KR100960603B1 - Construction method of retaining wall using phc pile - Google Patents

Construction method of retaining wall using phc pile Download PDF

Info

Publication number
KR100960603B1
KR100960603B1 KR1020090068125A KR20090068125A KR100960603B1 KR 100960603 B1 KR100960603 B1 KR 100960603B1 KR 1020090068125 A KR1020090068125 A KR 1020090068125A KR 20090068125 A KR20090068125 A KR 20090068125A KR 100960603 B1 KR100960603 B1 KR 100960603B1
Authority
KR
South Korea
Prior art keywords
wall
phc pile
ground
floor
phc
Prior art date
Application number
KR1020090068125A
Other languages
Korean (ko)
Inventor
김대호
김원근
김영호
Original Assignee
김대호
김원근
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김대호, 김원근 filed Critical 김대호
Priority to KR1020090068125A priority Critical patent/KR100960603B1/en
Application granted granted Critical
Publication of KR100960603B1 publication Critical patent/KR100960603B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE: An underground composition wall construction method using a retaining wall composed of PHC piles is provided to carry out simple and minute construction by reducing the thickness of a wall. CONSTITUTION: An underground composition wall construction method using a retaining wall composed of PHC piles(11) comprises following steps. The ground is bored along a ground boundary line and a PHC pile is inserted to form a retaining wall. A connecting bar fixing unit is welded after arranging the head of a PHC pile and inserting a connecting bar. The head of the PHC piles is connected by digging the ground at fixed depth, a reinforcing bar is arranged, a cap beam is formed, a mold is installed, and then concrete is poured.

Description

피에이치씨파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법{Construction method of retaining wall using PHC pile}Construction method of retaining wall using PHC pile}

본 발명은 건물의 지하층 외벽을 흙막이벽과 일체가 되도록 시공하는 지하합벽에 관한 것으로, 특히 지하층 외벽 및 지상층의 기둥 또는 벽체를 최대한 대지경계선에 근접하여 시공할 수 있고 동시에 합벽 시공시 벽체의 두께를 줄일 수 있는 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법에 관한 것이다.The present invention relates to an underground plywood that is constructed so that the basement outer wall of a building is integrated with an earthquake wall. In particular, it is possible to construct a column or wall of the basement outer wall and the ground floor as close to the land boundary as possible, and at the same time, to increase the thickness of the wall when constructing the plywood wall. The present invention relates to a construction method of underground plywood wall using a retaining wall composed of PHC piles.

도심지 건물 시공시 대지경계선에 근접시켜 지하 구조물을 시공할 경우 외벽 형틀 시공을 위한 작업공간이 없으므로 흙막이벽을 건축물의 지하층 외벽 구축을 위한 외부 거푸집으로 사용하여 합벽으로 시공하게 된다. In the case of the construction of the downtown building, when the underground structure is installed close to the ground boundary line, there is no work space for the exterior wall frame construction, so it is constructed as a plywood wall using the earthen wall as the external formwork for the construction of the exterior floor of the building.

흙막이벽을 H-파일+토류판으로 구성할 경우, 흙막이벽의 최소공간을 마련하기 위하여 H-PILE(엄지말뚝; 300x200x9x14, 300x300x10x15), 띠장(Wale; 300x300x10x15(H-PILE)) 및 차수공(L.W(물유리계약액주입공법) 공법 적용시 최소 500mm, S.G.R(Space Grouting Rocket System-물유리계)공법 적용시 최소 600mm)을 위한 공간을 감안하여 최소한 1,100mm가 필요하다. 차수공이 없더라도 시공 공간 확보를 위하여 천공기 사용시 대지경계선에서 최소 550mm가 필요하고. 경사계(계측 기) 및 지하수위계 등을 배면지반에 시공하려면 크롤라 드릴의 작업공간이 최소 400mm는 필요하므로 흙막이벽을 시공하려면 기본적으로 550 + 400 = 950mm가 필요하다. 결론적으로 건물 외벽선은 대지경계선에서 최소 1M 이상은 되어야 합벽(흙막이벽체를 외부 거푸집으로 사용)시공이 가능하고, 합벽이 아닌 되메우기로 해야 할 경우는 최소 1.5M 이상이 필요하다. 따라서, 건축도면상에 건물 외벽선과 대지경계선이 1M가 되지 않는 경우 벽체의 최소두께를 산정하고 철근배근이 가능한 범위에서 흙막이벽 시공을 계획하여야 하는 제한이 따른다.When the wall is composed of H-pile + earth plate, H-PILE (Thumb pile; 300x200x9x14, 300x300x10x15), Wale; 300x300x10x15 (H-PILE), and work order (LW) to provide the minimum space for the wall. (Water glass contract amount injection method) At least 1,100mm is required considering the space for at least 500mm when applying the method and at least 600mm when applying the Space Grouting Rocket System (SGR) method. Even if there is no liner, at least 550mm is required on the ground boundary line when using the drilling machine to secure the construction space. In order to install inclinometers and ground level gauges on the back ground, the crawler drill requires at least 400 mm of working space. Therefore, 550 + 400 = 950 mm is required to construct the wall. In conclusion, the outer wall of the building should be at least 1M above the boundary of the land to be able to construct a plywood wall (use the wall as an external formwork), and at least 1.5M should be needed to refill the plywood instead of the plywood wall. Therefore, when the outer wall line and the ground boundary line is less than 1M on the construction drawing, the minimum thickness of the wall should be calculated and the construction of the retaining wall should be planned in the range where reinforcement is possible.

합벽으로 계획한 경우에도 흙막이 띠장과 건물 외벽과의 관계에 따라 띠장과 외벽이 일치한 경우에는 철근 배근은 문제가 없지만 콘크리트 양이 상당히 늘어나는 문제가 있고, 엄지말뚝과 외벽이 일치할 경우에는 철근 배근은 띠장이 철거되어야 할 수 있으므로 공사가 지연되는 문제가 있다.Even if it is planned to be plywood, the rebar reinforcement is not a problem when the reinforcement and the outer wall coincide according to the relationship between the clamboard and the outer wall of the building, but there is a problem that the amount of concrete increases considerably. There is a problem that the construction is delayed because the silver belt may need to be removed.

도 6은 흙막이벽을 CIP공법으로 구축하고 지하층 외벽을 합벽으로 시공한 모습을 나타낸 단면도이다.Figure 6 is a cross-sectional view showing the construction of the retaining wall by the CIP method and the construction of the outer wall of the basement floor as a combined wall.

도 6에 도시된 바와 같이 흙막이벽을 오거 또는 보링기로 천공하여 구멍의 자립을 안정액 또는 케이싱으로 처리하고 구멍 내에 콘크리트를 타설하여 지중에 주열 벽체를 형성하는 CIP공법으로 구축한 경우 현장타설 콘크리트 흙막이벽(CIP흙막이벽, 100)의 두께(400mm), 지하층 외벽(200)의 두께(300~400mm) 그리고 바닥 슬래브(300)의 내민부분(310)의 길이(400mm)를 합하여 전체적으로 1100~1200mm 정도의 두께가 된다. 또한, CIP 흙막이벽(100)을 본 구조물의 기초로 사용하지 못하므로 지상층의 기둥이나 벽체(400)가 흙막이벽(100) 상부에 설치되지 못하고 지하층 외벽(200) 상에 설치되므로 지상층의 건축 바닥면적이 충분히 활용되지 못하게 되어 건축 리모델링이나 증축시 사업성 및 경제성에 큰 영향을 미치게 된다. 이러한 문제점은 흙막이벽을 H-파일+토류판으로 구성한 경우에도 동일하게 나타난다. As shown in FIG. 6 when the earthen wall is drilled with an auger or boring, the independence of the hole is treated with a stabilizer or a casing, and the concrete is poured into the hole to build a main heat wall in the ground. (CIP mudwall, 100) thickness (400mm), basement layer outer wall (200) thickness (300 ~ 400mm) and the length of the inner part 310 of the floor slab 300 (400mm) in total of about 1100 ~ 1200mm It becomes thickness. In addition, since the CIP mud wall 100 is not used as the basis of the structure, the ground floor pillars or walls 400 are not installed on the mud wall 100, but are installed on the basement outer wall 200, so that the ground floor is the building floor. The area will not be fully utilized, which will greatly affect the feasibility and economic feasibility of building remodeling or expansion. This problem also appears when the barrier wall is composed of H-pile + earth plate.

본 발명이 해결하고자 하는 과제는 지하층 외벽 및 지상층의 기둥 또는 벽체를 최대한 대지경계선에 근접하여 시공할 수 있어 대지의 이용도가 높고 합벽 시공시 벽체의 두께를 줄일 수 있어 경제적이며 또한 시공이 단순하여 공기단축 및 정밀도 높은 시공이 가능한 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법을 제공하는 데 있다.The problem to be solved by the present invention is to be able to construct the basement outer wall and the ground floor column or wall as close as possible to the boundary of the land line, the use of the land is high and the wall thickness can be reduced when constructing the plywood, economical and simple construction The present invention provides a construction method for underground plywood walls using an earthquake wall composed of PHC piles, which allows for shortening of air and high precision construction.

본 발명의 적절한 실시형태에 따르면, (a) 대지경계선을 따라 지반을 천공하고 PHC파일을 삽입 및 최종 경타하는 단계를 반복하여 지중에 PHC파일로 구성되는 흙막이벽을 형성하는 단계; (b) 버팀보를 지지하면서 동시에 본 구조물의 기둥이 되는 내부 기둥을 평면계획에 따라 시공하는 단계; (c) 각 PHC파일의 두부를 정리한 다음 연결바를 PHC파일의 중공에 노출되도록 삽입한 후 연결바 고정수단을 연결바에 접합시켜 연결바의 설치 위치를 고정하는 단계; (d) 일정한 심도로 굴토한 다음 각 PHC파일의 두부를 연결하면서 지상층 기둥 또는 벽체가 세워지는 기초가 되는 캡 빔 형성을 위한 철근을 배근하고 거푸집을 설치한 후 캡 빔 콘크리트와 각 PHC파일의 중공을 충전하는 콘크리트를 동시에 타설하는 단계; (e) 소정의 계획 심도까지 굴토한 다음 띠장을 대고 흙막이벽을 지지하도록 띠장과 내부 기둥을 연결하는 버팀보를 설치하는 공정을 반복하여 계획 굴착고에 도달할 때까지 굴토하는 단계; (f) 최하층에 해당하는 PHC파일의 외면에 다수의 전단연결재를 설치하고 메탈라스를 고정한 다음 기초 바닥 콘크리트를 타설하고 최하층 외벽 콘크리트를 타설하여 최하층 합벽을 시공하는 단계; (g) 최하층+1층에 해당하는 층의 띠장과 버팀보를 제거한 후 PHC파일의 외면에 다수의 전단연결재를 설치하고 메탈라스를 고정한 다음 당해 층 바닥 콘크리트를 타설하고 당해 층 외벽 콘크리트를 타설하여 당해 층 합벽을 시공하는 공정을 지상층-1층까지 반복하는 단계; 및 (h) 지상층 바닥 콘크리트를 타설하는 단계;를 포함하며, 상기 (f)단계에서 기초 바닥과 합벽이 접하는 부분의 기초 바닥 하면에는 합벽을 통해 전달되는 하중이 지반에 균등하게 전달하기 위해 기초 바닥의 다른 부분에 비해 춤이 큰 브라켓부가 형성되도록 하는 것을 특징으로 하는 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법.이 제공된다.According to a preferred embodiment of the present invention, the method comprises the steps of: (a) perforating the ground along the land boundary, inserting and finally struck the PHC pile to form a barrier wall composed of PHC piles in the ground; (b) constructing an internal column that is a pillar of the structure while supporting the brace and according to the plan; (c) arranging the head of each PHC pile and inserting the connecting bar to be exposed to the hollow of the PHC pile and then joining the connecting bar fixing means to the connecting bar to fix the installation position of the connecting bar; (d) After being dug to a certain depth, connecting the heads of each PHC pile, reinforcing the reinforcing bars for the formation of the cap beams on which the ground column pillars or walls are erected, and installing the formwork, and then hollowing the cap beam concrete and each PHC pile Pouring concrete at the same time filling the; (e) jutting to a predetermined depth of depth, then repeating the process of installing a brace to connect the girdle and the inner pillar to support the retaining wall, and gulting until the planned dig is reached; (f) installing a plurality of shear connectors on the outer surface of the PHC pile corresponding to the lowermost floor, fixing the metal lath, and then laying the foundation floor concrete and laying the lowermost outer wall concrete to construct the lowermost plywood; (g) After removing the strips and braces of the layer corresponding to the bottom layer +1, install a plurality of shear connectors on the outer surface of the PHC pile, fix the metal lath, cast the floor concrete of the floor, and cast the outer wall concrete of the floor. Repeating the process of constructing the laminated wall to the ground layer-1 layer; And (h) pouring the ground floor concrete; wherein, in step (f), the bottom of the bottom of the part where the foundation floor and the wall contact each other has a load transferred through the wall of the foundation to equally transfer the ground to the ground. Underground plywood construction method using a retaining wall consisting of a PHC pile, characterized in that to form a larger bracket than the other parts of the dance is provided.

본 발명의 다른 적절한 실시형태에 따르면, PHC파일은 서로 이웃하는 PHC파일에 의해 주입구멍이 형성될 수 있도록 대향하는 한 쌍의 차수그라우팅홈이 형성되어 있으며, 이 차수그라우팅홈은 외주면에 단면의 도심을 지나는 중심선에 대해 후방으로 소정의 편심거리를 가지며, (a)단계 이후에 차수그라우팅홈에 차수를 위한 그라우팅을 실시하는 단계를 더 포함한다.According to another suitable embodiment of the present invention, the PHC pile is formed with a pair of order grouting grooves facing each other so that injection holes can be formed by neighboring PHC piles. It has a predetermined eccentric distance to the rear of the center line passing through, and further comprising the step of performing grouting for the degree in the order grouting groove after step (a).

삭제delete

본 발명의 또 다른 적절한 실시형태에 따르면, (g)단계에서 해당 층 바닥과 합벽 사이에는 중간층 테두리보가 형성되도록 한다.According to another suitable embodiment of the present invention, in step (g), an intermediate layer border beam is formed between the bottom of the layer and the plywood.

본 발명에 의한 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법에 따르면 지하층 외벽 및 지상층의 기둥 또는 벽체를 최대한 대지경계선에 근접하여 시공할 수 있어 대지의 이용도가 높고 합벽 시공시 벽체의 두께를 줄일 수 있어 경제적이며 또한 시공이 단순하여 공기단축 및 정밀도 높은 시공이 가능하다.According to the construction method of underground plywood wall using PHC pile according to the present invention, it is possible to construct pillars or walls of the basement outer wall and ground layer as close as possible to the boundary of the land, so that the use of the land is high and the thickness of the wall when the plywood is constructed Economical and simple construction is possible because it can be reduced, so it is possible to shorten the air and high precision construction.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시 예를 상세히 설명하기로 한다. 도면들 중, 동일한 구성요소 또는 부품들은 가능한 한 동일한 참조부호를 표기하며, 관련된 공지기능 혹은 구성에 대한 구체적인 설명은 생략한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the drawings, the same components or parts are denoted by the same reference numerals as much as possible, and detailed descriptions of related known functions or configurations are omitted.

도 1은 본 발명에 따른 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법의 흙막이벽 구축단계를 설명하기 위한 도면이고, 도 2는 본 발명에 따라 시공된 지하합벽의 구성을 보여주는 단면도이며, 도 3은 PHC파일의 두부와 캡 빔 및 기상층 바닥의 접합부 구조를 보여주는 단면도이다.1 is a view for explaining the construction step of the earthquake wall construction of the underground plywood construction method using the earthquake wall consisting of PHC pile according to the present invention, Figure 2 is a cross-sectional view showing the configuration of the underground plywood constructed in accordance with the present invention, Figure 3 is a cross-sectional view showing the joint structure of the head of the PHC pile, the cap beam and the bottom of the vapor phase layer.

본 발명에 따른 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법은, 흙막이벽 구축단계, 내부 기둥 시공단계, PHC파일 두부 정리단계, 캡 빔 시공단계, 굴토단계, 기초 바닥 및 최하층 합벽 시공단계, 및 합벽 시공 반복 후 지상층 바닥 시공단계로 구성된다. 흙막이벽을 토압, 수압 등의 측압에 대해 저항하도록 지지하면서 굴토하는 방법으로는 다양한 방법이 공지되어 있고 본 발명에서는 이들 공지된 방법 중 대지의 주변조건, 지반의 성질, 건축물의 규모나 성격 등을 고려하여 적절히 선택하여 적용할 수 있으므로 흙막이벽의 지지방법이나 굴토방법 등에 대한 상세한 설명은 본 발명을 이해하는데 필요한 범위 내에서 설명하기로 한다. 따라서 본 발명은 아래에서 설명되는 흙막이벽의 지지방법 및 굴토방법에 한정되지 않는 다.Underground pavement construction method using the earthquake wall consisting of PHC pile according to the present invention, the construction of the earthquake wall construction step, internal column construction step, PHC pile head cleaning step, cap beam construction step, gulting step, foundation floor and bottom layer construction wall construction step, And ground floor floor construction step after repeating the construction of the plywood wall. Various methods are known as the method of supporting the retaining wall while resisting the side pressure such as earth pressure and water pressure, and in the present invention, various methods are known in the present invention. Since it can be appropriately selected and applied in consideration, a detailed description of the supporting method and the excavation method of the retaining wall will be described within the range necessary to understand the present invention. Therefore, the present invention is not limited to the supporting method and the excavation method of the retaining wall described below.

(a) 흙막이벽 구축단계(a) Block wall construction stage

대지경계선을 따라 지반을 천공하고 PHC파일(11)을 삽입 및 최종 경타하는 단계를 반복하여 지중에 PHC파일로 구성되는 흙막이벽을 형성한다. 본 발명에 적용되는 PHC파일(11)은 공지의 PHC파일을 적용하는 것도 가능하나 그 경우 차수를 위해서는 별도의 공정이 필요할 수 있는 단점이 있다. 이에 본 발명에서는 도 1에 나타낸 바와 같이, 외주면에 단면의 도심을 지나는 중심선(cl)에 대해 후방으로 소정의 편심거리(e)를 갖고 한 쌍의 차수그라우팅홈(111)이 형성된 PHC파일(11)을 적용한다. 이렇게 한 쌍의 차수그라우팅홈(111)을 단면의 도심을 지나는 중심선(cl)에 대해 후방으로 소정의 편심거리(e)를 갖도록 형성함에 따라 파일을 최대한 근접 시공할 수 있는 장점이 있다. 한 쌍의 차수그라우팅홈(111)이 단면의 도심을 지나는 중심선(cl) 상에 형성되어 있다면 그라우팅제가 파일의 후방으로 퍼져나가도록 하기 위해 파일을 서로 이격시키고 또한 전방으로 그라우팅제가 누출되지 않도록 별도의 대책을 강구할 필요가 있으나 본 발명에서와 같이 차수그라우팅홈(111)이 단면의 도심을 지나는 중심선(cl)에 대해 후방으로 소정의 편심거리(e)를 갖게 되면 인접하는 파일을 밀착시켜 그라우팅제가 누출되지 않도록 할 수 있다. 그라우팅제(약액)의 주입공법으로는 공지된 LW공법, SGR공법, JSP 공법 등이 선택적으로 적용될 수 있다. 또한 종래에는 천공홀의 직경이 파일의 직경보다 10cm 정도 크게 천공할 필요가 있었으나 본 발명에서는 천공홀의 직경을 휠씬 적게 할 수 있어 PHC파일(11)을 대지경계선에 최대한 근접하여 시공이 가능하다. Perforating the ground along the ground boundary line and repeating the step of inserting and final strike the PHC pile (11) to form a barrier wall consisting of PHC pile in the ground. PHC file 11 to be applied to the present invention is also possible to apply a known PHC file, but in that case there is a disadvantage that a separate process may be required for the order. In the present invention, as shown in Figure 1, PHC pile 11 having a pair of order grouting groove 111 is formed on the outer peripheral surface with a predetermined eccentric distance e rearward with respect to the center line (cl) passing through the center of the cross section ). Thus, by forming a pair of order grouting groove 111 to have a predetermined eccentric distance (e) to the rear with respect to the center line (cl) passing through the center of the cross section has the advantage that can be installed as close as possible. If a pair of order grouting grooves 111 are formed on the center line cl passing through the center of the cross section, the grouting agent is spaced apart from each other to allow the grouting agent to spread to the rear of the pile and also to prevent the grouting agent from leaking forward. Although it is necessary to take a countermeasure, when the degree grouting groove 111 has a predetermined eccentric distance e rearward with respect to the center line cl passing through the center of the cross section as in the present invention, the grouting agent is brought into close contact with the adjacent pile. It can be prevented from leaking. As the injection method of the grouting agent (chemical solution), a known LW method, SGR method, JSP method, etc. may be selectively applied. In addition, in the related art, the diameter of the drilling hole needs to be drilled about 10 cm larger than the diameter of the pile. However, in the present invention, the diameter of the drilling hole can be made much smaller, so that the construction of the PHC pile 11 as close as possible to the ground boundary line is possible.

(b) 내부 기둥 시공단계(b) Internal column construction stage

버팀보를 지지하면서 동시에 본 구조물의 기둥이 되는 내부 기둥을 평면계획에 따라 시공한다. 기둥의 설치방법은 주지된 탑다운(Top-down) 공법이나 SPS(Strut as Permanent System) 공법에서 적용되는 방법을 그대로 적용할 수 있다. 예를 들어 탑다운(Top-down) 공법에서와 같이 기둥이 설치될 위치를 천공한 다음 크레인을 이용해 선조립된 기초 철근과 철골 기둥을 설치하고 기초 부분은 콘크리트를 타설하고 나머지 부분은 자갈 혹은 빈배합 콘크리트를 채워 설치된 철골 기둥의 이동을 방지한다.At the same time, support the brace and construct the inner pillar which becomes the pillar of the structure according to the plan. The installation method of the column can be applied as it is applied in the known top-down method or the Strut as Permanent System (SPS) method. For example, drill the location where the column is to be installed, as in the top-down method, install the prefabricated foundation reinforcing bar and steel column using the crane, and the foundation part is concrete, and the rest part is gravel or empty mixture. Prevents the movement of steel columns installed with concrete.

(c) PHC파일 두부 정리단계(c) PHC file tofu cleanup step

각 PHC파일의 두부를 정리한 다음 PHC파일의 두부와 캡 빔 그리고 캡 빔 상부에 구축될 지상층 벽체 또는 기둥이 일체로 거동할 수 있도록 이들을 합성시키기 위한 연결바(21) 및 연결바 고정수단(22)을 설치한다. 도 3을 참조하면, 각 PHC파일(11)의 두부를 정리한 다음 연결바(21)를 PHC파일(11)의 중공에 노출되도록 삽입한 후 연결바 고정수단(22)을 연결바(21)에 접합시켜 연결바(21)의 설치 위치를 고정한다. 연결바(21)는 PHC파일(11)과 캡 빔(20) 그리고 캡 빔(20) 위에 설치되는 지상층 벽체 또는 기둥(30)이 서로 일체가 되도록 하기 위한 것으로 그 일단부는 PHC파일(11)의 중공에 삽입되고 타단부는 캡 빔(20)의 상부로 노출되도록 설치된다. 그리고 노출된 연결바(11)에 의해 캡 빔(20) 상부에 설치되는 지상층 벽체 또는 기둥(30)과 캡 빔(20)이 일체로 합성된다. 연결바 고정수단(22)은 연결바(21)를 임시로 고정시키기 위한 것으로 앵글이 사용될 수 있 수 있으며 PHC파일(11) 상부 의 좌판에 고정된다. After arranging the head of each PHC pile, the connecting bar 21 and the connecting bar fixing means 22 for synthesizing the head of the PHC pile and the cap beam and the ground layer wall or column to be built on the cap beam can be integrated. Install). Referring to FIG. 3, after arranging the head of each PHC pile 11, the connecting bar 21 is inserted to be exposed to the hollow of the PHC pile 11, and then the connecting bar fixing means 22 is connected to the connecting bar 21. To fix the installation position of the connecting bar (21). The connecting bar 21 is for the PHC pile 11 and the cap beam 20 and the ground layer wall or the pillar 30 installed on the cap beam 20 to be integrated with each other. Inserted into the hollow and the other end is installed to be exposed to the top of the cap beam (20). And the ground layer wall or pillar 30 and the cap beam 20 which is installed on the cap beam 20 by the exposed connecting bar 11 is synthesized integrally. The connection bar fixing means 22 is for fixing the connection bar 21 temporarily, the angle can be used and is fixed to the seat plate of the upper PHC pile (11).

(d) 캡 빔 시공단계 (d) Cap beam construction stage

일정한 심도로 굴토한 다음 각 PHC파일(11)의 두부를 연결하면서 지상층 기둥 또는 벽체(30)가 세워지는 기초가 되는 캡 빔(20) 형성을 위한 철근(23)을 배근하고 거푸집을 설치한 후 캡 빔 콘크리트와 각 PHC파일(11)의 중공을 충전하는 콘크리트를 동시에 타설한다. PHC파일(11)의 선단은 최종 경타에 의해 충분한 지지력을 발휘할 수 있는 깊이로 근입되게 되는데 PHC파일(11)의 두부를 캡 빔(20)으로 서로 연결함에 따라 토압이나 수압 등의 측압에 대해 PHC파일(11)들이 일체로 저항할 수 있도록 한다. 그리고 PHC파일(11)은 터파기시 토사의 붕괴와 이완을 방지하는 흙막이벽으로서 뿐만 아니라 본 구조물의 지하층 외벽으로도 기능하므로 내부에 콘크리트를 충전하여 강도와 강성을 증진시킨다. 한편, 캡 빔(20)의 하단은 후에 시공될 지하층 외벽(40)의 상단이 PHC파일(11)의 상단보다 더 높게 형성되도록 단차가 지도록 형성되어 있다. After digging to a certain depth and connecting the head of each PHC pile (11) after laying the reinforcing bar (23) for forming the cap beam 20, which is the foundation on which the ground floor column or wall (30) is erected and the formwork is installed The cap beam concrete and the concrete filling the hollow of each PHC pile 11 are poured at the same time. The tip of the PHC pile 11 is driven to a depth capable of exerting sufficient supporting force by the final strike. As the heads of the PHC pile 11 are connected to each other by the cap beam 20, the PHC pile is connected to the side pressure such as earth pressure or hydraulic pressure. Allow the piles 11 to resist integrally. In addition, the PHC pile 11 functions as an outer wall of the basement layer of the present structure as well as a barrier wall to prevent the collapse and relaxation of the soil during the excavation, thereby increasing the strength and rigidity by filling concrete therein. On the other hand, the lower end of the cap beam 20 is formed to have a step so that the upper end of the basement outer wall 40 to be constructed later is higher than the upper end of the PHC pile 11.

(e) 굴토단계 (e) Gulto stage

소정의 계획 심도까지 굴토한 다음 띠장을 대고 흙막이벽을 지지하도록 띠장과 내부 기둥을 연결하는 버팀보를 설치하는 공정을 반복하여 계획 굴착고에 도달할 때까지 굴토한다. 굴토시 흙막이벽을 지지하기 위한 방법으로는 이와 같이 H파일-토류판으로 구성된 흙막이벽을 지지하기 위한 버팀대(Strut) 공법이 사용할 수 있고 이 이외에 공지된 방법 중에서 임의로 선택될 수 있다. After excavating to a predetermined depth of planning, repeat the process of installing a brace that connects the girdle and the inner column to support the retaining wall and til until the planned excavation is reached. As a method for supporting the soil wall at the time of gulting, a strut method for supporting the soil wall composed of the H pile-earth plate may be used, and may be arbitrarily selected from known methods.

(f) 기초 바닥 및 최하층 합벽 시공단계(f) Foundation floor and lowest plywood construction

계획 굴착고까지 굴토가 완료된 후 최하층에 해당하는 PHC파일(11)의 외면에 다수의 전단연결재(411)를 고정하고 메탈라스(412)를 설치한다. 그 다음 기초 바닥(50) 콘크리트를 타설하고 최하층 외벽(41) 콘크리트를 타설하여 최하층 합벽을 시공한다. 전단연결재(411)는 PHC파일(11)과 지하층 외벽 콘크리트 사이의 면내 전단력에 저항하여 이들이 합성되어 일체로 거동할 수 하기 위한 것으로 공지된 스터드를 적용할 수 있으며 설치방법은 드릴을 이용해 PHC파일(11)에 구멍을 낸 후 스터드를 삽입 고정하는 방법을 적용할 수 있다. 메탈라스(412)는 지하층 외벽 콘크리트의 부착력 향상 및 내력 보강 뿐만 아니라 균열 발생을 억제할 목적으로 설치된다.After the excavation is completed until the planned excavation height, a plurality of shear connecting members 411 are fixed to the outer surface of the PHC pile 11 corresponding to the lowest layer and the metal lath 412 is installed. Then, the foundation floor 50 is poured concrete and the lowermost outer wall 41 concrete is poured to construct the lowest plywood wall. Shear connector 411 can be applied to the stud known to resist the in-plane shear force between the PHC pile (11) and the basement outer wall concrete can be synthesized and behave integrally. You can apply the method of inserting and fixing the stud after making a hole in 11). The metal lath 412 is installed for the purpose of suppressing cracking as well as improving adhesion and strength of the basement outer wall concrete.

(g) 합벽 시공 반복 (g) plywood construction repetition

최하층 합벽이 시공된 후 그 윗층 즉, 최하층+1층에 해당하는 층의 띠장과 버팀보를 제거한 후 위 (f)단계에서와 동일하게 PHC파일(11)의 외면에 다수의 전단연결재(411)를 설치하고 메탈라스(412)를 고정한 다음 당해 층 바닥 콘크리트(60)를 타설하고 당해 층 외벽(40+n) 콘크리트를 타설하여 당해 층 합벽을 시공하는 공정을 지상층-1층까지 반복한다.After the lowermost plywood is constructed, the strips and braces of the upper layer, that is, the lowermost layer + the first layer, are removed, and a plurality of shear connectors 411 are formed on the outer surface of the PHC pile 11 as in the above step (f). After installing and fixing the metal las 412, the layer floor concrete 60 is poured, and the layer outer wall 40 + n concrete is poured to construct the layered wall to the ground layer-1 layer.

(h) 지상층 바닥 시공단계(h) Ground floor floor construction stage

마지막으로 지상층 바닥(70)을 시공하는데 이때 지상층의 바닥(70) 단부는 미리 시공된 캡 빔(20)에 일체로 연결되도록 한다. 이를 위해 캡 빔(20)의 시공시 미리 지상층 바닥 철근(71)과 연결될 수 있도록 캡 빔(20)의 철근을 노출시켜 둔다. 또는 지상층 바닥(70)의 시공을 캡 빔(20)의 시공에 동시에 할 수 있으며 이 경우에는 지상층 바닥 철근(71)을 캡 빔(20) 속으로 매입하고 그 단부를 구부려 정착시킨다.Finally, the ground layer bottom 70 is constructed, and the bottom layer 70 end of the ground layer is integrally connected to the pre-constructed cap beam 20. To this end, when the cap beam 20 is constructed, the rebar of the cap beam 20 is exposed to be connected to the ground floor bottom reinforcement 71 in advance. Alternatively, the construction of the ground floor bottom 70 may be simultaneously performed for the construction of the cap beam 20. In this case, the ground floor bottom reinforcing bar 71 is embedded into the cap beam 20 and the end is bent and fixed.

이상에서 살펴본 바와 같이 본 발명에서는 캡 빔의 상부에 지상층의 벽체 또는 기둥을 설치할 수 있으므로 종래와 달리 지하층 외벽 및 지상층의 기둥 또는 벽체를 최대한 대지경계선에 근접하여 시공할 수 있어 대지의 이용도가 높고 합벽 시공시 벽체의 두께를 줄일 수 있어 경제적이며 또한 시공이 단순하여 공기단축 및 정밀도 높은 시공이 가능하다.As described above, in the present invention, since the ground wall or the pillar of the ground layer may be installed on the upper part of the cap beam, the basement outer wall and the ground or the pillar of the ground layer may be constructed as close as possible to the boundary of the ground, so that the use of the earth is high. When the plywood is constructed, the thickness of the wall can be reduced, so it is economical and the construction is simple. Therefore, the air shortening and high precision construction are possible.

도 4는 기초(최하층) 바닥 콘크리트와 합벽의 접합부 구조를 보여주는 단면도이고, 도 5는 중간층(최하층+n층) 바닥과 합벽의 접합부 구조를 보여주는 단면도이다.4 is a cross-sectional view showing the junction structure of the base (lowest floor) floor concrete and the plywood wall, Figure 5 is a cross-sectional view showing the junction structure of the middle layer (lowest layer + n layer) floor and the plywood wall.

도 4를 참조하면, 기초 바닥(50)과 최하층 외벽(41)이 접하는 부분의 기초 바닥(50) 하면에는 합벽을 통해 전달되는 하중이 지반에 균등하게 전달되도록 위해 기초 바닥의 다른 부분에 비해 춤이 큰 브라켓부(51)가 형성되도록 한다. 즉, 지상층 구조물로부터 전달되는 하중은 PHC파일(11) 및 PHC파일(11)과 일체로 시공된 지하층 외벽(40)을 통해 지반에 전달되는데 PHC파일(11)은 단단한 지반에 의해 지지되어 충분한 지지력을 확보하는 반면에 지하층 외벽(40)의 경우에는 지지력이 PHC파일(11)에 비해 부족하여 비록 전단연결재(411)에 의해 합성되어 있으나 PHC파일(11)과 변위가 서로 다를 수 있다. 이에 본 발명에서는 기초 바닥(50)과 최하층 외벽(41)이 접하는 부분의 기초 바닥 하면을 다른 부분에 비해 춤이 큰 브라켓부(51)를 형성함으로써 강성을 증대시키고 아울러 PHC파일(11)의 외주면에 접합된 다수개의 전단연결재(411)와 연결 루프 철근(511)을 통해 지하층 외벽(40)과 기초 바닥(50) 사이의 계면에서 슬립이 발생되지 않고 일체로 합성되도록 하였다. Referring to FIG. 4, the lower surface of the base bottom 50 of the portion where the base bottom 50 and the lowermost outer wall 41 are in contact with each other is compared with other parts of the base bottom so that the load transmitted through the plywood is evenly transmitted to the ground. This large bracket portion 51 is formed. That is, the load transmitted from the ground layer structure is transferred to the ground through the PHC pile 11 and the basement outer wall 40 which is constructed integrally with the PHC pile 11, and the PHC pile 11 is supported by the solid ground to have sufficient bearing capacity. On the other hand, in the case of the basement outer wall 40, the bearing capacity is insufficient compared to the PHC pile 11, although it is synthesized by the shear connector 411, PHC pile 11 and the displacement may be different. Therefore, in the present invention, by forming a bracket portion 51 having a larger dance than the other portion of the bottom of the foundation bottom of the portion where the foundation bottom 50 and the lowermost outer wall 41 contact each other, the rigidity is increased and the outer circumferential surface of the PHC pile 11 is provided. A plurality of shear connectors 411 and connecting loop reinforcing bars 511 bonded to the upper surface of the basement layer 40 and the base floor 50, the slip is not generated at the interface is synthesized integrally.

그리고 도 5에 도시한 바와 같이, 해당 층 바닥(60)과 외벽(40+n) 사이에는 중간층 테두리보(61)가 형성되도록 한다. 중간층 테두리보(61)는 PHC파일(11)의 외주면에 접합된 다수개의 전단연결재(411)와 연결 루프 철근(511)을 통해 PHC파일(11) 및 해당 층 바닥(60)을 일체로 합성시킨다.As shown in FIG. 5, an intermediate layer border beam 61 is formed between the floor bottom 60 and the outer wall 40 + n. The middle layer rim beam 61 synthesizes the PHC pile 11 and the layer bottom 60 integrally through a plurality of shear connecting members 411 and connecting loop reinforcing bars 511 bonded to the outer circumferential surface of the PHC pile 11. .

이상에서 본 발명을 예시한 도면을 참조로 하여 설명하였으나, 본 명세서에 개시된 실시 예와 도면에 의해 본 발명이 한정되는 것은 아니며, 본 발명의 기술사상의 범위 내에서 통상의 기술자에 의해 다양한 변형이 이루어질 수 있다.Although the present invention has been described above with reference to the drawings, the present invention is not limited to the embodiments and drawings disclosed herein, and various modifications may be made by those skilled in the art within the scope of the technical idea of the present invention. Can be done.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니된다.The following drawings, which are attached in this specification, illustrate the preferred embodiments of the present invention, and together with the detailed description thereof, serve to further understand the technical spirit of the present invention. It should not be construed as limited.

도 1은 본 발명에 따른 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법의 흙막이벽 구축단계를 설명하기 위한 도면이다. 1 is a view for explaining the step of constructing the retaining wall of the underground plywood construction method using the retaining wall consisting of PHC pile according to the present invention.

도 2는 본 발명에 따라 시공된 지하합벽의 구성을 보여주는 단면도이다.Figure 2 is a cross-sectional view showing the configuration of the underground plywood constructed in accordance with the present invention.

도 3은 PHC파일의 두부와 캡 빔 및 기상층 바닥의 접합부 구조를 보여주는 단면도이다. 3 is a cross-sectional view showing the joint structure of the head of the PHC pile, the cap beam and the bottom of the vapor phase layer.

도 4는 기초(최하층) 바닥 콘크리트와 합벽의 접합부 구조를 보여주는 단면도이다. Figure 4 is a cross-sectional view showing the junction structure of the base (lowest layer) floor concrete and the plywood.

도 5는 중간층(최하층+n층) 바닥과 합벽의 접합부 구조를 보여주는 단면도이다.5 is a cross-sectional view showing the junction structure between the bottom of the intermediate layer (lower layer + n layer) and the plywood wall.

도 6은 흙막이벽을 CIP공법으로 구축하고 지하층 외벽을 합벽으로 시공한 모습을 나타낸 단면도이다.Figure 6 is a cross-sectional view showing the construction of the retaining wall by the CIP method and the construction of the outer wall of the basement floor as a combined wall.

Claims (4)

(a) 대지경계선을 따라 지반을 천공하고 PHC파일을 삽입 및 최종 경타하는 단계를 반복하여 지중에 PHC파일로 구성되는 흙막이벽을 형성하는 단계;(a) repeating the steps of perforating the ground along the land boundary, inserting and finally struck the PHC file to form a retaining wall composed of PHC piles in the ground; (b) 버팀보를 지지하면서 동시에 본 구조물의 기둥이 되는 내부 기둥을 평면계획에 따라 시공하는 단계;(b) constructing an internal column that is a pillar of the structure while supporting the brace and according to the plan; (c) 각 PHC파일의 두부를 정리한 다음 연결바를 PHC파일의 중공에 노출되도록 삽입한 후 연결바 고정수단을 연결바에 접합시켜 연결바의 설치 위치를 고정하는 단계;(c) arranging the head of each PHC pile and inserting the connecting bar to be exposed to the hollow of the PHC pile and then joining the connecting bar fixing means to the connecting bar to fix the installation position of the connecting bar; (d) 일정한 심도로 굴토한 다음 각 PHC파일의 두부를 연결하면서 지상층 기둥 또는 벽체가 세워지는 기초가 되는 캡 빔 형성을 위한 철근을 배근하고 거푸집을 설치한 후 캡 빔 콘크리트와 각 PHC파일의 중공을 충전하는 콘크리트를 동시에 타설하는 단계;(d) After being dug to a certain depth, connecting the heads of each PHC pile, reinforcing the reinforcing bars for the formation of the cap beams on which the ground column pillars or walls are erected, and installing the formwork, and then hollowing the cap beam concrete and each PHC pile Pouring concrete at the same time filling the; (e) 소정의 계획 심도까지 굴토한 다음 띠장을 대고 흙막이벽을 지지하도록 띠장과 내부 기둥을 연결하는 버팀보를 설치하는 공정을 반복하여 계획 굴착고에 도달할 때까지 굴토하는 단계;(e) jutting to a predetermined depth of depth, then repeating the process of installing a brace to connect the girdle and the inner pillar to support the retaining wall, and gulting until the planned dig is reached; (f) 최하층에 해당하는 PHC파일의 외면에 다수의 전단연결재를 설치하고 메탈라스를 고정한 다음 기초 바닥 콘크리트를 타설하고 최하층 외벽 콘크리트를 타설하여 최하층 합벽을 시공하는 단계; (f) installing a plurality of shear connectors on the outer surface of the PHC pile corresponding to the lowermost floor, fixing the metal lath, and then laying the foundation floor concrete and laying the lowermost outer wall concrete to construct the lowermost plywood; (g) 최하층+1층에 해당하는 층의 띠장과 버팀보를 제거한 후 PHC파일의 외면에 다수의 전단연결재를 설치하고 메탈라스를 고정한 다음 당해 층 바닥 콘크리트를 타설하고 당해 층 외벽 콘크리트를 타설하여 당해 층 합벽을 시공하는 공정을 지상층-1층까지 반복하는 단계; 및(g) After removing the strips and braces of the layer corresponding to the bottom layer +1, install a plurality of shear connectors on the outer surface of the PHC pile, fix the metal lath, cast the floor concrete of the floor, and cast the outer wall concrete of the floor. Repeating the process of constructing the laminated wall to the ground layer-1 layer; And (h) 지상층 바닥 콘크리트를 타설하는 단계;를 포함하며,(h) pouring ground floor concrete; 상기 (f)단계에서 기초 바닥과 합벽이 접하는 부분의 기초 바닥 하면에는 합벽을 통해 전달되는 하중이 지반에 균등하게 전달하기 위해 기초 바닥의 다른 부분에 비해 춤이 큰 브라켓부가 형성되도록 하는 것을 특징으로 하는 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법.In the step (f), the base bottom and the bottom wall of the portion where the wall is in contact, characterized in that the bracket portion is danced larger than the other parts of the foundation floor so that the load transmitted through the wall is evenly transmitted to the ground Underground pavement construction method using soil wall consisting of PHC pile. 제1 항에 있어서,According to claim 1, PHC파일은 서로 이웃하는 PHC파일에 의해 주입구멍이 형성될 수 있도록 대향하는 한 쌍의 차수그라우팅홈이 형성되어 있으며, 이 차수그라우팅홈은 외주면에 단면의 도심을 지나는 중심선에 대해 후방으로 소정의 편심거리를 가지며,The PHC pile has a pair of order grouting grooves facing each other so that injection holes can be formed by neighboring PHC piles, and the order grouting grooves have a predetermined eccentricity toward the centerline passing through the center of the cross section on the outer peripheral surface. Has a distance, (a)단계 이후에 차수그라우팅홈에 차수를 위한 그라우팅을 실시하는 단계를 더 포함하는 것을 특징으로 하는 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법.After the step (a), the underground grout construction method using the earth retaining wall consisting of PHC pile, characterized in that further comprising the step of grouting for the order in the order grouting groove. 삭제delete 제1 항에 있어서,According to claim 1, (g)단계에서 해당 층 바닥과 합벽 사이에는 중간층 테두리보가 형성되도록 하는 것을 특징으로 하는 PHC파일로 구성된 흙막이벽을 이용한 지하합벽 시공방법.In step (g), the basement plywood construction method using the earth barrier wall consisting of PHC pile, characterized in that the intermediate layer rim beam is formed between the floor and the plywood wall.
KR1020090068125A 2009-07-24 2009-07-24 Construction method of retaining wall using phc pile KR100960603B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090068125A KR100960603B1 (en) 2009-07-24 2009-07-24 Construction method of retaining wall using phc pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090068125A KR100960603B1 (en) 2009-07-24 2009-07-24 Construction method of retaining wall using phc pile

Publications (1)

Publication Number Publication Date
KR100960603B1 true KR100960603B1 (en) 2010-06-07

Family

ID=42369446

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090068125A KR100960603B1 (en) 2009-07-24 2009-07-24 Construction method of retaining wall using phc pile

Country Status (1)

Country Link
KR (1) KR100960603B1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101288601B1 (en) * 2010-06-03 2013-07-22 김영호 Underpass using precast concrete pile and bottom slab and method for constructing the same
KR101288602B1 (en) * 2010-06-04 2013-07-22 김영호 Underpass using precast concrete pile and method for constructing the same
KR101302743B1 (en) * 2012-12-06 2013-08-30 김인종 Phc pile and its using the same soil cement wall construction methode
CN105089062A (en) * 2015-08-17 2015-11-25 陕西桩鑫建设工程有限公司 Engaged retaining pile and construction method and application thereof
KR102291349B1 (en) 2020-10-21 2021-08-23 주식회사 이지원건설 High Strength Concrete PreStressed Pile for Construction of Composite and Earth Retaining Wall
KR102357963B1 (en) * 2021-02-08 2022-02-08 주식회사 한화건설 Earthquake resistant slurry wall structure
KR20230052753A (en) * 2021-10-13 2023-04-20 미래이엔씨 주식회사 Construction method of foundation on the building structure using CIP wall
KR20230144862A (en) 2022-04-08 2023-10-17 주식회사 덕암테크 Pile wall for both retaining and permanent walls And Construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100615149B1 (en) 2005-12-02 2006-08-22 주식회사 행림종합 건축사사무소 A method of construction top-down for the ground fabric construction

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100615149B1 (en) 2005-12-02 2006-08-22 주식회사 행림종합 건축사사무소 A method of construction top-down for the ground fabric construction

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101288601B1 (en) * 2010-06-03 2013-07-22 김영호 Underpass using precast concrete pile and bottom slab and method for constructing the same
KR101288602B1 (en) * 2010-06-04 2013-07-22 김영호 Underpass using precast concrete pile and method for constructing the same
KR101302743B1 (en) * 2012-12-06 2013-08-30 김인종 Phc pile and its using the same soil cement wall construction methode
CN105089062A (en) * 2015-08-17 2015-11-25 陕西桩鑫建设工程有限公司 Engaged retaining pile and construction method and application thereof
CN105089062B (en) * 2015-08-17 2016-08-17 陕西桩鑫建设工程有限公司 It is engaged lagging pile and construction method thereof and application
KR102291349B1 (en) 2020-10-21 2021-08-23 주식회사 이지원건설 High Strength Concrete PreStressed Pile for Construction of Composite and Earth Retaining Wall
KR102357963B1 (en) * 2021-02-08 2022-02-08 주식회사 한화건설 Earthquake resistant slurry wall structure
KR20230052753A (en) * 2021-10-13 2023-04-20 미래이엔씨 주식회사 Construction method of foundation on the building structure using CIP wall
KR102700900B1 (en) * 2021-10-13 2024-09-02 미래이엔씨 주식회사 Construction method of foundation on the building structure using CIP wall
KR20230144862A (en) 2022-04-08 2023-10-17 주식회사 덕암테크 Pile wall for both retaining and permanent walls And Construction method

Similar Documents

Publication Publication Date Title
KR100960603B1 (en) Construction method of retaining wall using phc pile
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR100866162B1 (en) Chair-type self-supported earth retaining wall constructing method
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
KR20110043017A (en) The earth retaining wall and waterproof construction technique for which cast in place concrete pile and grouting column was used
KR101121538B1 (en) Diaphragm wall tunnel method - dtm, and tunnel structure using diaphragm wall
KR20100068597A (en) A shoring method using arch plate pile and h-pile
JP6543176B2 (en) Building method
KR101182704B1 (en) Construction method of undergroud structure using PHC pile
JP4881555B2 (en) Construction method of underground structure
KR20080007483A (en) Underground retaining wall for public works and method for constructing the same
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR20100094140A (en) Wall structure capable of earth retaining and the building method of the same
KR20190012368A (en) Smallcaliber composite pile wall using small drilling rig at adjacent building proximity section and construction method of the same
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
CN210087321U (en) Pile foundation pre-reinforcing and supporting structure for controlling tunnel settlement
KR20030065963A (en) A method of constrution method for tunnel of structure pipe
JP4407716B2 (en) Construction method of earth retaining wall
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
JP4243069B2 (en) Construction method of earth retaining wall
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
JP5140515B2 (en) Installation method of underground floor pillar and construction method of underground structure

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130429

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20140404

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160201

Year of fee payment: 6

R401 Registration of restoration
FPAY Annual fee payment

Payment date: 20170405

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20180319

Year of fee payment: 9