JP4223147B2 - Construction method for undersea structures - Google Patents

Construction method for undersea structures Download PDF

Info

Publication number
JP4223147B2
JP4223147B2 JP20414199A JP20414199A JP4223147B2 JP 4223147 B2 JP4223147 B2 JP 4223147B2 JP 20414199 A JP20414199 A JP 20414199A JP 20414199 A JP20414199 A JP 20414199A JP 4223147 B2 JP4223147 B2 JP 4223147B2
Authority
JP
Japan
Prior art keywords
support layer
layer
pipe
constructed
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP20414199A
Other languages
Japanese (ja)
Other versions
JP2001032301A (en
Inventor
多克 和木
正美 折笠
充 野々田
隆彦 伊藤
勝夫 松崎
浩 中野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Road Co Ltd
Taisei Rotec Corp
Original Assignee
Nippon Road Co Ltd
Taisei Rotec Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Road Co Ltd, Taisei Rotec Corp filed Critical Nippon Road Co Ltd
Priority to JP20414199A priority Critical patent/JP4223147B2/en
Publication of JP2001032301A publication Critical patent/JP2001032301A/en
Application granted granted Critical
Publication of JP4223147B2 publication Critical patent/JP4223147B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、海底を浅く掘削して埋設して敷設するパイプラインや、沈埋トンネル等のような埋設構造物に対して、その支持と保護を行うための構築工法に関する。
【0002】
【従来の技術】
海岸に立地する発電所や液化天然ガスの処理設備、海水を冷却や加熱のために使用する工場等においては、海水を大量に取り入れて冷却や加熱に使用し、使用後の温排水や冷排水を再び海中に放出させる設備を設けている。前記給排水管路は、海底地盤を所定の深さまで掘削して形成した溝の底にパイプを配置し、海底面から露出させないように敷設して、船のアンカーにより損傷されたり、漁業に影響を与えることがないようにされている。
【0003】
火力発電所の温排水を放流する放水設備では、図9、図10に示されるような海底管路1を設けているもので、前記海底管路1は、陸上の冷却設備に接続される大径管路2、分岐部を介して複数に分割される中径管路3……と、さらに分割される多数本の小径管路4……から構成される。前記海底管路1においては、例えば、大径管路2を径が4mのパイプで、中径管路3を径が3m、小径管路4を径が2mのパイプで各々形成しており、図10に示すように、小径管路4の端部に立上がり管5を配置して、略水平方向に向けて配置した放水口6から温排水を放流するようにしている。そして、前記多数の放水口6………から温排水を少量ずつ、水流7として示すように放流することにより、海水の温度が局部的に上昇することなく、放流区域全体に温排水を分散させ得るようにしている。
【0004】
前記海底管路1を敷設する場合には、図11に示すように、海底地盤面から所定の深さに掘削溝10を掘削し、パイプPを支持部材を介して敷設して、前記パイプPの下面には下部支持層11を施工する。また、パイプの上部には、海底を掘削した土砂等を上部被覆層12として埋め戻し、海底面とほぼ平行になるように、パイプPの上部には保護捨石層13を所定の厚さで施工して、パイプに対する保護と上部被覆層に洗掘が生じないようにする。
【0005】
また、陸上で作成したトンネルセグメント等を海底に掘削した溝に沈設して、海底トンネル等の埋設構造物等を構築する場合においても、前記セグメントを溝に設置した後で、そのセグメントの下面に支持層を構築している。前記下部支持層としては、溝の底面とセグメントの隙間に砂や砂利を水圧を利用して押し込むことや、モルタルのような流動性を有する材料を注入して構築している。
【0006】
【発明が解決しようとする課題】
ところが、前記海底管路の管路が大径のパイプで構成されている場合には、船から土砂を投下したのみでは、パイプの直下の部分に対して両側から投下した土砂が、図11の層11、11aのように堆積し、パイプの直下の部分には土砂が完全に充填されないという問題がある。また、海底トンネルのような巾の広いセグメントの下部に支持層を形成する場合には、パイプの場合に比較して、セグメント下面全体に支持層を構築することが困難である。すなわち、前記セグメントの横から支持層の材料を注入する時に、奥の深い部分にまで砂利や砂等を隙間なく詰め込むことは、非常に面倒な作業を強いられるが、良好な結果を期待できないことが多くある。
【0007】
前記問題を解決するために、例えば、砕石や砂等の塊状体をサンドポンプによりパイプの下面に向けて噴出させ、パイプの下面に砕石を充填させるような手段を用いることや、砂等にバイブレータによる振動を付与して流動化させ、隙間が生じないような処理を行うことが実施されている。しかしながら、前記ポンプにより砕石をパイプ下面に充填させる工法を用いる場合には、潜水作業員がその砕石搬送パイプを海底で操作する必要があることと、パイプの下面に十分な量の充填材を送り込んで、下部支持層を構築することが困難であるという問題が残る。さらに、前記下部支持層の層をパイプの重量や、振動等の外力に対して十分に対応可能な支持層として構築するためには、潮流の影響を受けたりして工事が円滑に行われないことや、その下部支持層の施工コストも大きくなるという問題がある。また、パイプ支持の作用にも信頼性が得られにくいと想定され、一般のパイプラインにも適用するためには、多くの解決を要する課題が残っている。
【0008】
本発明は、前述したような従来の海底管路の構築の問題を解消するもので、パイプの下面に打設したアスファルト混合物により、パイプの支持を容易に行い得るとともに、施工の容易な工法を提供することを目的としている。
【0009】
【課題を解決するための手段】
本発明は、海底地盤面から掘り下げて構築する掘削溝に、埋設構造物を敷設して海底構造物を構築する工法に関する。
請求項1の発明は、前記掘削溝の底部に所定の厚さで石を積み重ねて構築する基礎支持層と、前記基礎支持層の上で埋設構造物を支持するための支持部材と、を設け、
前記支持部材の上に埋設構造物を敷設した状態で、前記基礎支持層の石の間にアスファルト混合物を浸透させて一体化し、さらに、前記基礎支持層および埋設構造物の上を覆うように、上部被覆層を海底地盤面に合わせて施工してから、海底地盤面に対応させて上面保護部材を敷設することを特徴とする。
【0010】
請求項2の発明は、前記基礎支持層を構築するに際して、埋設構造物の両側部に任意の間隔を介して区画部材を配置し、前記区画部材の間に石の層を施工し、
前記石の層に対してアスファルト混合物を施工して構築することを特徴とする。
【0011】
請求項3の発明は、前記掘削溝の底部の長さ方向に所定の間隔で基礎支持層と支持部材を構築し、
前記支持部材に支持させて埋設構造物を敷設し、
前記敷設した埋設構造物の底部と側部に、所定の厚さとなるようにアスファルト混合物を施工して基礎支持層を構築する工程の後で、
前記基礎支持層および埋設構造物の上を覆い、海底地盤面に合わせて上部被覆層を施工することを特徴とする。
【0013】
前述したような工法を用いることにより、パイプや沈埋トンネル等の海底埋設構造物に対する基礎支持層や支持層の支持手段を、海上からの工事により行うことができ、潜水作業員の負担を軽減することができる。また、砕石のような隙間の多い塊状体(以下砕石または割石と呼ぶ)の層にアスファルト混合物を打設して支持層を構築する場合には、砕石の隙間にアスファルト混合物が入り込んで一体化した支持層を構築でき、パイプ等の構造物の支持作用を広くて厚い層により保護することができ、海底地盤に対して構造物を安定した状態で支持させることが可能になる。さらに、区画部材を任意の間隔で配置して支持層の巾を規定する場合には、地盤の支持強度等の条件に対応させて構造物の保護を行うことが可能となり、海底管路の敷設海域に容易に対応させることができる。そして、掘削溝の上に上面保護材を配置する場合には、埋め戻した土砂を洗掘から保護するとともに、構造物上の上部被覆層が薄い場合でも、アンカー等の落下による衝撃から構造物を保護でき、海底管路の安定性を向上させることができる。
【0014】
【発明の実施の形態】
図示される例にしたがって、本発明の海底埋設構造物の構築工法を説明する。本実施例に示される海底管路は、例えば、前記図9、図10に示したような火力発電所の温排水を放流する管路や、その他の海底に敷設する管路を対象とすることができるものであるが、本発明の第1実施例の説明においては、海底に掘削して設けた掘削溝の内部で、海底埋設構造物の1例として、パイプを支持する手段を主として説明する。図1に示す例は、海底地盤面8から所定の深さに掘削して構築した掘削溝20に対して、掘削溝の底面に所定の厚さで砕石や砂等を用いて基礎支持層21として構成し、その基礎支持層21の上面に支持部材27を配置してから、比較的小さな砕石等の塊状体を船から投下して均し、その塊状体の層に対して流動性の大きなアスファルト混合物を注入して支持層22を構築する場合を示している。また、前記支持層22によりパイプPに対する支持部材を構築した後で、従来の工法の場合と同様にして、他の場所から得た掘削土砂を、敷設したパイプの上にまで搬送して上部被覆層26を構築し、ほぼ海底地盤面8と同じ高さに施工してから、洗掘保護部材としてアスファルトマット等の上面保護材28を敷設し、パイプをアンカー等の投下の衝撃から保護することができるようにする。
【0015】
前記支持層22を構築する塊状体としては、例えば、5〜10cm程度の大きさの砕石や砂利、砂等を用いることができるもので、船から砕石等の塊状体を投下した後で潜水作業員が特に大きな凹凸や、パイプ下面に十分に入り込んでいない部分等を修正する。そして、前記塊状体の層に対して、その上からアスファルト混合物25をパイプを用いて打設することで、砕石をアスファルト混合物で固化させた支持層として構築する。前記砕石交じりのアスファルト混合物の層では、打設したアスファルト混合物25が砕石の大きな隙間に充填されて固化し、パイプPの下面に広い支持層を構築できる。また、基礎支持層21の上にコンクリートブロックやアスファルトブロック等で構成した支持部材27を配置した場合でも、前記支持部材のない部分の空間まで、アスファルト混合物が浸透するので、前記基礎支持層21の上の部分に、パイプPを支持するための厚い支持層を所定の厚さで構築することができる。
【0016】
さらに、前記砕石交じりのアスファルト混合物の層を構築して、パイプPの支持を行う場合には、パイプの下面に砕石が完全に詰め込まれていない状態でも、後で打設したアスファルト混合物がパイプの下面にまで流れ込んで充填されるので、パイプの下面には空隙が形成されない。そして、前記掘削溝に配置したパイプPを、所定の巾と厚さを有するアスファルト層により一体に支持することができ、海底管路に何等かの衝撃や振動等が付与された場合でも、パイプと支持層とが一体となって対応するので、基礎支持層に対して不均一な振動や重量等が付与されることを防止できる。
【0017】
図2に示す例は、大きな砕石を塊状体として使用し、その塊状体の隙間に侵入させたアスファルト混合物で固めて、支持層23を構築する場合を示している。この例において、敷設するパイプの径が3〜4mのものに対しては、40〜50cm程度の大きな割石を用いることができるもので、船から投下した割石をパイプの下部と横の部分に所定の厚さに均し、その割石の隙間に対してアスファルト混合物25を打設する。前述したようにして大きな割石の層にアスファルト混合物を打設すると、前記アスファルトが流動性の大きいものであることから、割石の間の空隙に入り込み、基礎支持層21の上から所定の高さまで、アスファルトにより固化された割石の層が支持層23として構築される。そして、前記支持層23においては、パイプPから支持層に付与される荷重や振動等は、支持層23に対して均一に伝達されるが、積み重ねられた割石を介して基礎支持層21から溝の底面に向けて大きな割石を介して伝達される。
【0018】
図3に示す例は、アスファルト混合物の使用量を少なくして、パイプに対する支持作用を良好な状態で発揮可能にする支持層形成工法を示している。掘削溝20内の基礎支持層21の上に敷設したパイプPに対して、その横側の部分に区画部材24、24aを配置し、前記区画部材とパイプとの間に小さな砕石を詰め込んでから、アスファルト混合物25を打設する。前述したようにして巾を狭くした区間に対して支持層22を構築する場合には、パイプPの径に対して、任意の巾と厚さとを有する帯状の支持層を構築することが可能である。
【0019】
また、海底地盤面から掘削して掘削溝を構築する場合に、前記海底地盤面はシルトや泥の層等のように軟質の地層であることが多く、そのような地盤に掘削溝を掘削する時には、掘削溝の斜面の角度を小さくして崩壊を防ぐことが必要である。したがって、前記掘削溝に埋設するパイプの直径に比較して、掘削溝の開口部の巾が非常に大きくなるので、下部支持層を割石の投下等により構築する場合には、大量の割石を用いることが必要となる。これに対して、本実施例のように、パイプPの側部に所定の間隔をおいて区画部材24、24aを配置して、パイプの下部の支持層を区画する場合には、軟質の地盤に対して、支持層を任意の巾で構築することが可能であり、地盤に対するパイプ支持のための支持層の設計を容易に行うことが可能になる。
【0020】
前記区画部材を作成する場合には、例えば、コンクリートブロックやアスファルトブロック等の任意の材料を用いて構成することができるが、アスファルトブロックを用いる場合には、ブロックの内部にワイヤやその他の補強材料を挿入することで任意の長さで作成できる。また、長いアスファルトブロックが途中で折れたとしても、仕切りとして用いる場合に周囲からアスファルト混合物が漏出しない限りは、区画部材としての役目を良好に発揮できるものとされる。
【0021】
なお、前記区画部材はアスファルト混合物を打設する際の型枠としてのみ用いることができるが、そのように型枠としての用途に適応させる際には、区画部材の間に詰め込む割石から加えられる衝撃と、アスファルト混合物を打設する際の圧力に対抗できる強度を有するものであれば、薄い鉄板を加工したり、その他の任意の材料を用いて構成することも可能である。そして、割石をアスファルト成分で固めてから、その側面と上面とに上部被覆層26の土砂が充填されることにより、長い年月を経て仕切り部材が腐食したとしても、支持層の周囲は上部被覆層により充填されているのであるから、前記パイプ支持層としての支持層が変形することは考えられない。
【0022】
前記各実施例において、掘削溝20を掘削した後で溝の底部分に基礎支持層21を任意のサイズの割石等を投下して構築し、適当に均してから支持部材27を所定の間隔で配置して、パイプPを敷設することができる。前記支持部材としては、任意の材料を用いて構成することができるもので、海底管路のパイプの継ぎ目の部分や、大径と小径のパイプを接続する部分等に対応させて、任意の高さの支持部材27を用いてパイプに不陸が生じないようにして敷設する。そして、その後で、底開きの船から直接割石を投下するか、あるいはバケット等を用いてパイプの側部に所定の厚さで割石を敷設し、その割石の層に対してアスファルト混合物を打設して、割石の隙間をアスファルト混合物により充填し、1枚のパイプ支持層を構築する。
【0023】
前述したようにして、割石または砕石交じりのアスファルト混合物層をパイプ支持層として構築する場合には、パイプの下面の割石や砕石が入り込まなかった空隙部にまで、アスファルト混合物が流れ込んで固化する。したがって、前記支持層によるパイプの支持の作用は、アスファルト混合物により固化された割石と砕石交じりの層で、割石間での力の伝達により行うことが可能であり、支持層を介して基礎支持層に伝達される圧力を、掘削溝の底面の地盤に伝達することで、巾の広いパイプ支持層として作用させることができる。また、前記基礎支持層の上に構築する支持層を、アスファルト混合物により固化された割石と砕石交じりの層として構成する場合には、例えば、上部被覆層が薄い層であって、海流等により洗掘された場合でも、支持層には洗掘が発生することはないので、パイプの支持作用には支障が発生しない。
【0024】
図4に示す例は、前記図3に示すように、枕木状の支持部材を所定の間隔で配置することに代えて、略溝型のチャンネル部材を用いる場合を示している。この例においては、掘削溝20を掘削した後で、溝の底部分に基礎支持層21を任意のサイズの割石等を投下して構築する。そして、前記基礎支持層21の表面を均してから溝状支持体27aを全面に敷設し、前記溝状支持体27aの上にパイプPを敷設し、前記パイプPの横部分の空間部にアスファルト混合物を打設する。前記溝状支持体の内部に打設するアスファルト混合物は、パイプが転動しないように支持する作用を発揮するものであるが、必要に応じて割石や砕石等をその空間に入れてから、アスファルト混合物を充填することも可能である。したがって、前述したような溝状支持体を用いることによって、基礎支持層の上にパイプを容易に位置決めして支持させることが可能となり、パイプを設置した後で、前記図3の場合と同様な上部被覆層を構築してパイプを埋設することができる。
【0025】
なお、前記各実施例および後述する実施例においては、上部被覆層26の上面に上面保護材28を構築することを想定している。前記上面保護材28を任意の厚さのアスファルトマットにより構築する場合には、パイプ敷設現場近くから得られる軟質の土砂等を用いて上部被覆層に対する保護層を構築したとしても、その上部被覆層が洗掘の被害を受けることがなく、パイプに対する保護作用を良好に発揮できる。前記上面保護部材は、図示されるように、掘削した溝の上部分に任意の巾で配置できるが、その他に溝の上面を全部覆い、その溝の側部に対しても、任意の範囲で被覆可能な巾の広いものとして構成することも可能であり、海底地盤の状態に応じて、前記保護部材の敷設範囲を選択できる。また、前記上面保護材としては、割石や砕石等を船から投下して、任意の幅と厚みとを有する石の層を構築することが可能であり、その他の任意の保護層を形成することが可能である。
【0026】
そして、前記実施例に示したパイプ支持工法を用いる場合には、従来のパイプ下面に砂や砕石、または割石等の塊状体のみを用い、それ等を構造物の下部に詰め込む工法を用いる場合に比較して、主要な作業を海上から行い得ることになるので、潜水作業員により行う海底作業を減らすことができ、工事の施工コストと工期を低減することが可能となる。なお、前記実施例に示す工法は、図9、図10に示したような海底管路に適用することの他に、任意の流体搬送のパイプライン等にも適用することが可能である。また、前記各実施例において、掘削溝の底部に施工する基礎支持層は、パイプの敷設に際しての支持手段として用いるものであることから、任意の高さの支持部材を用い得る時には、掘削溝の底から支持部材を介してパイプの支持を行い、その後に支持層と基礎支持層とを共通の砕石層により構築して、アスファルト混合物を打設し、一体化させたパイプの支持層を構築することも可能である。
【0027】
前記実施例は、構造物として海底パイプラインのパイプを敷設する場合で説明したが、本発明においては、例えば、沈埋トンネルのような巾の広い大型の構造物を海底の溝に構築する場合にも、前記工法を適用することが可能である。図5に示す例は、道路トンネル等を海底に沈設して構築する場合を示しているもので、鉄筋コンクリート等で構成した沈埋トンネル40を掘削溝30に設置する。前記片道2車線の沈埋トンネルの場合には、巾が20m、高さが10m、長さが50〜100m程度の大きさの構造物として陸上で製作され、設置現場で沈下させて海底で接続することにより、道路トンネルとして構築する。
【0028】
前記沈埋トンネル40を敷設するに際しては、巾が広くて深い掘削溝30を浚渫等により掘削し、掘削溝の底面に捨石を投棄して所定の厚さの基礎支持層31を構築してから、前記沈埋トンネル40を設置する。前記沈埋トンネル40を掘削溝に設置した後で、沈埋トンネルの底面と基礎支持層31との間には隙間が生じるので、その下部の隙間に砕石や砂等の塊状体を挿入して沈埋トンネルに対する支持層を形成する。
【0029】
前記支持層を形成するためには、砂や砂利等の水に混合した塊状体を注入する方法を用いることにより下部支持層32を構築し、その下部支持層32に対してアスファルト混合物35を海上から施工して、塊状体の隙間に浸透させ、塊状体をアスファルト混合物35により固化させた支持層を構築する。前述したようにして、アスファルト混合物と塊状体により支持層を構築して、沈埋トンネル40の下面に対する支持部材を配置してから、沈埋トンネル40の側部と上面に浚渫土等を充填させて上部充填層36を構築し、必要に応じてアスファルトマット等の上面保護材37を敷設して沈埋トンネル保護工を設けることができる。
【0030】
図6に示す例は、掘削溝30の底部に基礎支持層31を形成してから、点状にコンクリートブロック等の塊状支持材33を配置し、その塊状支持材上に沈埋トンネル40を位置決めする場合を示している。前記基礎支持層31の上に塊状支持材33を介して沈埋トンネルを設置する場合には、沈埋トンネルの下面には大きな空隙が形成されていることになるので、沈埋トンネルの側部からアスファルト混合物を注入することにより、前記隙間を埋めて塊状支持材と一体化したアスファルト層を下部支持層として構築することができる。
【0031】
前述したように、巾が広い構造物を海底に掘削形成した掘削溝に設置する場合には、構造物の下面に砂や砂利等の塊状体を挿入することが困難であるから、その構造物の下面に流動性の大きいアスファルト混合物などを注入することで、隙間のない下部支持層を構築することが可能となる。そして、前記塊状体や塊状支持材を一体化したアスファルト混合物のような下部支持層を構築する場合には、構造物の下面に1枚の任意の厚さの板状体を構成することが容易に行い得て、軟弱地盤の上にでも、沈埋トンネルのような大型の構造物を構築することが可能になる。
【0032】
図7に示す例は、パイプPの支持を行うために、前記図1等に示した例とは別の例を示しているもので、掘削溝20の底部に支持台29を所定の間隔で構築し、前記支持台29の上にパイプPを敷設する例を示している。前記図7に示す例では、支持台29としては型鋼を門型に組み合わせて構成したものや、その他の任意のパイプ支持部材を用いることができるもので、溝の底面に構築した支持台に支持させるようにしてパイプPを敷設する。
【0033】
そして、前記支持台29とパイプPの下部の所定の範囲を埋めるように、アスファルト混合物を打設して板状の支持部材として構築するが、割石等でパイプの下部の隙間を少なくしてから、前記アスファルト混合物を打設して、割石交じりのアスファルト層を構築しても良い。なお。一般に、アスファルト混合物は、海中で施工した場合でもその流動性により、凹凸が少ないほぼ平らな表面を形成するという性質があり、また、比較的小さな隙間にも容易に流れ込んで充填されるという性質がある。
【0034】
図8に示す例は、大型の構造物を構築する場合等に、下部支持層をアスファルト混合物の板体で構成し、沈埋トンネル40のような構造物を支持する例を示している。この例においては、例えば、沈埋トンネル40を敷設するための掘削溝30のように、巾が広くて深い溝を掘削してから、その溝の底面に任意の厚さのアスファルト混合物の層を構築し、前記アスファルトの平坦性を利用して凹凸の少ない下部支持層34を構築することができる。そして、前記下部支持層34の上に大型の構造物を載置して位置決めすることで、沈埋トンネル40等を容易に構築できるので、前記図6、図7に示したように、掘削溝30内で構造物の横や上の余裕空間部には、浚渫土や捨て石等を投棄して埋めることにより、前記埋設物の保護を容易に行うことができる。なお、前記図8に示すように、支持層をアスファルト混合物により構築する手段は、前記パイプを支持するためにも適用が可能なことは当然である。
【0035】
前記本発明の実施例において、構造物を掘削溝の底に対して支持するためには、コンクリート混合物や、アスファルト混合物等の任意の材料を打設して、任意の厚さの支持層を構築することができる。また、支持台や支持構造物を溝の底に配置する場合にも、前記支持部材の材料としては、鉄鋼構造物やコンクリート、その他の任意の材料を用いることが可能である。さらに、前記海底埋設物が剛体の場合には、前記各実施例に示されたような比較的剛性を有する支持体を構築するが、例えば、比較的フレキシビリティのある管路等の場合には、アスファルト混合物の薄い支持層を構築した上に構造物を配置するようにして、支持面の凹凸にしたがって構造物を敷設しても良い。
【0036】
なお、埋設して施工する構造物の構造や重量、または、海底地盤の条件等により、掘削溝の底面に基礎支持層を構築しなくても良い場合かあるとも考えられる場合には、溝の底面に直接構造物を施工して、必要とされる場所にのみ、アスファルト混合物やその他の材料を打設して、構造物を支持させることも可能である。また、溝の底面に構築する支持層としては、アスファルト混合物等のような流動性を有する材料の他に、アスファルトマット等のような既成の層状の部材を敷きこむことで構築しても良い。
【0037】
【発明の効果】
本発明は、前述したような工法を用いているものであるから、パイプや沈埋トンネル等のような構造物に対する基礎支持層や支持層の支持手段を、海上からの工事により行うことができ、潜水作業員の負担を軽減することができる。また、砕石の層にアスファルト混合物を打設して支持層を構築する場合には、砕石の隙間にアスファルト混合物が入り込んで一体化した層を構築でき、構造物の支持作用を広くて厚い層により保護することができ、海底地盤に対して構造物を安定した状態で支持させることが可能になる。さらに、区画部材を任意の間隔で配置して支持層の巾を規定する場合には、地盤の支持強度等の条件に対応させて構造物の保護を行うことが可能となり、海底管路の敷設海域に容易に対応させることができる。そして、掘削溝の上に上面保護材を配置する場合には、埋め戻した土砂を洗掘から保護するとともに、構造物上の上部被覆層が薄い場合でも、アンカー等の落下による衝撃から構造物を保護でき、海底管路の安定性を向上させることが可能である。
【図面の簡単な説明】
【図1】 本発明の工法の実施例の説明図である。
【図2】 パイプ支持工法の別の実施例の説明図である。
【図3】 パイプ支持工法の他の実施例の説明図である。
【図4】 図3の別の例の説明図である。
【図5】 角型の構造物に対する支持工法の説明図である。
【図6】 角型の構造物に対する別の支持工法の説明図である。
【図7】 支持構造物とアスファルト混合物とを組み合わせた支持工法の説明図である。
【図8】 アスファルト混合物による支持工法の説明図である。
【図9】 海底管路の配置状態の説明図である。
【図10】 図9の海底管路の側面図である。
【図11】 従来の工法の説明図である。
【符号の説明】
1 海底管路、 2 大径管路、 3 中径管路、 4 小径管路、
5 立上がり管、 6 放水口、 7 水流、 8 海底地盤面、
10 掘削溝、 11 下部支持層、 12 上部被覆層、
13 保護捨石層、 20 掘削溝、 21 基礎支持層、
22・23 支持層、 24 区画部材、
25・35 アスファルト混合物、 26 上部被覆層、
27 支持部材、 28 上面保護材、 29 支持台、
30 掘削溝、 31 基礎支持層、 32 下部支持層、
33 塊状支持材、 34 下部支持層、
36 上部充填層、 37 上面保護材、
40 沈埋トンネル。
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method for supporting and protecting a buried structure such as a pipeline that is excavated and buried by shallow excavation of the seabed or a submerged tunnel.
[0002]
[Prior art]
In power plants located on the coast, liquefied natural gas processing facilities, and factories that use seawater for cooling and heating, a large amount of seawater is used for cooling and heating. Is installed in the sea. The water supply and drainage pipes are arranged at the bottom of a groove formed by excavating the seabed ground to a predetermined depth and laid so as not to be exposed from the bottom of the sea. It is not to give.
[0003]
In the water discharge facility for discharging the thermal drainage of the thermal power plant, a submarine pipeline 1 as shown in FIGS. 9 and 10 is provided. It is composed of a radial pipe 2, a medium-diameter pipe 3 divided into a plurality of parts via a branching portion, and a plurality of small-diameter pipes 4 divided further. In the submarine pipeline 1, for example, the large diameter pipe 2 is formed with a pipe having a diameter of 4 m, the medium diameter pipe 3 is formed with a diameter of 3 m, and the small diameter pipe 4 is formed with a pipe having a diameter of 2 m. As shown in FIG. 10, a rising pipe 5 is arranged at the end of the small-diameter pipe 4 so that the warm drainage is discharged from a water outlet 6 arranged in a substantially horizontal direction. Then, by discharging a small amount of warm wastewater from the large number of water discharge ports 6... As shown as a water flow 7, the temperature of the seawater is not increased locally, and the warm wastewater is dispersed throughout the discharge area. Trying to get.
[0004]
When laying the submarine pipeline 1, as shown in FIG. 11, the excavation groove 10 is excavated to a predetermined depth from the seabed ground surface, the pipe P is laid through a support member, and the pipe P A lower support layer 11 is applied to the lower surface of the substrate. In addition, the upper part of the pipe is filled with earth and sand excavated from the sea bottom as an upper covering layer 12, and a protective rubble layer 13 is applied to the upper part of the pipe P with a predetermined thickness so as to be almost parallel to the sea bottom. Thus, the pipe is protected and the upper covering layer is prevented from being scoured.
[0005]
Also, when constructing buried structures such as submarine tunnels by submerging tunnel segments created on land in a trench excavated in the seabed, after the segment is installed in the groove, Support layer is built. The lower support layer is constructed by pushing sand or gravel into the gap between the bottom of the groove and the segment using water pressure or by injecting a fluid material such as mortar.
[0006]
[Problems to be solved by the invention]
However, when the pipeline of the submarine pipe is composed of a large-diameter pipe, the earth and sand dropped from both sides with respect to the portion directly below the pipe is simply dropped from the ship. There exists a problem that it accumulates like the layers 11 and 11a, and earth and sand are not completely filled into the part directly under a pipe. Moreover, when forming a support layer in the lower part of a wide segment such as a submarine tunnel, it is difficult to construct a support layer on the entire lower surface of the segment as compared to a pipe. That is, when injecting the material of the support layer from the side of the segment, it is very troublesome to pack gravel and sand into the deep part without any gaps, but good results cannot be expected. There are many.
[0007]
In order to solve the above-mentioned problem, for example, a means such that a lump of crushed stone or sand is ejected toward the lower surface of the pipe by a sand pump and the lower surface of the pipe is filled with crushed stone, or a vibrator for sand or the like is used. It is practiced to apply a vibration to cause fluidization so that no gap is generated. However, when using the method of filling the lower surface of the pipe with crushed stone by the pump, it is necessary for the diving worker to operate the crushed stone transport pipe on the seabed, and to send a sufficient amount of filler to the lower surface of the pipe. Thus, there remains a problem that it is difficult to construct the lower support layer. Furthermore, in order to construct the lower support layer as a support layer that can sufficiently cope with the weight of pipes and external forces such as vibration, the construction is not smoothly performed due to the influence of tidal currents. In addition, there is a problem that the construction cost of the lower support layer is increased. In addition, it is assumed that it is difficult to obtain reliability in the operation of the pipe support, and there are still problems that require many solutions to be applied to a general pipeline.
[0008]
The present invention solves the problem of the construction of the conventional submarine pipe as described above, and the asphalt mixture placed on the lower surface of the pipe can easily support the pipe, and an easy construction method is provided. It is intended to provide.
[0009]
[Means for Solving the Problems]
The present invention relates to a construction method for constructing a submarine structure by laying a buried structure in an excavation groove constructed by digging down from the seabed ground surface.
The invention of claim 1 is provided with a foundation support layer constructed by stacking stones with a predetermined thickness on the bottom of the excavation groove, and a support member for supporting an embedded structure on the foundation support layer. ,
In a state where an embedded structure is laid on the support member, an asphalt mixture is infiltrated and integrated between the stones of the base support layer, and further, so as to cover the base support layer and the embedded structure. The upper covering layer is constructed according to the seabed ground surface, and then the upper surface protection member is laid according to the seabed ground surface.
[0010]
In the invention of claim 2, when constructing the foundation support layer, partition members are arranged on both sides of the embedded structure via an arbitrary interval, and a stone layer is constructed between the partition members,
The asphalt mixture is constructed and constructed on the stone layer.
[0011]
The invention of claim 3 constructs the base support layer and the support member at a predetermined interval in the length direction of the bottom of the excavation groove,
Laying an embedded structure supported by the support member,
After the step of constructing the foundation support layer by constructing the asphalt mixture to a predetermined thickness on the bottom and side of the laid buried structure,
The top support layer and the buried structure are covered, and an upper covering layer is constructed according to the seabed ground surface.
[0013]
By using the construction method described above, the foundation support layer and support means of the support layer for submarine structures such as pipes and submerged tunnels can be carried out from the sea, reducing the burden on diving workers. be able to. In addition, when a support layer is constructed by placing an asphalt mixture in a layer of a lump like a crushed stone (hereinafter referred to as crushed stone or crushed stone), the asphalt mixture enters the gap between the crushed stones and is integrated. A support layer can be constructed, and the support action of a structure such as a pipe can be protected by a wide and thick layer, and the structure can be supported stably on the seabed ground. Furthermore, when the partition members are arranged at arbitrary intervals to define the width of the support layer, it becomes possible to protect the structure according to conditions such as the support strength of the ground, and laying the submarine pipeline It can be easily adapted to the sea area. And when arranging the upper surface protection material on the excavation groove, the earth and sand that have been backfilled are protected from scouring, and even if the upper covering layer on the structure is thin, the structure from the impact due to the fall of the anchor etc. And the stability of the submarine pipeline can be improved.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
The construction method of the seafloor buried structure of the present invention will be described according to the illustrated example. The submarine pipeline shown in the present embodiment is intended for, for example, pipelines for discharging the thermal drainage of thermal power plants as shown in FIGS. 9 and 10, and other pipelines laid on the seabed. However, in the description of the first embodiment of the present invention, the means for supporting the pipe will be mainly described as an example of the seabed buried structure inside the excavation groove provided by excavation on the seabed. . In the example shown in FIG. 1, a foundation support layer 21 is formed by using crushed stone, sand or the like with a predetermined thickness on the bottom surface of the excavation groove with respect to the excavation groove 20 constructed by excavating the seabed ground surface 8 to a predetermined depth. After the support member 27 is arranged on the upper surface of the basic support layer 21, a relatively small lump of crushed stone or the like is dropped from the ship and leveled, and the fluidity of the lump is large. The case where the support layer 22 is constructed by injecting an asphalt mixture is shown. In addition, after the support member for the pipe P is constructed by the support layer 22, the excavated earth and sand obtained from other places are transported to the laid pipe in the same manner as in the case of the conventional construction method, and the upper cover is covered. After constructing the layer 26 and constructing it at almost the same height as the seabed surface 8, laying a top protection material 28 such as an asphalt mat as a scour protection member to protect the pipe from the impact of dropping the anchor etc. To be able to.
[0015]
As the lump for constructing the support layer 22, for example, crushed stone, gravel, sand or the like having a size of about 5 to 10 cm can be used, and diving work after dropping the lump such as crushed stone from the ship. The worker corrects particularly large irregularities and portions that do not sufficiently enter the lower surface of the pipe. Then, the asphalt mixture 25 is driven from above the lump layer using a pipe, thereby constructing a crushed stone as a support layer solidified with the asphalt mixture. In the layer of asphalt mixture mixed with crushed stone, the cast asphalt mixture 25 is filled in a large gap of crushed stone and solidified, and a wide support layer can be constructed on the lower surface of the pipe P. Further, even when the support member 27 composed of a concrete block, an asphalt block, or the like is disposed on the foundation support layer 21, the asphalt mixture penetrates to the space where there is no support member. In the upper part, a thick supporting layer for supporting the pipe P can be constructed with a predetermined thickness.
[0016]
Furthermore, when a layer of asphalt mixture mixed with crushed stone is constructed to support the pipe P, the asphalt mixture placed later is not even if the crushed stone is not completely packed on the lower surface of the pipe. Since it flows into the lower surface and is filled, no gap is formed on the lower surface of the pipe. The pipe P arranged in the excavation groove can be integrally supported by an asphalt layer having a predetermined width and thickness, and even if any impact or vibration is applied to the submarine pipe, Since the support layer and the support layer are integrated, it is possible to prevent uneven vibration, weight, and the like from being imparted to the basic support layer.
[0017]
The example shown in FIG. 2 shows a case where the support layer 23 is constructed by using a large crushed stone as a lump and solidifying with an asphalt mixture that has entered the gaps between the lump. In this example, a large quarry stone of about 40 to 50 cm can be used for pipes with a diameter of 3 to 4 m. The asphalt mixture 25 is cast into the gap between the crushed stones. As described above, when the asphalt mixture is placed in a large crushed stone layer, since the asphalt is highly fluid, it enters the gap between the crushed stones, from above the foundation support layer 21 to a predetermined height, A layer of crushed stone solidified by asphalt is constructed as the support layer 23. In the support layer 23, the load, vibration, and the like applied from the pipe P to the support layer are uniformly transmitted to the support layer 23. However, the groove is removed from the basic support layer 21 through the stacked calculus. It is transmitted through a large crushed stone toward the bottom surface.
[0018]
The example shown in FIG. 3 shows a support layer forming method that reduces the amount of asphalt mixture used and enables the pipe to perform a supporting action in a good state. For the pipe P laid on the foundation support layer 21 in the excavation groove 20, the partition members 24 and 24a are arranged on the side portions thereof, and small crushed stones are packed between the partition member and the pipe. Asphalt mixture 25 is placed. When the support layer 22 is constructed for the section having a narrow width as described above, it is possible to construct a belt-like support layer having an arbitrary width and thickness with respect to the diameter of the pipe P. is there.
[0019]
In addition, when constructing a trench by excavating from the seabed ground surface, the seabed ground surface is often a soft layer such as a silt or mud layer, and the trench is excavated in such ground. Sometimes it is necessary to reduce the angle of the slope of the excavation groove to prevent collapse. Therefore, since the width of the opening of the excavation groove becomes very large compared to the diameter of the pipe embedded in the excavation groove, when constructing the lower support layer by dropping calculus or the like, a large amount of calculus is used. It will be necessary. On the other hand, when the partition members 24 and 24a are arranged at predetermined intervals on the side portion of the pipe P to partition the support layer below the pipe as in this embodiment, the soft ground On the other hand, the support layer can be constructed with an arbitrary width, and the support layer for supporting the pipe to the ground can be easily designed.
[0020]
When creating the partition member, for example, it can be configured using an arbitrary material such as a concrete block or an asphalt block, but when using an asphalt block, a wire or other reinforcing material is used inside the block. It can be created with any length by inserting. Moreover, even if a long asphalt block breaks in the middle, when used as a partition, as long as the asphalt mixture does not leak from the surroundings, the function as a partition member can be satisfactorily exhibited.
[0021]
The partition member can be used only as a mold for placing an asphalt mixture. However, when adapting to the use as a mold, the impact applied from the crushed stone packed between the partition members. As long as it has a strength capable of resisting the pressure when placing the asphalt mixture, it is possible to process a thin iron plate or to use other arbitrary materials. Then, after the calcite is hardened with the asphalt component, the side and upper surfaces are filled with the earth and sand of the upper covering layer 26, so that even if the partition member is corroded over many years, the periphery of the support layer is covered with the upper covering. Since it is filled with the layer, it is not considered that the support layer as the pipe support layer is deformed.
[0022]
In each of the above-described embodiments, after excavating the excavation groove 20, the base support layer 21 is constructed by dropping a crushed stone of an arbitrary size on the bottom portion of the groove, and the support member 27 is arranged at a predetermined interval after being appropriately leveled. And the pipe P can be laid. The support member can be configured using any material, and can be configured to have any height corresponding to a seam portion of a pipe in a submarine conduit or a portion connecting a large diameter pipe and a small diameter pipe. The support member 27 is used to lay the pipe so as not to be uneven. After that, either throw the chopping stone directly from the open-bottomed ship, or lay the chopping stone at a predetermined thickness on the side of the pipe using a bucket or the like, and lay the asphalt mixture on the crushed stone layer Then, the gap between the quarry stones is filled with the asphalt mixture, and one pipe support layer is constructed.
[0023]
As described above, when the asphalt mixture layer mixed with crushed stone or crushed stone is constructed as a pipe support layer, the asphalt mixture flows into the void portion where the crushed stone or crushed stone does not enter the lower surface of the pipe and solidifies. Therefore, the support of the pipe by the support layer is a layer of crushed stone and crushed stone solidified by the asphalt mixture, and can be performed by transmitting force between the crushed stones, and the basic support layer is interposed through the support layer. By transmitting the pressure transmitted to the bottom of the excavation groove to the ground, it is possible to act as a wide pipe support layer. Further, when the support layer constructed on the foundation support layer is configured as a layer of crushed stone and crushed stone solidified by an asphalt mixture, for example, the upper covering layer is a thin layer, and is washed by a sea current or the like. Even when excavated, scouring does not occur in the support layer, so that there is no problem in supporting the pipe.
[0024]
The example shown in FIG. 4 shows a case where a substantially groove-shaped channel member is used instead of arranging sleeper-like support members at a predetermined interval, as shown in FIG. In this example, after excavating the excavation groove 20, the foundation support layer 21 is constructed by dropping crushed stone or the like of an arbitrary size on the bottom portion of the groove. Then, after leveling the surface of the base support layer 21, the groove-like support 27 a is laid on the entire surface, and the pipe P is laid on the groove-like support 27 a, and in the space portion of the lateral portion of the pipe P Place the asphalt mixture. The asphalt mixture to be cast inside the groove-shaped support body has an effect of supporting the pipe so that it does not roll, but if necessary, crushed stones or crushed stones are put into the space, and the asphalt It is also possible to fill the mixture. Therefore, by using the grooved support as described above, the pipe can be easily positioned and supported on the base support layer, and after the pipe is installed, the same as in the case of FIG. An upper covering layer can be constructed to embed the pipe.
[0025]
In each of the above embodiments and the embodiments described later, it is assumed that the upper surface protective material 28 is constructed on the upper surface of the upper covering layer 26. When the upper surface protective material 28 is constructed by an asphalt mat having an arbitrary thickness, even if a protective layer for the upper coating layer is constructed using soft earth and sand obtained from the vicinity of the pipe laying site, the upper coating layer However, it will not be damaged by scouring, and the protective effect on the pipe can be demonstrated well. As shown in the drawing, the upper surface protection member can be arranged in an arbitrary width on the upper portion of the excavated groove, but also covers the entire upper surface of the groove and also on the side of the groove in an arbitrary range. It is also possible to configure the cover so as to have a wide width, and the laying range of the protection member can be selected according to the state of the seabed ground. Moreover, as the upper surface protective material, it is possible to construct a stone layer having an arbitrary width and thickness by dropping crushed stones, crushed stones, etc. from the ship, and to form other arbitrary protective layers Is possible.
[0026]
And, when using the pipe support method shown in the above embodiment, when using a conventional method that uses only a lump such as sand, crushed stone, or crushed stone on the lower surface of the pipe, and stuffs them into the lower part of the structure In comparison, since the main work can be performed from the sea, the submarine work performed by the submersible worker can be reduced, and the construction cost and construction period of the construction can be reduced. In addition, the construction method shown in the embodiment can be applied not only to the submarine pipeline as shown in FIGS. 9 and 10, but also to an arbitrary fluid conveyance pipeline. In each of the above embodiments, since the foundation support layer to be constructed at the bottom of the excavation groove is used as a support means when laying the pipe, when a support member having an arbitrary height can be used, The pipe is supported from the bottom through the support member, and then the support layer and the base support layer are constructed with a common crushed stone layer, and the asphalt mixture is cast and an integrated pipe support layer is constructed. It is also possible.
[0027]
In the above embodiment, the submarine pipeline pipe is laid as a structure. However, in the present invention, for example, when a wide large structure such as a submerged tunnel is constructed in a submarine trench. It is also possible to apply the construction method. The example shown in FIG. 5 shows a case where a road tunnel or the like is submerged and constructed, and a submerged tunnel 40 made of reinforced concrete or the like is installed in the excavation groove 30. In the case of the one-way two-lane submerged tunnel, it is manufactured on the ground as a structure having a width of 20 m, a height of 10 m, and a length of about 50 to 100 m, and is submerged at the installation site and connected on the seabed. Therefore, it is constructed as a road tunnel.
[0028]
When laying the submerged tunnel 40, a wide and deep excavation groove 30 is excavated with a fence or the like, and a rubble is dumped on the bottom surface of the excavation groove to construct a foundation support layer 31 having a predetermined thickness. The submerged tunnel 40 is installed. After the submerged tunnel 40 is installed in the excavation groove, a gap is formed between the bottom surface of the submerged tunnel and the base support layer 31. Therefore, a submerged tunnel such as crushed stone or sand is inserted into the lower gap. A support layer is formed.
[0029]
In order to form the support layer, a lower support layer 32 is constructed by using a method of injecting a lump mixed with water such as sand or gravel, and the asphalt mixture 35 is placed on the sea with respect to the lower support layer 32. The support layer is constructed by infiltrating into the gaps between the blocks and solidifying the blocks with the asphalt mixture 35. As described above, the support layer is constructed by the asphalt mixture and the lump, and the support member for the lower surface of the submerged tunnel 40 is disposed, and then the side and upper surfaces of the submerged tunnel 40 are filled with clay and the like. The filling layer 36 can be constructed, and an upper surface protective material 37 such as an asphalt mat can be laid as necessary to provide a buried tunnel protective work.
[0030]
In the example shown in FIG. 6, after the foundation support layer 31 is formed at the bottom of the excavation groove 30, a massive support material 33 such as a concrete block is arranged in a dotted shape, and the submerged tunnel 40 is positioned on the massive support material. Shows the case. When a submerged tunnel is installed on the base support layer 31 via the massive support member 33, a large gap is formed on the lower surface of the submerged tunnel, so that the asphalt mixture is formed from the side of the submerged tunnel. By injecting the asphalt layer, the asphalt layer integrated with the massive support material by filling the gap can be constructed as the lower support layer.
[0031]
As described above, when installing a wide structure in a drilling groove formed on the seabed, it is difficult to insert a lump such as sand or gravel into the bottom surface of the structure. It is possible to construct a lower support layer without a gap by injecting a flowable asphalt mixture or the like into the lower surface of the substrate. And when constructing a lower support layer such as an asphalt mixture in which the block body and the block support material are integrated, it is easy to form a single plate-like body having an arbitrary thickness on the lower surface of the structure. It is possible to construct a large structure such as a submerged tunnel even on soft ground.
[0032]
The example shown in FIG. 7 shows an example different from the example shown in FIG. 1 or the like in order to support the pipe P. A support base 29 is provided at a predetermined interval at the bottom of the excavation groove 20. An example in which the pipe P is constructed and laid on the support base 29 is shown. In the example shown in FIG. 7, the support base 29 is configured by combining a steel plate with a gate shape, or any other pipe support member can be used, and is supported by a support base constructed on the bottom surface of the groove. In this way, the pipe P is laid.
[0033]
And asphalt mixture is casted and built as a plate-shaped support member so as to fill a predetermined range of the support base 29 and the lower part of the pipe P. The asphalt mixture may be placed to construct a bitumen asphalt layer. Note that. Generally, an asphalt mixture has the property of forming a substantially flat surface with few irregularities due to its fluidity even when applied in the sea, and also has the property of easily flowing into and filling relatively small gaps. is there.
[0034]
The example shown in FIG. 8 shows an example in which the lower support layer is formed of a plate of asphalt mixture and a structure such as the buried tunnel 40 is supported when a large structure is constructed. In this example, for example, a wide and deep groove such as the excavation groove 30 for laying the submerged tunnel 40 is excavated, and then an asphalt mixture layer having an arbitrary thickness is constructed on the bottom surface of the groove. In addition, the lower support layer 34 with less unevenness can be constructed using the flatness of the asphalt. Then, by placing and positioning a large structure on the lower support layer 34, the submerged tunnel 40 and the like can be easily constructed. Therefore, as shown in FIG. 6 and FIG. The buried space can be easily protected by dumping dredged material, stones, or the like in the marginal space next to or above the structure. As shown in FIG. 8, the means for constructing the support layer with the asphalt mixture is naturally applicable to support the pipe.
[0035]
In the embodiment of the present invention, in order to support the structure against the bottom of the excavation groove, an arbitrary material such as a concrete mixture or an asphalt mixture is placed to construct a support layer having an arbitrary thickness. can do. Moreover, also when arrange | positioning a support stand and a support structure in the bottom of a groove | channel, as a material of the said support member, it is possible to use steel structures, concrete, and other arbitrary materials. Further, when the seabed buried object is a rigid body, a relatively rigid support body as shown in each of the above embodiments is constructed. For example, in the case of a relatively flexible pipe line, etc. The structure may be laid according to the unevenness of the support surface in such a manner that the structure is arranged on the thin support layer of the asphalt mixture.
[0036]
If the foundation support layer may or may not need to be constructed on the bottom of the excavation groove, depending on the structure and weight of the structure to be buried and constructed, or the conditions of the seabed ground, etc. It is also possible to construct the structure directly on the bottom surface and to place the asphalt mixture or other material only where it is needed to support the structure. Moreover, as a support layer constructed | assembled on the bottom face of a groove | channel, you may construct | assemble by laying down the existing layered member like an asphalt mat etc. other than the material which has fluidity | liquidity like an asphalt mixture.
[0037]
【The invention's effect】
Since the present invention uses the construction method as described above, the support means for the foundation support layer and the support layer for structures such as pipes and submerged tunnels can be performed by construction from the sea, It is possible to reduce the burden on diving workers. In addition, when constructing a support layer by placing an asphalt mixture in a layer of crushed stone, it is possible to construct an integrated layer with the asphalt mixture entering the gap between crushed stones. It can protect, and it becomes possible to support a structure in a stable state with respect to the seabed ground. Furthermore, when the partition members are arranged at arbitrary intervals to define the width of the support layer, it becomes possible to protect the structure according to conditions such as the support strength of the ground, and laying the submarine pipeline It can be easily adapted to the sea area. And when arranging the upper surface protection material on the excavation groove, the earth and sand that have been backfilled are protected from scouring, and even if the upper covering layer on the structure is thin, the structure from the impact due to the fall of the anchor etc. It is possible to improve the stability of the submarine pipeline.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram of an embodiment of the construction method of the present invention.
FIG. 2 is an explanatory diagram of another embodiment of the pipe support method.
FIG. 3 is an explanatory diagram of another embodiment of the pipe support method.
FIG. 4 is an explanatory diagram of another example of FIG. 3;
FIG. 5 is an explanatory diagram of a support method for a square structure.
FIG. 6 is an explanatory diagram of another support method for a square structure.
FIG. 7 is an explanatory view of a support method in which a support structure and an asphalt mixture are combined.
FIG. 8 is an explanatory diagram of a support method using an asphalt mixture.
FIG. 9 is an explanatory diagram of an arrangement state of submarine pipelines.
10 is a side view of the submarine conduit of FIG. 9. FIG.
FIG. 11 is an explanatory diagram of a conventional construction method.
[Explanation of symbols]
1 submarine pipeline, 2 large-diameter pipeline, 3 medium-diameter pipeline, 4 small-diameter pipeline,
5 rise pipes, 6 water outlets, 7 water currents, 8 submarine ground surface,
10 excavation groove, 11 lower support layer, 12 upper covering layer,
13 protective rubble layer, 20 excavation groove, 21 foundation support layer,
22, 23 support layer, 24 partition member,
25/35 asphalt mixture, 26 top coating layer,
27 support member, 28 upper surface protective material, 29 support base,
30 excavation grooves, 31 foundation support layer, 32 lower support layer,
33 Massive support material, 34 Lower support layer,
36 upper packing layer, 37 upper surface protective material,
40 Submerged tunnel.

Claims (3)

海底地盤面から掘り下げて構築する掘削溝に、埋設構造物を敷設して海底構造物を構築する工法であって、
前記掘削溝の底部に所定の厚さで石を積み重ねて構築する基礎支持層と、前記基礎支持層の上で埋設構造物を支持するための支持部材と、を設け、
前記支持部材の上に埋設構造物を敷設した状態で、前記基礎支持層の石の間にアスファルト混合物を浸透させて一体化し、
さらに、前記基礎支持層および埋設構造物の上を覆うように、上部被覆層を海底地盤面に合わせて施工してから、海底地盤面に対応させて上面保護部材を敷設することを特徴とする海底埋設構造物の構築工法。
It is a construction method to construct a submarine structure by laying a buried structure in a excavation groove constructed by digging down from the seabed ground surface,
A foundation support layer constructed by stacking stones with a predetermined thickness on the bottom of the excavation groove, and a support member for supporting the buried structure on the foundation support layer,
In a state where an embedded structure is laid on the support member, the asphalt mixture is infiltrated and integrated between the stones of the foundation support layer,
Furthermore, after covering the foundation support layer and the buried structure, the upper covering layer is constructed according to the seabed ground surface, and then an upper surface protection member is laid corresponding to the seabed ground surface. Construction method for undersea structures.
前記基礎支持層を構築するに際して、埋設構造物の両側部に任意の間隔を介して区画部材を配置し、前記区画部材の間に石の層を施工し、
前記石の層に対してアスファルト混合物を施工して構築することを特徴とする請求項1に記載の海底埋設構造物の構築工法。
When constructing the foundation support layer, disposing partition members on the both sides of the embedded structure via an arbitrary interval, constructing a stone layer between the partition members,
The construction method of a submarine buried structure according to claim 1, wherein an asphalt mixture is constructed on the stone layer.
前記掘削溝の底部の長さ方向に所定の間隔で基礎支持層と支持部材を構築し、
前記支持部材に支持させて埋設構造物を敷設し、
前記敷設した埋設構造物の底部と側部に、所定の厚さとなるようにアスファルト混合物を施工して基礎支持層を構築する工程の後で、
前記基礎支持層および埋設構造物の上を覆い、海底地盤面に合わせて上部被覆層を施工することを特徴とする請求項1に記載の海底埋設構造物の構築工法。
Constructing a base support layer and a support member at predetermined intervals in the length direction of the bottom of the excavation groove,
Laying an embedded structure supported by the support member,
After the step of constructing the foundation support layer by constructing the asphalt mixture to a predetermined thickness on the bottom and side of the laid buried structure,
2. The construction method for a submarine embedded structure according to claim 1, wherein the foundation support layer and the embedded structure are covered and an upper covering layer is constructed in accordance with the seabed ground surface.
JP20414199A 1999-07-19 1999-07-19 Construction method for undersea structures Expired - Fee Related JP4223147B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20414199A JP4223147B2 (en) 1999-07-19 1999-07-19 Construction method for undersea structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20414199A JP4223147B2 (en) 1999-07-19 1999-07-19 Construction method for undersea structures

Publications (2)

Publication Number Publication Date
JP2001032301A JP2001032301A (en) 2001-02-06
JP4223147B2 true JP4223147B2 (en) 2009-02-12

Family

ID=16485524

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20414199A Expired - Fee Related JP4223147B2 (en) 1999-07-19 1999-07-19 Construction method for undersea structures

Country Status (1)

Country Link
JP (1) JP4223147B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943945A (en) * 2012-12-07 2013-02-27 中国石油集团工程设计有限责任公司 Earthquake-proof protection method for pipeline projects passing through fault zones
CN112344096B (en) * 2020-11-13 2022-07-29 中船华南船舶机械有限公司 Construction method of submarine pipeline leveling, laying, locking and burying equipment
CN113585346A (en) * 2021-08-13 2021-11-02 中南大学 Immersed tube foundation tank treatment process and immersed tube installation process for offshore inland river junction area

Also Published As

Publication number Publication date
JP2001032301A (en) 2001-02-06

Similar Documents

Publication Publication Date Title
CN103958780B (en) The method for forming cementing retaining wall
JP4898233B2 (en) Manhole floating prevention structure
US8882397B2 (en) Methods for waterproofing depositing sites
JP4293435B2 (en) Construction method of managed revetment
GB1558427A (en) Laying of underground pipes
KR20120012503A (en) Reverse Circulation Drill Method With precast type Caisson and Jacket
CN111335263B (en) Method for building artificial island
JP4223147B2 (en) Construction method for undersea structures
JP5099709B2 (en) Construction method of managed revetment
JP5728206B2 (en) Construction method of partition revetment
KR940002457B1 (en) Method and apparatus for increasing bearing capacity of soft soil and constructing cutoff wall
KR20190072213A (en) Method Of Ground Half-Openning For Tunnel Excavation
JP3756077B2 (en) Burial method and structure of underground objects
JP6341834B2 (en) Caisson type hybrid bank structure
JP2002309569A (en) Process for making joint part of water-impervious wall impervious to water
JP2003071401A (en) Water sealing treatment method of revetment for controlled waste landfill
JP3320580B2 (en) Foundation construction method for offshore structures
JP2006183244A (en) Constructing structure for preventing thrusting flotation and frost heave of manhole and settlement, crack, waviness and frost heave of backfill soil on main pipe due to earthquake or the like
JP4606454B2 (en) Construction method of managed revetment
JP5131742B2 (en) Foundation construction method for revetment structures
JP4320972B2 (en) Landfill soil runoff prevention structure for quay and revetment
JPH07300845A (en) Preventive method against liquefaction of underground linear structure
Meyer Quay Wall Structures in Container Sea Ports and Influences on the Design
CN116122254A (en) Filling device, filling structure, dyke structure and sludge treatment method
JP3690875B2 (en) Ground fluidization countermeasure construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060117

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070920

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080220

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080401

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080715

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080723

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20081118

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20081119

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111128

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111128

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121128

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131128

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees