KR20120012503A - Reverse Circulation Drill Method With precast type Caisson and Jacket - Google Patents

Reverse Circulation Drill Method With precast type Caisson and Jacket Download PDF

Info

Publication number
KR20120012503A
KR20120012503A KR1020100074478A KR20100074478A KR20120012503A KR 20120012503 A KR20120012503 A KR 20120012503A KR 1020100074478 A KR1020100074478 A KR 1020100074478A KR 20100074478 A KR20100074478 A KR 20100074478A KR 20120012503 A KR20120012503 A KR 20120012503A
Authority
KR
South Korea
Prior art keywords
caisson
jacket
steel pipe
concrete
assembly
Prior art date
Application number
KR1020100074478A
Other languages
Korean (ko)
Other versions
KR101256274B1 (en
Inventor
김상훈
Original Assignee
김상훈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김상훈 filed Critical 김상훈
Priority to KR1020100074478A priority Critical patent/KR101256274B1/en
Publication of KR20120012503A publication Critical patent/KR20120012503A/en
Application granted granted Critical
Publication of KR101256274B1 publication Critical patent/KR101256274B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/18Foundations formed by making use of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/28Stressing the soil or the foundation structure while forming foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1628Shapes rectangular

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE: A reverse circulation drill method using a prefabricated caisson and a jacket is provided to reduce resistance to stress and differential settlement using a pile foundation. CONSTITUTION: A reverse circulation drill method using a prefabricated caisson and a jacket is as follows. A concrete structure of a prefabricated caisson(10) is put into a sea bottom. The inner part of the prefabricated caisson is dredged using a clamshell bucket and a sand pump. A jacket(15) having a guide steel pipe(33) is installed in the dredged part, and underwater concrete is placed.

Description

조립케이슨 및 쟈켓을 이용한 알시디(RCD)공법{Reverse Circulation Drill Method With precast type Caisson and Jacket}Reverse Circulation Drill Method With precast type Caisson and Jacket}

본 발명은 하상 및 해상에서 이루어지는 교량공사중 기초 시공 부분과 해상 연약지반을 치환 보강하는 시공공법으로, 현장타설말뚝 공사시 발생하는 여러 가지의 문제점을 직접 기초방식과 케이슨 공법의 플로팅(Floating) 타입의 장점을 발췌 도입하여 알시디(RCD : Reverse Circulation Drill)를 사용함과 시공방법을 달리하여 각 공법들의 제약 요건들을 취합 보완함으로써 목적물의 구조적인 안정성 증대와 시간적, 경제적인 절감을 도모할 수 있는 조립케이슨 및 쟈켓을 이용한 알시디(RCD)공법에 관한 것이다.The present invention is a construction method that replaces and reinforces the foundation construction part and the marine soft ground in the bridge construction made in the seabed and the sea, and solves the various problems that occur during the construction of the cast-in-place pile. Assembled caisson which can increase structural stability and save time and economics of targets by using RCD (Reverse Circulation Drill) by adopting excerpts and collecting and supplementing constraints of each method by changing construction method. And it relates to an Alcidi (RCD) method using a jacket.

토질 및 기초 분야에서 깊은 기초는 말뚝기초, 현장타설말뚝 및 케이슨 (Caisson) 기초로 나누어지고 있는 바, 상기 말뚝기초는 재료에 따라 강관, PHC 및 RC 말뚝으로 구분되고 말뚝기초에서 시공법에 따라 타입(항타)말뚝과 매입말뚝으로 구분한다. 통상적으로 구조물에서 지지력은 항타말뚝일 경우, 공사비 측면에서 경제적이고 지지력 발휘가 큰데 비하여 소음 진동의 영향으로 공사 여건이 쉽지 않다. 그리고, 지층상에 자갈이나 단단한 층이 있을 때 항타할 경우, 말뚝이 부러지는 경우가 발생함으로 적용 여건이 쉽지 않다.In the soil and foundation fields, deep foundations are divided into pile foundations, cast-in-place piles and caisson foundations, which are divided into steel pipes, PHC and RC piles according to the material, Driven) It is divided into pile and purchase pile. In general, when the bearing capacity is the pile pile, the construction conditions are not easy due to the noise and vibration. In addition, when driving when there is gravel or a hard layer on the strata, the piles are broken, so the application conditions are not easy.

따라서, 상기 조건에 맞지 않을 때에는 매입이나 현장 타설말뚝을 쓰게 되는 바, 상기 매입은 지반을 선굴착후 말뚝을 삽입하는데에 SIP, SDA 및 PRD등 시공방법이 발달되어 지층조건 등에 따라 적용공법이 많다. 상기 현장타설말뚝은 기성제품이 아닌 현장에서 타설하는 관계로 시공관리와 품질관리에 어려움이 많으며, 대체적으로 교량에서는 대구경으로 많이 사용되고 있다.Therefore, when it does not meet the above conditions, it is necessary to use the embedding or on-site pour pile. The embedding is a method of inserting the pile after pre-excavation of the ground. . The cast-in-place piles are not ready-made products, so they are difficult to install and quality control, and are generally used as large diameters in bridges.

한편, RCD(Reverse Circulation Drill)에 의한 현장타설 말뚝기초공법 또한 제한된 직경이상의 대구경기초는 시공이 불가능하며, 수중콘크리트 타설시 품질관리가 어렵고 완성된 기초구조물의 양호여부를 확인할 수 없을 뿐 아니라, 필요시 보완이나 수정작업이 불가능하고, 기타 여러 종류의 재래식 Pier기초시공법 또한 연약지반과 같은 토사층에서의 굴착은 대체로 쉬운 편이나 풍화암이나 연암층과 같은 지지층까지 케이슨(Caisson)을 침설시키려면 발파 균열로 인한 침투수 유입과 수중콘크리트 타설 등으로 인한 품질관리에 많은 제한을 받게 된다.On the other hand, the site foundation pile foundation method by RCD (Reverse Circulation Drill) is also impossible to construct large-diameter foundations with a limited diameter, and it is difficult to check the quality of the finished foundation structure when underwater casting, It is not possible to supplement or modify the soil, and many other types of conventional Pier Foundation methods are also easy to excavate from soil layers such as soft ground. However, if the caisson is settled to the supporting layer such as weathered rock or soft rock, Due to the infiltration of infiltrated water and the placing of underwater concrete, quality control is restricted.

지지층까지의 굴착심도가 비교적 얕은 경우에 적용되는 직접기초공법 또한 수평지지력확보를 위해서는 확대기초와 같은 폭넓은 기초형식이 요구되거나, 하천이나 호수, 해상에서와 같이 수심이 깊은 곳에서는 시트파일을 이용한 가시설이나 강재 가물막이공 등이 부가적으로 필요하게 됨으로써 기초구조물 시공에 많은 제한을 받게 된다.The direct foundation method, which is applied when the depth of excavation to the support layer is relatively shallow, also requires a wide range of basic types such as an enlarged foundation to secure horizontal bearing capacity, or uses sheet piles in deep waters such as rivers, lakes, and seas. As additional provision of temporary installations or steel cladding is required, the construction of foundation structures is greatly limited.

상기 현장타설 말뚝시공중 강관근입시 바이브로 햄머로 항타가 끝나고 RCD를 장착하는 동안 조류의 영향 및 세굴현상 때문에 완전히 안착되지 못한 상태에서 강관은 최초 지점에서 이탈되고 만다. 다시 안착시키기 위해 같은 작업을 반복한다. 또한, 해저면의 지층상태에 따라 많은 영향을 받는다.The steel pipe is released from the initial point in the state that the steel pipe is not fully seated due to the effects of algae and scouring during the installation of the RCD when the steel pipe is entered during the construction of the cast-in-place pile. Do the same to get it back on. In addition, it is greatly affected by the stratum state of the sea bottom.

하중의 경감에 대한 적응성이 좋고 교량의 상부 및 연직 하중을 등분포로 지지층에 직접 전달하는 직접 기초 방식의 교각 하부기초(Footing)를 해저면에 설치하는 방법으로, 파고의 영향이 적고 지지면과 접촉 단면이 커서 주변 마찰력이 큰 케이슨(Caisson)의 형태를 변형시켜 조합 사용하는 방법인 것이다. 이에 연암층까지 굴착이 가능한 알시디(RCD)를 장착 소정의 깊이까지 시공할 수 있다.It is adaptable to the reduction of load and installs the direct foundation pier footing on the sea floor, which transmits the upper and vertical loads of the bridge directly to the support layer in equal distribution. It is a method of using a combination of deformations of the shape of the caisson, which has a large cross-sectional friction force. In this case, it is possible to construct a predetermined depth by mounting an RCD that can be excavated to the soft rock layer.

따라서, 교량의 기초로 많이 사용하는 말뚝기초에서 필연적으로 발생하는 세굴현상에 따른 말뚝 주변의 함몰현상과, 강관 근입 및 굴착시 발생하는 여러 가지 시공상의 문제점이 있다. 또한, 케이슨 작업시 수반되는 제작상의 문제와, 육상에서의 입지 조건, 접안 시설까지의 운송 수단 및 방법, 그리고 해상 운반시 제약 받는 기상조건 및 운반장비 등의 제약 조건을 고려하게 된다.Therefore, there are various construction problems that occur during the recession of piles around the piles due to scour phenomena which are inevitably generated in pile foundations that are frequently used as foundations of bridges, and when the steel pipes enter and excavate. In addition, consideration will be given to the manufacturing problems involved in the caisson work, the conditions of onshore land, the means and method of transportation to the berthing facilities, and the constraints of weather conditions and transportation equipment that are restricted by sea transport.

실무토목기초 설계와 시공, 토목발전연구회편저. 도서출판 건설정보, 도로설계 편람 제5편 교량, 국토해양부. 최신기초설계 시공 핸드북, 건설문화사 p758/804. 해상 R.C.D 기초공법의 시공설명 2006년 대한토목회 정기학술대회. 공장형 슬림폼을 이용한 제작 운송 진수 공법, 현대건설 기술 개발실.Design and construction of working civil engineering foundation, civil engineering research society. Book Publishing Construction Information, Road Design Manual, Part 5 Bridges, Ministry of Land, Transport and Maritime Affairs. Latest Basic Design Construction Handbook, Construction Culture History p758 / 804. Explanation of Construction of Marine R.C.D Basic Construction Method 2006 Korean Society of Civil Engineers Regular Conference. Production construction launching method using factory slim form, Hyundai Construction Technology Development Office.

본 발명은 상기와 같은 제반 사정을 감안하여 발명한 것으로, 직접 기초 방식의 확대 기초로 사용하는 풋팅을 하저 또는 해저면에 설치함으로써 연직 또는 수평 방향의 지지력과 휨 모멘트, 편심 하중을 상쇄시킬 수 있으며, 지반 반력에 의한 응력과 부등 침하에 대한 저항력은 말뚝기초로 감소시켜 상부 교량의 상재하중의 경감에 따른 대응력을 증가시킬 수 있는 조립케이슨 및 쟈켓을 이용한 알시디(RCD)공법을 제공하고자 함에 그 목적이 있다.The present invention has been made in view of the above circumstances, and by installing a footing used as an extension base of the direct foundation method on the bottom or the bottom surface, it is possible to offset the bearing force, bending moment, and eccentric load in the vertical or horizontal direction. In order to provide the RCD method using the assembly caisson and jacket, the resistance to stress and uneven settlement due to the ground reaction force can be reduced to the pile foundation to increase the coping force according to the reduction of the overhead load of the upper bridge. There is a purpose.

상기 목적을 달성하기 위한 본 발명은, 케이슨을 투하 연하여 조립케이슨으로 결속하고 그 내부를 크람쉘 버켓을 사용하여 풍화암상단까지 준설하며, 그 후에 유도강관이 부착된 쟈켓을 설치하고 수중 콘크리트 타설하여 일체화시키도록 구성하되; 조립케이슨의 콘크리트 구조물을 해저면에 투하하고, 크람쉘 버켓과 샌드 펌프를 사용하여 케이슨 조립체의 내부 구역을 준설하며, 쟈켓을 침설한 다음 1 차 콘크리트 타설하고, 강관 근입 압입하며, 기반암 굴착하고 철근망 근압하며, 콘크리트 타설후 2 차 콘크리트 타설하고, 인공 어초를 설치한 것을 그 특징으로 한다.In order to achieve the above object, the present invention, by dropping and casing the caisson to bind the assembly caisson and dredging the inside of the weathered rock using the cram shell bucket, and then install the jacket with the guide steel pipe attached and poured the concrete underwater Configured to integrate; Drop the concrete structure of the assembled caisson on the sea floor, dredge the inner area of the caisson assembly using the cramshell bucket and sand pump, immerse the jacket, then pour the primary concrete, press-fit the steel pipe, excavate the bedrock and reinforce the It is characterized by the fact that the net pressure, after the concrete is poured secondary concrete, and installed artificial reefs.

이상 설명한 바와 같이 본 발명에 의하면, 하저 또는 해저면에 교각 기초 부분(Footing)을 간편히 설치할 수 있으며, 강관 근입 및 알시디(RCD)굴착이 용이할 뿐만 아니라 세굴에 따른 함몰을 줄일 수 있는 효과가 있다.As described above, according to the present invention, the pier foundation can be easily installed on the bottom or the bottom of the seabed, and the steel pipe indentation and Alcidi (RCD) excavation can be easily performed, and the effect of reducing the scour caused by the scour can be reduced. have.

도 1 은 본 발명의 실시예에 관한 조립케이슨 및 쟈켓을 이용한 RCD 공법을 설명하기 위한 설치도,
도 2 는 도 1 에 도시된 조립케이슨 및 쟈켓을 나타낸 평면도와 단면도,
도 3 은 현장 타설말뚝에서 알시디(RCD)공법의 작업순서도이다.
1 is an installation diagram for explaining the RCD method using the assembly caisson and jacket according to an embodiment of the present invention,
2 is a plan view and a cross-sectional view showing the assembly caisson and jacket shown in FIG.
Figure 3 is a flow chart of the work of Alcidi (RCD) method in the site of the pile.

본 발명의 바람직한 실시예를 예시도면에 의거하여 상세히 설명한다.Preferred embodiments of the present invention will be described in detail with reference to the drawings.

도 1 은 본 발명의 실시예에 관한 조립케이슨 및 쟈켓을 이용한 RCD 공법을 설명하기 위한 설치도이다. 도 2 는 도 1 에 도시된 조립케이슨 및 쟈켓을 나타낸 평면도와 단면도이고, 도 3 은 현장 타설말뚝에서 알시디(RCD)공법의 작업순서도이다.1 is an installation diagram for explaining the RCD method using the assembly caisson and jacket according to an embodiment of the present invention. Figure 2 is a plan view and a cross-sectional view showing the assembly caisson and jacket shown in Figure 1, Figure 3 is a work flow chart of the Alcidi (RCD) method in the site-pouring pile.

본 발명은 하상 및 해상에서 이루어지는 교량공사중 기초 시공 부분과 해상 연약지반을 치환 보강하는 시공공법으로, 현장타설말뚝 공사시 발생하는 여러 가지의 문제점을 직접 기초방식과 케이슨 공법의 플로팅(Floating) 타입의 장점을 발췌 도입하여 알시디(RCD)를 사용함과 시공방법을 달리하여 각 공법들의 제약 요건들을 취합 보완함으로써 목적물의 구조적인 안정성 증대와 시간적, 경제적인 절감을 도모할 수 있는 조립케이슨 및 쟈켓을 이용한 알시디(RCD)공법인 것이다.The present invention is a construction method that replaces and reinforces the foundation construction part and the marine soft ground in the bridge construction made in the seabed and the sea, and solves the various problems that occur during the construction of the cast-in-place pile. By using the introduction of Alcidi (RCD) by extracting the merits, and using the assembly caisson and jacket that can improve the structural stability of the target and save time and economics by collecting and supplementing the constraints of each method by changing the construction method. Alcidi (RCD) method.

도 1 에 도시된 바와 같이, 본 발명의 시공 방법으로서는 케이슨을 투하 연하여 조립케이슨(10)으로 결속하고 그 내부를 크람쉘 버켓을 사용하여 풍화암상단까지 준설한다. 그 후에 유도강관(33)이 부착된 철재류 쟈켓(15)을 설치하고, 수중 콘크리트 타설(37)하여 일체화시킨다. 그러므로, 교각의 푸팅 역할과 기능을 증대시키고, 강관 근입시 오차의 범위를 줄이므로 작업의 안정성을 확보하여 시간적이고 경제적 절감을 기할 수 있다.As shown in Figure 1, in the construction method of the present invention by dropping the caisson to bind to the assembly caisson 10, the inside of the dredging to the upper weathered rock using the cram shell bucket. After that, the steel jacket 15 to which the guide steel pipe 33 is attached is installed, and the water concrete pouring 37 is integrated. Therefore, it increases the role and function of the footing of the piers, and reduces the range of errors in the inductance of the steel pipe, thereby securing time stability and saving time.

유도 강관(33)의 상부에는 구멍을 내어 붓싱 로울러(36)를 부착하여 근입강관(31)을 근입할 때 견인 크레인의 부하를 감소시킨다. 그 상부 용접 고리(32)는 설치 완료 후 제거한다. 바지선(20)의 크레인으로부터 와이어로프(35)가 유도강관(33)의 견인 구멍(34)에 체결되고, 상기 유도강관(33)은 해저면내에 점선만큼 RCD 굴착깊이(38)가 들어가게 된다.A hole in the upper portion of the guide steel pipe 33 is attached to the bushing roller 36 to reduce the load of the traction crane when entering the inlet steel pipe 31. The upper welding ring 32 is removed after the installation is completed. The wire rope 35 is fastened from the crane of the barge 20 to the traction hole 34 of the guide steel pipe 33, and the guide steel pipe 33 enters the RCD drilling depth 38 by a dotted line in the sea bottom.

도 2 에 도시된 조립케이슨(10)을 제작함에 있어, 기존의 케이슨은 그 규모 자체가 크고 그 구조상 형틀이 손괴되지 않고 유지하기 위해 격벽이 필요 불가결하므로, 작업상 공간의 제약등 여러 가지의 애로 사항이 상존한다, 그 높이 또한 공법의 특성상 상단 높이 또한 수면보다 높아야 하므로 심도가 깊은 지역에서는 설치가 불가능 하다. 이에 물속에 설치할 수 있으며, 규모를 축소화해서 제작과 운반, 설치가 용이한 조립식으로 한다.In manufacturing the assembly caisson 10 shown in Figure 2, the existing caisson is large in size itself and its structural form is indispensable to maintain the bulkhead, it is indispensable for various difficulties, such as constraints of the working space. It is impossible to install in deep areas because its height must also be higher than the surface due to the nature of the process. Therefore, it can be installed in the water, and the scale is reduced to make it easy to manufacture, transport and install.

도 2 에 도시된 쟈켓(15)의 제작 및 설치함에 있어, 강관 근입, 굴착시 나타나는 여러 가지의 자연 현상의 제약 조건을 극복하기 위해 해저면에 시공 거점을 확보하기 위해 강관을 유도 근입시키기 위한 장치와 이를 지지하기 위한 철재 조립물을 제작 설치할 수 있다. 조립체내의 수중 콘크리트 타설은 케이슨형태의 축소에 따른 그 기능상 효과를 충족시키기 위해 자중을 늘림으로써 파력의 영향력을 제거할 수 있다.In manufacturing and installing the jacket 15 shown in FIG. 2, the apparatus for inducing and inducing the steel pipe to secure the construction base on the sea floor in order to overcome the constraints of various natural phenomena which appear during the steel pipe ingress and excavation And steel assembly to support it can be manufactured and installed. Underwater concrete placement in an assembly can eliminate the effects of wave forces by increasing its own weight to meet its functional effects of shrinking caissons.

도 2(a)는 조립케이슨(10)의 평면도로서 연결부분(a)에 숫케이슨(12)와 암케이슨(14)이 체결되고 모서리케이슨(13)도 체결되며, 도 2(b)는 조립케이슨(10)의 단면도로서 상부경사면(19)이 형성되게 된다. 도 2(c)(d)는 연결시 숫케이슨(12)으로써 원형구멍(16)을 중심으로 4 개의 고리(17)와 수중발신기(18)가 형성되면서 좌우 연결부(m)가 형성된다.Figure 2 (a) is a plan view of the assembly caisson 10, the male caisson 12 and the female caisson 14 is fastened to the connection portion (a) and the corner caisson 13 is also fastened, Figure 2 (b) is assembled An upper sloped surface 19 is formed as a sectional view of the caisson 10. Figure 2 (c) (d) is a male caisson 12 at the time of the connection to the four holes 17 and the underwater transmitter 18 around the circular hole 16 is formed, the left and right connecting portion (m) is formed.

도 2(e)는 쟈켓(15)으로 4 개의 유도강관(33)을 다수의 H 비임(101)과 지지대(102)를 이용하여 고정시키고 간격유지 연결철판(103)이 사면에 설치되어 있다. 도 6(f)는 쟈켓(15)의 단면으로 상기 유도강관(33)에 근입 강관(31)이 유입되어 있다.Figure 2 (e) is a jacket 15 to fix the four guided steel pipes 33 using a plurality of H beams 101 and the support 102 and the spacing connecting connecting plate 103 is installed on the slope. 6 (f) is a cross section of the jacket 15, the inlet steel pipe 31 is introduced into the guide steel pipe 33.

현장타설 말뚝공법에서 RCD공법의 작업순서도로서, 도 3(a)는 강관 근입 과정이고, 도 3(b)는 바이브로 햄머 작업과정이며, 도 3(c)는 RCD 작업과정이고, 도 3(d)는 철근망 근입과정이며, 도 3(e)는 트레미 파이프 조립과정이고, 도 3(f)는 콘크리트 타설과정인 것이다.As the work flow chart of the RCD method in the cast-in-place method, Figure 3 (a) is a steel pipe indentation process, Figure 3 (b) is a Vibro hammer work process, Figure 3 (c) is an RCD work process, Figure 3 ( d) is a rebar network entry process, Figure 3 (e) is a tremi pipe assembly process, Figure 3 (f) is a concrete pouring process.

상기 현장타설 말뚝공법의 RCD 공법을 작업하는 순서를 살펴보면, 도 3(a)에 도시된 바와 같이 측량지점에 용접 연결된 근입 강관(31)을 짹업 바지선(40)의 상부에 설치된 해수면의 가이드 프레임(30)을 이용한다.Looking at the order of working the RCD method of the cast-in-place pile method, as shown in Figure 3 (a) is a guide frame of the sea level installed in the upper part of the steel pipe 31 welded to the survey point on the tweeter barge 40 ( 30).

도 3(b)에 도시된 바와 같이 짹업 바지선(40)에서 크레인으로 바이브로 햄머(42)를 장착 강관을 물고 해저면의 압입한다. 상기 바이브로 햄머(42)를 내려놓고 햄머 그래브로 토사층까지 굴착한다.As shown in FIG. 3 (b), the vibrating hammer 42 is fitted with a vibro hammer 42 by a crane in the trough barge 40 and press-fits the bottom of the seabed. The hammer 42 is put down by the vibro and excavated to the soil layer with a hammer grab.

이때 암반이 출현하면, 도 3(c)에 도시된 바와 같이 RCD(43)를 강관 상단에 셋팅하여 소정의 깊이까지 굴착 작업을 진행한다. 여기서, 상기 RCD의 굴착비트(44)를 사용하게 된다.At this time, when the rock appears, as shown in Figure 3 (c) is set to the top of the steel pipe RCD (43) proceeds the excavation work to a predetermined depth. Here, the drilling bit 44 of the RCD is used.

굴착 작업이 끝나면 RCD(43)를 해체하고, 도 3(d)에 도시된 바와 같이 조립된 철근망(45)을 근입시킨다. 이어 도 3(e)에 도시된 바와 같이 트레미 파이프(46)를 조립 설치한다. 이후 수중콘크리트 타설을 위해 트레미 파이프(46)를 이용하여 콘크리트 타설(도 3(f) 참조)을 소정의 높이까지 타설한다.After the excavation work, the RCD 43 is dismantled, and the assembled reinforcing bar 45 as shown in FIG. Subsequently, the tremi pipe 46 is assembled and installed as shown in FIG. Thereafter, the concrete placing (see FIG. 3 (f)) is poured to a predetermined height using the tremi pipe 46 for underwater concrete placement.

이상 설명한 바와 같이 도 1 내지 도 3 에 의거하여 본 발명의 조립케이슨 및 쟈켓을 이용한 RCD 공법을 설명하면 다음과 같다.As described above, the RCD method using the assembled caisson and the jacket of the present invention will be described with reference to FIGS. 1 to 3 as follows.

첫째, 조립케이슨(10)의 콘크리트 구조물을 해저면에 투하한다.First, the concrete structure of the assembly caisson 10 is dropped on the sea bottom.

조립케이슨을 설치하는 것은 길이가 제일 큰 케이슨을 우선순위로 한쪽 면부터 완성한 후 양쪽으로 번갈아가면서 계속해서 조립하며, 마지막에는 제일 먼저 설치한 그 반대편 것의 순서로 한다. 연결 작업을 원활하게하기 위하여 연결 부위, 즉 암숫 케이슨의 접촉 부분에는 목재를 부착하여야 한다. 이때 측량은 케이슨 조립체의 양 모서리에 부착되어 있는 수중발신기(18)와 저주파 소나 영상장치를 이용하여 DGPS 미세 조정할 수 있다.Installation of the assembly caisson is done by completing the largest caisson in order of priority from one side and then alternately on both sides, and finally in the order of the opposite installation first. Woodwork should be attached to the joint, ie the female caisson contact, to facilitate the joining process. At this time, the measurement can be fine-tuned DGPS using the underwater transmitter 18 and the low frequency sonar imaging apparatus attached to both corners of the caisson assembly.

도 2(c)(d)에 도시된 고리를 통하여 마심 와이어로프로 각 케이슨 조립체를 연하여 결속하고, 마지막 연결부분은 와이어 소켓으로 마감처리한다. 저면의 평탄함을 유지할 필요가 있을 때에는 대형 모래 마대를 이용해서, 그 크기와 양에 따라 속 채움양을 조절하여 채운다.Each caisson assembly is connected and tied with a coring wire rope through the loop shown in FIG. 2 (c) (d), and the last connection is finished with a wire socket. When it is necessary to keep the bottom flat, use a large sand spigot and adjust the filling amount according to its size and quantity.

둘째는 크람쉘 버켓과 샌드 펌프를 사용하여 케이슨 조립체의 내부 구역을 준설한다. 이는 풍화암(사암)층 상단 혹은 기반암 상단까지 준설한다.Second, dredging the interior area of the caisson assembly using a cramshell bucket and a sand pump. It dredges to the top of weathered rock (sandstone) layer or to the top of bedrock.

셋째는 쟈켓(15)을 침설한다. 상기 쟈켓의 형틀은 H 비임(예컨대 300*300*9*12), 보강재는 ㄱ형강(Angle : 90*90*6)로 제작하며, 그 속에 다수의 유도강관을 설치한다. 상기 유도강관의 직경은 근입강관의 직경보다 300m/m큰 구경으로 사용한다. 높이는 1.5D(D=직경)이상이어야 한다.Third, immerse the jacket (15). The frame of the jacket is made of H beam (eg 300 * 300 * 9 * 12), the reinforcement is made of a-beam (Angle: 90 * 90 * 6), and a plurality of induction steel pipes are installed therein. The diameter of the induction steel pipe is used with a diameter of 300m / m larger than the diameter of the near entrance steel pipe. The height must be at least 1.5D (D = diameter).

상기 쟈켓의 크기는 케이슨 조립체 내부의 폭 보다 가로, 세로 300m/m 적게 제작한다. 도 2 에 도시된 바와 같이, 형틀 상단 각 변 마다 2개소 씩 간격 유지용 철판을 댈 수 있게끔 구멍을 내며, 각 변 모서리 에는 제작된 철근망을 덮어 조립할 수 있게끔 지지대를 만든다. 유도 강관의 하부는 콘크리트 타설시 유입되지 않도록 폴리에틸렌 재질을 사용한 보호막을 부착하며, 상부에는 근입 강관 설치시 용이하게 하기 위하여 구멍을 내며 도 1 과 같이 붓싱 로울러를 부착한다.The size of the jacket is made 300m / m less than the width of the inside of the caisson assembly. As shown in Figure 2, each hole in the upper side of the mold to make a hole to hold the spacing plate for two places, each side edge is made to support the assembly so as to cover the fabricated rebar mesh. The lower part of the induction steel pipe is attached with a protective film using a polyethylene material so that it does not flow in the concrete pouring, the upper part is attached to the bushing roller as shown in Fig.

넷째는 유도 강관의 근입이다. 도 1 과 같이 견인 크레인을 사용하여 강관을 설치한다. 용접된 고리의 높이는 유도 강관 보다 500 m/m이상 높게 설치되어야 하며, 설치후 제거한다. 1차 콘크리트 타설이다. 각 케이슨 조립체간의 유동을 막기 위해 트레미 파이프를 이용하여 수중 콘크리트로 타설한다. 타설 높이는 조립식 케이슨의 1/3지점까지한다.Fourth is the induction of induction steel pipe. Install the steel pipe using a traction crane as shown in FIG. The height of the welded ring shall be installed at least 500 m / m higher than the guided steel pipe and removed after installation. Primary concrete pouring. In order to prevent the flow between each caisson assembly, it is poured into underwater concrete using Tremi pipe. The pouring height is up to one third of the prefabricated caisson.

다섯째는 1차 콘크리트 타설이다. 각 케이슨 조립체간의 유동을 막기 위해 트레미 파이프를 이용하여 수중 콘크리트로 타설한다. 타설 높이는 조립식 케이슨의 1/3지점까지한다.Fifth is the primary concrete pouring. In order to prevent the flow between each caisson assembly, it is poured into underwater concrete using Tremi pipe. The pouring height is up to one third of the prefabricated caisson.

여섯째는 강관 압입이다. 도 3 과 같이 바이브로 햄머와 햄머 그렙을 사용하여 기반암 상단 출현시까지 반복하여 굴착 압입한다.Sixth is steel pipe indentation. As shown in Figure 3 using a vibro hammer and hammer grep is repeatedly excavated indentation until the top of the bedrock appeared.

일곱째는 기반암 굴착이다. RCD를 장착하여 소정의 깊이까지 기반암을 갈아낸다.Seventh is bedrock excavation. The RCD is mounted to grind the bedrock to a predetermined depth.

여덟째는 철근망 근입이다. 지상에서 조립된 철근망을 설치한다.Eighth is the reinforcement network. Install rebar network assembled from the ground.

아홉째는 콘크리트 타설로서 트레미 파이프를 이용 원하는 높이까지 타설한다.Ninth is concrete pouring, using the Tremi pipe to the desired height.

열째는 2차 콘크리트 타설이다. 즉 조립식 케이슨 상단 높이까지 타설한다. 이때 유도 강관과 근입 강관 사이의 빈 공간도 속 채움한다. 콘크리트가 조립체 연결 부위를 통하여 외부로 유출되는 것은 구조상 요철 형태로 되어 있고, 콘크리트의 골재 규격의 특성상 방지된다.The tenth is secondary concrete pouring. That is, to the top of the prefabricated caisson. At this time, the empty space between the guided steel pipe and the adjacent steel pipe is also filled. The outflow of concrete to the outside through the assembly connection portion is in the form of uneven structure, and is prevented due to the characteristics of the aggregate specification of the concrete.

구역내 지층 상태로 인하여 쟈켓의 설치지점이 정도 이상으로 낮아 졌을 경우, 도 3 과 같이 보강용 철근망을 덮어 조립 타설할 수 있도록 한다. 상부면의 마감 처리는 수중 바이브레이타를 사용하여 콘크리트내의 공기 함유율을 낮추고 충진시켜 균일하게 면 처리를 한다.When the installation point of the jacket is lowered by about more than the ground due to the state of the stratum in the zone, as shown in FIG. The finishing of the upper surface is done by lowering and filling the air content in the concrete using an underwater vibrator to uniformly treat the surface.

열한번째는 인공 어초를 설치한다. 상기 인공 어초를 수면위까지 해상에서 육안으로 식별할 수 있는 높이까지 설치한다.Eleventh installs artificial reefs. The artificial reefs are installed up to the level above the surface of the water so that the naked eye can identify them.

이상 설명한 바와 같이 본 발명은 강관 근입 및 RCD굴착의 용이하다. 즉, 강관 근입시 패류충 다음 암반이 곧 바로 노출되거나 조류가 센 지역에서는 물속에 접촉된 강관의 그 단면적에 따른 부력과 그 하중으로 인하여 작업 바지선 상부에 설치되어 있는 가이드 프레임이 과도한 부하를 받게 되어 안착 지점의 조정 자체가 어려운 실정이며, 강관의 구경이 클수록 비례한다. 사항 근입일 경우 그 정도는 더 심하다.As described above, the present invention facilitates steel pipe intrusion and RCD excavation. In other words, in the area where the shellfish is exposed immediately after invading the steel pipe or in the area where the tide is high, the guide frame installed on the work barge is subjected to excessive load due to the buoyancy and the load according to the cross-sectional area of the steel pipe in contact with the water. The adjustment of the seating point itself is difficult, and the larger the diameter of the steel pipe is proportional. It's even worse when it comes to getting involved.

이에 따른 보완책으로 핀 파일을 부착한 가이드 프레임을 제작 운용하나 그 조차도 핀 파일이 완전히 근입되지 못한 상황에서 작업을 시행하나, 이 또한 조류가 센 지역에서는 핀파일 고리가 찢겨져 나가는 현상이 발생 하고 있다. 설혹 안착이 됐다 하더라도 바이브로 햄머를 장착, 요동 압입을 시도하는 동안 비끌어 지는 경우가 비일 비재 하다.As a countermeasure, a guide frame with a pin pile is manufactured and operated, but even the pin pile is not fully entered. However, the pin pile ring is torn in the tide region. Even if it is settled down, it is unusual to be dragged while attempting to insert a vibratory hammer and swing indentation.

때문에 최초 측량 지점에서 이탈, 짹업 바지선의 렉(Leg)을 올려서 다시 셋팅을 해야 한다. 같은 작업을 수 없이 반복해야 하므로 많은 시간이 소비 된다. 굴착시의 장점은 안착지점 주변의 공극률이 큰 각종 토사층 및 여타 침전물을 제거 하고, 균일한 매질의 콘크리트로 주변을 감싸고 있기 때문에 압밀효과를 증가 시키므로, 강관내의 압력을 감소시켜 누압 현상이 생기지 않아 굴착 작업의 효율을 증가시킨다.Therefore, it is necessary to lift and reset the leg of the tweet-up barge from the initial survey point. This can be a lot of time because the same task must be repeated many times. The advantage of the excavation is that it removes various soil layers and other sediments with large porosity around the seating point and wraps the surroundings with concrete of uniform media, which increases the consolidation effect. Increase the efficiency of work.

또한 강관 근입시는 기상 상태가 좋아야 하며, 그 작업이 선행되지 않으면 후속 작업이 이루어지지 않으므로 대기 하는 동안 시간적, 경제적인 손실은 막대하다. 이에 해저면에 기점을 설정 구조물을 미리 설치함으로써 허용오차 범위내에서 시공을 할 수 있어 품질의 향상을 기할 수 있으며, 파랑의 영향을 받지 않고 작업을 함으로 공기를 줄일 수 있다.In addition, the weather conditions should be good when entering the steel pipe, and if the work is not preceded, no subsequent work is performed, so the time and economic loss during the waiting time is enormous. Therefore, by installing the structure to set the starting point on the sea floor in advance, the construction can be performed within the tolerance range, and the quality can be improved, and the air can be reduced by working without being affected by the blue.

본 발명은 세굴에 따른 함몰을 줄일 수 있다. 즉, 지지층 하수 및 해류에 대응하는 단면적을 확대함으로 말뚝 기초공의 필연적으로 따르는 세굴심의 깊이를 상쇄함과 교각 주위를 돌아 흐르는 해류의 접근 각도를 둔화 시키고, 와류의 집중력을 감쇄 시켜 단면 축소 세굴, 국부 세굴을 방지할 수 있다.The present invention can reduce depression due to scour. In other words, by increasing the cross-sectional area corresponding to the sewer and current of the support layer, the depth of scour depth inevitably followed by pile foundation holes is canceled, and the approach angle of the currents flowing around the piers is slowed, and the concentration of the vortices is reduced to reduce the concentration of vortices. Scour can be prevented.

10 : 조립케이슨
12 : 숫케이슨
13 : 모서리 케이슨
14 : 암케이슨
15 : 쟈켓
16 : 원형구멍
17 : 고리
18 : 수중발신기
19 : 경사면
20 : 바지선
30 : 가이드 프레임
31 : 근입강관
32 : 연결고리
33 : 유도강관
34 : 원형구멍
36 : 붓싱로울러
38 : RCD 굴착
40 : 짹업 바지선
42 : 바이브로 햄머
43 : R.C.D.
44 : R.C.D.비트
45 : 철근망
46 : 트레미 파이프
47 : 콘크리트 타설
101 : H-비임
102 : 앵글(ㄱ형강)
103 : 연결철판
10: assembly caisson
12: male caisson
13: corner caisson
14: cancer caisson
15: jacket
16: round hole
17: ring
18: underwater transmitter
19: slope
20: barge
30: guide frame
31: near-mouth steel pipe
32: link
33: induction steel pipe
34: round hole
36: bushing roller
38: RCD excavation
40: Tit-Up Barge
42: Vibro Hammer
43: RCD
44: RCD bit
45: rebar network
46: tremi pipe
47: concrete pouring
101: H-beam
102: angle (a section steel)
103: connecting iron plate

Claims (1)

케이슨을 투하 연하여 조립케이슨으로 결속하고 그 내부를 크람쉘 버켓을 사용하여 연암상단까지 준설하며, 그 후에 유도강관이 부착된 쟈켓을 설치하고 수중 콘크리트 타설하여 일체화시키도록 구성하되;
조립케이슨의 콘크리트 구조물을 해저면에 투하하고, 크람쉘 버켓과 샌드 펌프를 사용하여 케이슨 조립체의 내부 구역을 준설하며, 쟈켓을 침설한 다음 1 차 콘크리트 타설하고, 유도 강관 근입한 다음 강관 압입하며, 기반암 굴착하고 철근망 근압하며, 콘크리트 타설후 2 차 콘크리트 타설하고, 인공 어초를 설치한 것을 특징으로 하는 조립케이슨 및 쟈켓을 이용한 알시디(RCD)공법.
Caisson dropping and binding to the assembly caisson and the inside of the dredging to the upper end of the soft rock using the cramshell bucket, after which the jacket with the guide steel pipe is installed, and it is configured to be integrated by pouring concrete under water;
Drop the concrete structure of the assembled caisson on the sea floor, dredge the inner area of the caisson assembly using the cramshell bucket and sand pump, immerse the jacket and pour the primary concrete, intrude the induction steel pipe and press in the steel pipe, Alcidi (RCD) method using assembling caisson and jacket, characterized in that the foundation rock excavation, reinforcing the reinforcing bar network, and after the concrete is poured secondary concrete, and installed artificial reefs.
KR1020100074478A 2010-08-02 2010-08-02 Reverse Drill Method With precast type Caisson and Jacket KR101256274B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100074478A KR101256274B1 (en) 2010-08-02 2010-08-02 Reverse Drill Method With precast type Caisson and Jacket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100074478A KR101256274B1 (en) 2010-08-02 2010-08-02 Reverse Drill Method With precast type Caisson and Jacket

Publications (2)

Publication Number Publication Date
KR20120012503A true KR20120012503A (en) 2012-02-10
KR101256274B1 KR101256274B1 (en) 2013-04-18

Family

ID=45836364

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100074478A KR101256274B1 (en) 2010-08-02 2010-08-02 Reverse Drill Method With precast type Caisson and Jacket

Country Status (1)

Country Link
KR (1) KR101256274B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101236542B1 (en) * 2012-06-08 2013-02-22 삼보이엔씨 주식회사 Method for piling works using self jig jacket pileframe

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101650231B1 (en) 2014-03-24 2016-08-22 김상훈 Construction structures with wave power generator of semipermeable breakwater
KR101650232B1 (en) 2014-03-24 2016-08-22 김상훈 Semipermeable breakwater of combined power generation facility
KR20160080028A (en) 2014-12-29 2016-07-07 김상훈 Multipurpose artifical island
CN106320187A (en) * 2016-10-27 2017-01-11 朱育盼 Bridge construction method and device for special strata
KR101961319B1 (en) 2018-12-21 2019-03-25 한국건설기술연구원 Construction Method for Base Piles using Steel Pipe Casing Withdraw and Suction-type Cofferdam

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001342640A (en) 2000-06-01 2001-12-14 Kajima Corp Construction method for underground structure below water bottom and underground structure below water bottom
JP3735273B2 (en) 2001-06-07 2006-01-18 三菱重工業株式会社 How to install underwater foundation
KR100556302B1 (en) * 2004-04-02 2006-03-07 (주) 선암기술연구소 Caisson Installed Support Means and Construction Method of Underwater Structure Using It
KR100819624B1 (en) * 2006-03-03 2008-04-04 정혜진 Waterproof open caisson assembly and concrete foundation construction method using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101236542B1 (en) * 2012-06-08 2013-02-22 삼보이엔씨 주식회사 Method for piling works using self jig jacket pileframe

Also Published As

Publication number Publication date
KR101256274B1 (en) 2013-04-18

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
KR101211811B1 (en) Cast in concrete pile With precast type Caisson
KR102011321B1 (en) Construction method of foundation using rectangular pipe and its foundation
KR100819624B1 (en) Waterproof open caisson assembly and concrete foundation construction method using the same
WO2015135471A1 (en) Hollow cylindrical pier for fixing offshore platform structure to bed and method of installing and constructing same
KR101256274B1 (en) Reverse Drill Method With precast type Caisson and Jacket
CN104452829A (en) Piled raft foundation anti-floating structure and construction method
CN102561371A (en) Steel caisson enclosure structure at island-tunnel combination part
CN106869138A (en) A kind of load retaining wall Retaining Structure with Double-row Piles and its foundation ditch excavation method
CN102561379A (en) Novel bridge installation foundation and construction method thereof
JP3423394B2 (en) Underwater frame structure
CN102733407A (en) Two-ring grouted single pile foundation
CN101392521A (en) Rock-socketed steel dock structure and construction method thereof
KR20010096389A (en) Construction Method of Direct Foundation for using Caisson
WO2016109962A1 (en) Construction method for fixing offshore marine platform to a seabed having layers of a soil/clay nature
CN109518674B (en) Artificial island segment, assembled artificial island and construction method of assembled artificial island
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
KR20200014531A (en) Fixed anchor construction method of marine structure
KR100931918B1 (en) Underwater tunnelling method for using inner and outer water pressure of structure
JP2726611B2 (en) How to set up an open caisson
KR20020081530A (en) Well form for the base operation of pier and it's operation method
KR20150105891A (en) The underground facilities for offshore airfield of semi land reclamation type
CN106049516A (en) Corrugated steel cofferdam hollow digging pile and manufacturing technique thereof
KR20210047481A (en) Core wall structure of composite cassion for offshore runway
KR20120012502A (en) Cast in place concrete pile With precast type Caisson

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160211

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170404

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20180323

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20190329

Year of fee payment: 7