KR20210047481A - Core wall structure of composite cassion for offshore runway - Google Patents

Core wall structure of composite cassion for offshore runway Download PDF

Info

Publication number
KR20210047481A
KR20210047481A KR1020190131126A KR20190131126A KR20210047481A KR 20210047481 A KR20210047481 A KR 20210047481A KR 1020190131126 A KR1020190131126 A KR 1020190131126A KR 20190131126 A KR20190131126 A KR 20190131126A KR 20210047481 A KR20210047481 A KR 20210047481A
Authority
KR
South Korea
Prior art keywords
caisson
composite
wall
runway
core
Prior art date
Application number
KR1020190131126A
Other languages
Korean (ko)
Other versions
KR102294870B1 (en
Inventor
김상훈
Original Assignee
김상훈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김상훈 filed Critical 김상훈
Priority to KR1020190131126A priority Critical patent/KR102294870B1/en
Publication of KR20210047481A publication Critical patent/KR20210047481A/en
Application granted granted Critical
Publication of KR102294870B1 publication Critical patent/KR102294870B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D25/00Joining caissons, sinkers, or other units to each other under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Abstract

The present invention relates to the construction of an offshore runway, which can install a support pillar that prevents scouring, and install the support pillar in a grid type in an area except where the support pillar is installed and then install the runway, which is a top plate, thereon. Accordingly, fatigue of the support pillar can be reduced to secure structural stability.

Description

해상활주로용 복합케이슨의 코어(core)벽체 구조물{CORE WALL STRUCTURE OF COMPOSITE CASSION FOR OFFSHORE RUNWAY}Core wall structure of composite caisson for offshore runway {CORE WALL STRUCTURE OF COMPOSITE CASSION FOR OFFSHORE RUNWAY}

본 발명은 해상비행장의 활주로를 설치함에 있어 수심이 깊어 박스형 케이슨을 침설하기가 곤란한 지역에서 교각식 구조를 적용하여 수중 및 해상에서 설치가 용이한 것으로서, 벽식구조로 독립된 코어(core)로 제작, 설치가 용이한 연결형 블럭을 연결하여 단계별 블럭을 만들고 단계별 블럭을 적층, 결합하여 결합형 블럭을 형성하고 지주기둥과 수중연속벽을 타설하여 복합케이슨 벽체구조물을 만들어 구조물지지대를 조성하고 복합케이슨간을 연결하는 공법이며, 라멘구조방식으로 기둥과 보,슬래브를 강접한 라멘구조방식으로 해상활주로를 설치하는 것으로 연약지반에 의한 부등침하를 예방할 수 있으며, 매립식으로 축조된 계류장과 연결이 용이하며 각종 환경외력에 대응력이 우수한 해상활주로의 건설에 관한 것이다.The present invention is easy to install underwater and at sea by applying a pier structure in an area where it is difficult to submerge a box-type caisson due to a deep depth in installing the runway of a marine aerodrome, and it is manufactured as an independent core with a wall structure, Connect blocks that are easy to install to create step-by-step blocks, stack and combine step-by-step blocks to form a combined block, and place pillars and underwater continuous walls to create a composite caisson wall structure to create a structural support, and connect the composite caissons. It is a method of connecting, and by installing an offshore runway with a ramen structure method in which columns, beams, and slabs are strongly connected to each other, it is possible to prevent differential subsidence due to soft ground, and it is easy to connect to the apron built in a buried type. It relates to the construction of an offshore runway with excellent responsiveness to external forces.

항공기의 이착륙 문제로 발생하는 소음과 피해보상 문제는 많은 갈등과 비용이 따르고, 항공수요의 증대와 항공기의 대형화로 인해서 비행장을 확장하거나 증설할 경우 수용지역 보상비와 비행기 이착륙에 따른 비행구역상의 진입, 수평, 원추표면상의 안전을 확보하기 위해서 구역내의 장애물 제거를 위한 비용, 그에 따른 건축물 고도 제한등은 환경훼손 및 여러가지 민원을 야기시키고 있다. 상기와 같은 문제점을 해소할 수 있는 해상비행장의 필연성은 날로 증대되고 있으며, 여객기를 이착륙할 수 있는 공항은 계류장, 정비시설, 여객 및 화물터미널 주차장, 격납고 등 부대시설과 활주로를 구비해야 한다.Noise and damage compensation problems arising from the take-off and landing of the aircraft are accompanied by a lot of conflict and cost, and if the airfield is expanded or expanded due to the increase in air demand and the enlargement of the aircraft, the compensation fee for the receiving area and the entry into the flight area due to the take-off and landing of the plane, In order to ensure the safety on the horizontal and conical surface, the cost for removing obstacles in the area and the consequent restrictions on the height of the building are causing environmental damage and various civil complaints. The necessity of maritime aerodromes that can solve the above problems is increasing day by day, and airports where passenger planes can take off and land should be equipped with an apron, maintenance facilities, passenger and cargo terminal parking lots, hangars, and other auxiliary facilities and runways.

해상활주로는 이륙하는 항공기의 양력을 받기 위해서는 이륙 가용거리가 보장되어야 하며, 해당 공항은 등급에 따라 차이가 있으나, 예컨데 최소 50 인승 여객기를 운용하는 E 등급 이상 공항에서는 이륙하는 항공기의 양력을 받기 위해서 필요한 이륙 가용거리와 착륙대는 이설시단, 블래스트 패드를 포함하여 폭은 최소 45 m, 길이는 1,200 m 이상이 되어야 하며, 평행 착륙시(시계 비행) 활주로간 이격거리는 210m 이상 되어야 한다.In order to receive the lift of an aircraft taking off on a sea runway, the available take-off distance must be guaranteed, and the airport varies depending on the class, but for example, at an E class or higher airport operating a 50-seater passenger aircraft, in order to receive the lift of an aircraft taking off. The required take-off distance and landing pad must be at least 45 m wide and 1,200 m long, including blast pads at the time of relocation and at least 1,200 m long, and at least 210 m between runways when landing in parallel (clockwise flight).

해상 활주로를 조성하는 방법으로는 매립식, 교각식, 부유식 3 가지로 대별되고 있는 바, 먼저 부유식은 구조형식이 간단하고 입지선정의 자유로움이 있는 장점이 있으나, 부체 흘수에 따른 구조물의 제한 등으로 대형항공기의 이착륙은 제한되며 파랑에 의한 요동은 완전히 극복할 수 없는 한계를 지니고 있다. 또한, 부체의 고정을 위한 계류시설과 항공기의 대형화로 구조물의 크기가 확장될 때, 반잠수식으로 전환될 수 밖에 없으며 이에 따른 수제시설인 방파제 건설이 불가피하다.There are three methods of constructing an offshore runway: a reclamation type, a pier type, and a floating type. First, the floating type has the advantage of having a simple structure type and freedom of location selection, but the structure is limited by the draft of the floating body. As such, take-off and landing of large aircraft is limited, and fluctuations caused by waves have limitations that cannot be completely overcome. In addition, when the size of the structure is expanded due to the mooring facility for fixing the floating body and the enlargement of the aircraft, it has no choice but to be converted to a semi-submersible type, and accordingly, the construction of a handcrafted breakwater is inevitable.

그러므로, 해상 비행장을 축조하는 공법으로서 수심 20 m 까지는 매립식이 시공성이 우월하나, 해저면 수심이 깊은 지역에서 매립식으로 진행하기엔 경제성이 결여되고 박스형 케이슨을 설치하기엔 해저면 지형이 부적합한 장소에 매립식으로 축조된 계류장과 연결시공이 가능한 해상활주로를 건설하는 공법이고, 혼성식으로 해저면에 기초사석부를 조성하고 직립재인 박스형 케이슨(통상 20 ~ 40 m)을 설치하는 공법을 채택하고 있다.Therefore, as a method of constructing an offshore aerodrome, a burial type is superior in constructability up to a depth of 20 m, but it is not economical to proceed in a burial type in an area with a deep seafloor, and a burial type in a place where the bottom topography is not suitable for installing a box-type caisson. It is a construction method of constructing an offshore runway that can be connected to an apron built with a method, and a construction method of constructing a foundation stone part on the sea floor in a hybrid type and installing a box-type caisson (usually 20 to 40 m), which is an erect material, is adopted.

박스형 케이슨은 자체하중으로 외력에 저항하므로 해상활주로를 구축하고자 하는 영역의 길이방향을 따라 단위 케이슨을 나란히 연속구조체로 연결하고, 외해로부터 진입하는 수평력에 대응할 수 있도록 파력을 평활화시켜 구조물의 안정성을 확보한다.The box-type caisson resists external force with its own load, so the unit caissons are connected in a continuous structure along the length direction of the area to be built on the offshore runway, and the wave force is smoothed to cope with the horizontal force entering from the open sea to secure the stability of the structure. do.

하지만, 박스형 케이슨 설치구역의 기초사석부에서 부등침하가 일어날 경우, 상기 케이슨은 그 자체가 하나의 강체로 작용하기 때문에 단위 케이슨에 위상차를 가지고 작용하는 파랑에너지는 국부적인 에너지 집중을 일으킬 수 있어, 어떤 부분에 불규칙적인 파력이 집중될 때 연결된 상기 케이슨의 어느 한지점에 응력이 집중되어 인접케이슨이 한쪽으로 밀리면서 인터로킹을 유지하지 못하고 파손되는 현상이 발생한다.However, when differential settlement occurs in the foundation stone part of the box-type caisson installation area, the caisson itself acts as a single rigid body, so the wave energy acting with a phase difference to the unit caisson can cause local energy concentration. When an irregular wave force is concentrated in a certain part, the stress is concentrated at one point of the connected caisson, and the adjacent caisson is pushed to one side, and the phenomenon that the interlocking is not maintained and breakage occurs.

박스형 케이슨은 폭이 25 m, 높이가 35 m 를 초과할 때에는 그 크기와 중량때문에 제작상의 문제와 운반, 진수 및 운용장비에 의한 많은 제약요건들이 상존하므로 그 크기를 초과해서는 설치가 어렵다. 최근 50년 출현빈도 설계 최대 파고치(19.4 m)를 고려하면 수심이 30 m 를 초과하는 지역에서의 설치는 구조물의 높이가 50 m 를 상회해야 한다.When the box-type caisson exceeds 25 m in width and 35 m in height, it is difficult to install beyond the size because there are manufacturing problems and many restrictions due to transportation, launching and operating equipment due to its size and weight. Considering the maximum wave height (19.4 m) of the design frequency of appearance in the last 50 years, the height of the structure must exceed 50 m for installation in areas where the water depth exceeds 30 m.

또한, 넓은 폭과 긴 길이가 요구되는 해상비행장의 활주로 부분에서는 해저면 지형의 경사도가 어느 정도 이상되면 시점과 종점의 단차가 커져서 기초지반부 사석포설량이 증가될 수 밖에 없다. 해안선의 굴곡이 심하거나 요철이 심한 지역이나 활주로 길이방향과 교차되는 방향으로 경사가 져서 등고선이 분포되어 있는 지역에서는 설치가 곤란하다.In addition, in the runway part of a maritime aerodrome that requires a wide width and a long length, if the slope of the seafloor topography is more than a certain degree, the step difference between the starting point and the ending point increases, so that the amount of sandstone laying in the foundation ground is inevitably increased. Installation is difficult in areas with severe curvature or irregularities of the coastline, or in areas where contour lines are distributed because the slope is inclined in the direction crossing the length of the runway.

그렇기 때문에, 해저면 수심이 깊은 구역에서는 기초사석부를 그 높이만큼 높여야 하므로, 평탄함을 유지하기 위한 잡석지정 또는 연약지반 처리를 위한 많은 노력과 비용이 소요된다. 따라서, 해저면에 설치될 구조물의 높이가 50 m 를 초과하는 지역에서 해상활주로를 설치(수심 - 80 m ; 산업잠수부 작업가능 심도)할 수 있는 것으로, 구조물지지대가 집약된 형태로 존재하며 내력적 구조체로서 외곽이 내진벽 역할을 할 수 있으면서 환경외력에 대응할 수 있는 구조체가 필요한 것이다.Therefore, in a deep seafloor area, the foundation stone part must be raised as high as its height, so it takes a lot of effort and cost to designate rubble or treat soft ground to maintain flatness. Therefore, it is possible to install an offshore runway (depth-80 m; possible depth of work by industrial divers) in an area where the height of the structure to be installed on the sea floor exceeds 50 m. As a structure, a structure capable of responding to external environmental forces while the outer periphery can act as a seismic wall is required.

이에 본 발명자는 고층건축물에서 많이 사용하고 있는 코어(core)구조방식으로 사각형태의 다수개로 구성한 복합케이슨 벽체구조물을 수중에서 설치할 수 있는 건설공법을 제공하고자 한다.Accordingly, the inventors of the present invention intend to provide a construction method capable of installing a composite caisson wall structure composed of a plurality of squares in a core structure method widely used in high-rise buildings in water.

이를 테면, 구조물의 높이가 높아지면 기둥과 보의 부재단면이 축하중에 저항할 수 있는 단면이 훨씬 커져야 하는 문제가 발생하므로, 이러한 문제점을 해결하기 위한 구조방식으로 코어벽체 구조방식을 많이 사용하고 있다.For example, as the height of the structure increases, the cross section of the members of the pillars and beams has to be much larger to resist the axis, so the core wall structure method is widely used as a structural method to solve this problem. .

또 공용구간인 엘리베이터, 계단실 등을 기능적으로 한데 묶어 콘크리트 파이프처럼 만든 코어를 형성하고 코어를 중심으로 일정한 간격으로 전단벽을 설치해서 구조물을 확장할 수 있도록 시공하고, 기둥과 보의 라멘구조가 합성되어 상재하중을 감당하는 방식으로 코어에 횡력을 전달하는 부재는 구조물내부의 바닥판 슬래브와 전단벽, 그 위에 설치되는 슬래브로 감당하며 축하중은 기둥과 보를 통하고 수평하중은 하단의 벽체를 타고 내려가 기초사석부로 전달되는 것이다.In addition, the common section elevators and stair rooms are functionally tied together to form a core made of concrete pipes, and shear walls are installed at regular intervals around the core to expand the structure, and the ramen structure of columns and beams is synthesized. The member that transmits the lateral force to the core in a way that handles the overhead load is covered by the slab of the floor plate and the shear wall inside the structure, and the slab installed on it, and the axial load goes through the columns and beams, and the horizontal load goes down along the wall at the bottom to the foundation. It is delivered to the private parts.

본 발명은 상기와 같은 제반 사정을 감안하여 복합케이슨 발명한 것으로, 매립식으로 이루어진 해상비행장에서 계류장과 연결이 용이한 해상활주로 건설임으로 구체적으로 내부가 비어있고, 좌우로 연결할 수 있는 연결형 블럭으로 이루어진 독립케이슨을 병렬로 연결하여 만든 복합케이슨으로 코어(core)벽체구조물을 건설함에 그 목적이 있다.The present invention is a composite caisson invented in consideration of the above circumstances, and is a sea runway construction that is easy to connect with an apron in a burial-type maritime aerodrome. Its purpose is to construct a core wall structure with a composite caisson made by connecting independent caissons in parallel.

본 발명의 다른 목적은, 복합케이슨간을 연결하는 공법임으로 연속보와 슬래브를 사용해서 활주로를 구축하는 시공이고, 해저면 지형이 매립식으로 설치하기에 해저수심이 깊어 경제성이 없고 박스형 케이슨으로 설치하기에 많은 제약요건이 따르는 지형조건에 매립식과 연결, 설치가 가능한 복합케이슨으로 구조물지지대를 구성하는 시공이며, 보와 기둥, 벽식구조로 복합된 코어를 라멘구조로 강접한 복합케이슨 코어 벽체 구조물을 해상에서 설치하는 시공을 제공할 수 있다.Another object of the present invention is to construct a runway using continuous beams and slabs as it is a method of connecting composite caissons, and because the seafloor is installed in a buried type, it is not economical due to the deep sea depth and is installed with a box-type caisson. It is a construction that composes a structure support with a composite caisson that can be embedded, connected, and installed in the terrain conditions subject to many constraints below, and a composite caisson core wall structure in which a composite core composed of beams, columns, and wall structures is bonded to a ramen structure. It can provide construction to be installed at sea.

본 발명의 또 다른 목적은, 복합케이슨을 구축하는 공법임으로 기반암에 접속된 현장타설말뚝과 결합된 확대기초의 하부후팅 마운드부상에 말뚝보강 지지대를 설치하고, 증기 양생된 프리캐스트 콘크리트(precast concrete)로 제작된 박스형으로 연결형 블럭과 칸막이 블럭, 지주기둥이 서로 연결되어 독립형 케이슨이 병렬로 연결된 복합케이슨 형태의 단계별 블럭이 조합되면 단계별 블럭을 3 개씩 적층하여 연결한 결합형 블럭이 조성됨을 제공할 수 있다.Another object of the present invention is to install a pile reinforcement support on the lower hooking mound of the expanded foundation combined with the cast-in-place pile connected to the bedrock as it is a method of constructing a composite caisson, and steam cured precast concrete It can be provided that a combined block is formed by stacking three step-by-step blocks by stacking three step-by-step blocks when step-by-step blocks in the form of a composite caisson that are connected in parallel by connecting blocks, partition blocks, and post columns are connected to each other. have.

본 발명의 또 다른 목적은, 이 결합형 블럭의 곡각부분의 패널존(pannel zone)과 결합형 블럭내의 격자공간에 철근, 콘크리트를 타설하여 지주기둥과 수중연속벽을 조성한 결합형 블럭을 같은 공법으로 시공하고, 복합케이슨 코어벽체 구조물을 만들고 해수면위 9 m ~ 12 m 지점(1 개의 결합형 블럭의 높이)까지 결합하여 복층으로 된 연속보를 설치하며, 각 복합케이슨간을 연속보를 설치한 라멘구조 방식으로 강접하고 그 위에 플랫 슬래브를 설치해서 하부슬래브를 만들어 지하시설 공간으로 사용하고 그 상부에 다시 연속보와 슬래브로 해상활주로를 구축하는 것을 제공할 수 있다.Another object of the present invention is to use the same method of constructing a post column and an underwater continuous wall by placing reinforcing bars and concrete in the panel zone of the curved portion of the combined block and the grid space within the combined block. And construct a composite caisson core wall structure and combine it up to a point 9 m to 12 m above sea level (the height of one combined block) to install a double-layered continuous beam, and a ramen structure in which continuous beams are installed between each composite caisson. It is possible to provide the construction of a sea runway with continuous beams and slabs on the upper part of it by making a lower slab by making a lower slab and using it as an underground facility space by attaching it in a strong manner and installing a flat slab on it.

이를 위한 본 발명은, 경사 급한 곳과 요철이 심한 곳의 해저면 지지층에 확대기초 하부후팅 마운드부를 설치하여 연약지반 생성 소지를 사전에 없애고, 하부후팅 마운드부와 결합된 현장타설말뚝을 기반암에 접속시켜 지진파에 대한 적응력이 좋은 현장타설말뚝의 독립기초 지지와 확대기초로 복합벽체 구조물을 구축하여 세굴발생을 방지하는 지주기둥을 설치하고; 각종 환경외력을 감당할 수 있는 현장타설된 연결형 블럭, 단계별 블럭 및 결합형 블럭으로 형성된 복합벽체 케이슨의 지주기둥 위에 슬래브를 설치하고 내부공간을 확보해서 시설 및 부대공간으로 사용하고, 지주기둥이 설치된 곳을 제외한 구역은 해수가 유통될 수 있게 격자식으로 지주기둥을 설치하며 그위에 상판인 활주로를 설치하며; 해상 활주로 하부슬래브의 적재하중과 고정하중이 보를 통해 모여져서 지주기둥과 복합벽체 케이슨의 코어벽체로 전달되어 제반 축하중은 지주기둥을 타고 내려가 하부후팅 마운드부로 전달되고, 각 부재간 접합을 라멘구조로 강접하여 기둥과 보, 코어벽체가 서로 강하게 결속되어 수평하중을 극복하는 코어벽체를 하부후팅 마운드부와 직결된 벽체구조물의 본벽으로 사용되게 설치하며 상재하중을 분담하여 지주기둥의 피로도를 경감시킴으로 구조적 안정성을 확보한 것을 그 특징으로 한다.The present invention for this purpose is to install an expanded base lower hoisting mount on the sea floor support layer in a steep slope and a place with severe irregularities to eliminate the possibility of generating soft ground in advance, and to connect the cast-in-place pile combined with the lower hoisting mount to the bedrock. By constructing a composite wall structure with an independent foundation support and an expansion foundation of cast-in-place piles with good adaptability to seismic waves, post columns to prevent scouring are installed; A slab is installed on the pillars of the caisson, a composite wall formed of on-site connected blocks that can withstand various external forces, step-by-step blocks and combined blocks, and secured internal space to be used as facilities and auxiliary spaces, and where the pillars are installed. In the area except for, a grid-type pillar is installed to allow seawater to flow, and a runway as a top plate is installed on it; The loading and fixed loads of the lower slab of the offshore runway are collected through the beams and transmitted to the pillars and the core wall of the composite wall caisson. The core wall is installed to be used as the main wall of the wall structure directly connected to the lower hooking mount part as the pillar, beam, and core wall are strongly bonded to each other to overcome the horizontal load, and the overhead load is shared to reduce the fatigue of the pillar column. It is characterized by securing structural stability.

이상 설명한 바와 같이 본 발명에 의하면, 현장타설로 결합된 복합케이슨의 코어벽체로 이루어진 지주기둥이 기반암에 접속되어져 구조적으로 안정되고 격자식으로 설치될 수 있어 투입되는 충진재를 절감할 수 있으며, 조류의 변화를 감소시키고 환경훼손을 경감시킬 수 있는 효과가 있다.As described above, according to the present invention, the pillars made of the core wall of the composite caisson combined by casting on-site are connected to the bedrock, so that they are structurally stable and can be installed in a lattice manner, so that the input filler can be reduced, and It has the effect of reducing change and reducing environmental damage.

본 발명은 수심이 깊은 구역에서도 설치가 가능하므로 해상활주로의 입지선정의 폭이 확대되며, 지주기둥간 연결하는 상부슬래브는 주차장 및 부대시설공간으로 활용할 수 있으며, 그 하부공간은 대규모의 그늘진 어패류 서식장이 형성되어져 인근어장의 소득증대를 기할 수 있어 민원해소에 도움이 된다,Since the present invention can be installed in a deep water area, the width of site selection of the offshore runway is expanded, and the upper slab connecting between the pillars can be used as a parking lot and auxiliary facility space, and the lower space is a large-scale shady fish and shellfish habitat. It is helpful in resolving civil complaints as a market is formed and the income of the nearby fishing grounds can be increased.

본 발명은, 준설, 토공사로 편중되어 있는 해상 매립공정에서 탈피하여 철강산업, 콘크리트산업, 수중 건설장비산업, 로봇, 유무인 잠수정 산업 시장이 동반 성장할 수 있으며, 대수심 현장의 적용 및 응용기술이 발전될 수 있는 교두보를 확보할 수 있을 뿐 아니라, 부가가치가 높은 해양플랜트 산업, 즉 대륙붕 석유 및 개스시추 플랫폼(Platform) 및 심해로의 진출을 위한 저변이 확대되어, 4차 산업의 다양한 분야를 접목시켜 발전시킬수 있는 가능성이 충분하다.In the present invention, the steel industry, concrete industry, underwater construction equipment industry, robots, and submersible industry markets can grow together by breaking away from the offshore reclamation process, which is concentrated in dredging and earthworks, and the application and application technology of deep water sites are In addition to securing a bridgehead that can be developed, the offshore plant industry with high added value, i.e., the continental shelf oil and gas drilling platform, and the base for advancing into the deep sea are expanded, combining various fields of the 4th industry. There is enough possibility to develop it by doing it.

도 1 은 본 발명의 실시예에 따른 매립식과 연결된 복합케이슨 코어벽체 구조물의 해상활주로를 설명하기 위한 사시도,
도 2 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물을 이용한 해상활주로의 평면도,
도 3 은 사석경사제와 연결된 정면, 측면 단면도,
도 4 는 사석경사제와 연결된 복합케이슨 활주로 단면도,
도 5 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 하부후팅 조성을 위한 하부후팅용 조립식 케이슨과 그 내부에 들어가는 자켓, 하부후팅 보강용 철근망 사시도,
도 6 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블럭을 연결하는 연결판의 사시도,
도 7 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블럭의 단면도,
도 8 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블럭과 칸막이 블럭의 사시도 및 연결 상세도,
도 9 및 도 10 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 말뚝보강 지지대의 사시도,
도 11 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 패널 존(pannel zone)에 들어가는 지주기둥 보강용 철근망의 사시도,
도 12 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블럭 격자공간내에 들어가는 결합형 블럭 철근망의 사시도,
도 13 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블록과 칸막이 블록, 현장타설말뚝,지주기둥,연결판으로 형성된 단계별 블럭의 평면도,
도 14 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 하부후팅 마운드부로부터 결합형블럭을 연결하는 요약 상세도,
도 15 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 결합형 블럭내에 충진토 투입과 고결화를 위한 그라우팅의 단면도,
도 16 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연속보의 사시도,
도 17 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 P.C 빔과 P.C 판넬의 사시도,
도 18 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 완성된 복합케이슨의 활주로 정면의 단면도,
도 19 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 복합복합케이슨의 활주로 측면의 단면도,
도 20 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 지주기둥과 큰보(연속보), 작은보(P.C 빔), P.C 판넬과 슬래브를 설치하는 상세도이다.
1 is a perspective view for explaining an offshore runway of a composite caisson core wall structure connected to a buried type according to an embodiment of the present invention,
2 is a plan view of an offshore runway using a core wall structure of a composite caisson for offshore runways of the present invention,
3 is a front and side cross-sectional view connected to a serpentine slope,
4 is a cross-sectional view of a composite caisson runway connected to a sandstone slope,
Figure 5 is a perspective view of the prefabricated caisson for lower hooking for the composition of the lower hooking in the core wall structure of the composite caisson for offshore runways of the present invention, a jacket entering the inside, and a reinforcing bar network for reinforcing the lower hooking,
6 is a perspective view of a connecting plate connecting a connecting block in a core wall structure of a composite caisson for an offshore runway of the present invention,
7 is a cross-sectional view of a connecting block in the core wall structure of the composite caisson for an offshore runway of the present invention,
8 is a perspective view and a detailed connection view of a connecting block and a partition block in a core wall structure of a composite caisson for an offshore runway of the present invention,
9 and 10 are perspective views of the pile reinforcement support in the core wall structure of the composite caisson for offshore runways of the present invention,
11 is a perspective view of a reinforcing reinforcing bar network for post columns entering a panel zone in a core wall structure of a composite caisson for an offshore runway of the present invention,
12 is a perspective view of a combined block reinforcing bar network entering a connected block grid space in a core wall structure of a composite caisson for an offshore runway of the present invention;
13 is a plan view of a step-by-step block formed of a connecting block and a partition block, a cast-in-place pile, a pillar, and a connecting plate in the core wall structure of the composite caisson for an offshore runway of the present invention,
FIG. 14 is a detailed summary view for connecting the coupling block from the lower hooking mount part in the core wall structure of the composite caisson for offshore runways of the present invention,
15 is a cross-sectional view of grouting for filling and solidifying filled soil in a combined block in a core wall structure of a composite caisson for an offshore runway of the present invention;
16 is a perspective view of a continuous beam in the core wall structure of the composite caisson for an offshore runway of the present invention,
17 is a perspective view of a PC beam and a PC panel in the core wall structure of the composite caisson for an offshore runway of the present invention,
18 is a cross-sectional view of the runway front of the composite caisson completed in the core wall structure of the composite caisson for offshore runways of the present invention,
19 is a cross-sectional view of the runway side of the composite caisson in the core wall structure of the composite caisson for offshore runways of the present invention,
FIG. 20 is a detailed view of installing pillars, large beams (continuous beams), small beams (PC beams), PC panels and slabs in the core wall structure of the composite caisson for offshore runways of the present invention.

이하, 본 발명의 바람직한 실시예를 예시도면에 의거하여 상세히 설명한다.Hereinafter, a preferred embodiment of the present invention will be described in detail on the basis of exemplary drawings.

도 1 은 본 발명의 실시예에 따른 매립식과 연결된 복합케이슨 코어벽체 구조물의 해상활주로를 설명하기 위한 사시도이고, 도 2 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물을 이용한 해상활주로의 평면도이며, 도 3 은 사석경사제와 연결된 정면, 측면 단면도이고, 도 4 는 사석경사제와 연결된 복합케이슨 활주로 단면도이다.1 is a perspective view for explaining a sea runway of a composite caisson core wall structure connected to a buried type according to an embodiment of the present invention, and FIG. 2 is a sea runway using a core wall structure of a composite caisson for a marine runway of the present invention 3 is a front and side cross-sectional view connected to the serpentine slope, and FIG. 4 is a cross-sectional view of the composite caisson runway connected to the serpentine slope.

도 1 에 도시된 바와 같이, 기초사석부(017)로부터 경사 급한 곳(116)과 요철이 심한 곳(117)의 해저면 지지층에 확대기초 하부후팅 마운드부(104)를 설치하여 연약지반 생성 소지를 사전에 없애는 한편, 상기 하부후팅 마운드부(104)와 결합된 현장타설말뚝(106)을 기반암에 접속시켜 지진파에 대한 적응력이 좋은 현장타설말뚝(106)의 독립기초 지지와 확대기초로 복합벽체 구조물을 구축하여 세굴발생을 방지하는 지주기둥을 설치하고 있다.As shown in Fig. 1, by installing an expanded foundation lower hoisting mound 104 on the sea floor support layer at a steep place 116 and a place 117 with severe irregularities from the foundation stone part 017, it is possible to generate soft ground. While removing in advance, by connecting the cast-in-place pile 106 combined with the lower hooking mount part 104 to the bedrock, the composite wall is used as an independent foundation support and an enlarged foundation for the in-place pile 106, which has good adaptability to seismic waves. By constructing a structure, pillars are installed to prevent scouring.

각종 환경외력을 감당할 수 있는 현장타설된 결합형 블럭으로 형성된 복합벽체 케이슨(105)의 지주기둥 위에 슬래브를 설치하고 내부공간을 확보해서 시설 및 부대공간(108)으로 사용하고(도 3 참조), 상기 지주기둥이 설치된 곳(109)을 제외한 구역(114)은 해수가 유통될 수 있게 격자식으로 지주기둥을 설치하며 그 위에 상판인 해상활주로(101)를 설치하도록 구성되어 있다.A slab is installed on the post column of the composite wall caisson 105 formed of a combined block placed on-site capable of withstanding various external forces, and an internal space is secured to be used as a facility and auxiliary space 108 (see Fig. 3), The area 114 except the place 109 where the pillars are installed is configured to install the pillars in a grid manner so that seawater can be circulated, and to install the marine runway 101 as an upper plate thereon.

도 2 및 도 4 에 도시된 바와 같이, 해상 활주로(101) 하부슬래브의 적재하중과 고정하중이 보를 통해 모여져서 지주기둥과 복합벽체 케이슨(105)의 코어벽체로 전달되어 제반 축하중은 지주기둥을 타고 내려가 하부후팅 마운드부(104)로 전달되고, 각 부재간 접합을 라멘구조로 강접하여 기둥과 보, 코어벽체가 서로 강하게 결속되어 수평하중을 극복하는 코어벽체를 하부후팅 마운드부(104)와 직결된 복합벽체 케이슨(105) 구조물의 본벽으로 사용되게 설치하며, 해상활주로(101) 상재하중을 분담하여 지주기둥의 피로도를 경감시킴으로 구조적 안정성을 확보할 수 있는 것이다.2 and 4, the loading load and the fixed load of the lower slab of the offshore runway 101 are collected through the beams and transmitted to the pillars and the core wall of the composite wall caisson 105, so that the overall axis weight is the pillars. The lower hooking mount part 104 is transferred to the lower hooking mount part 104 by riding down, and the core wall that overcomes the horizontal load by strongly bonding the pillars, beams, and core walls to each other by strongly bonding the joints between the members in a ramen structure. The composite wall caisson 105 directly connected to the caisson 105 is installed to be used as the main wall of the structure, and structural stability can be secured by allocating the overhead load of the offshore runway 101 to reduce the fatigue of the pillars.

그러므로, 본 발명은 해상비행장의 활주로(101)를 설치함에 있어 수심이 깊어 박스형 케이슨을 침설하기가 곤란한 지역에서 교각식 구조를 적용하여 수중 및 해상에서 설치가 용이한 것이다.Therefore, in the present invention, in installing the runway 101 of a marine aerodrome, it is easy to install it underwater and at sea by applying a pier structure in an area where it is difficult to submerge the box-type caisson due to the deep depth of water.

여기서, 벽식구조로 독립된 코어벽체의 복합벽체 케이슨(105)로써 제작, 설치가 용이한 연결형 블럭을 연결하여 단계별 블럭을 만들고 단계별 블럭을 적층, 결합하여 결합형 블럭을 형성시키고 지주기둥(210)과 수중연속벽을 타설하여 복합케이슨 벽체구조물을 만들어 구조물 지지기둥으로 조성하고 복합벽체 케이슨(105)간을 연결하는 공법인 것이다.Here, as a composite wall caisson 105 of an independent core wall in a wall structure, a step-by-step block is made by connecting a connection-type block that is easy to manufacture and install, and a step-by-step block is stacked and combined to form a combined block, and the post column 210 and It is a construction method that creates a composite caisson wall structure by pouring an underwater continuous wall, creates a structure support column, and connects the composite wall caissons (105).

라멘구조 방식으로 기둥과 보, 슬래브를 강접한 라멘구조 방식인 바, 이는 해상활주로(101)를 설치하는 것임으로 연약지반에 의한 부등침하를 예방할 수 있으며, 매립식으로 축조된 계류장(102)과 연결이 용이하며 각종 환경외력에 대응력이 우수한 해상활주로(101)를 건설하는 것이다.It is a ramen structure method in which columns, beams, and slabs are strongly connected to each other in a ramen structure method. This is to install an offshore runway 101 to prevent differential settlement due to soft ground. It is to build a marine runway 101 that is easy to connect and has excellent response to various external forces.

상기 코어벽체는 지반을 기점으로 한 캔틸레버 거동을 하므로 코어만으로 수평하중을 저항하려면 파랑의 수평력에 대응하기 위해 넓은 벽두께가 설치되어야 한다. 코어벽체의 방식은 공용시설의 엘리베이터, 계단실인 코어를 벽식구조로 선시공하고, 코어주변에 설치하는 전단벽을 라멘구조를 후시공하여 벽식구조와 라멘구조의 강성차이를 이용하여 건축물의 수평안정을 찾는 R.C 코어 공법을 많이 사용하고 있다.Since the core wall acts as a cantilever based on the ground, in order to resist the horizontal load with only the core, a wide wall thickness must be installed to respond to the horizontal force of waves. The core wall method is to find the horizontal stability of the building by pre-installing the core, which is an elevator and stair room in a common facility, in a wall-type structure, and by post-installing the ramen structure on the shear wall installed around the core, using the stiffness difference between the wall structure and the ramen structure. RC core method is used a lot.

이를 위해서는 설치, 고정, 해체가 시스템화되어 있는 거푸집이 필요하며, 수중에서 적용, 시공하기에는 극복해야 할 문제가 많이 상존하고 있다. 그러나, 모듈식이나 P.C 하우스, 프리캐스터 콘크리트 패널 등 조립체를 사용해서 구조물을 구축할 경우에도 기둥이나 코어벽체의 수직부재는 건물의 자체하중, 수직부재간의 하중 분담비(응력비)의 차이, 콘크리트 재료특성에 기인하는 크리프(creep)변형, 건조, 수축변형등으로 수직부재들간에 부등축소 현상이 발생한다.For this, a formwork that has been systemized for installation, fixation, and dismantling is required, and there are many problems to be overcome in applying and constructing underwater. However, even when constructing a structure using an assembly such as a modular, PC house, or precast concrete panel, the vertical member of the pillar or core wall is the building's own load, the difference in the load-sharing ratio (stress ratio) between the vertical members, and the concrete material. Inequality reduction occurs between vertical members due to creep deformation, drying, shrinkage deformation, etc. due to the characteristics.

각 수직부재들간에 부등 축소현상이 클 경우 후속공사나 마감공사에 하자를 일으켜 구조물의 역학적 안정성에 영향을 미친다. 그러므로, 인접한 수직부재간의 변형량 차이나 내부 코어와 외부전단벽의 변형량 차이로 인해 생기는 부등축소량은 슬래브나 보 등에 부가응력을 유발하여 골조의 안정성에 심각한 악영향을 줌으로 슬래브를 기울게하여 칸막이 벽이나 기타 여러 연결부분의 균열원인이 되어 안정성과 사용성에 심각한 문제를 일으킬 수 있다.If the unequal reduction phenomenon between each vertical member is large, it may cause defects in subsequent construction or finishing work, affecting the mechanical stability of the structure. Therefore, the difference in the amount of deformation between adjacent vertical members or the amount of inequality reduction caused by the difference in the amount of deformation between the inner core and the outer shear wall causes additional stress on the slab or beam, which seriously adversely affects the stability of the frame. It may cause a crack in the joint and cause serious problems in stability and usability.

따라서, 폐쇄형 평면구조의 코어벽체는 횡력을 전달하는 부재이고 코어상부에 설치되는 슬래브와 코어내부의 바닥판 슬래브로서 전단벽으로 수평하중을 전달하며, 해상활주로(101)의 폭이 넓어지게 되면 그 폭에 맞게 코어벽체를 설치해야 하므로 코어벽체의 폭이 커질 수밖에 없다.Therefore, the core wall of the closed planar structure is a member that transmits lateral force, and the slab installed on the upper part of the core and the floor plate slab inside the core transmit the horizontal load to the shear wall. Since the core wall must be installed according to the width, the width of the core wall is inevitably increased.

이는 코어벽체 폭만큼 기초 지반부를 지점으로 한 캔틸레버 거동을 함과 진입하는 파력 등 여러 가지 환경외력에 의한 전도 모멘트가 작용하고, 코어벽체만으로 수평하중을 저항하려면 벽식 구조방식인 코어의 벽두께가 상당히 커져야 하고, 활주로 폭이 넓어진 만큼 그 방향으로 일정한 간격으로 콘크리트 전단벽을 형성해야 한다.This is due to the conduction moment of various environmental external forces, such as the cantilever behavior at the base ground as the core wall width, and the incoming wave force, and the wall thickness of the core, which is a wall-type structure, is considerably higher to resist horizontal loads with only the core wall. As the runway width increases, concrete shear walls must be formed at regular intervals in that direction.

그러므로, 이를 위해서는 슬립 폼(slip form) 및 갱폼(gang form)을 시스템화시켜 단계적으로 코어벽체를 설치해야 하는데, 이를 수중에서 설치하고자 할 때는 설치, 해체시 극복해야 할 문제가 많다.Therefore, for this purpose, the core wall must be installed step by step by systemizing a slip form and a gang form, and there are many problems that must be overcome during installation and dismantling when attempting to install this underwater.

상기 코어벽체를 지지하기 위한 기초사석부(107)는 부등침하가 발생하지 않도록 지반의 안정성 확보를 위한 연약지반 치환 및 처리와, 기초사석부(107)에 대한 잡석지정 작업등 많은 노력과 비용이 소요되며, 코어벽체를 위한 기초사석부 (107)의 마운드 설치가 완료되기 전 도래하는 태풍등 천재지변에 의한 투입재 유실등은 감내해야 될 부분인 것이다.The foundation stone part 107 for supporting the core wall requires a lot of effort and cost, such as replacing and processing the soft ground for securing the stability of the ground so that unequal settlement does not occur, and designating rubble for the foundation stone part 107. It is required, and the loss of input materials due to natural disasters such as typhoons that arrive before the mound installation of the foundation stone part 107 for the core wall is completed is a part to be tolerated.

이에 본 발명자는 해저면 코어벽체의 지반안정을 위하여, 특허등록 10 - 1256274와 10 - 1211811은 직접기초방식의 확대기초로 사용하는 하부후팅 마운드부 (104) 해저면에 설치함으로 연직 또는 수평방향의 지지력과 휨 모멘트, 편심하중을 상쇄시킬수 있으며, 지반반력에 의한 응력은 말뚝기초로 상재하중의 경감에 따른 대응력을 증가시킬 수 있는 조립케이슨 및 쟈켓을 이용한 R.C.D공법을 제공하고 있다.Accordingly, the inventors of the present invention have provided patent registrations 10-1256274 and 10-1211811 for ground stability of the core wall at the bottom of the sea floor. Supporting force, bending moment, and eccentric load can be canceled, and the stress caused by the ground reaction force is based on a pile and provides an RCD method using an assembly caisson and a jacket that can increase the response force according to the reduction of the overhead load.

상기 하부후팅 마운드부(104)의 설치지역을 크람쉘 버켓을 사용하여 풍화암 상단까지 준설하여 연약지반 생성을 사전에 제거하고, 수중굴착기를 사용하여 사각형 구조체의 거치장소를 정지한 다음 하부후팅용 조립식 케이슨을 연결하여 수중 콘크리트를 타설함으로, 하부후팅용 조립식 케이슨을 병렬로 연결, 결합하여 해저면 구조물 지지층에 밀착되고 기반암에 접속된 현장타설 말뚝(106)과 하부후팅의 확대기초로 결합한 마운드부(104)를 조성할 수 있다.The installation area of the lower hooking mound 104 is dredged up to the top of the weathered rock using a clamshell bucket to remove soft ground in advance, and the mounting place of the square structure is stopped using an underwater excavator, and then assembled for lower hooking. By connecting the caisson and pouring underwater concrete, the prefabricated caisson for lower hoisting is connected in parallel and bonded to the seafloor structure support layer, and the in-situ pile 106 connected to the bedrock and the mound unit combined with the expanded foundation of the lower hoisting ( 104).

그러므로, 연약지반 치환 및 잡석지정 공정이 필요없고 해저면 지반의 안정성을 높여 부등침하를 예방하고, 내진 적응력이 우수한 기초지반부를 제공함으로 천재지변에 의한 투입재 유실과 캔틸레버 거동을 하는 코어벽체의 전도모멘트에 대응할 수 있다.Therefore, it eliminates the need for soft ground replacement and rubble designation processes, prevents differential settlement by increasing the stability of the seabed ground, and provides a foundation ground with excellent seismic adaptability, resulting in loss of input materials due to natural disasters and the conduction moment of the core wall that acts as a cantilever. Can respond to.

특허등록 10 - 1650231과 10 - 1650232에서는, 케이슨 설치지역을 구분하여 구역별로 하부후팅 마운드부(104)상에 조립식 판넬을 쌓아 케이슨을 만들어 그 내부를 쇄석 및 토사로 충진시켜 그라우팅하여 고결화시킴으로 충진재의 압축하중을 균등한 분포하중으로 변환시켜 자중을 늘려 안정성을 증진시킬 수 있는 시공공법을 제공하고 있다.In patent registrations 10-1650231 and 10-1650232, the caisson installation area is divided and prefabricated panels are stacked on the lower hooking mount part 104 for each area to make a caisson, and the inside of the caisson is filled with crushed stone and soil and grouted to solidify the filling material. It provides a construction method that can increase the stability by increasing the self-weight by converting the compressive load of the unit into an even distributed load.

이러한 시공공법으로 연결형 블럭을 사용하여 각 구성품과의 결합을 단순화하고, 지내력을 증진시킨 코어벽체를 설치하여 박스형으로 구성된 독립케이슨을 병렬로 연결한 형태의 복합벽체 케이슨(105)으로 상재하중과 수직 및 수평하중을 감당하여 해저면 지형상태에 크게 영향을 받지 않고, 매립식으로 축조된 계류장(102)과 연결시공이 가능한 해상활주로(101)를 축조할 수 있는 것이다.With this construction method, a composite wall caisson 105 in a form in which independent caissons composed of a box type are connected in parallel by installing a core wall that has improved bearing capacity and a core wall that has improved bearing capacity and a stacked load is perpendicular to the overhead load. And it is possible to build the offshore runway 101 capable of connecting construction with the apron 102 built in a buried type without being greatly affected by the topography of the sea floor by handling the horizontal load.

도 5 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 하부후팅 조성을 위한 하부후팅용 조립식 케이슨과 그 내부에 들어가는 쟈켓, 하부후팅 보강용 철근망 사시도이고, 도 6 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블럭을 연결하는 연결판의 사시도이며, 도 7 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블럭의 단면도이다.Figure 5 is a perspective view of the prefabricated caisson for the lower hooking for the composition of the lower hooking in the core wall structure of the composite caisson for the offshore runway of the present invention, a jacket and a reinforcing reinforced lower hooking reinforcement network, and Fig. It is a perspective view of the connecting plate connecting the connecting block in the core wall structure of the composite caisson for offshore runways, and FIG. 7 is a cross-sectional view of the connecting block in the core wall structure of the composite caisson for offshore runways of the present invention.

도 8 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블럭과 칸막이 블럭의 사시도 및 연결 상세도이고, 도 9 및 도 10 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 말뚝보강 지지대의 사시도이며, 도 11 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 패널 존(pannel zone)에 들어가는 지주기둥 보강용 철근망의 사시도이다.8 is a perspective view and a detailed connection diagram of a connecting block and a partition block in the core wall structure of the composite caisson for a marine runway of the present invention, and FIGS. 9 and 10 are the core of the composite caisson for a marine runway of the present invention. ) It is a perspective view of a pile reinforcement support in a wall structure, and FIG. 11 is a perspective view of a reinforcing reinforcing column for a post entering a panel zone in a core wall structure of a composite caisson for an offshore runway of the present invention.

도 12 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블럭 격자공간내에 들어가는 결합형 블럭 철근망의 사시도이고, 도 13 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연결형 블록과 칸막이 블록,현장타설말뚝,지주기둥,연결판으로 형성된 단계별 블럭의 평면도이며, 도 14 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 하부후팅 마운드부로부터 결합형블럭을 연결하는 요약 상세도이다.FIG. 12 is a perspective view of a combined block reinforced network entering a connected block grid space in a core wall structure of a composite caisson for a marine runway of the present invention, and FIG. 13 is a core of a composite caisson for a marine runway of the present invention. It is a plan view of a step-by-step block formed of a connecting block and a partition block, a cast-in-place pile, a post column, and a connecting plate in a wall structure, and FIG. 14 is from the lower hooking mound in the core wall structure of the composite caisson for an offshore runway of the present invention. It is a summary detail diagram connecting the combined blocks.

도 15 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 결합형 블럭내에 충진토 투입과 고결화를 위한 그라우팅의 단면도이고, 도 16 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 연속보의 사시도 이며, 도 17 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 P.C 빔과 P.C 판넬의 사시도이다.15 is a cross-sectional view of grouting for inputting and solidifying filled soil in a combined block in the core wall structure of the composite caisson for a marine runway of the present invention, and FIG. 16 is a core of the composite caisson for a marine runway of the present invention ( core) is a perspective view of a continuous beam in a wall structure, and FIG. 17 is a perspective view of a PC beam and a PC panel in a core wall structure of a composite caisson for an offshore runway of the present invention.

본 발명에서 후술할 코어벽체의 전단벽에 작용하는 수평력에 의한 캔틸레버 거동으로 인한 전도모멘트에 대응할 수 있는 것이고, 벽두께를 키우는 대신 도 8 에 도시된 철근, 콘크리트블럭(407)을 만들어 블럭벽돌과 같은 구조로 박스형 벽체를 구성하는 코어벽체(도13 참조)이며, 그 내부를 공용구간(엘리베이터, 계단실)으로 사용하지 않고 철근, 콘크리트로 지주기둥(210)과 수중연속벽을 타설하여 단계별 블럭을 결합하여 결합형 블럭을 형성하여 수직부재인 결합형 블럭의 단면성능을 확장시킬 수 있다.In the present invention, it is possible to cope with the conduction moment due to the cantilever behavior caused by the horizontal force acting on the shear wall of the core wall to be described later, and instead of increasing the wall thickness, the reinforcing bar and concrete block 407 shown in FIG. It is a core wall (refer to Fig. 13) that constitutes a box-shaped wall in a structure, and it is not used as a common section (elevator, stair room), but a post column 210 and an underwater continuous wall are poured out of reinforced steel and concrete to combine step-by-step blocks. Thus, by forming a combined block, the cross-sectional performance of the combined block, which is a vertical member, can be expanded.

경우에 따라서는 지내력이 증진된 도 14 의 내력벽(409)을 추가 보강 설치할 수도 있다.In some cases, the bearing wall 409 of FIG. 14 with improved bearing strength may be additionally reinforced.

이로서 해상활주로 및 코어벽체 등의 수직하중과 구조물에 가해지는 수평하중을 받는 코어벽체로서 전단벽 역활을 동시에 수행하는 내력벽이 수평하중을 받으면 전단작용과 휨 모멘트를 동시에 받게 된다.As a result, when the bearing wall, which is a core wall that receives vertical loads such as offshore runways and core walls, and a horizontal load applied to the structure, simultaneously performing the role of a shear wall, receives a horizontal load, it receives shearing action and bending moment at the same time.

도 14 에 도시된 바와 같이, 상기 휨 모멘트는 결합형 블럭(409) 벽체의 단부와 결합형 블럭(409)과 결합된 지주기둥(210)과, 연속보(801, 802), 말뚝보강 지지대 (601)가 분담하고 전단력은 코어벽체가 수용하는 것이다.As shown in Figure 14, the bending moment is the coupling-type block 409, the end of the wall and the post column 210 coupled with the coupling-type block 409, continuous beams 801, 802, pile reinforcement support ( 601) is shared and the shear force is received by the core wall.

도 8 및 도 14 에 도시된 말뚝보강 지지대(601)는 기반암에 쇼켓팅(socketing)된 현장타설말뚝(106)과 각 연결형 블록(407)및 칸막이 블록(406)과 결합되어져 일정한 높이(결합형블럭 높이와 동일)마다 설치하고 있다.The pile reinforcement support 601 shown in FIGS. 8 and 14 is combined with the cast-in-place pile 106 and each connection-type block 407 and the partition block 406 that are shocketed on the bedrock to have a certain height (combination-type It is installed at each block height).

상기 코어벽체의 구조 및 역학적 안정성을 유지하면서 전도모멘트 및 코어벽체에 가해지는 수평력 및 각 부재간에 발생하는 건조, 수축, 크리프(creep) 변형등에 의한 부등축소를 그 상단에 설치되는 연결형 블럭(407)과 칸막이 블럭(406)내의 격자공간(109), 패널존(115)에 타설되는 수중 콘크리트에 의한 압축력과 말뚝보강 지지대(601)의 인장력을 발휘하여 수직부재(지주기둥(210), 연결형 블럭(407), 칸막이블럭(406))의 부등축소량을 제어할 수 있다.A connection type block 407 installed on the top of the core wall to maintain the structure and mechanical stability of the core wall, while reducing the inequality caused by the conduction moment, the horizontal force applied to the core wall, and drying, shrinkage, creep deformation, etc. generated between each member And the vertical member (post column 210, connecting block) by exerting the compressive force by the underwater concrete poured into the grid space 109 and the panel zone 115 in the partition block 406 and the tensile force of the pile reinforcement support 601 407), the inequality reduction amount of the partition block 406 can be controlled.

해수면위 복합벽체 케이슨(105) 상부에 설치되는 복층으로 구성된 연속보는 강한 휨강성과 수평하중 대응력을 증진시킬 수 있고, 확장된 수평부재(801, 802 : 도 20 참조)의 단면성능으로 부등 축소를 제어할 수 있으며, 넓은 복합벽체 케이슨(105)의 단면적은 그 넓이만큼 활주로(101)의 고정하중과 적재하중을 감당하고 지주기둥 (210)으로 전달되는 축하중의 분담력을 감소시킬 수 있다.A continuous beam composed of a double layer installed on the top of the composite wall caisson 105 on the sea level can enhance strong flexural stiffness and horizontal load response, and control the inequality reduction with the cross-sectional performance of the expanded horizontal members (801, 802: see Fig. 20). It is possible, and the cross-sectional area of the wide composite wall caisson 105 can bear the fixed load and the loading load of the runway 101 as much as the width thereof, and reduce the share of the axial load transmitted to the pillars 210.

한편, 현장타설로 기반암에 접속되어진 확대기초의 하부후팅 마운드부(104)는 압축 및 부착강도, 연성, 내하성능등 구조성능과 내진적응력이 우수한 C.F.T (concrete filled steel tube)의 현장타설말뚝(106)과 해저면 지지층에 밀착, 접합되어, 코어 기초지반부 내의 침전물을 제거하여 연약지반 생성소지를 사전에 제거하여 부등침하를 예방할 수 있다.On the other hand, the bottom hooking mount part 104 of the expanded foundation connected to the bedrock by cast in place is a cast-in-place pile of CFT (concrete filled steel tube) with excellent structural performance such as compression and adhesion strength, ductility, and load-bearing performance, and seismic adaptation. ) And the seafloor support layer to remove sediment in the core foundation ground and remove the soft ground generation material in advance to prevent differential settlement.

도 8 에 도시된 연결형 블럭(407)으로 조합된 패널 존(115)을 확보하여 말뚝의 수평단면적이 확장된 지주기둥(210)을 만들어 말뚝의 세장비를 높여 좌굴내력을 높이고, 지지말뚝이 마찰말뚝으로 변환되어져 주면마찰력이 증가되어 부마찰력을 감소시킴과 수직부재의 접합 단면적을 확장하여 상재하중에 대한 축하중 분담률을 높일 수 있다,By securing the panel zone 115 combined with the connection-type block 407 shown in FIG. 8, a post column 210 with an expanded horizontal cross-sectional area of the pile is made to increase the slenderness of the pile to increase the buckling strength, and the support pile is used as a friction pile. It is converted to increase the main surface friction force, thereby reducing the secondary friction force, and increasing the axial weight share of the upper load by expanding the joint cross-sectional area of the vertical member.

상기 지지기둥(210)과 보(801, 802, 803)를 통해 각 수직부재의 부등축소량을 제어함으로 구조적 안정성을 증진시킬 수 있다. 또한, 해상활주로 폭이 넓어지게 되면 일정한 면적으로 독립형으로 분할되어진 도 13 의 코어벽체(412)를 병렬로 전단벽을 설치하기 위한 방법이고, 칸막이 블럭(406)을 연결하여 박스형태를 갖추어 연결함으로써 추가의 수평강성을 얻을 수 있다.Structural stability can be improved by controlling the amount of inequality reduction of each vertical member through the support pillar 210 and the beams 801, 802, and 803. In addition, when the width of the marine runway becomes wider, it is a method to install the shear wall in parallel with the core wall 412 of FIG. 13 divided into a certain area in a separate area, and by connecting the partition block 406 to form a box and connect it. The horizontal stiffness of can be obtained.

이어 도 14의 각 결합형블럭(409) 하단에 압축된 고무판을 넣은 연결부분을 두어 상재하중의 수직적으로 누적된 하중이 하부층으로 전달되는 것을 방지하며, 캔틸레버 거동을 하는 내벽체에 생기는 과도한 전단응력을 방지하면서 응력을 수직적으로 전이시키지 않게 한다.Subsequently, a connection part containing a compressed rubber plate is placed at the bottom of each coupling block 409 of FIG. 14 to prevent the vertically accumulated load of the upper load from being transmitted to the lower layer, and excessive shear stress generated in the inner wall body acting as a cantilever. While preventing the stress from being transferred vertically.

따라서, 상재하중과 항공기 이, 착륙시 충격하중을 복합벽체 케이슨(105) 내부의 충진재 구역으로 유도하여 누적하중으로 인한 응력집중이 완화되어 각 연결부분에서부터 연결된 전단벽의 곡률이 달라지게 하며, 전체적인 수평강성을 크게 높일 수 있다. 그러므로, 크리프변형 및 복합벽체 케이슨(105)의 피로도를 경감시켜 구조물 생애주기를 연장시키는데 기여할 수 있다Therefore, by inducing the overhead load and the impact load during landing and the impact load to the filler area inside the composite wall caisson 105, stress concentration due to the cumulative load is alleviated so that the curvature of the shear wall connected from each connection part is different, and the overall horizontal The stiffness can be greatly increased. Therefore, it can contribute to extending the life cycle of the structure by reducing the creep deformation and fatigue of the composite wall caisson 105.

도 2 에 도시된 코어벽체 설치구간을 제외한 곳(114)은 해수를 통과시킴으로 외해로부터 진입하는 파력의 대항면적을 줄이고, 조류의 변화를 감소시킬 수 있다. 지내력을 높일 수 있는 단계별 블록(도 13 참조) 조립을 도 7 및 도 8 의 스터드 볼트(707), 넛트, 연결판(도 6 참조), 도 8의 연결고리(705)와 스테인래스 크립밴드(701)로 단순화시켜 연결을 용이하게 하여 시공성을 높여 공기를 줄일 수 있다.Except for the core wall installation section shown in FIG. 2, the area 114 of the core wall passes through seawater, thereby reducing the opposing area of the wave force entering from the open sea and reducing the change in current. A step-by-step block (see Fig. 13) that can increase endurance is assembled with a stud bolt 707, a nut, a connecting plate (see Fig. 6) of Figs. 7 and 8, a connecting ring 705 of Fig. 8, and a stainless steel creep band ( Simplify it to 701) to facilitate connection, thereby increasing workability and reducing the amount of time.

도 18 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 완성된 복합케이슨의 활주로 정면의 단면도이고, 도 19 는 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 복합복합케이슨의 활주로 측면의 단면도이며, 도 20 은 본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물에서 지주기둥과 큰보(연속보), 작은보(P.C 빔), P.C 판넬과 슬래브를 설치하는 상세도이다.Figure 18 is a cross-sectional view of the runway front of the composite caisson completed in the core wall structure of the composite caisson for offshore runways of the present invention, and Figure 19 is a composite in the core wall structure of the composite caisson for offshore runways of the present invention It is a cross-sectional view of the runway side of the composite caisson, and FIG. 20 is a cross-sectional view of the core wall structure of the composite caisson for an offshore runway of the present invention, in which post columns, large beams (continuous beams), small beams (PC beams), PC panels and slabs are installed. It is a detailed view.

본 발명에서 연결형 블럭(407)내 격자공간(109)에 수직, 수평강성을 증강시킨 내력벽과 전단벽성능을 동시에 보강, 발휘할 수 있는 도 14 의 수중연속벽(120)을 타설하여, 도 18의 복합벽체 케이슨(105) 내력벽체를 강화함으로 연직하중과 횡방향으로 작용하는 수평하중의 대응력을 높일 수 있다.In the present invention, in the grid space 109 in the connection-type block 407, the underwater continuous wall 120 of FIG. 14 that can simultaneously reinforce and exhibit vertical and horizontal stiffness-reinforced load-bearing walls and shear wall performances is placed, and the composite of FIG. Wall caisson 105 By reinforcing the bearing wall, it is possible to increase the response power of the vertical load and the horizontal load acting in the lateral direction.

해수면위 복합벽체 케이슨(105) 상단부에 설치되는 연속보(801, 802)는 부등축소량을 감소시키고 횡하중 분담성능을 증진시킬 수 있으며, 해상에서 작업하기에 충분히 넓은 공간을 마련하여 각종 부재의 연결 및 설치에 편리함을 제공하여 시공성을 높일 수 있다.The continuous beams (801, 802) installed on the upper part of the composite wall caisson 105 above sea level can reduce the amount of inequality reduction and improve the lateral load sharing performance, and provide a large enough space for working at sea to connect various members. And it is possible to increase the constructability by providing convenience for installation.

산업잠수부의 활동이 가능한 수심 - 80 m 까지 시공이 가능하고, 또한 수중건설장비의 발달로 인한 시공심도가 깊어질 수 있는 개연성이 충분하므로 해상활주로(101) 입지선정의 폭을 넓힐 수 있다.It is possible to construct up to a depth of 80 m in which the activities of industrial divers are possible, and there is sufficient probability that the construction depth can be deepened due to the development of underwater construction equipment, so it is possible to widen the width of the site selection of the marine runway 101.

F 등급이상 여객기를 운용하는 공항의 활주로는 이륙거리와 착륙대는 이설시단, 블래스트 패드, 과주대를 포함하여 폭은 최소 60 m, 길이는 1,800 m 이상 되어야 하므로 비행장 부지중 그 길이의 상당부분을 차지하는 해저면 활주로(101)의 입지여건을 충족시키기 곳은 극히 드물다.The runway of an airport operating a class F or higher passenger plane must be at least 60 m wide and 1,800 m long, including the take-off distance and landing pad at the time of relocation, blast pads, and overloading pads, and thus occupy a significant portion of the length of the aerodrome site. There are very few places to meet the location conditions of the runway 101 on the bottom of the sea.

본 발명은 도 1 에 도시된 바와 같이, 해저면 경사도가 심한 곳(116)이나 요철이 심한 곳(117), 단차가 많이 발생하는 부분(119)에서도 설치가 가능하므로, 매립식으로 축조된 계류장(102)과도 연결시공이 용이한 것이다.The present invention, as shown in Figure 1, because it can be installed in the place where the slope of the sea floor is severe 116, the place where the unevenness is severe 117, and the part 119 where the step occurs a lot, the apron built in a buried type It is also easy to connect with (102).

해상활주로(101) 설치구역 전구간을 코어방식으로 설치하지 않고 교각식으로 구조물 설치부분만 복합벽체 케이슨(105)으로 보강된 코어벽체를 설치하고, 도 18 의 각 복합 벽체 케이슨(105)간에는 연속보(801, 802)와 슬래브(101, 103)로 라멘구조 방식으로 강접하여 해상활주로(101)를 구축함으로 투입재를 대폭 절감할 수 있다. 도 1 에 도시된 바와 같이, 활주로 하부공간은 부대시설공간(108)으로 활용할 수 있고, 그 하부(114)는 해수를 유통시켜 조류차단을 지양하므로 환경훼손을 줄일 수 있다.A core wall reinforced with a composite wall caisson 105 is installed only in the structure installation part in a pier type without installing the entire section of the marine runway 101 installation area in a core method, and a continuous beam between each composite wall caisson 105 in FIG. By constructing the offshore runway 101 by strongly adjoining the (801, 802) and the slabs (101, 103) in a ramen structure method, the input material can be significantly reduced. As shown in FIG. 1, the space under the runway can be utilized as an auxiliary facility space 108, and the lower portion 114 of the runway circulates seawater to avoid tidal currents, thereby reducing environmental damage.

이상 설명한 바와 같이 본 발명을 도 1 내지 도 20 을 참조하여 상세히 설명한다,As described above, the present invention will be described in detail with reference to FIGS. 1 to 20,

본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물은, 크게 도 14가 에 도시된 하부후팅 설치단계, 도 14나 에 도시된 코어벽체 설치단계 및, 도 20 에 도시된 보와 슬래브 설치단계로 구분할 수 있다.The core wall structure of the composite caisson for an offshore runway of the present invention is largely the lower hooking installation step shown in Fig. 14A, the core wall installation step shown in Fig. 14B, and the beam and slab installation shown in Fig. 20 It can be divided into stages.

본 발명은 해상활주로(101) 구축시 설치되는 복합벽체 케이슨(105)의 코어벽체를 그 목적에 적합한 길이대로 전체적으로 전부 설치하지 않고, 도 2 에 도시된 코어벽체 설치구간(105)과 해수 유통구간(114)을 구분해서 배열하며, 외해로부터 진입하는 파랑을 일부 관통시키므로 진입파랑의 첨두를 분할시켜 코어의 파력 대항면적을 축소시키고 조류의 변화를 감소시킬 수 있다.The present invention does not entirely install the core wall of the composite wall caisson 105 installed at the time of construction of the offshore runway 101 in a length suitable for the purpose, but the core wall installation section 105 and the seawater distribution section shown in FIG. (114) is divided and arranged, and since it partially penetrates the wave entering from the open sea, it is possible to reduce the area against the wave force of the core and reduce the change of tide by dividing the peak of the entering wave.

구체적으로, 도 5 에 도시된 바와 같이, 하부후팅 마운드부(104) 설치지역을 크람쉘 버켓, 준설펌프 등으로 구역내를 준설하고, 수중굴착기를 사용하여 코어벽체구조물의 지지층인 풍화암 상단까지 굴착하므로 연약지반 생성소지를 사전에 제거한 후, 사각형태로 중간에 도 5 의 칸막이 P.C(411)를 설치해서 하부후팅용 조립식 케이슨(402)을 조립한다.Specifically, as shown in FIG. 5, the area where the lower hooking mount part 104 is installed is dredged in the area with a clamshell bucket, a dredging pump, etc., and excavated to the top of the weathered rock, which is the support layer of the core wall structure, using an underwater excavator. Therefore, after removing the soft ground generation material in advance, the partition PC 411 of FIG. 5 is installed in the middle in a rectangular shape to assemble the assembled caisson 402 for lower hoisting.

도 5 에 도시된 바와 같이, 해저면 지형의 경사로 인해 단차가 생기는 곳은 하부후팅용 조립식 케이슨(402)을 2 ~ 3 단으로 쌓고, 돌망태(213)와 고일목(211), 모래주머니(212)로 그 틈새를 메우고 평탄하게 하여 그 높이를 맞춘 후, 각 조립식 P.C(403, 404, 405)의 내, 외측에 부착되어 있는 연결고리(705)를 통해 스테인테스 크립밴드(701)를 끼워넣고, 인장, 결속을 단순, 용이하게 하여 하부후팅용 조립식 케이슨(402)을 만든다.As shown in FIG. 5, where a step occurs due to the slope of the sea floor topography, the prefabricated caisson 402 for lower hoisting is stacked in 2 to 3 stages, and a gabion 213 and a goil tree 211, and a sand bag 212 ) To fill in the gap and flatten the height, and then insert the stainless steel creep band 701 through the connecting ring 705 attached to the inside and outside of each assembly type PC (403, 404, 405). It makes the assembly type caisson 402 for the lower hooking by simple and easy tensioning and binding.

이때 칸막이 P.C (411)는 추후 설치될 쟈켓 거치대(214)가 들어갈수 있게 1 m 낮게 설치한다. 그 속에 다수개의 유도강관(207)과 다수개의 그라우팅 파이프 (206)가 부착되어진 H 비임(304)과 ㄱ 형강(305)으로 제작된 쟈켓(209)을 하부후팅용 조립식케이슨(402)안에 집어넣되 쟈켓거치대(214)가 칸막이 P.C (411)에 들어가게 설치해서, 인접 쟈켓과 연결판(704)을 통해 결속한 후 후팅보강용 철근망(505)를 덮고 볼트, 넛트로 결합한 다음 트레미 파이프를 사용하여 수중 콘크리트를 타설하여 지반에 밀착, 접합된 확대기초를 형성한다.At this time, the partition P.C 411 is installed 1 m lower so that the jacket holder 214 to be installed later can enter. A jacket 209 made of H-beam 304 and a-beam 305 to which a plurality of guided steel pipes 207 and a plurality of grouting pipes 206 are attached is inserted into the prefabricated caisson 402 for lower hoisting. Install the jacket holder 214 into the partition PC 411, bind it through the adjacent jacket and the connecting plate 704, cover the reinforcing reinforcing reinforcing bar 505, and connect it with bolts and nuts, and then use a treadmill pipe. Thus, underwater concrete is poured to form an enlarged foundation that is closely adhered and bonded to the ground.

칸막이 P.C (411)는 각기 4 개의 현장타설말뚝(106)이 설치되게 분할된 단위구역을 연속적으로 설치된 하부후팅용 조립식 케이슨(402)의 장방향 벽체에 작용하는 수압을 반대편 벽체로 전달하여 축력을 상쇄시키는 역할과, 상재하중의 접지압을 하부구조체에 균등하게 분포될 수 있게 하기 위한 것이며, 그 위에 거치되는 쟈켓(209)은 단위구역으로 분할되어진 하부후팅 마운드부(104)로 일체화시키기 위한 것이다.The partition PC 411 transmits the hydraulic pressure acting on the longitudinal wall of the prefabricated caisson 402 for lower hooking, which is continuously installed in a unit area divided so that four cast-in-place piles 106 are installed, to the opposite wall to transfer the axial force. It is to offset the role and to allow the ground pressure of the overhead load to be evenly distributed to the lower structure, and the jacket 209 mounted thereon is to be integrated into the lower hooking mount part 104 divided into unit zones.

유도강관(207)속에 근입강관(208)을 집어넣고 유압햄머로 항타한 후 R.C.D.장비를 장착하여 기반암까지 굴착하고, 그 내부에 철근망을 근입하여 콘크리트를 타설하여 현장타설말뚝(106)을 기반암과 쇼켓팅(socketing)시킨다.After inserting the steel pipe 208 into the guided steel pipe 207 and driving it with a hydraulic hammer, the RCD equipment is mounted to excavate the bedrock, and the reinforcing bar network is inserted into the inside of the pipe to pour concrete, and the cast-in-place pile 106 is used as the bedrock. And socketing.

이때 조립식케이슨 원형구멍(710)내에도 같이 타설한 후 도 15 의 천공 및 주입장비(202)를 사용하여 하부후팅용 조립식케이슨(402)의 그라우팅 주입구(204)와 하부후팅의 그라우팅 파이프(206)을 통해 하부후팅 마운드부(104) 하단 1 ~ 2 m까지 천공한다.At this time, the grouting inlet 204 of the prefabricated caisson 402 for lower hooking and the grouting pipe 206 of the lower hooking by using the drilling and injection equipment 202 of FIG. 15 after pouring in the prefabricated caisson circular hole 710 Through the hole, the lower hooking mount portion 104 is drilled to the bottom of 1 to 2 m.

그 후 코어벽체 설치지반과 하부후팅 하단 사이를 그라우팅하여 하부후팅 마운드부 주변지반의 공극 충진하여 해저면 지반의 안정성을 높이고, 기반암에 접속된 현장타설말뚝(106)은 연직 또는 수평방향의 지지력과 휨 모멘트, 편심하중을 상쇄시킬수 있으며, 지반반력에 따른 대응력을 증가시킨 내진적응력이 우수한 마운드부를 제공함으로 캔틸레버거동을 하는 코어벽체의 전도모멘트에 대한 대응력과 우수한 내진적응력을 유지할 수 있다.After that, grouting between the bottom of the core wall installation ground and the bottom of the bottom hooking is performed to fill the voids in the ground around the bottom of the bottom hooking mount to increase the stability of the seafloor ground, and the cast-in-place piles 106 connected to the bedrock have a vertical or horizontal support and Bending moment and eccentric load can be canceled, and by providing a mound part with excellent seismic adaptation that increases the response force according to the ground reaction force, the ability to respond to the overturning moment of the core wall acting as a cantilever and excellent seismic adaptation can be maintained.

하부후팅 마운드부(104)과 결합되어 기반암에 쇼켓팅된 현장타설말뚝(106)은 콘크리트 충진된 강관기둥으로 원주방향의 압력이 콘크리트를 효율적으로 구속함으로 콘크리트의 체적팽창을 억제하고, 강관내부에 콘크리트 압축강도가 상승되어 강관의 국부좌굴이 방지되는 뛰어난 변형능력이 발휘되어 횡변위가 감소된 높은 강성을 유지하여 지진발생시 적응력이 우수한 C.F.T 구조인 것이다.The cast-in-place pile 106 coupled with the lower hooking mound 104 and shocked to the bedrock is a concrete-filled steel pipe column, and the pressure in the circumferential direction effectively restrains the concrete, thereby suppressing the volume expansion of the concrete. It is a CFT structure with excellent adaptability when an earthquake occurs by maintaining high stiffness with reduced lateral displacement by exerting excellent deformability to prevent local buckling of steel pipes due to increased concrete compressive strength.

이는 안정성 측면에서 뛰어난 성능을 보인 예는 1995년 일본 고베 대지진에서 C.F.T를 사용한 건축물들은 거의 피해사례가 없는 것으로 밝혀져 그 안정성이 입증된바 있다.This is an example of excellent performance in terms of stability. In the 1995 Great Kobe Earthquake in Japan, buildings using C.F.T were found to have little damage, and the stability was proven.

도 14 나에 도시된 바와 같이, 코어벽체 설치 단계로서 폐쇄형 평면구조의 코어벽체는 지반을 기점으로 한 캔틸레버 거동을 하므로, 코어벽체만으로 수평하중을 저항하려면 파랑의 수평력에 대응하기 위해 넓은 벽두께를 설치하고, 활주로 폭만큼 일정한 간격으로 전단벽을 설치하는 대신 코어벽체의 크기만큼 내부가 비어 있는 것이다.As shown in Fig. 14B, as the core wall installation step, the core wall of the closed planar structure has a cantilever behavior based on the ground. Therefore, to resist the horizontal load with only the core wall, a wide wall thickness is required to respond to the horizontal force of waves. Instead of installing shear walls at regular intervals equal to the width of the runway, the interior is empty as much as the core wall.

도 8 에 도시된 좌, 우연결이 가능한 박스형으로 높이보다 폭이 넓은 연결형블럭(407)을 프리캐스트 콘크리트로 제작하여 좌, 우로 연결하여 박스형으로 복합벽체 케이슨(105)을 다수개 연결한 형태의 복합벽체 케이슨(105)의 전단벽을 설치함으로, 기존의 코어 전단벽 설치시 사용하는 슬립폼 및 갱폼과 같은 시스템화 되어있는 거푸집이 필요없고 연결형 블럭(407) 조립시 그 내부공간의 부피만큼의 해수를 수용하고 있다.A box-shaped connection block 407 with a width greater than the height of the box-type connection shown in FIG. 8 is made of precast concrete, and is connected to the left and right to connect a plurality of composite wall caissons 105 in a box-like shape. By installing the shear wall of the composite wall caisson 105, there is no need for a systemized form such as slip foam and gang foam used when installing the existing core shear wall, and when assembling the connecting block 407, seawater as much as the volume of the inner space is accommodated. I'm doing it.

그러므로, 그 체적만큼 대응수압이 작용하므로 충진재가 채워지기 전까지 내습하는 파력에 전도되지 않으며, 코어벽체의 엘리베이터, 계단실과 같은 공용시설 사용목적과 달리 그 내부에 후시공되는 수중연속벽(120)과 블럭벽체는 지내력이 증강된 코어의 내력벽으로서 상재하중에 대한 지내력을 증진시킴과 파랑의 수평력에 대응력이 우수한 수직부재의 내력벽으로서도 그 기능을 발휘할 수 있다.Therefore, since the corresponding water pressure acts as much as its volume, it is not conducted to the wave power that invades until the filler is filled, and unlike the purpose of using common facilities such as elevators and stairwells of the core wall, the underwater continuous wall 120 and the post-construction therein The block wall is a bearing wall of a core whose bearing capacity has been enhanced, and can function as a bearing wall of a vertical member that has an excellent ability to cope with the horizontal force of waves and to improve bearing load against the overhead load.

코어벽체를 설치하기 위한 그 세부적인 방법으로, 도 14 에 도시된 바와 같이 말뚝보강 지지대(601)과 같이 하부후팅 마운드부(104)위에 각 현장타설말뚝 (106)과 결속된 말뚝보강 지지대(601)를 설치한다.As the detailed method for installing the core wall, the pile reinforcement support 601 bound to each of the cast-in-place piles 106 on the lower hooking mount part 104 like the pile reinforcement support 601 as shown in FIG. 14 ) Is installed.

도 9 에 도시된 바와 같이, 외곽쪽에는 2 개의 원형부(603)와 2 개의 직선부 (604)가 도 13 의 칸막이 블럭(406)쪽에는 도 10 에 도시된 3 개의 원형부(603)와 3 개의 직선부(604)가 들어갈 수 있게 설치한다.As shown in FIG. 9, two circular portions 603 and two straight portions 604 on the outer side, and three circular portions 603 shown in FIG. 10 on the partition block 406 side of FIG. It is installed so that the three straight portions 604 can enter.

여기서, 재질은 내해성이 강한 티타늄이나 철, 니켈 합금강이나 아연도금강을 사용한다. 두께는 50 mm 이상, 폭은 400 ~ 600 mm, 직선부 길이는 10 ~ 20 m, 원형부는 현장타설말뚝 직경에 비례해서 제작하며, 연결부는 500 ~ 800 mm 로, 연결은 볼트, 넛트로 한다.Here, as the material, titanium, iron, nickel alloy steel, or galvanized steel with strong corrosion resistance is used. The thickness is 50 mm or more, the width is 400 ~ 600 mm, the length of the straight section is 10 ~ 20 m, the circular section is manufactured in proportion to the diameter of the cast-in-place pile, the connection section is 500 ~ 800 mm, and the connection is made with bolts and nuts.

이는 기반암에 접속되어진 현장타설말뚝(106)과 결합되어져 있는 각 결합형 블록(409)에 가해지는 파력에 의한 수평력과 그 속에 채워지는 도 15 의 충진재 (506)에 의한 수동압에 대한 저항력을 유지함과 동시에, 그 상단에 설치되는 연결형 블럭(407)과 칸막이 블럭(406)내의 격자공간(109), 패널존(115)에 타설되는 수중 콘크리트에 의한 압축력과 인장력을 발휘하여 수직부재(지주기둥, 연결형 블럭, 칸막이 블럭)의 부등축소량을 제어할 수 있다.This maintains the horizontal force due to the wave force applied to each coupling block 409 coupled with the cast-in-place pile 106 connected to the bedrock and the resistance to passive pressure by the filler 506 of FIG. 15 filled therein. At the same time, by exerting compressive and tensile force by underwater concrete poured into the grid space 109 and panel zone 115 in the connecting block 407 and the partition block 406 installed at the top, vertical members (post columns, You can control the amount of inequality reduction (connected blocks, partition blocks).

또한, 각 결합형 블록(409)과 기반암에 접속된 현장타설말뚝(106)간의 결합을 공고히 하여 기둥과 결합된 철골보 기능을 수행하여 구조적, 역학적 안정성을 증진시키는 것이다.In addition, by strengthening the coupling between each coupling block 409 and the cast-in-place pile 106 connected to the bedrock, it improves structural and mechanical stability by performing the function of a steel beam combined with a column.

그 위에 설치되는 연결형 블럭(407)은 도 7 과 같이 좌, 우측 연결형 블럭끼리 연결시키기 위해 양단에 내해성이 강한 스터트 볼트(stud bolt ; 707))가 부착되어 있다. 상, 하 연결을 위해서는 하부에는 말뚝보강 지지대(601)가 들어갈 수 있는 연결홈(602)과 상부에는 블럭 연결키(501)와 연결홈(502)이 있으며, 콘크리트 타설시 말뚝보강 지지대(601)와의 결합을 위한 연결홈(602)이 있다.The connection-type block 407 installed thereon is attached with a stud bolt 707 having strong resistance to harm at both ends to connect the left and right connection-type blocks as shown in FIG. 7. For the upper and lower connection, there are a connection groove 602 in which the pile reinforcement support 601 can be inserted, and a block connection key 501 and a connection groove 502 in the upper part, and the pile reinforcement support 601 when concrete is placed. There is a connection groove 602 for coupling with.

또한, 그 내부에 수중연속벽(120)을 조성을 위한 격자공간(109)이 있으며, 콘크리트 타설시 시멘트 페이스트 유출을 막고 내부 그라우팅(205)을 할 때 현탁액이 유출되지 않도록 압축된 무독성 발포스펀지(309)가 부착되어 있다. 상기 스터트볼트 (707)는 직경 100 mm 이상 짜리를 사용한다.In addition, there is a grid space 109 for forming the underwater continuous wall 120 therein, and a non-toxic foam sponge 309 compressed to prevent leakage of cement paste during concrete pouring and to prevent the suspension from flowing out when the internal grouting 205 is performed. ) Is attached. The stud bolt 707 has a diameter of 100 mm or more.

상기 연결형 블럭(407)은 한쪽은 짧고 한쪽은 길게 하여 긴 쪽과 짧은 쪽이 서로 교차되게 하여 현장타설말뚝(106)을 감싸서 지주기둥(210) 형성할 수 있는 패널 존(115)을 만들고 있다.The connection-type block 407 has one short and one long so that the long side and the short side cross each other to create a panel zone 115 capable of forming a post column 210 by surrounding the cast-in-place pile 106.

장방향쪽에는 한쪽은 길게 한쪽은 짧고 경사지게 한 연결형 블럭(407)과 칸막이 블럭(406)을 양쪽이 경사지게 연결형 블럭(407)과 연결되게 설치해서 그 공간을 확보하며, 블럭 중앙에는 격자판을 넣어 양쪽에 수중연속벽(120)을 조성할 수 있는 격자공간(109)이 형성되어져 있다.In the long direction, a connecting block 407 and a partition block 406 in which one is long and one is inclined are installed so that both sides are connected to the connecting block 407 to secure the space, and a grid plate is placed in the center of the block to secure the space. A lattice space 109 capable of forming the underwater continuous wall 120 is formed.

도 8 에 도시된 연결형 블럭(407)과 칸막이 블럭(406)은 증기 양생된 프리캐스트 콘크리트로 벽체 두께는 800 m/m ~ 1,000 m/m으로 하여 높이는 3 ~ 4 m, 길이는 10 m ~ 20 m로, 폭은 4 ~ 6 m로 제작한다.The connecting block 407 and the partition block 406 shown in FIG. 8 are steam-cured precast concrete with a wall thickness of 800 m/m to 1,000 m/m, a height of 3 to 4 m, and a length of 10 m to 20. It is manufactured in m, and the width is 4 to 6 m.

상기 블럭을 연결할 때, 외해쪽 방향으로 긴 부분이 현장타설말뚝(106)바깥쪽으로 위치시키고, 인접 블럭은 그 반대로 배열하며 곡각부분에서는 벽체 폭이 나란히 조합되게 하여 현장타설말뚝(106)을 감싸고, 곡각 연결판(702)과 도 6 의 평 연결판(703)을 연결구(706)를 통해 연결형 블럭양단에 부착되어져 있는 스터트 볼트(도707)에 끼워 넣고 와샤, 너트로 조립한다.When connecting the blocks, a long part in the outer sea direction is located outside the cast-in-place pile 106, adjacent blocks are arranged in the opposite direction, and the width of the wall is combined side by side in the curved part to surround the cast-in-place pile 106, The curved connecting plate 702 and the flat connecting plate 703 of FIG. 6 are inserted through the connector 706 into the stud bolts (FIG. 707) attached to both ends of the connecting block, and assembled with washers and nuts.

그 후 그 옆에 부착된 연결고리(705)에 스테인레스 크립밴드(701)로 인장하여 체결하면, 도 13 과 같은 박스형의 단계별 블록(408)이 완성된다. 이렇게 하여 3 개의 단계별 블럭(408)을 적층해서 말뚝보강 지지대(601)를 연결하면 결합형 블럭(409)이 완성되고, 격자공간(109)에 결합형 블럭철근망(503)을 넣고 트레미파이프(203)를 사용하여 수중 콘크리트를 타설하면 수중연속벽(120)이 설치된 다수개의 독립케이슨(412)이 결합된 형태의 복합케이슨 코어벽체 구조물이 완성된다.Thereafter, when the connecting ring 705 attached to the side thereof is tensioned and fastened with a stainless creep band 701, a box-shaped step-by-step block 408 as shown in FIG. 13 is completed. In this way, when three step-by-step blocks 408 are stacked and the pile reinforcement support 601 is connected, the combined block 409 is completed, and the combined block reinforcing bar network 503 is put in the grid space 109 and the tremi pipe When underwater concrete is poured using (203), a composite caisson core wall structure in the form of a combination of a plurality of independent caissons 412 on which the underwater continuous wall 120 is installed is completed.

또한, 활주로 폭이 넓어지게 되면 일정한 면적으로 독립형으로 분할되어진 코어를 병렬로 지내력을 증진시킬 수 있는 수중 연속벽(120)은 지중연속벽 (slurry wall) 과 달리, 하부후팅 마운드부(104)위에 설치되는 결합형 블럭내에 격자공간이 형성되어지므로 벽체 자립을 위한 근입장과 판넬벽체 연결을 위한 조인트처리가 필요없고, 연결된 결합형 블럭(409)벽체가 일체화될 수 있는 구조로 되어 있다.In addition, when the runway width becomes wider, the underwater continuous wall 120, which can increase the bearing capacity of the core divided into a certain area in parallel, is located on the lower hooking mount part 104, unlike a slurry wall. Since a grid space is formed in the combined block to be installed, there is no need for a joint treatment for connecting the wall to the panel wall and the near position for self-standing of the wall, and the connected combined block 409 has a structure in which the wall can be integrated.

따라서, 지중 연속벽같이 벽체형성을 위한 안내벽(guide wall)설치 및 트렌치(trench)조성을 위한 굴착작업등 시공을 위한 제반 플렌트 설비가 불필요하다. 단지 철근망근입과 콘크리트 타설만으로 연속벽체를 조성할수 있으므로 공기와 시공비가 절감되고 벤토나이트(bentonite)를 사용하지 않으므로 품질좋은 수중연속벽을 조성할 수 있다.Accordingly, there is no need for all plant facilities for construction, such as installation of a guide wall for forming a wall, such as an underground continuous wall, and excavation work for forming a trench. Since it is possible to create a continuous wall with only reinforced reinforcement and concrete pouring, construction costs and construction costs are reduced, and since bentonite is not used, a high-quality underwater continuous wall can be created.

지중연속벽은 건축 구조물의 본벽으로서 지내력과 그 내구성이 입증되어 내력벽으로 톱다운(top down)공법의 내력벽으로 많이 사용하고 있다. 전단벽을 설치하기 위한 방법으로, 도 13 의 칸막이 블럭(406)을 추가로 연결함으로써 추가의 수평강성을 얻을 수 있다.As the main wall of a building structure, the underground continuous wall has proven its bearing strength and durability, so it is widely used as a bearing wall in the top down method as a bearing wall. As a method for installing the shear wall, additional horizontal stiffness can be obtained by additionally connecting the partition block 406 of FIG. 13.

지주기둥은 패널 존(115)속에 기 설치되어 있는 지지말뚝인 현장타설말뚝 (106)사이에 도 11 의 지주기둥 철근망(504)을 집어넣고 트레미 파이프(203)를 사용하여 수중 콘크리트를 타설하여 마찰말뚝인 도 16 의 지주기둥(210)을 만든다.For the pillars, the reinforcing steel reinforcing bars of Fig. 11 are inserted between the in-situ piles 106, which are pre-installed support piles in the panel zone 115, and underwater concrete is poured using the tremi pipe 203. This makes the column 210 of Fig. 16, which is a friction pile.

이는 지지말뚝인 현장타설말뚝(106)의 수평 단면적이 2 배 이상 증가된 지주기둥(210)이 형성되며, 패널존(115)에 들어가는 지주기둥 철근망(510)은 패널 존 (115)과 연결형 블록(407)과의 부착능력을 증진시킴과 동시에 지주기둥에 응집되는 축력을 하부후팅 마운드부(104)에 유도하여 응력의 재분배를 유발시킬 수 있다.This is a support pile, the horizontal cross-sectional area of the cast-in-place pile 106, the horizontal cross-sectional area of which is increased by more than two times is formed, and the post column reinforcing bar network 510 entering the panel zone 115 is connected to the panel zone 115. At the same time, it is possible to induce redistribution of stress by inducing an axial force that is aggregated to the post column to the lower hooking mount portion 104 while improving the adhesion with the block 407.

그러므로, 타설된 콘크리트로 인해 지지말뚝인 현장타설말뚝(106)에 마찰말뚝의 기능이 부가되어 지주기둥의 세장비를 키워 좌굴하중을 낮추고 말뚝의 주면마찰력이 증대되어 부마찰력을 감소시키므로 지주기둥(210)의 축하중 분담력을 높일 수 있다.Therefore, the function of a friction pile is added to the in-situ pile 106, which is a support pile, due to the poured concrete, to increase the slenderness of the post column to lower the buckling load and increase the main surface friction of the pile to reduce the secondary friction. You can increase your sharing power during celebrations.

상기 결합형 블럭(409)의 적층시공이 어느 정도 진행되면 그 내부공간을 집중적으로 투하지역을 용이하게 조정할 수 있는 연결식 케이싱과 대구경용 오실레이터로 구성된 집중투하장비(201)로 복합케이슨(401)내부를 도 15 에 도시된 바와 같이 1 구역씩 충진시킨다.When the stacking construction of the combined block 409 progresses to a certain extent, the integrated caisson 401 is built with a intensive delivery device 201 consisting of a connection-type casing and a large-diameter oscillator that can easily adjust the delivery area intensively in the internal space. As shown in Fig. 15, it is filled in one zone at a time.

그리고, 충진재(쇄석, 토사)의 흐트러짐을 예방하기 위해서 결합형 블럭(409)을 1 구역씩 수중 진동로룰러로 지정작업을 한 다음 버림콘크리트를 타설한다. 이때 콘크리트 부착성능 향상과 항복강도, 인장강도를 높이고 균열을 제어하며, 재하하중의 고른 분산효과를 기하기 위해 도 14 의 와이어 매쉬(307)를 포설하고, 도 15 의 버림 콘크리트(303)를 300 mm 이상 타설한다.In addition, in order to prevent the filling material (crushed stone, soil) from being disturbed, the combined block 409 is designated as an underwater vibrating furnace for each zone, and then discarded concrete is poured. At this time, the wire mesh 307 of FIG. 14 was installed to improve the concrete adhesion performance, increase the yield strength, and tensile strength, control cracking, and evenly distribute the load load, and the discarded concrete 303 of FIG. 15 was 300 Pour more than mm.

도 15 에 도시된 바와 같이, 콘크리트를 관통할 수 있는 비트를 장착한 천공장비(202)로 그 내부를 천공하여 그라우팅(205)하므로, 그 후 내부에 채워지는 충진재(쇄석, 토사)의 전단강도를 높여 지내력을 안정화시킴과 동시에, 압축하중을 분포하중으로 균등하게 하부후팅 마운드부(104)로 전달케하여 구조적 안정성을 더할 수 있다.As shown in Fig. 15, since the inside is drilled and grouted 205 with a drilling equipment 202 equipped with a bit capable of penetrating concrete, the shear strength of the filler (crushed stone, soil) filled thereafter Structural stability can be added by increasing the value to stabilize the bearing capacity, and at the same time allowing the compressive load to be evenly transmitted to the lower hooking mount portion 104 as a distributed load.

각 결합형 블럭(409) 상단에 말뚝보강 지지대(601)를 설치한 그 여백부분에 압축된 고무판등 코킹재를 넣고 연결부분을 두어 상재하중의 수직적으로 누적된 하중이 하부층으로 전달되는 것을 방지한다.A caulking material such as a compressed rubber plate is placed in the margin where the pile reinforcement support 601 is installed at the top of each coupling block 409, and a connection part is placed to prevent the vertically accumulated load of the upper load from being transmitted to the lower layer. .

캔틸레버거동을 하는 내벽체에 생기는 과도한 전단응력을 방지하면서 응력을 수직적으로 전이시키지 않게 하고, 상재하중과 항공기 이, 착륙시 충격하중을 복합케이슨 내부로 흡수할수 있도록 하여, 누적하중으로 인한 응력집중이 완화되어 각 연결부분에서부터 연결된 전단벽의 곡률이 달라지게 하며, 전체적인 수평강성을 크게 높일수 있으며 크리프변형 및 복합벽체 케이슨(105)의 피로도를 경감시켜 구조물 생애주기를 연장시키는데 기여할 수 있다.Stress concentration due to cumulative load is prevented by preventing excessive shear stress generated in the cantilever-acting inner wall, while preventing the stress from being transferred vertically, and absorbing the overhead load, the aircraft, and the impact load during landing into the complex caisson. It is alleviated so that the curvature of the shear wall connected from each connection part is different, and the overall horizontal stiffness can be greatly increased, and it can contribute to prolonging the life cycle of the structure by reducing creep deformation and fatigue of the composite wall caisson 105.

그리고, 케이슨 설치 및 기타 공법은 시공기간중 도래하는 천재지변에 대처 하는 대피방법 및 수단이 극히 제한되어 있고, 기초지반부의 마운드 조성을 위한 시공중 내습하는 태풍에 투입재의 유실은 피할수 없는 반면, 본 발명은 기반암에 접속된 하부후팅 마운드부(104)로부터 단계적으로 단계별 블럭(408)을 연결하여 완성시켜 나가고, 각 조립체의 연결고리(705)와 좌,우,상,하 연결밴드 (701, 711)등을 사용하여 단계별 블럭(408)을 고정시켜 적층하는 방식으로, 시공중 도래하는 태풍등에 의한 투입재 유실을 예방할 수 있으며, 급변하는 기상상황과 각종 환경외력에 유연하게 대처할 수 있으므로 천재지변에 대한 우월한 적응력을 발휘할 수 있는 것이다.In addition, the caisson installation and other construction methods have extremely limited evacuation methods and means to cope with natural disasters that arrive during the construction period. The invention is completed by connecting the step-by-step block 408 from the lower hooking mount part 104 connected to the bedrock, and the connection ring 705 of each assembly and the left, right, upper and lower connection bands 701, 711 ), etc., by fixing and stacking the blocks 408 for each step by using, etc., it is possible to prevent the loss of input materials due to typhoons coming during construction, and can flexibly cope with rapidly changing weather conditions and various external forces. They can show superior adaptability.

도 20 에 도시된 바와 같이, 보와 슬래브 설치단계로는 도 18 및 도 19 에서의 해수면위로 1개단의 결합형 블럭(409)높이 위에 연속보(801, 802)를 설치하고 슬래브(103)를 설치하는 것이다.As shown in Fig. 20, in the step of installing beams and slabs, continuous beams 801 and 802 are installed above the height of the combined block 409 at one stage above the sea level in Figs. 18 and 19, and the slab 103 is installed. To install.

이때, 설치장소는 해수면위 9 ~ 12 m 지점(1개단의 결합형 블럭의 높이)의 하부슬래브(103)와 상판(101)에 설치하며, 지주기둥(210)간에 연결되는 연속보 (801)는 내부에 공간이 형성되어 있는 중공보(801)를 설치하며, 경간간 설치되는 연속보(802)는 P.C 빔(803)이 설치될 수 있게 요철화하여 설치한다.At this time, the installation place is installed on the lower slab 103 and the upper plate 101 at a point 9 to 12 m above sea level (the height of one combined block), and a continuous beam 801 connected between the pillars 210 The hollow beam 801 is installed with a space formed therein, and the continuous beam 802 installed between the span is uneven so that the PC beam 803 can be installed.

도 17 의 P.C 빔(803)은 곡각부분(812)이 연속보(802)에 걸리게 설치하며, 보의 폭과 높이는 결합형 블럭(409)의 폭과 같게 하며 중공보(801)의 벽체 두께는 1.2 ~ 1.5 m로 한다,The PC beam 803 of FIG. 17 is installed so that the curved portion 812 is caught on the continuous beam 802, the width and height of the beam are the same as the width of the combined block 409, and the wall thickness of the hollow beam 801 is 1.2 to 1.5 m,

경간위에 설치하는 P.C 빔(803)은 요철화된 부분(805)에 끼워 넣고 경간쪽연속보 연결고리(705)에 크립밴드(701)로 인장, 결속하고, 복합벽체 케이슨(105)위에 설치되는 P. C 빔(803)과의 빈공간(813)은 콘크리트를 타설하여 각 복합벽체 케이슨(105)간 결속을 공고히 하므로 보의 비틀림을 막고 상부에 설치되는 슬래브의 판좌굴을 막을 수 있다The PC beam 803 installed on the span is inserted into the concave-convex portion 805, tensioned and bound with a creep band 701 to the span-side continuous beam connecting ring 705, and installed on the caisson 105 of the composite wall. In the empty space 813 with the P. C beam 803, it is possible to prevent the torsion of the beam and the plate buckling of the slab installed at the top because concrete is poured to solidify the bond between the caissons 105 of each composite wall.

상기 P.C 빔(803)의 폭과 높이의 비율은 1 : 2로 하며 길이는 경간과 같게 한다. P.C빔(803)의 설치가 완료되면 그 위에 P.C 판넬(804)을 설치한다. 상기 P.C 판넬(804)은 P.C 빔과 접속될 수 있는 연결핀(708)이 부착되어져 있다.The ratio of the width and height of the P.C beam 803 is 1:1 and the length is the same as the span. When the installation of the P.C beam 803 is completed, a P.C panel 804 is installed on it. The P.C panel 804 has a connection pin 708 that can be connected to the P.C beam.

스터트 볼트로 제작된 P.C 빔의 연결핀(708)이 결속될 수 있는 연결구(706)는 볼트, 와샤. 넛트로 체결되며, 연결핀(708)에 맞게 P. C 판넬(804)의 연결구(706)를 맞추어 끼운다.The connector 706 to which the connection pin 708 of the P.C beam made of stud bolts can be bound is a bolt, washer. It is fastened with a nut, and fits the connector 706 of the P.C panel 804 to fit the connection pin 708 and fits it.

인접판넬과 연결할 수 있는 연결키(809)와 연결홈(810)으로 구성되어져 있으며, 두께는 300 ~ 400 mm, 폭은 4 ~ 6 m, 길이는 경간 길이와 같게 한다.It is composed of a connection key 809 and a connection groove 810 that can be connected to adjacent panels, and the thickness is 300 ~ 400 mm, the width is 4 ~ 6 m, and the length is the same as the span length.

이를 설치할 때는 P.C 빔(803)과 직각방향으로 연결구(706)에 맞추어 설치한다. 그 위에 철근, 콘크리트를 타설하여 하부슬래브(302)를 완성함으로 슬래브의 두께를 키워 횡하중 대응력을 증가시킴과 동시에, P.C 판넬(804)의 판좌굴을 예방할 수 있다.When installing this, it is installed in accordance with the connector 706 in a direction perpendicular to the P.C beam 803. Reinforcing bars and concrete are poured thereon to complete the lower slab 302, thereby increasing the thickness of the slab to increase lateral load response, and at the same time, preventing the plate buckling of the P.C panel 804.

이는 상부에 설치되는 슬래브(302)의 거푸집과 써포트, 동바리가 필요없으므로. 그에 대한 작업공정이 생략되고 노동력과 비용이 절감된다. 여기서, 슬래브 콘크리트 두께는 300 ~ 600 mm 로 한다.This is because there is no need for the formwork, support, and movement of the slab 302 installed on the top. The work process is omitted and labor and cost are saved. Here, the slab concrete thickness is set to 300 ~ 600 mm.

도 18의 도면부호 113 은 부대시설공간을 교통하는 통행구이고, 하부 슬래브 (103)위에 설치하며 폭은 5 ~ 8 m, 높이는 5 ~ 7 m로. 벽체 두께는 1 ~ 1.5 m 로하여 설치한다.Reference numeral 113 of FIG. 18 is a passageway for communicating an auxiliary facility space, and is installed on the lower slab 103 with a width of 5 to 8 m and a height of 5 to 7 m. The wall thickness should be 1 ~ 1.5 m.

상판(해상활주로)조성시 복합벽체 케이슨 내부는 와이어 매쉬(307)를 깔고 버림 콘크리트(303)을 타설한 후 300 ~ 400 mm 의 보조기층(311)과 200 ~ 300 mm 의 쇄석기층(312)을 다짐한 후 300 ~ 400 mm 의 아스콘 표층으로 포장을 한다.When constructing the upper plate (sea runway), the inside of the composite wall caisson is laid with a wire mesh 307 and discarded concrete 303 is poured, and then a 300-400 mm sub-base 311 and a 200-300 mm crushed stone base 312 are formed. After compacting, wrap it with the surface layer of ascon of 300 ~ 400 mm.

이는 동결, 응해에 따른 콘크리트 구조물의 팽창, 수축에 따른 균열현상을 예방하고, 생애주기 연장을 위한 지주기둥내의 충진토의 고결화를 위한 보강그라우팅 작업을 용이하게 함과, 주기적(3 ~ 5 년)으로 복합벽체 케이슨(105)내부에 채워져 있는 충진토의 고결화를 보강하기 위한 것이다.This prevents cracking due to expansion and contraction of the concrete structure due to freezing and condensation, and facilitates reinforcing grouting work for solidifying the filled soil in the column for extending the life cycle, and periodic (3 to 5 years). It is to reinforce the solidification of the filled soil filled in the composite wall caisson (105).

콘크리트로 포장을 할 경우에는 각 경간 구역별로 충분한 신축이음장치를 설치해서 철근, 콘크리트를 타설하며, P.C 판넬(804)을 포함한 슬래브의 총 두께(314)는 800 ~ 1,100 mm 로 한다.When paving with concrete, sufficient expansion joints are installed for each span area to pour reinforcement and concrete, and the total thickness 314 of the slab including the P.C panel 804 is 800 ~ 1,100 mm.

이렇게 하여 복층으로 형성한 수평부재101, 103)는 기반암에 접속된 하부후팅 마운드부(104)의 현장타설말뚝(106)과 각 지주기둥(210)간과 결합형 블럭(409)과 결합된 말뚝보강지지대(601)와 결합되어 역학적, 구조적안정성을 지닌 복합케이슨 코어 벽체구조물로서 수직하중 및 수평하중에 우수한 대응성능을 발휘할 수 있다.The horizontal members 101 and 103 formed in a double layer in this way reinforce the piles that are combined with the cast-in-place pile 106 of the lower hooking mount part 104 connected to the bedrock and each post column 210 and the coupling block 409 As a composite caisson core wall structure with mechanical and structural stability combined with the support 601, it can exhibit excellent response performance to vertical and horizontal loads.

해상활주로로써 상판(101)과 하부슬래브(103)사이에 형성된 부대시설공간 (108)은 별도의 공정이나 건축비가 소요됨 없이 자동적으로 생성되어져 공항의 부대시설과 주차장등으로 활용할 수 있다.As an offshore runway, the auxiliary facility space 108 formed between the upper plate 101 and the lower slab 103 is automatically generated without requiring a separate process or construction cost, and can be used as an auxiliary facility of the airport and a parking lot.

해상작업시 제일 애로를 겪는 해상작업발판을 선 구축하여 후속공사를 원활하게 진행할 수 있는 작업거점을 확보할수 있으므로, 매립식과 연결시 해안선에서부터 매립해 나오는 통상적인 방법과 달리 매립식의 종점부분에 선시공된 복합벽체 케이슨(105)을 설치함으로, 매립고착점이 형성됨으로 활주로 시점부분에 마운드조성을 생략할 수 있고, 그 구역을 기반으로 성토를 할 수 있으므로 매립작업의 효율성을 기할 수 있다.Unlike the usual method of reclamation from the shoreline when connecting with the reclamation type, it is possible to secure a work base that can smoothly proceed by pre-establishing an offshore working scaffold that suffers the most difficulties during offshore work. By installing the composite wall caisson 105, it is possible to omit the mound composition at the point of view of the runway due to the formation of the buried fixing point, and since the embankment can be performed based on the area, the efficiency of the reclamation operation can be achieved.

따라서, 도 1 에 도시된 바와 같이 본 발명은 해저면의 지층 및 지형에 큰 구애됨이 없이 해저면 경사도가 심한곳(116)이나 요철이 심한곳(117), 단차가 많이 발생하는 부분(119)에서도 설치가 가능하므로, 매립식으로 축조된 계류장(102)과도 연결시공이 용이한 것이며 연약지반에 의한 부등 침하우려를 사전에 제거할 수 있는 것이다.Therefore, as shown in Figure 1, the present invention is a place where the slope of the sea floor is severe 116, the place where the unevenness is severe 117, and the part where the step 119 has a lot of steps without being largely concerned with the stratum and topography of the sea floor. ) Can also be installed, so it is easy to connect with the apron 102 built in a buried type, and it is possible to remove the concerns of unequal settlement due to the soft ground in advance.

도 14 에 도시된 바와 같이, 하부후팅 마운드부(104)를 해저면 지지층에 밀착 침설시키고, 이와 결합된 현장타설말뚝(106)을 기반암에 접속(socketing)시켜 내진적응력을 향상시킴과 결합형 블럭(409)마다 말뚝보강지지대(601)를 설치하고, 그 내부를 고결화된 충진재로 자중을 늘림으로 코어벽체 구조물의 복합벽체 케이슨(105)의 역학적 안정성을 확보하고 복층으로 된 연속보와 슬래브를 설치할 수 있는 구조인 것이다.As shown in Fig. 14, the lower hooking mount part 104 is closely immersed in the support layer on the sea floor, and the in-situ pile 106 combined with it is connected to the bedrock to improve seismic adaptation and a combined block A pile reinforcement support 601 is installed for each 409, and its internal weight is increased with a solidified filler to secure the mechanical stability of the composite wall caisson 105 of the core wall structure, and a continuous beam and slab made of double layers are It is a structure that can be installed.

어떤 지형에서나 착공이 가능하고 공구를 분할이 용이하며 동시 다발적인 시공이 가능하다. 해저면에 침설된 하부후팅 마운드부와 복합벽체 케이슨의 코어벽체에 부착되어있는 연결고리 등은 바지선등 작업선단의 계류시설로도 활용이 가능하여 해상작업 효율을 높일수 있으므로 공기를 단축할수 있다.Construction can be started on any terrain, it is easy to divide the tool, and simultaneous construction is possible. The lower hooking mount in the bottom of the seabed and the link attached to the core wall of the composite wall caisson can be used as a mooring facility for work fleets such as barges, which can increase the efficiency of offshore work, thus reducing the construction period.

각종 환경외력 대응력이 우수하므로 추후 발생할 수 있는 해상활주로 폭확장 및 증설시에도 유리한 공법인 것이다. 또한, 그 하부공간은 대규모의 그늘진 어패류 서식장이 형성되어져 인근어장의 소득증대를 기할 수 있어 민원해소에 도움이 된다.As it has excellent response to various external forces, it is an advantageous construction method for expanding and expanding the width of an offshore runway that may occur in the future. In addition, a large-scale shady fish and shellfish habitat is formed in the lower space, which can increase the income of nearby fishing grounds, which helps in resolving civil complaints.

본 발명의 해상활주로용 복합케이슨의 코어(core)벽체 구조물를 실시하기 위한 구체적인 내용에는 본 발명의 바람직한 실시예를 참조하여 설명하였지만, 해당 기술 분야의 당업자라면 후술 될 특허청구 범위에 기재된 발명의 사상 및 기술 영역으로부터 벗어나지 않는 범위 내에서 본 발명을 다양하게 수정 및 변형시킬 수 있음을 이해할 수 있을 것이다.Specific details for implementing the core wall structure of the composite caisson for a marine runway of the present invention have been described with reference to preferred embodiments of the present invention, but those skilled in the art will have the spirit of the invention described in the claims to be described later. It will be appreciated that various modifications and variations can be made to the present invention without departing from the technical field.

101 : 해상활주로
102 : 계류장
103 : 하부슬래브
104 : 하부후팅 마운드부
105 : 복합벽체 케이슨
106 : 현장타설말뚝
107 : 기초사석부
108 : 부대시설공간
109 : 격자공간
110 : 사석경사제
111 : 피복석
112 : 근고블럭
113 : 통행구
114 : 해수유통구간
115 : 패널 존
116 : 경사가 급한 곳
117 : 요철이 심한 곳
118 : 협곡
119 : 단차가 심한곳
120 : 수중연속벽
101: sea runway
102: apron
103: lower slab
104: lower hooking mount
105: composite wall caisson
106: cast-in-place pile
107: Basic stone department
108: auxiliary facility space
109: grid space
110: sandstone slope
111: cloth stone
112: Geungo block
113: passage
114: Seawater distribution section
115: panel zone
116: steep slope
117: places with severe irregularities
118: Canyon
119: where the step is severe
120: underwater continuous wall

Claims (8)

경사 습한 곳과 요철이 심한 곳의 해저면 지지층에 확대기초 하부후팅 마운드부를 설치하여 연약지반 생성 소지를 사전에 없애고, 하부후팅 마운드부와 결합된 현장타설말뚝을 기반암에 접속시켜 지진파에 대한 적응력이 좋은 현장타설말뚝의 독립기초 지지와 확대기초로 복합벽체 구조물을 구축하여 세굴발생을 방지하는 지주기둥을 설치하고;
각종 환경외력을 감당할 수 있는 현장타설된 연결형 블럭, 단계별 블럭 및 결합형 블럭으로 형성된 복합벽체 케이슨의 지주기둥 위에 슬래브를 설치하고 내부공간을 확보해서 시설 및 부대공간으로 사용하고, 지주기둥이 설치된 곳을 제외한 구역은 해수가 유통될 수 있게 격자식으로 지주기둥을 설치하며 그위에 상판인 활주로를 설치하며;
해상 활주로 하부슬래브의 적재하중과 고정하중이 보를 통해 모여져서 지주기둥과 복합벽체 케이슨의 코어벽체로 전달되어 제반 축하중은 지주기둥을 타고 내려가 하부후팅 마운드부로 전달되고, 각 부재간 접합을 라멘구조로 강접하여 기둥과 보, 코어벽체가 서로 강하게 결속되어 수평하중을 극복하는 코어벽체를 하부후팅 마운드부와 직결된 벽체구조물의 본벽으로 사용되게 설치하며 상재하중을 분담하여 지주기둥의 피로도를 경감시킴으로 구조적 안정성을 확보한 것을 특징으로 하는 해상활주로용 복합케이슨의 코어(core)벽체 구조물.
By installing an expanded base lower hoisting mount on the seabed support layer in humid places and places with severe irregularities, the possibility of generating soft ground is eliminated in advance, and the in-situ piles combined with the lower hoisting mounds are connected to bedrock to increase adaptability to seismic waves. Constructing a composite wall structure as an independent foundation support and expansion foundation for good cast-in-place piles to install a pillar to prevent scouring;
A slab is installed on the pillars of the caisson, a composite wall formed of on-site connected blocks that can withstand various external forces, step-by-step blocks and combined blocks, and secured internal space to use as facilities and auxiliary spaces, and where the pillars are installed. In the area except for, a grid-type pillar is installed to allow seawater to flow, and a runway as a top plate is installed on it;
The loading and fixed loads of the lower slab of the offshore runway are collected through the beams and transmitted to the pillars and the core wall of the composite wall caisson. The core wall is installed to be used as the main wall of the wall structure directly connected to the lower hooking mount part as the pillar, beam, and core wall are strongly bonded to each other to overcome the horizontal load, and the overhead load is shared to reduce the fatigue of the pillar column. A core wall structure of a composite caisson for offshore runways, characterized in that securing structural stability.
제 1 항에 있어서,
상기 연결형 블럭은 한쪽은 짧고 한쪽은 길게 하여 긴 쪽과 짧은 쪽이 서로 교차되게 하여 현장타설말뚝을 감싸서 지주기둥을 형성할 수 있는 패널 존을 만들는 것을 특징으로 하는 해상활주로용 복합케이슨의 코어(core)벽체 구조물.
The method of claim 1,
The connecting block is a core of a composite caisson for a marine runway, characterized in that one side is short and one side is lengthened so that the long side and the short side intersect each other to form a panel zone that can form a pillar by wrapping on-site piles. A) wall structure.
제 2 항에 있어서, 장방향쪽에는 한쪽은 길게 한쪽은 짧고 경사지게 상기 연결형 블록은 장방향쪽으로 한쪽이 길게 따른 한쪽이 짧고 경사지게 하고, 연결형 블럭과 칸막이 블럭을 양쪽이 경사지게 연결형 블럭과 연결되게 설치해서 그 공간을 확보하며, 블럭 중앙에는 격자판을 넣어 양쪽에 수중연속벽을 조성할 수 있는 격자공간이 형성되는 것을 특징으로 하는 해상활주로용 복합케이슨의 코어(core)벽체 구조물.The method of claim 2, wherein one side is long in the long direction and one side is short and inclined, and the connecting block is installed so that one side is short and inclined in the long direction, and the connecting block and the partition block are obliquely connected to the connecting block. A core wall structure of a composite caisson for a marine runway, characterized in that the space is secured, and a grid space is formed in which a grid plate is placed in the center of the block to form an underwater continuous wall on both sides. 제 3 항에 있어서,
상기 결합형 블럭 벽체의 단부와 결합형 블럭과 결합된 지주기둥과, 연속보, 말뚝보강 지지대가 휨모메트를 분담하고 전단력은 코어벽체가 수용하는 것을 특징으로 하는 해상활주로용 복합케이슨의 코어(core)벽체 구조물.
The method of claim 3,
The core of the composite caisson for an offshore runway, characterized in that the end of the combined block wall and the post column, continuous beam, and pile reinforcement support combined with the combined block share the bending moment and the shear force is received by the core wall. A) wall structure.
제 1 항에 있어서,
상기 기반암에 접속된 하부후팅 마운드부로부터 단계적으로 단계별 블럭을 연결하여 완성시켜 나가고, 각 조립체의 연결고리와 좌, 우, 상, 하 연결밴드를 사용하여 단계별 블럭을 고정시켜 적층하는 것을 특징으로 하는 해상활주로용 복합케이슨의 코어(core)벽체 구조물.
The method of claim 1,
It characterized in that the step-by-step blocks are connected and completed step by step from the lower hooking mound connected to the bedrock, and the step-by-step blocks are fixed and stacked using a connection ring of each assembly and a left, right, upper and lower connection band. Core wall structure of composite caisson for offshore runway.
제 5 항에 있어서,
상기 결합형 블럭을 해수면위로 1 개단 높이위에 연속보들을 설치하고 슬래브를 설치하는 것을 특징으로 하는 해상활주로용 복합케이슨의 코어(core)벽체 구조물.
The method of claim 5,
The core wall structure of a composite caisson for an offshore runway, characterized in that the combined block is installed with continuous beams above the sea level and above the height of one step, and a slab is installed.
제 5 항에 있어서,
상기 기반암에 접속된 하부후팅 마운드부의 현장타설말뚝과 각 지주기둥간과 결합형 블럭과 결합된 말뚝보강지지대와 결합되어 역학적, 구조적 안정성을 갖는 것을 특징으로 하는 해상활주로용 복합케이슨의 코어(core)벽체 구조물.
The method of claim 5,
The core wall of the composite caisson for offshore runways, characterized in that it has mechanical and structural stability by being combined with the in-situ pile of the lower hooking mound connected to the bedrock and the pile reinforcement support combined with the linkage block and between each post column structure.
제 1 항에 있어서,
상기 하부후팅 마운드부(를 해저면 지지층에 밀착 침설시키고, 이와 결합된 현장타설말뚝을 기반암에 쇼켓팅시켜 내진적응력을 향상시킴과 결합형 블럭마다 말뚝보강지지대를 설치하며, 그 내부를 고결화된 충진재로 자중을 늘림으로 코어벽체 구조물인 복합벽체 케이슨의 역학적 안정성을 확보하고 복층으로 된 연속보와 슬래브를 설치한 것을 특징으로 하는 해상활주로용 복합케이슨의 코어(core)벽체 구조물.
The method of claim 1,
The lower hooking mound is closely immersed in the support layer on the sea floor, and the combined on-site piles are shocked to the bedrock to improve seismic adaptation, and a pile reinforcement support is installed for each combined block, and the interior is solidified. A core wall structure of a composite caisson for a marine runway, characterized in that the mechanical stability of the composite wall caisson, which is a core wall structure, is secured by increasing its own weight with a filler, and a continuous beam and slab are installed.
KR1020190131126A 2019-10-22 2019-10-22 Core wall structure of composite cassion for offshore runway KR102294870B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190131126A KR102294870B1 (en) 2019-10-22 2019-10-22 Core wall structure of composite cassion for offshore runway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190131126A KR102294870B1 (en) 2019-10-22 2019-10-22 Core wall structure of composite cassion for offshore runway

Publications (2)

Publication Number Publication Date
KR20210047481A true KR20210047481A (en) 2021-04-30
KR102294870B1 KR102294870B1 (en) 2021-08-26

Family

ID=75740565

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190131126A KR102294870B1 (en) 2019-10-22 2019-10-22 Core wall structure of composite cassion for offshore runway

Country Status (1)

Country Link
KR (1) KR102294870B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20220412030A1 (en) * 2020-03-10 2022-12-29 Yujoo Co., Ltd. Construction method for underwater concrete block structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0835210A (en) * 1994-07-22 1996-02-06 Shimizu Corp Tower-like structure and construction method thereof
JP2000120081A (en) * 1998-10-19 2000-04-25 Kajima Corp Slope footing structure
CN205035966U (en) * 2015-09-24 2016-02-17 淮南金科再生资源利用有限公司 Building garbage recovery insulating brick
KR20160080028A (en) * 2014-12-29 2016-07-07 김상훈 Multipurpose artifical island

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0835210A (en) * 1994-07-22 1996-02-06 Shimizu Corp Tower-like structure and construction method thereof
JP2000120081A (en) * 1998-10-19 2000-04-25 Kajima Corp Slope footing structure
KR20160080028A (en) * 2014-12-29 2016-07-07 김상훈 Multipurpose artifical island
CN205035966U (en) * 2015-09-24 2016-02-17 淮南金科再生资源利用有限公司 Building garbage recovery insulating brick

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20220412030A1 (en) * 2020-03-10 2022-12-29 Yujoo Co., Ltd. Construction method for underwater concrete block structure
US11933011B2 (en) * 2020-03-10 2024-03-19 Yujoo Co., Ltd. Construction method for underwater concrete block structure

Also Published As

Publication number Publication date
KR102294870B1 (en) 2021-08-26

Similar Documents

Publication Publication Date Title
CN108914931B (en) Assembled vertical shield annular foundation pile and construction method
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN102444142A (en) Pile group column replacement expanded basement and construction method of same
CN210104758U (en) Foundation pit supporting system of soil nail bored concrete pile anchor cable combination
CN110374111B (en) Slope releasing and steel pipe pile anchor cooperative supporting system
CN104818728A (en) Permanent supporting system with basement floor and supporting piles capable of working together
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
KR20120012504A (en) Cast in place concrete pile With precast type Caisson
US7025537B2 (en) Subterranean structures and methods for constructing subterranean structures
KR102294871B1 (en) Core wall structure method of the independent cassion for offshore runway
CN113417300B (en) Slope support system and construction method thereof
KR20150110237A (en) Construction structures with wave power generator of semipermeable breakwater
KR102294870B1 (en) Core wall structure of composite cassion for offshore runway
CN102605801A (en) Suspension semi-reverse-construction method for underground circular water tank
JP7149919B2 (en) Improvement structure and improvement method of existing wharf
JPH06146305A (en) Underwater foundation and installation method thereof
TW201741529A (en) Method for constructing advanced pavement for preventing construction site collapse before construction of diaphragm wall in which support piles are first established and grid beams are welded to tops of the piles for supporting grouting and forming of a concrete pavement thereon
KR100493516B1 (en) Micro pile and assembly foundation reinforcement structure member and its method for pier
RU59650U1 (en) SEISMIC RESISTANT SMALL BUILDING, STRUCTURE
KR101058628B1 (en) Retaining wall construction structure using landscape stones
CN219158994U (en) Deep soft soil area ultra-deep large-diameter round pipe jacking working well foundation pit supporting structure
KR20150105891A (en) The underground facilities for offshore airfield of semi land reclamation type
CN213625630U (en) Deep soft soil area large-span channel side slope supporting construction
RU2807350C1 (en) Constructive and technological solution for foundation of intermediate support of high pile work type constructed in temporary enclosing structure
JP2566867B2 (en) Dam

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant