JP2007277825A - Construction method of buried pipe under road - Google Patents

Construction method of buried pipe under road Download PDF

Info

Publication number
JP2007277825A
JP2007277825A JP2006101981A JP2006101981A JP2007277825A JP 2007277825 A JP2007277825 A JP 2007277825A JP 2006101981 A JP2006101981 A JP 2006101981A JP 2006101981 A JP2006101981 A JP 2006101981A JP 2007277825 A JP2007277825 A JP 2007277825A
Authority
JP
Japan
Prior art keywords
buried pipe
crushing
excavation hole
paving
road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2006101981A
Other languages
Japanese (ja)
Other versions
JP4822426B2 (en
Inventor
Hiromi Yamamoto
裕実 山本
Hiroshi Onuki
博司 大貫
Osamu Yokoyama
修 横山
Kazuhisa Tamura
和久 田村
Kokan Kudo
匡貫 工藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2006101981A priority Critical patent/JP4822426B2/en
Publication of JP2007277825A publication Critical patent/JP2007277825A/en
Application granted granted Critical
Publication of JP4822426B2 publication Critical patent/JP4822426B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method of a buried pipe capable of laying regardless of the length of the buried pipe, when installing the buried pipe of a road including the hard ground such as base rock. <P>SOLUTION: This invention relates to the construction method of the buried pipe by the following processes: (1) the process of crushing the hard ground above an installation position of the buried pipe in a shape without hindering installation, (2) the process of performing up to temporary restoration on the same day, by easily paving, by temporarily filling up an excavation hole finished with crushing by a backfilling material such as a crushed stone, (3) the process of performing up to temporary restoration similar to the above process on the same day to the excavation hole finished with its crushing, by crushing the hard ground of a position continuing with the excavation hole of the process of (2) in a predetermined shape, and (4) the process of performing up to restoration on the same day, by paving with a paving material, by backfilling the periphery and an upper part of the buried pipe by protective sand and the backfilling material, by integrally connecting with a previously laid buried pipe, by laying the buried pipe in a predetermined position, by digging up a part temporarily restored in the above process, when the total extension of a crushed part reaches the expected buried pipe length, by repeating the processes of (1) to (3). <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は、道路下の岩盤等の硬い地盤の下方位置に埋設管を設置する場合の埋設管の施工方法に関する。   The present invention relates to a method for constructing a buried pipe when the buried pipe is installed at a position below a hard ground such as a rock under a road.

ガス管や水道管或いは下水管等の管を道路下に埋設する際、道路の掘削孔工事をすることになるが、交通量の多い主要幹線道路においては、工事に伴う道路通行規制による交通渋滞緩和対策として、通勤時間帯など交通量が多い時間帯は路面を開放するなどの条件で、道路使用許可が得られる場合が多い。このような道路使用許可条件下では、これまで下記の2通りの施工方法が採用されてきた。
(1)作業可能時間帯の中で掘削、埋設管の敷設、埋戻、仮復旧までを即日で行なう施工方法、
(2)道路開放時間帯及び休日は覆工板により掘削孔を覆い、道路面を仮完成して路面開放を行ない、後日、該覆工板を取り除いて工事を続行する方法。
When pipes such as gas pipes, water pipes or sewage pipes are buried under the roads, road excavation work will be carried out. On main trunk roads with heavy traffic, traffic congestion due to road traffic regulations accompanying construction As a mitigation measure, road use permission is often obtained under conditions such as opening the road surface during heavy traffic hours such as commuting hours. Under such road use permission conditions, the following two construction methods have been adopted so far.
(1) Construction method that performs excavation, laying of buried pipes, backfilling, and temporary restoration within the workable time zone on the same day,
(2) A method of covering the excavation hole with a lining plate during road opening hours and holidays, temporarily completing the road surface to open the road surface, and removing the lining plate at a later date to continue the construction.

しかし、道路下に熔岩層などの堅硬な岩盤が存在する場所では、掘削時に岩盤を破砕するのに長時間を要するため、上記(1)の即日復旧施工は不可能なことが多かった。このような場合は、上記(2)の覆工板による方法によらなければならなかった。
但し、この場合も掘削範囲の岩盤をブレーカにより打撃破砕を行なうと、破砕時の振動により覆工板受桁の基礎部に崩壊等の悪影響が生じ、それらに対処しなければならなかった。更に、上記破砕作業は騒音を伴うため、作業時間帯は昼間に限定されることになり、路面開放時における通過車両の安全を確保しながら破砕、掘削、土留までの一連作業を1日の作業時間内で完成させることは、岩盤の量、硬さによっては1日の施工延長が実質ゼロになる場合も発生し、施工速度が著しく低下していた。
However, in places where a hard rock such as a lava layer exists under the road, it takes a long time to crush the rock during excavation, so the restoration work of (1) above was often impossible on the same day. In such a case, it was necessary to use the method (2) using the lining plate.
However, in this case as well, when the rock in the excavation area was crushed with a breaker, the foundation of the lining plate support girder had a bad influence due to vibration during crushing, and it was necessary to deal with them. Furthermore, since the above crushing work involves noise, the work hours are limited to daytime, and a series of work up to crushing, excavation, and earth retaining is performed for one day while ensuring the safety of passing vehicles when the road surface is open. Completion in time occurred depending on the amount and hardness of the rock mass, even when the construction extension for one day was substantially zero, and the construction speed was significantly reduced.

このように埋設管敷設の施工速度は、最も時間を必要とする岩盤破砕の施工速度で決まるため、硬い地盤によっては著しい工期の遅延につながり、周辺住民及び通過車両への迷惑が長期間に及ぶことが多かった。
特公平1−14365号公報 特開平8−193304号公報 特開2001−81708号公報 特開2001−311109号公報
In this way, the construction speed of buried pipe laying is determined by the speed of rock crushing, which requires the most time. Therefore, depending on the hard ground, it can lead to a significant delay in the construction period, causing inconvenience to surrounding residents and passing vehicles for a long time. There were many things.
Japanese Patent Publication No. 1-14365 JP-A-8-193304 JP 2001-81708 A Japanese Patent Laid-Open No. 2001-311109

本発明は、上記岩盤等の硬い地盤を含む道路下における埋設管の設置の困難性に鑑みて創案されたもので、昼間において硬い地盤の破砕工事とその仮埋め及び簡易舗装による仮復旧までを即日施工し、それら工事を何日かにわたって先行し、所定長区画が得られた時点で一気に上記仮復旧工事面の掘り起こしと埋設管の設置とその接続を主として昼間における作業時間内に即日で行ない、再度復旧することとした施工方法を提供するものである。   The present invention was devised in view of the difficulty of installing buried pipes under the road including hard ground such as the above-mentioned rocks, etc., until the hard ground crushing work in the daytime and temporary restoration by temporary paving. Constructed on the same day, leading the work over several days, and when the predetermined length section was obtained, excavating the temporary restoration work surface and installing and connecting the buried pipe at once, mainly during the work hours in the daytime The construction method decided to be restored again is provided.

本発明は、下記の工程よりなる道路下の埋設管の施工方法を特徴とする。
1)道路下の埋設管の設置場所となる上方側に位置する岩盤等の硬い地盤を該埋設管の設置に支障のない深さと幅をもって破砕する工程。
2)破砕が終了した掘削孔に対し砕石等の埋戻し材により仮埋めし、舗装材により簡易舗装して仮復旧するまでを即日に行なう工程。
3)上記2)の工程の掘削孔に連続する位置の岩盤等の硬い地盤を所定の深さと幅をもって破砕し、その破砕が終了した掘削孔に対し、上記工程同様、砕石等の埋戻し材により仮埋めし、舗装材により簡易舗装して仮復旧するまでを即日に行なう工程。
4)上記1)乃至3)の工程を繰り返し、破砕部分の総延長が1本或いは数本の埋設管の長さに達した時点において、上記工程で仮復旧した舗装材及び埋戻し材を掘り起こし、埋設管を所定位置に敷設し、先に敷設した埋設管と接続一体化し、該埋設管の周囲を保護砂により埋戻し、その周囲及び上方部を埋戻し材により埋戻し、舗装材により舗装して復旧するまでを即日に行なう工程。
This invention is characterized by the construction method of the underground pipe under the road which consists of the following processes.
1) A step of crushing a hard ground such as a bedrock located on the upper side, which is an installation location of a buried pipe under a road, with a depth and a width that does not hinder the installation of the buried pipe.
2) The process of temporarily filling the excavation hole after crushing with a backfill material such as crushed stone, performing simple paving with a paving material, and temporarily restoring it.
3) Crushing hard ground such as rock in a position continuous to the excavation hole in step 2) with a predetermined depth and width, and backfilling material such as crushed stone in the excavation hole after crushing, as in the above step The process of temporarily filling in and then paving with a paving material and temporarily recovering.
4) The above steps 1) to 3) are repeated, and when the total length of the crushed portion reaches the length of one or several buried pipes, the paving material and backfill material temporarily restored in the above steps are dug up. The buried pipe is laid at a predetermined position, connected and integrated with the previously buried pipe, the surrounding area of the buried pipe is backfilled with protective sand, the surrounding area and the upper part are backfilled with the backfill material, and the pavement is paved. The process of performing the same day until recovery.

上記埋戻し材は、破砕した岩盤をそのまま或いは併用して使用する道路下の埋設管の施工方法を特徴とする。   The backfilling material is characterized by a construction method for a buried pipe under a road that uses a crushed bedrock as it is or in combination.

また、上記埋戻し材は、掘削孔に発泡スチロールを配置し、その周囲を砕石等により囲繞するようにして埋戻してなる道路下の埋設管の施工方法を特徴とする。   Further, the backfill material is characterized by a construction method of a buried pipe under a road in which polystyrene foam is disposed in a drilling hole and the surrounding area is backfilled by crushed stone or the like.

更に、上記埋戻し材は、掘削孔の中心部に砕石等を詰め込んだ袋パックを配置し、その周囲を砕石等により囲繞するようにして埋戻してなる道路下の埋設管の施工方法を特徴とする。   Furthermore, the backfilling material is characterized by a construction method of a buried pipe under a road in which a bag pack filled with crushed stone is placed in the center of the excavation hole, and the surrounding area is backfilled by crushed stone or the like. And

また、上記舗装材を、アスファルトとした埋設管の施工方法を特徴とする。   Moreover, the construction method of the buried pipe which used the said pavement material as the asphalt is characterized.

更に、上記舗装材を、鉄板とした道路下の埋設管の施工方法を特徴とする。   Furthermore, the construction method of the underground pipe under the road which used the said pavement material as the iron plate is characterized.

本発明は、埋設管の設置工事である掘削、埋設管の敷設、埋戻し及び舗装という即日の作業の内、埋設管の敷設を割愛して掘削と仮埋め及び簡易舗装の工事を先行させ、所定長の掘削孔が完了した時点でそれら掘削孔内の復旧手段を除去して一気に埋設管の設置作業を行なう施工方法で、多くの施工時間を必要とする岩盤等の掘削工事と埋設管敷設工事とを分離することにより、埋設管の敷設を最も速い施工速度で施工することが可能となった。   In the present invention, among the same day work of excavation, laying of buried pipe, backfilling and pavement, which is the construction work of buried pipe, omitting the laying of buried pipe, leading the construction of excavation and temporary filling and simple pavement, When a predetermined length of excavation hole is completed, the recovery method in the excavation hole is removed and the buried pipe is installed at once. By separating the construction, it was possible to construct the buried pipe at the fastest construction speed.

また、本発明の施工方法を採用することにより、周辺住民及び通行車両への影響を最小限に留めることができ、且つ長い埋設管を一気に敷設することが可能となり、従来、岩盤の破砕工程以外で5〜6日を要していた覆工板設置、撤去、掘削・土留、管の敷設、埋戻、仮復旧の作業工程を1日で可能とした。
更に、長い埋設管の敷設を可能としたことにより管の接続箇所を少なくすることが出来るので、接続作業に必要な掘削溝の拡幅と設備の設置作業が少なくなり、作業効率が極めて向上し、環境面及び経済面で優位な施工方法を提供することが可能となった。
In addition, by adopting the construction method of the present invention, it is possible to minimize the influence on the inhabitants and passing vehicles, and it is possible to lay long buried pipes at a stretch. The lining plate installation, removal, excavation and earth retaining, pipe laying, backfilling, and temporary restoration, which required 5-6 days, were made possible in one day.
Furthermore, since it is possible to lay long buried pipes, it is possible to reduce the number of pipe connections, so that the width of excavation grooves and installation work required for connection work are reduced, and work efficiency is greatly improved. It has become possible to provide construction methods that are superior in terms of environment and economy.

更に、埋設管の接続箇所を少なくすることが可能となったことにより、当該箇所の接続部品を省くことができ、且つ当該箇所からのガスや水等の漏れの発生率を少なくすることが可能となった。   Furthermore, since it is possible to reduce the number of connection points of the buried pipe, it is possible to omit the connection parts at that point, and to reduce the rate of occurrence of leakage of gas, water, etc. from that point. It became.

また、掘削孔への仮埋め手段としてその中心部に発泡スチロールや砕石等を詰め込んだ袋パックを使用することにより、仮埋め作業の短縮化ができ、同時に、埋設管の敷設時における掘り起こし作業の効率化を図ることが可能となった。   In addition, by using a bag pack filled with foamed polystyrene or crushed stone at the center as a means for temporarily filling the borehole, the temporary filling work can be shortened, and at the same time, the efficiency of the excavation work when laying the buried pipe It became possible to plan.

更に、舗装材を鉄板としたことにより、掘削孔の道路面側に据え置くだけの工事で済み、仮復旧作業及び掘り起こし作業の時間短縮を図ることが可能となった。   Furthermore, since the pavement material is an iron plate, it is only necessary to install it on the road surface side of the excavation hole, and it is possible to shorten the time for temporary restoration work and excavation work.

以下、本発明の実施例の形態を図面に基づいて説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

図1は道路下にガス管や水道管或いは下水管等の埋設管2を敷設する位置を示した道路1の断面図で、該道路1の該埋設管2を敷設する位置となる上方部に岩盤等の硬い地盤3が存在している。該埋設管2を敷設するには上記硬い地盤3を破砕する必要がある。例えば、岩盤の場合、図2に示すようにブレーカ4により該岩盤を破砕することになるが、深さ約2m、幅約1mの掘削孔に厚さ30〜40cm程度の岩盤が存在する場合、作業範囲の関係で、効率良く作業しても1日における破砕の延長はせいぜい約3m前後にしかすぎなかった。   FIG. 1 is a cross-sectional view of a road 1 showing a position where a buried pipe 2 such as a gas pipe, a water pipe or a sewage pipe is laid under the road. In the upper portion of the road 1 where the buried pipe 2 is laid. Hard ground 3 such as bedrock exists. In order to lay the buried pipe 2, the hard ground 3 needs to be crushed. For example, in the case of a rock mass, the rock mass will be crushed by the breaker 4 as shown in FIG. 2, but when a rock mass of about 30 to 40 cm in thickness exists in a drilling hole having a depth of about 2 m and a width of about 1 m, Due to the work range, even if the work was carried out efficiently, the crushing extension in one day was only about 3 m at most.

従って、岩盤を破砕し、掘削孔を形成し、その掘削孔内に埋設管を埋設して埋戻しを行ない、簡易舗装までを行なう施工は掘削における岩盤破砕に要する時間が長時間となり、即日に上記工程を完了させることは極めて困難であり、且つ埋設管の長さも短く限定されたものとなり、実質的には不可能な施工方法となっていた。   Therefore, crushing the rock mass, forming an excavation hole, burying a buried pipe in the excavation hole, performing backfilling and performing simple pavement requires a long time for excavation of the rock mass, It is extremely difficult to complete the above steps, and the length of the buried pipe is limited to a short length, which is a practically impossible construction method.

そこで本発明における実施例では、図2に示すように、岩盤等の硬い地盤3の破砕の工程を主として行なうこととし、破砕が終了した掘削孔は、図3に示すように、破砕した岩盤或いは他の砕石等の埋戻し材5により仮埋めし、その表面側となる道路1面側の舗装材6はアスファルトや鉄板等の簡易舗装手段により仮復旧する。   Therefore, in the embodiment of the present invention, as shown in FIG. 2, the crushing process of the hard ground 3 such as a rock is mainly performed, and the excavation hole after the crushing is performed as shown in FIG. The material is temporarily buried with another backfill material 5 such as crushed stone, and the pavement material 6 on the road 1 side which is the surface side is temporarily restored by simple pavement means such as asphalt or iron plate.

上記工程によって形成された掘削孔に連続する位置には、後日、上記同様の施工方法である岩盤等の硬い地盤3の破砕、埋戻し材5による仮埋め及び舗装材6により仮復旧を即日で行なうことになる。   At a position continuing to the excavation hole formed by the above process, the hard ground 3 such as the bedrock, which is the same construction method as described above, will be crushed by the backfill material 5 and temporarily restored by the pavement material 6 at a later date. Will do.

上記施工を何日か繰り返すことにより、所定長の仮復旧された状態の硬い地盤3の存在しない掘削孔を構築することができるが、その破砕済によって完成された掘削孔長が埋設する管長に達したとき、図4に示すように、上記先行工程により仮復旧された舗装材6及び仮埋めされた埋戻し材5を該掘削孔7より除去し、該掘削孔7内の所定位置に埋設管2を敷設する。   By repeating the above construction for several days, it is possible to construct a drilling hole in which the hard ground 3 in a temporarily restored state having a predetermined length does not exist. 4, as shown in FIG. 4, the pavement material 6 and the temporarily backfill material 5 temporarily restored by the preceding process are removed from the excavation hole 7 and buried in a predetermined position in the excavation hole 7. Pipe 2 is laid.

敷設された埋設管2は、図7に示すように、先に敷設されている埋設管の端部において端部相互を溶接や他の接続手段8により連結する。   As shown in FIG. 7, the laid pipe 2 is connected to each other by welding or other connecting means 8 at the end of the previously laid pipe.

埋設管2の敷設及び連結が終了した後、図5の断面図に示すように、該埋設管2の周囲に保護砂9による埋戻しを行ない、その上方部には砕石等の埋戻し材5を埋戻し、道路面側は舗装材6により復旧する。   After the laying and connection of the buried pipe 2 are completed, as shown in the cross-sectional view of FIG. 5, the buried pipe 2 is backfilled with protective sand 9, and the backfill material 5 such as crushed stone is provided above the buried pipe 2. The road surface side is restored by the pavement 6.

上記埋設管2の設置は、即日において硬い地盤を破砕する工程が必要なく施工されるため、効率良く行なうことができ、その後の復旧も時間的に余裕をもって即日施工することが可能となる。   Since the installation of the buried pipe 2 is performed without the need to crush the hard ground on the same day, it can be performed efficiently, and the subsequent recovery can be performed on the same day with sufficient time.

図6は、岩盤等の硬い地盤3を破砕して該硬い地盤3を除去した掘削孔の位置を示した道路の長手方向の断面図で、4日間にわたり硬い地盤の破砕及びそれにより形成された掘削孔の仮埋め及び簡易舗装を連続して行ない、5日目に上記4日間にわたって破砕済となっている仮復旧区間の再度の掘り起こしを行ない、図7に示すように、該破砕済区間となる掘削孔7の所定位置に埋設管2を1本或いは適数本敷設し、先に埋設した埋設管の端部と適宜な接続手段8により相互に連結し、その後、埋設管2の周囲を保護砂9により保護しながら固定し、その上方に砕石等の埋戻し材5を埋戻し、舗装材6により舗装して復旧する。   FIG. 6 is a cross-sectional view in the longitudinal direction of the road showing the position of the excavation hole from which the hard ground 3 such as a rock was crushed and the hard ground 3 was removed, and was formed by crushing the hard ground over 4 days and The temporary filling of the excavation hole and the simple pavement are continuously performed, and the temporary restoration section that has been crushed for the above four days is digged up again on the fifth day, and as shown in FIG. One or a suitable number of buried pipes 2 are laid in a predetermined position of the excavation hole 7 to be connected to each other by an appropriate connecting means 8 and the end of the buried pipe, and then the surroundings of the buried pipe 2 are It is fixed while being protected by the protective sand 9, and the backfill material 5 such as crushed stone is backfilled above it, and the pavement material 6 is paved and restored.

図8は、掘削孔に仮埋めする埋戻し材10の他の実施例を示したもので、該掘削孔の中心部に発泡スチロールを適数個配置し、その周囲に砕石等の他の粒状の埋戻し材11を充填した状態を示す断面図である。発泡スチロールは圧縮力には強いので掘削孔の中心部は主として上方からの車両等の荷重により圧縮力がかかる場所となるのでその位置に配置することになる。また、発泡スチロールの周囲と掘削孔の壁との間の隙間には砕石等の隅々まで行き渡る粒状の埋戻し材11を詰め込み充填することにより、該発泡スチロールの破断や掘削孔壁の崩落等を防止することができる。該発泡スチロールの形状は周囲に隙間が生じない形状のものであれば適宜な形状のものが採用できる。   FIG. 8 shows another embodiment of the backfilling material 10 temporarily buried in the excavation hole, in which an appropriate number of polystyrene foams are arranged in the center of the excavation hole, and other granular materials such as crushed stones are arranged around it. It is sectional drawing which shows the state with which the backfill material 11 was filled. Since the expanded polystyrene is strong in compressive force, the central part of the excavation hole is a place where the compressive force is applied mainly by the load of the vehicle or the like from above, and therefore it is arranged at that position. In addition, the gap between the periphery of the expanded polystyrene and the wall of the drilling hole is filled with a granular backfill material 11 such as crushed stones to prevent breakage of the expanded polystyrene and the collapse of the drilled hole wall. can do. As the shape of the polystyrene foam, a shape having an appropriate shape can be adopted as long as it has a shape in which a gap does not occur in the periphery.

上記掘削孔内への発泡スチロールの配設により、仮埋め及び掘り起こし作業が極めて簡便となり、効率良く行なうことが可能である。   By disposing the expanded polystyrene in the excavation hole, the temporary filling and excavation work becomes extremely simple and can be performed efficiently.

図9は、上記実施例2同様、掘削孔に仮埋めする埋戻し材12の他の実施例を示したもので、該掘削孔の中心部に砕石を詰め込んだ袋パックを適数個配置し、その周囲に砕石等の他の粒状の埋戻し材13を充填した状態を示す断面図である。上記の通り、砕石が袋詰状態となっているので掘削孔内への仮埋め及びそこからの掘り起こし作業が容易であると同時に、袋詰状態となっている砕石のため不定形を保持して周囲の形状になじむことができ、該袋パックの埋戻し材12の周囲と掘削孔の壁との間の隙間に他の粒状の埋戻し材13を詰め込み充填することにより、隙間のない緻密な埋戻しを行なうことが可能となる。   FIG. 9 shows another embodiment of the backfilling material 12 temporarily buried in the excavation hole as in the second embodiment, and an appropriate number of bag packs filled with crushed stones are arranged in the center of the excavation hole. FIG. 3 is a cross-sectional view showing a state in which other granular backfill material 13 such as crushed stone is filled in the periphery thereof. As mentioned above, since the crushed stone is packed, it is easy to temporarily bury it in the drilling hole and dig up from it, and at the same time hold the irregular shape because the crushed stone is packed. By filling and filling other granular backfilling material 13 into the gap between the backfilling material 12 of the bag pack and the wall of the excavation hole, it is possible to adapt to the surrounding shape. Backfilling can be performed.

本発明の埋設管敷設の実施例を示す道路の断面図Cross-sectional view of a road showing an embodiment of the buried pipe laying of the present invention 本発明の実施例の岩盤を破砕している状態を示す道路の断面図Sectional drawing of the road which shows the state which is crushing the bedrock of the Example of this invention 本発明の実施例の掘削孔に埋戻し材及び舗装材を施工して仮復旧した状態の道路の断面図Sectional drawing of the road of the state which carried out the temporary restoration | restoration by constructing a backfill material and a pavement material in the excavation hole of the Example of this invention 本発明の実施例の破砕済区間における掘削孔内の舗装材及び埋戻し材を掘り起こして埋設管を敷設した状態の道路の断面図Sectional drawing of the road of the state which dug up the pavement material and backfilling material in the excavation hole in the crushed section of the Example of this invention, and laid the buried pipe 本発明の実施例の埋設管を敷設し、埋戻し材及び舗装材を施工して仮復旧した状態の道路の断面図Sectional drawing of the road of the state which laid the underground pipe of the Example of this invention, constructed the backfill material and the pavement material, and was temporarily restored. 本発明の実施例の4日間にわたって硬い地盤を破砕する掘削孔の位置を示した道路の長手方向断面図Longitudinal sectional view of the road showing the position of the excavation hole for crushing the hard ground over the four days of the embodiment of the present invention 本発明の実施例の4日間にわたって形成した掘削孔内に埋設管を敷設した状態の道路の長手方向断面図Longitudinal sectional view of a road in a state where a buried pipe is laid in an excavation hole formed over four days according to an embodiment of the present invention 本発明の他の実施例を示す埋戻し材を埋戻した状態の道路の断面図Sectional drawing of the road of the state which backfilled the backfill material which shows the other Example of this invention 本発明の他の実施例を示す埋戻し材を埋戻した状態の道路の断面図Sectional drawing of the road of the state which backfilled the backfill material which shows the other Example of this invention

符号の説明Explanation of symbols

1 道路
2 埋設管
3 硬い地盤
4 ブレーカ
5 埋戻し材
6 舗装材
7 掘削孔
8 接続手段
9 保護砂
10、12 埋戻し材
11、13 他の粒状の埋戻し材
DESCRIPTION OF SYMBOLS 1 Road 2 Buried pipe 3 Hard ground 4 Breaker 5 Backfill material 6 Pavement material 7 Drilling hole 8 Connection means 9 Protective sand 10,12 Backfill material 11,13 Other granular backfill materials

Claims (6)

下記の工程よりなる道路下の埋設管の施工方法。
1)道路下の埋設管の設置場所となる上方側に位置する岩盤等の硬い地盤を該埋設管の設置に支障のない深さと幅をもって破砕する工程。
2)破砕が終了した掘削孔に対し砕石等の埋戻し材により仮埋めし、舗装材により簡易舗装して仮復旧するまでを即日に行なう工程。
3)上記2)の工程の掘削孔に連続する位置の岩盤等の硬い地盤を所定の深さと幅をもって破砕し、その破砕が終了した掘削孔に対し、上記工程同様、砕石等の埋戻し材により仮埋めし、舗装材により簡易舗装して仮復旧するまでを即日に行なう工程。
4)上記1)乃至3)の工程を繰り返し、破砕部分の総延長が1本或いは数本の埋設管の長さに達した時点において、上記工程で仮復旧した舗装材及び埋戻し材を掘り起こし、埋設管を所定位置に敷設し、先に敷設した埋設管と接続一体化し、該埋設管の周囲を保護砂により埋戻し、その周囲及び上方部を埋戻し材により埋戻し、舗装材により舗装して復旧するまでを即日に行なう工程。
Construction method of buried pipe under the road consisting of the following processes.
1) A step of crushing a hard ground such as a bedrock located on the upper side, which is an installation location of a buried pipe under a road, with a depth and a width that does not hinder the installation of the buried pipe.
2) The process of temporarily filling the excavation hole after crushing with a backfill material such as crushed stone, performing simple paving with a paving material, and temporarily restoring it.
3) Crushing hard ground such as rock in a position continuous to the excavation hole in step 2) with a predetermined depth and width, and backfilling material such as crushed stone in the excavation hole after crushing, as in the above step The process of temporarily filling in and then paving with a paving material and temporarily recovering.
4) The above steps 1) to 3) are repeated, and when the total length of the crushed portion reaches the length of one or several buried pipes, the paving material and backfill material temporarily restored in the above steps are dug up. The buried pipe is laid in a predetermined position, connected and integrated with the previously buried pipe, the surrounding area of the buried pipe is backfilled with protective sand, the surrounding area and the upper part are backfilled with the backfill material, and the pavement is paved. The process of performing the same day until recovery.
埋戻し材は、破砕した岩盤をそのまま或いは併用して使用することを特徴とする請求項1に記載の道路下の埋設管の施工方法。   The method for constructing a buried pipe under a road according to claim 1, wherein the backfilling material is used as it is or in combination with the crushed bedrock. 埋戻し材は、掘削孔に発泡スチロールを配置し、その周囲を砕石等により囲繞するようにして埋戻してなることを特徴とする請求項1に記載の道路下の埋設管の施工方法。   2. The method for constructing a buried pipe under a road according to claim 1, wherein the backfill material is formed by placing foamed polystyrene in the excavation hole and surrounding the surrounding area with crushed stone or the like. 埋戻し材は、掘削孔の中心部に砕石等を詰め込んだ袋パックを配置し、その周囲を砕石等により囲繞するようにして埋戻してなることを特徴とする請求項1に記載の道路下の埋設管の施工方法。   The backfilling material according to claim 1, wherein the backfilling material is formed by placing a bag pack filled with crushed stone or the like at the center of the excavation hole and surrounding the surrounding area with crushed stone or the like. Construction method for underground pipes. 舗装材を、アスファルトとしたことを特徴とする請求項1乃至4のいずれかに記載の道路下の埋設管の施工方法。   The construction method for buried pipes under a road according to any one of claims 1 to 4, wherein the paving material is asphalt. 舗装材を、鉄板としたことを特徴とする請求項1乃至4のいずれかに記載の道路下の埋設管の施工方法。   The construction method of the buried pipe under the road according to any one of claims 1 to 4, wherein the pavement material is an iron plate.
JP2006101981A 2006-04-03 2006-04-03 Construction method of buried pipe under the road Expired - Fee Related JP4822426B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006101981A JP4822426B2 (en) 2006-04-03 2006-04-03 Construction method of buried pipe under the road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006101981A JP4822426B2 (en) 2006-04-03 2006-04-03 Construction method of buried pipe under the road

Publications (2)

Publication Number Publication Date
JP2007277825A true JP2007277825A (en) 2007-10-25
JP4822426B2 JP4822426B2 (en) 2011-11-24

Family

ID=38679535

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006101981A Expired - Fee Related JP4822426B2 (en) 2006-04-03 2006-04-03 Construction method of buried pipe under the road

Country Status (1)

Country Link
JP (1) JP4822426B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010031564A (en) * 2008-07-29 2010-02-12 Taisei Corp Basement pillar installation method and construction method for underground structure
JP2012136862A (en) * 2010-12-27 2012-07-19 Meiwa Industries Ltd Installation method of temporary pipe
JP5763254B1 (en) * 2014-10-17 2015-08-12 株式会社山▲崎▼砂利商店 Cushion material for buried pipe and buried pipe refill method using the same
JP2016217099A (en) * 2015-05-26 2016-12-22 博 北川 Temporary restoration method of road surface
CN113481771A (en) * 2021-08-05 2021-10-08 常熟市第二市政路桥建设工程有限公司 Permanent-temporary combined construction structure for municipal road and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0114365B2 (en) * 1980-12-15 1989-03-10 Osaka Gas Co Ltd
JPH07293748A (en) * 1994-04-19 1995-11-10 Kansai Electric Power Co Inc:The Laying construction method for pipe body
JPH08193304A (en) * 1995-01-13 1996-07-30 Nippon Steel Corp Temporary burying method for hole excavated for laying burying pipe
JPH10168926A (en) * 1996-12-16 1998-06-23 Fumito Chiba Excavator
JP2001081708A (en) * 1999-09-13 2001-03-27 Okumura Engineering Corp Structure and method for temporarily filling excavated hole for underground pipe
JP2001311109A (en) * 2000-04-28 2001-11-09 Tokyo Gas Co Ltd Temporary back-filling method for excavated shaft

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0114365B2 (en) * 1980-12-15 1989-03-10 Osaka Gas Co Ltd
JPH07293748A (en) * 1994-04-19 1995-11-10 Kansai Electric Power Co Inc:The Laying construction method for pipe body
JPH08193304A (en) * 1995-01-13 1996-07-30 Nippon Steel Corp Temporary burying method for hole excavated for laying burying pipe
JPH10168926A (en) * 1996-12-16 1998-06-23 Fumito Chiba Excavator
JP2001081708A (en) * 1999-09-13 2001-03-27 Okumura Engineering Corp Structure and method for temporarily filling excavated hole for underground pipe
JP2001311109A (en) * 2000-04-28 2001-11-09 Tokyo Gas Co Ltd Temporary back-filling method for excavated shaft

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010031564A (en) * 2008-07-29 2010-02-12 Taisei Corp Basement pillar installation method and construction method for underground structure
JP2012136862A (en) * 2010-12-27 2012-07-19 Meiwa Industries Ltd Installation method of temporary pipe
JP5763254B1 (en) * 2014-10-17 2015-08-12 株式会社山▲崎▼砂利商店 Cushion material for buried pipe and buried pipe refill method using the same
JP2016217099A (en) * 2015-05-26 2016-12-22 博 北川 Temporary restoration method of road surface
CN113481771A (en) * 2021-08-05 2021-10-08 常熟市第二市政路桥建设工程有限公司 Permanent-temporary combined construction structure for municipal road and construction method thereof

Also Published As

Publication number Publication date
JP4822426B2 (en) 2011-11-24

Similar Documents

Publication Publication Date Title
JP4822426B2 (en) Construction method of buried pipe under the road
KR20180118009A (en) Duplex tunnel construction method
KR20190079588A (en) Construction Method of Duplex Tunnel
JP5843413B1 (en) Lowering method of existing tunnel
JP2019124019A (en) Invert construction method to existing tunnel
JP3893056B2 (en) Construction method of underground structure
JP5524642B2 (en) Cutting method
KR102243450B1 (en) Fabrication Method of Protection Facility for Rock Breaking
KR100297436B1 (en) Methods for constructing a backfill of concrete structures
JP2006233580A (en) Vibration-isolating pile, vibration-isolating wall using the same and its execution method
JP3101371B2 (en) Temporary backfill method
JP2002317430A (en) Method and structure for burying material to be buried under ground
Kambesis et al. Dishman lane collapse, bowling green, Kentucky
JP2006183244A (en) Constructing structure for preventing thrusting flotation and frost heave of manhole and settlement, crack, waviness and frost heave of backfill soil on main pipe due to earthquake or the like
JP4223147B2 (en) Construction method for undersea structures
JP7265451B2 (en) Floating prevention method for underground buried objects
JP2013150445A (en) Conduit section of wire common duct and installation structure
JP6891637B2 (en) Partition partition and pipe burying method
JP2006057242A (en) Construction method for earth retaining wall
JP2892304B2 (en) How to protect substructures from formation migration
JP2006193900A (en) Manhole burial structure
JP2008057188A (en) Earthquake resisting manhole structure and its manufacturing method
JP2881224B2 (en) Structure liquefaction countermeasure system and its construction method
JP2002275897A (en) Earth retaining method for open-cut ditch
JP3352951B2 (en) Installation method of invert and underground drainage in mountain tunnel

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090108

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20101227

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110830

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110902

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140916

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees