の杭頭部に埋設する工程と、前記鋼製芯材の周囲に硬質粒状材料を投入する工程と、前記硬質粒状材料の上側に埋戻材を投入する工程と、を含むことを特徴とする地下階柱の設置方法である。   The basement column installation method according to the present invention is a method for inserting a basement column having a column part made of precast concrete and a steel core extending downward from the column part into an excavation hole formed in the ground. A step of burying the lower end portion of the steel core material in the pile head of the foundation pile, a step of introducing a hard granular material around the steel core material, and a backfill material on the upper side of the hard granular material And a step of installing the underground floor pillar.

「硬質粒状材料」とは、掘削泥水や地下水によって解泥・変質しない粒状の硬質材料(例えば、砕石、スラグ、コンクリート片等)の総称である。   “Hard granular material” is a general term for granular hard materials (for example, crushed stone, slag, concrete pieces, etc.) that are not thawed or altered by drilling mud or groundwater.

本発明によると、柱部の下側に延出する鋼製芯材が硬質粒状材料によって根固めされるようになるので、単なる掘削残土で根固めした場合に比べて、地下階柱の据付位置がずれ難くなる。また、本発明によると、泥状になり難い硬質粒状材料によって鋼製芯材が覆われることになるので、鋼製芯材の表面に泥等が固着し難くなり、その結果、基礎躯体用コンクリートを打設する前に行う鋼製芯材の清掃作業を軽減することが可能になる。   According to the present invention, since the steel core extending below the column part is rooted by the hard granular material, the installation position of the basement column is compared to the case where it is rooted by mere excavation residual soil It becomes difficult to slip. Further, according to the present invention, the steel core material is covered with the hard granular material that is difficult to be mud, so that it is difficult for mud or the like to adhere to the surface of the steel core material. It becomes possible to reduce the cleaning work of the steel core material performed before placing.

本発明に係る地中構造物の構築方法は、前記した本発明に係る地下階柱の設置方法を利用するものである。
すなわち、本発明に係る地中構造物の構築方法は、前記した本発明に係る地下階柱の設置方法により地下階柱を設置する工程と、トップスラブを構築し、当該トップスラブを前記地下階柱に支持させる工程と、前記トップスラブの下側を掘削する工程と、前記基礎躯体の床付面上に前記硬質粒状材料を敷き均して下地層を形成する工程と、前記下地層上に前記基礎躯体用のコンクリートを打設し、前記杭頭部から露出した前記鋼製芯材を前記基礎躯体に埋設する工程とを含むことを特徴とする。
The underground structure construction method according to the present invention uses the above-described underground floor pillar installation method according to the present invention.
That is, the construction method of the underground structure according to the present invention includes a step of installing the underground floor pillar by the above-described method of installing the underground floor pillar according to the present invention, a top slab, and the top slab to the basement floor. A step of supporting by a pillar, a step of excavating the lower side of the top slab, a step of spreading the hard granular material on the floored surface of the foundation frame to form an underlayer, and on the underlayer Placing the concrete for the foundation frame and burying the steel core material exposed from the pile head in the foundation frame.

本発明によれば、鋼製芯材の周囲に投入した硬質粒状材料を床付面に敷き均すこととしたので、割栗石等の搬入作業を省略あるいは軽減することが可能になる。   According to the present invention, since the hard granular material thrown around the steel core material is spread and leveled on the floored surface, it is possible to omit or reduce the work of carrying in, for example, quarry stone.

なお、本発明における「地中構造物」には、その全体が地下に構築される構造物のみならず、ビル等の地下階など地上構造物の地下に構築される構造物も含まれる。   Note that the “underground structure” in the present invention includes not only a structure constructed entirely under the ground but also a structure constructed under the ground structure such as a basement floor of a building or the like.

本発明によれば、地下階柱の据付位置にズレが発生し難くなり、かつ、基礎躯体用コンクリートの打設前に行う清掃作業を軽減することが可能となる。   ADVANTAGE OF THE INVENTION According to this invention, it becomes difficult to generate | occur | produce a shift | offset | difference in the installation position of an underground floor pillar, and it becomes possible to reduce the cleaning operation performed before placing concrete for foundation frame.

添付した図面を参照しつつ、本発明を実施するための最良の形態の一例を詳細に説明する。なお、以下の実施形態では、ビル等の地下階を構築する場合を例示するが、本発明の適用対象を限定する趣旨ではない。   An example of the best mode for carrying out the present invention will be described in detail with reference to the accompanying drawings. In addition, although the case where a basement floor, such as a building, is constructed is illustrated in the following embodiments, the scope of application of the present invention is not limited.

本実施形態に係る地中構造物の構築方法は、地下階柱設置工程(図1および図2参照)と、トップスラブ構築工程(図3の(a)参照)と、地下中間階構築工程(図3の(b)参照)と、基礎躯体構築工程(図4参照)とを含むものである。   The underground structure construction method according to the present embodiment includes an underground floor pillar installation process (see FIGS. 1 and 2), a top slab construction process (see (a) of FIG. 3), and an underground intermediate floor construction process ( 3 (b) in FIG. 3) and a basic chassis construction step (see FIG. 4).

地下階柱設置工程(本実施形態に係る地下階柱の設置方法)は、図1および図2に示すように、地下階柱1を地盤中に設置する工程である。   The underground floor pillar installation process (the installation method of the underground floor pillar according to this embodiment) is a process of installing the underground floor pillar 1 in the ground as shown in FIGS.

地下階柱1は、図1の(a)に示すように、プレキャストコンクリート製の柱部1aと、柱部1aから下方向に向って延出する鋼製芯材1bとを具備している。柱部1aは鉄筋コンクリートからなり、鋼製芯材1bは鉄骨(例えば、H形鋼)からなる。鋼製芯材1bの上部は、柱部1aに埋設されている。柱部1aの構成に制限はなく、例えば、単一のプレキャスト部材にて柱部1aを構成してもよいし、複数のプレキャスト部材を上下方向に連設して柱部1aを構成してもよい。   As shown in FIG. 1A, the basement column 1 includes a precast concrete column portion 1a and a steel core 1b extending downward from the column portion 1a. The column part 1a consists of reinforced concrete, and the steel core material 1b consists of steel frames (for example, H-section steel). The upper part of the steel core 1b is embedded in the column part 1a. There is no restriction | limiting in the structure of the pillar part 1a, For example, the pillar part 1a may be comprised with a single precast member, or even if it connects the some precast member in the up-down direction, and comprises the pillar part 1a. Good.

本実施形態の地下階柱設置工程には、削孔工程、鉄筋籠挿入工程、地下階柱挿入工程(図1の(a)参照)、杭用コンクリート打設工程(図1の(b)参照)、下部埋戻し工程(図2の(a)参照)、上部埋戻し工程(図2の(b)参照)などが含まれている。   The underground floor pillar installation process of the present embodiment includes a drilling process, a reinforcing bar punch insertion process, an underground floor pillar insertion process (see FIG. 1A), and a pile concrete placing process (see FIG. 1B). ), A lower backfilling step (see FIG. 2A), an upper backfilling step (see FIG. 2B), and the like.

削孔工程は、支持地盤(図示略)に達する掘削孔A(図1の(a)参照)を形成する工程であり、鉄筋籠挿入工程は、基礎杭2用の鉄筋籠2a(図1の(a)参照)を掘削孔Aに建て込む工程である。なお、掘削孔Aの上端部には、孔壁の崩落を防ぐための図示せぬケーシングを挿入する。   The drilling step is a step of forming an excavation hole A (see FIG. 1A) that reaches the support ground (not shown), and the reinforcing rod insertion step is a reinforcing rod 2a for the foundation pile 2 (in FIG. 1). (See (a)). A casing (not shown) for preventing the hole wall from collapsing is inserted into the upper end of the excavation hole A.

地下階柱挿入工程は、図1の(a)に示すように、地下階柱1を掘削孔Aに建て込む工程である。地下階柱1を建て込む際には、例えば、ヤットコ(延長治具)Yを接続した地下階柱1を図示せぬクレーン等で掘削孔A内に吊り下ろし、鋼製芯材1bの下端部を鉄筋籠2aの上端部に挿入しつつヤットコYの側面に付設したブラケットBを保持架台Kの上面に載置すればよい。地下階柱1の水平位置は、保持架台Kに取り付けた図示せぬジャッキを利用して調整する。具体的には、例えば、ヤットコYの前後左右の四箇所にジャッキを配置し、ヤットコYを挟んで対向する一対のジャッキを適宜伸縮させることで、地下階柱1の水平位置を調整すればよい。また、地下階柱1の高さ位置は、保持架台KとブラケットBとの間に介設した図示せぬジャッキを利用して調整する。ちなみに、柱部1aの上端はトップスラブ5を支える大梁5a(図3の(a)参照)の下端と一致させ、柱部1aの下端は基礎躯体9(図4の(b)参照)の天端よりも若干下側に位置させる。   The underground floor pillar insertion process is a process of building the underground floor pillar 1 into the excavation hole A as shown in FIG. When the basement column 1 is built, for example, the basement column 1 connected to a Yatco (extension jig) Y is suspended in the excavation hole A by a crane (not shown) and the lower end of the steel core 1b. May be placed on the upper surface of the holding base K while the bracket B is attached to the side surface of the Yattoko Y while inserting the upper end of the reinforcing bar 2a. The horizontal position of the basement column 1 is adjusted using a jack (not shown) attached to the holding frame K. Specifically, for example, the horizontal position of the basement column 1 may be adjusted by arranging jacks at four locations on the front, rear, left, and right sides of the Y-cots Y and appropriately expanding and contracting a pair of jacks facing each other with the Y-cots Y interposed therebetween. . Moreover, the height position of the underground floor pillar 1 is adjusted using a jack (not shown) interposed between the holding base K and the bracket B. Incidentally, the upper end of the column part 1a is made to coincide with the lower end of the large beam 5a (see FIG. 3A) that supports the top slab 5, and the lower end of the column part 1a is the top of the foundation frame 9 (see FIG. 4B). Position slightly below the edge.

杭用コンクリート打設工程は、図1の(b)に示すように、基礎杭2用のコンクリートを打設する工程である。コンクリートを打設する際には、地下階柱1と掘削孔Aの孔壁との間に挿入した図示せぬトレミー管を利用する。杭用コンクリート打設工程を経ると、鋼製芯材1bの下端部が基礎杭2の杭頭部に埋設される。基礎杭2用のコンクリートが所定の強度に達したら、ヤットコYを取り外し、掘削孔Aの上端部に設けた図示せぬケーシングに地下階柱1を固定する。なお、杭用コンクリート打設工程を行った後に、地下階柱挿入工程を行っても差し支えない。   The concrete placing process for piles is a process for placing concrete for foundation piles 2 as shown in FIG. When placing concrete, a tremy tube (not shown) inserted between the underground floor column 1 and the hole wall of the excavation hole A is used. After passing through the concrete placing process for piles, the lower end portion of the steel core 1b is buried in the pile head of the foundation pile 2. When the concrete for the foundation pile 2 reaches a predetermined strength, the Yatco Y is removed, and the underground floor column 1 is fixed to a casing (not shown) provided at the upper end of the excavation hole A. In addition, after performing the concrete placing process for piles, an underground floor pillar insertion process may be performed.

下部埋戻し工程は、図2の(a)に示すように、鋼製芯材1bの周囲に硬質粒状材料3を投入する工程である。硬質粒状材料3は、掘削泥水や地下水によって解泥・変質しない粒状の硬質材料(例えば、粒径が20mm〜40mmの砕石、スラグ、コンクリート片等)からなる。硬質粒状材料3を充填する範囲に制限はないが、地下階柱1のうち、少なくとも基礎躯体9(図4の(b)参照)に埋設される部位の周囲に硬質粒状材料3を充填することが望ましい。本実施形態では、鋼製芯材1bの露出部分(柱部1aの下端面と基礎杭2の上端面との間に位置する部分)の周囲の空間と柱部1aの下端部の周囲の空間とに硬質粒状材料3を充填している。   The lower backfilling step is a step of putting the hard granular material 3 around the steel core 1b as shown in FIG. The hard granular material 3 is made of a granular hard material (for example, crushed stone, slag, concrete pieces, etc. having a particle diameter of 20 mm to 40 mm) that is not thawed or altered by drilling mud or groundwater. Although there is no restriction | limiting in the range with which the hard granular material 3 is filled, Fill the hard granular material 3 around the site | part embed | buried in the base frame 9 (refer FIG.4 (b)) among the underground floor pillars 1. FIG. Is desirable. In the present embodiment, the space around the exposed portion of the steel core 1b (the portion located between the lower end surface of the column portion 1a and the upper end surface of the foundation pile 2) and the space around the lower end portion of the column portion 1a. Are filled with hard granular material 3.

上部埋戻し工程は、図2の(b)に示すように、埋戻材4を硬質粒状材料3の上側に投入する工程である。埋戻材4の種類等に制限はなく、適宜な材料を使用することができる。例えば、前記した硬質粒状材料を埋戻材4としてもよいし、掘削孔Aを削孔する際に発生した残土を埋戻材4としてもよい。なお、残土が汚泥である場合には、乾燥処理または固化処理したものを埋戻材4とすればよい。   The upper backfilling step is a step of feeding the backfilling material 4 to the upper side of the hard granular material 3 as shown in FIG. There is no restriction | limiting in the kind etc. of the backfilling material 4, An appropriate material can be used. For example, the above-described hard granular material may be used as the backfill material 4, and the residual soil generated when the excavation hole A is drilled may be used as the backfill material 4. In addition, what is necessary is just to use the thing which dried or solidified as the backfill material 4 when residual soil is sludge.

上記した各工程を含む地下階柱設置工程(本実施形態に係る地下階柱の設置方法)が完了したならば、図3の(a)に示すように、トップスラブ構築工程に移行する。   If the underground floor pillar installation process (the installation method of the underground floor pillar which concerns on this embodiment) including each process mentioned above is completed, as shown to (a) of FIG. 3, it will transfer to a top slab construction process.

トップスラブ構築工程は、図3の(a)に示すように、建物1階の床スラブとなるトップスラブ5を構築し、このトップスラブ5を地下階柱1,1に支持させる工程である。本実施形態のトップスラブ構築工程には、土留壁W,Wの内側において地盤を所定深さまで掘削する工程(一次掘削工程)、トップスラブ5用の型枠や鉄筋(図示略)を配置する工程、型枠内にコンクリートを打設する工程などが含まれている。なお、本実施形態のトップスラブ5は、隣り合う地下階柱1,1の上端部同士を繋ぐ大梁5aと一体に形成され、大梁5aを介して地下階柱1,1に支持される。トップスラブ5は、トップスラブ構築工程以後の工程を行う際の作業床となる。   As shown in FIG. 3A, the top slab construction step is a step of constructing a top slab 5 to be a floor slab on the first floor of the building and supporting the top slab 5 on the underground floor columns 1 and 1. In the top slab construction process of the present embodiment, a process of excavating the ground to a predetermined depth inside the retaining walls W, W (primary excavation process), a process of arranging a formwork and reinforcing bars (not shown) for the top slab 5 The process includes placing concrete in the mold. In addition, the top slab 5 of this embodiment is integrally formed with the large beam 5a which connects the upper end parts of the adjacent underground story columns 1 and 1, and is supported by the underground story columns 1 and 1 via the large beam 5a. The top slab 5 serves as a work floor when performing processes after the top slab construction process.

地下中間階構築工程は、図3の(b)に示すように、地下中間階の床スラブとなる中間スラブ6や地下階柱1,1の中間部同士を繋ぐ大梁6aなどを構築する工程である。本実施形態の地下中間階構築工程には、トップスラブ5の下側の地盤を中間スラブ6や大梁6aの構築予定位置の下側まで掘削する工程(二次掘削工程)、中間スラブ6用の型枠や鉄筋(図示略)を配置する工程、型枠内にコンクリートを打設する工程などが含まれている。   As shown in FIG. 3 (b), the underground intermediate floor construction process is a process of constructing an intermediate slab 6 that becomes a floor slab of the underground intermediate floor, a large beam 6a that connects the intermediate portions of the underground floor pillars 1 and 1, and the like. is there. In the underground intermediate floor construction process of the present embodiment, a process of excavating the ground below the top slab 5 to a position below the planned construction position of the intermediate slab 6 and the large beam 6a (secondary excavation process), It includes a step of placing a formwork and a reinforcing bar (not shown), a step of placing concrete in the formwork, and the like.

なお、地下中間階を構築しない場合には、地下中間階構築工程を省略し、複数の地下中間階を構築する場合には、地下中間階構築工程を繰り返せばよい。また、中間スラブ6や大梁6aは、地下躯体9(図4の(b)参照)を構築した後に構築してもよい。   In addition, when not building a basement intermediate floor, a basement intermediate floor construction process is abbreviate | omitted, and when building a some underground basement floor, a basement intermediate floor construction process should just be repeated. Further, the intermediate slab 6 and the large beam 6a may be constructed after constructing the underground frame 9 (see FIG. 4B).

基礎躯体構築工程は、図4の(a)および(b)に示すように、トップスラブ5の下方に基礎躯体9を構築する工程である。なお、図示は省略するが、本実施形態の基礎躯体9は、隣り合う基礎杭2,2の上端部同士を繋ぐ基礎梁と、最下階の床スラブと、を具備している。   As shown in FIGS. 4A and 4B, the foundation chassis construction process is a process of constructing the foundation chassis 9 below the top slab 5. In addition, although illustration is abbreviate | omitted, the foundation frame 9 of this embodiment is equipped with the foundation beam which connects the upper end parts of the adjacent foundation piles 2 and 2, and the floor slab of the lowest floor.

本実施形態の基礎躯体構築工程には、床付け掘削工程、下地層形成工程、打設準備工程、基礎躯体用コンクリート打設工程などが含まれている。   The foundation frame construction process of the present embodiment includes a flooring excavation process, a foundation layer forming process, a placing preparation process, a concrete placing process for foundation foundations, and the like.

床付け掘削工程は、中間スラブ6の下側の地盤を基礎躯体9の構築予定位置の下側まで掘削する工程である。   The flooring excavation step is a step of excavating the lower ground of the intermediate slab 6 to the lower side of the construction planned position of the foundation frame 9.

下地層形成工程は、鋼製芯材1bの周囲に投入されていた硬質粒状材料3(図3の(b)参照)を床付面上に敷き均して下地層7を形成する工程である。硬質粒状材料3の量が不足している場合には、不足分に相当する量の割栗石等を搬入する。   The underlayer forming step is a step of forming the underlayer 7 by spreading the hard granular material 3 (see FIG. 3B), which has been introduced around the steel core 1b, on the floored surface. . When the amount of the hard granular material 3 is insufficient, the amount of cracked stone corresponding to the shortage is carried in.

打設準備工程は、下地層7上に捨てコンクリート8を打設するとともに、硬化した捨てコンクリート8上に基礎躯体9用の型枠や鉄筋を配置する工程である。   The placing preparation step is a step of placing the discarded concrete 8 on the foundation layer 7 and arranging the formwork and reinforcing bars for the foundation frame 9 on the hardened discarded concrete 8.

基礎躯体用コンクリート打設工程は、図4の(b)に示すように、捨てコンクリート8上や型枠内に基礎躯体9用のコンクリートを打設し、基礎杭2の杭頭部から露出した鋼製芯材1bを基礎躯体9に埋設する工程である。なお、基礎躯体用コンクリート打設工程に先立って、柱部1aの下端部および鋼製芯材1bの露出部分(すなわち、基礎躯体9に埋設される部分)に対して清掃を行う。本実施形態では、柱部1aの下端部および鋼製芯材1bの露出部分の周囲に、泥状になり難い硬質粒状材料3を充填していたので、鋼製芯材1b等の表面に泥等が固着し難く、したがって、泥状になり易い掘削残土で埋め戻した場合に比べて、清掃作業が容易になる。   As shown in FIG. 4 (b), the concrete placing process for the foundation frame is placed from the pile head of the foundation pile 2 by placing concrete for the foundation frame 9 on the discarded concrete 8 or in the formwork. This is a step of embedding the steel core 1b in the foundation housing 9. Prior to the concrete placing process for the foundation frame, cleaning is performed on the lower end of the column part 1a and the exposed portion of the steel core 1b (that is, the part embedded in the foundation frame 9). In the present embodiment, since the hard granular material 3 that is unlikely to be mud is filled around the lower end of the pillar portion 1a and the exposed portion of the steel core material 1b, the surface of the steel core material 1b or the like is mud. Therefore, the cleaning work is easier than in the case of backfilling with excavated residual soil that tends to be mud.

本実施形態に係る地中構造物の構築方法は、以上のような工程を含むものであり、上記各工程を経ることで、地中構造物(地下階)を構築することができる。   The construction method of the underground structure according to the present embodiment includes the steps as described above, and the underground structure (underground floor) can be constructed through the above steps.

本実施形態に係る地下階柱の設置方法によると、地下階柱1の鋼製芯材1bが硬質粒状材料3によって根固めされるようになるので、単なる掘削残土で根固めした場合に比べて、地下階柱1の据付位置がずれ難くなる。また、本実施形態に係る地中構造物の構築方法によると、鋼製芯材1bの周囲に投入した硬質粒状材料3を床付面に敷き均すこととしたので、割栗石等の搬入作業を省略あるいは軽減することが可能になる。   According to the installation method of the underground floor pillar according to the present embodiment, the steel core 1b of the underground floor pillar 1 is rooted by the hard granular material 3, so that it is compared with a case where the steel core material 1b is rooted by simple excavation residual soil. The installation position of the underground floor pillar 1 becomes difficult to shift. Moreover, according to the construction method of the underground structure according to the present embodiment, since the hard granular material 3 thrown around the steel core 1b is spread on the floored surface, the work of carrying in, for example, quarrel stone Can be omitted or reduced.

(a)および(b)は、本発明の一実施形態に係る地下階柱の設置方法および地中構造物の構築方法を説明するための模式的な断面図である。(A) And (b) is typical sectional drawing for demonstrating the installation method of the underground floor pillar which concerns on one Embodiment of this invention, and the construction method of an underground structure. (a)および(b)は、図1の(b)に続く工程を説明するための模式的な断面図である。(A) And (b) is typical sectional drawing for demonstrating the process following (b) of FIG. (a)および(b)は、図2の(b)に続く工程を説明するための模式的な断面図である。(A) And (b) is typical sectional drawing for demonstrating the process following (b) of FIG. (a)および(b)は、図3の(b)に続く工程を説明するための模式的な断面図である。(A) And (b) is typical sectional drawing for demonstrating the process following (b) of FIG.

符号の説明Explanation of symbols

1 地下階柱
1a 柱部
1b 鋼製芯材
2 基礎杭
3 硬質粒状材料
4 埋戻土
5 トップスラブ
6 中間スラブ
7 下地層
8 捨てコンクリート
9 基礎躯体
A 掘削孔
DESCRIPTION OF SYMBOLS 1 Basement column 1a Column part 1b Steel core material 2 Foundation pile 3 Hard granular material 4 Backfill 5 Top slab 6 Intermediate slab 7 Underlayer 8 Discarded concrete 9 Foundation frame A Drilling hole

Claims (2)

プレキャストコンクリート製の柱部と当該柱部から下方向に向って延出する鋼製芯材とを有する地下階柱を地盤に形成した掘削孔に挿入し、前記鋼製芯材の下端部を基礎杭の杭頭部に埋設する工程と、
前記鋼製芯材の周囲に硬質粒状材料を投入する工程と、
前記硬質粒状材料の上側に埋戻材を投入する工程と、を含むことを特徴とする地下階柱の設置方法。
A basement column having a precast concrete column and a steel core extending downward from the column is inserted into an excavation hole formed in the ground, and the lower end of the steel core is used as a foundation. A process of burying in a pile head,
Introducing a hard granular material around the steel core;
And a step of introducing a backfill material to the upper side of the hard granular material.
プレキャストコンクリート製の柱部と当該柱部から下方向に向って延出する鋼製芯材とを有する地下階柱を地盤に形成した掘削孔に挿入し、前記鋼製芯材の下端部を基礎杭の杭頭部に埋設する工程と、
前記鋼製芯材の周囲に硬質粒状材料を投入する工程と、
前記硬質粒状材料の上側に埋戻材を投入する工程と、
トップスラブを構築し、当該トップスラブを前記地下階柱に支持させる工程と、
前記トップスラブの下側を掘削する工程と、
前記基礎躯体の床付面上に前記硬質粒状材料を敷き均して下地層を形成する工程と、
前記下地層上に前記基礎躯体用のコンクリートを打設し、前記杭頭部から露出した前記鋼製芯材を前記基礎躯体に埋設する工程とを含むことを特徴とする地中構造物の構築方法。
A basement column having a precast concrete column and a steel core extending downward from the column is inserted into an excavation hole formed in the ground, and the lower end of the steel core is used as a foundation. A process of burying in a pile head,
Introducing a hard granular material around the steel core;
Introducing a backfill material above the hard granular material;
Constructing a top slab and supporting the top slab on the basement pillar;
Drilling the underside of the top slab;
Laying and leveling the hard granular material on the flooring surface of the foundation housing to form an underlayer;
Constructing an underground structure characterized by including placing the concrete for the foundation frame on the foundation layer and burying the steel core material exposed from the pile head in the foundation frame Method.
JP2008195504A 2008-07-29 2008-07-29 Installation method of underground floor pillar and construction method of underground structure Expired - Fee Related JP5140515B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008195504A JP5140515B2 (en) 2008-07-29 2008-07-29 Installation method of underground floor pillar and construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008195504A JP5140515B2 (en) 2008-07-29 2008-07-29 Installation method of underground floor pillar and construction method of underground structure

Publications (2)

Publication Number Publication Date
JP2010031564A true JP2010031564A (en) 2010-02-12
JP5140515B2 JP5140515B2 (en) 2013-02-06

Family

ID=41736354

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008195504A Expired - Fee Related JP5140515B2 (en) 2008-07-29 2008-07-29 Installation method of underground floor pillar and construction method of underground structure

Country Status (1)

Country Link
JP (1) JP5140515B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018178562A (en) * 2017-04-14 2018-11-15 株式会社横河住金ブリッジ Tide embankment and method for constructing tide embankment
CN114658031A (en) * 2021-12-23 2022-06-24 中国建筑第二工程局有限公司 Basement back-jacking supporting structure of overweight steel structure truss and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6286242A (en) * 1985-10-09 1987-04-20 株式会社フジタ Reverse casting consttructin method
JPH08296243A (en) * 1995-04-24 1996-11-12 Konoike Constr Ltd Construction method for underground structure by precast concrete central pillar
JP2006037483A (en) * 2004-07-27 2006-02-09 Mitsui Kagaku Sanshi Kk Geogrid temporarily fastening pile to be buried underground and its use
JP2007277825A (en) * 2006-04-03 2007-10-25 Kajima Corp Construction method of buried pipe under road

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6286242A (en) * 1985-10-09 1987-04-20 株式会社フジタ Reverse casting consttructin method
JPH08296243A (en) * 1995-04-24 1996-11-12 Konoike Constr Ltd Construction method for underground structure by precast concrete central pillar
JP2006037483A (en) * 2004-07-27 2006-02-09 Mitsui Kagaku Sanshi Kk Geogrid temporarily fastening pile to be buried underground and its use
JP2007277825A (en) * 2006-04-03 2007-10-25 Kajima Corp Construction method of buried pipe under road

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018178562A (en) * 2017-04-14 2018-11-15 株式会社横河住金ブリッジ Tide embankment and method for constructing tide embankment
CN114658031A (en) * 2021-12-23 2022-06-24 中国建筑第二工程局有限公司 Basement back-jacking supporting structure of overweight steel structure truss and construction method

Also Published As

Publication number Publication date
JP5140515B2 (en) 2013-02-06

Similar Documents

Publication Publication Date Title
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
JP2008013926A (en) Existing building foundation reinforcing method
KR100984898B1 (en) The Construction Method of Descenting Underground Structure
JP2006328716A (en) Structure and method for underpinning of existing structure and method of constructing new structure near existing structure
KR100960603B1 (en) Construction method of retaining wall using phc pile
JP4611113B2 (en) Integrated construction method of pile and column
JP5351125B2 (en) Open shield machine start method of open shield method
JP6422084B2 (en) Underground space construction method
JP5140515B2 (en) Installation method of underground floor pillar and construction method of underground structure
JP2012087561A (en) Construction method of outer peripheral column in inverted construction
KR20190012368A (en) Smallcaliber composite pile wall using small drilling rig at adjacent building proximity section and construction method of the same
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
JP6220659B2 (en) Position adjustment method of reaction force receiving member and top of column
JP5378066B2 (en) Mountain fastening method
JP2011089320A (en) Method for constructing precast basement column
JP5027752B2 (en) Construction method of underground floor pillar and underground floor pillar
KR101222348B1 (en) The Supporting Structure and Pressing device of Underground Structure
JP2020159006A (en) Retaining wall and its construction method
KR101135652B1 (en) Pulling method of pile
JP2007224716A (en) Method for constructing earth retaining wall
JP6534026B2 (en) Seismic isolation building and its construction method
JP2005307688A (en) Construction method for earth retaining wall for newly built underground skeleton and construction method for newly built skeleton by use of its method
KR101128955B1 (en) The Construction Method of Pressing Underground Structure
JP4344733B2 (en) Seismic reinforcement structure for existing pile foundation structures
JP4195215B2 (en) Mountain retaining method and foundation construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110107

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120420

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120508

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120703

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20121113

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20121119

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 5140515

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20181122

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees