TW201741529A - Method for constructing advanced pavement for preventing construction site collapse before construction of diaphragm wall in which support piles are first established and grid beams are welded to tops of the piles for supporting grouting and forming of a concrete pavement thereon - Google Patents

Method for constructing advanced pavement for preventing construction site collapse before construction of diaphragm wall in which support piles are first established and grid beams are welded to tops of the piles for supporting grouting and forming of a concrete pavement thereon Download PDF

Info

Publication number
TW201741529A
TW201741529A TW105115362A TW105115362A TW201741529A TW 201741529 A TW201741529 A TW 201741529A TW 105115362 A TW105115362 A TW 105115362A TW 105115362 A TW105115362 A TW 105115362A TW 201741529 A TW201741529 A TW 201741529A
Authority
TW
Taiwan
Prior art keywords
construction
pavement
pile
support
piles
Prior art date
Application number
TW105115362A
Other languages
Chinese (zh)
Other versions
TWI623669B (en
Inventor
Zheng Xiong Hong
Cai Ming Cai
Original Assignee
Saint Land Construction Eng Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Saint Land Construction Eng Corp filed Critical Saint Land Construction Eng Corp
Priority to TW105115362A priority Critical patent/TWI623669B/en
Publication of TW201741529A publication Critical patent/TW201741529A/en
Application granted granted Critical
Publication of TWI623669B publication Critical patent/TWI623669B/en

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

A method for constructing advanced pavement for preventing a construction site collapse before construction of a diaphragm wall is generally applicable to construction of concrete pavement on a construction foundation of soft earth to form a safety floor for construction. The prevent invention generally includes first driving support piles for excavating ground before construction of a diaphragm wall and using the support piles as a vertical support for advanced construction of concrete pavement on the construction base so as to form a floor having capability of supporting on a ground surface of an earth base that is originally weak. Steps of construction according to the present invention include: applying and establishing support piles, welding and fixing steel plates to tops of the support piles, constructing grid beams and/or reinforced steel bar network between tops of adjacent ones of the support piles, constructing a pavement steel bar network, and grouting concrete to form a safe construction concrete pavement to form a floor that is capable of preventing collapse of construction site. The concrete pavement may serve as improved floor for the base. In subsequent construction of a diaphragm wall, there is no need to apply overall earth modification and making earth modification at the site of an edge of a gutter alone is sufficient to prevent collapse of the gutter and an excavation trough so as to obtain good quality of diaphragm wall construction.

Description

連續壁施工前防止工地下陷的先行鋪面的施工方法 Construction method for preventing premature pavement of workers before underground wall construction

本發明涉及一種連續壁施工前防止工地下陷的先行鋪面的施工方法,其主要解決土質軟弱、土壤有液化現象、土壤含有水量高的基地在施作連續壁工程中,防止地層下陷與連續壁挖掘槽坍方的問題。 The invention relates to a construction method for preventing premature sag of a working face before continuous wall construction, which mainly solves the problem that the soil is weak, the soil has liquefaction, and the soil containing high water content is applied in the continuous wall project to prevent formation subsidence and continuous wall excavation. The problem with the slot side.

現今連續壁連續壁的基礎越做越深,所以有扶壁、橫隔壁等配套設計。此種有扶壁、橫隔壁配套設計的連續壁施工,會導致施工基地被切割若干個小體,破壞原有施工地坪的完整性,造成軟弱地層的施工環境。 Nowadays, the foundation of the continuous wall of the continuous wall is deeper and deeper, so there are supporting designs such as buttress and transverse partition. Such continuous wall construction with buttress and transverse partition design will cause the construction base to be cut into several small bodies, destroying the integrity of the original construction floor and causing the construction environment of the weak formation.

土壤液化也會造成地層下陷。原本為池塘、水坑,再回填成地面的地層,因含水量高。當重型機具進駐此類施工基地後,也會造成地坪下陷,地下水滲出地表。 Soil liquefaction also causes the formation to sink. Originally a pond, a puddle, and then backfilled into the ground, due to high water content. When heavy machinery is stationed in such a construction base, it will also cause the floor to sink and groundwater seep out of the surface.

在地層軟弱的施工基地進行連續壁施工,必須在導溝邊做樁徑施工,進行地坪改造,避免挖掘時造成導溝或/及挖掘槽坍方。另外,由於施工基地的地層屬軟弱地質,連需必施工前必須做全面地質改良強化工程,增加施工成本,也增加未來開挖時的困難度。假若施工單位的地質改良強化工程不確實,在重型機具進入基地後容易造成地層下陷,甚至令連續壁挖掘槽發生坍方情形。 For the continuous wall construction in the weak construction base, the pile diameter construction must be carried out at the side of the guide groove to carry out the floor reconstruction to avoid the guide groove or/and the excavation groove. In addition, since the stratum of the construction base is weak and geological, it is necessary to do comprehensive geological improvement and reinforcement projects before construction, increase construction costs, and increase the difficulty in excavation in the future. If the geological improvement and strengthening project of the construction unit is not correct, it will easily cause the formation to sink after the heavy machinery enters the base, and even the continuous wall excavation tank will be in an awkward situation.

當施工基地發生地坪下陷時,容易損及鄰房建築,增加後續 的法律與賠償事件。地坪下陷時,若有工作人員正在工地工作或操作機具,就會發生傷人或致死的工安事件。連續壁挖掘槽的坍方,就必須回填還需進行地質改良才能重新挖掘,既增加工時,也影響連續壁施工品質。如何在軟弱地質的施工基地上,以安全、可靠的施工方式來必避免地坪下陷,提高連續壁施工品質,是業者汲汲所求者。 When the grounding subsidence occurs in the construction base, it is easy to damage the adjacent building and increase the follow-up Legal and compensation events. When the ground subsides, if a staff member is working on the construction site or operating the machine, there will be an incident of injury or death. The back side of the continuous wall excavation tank must be backfilled and further geological improvement is required to re-excavate, which not only increases the working hours but also the quality of the continuous wall construction. How to avoid the floor subsidence and improve the quality of continuous wall construction in a soft and geological construction base with safe and reliable construction methods is the industry's demand.

為了解決前述軟質地層的連續壁施工問題,申請人乃提供一種連續壁施工前防止工地下陷的先行鋪面的施工方法,以提高施工基地的地坪強度,避免發生地坪坍方問題。 In order to solve the problem of continuous wall construction of the soft formation mentioned above, the applicant provides a construction method for preventing the underground pavement of the construction site before the continuous wall construction, so as to improve the floor strength of the construction base and avoid the problem of the floor slab.

本發明所提供之連續壁施工前防止工地下陷的先行鋪面的施工方法,能夠進一步地強化導溝強度,使降低對導溝做樁徑施工的數量,以縮減工期,可降低施工成本。 The construction method for preventing the underground pavement before the continuous wall construction provided by the invention can further strengthen the strength of the guide groove, so as to reduce the number of pile diameter construction of the guide groove, thereby reducing the construction period and reducing the construction cost.

本發明所提供之連續壁施工前防止工地下陷的先行鋪面的施工方法,主要在連續壁施作前先行施打地面開挖用支撐樁,並利用該支撐樁作為施工基地的混凝土鋪面的垂直承載支撐,而在原本軟弱地層基地的地表形成炬承載能力的地坪。則施作連續壁工程時,只需在導溝邊做重點地改,即可防止該溝槽與挖掘槽發生坍塌的情形,以獲致良好品質的連續壁工程。 The construction method for preventing the underground pavement of the underground subsidence before the continuous wall construction provided by the invention mainly applies the support pile for ground excavation before the continuous wall is applied, and uses the support pile as the vertical load of the concrete pavement of the construction base Support, and the surface of the original weak formation base forms the floor of the torch carrying capacity. When it is applied as a continuous wall project, it is only necessary to make a key change in the guide groove to prevent the groove and the excavation groove from collapsing, so as to obtain a good quality continuous wall project.

本發明施工前先於施工基地上確認建物放樣,連續壁施作設計,以及支撐樁位置與數量。其施工步驟包含:施打支撐樁、支撐樁的樁頂焊固鋼板、於相鄰支撐樁的樁頂與樁頂之間施作格子樑或/及加強鋼筋網、澆注混凝土形成鋪面、完成該混凝土鋪面。該混凝土鋪面即為基地改 善後的地坪。 Before the construction of the invention, the construction stakeout is confirmed on the construction base, the design of the continuous wall is applied, and the position and quantity of the support piles. The construction steps include: applying the support pile, the pile top welded steel plate of the support pile, applying the lattice beam or/and reinforcing the steel mesh between the pile top and the pile top of the adjacent support pile, pouring the concrete to form the pavement, and completing the Concrete pavement. The concrete pavement is the base change The floor of the aftermath.

前述相鄰支撐樁的樁頂與樁頂之間施作格子樑或/及加強鋼筋網,以構成鋪面的內部結構。該支撐樁頂與樁頂端的鋼板,即為施作格子樑/及加強鋼筋網的搭接面與承載點。則該各支撐樁即為該混凝土鋪面的垂直承載支撐。 A lattice beam or/and a reinforcing mesh is applied between the pile top of the adjacent support pile and the top of the pile to form an internal structure of the pavement. The steel plate at the top of the supporting pile and the top of the pile is the overlapping surface and bearing point of the lattice beam/reinforced mesh. Then the support piles are the vertical bearing support of the concrete pavement.

該支撐樁上的的鋼板可以是一公尺見方的方形板,也可以直徑一公尺的圓形板。 The steel plate on the support pile may be a square plate of one square square or a circular plate of one meter diameter.

憑藉該於相鄰支撐樁的樁頂之間格子樑、加強鋼筋網的高度,來決定鋪面的厚度,以及決定該鋪面的承載能力。 The thickness of the pavement is determined by the height of the lattice beam between the pile tops of the adjacent support piles and the reinforcing mesh, and the bearing capacity of the pavement is determined.

10‧‧‧連續壁位置 10‧‧‧Continuous wall location

11‧‧‧扶壁位置 11‧‧‧Bottom position

20‧‧‧支撐樁 20‧‧‧Support pile

21‧‧‧鋼板 21‧‧‧ steel plate

22‧‧‧格子樑 22‧‧‧ lattice beam

23‧‧‧鋼筋網 23‧‧‧ steel mesh

30‧‧‧土壤 30‧‧‧ soil

40‧‧‧鋪面 40‧‧ ‧ pavement

41‧‧‧鋪面鋼筋網 41‧‧‧Pavement mesh

步驟a‧‧‧施打支撐樁 Step a‧‧‧ hitting support pile

步驟b‧‧‧於支撐樁的樁頂焊固鋼板 Step b‧‧‧ Welded steel plate at the top of the pile

步驟c‧‧‧於相鄰支撐樁的樁頂格子樑或/及加強鋼筋 Step c‧‧‧Segmented lattice beams or/and reinforcing bars on adjacent support piles

步驟d‧‧‧施作鋪面鋼筋網 Step d‧‧‧ applied as a pavement mesh

步驟e‧‧‧澆注混凝土形成鋪面 Step e‧‧‧casting concrete to form a pavement

步驟f‧‧‧完成混凝土鋪面 Step f‧‧‧Complete concrete paving

圖一為本發明施工方法的施工流程。 Figure 1 shows the construction process of the construction method of the present invention.

圖二為連續壁施作設計及支撐樁設計工程圖。 Figure 2 shows the design of the continuous wall and the design of the support pile design.

圖三為支撐樁打入基地土壤內的剖示圖。 Figure 3 is a cross-sectional view of the support pile driven into the soil of the base.

圖四為支撐樁打入基地土壤內的外觀圖。 Figure 4 shows the appearance of the support pile into the soil of the base.

圖五為支撐樁的樁頂焊固鋼板的外觀圖。 Figure 5 is an external view of the pile top welded steel plate of the supporting pile.

圖六為支撐樁的樁頂焊固鋼板的縱向剖示圖 Figure 6 is a longitudinal sectional view of the pile top welded steel plate of the supporting pile

圖七為支撐樁的樁頂格子樑及加強鋼筋的示意圖。 Figure 7 is a schematic view of the pile top lattice beam and the reinforcing steel reinforcement of the support pile.

圖八為支撐樁的樁頂格子樑的縱向剖示圖。 Figure 8 is a longitudinal cross-sectional view of the pile top lattice beam of the support pile.

圖九為混凝土鋪面的剖示圖。 Figure 9 is a cross-sectional view of a concrete pavement.

在連續壁施工時,容易發生地坪下陷的基地,大都屬於地層軟弱的地區,或者是因為基地地形過小或過於狹窄,造成重機過於集中而 造成地坪局部下陷。對於容易發生地坪下陷的基地,必須做全盤地改,以提高地層強度。申請人緣於對基地做全盤地改,會延長工期、增加成本,乃研發一種連續壁施工前防止工地下陷的先行鋪面施工方法。 In the continuous wall construction, the bases that are prone to land subsidence are mostly in areas with weak formations, or because the terrain of the base is too small or too narrow, causing the heavy machine to be too concentrated. Caused a partial subsidence of the floor. For bases that are prone to land subsidence, a comprehensive reform must be done to increase the strength of the formation. The applicant's decision to do a comprehensive reform of the base will extend the construction period and increase the cost. It is a method for constructing a prefabricated pavement to prevent underground subsidence before continuous wall construction.

本發明施工方法的主要思維,是在基地上先行鋪設具有高承載能力的鋪面,憑藉該鋪面來承載重型機具,以及強化導溝的強度。 The main idea of the construction method of the present invention is to lay a pavement with high load carrying capacity on the base first, and to carry heavy equipment and strengthen the strength of the guide groove by virtue of the pavement.

當施工基地的地層為軟弱土壤,若直接將鋪面直接鋪設在地面上,該鋪面必會因地層下陷而破裂,無法達到承載機具以及防止地坪下陷的目的。然而,傳統的連續壁施工在連續壁施工完成後,就會在基地內作地面開挖。地面開挖前要先在基地內放置多數個支撐樁,以支撐連續壁,才可進行地面開挖工程。本發明就是以該各支撐樁提前先行施工作為舖面之底部承載支撐。 When the stratum of the construction base is weak soil, if the pavement is directly laid on the ground, the pavement will be broken due to the subsidence of the stratum, and it is impossible to achieve the purpose of carrying the implements and preventing the subsidence of the ground. However, the traditional continuous wall construction will be grounded in the base after the continuous wall construction is completed. Before the ground excavation, a large number of supporting piles should be placed in the base to support the continuous wall before the ground excavation works can be carried out. In the invention, the support piles are advanced in advance as the bottom bearing support of the pavement.

請參閱圖一及圖二。本發明施工前,先於施工基地上確認建物位置放樣,連續壁施作位置10設計,包含扶壁11位置設計,以及支撐樁20位置與數量。本發明施工步驟: Please refer to Figure 1 and Figure 2. Before the construction of the invention, the construction site is confirmed to be staked out on the construction base, and the continuous wall is applied to the position 10 design, including the position design of the buttress 11 and the position and number of the support pile 20. Construction steps of the invention:

a.施打支撐樁20: a. Strike support pile 20:

將各支撐樁20打入基地的土壤30內,如圖三、圖四所示。該各支撐樁20的樁頂高度即為施作混凝土鋪面40(見圖九)的下方高程。 Each support pile 20 is driven into the soil 30 of the base, as shown in FIG. 3 and FIG. The pile top height of each of the support piles 20 is the lower elevation of the concrete pavement 40 (see Fig. 9).

b.於支撐樁20的樁頂焊固鋼板21: b. The top of the support pile 20 is welded to the steel plate 21:

該各支撐樁20的樁頂焊固鋼板21,如圖五、圖六所示。該鋼板21可為一公尺見方的方形板,也可以為直徑一公尺的圓形板。該鋼板21的尺寸大小,視施工需要可做適當的改變。 The pile top welded steel plate 21 of each of the support piles 20 is as shown in FIG. 5 and FIG. The steel plate 21 may be a square plate of one meter square or a circular plate of one meter diameter. The size of the steel sheet 21 can be appropriately changed depending on the construction needs.

c.於相鄰支撐樁20的樁頂之間施作格子樑22或/及加強鋼筋網23: c. Applying a lattice beam 22 or/and a reinforcing mesh 23 between the pile tops of adjacent support piles 20:

相鄰支撐樁20的樁頂之間施作格子樑22或/及加強鋼筋網23,以構成鋪面的內部結構之一部分,如圖七、圖八所示。該支撐樁20頂端的鋼板21,可做為施作格子樑22、加強鋼筋網23的搭接面,以提高鋪面的結構強度。亦可憑藉該於相鄰支撐樁20的樁頂之間的格子樑22、加強鋼筋網23的高度,來決定混凝土鋪面40的厚度,來提高該混凝土鋪面40的承載能力。 A lattice beam 22 or/and a reinforcing mesh 23 are applied between the pile tops of adjacent support piles 20 to form part of the internal structure of the pavement, as shown in FIGS. 7 and 8. The steel plate 21 at the top of the support pile 20 can be used as a lap joint of the lattice beam 22 and the reinforcing steel mesh 23 to improve the structural strength of the pavement. The thickness of the concrete deck 40 can also be determined by the height of the lattice beam 22 between the pile tops of the adjacent support piles 20 and the height of the reinforcing mesh 23 to improve the load carrying capacity of the concrete deck 40.

d.施作鋪面鋼筋網41: d. Application of paving reinforcement mesh 41:

於前述各支撐樁20樁頂之間所施作格子樑22或/及加強鋼筋網23的上方,施作原設計的鋪面鋼筋網41。 The pavement reinforcement mesh 41 of the original design is applied above the lattice beam 22 or/and the reinforcing steel mesh 23 between the pile tops of the respective support piles 20.

e.澆注混凝土形成鋪面40: e. Pouring concrete to form pavement 40:

於該施工基地內澆注混凝土,以覆蓋各支撐樁20、格子樑22、加強鋼筋網23、以及原設計的鋪面鋼筋網41,而形成混凝土鋪面40。 Concrete is poured into the construction base to cover each of the support piles 20, the lattice beams 22, the reinforcing steel mesh 23, and the original design of the pavement reinforcement mesh 41 to form a concrete pavement 40.

f.完成該混凝土鋪面: f. Complete the concrete pavement:

該混凝土鋪面40即為改善後的地坪。 The concrete pavement 40 is the improved floor.

本發明所施作完成的鋪面40,其垂直支撐為各支撐樁20。該各支撐樁20為地面順打開挖的支撐結構,其支撐強度設計,已經考慮到地下層完全開挖後,依然能夠保有足夠安全係數的支撐強度。本發明所完成的混凝土鋪面40,除了支撐樁20原本設計的安全支撐係數外,因為地面為未開挖狀態,所以更增加了土壤30對支撐樁20的摩擦支撐。故該混凝土鋪面40的垂直支撐強度有很高的安全係數。 The pavement 40 which is completed by the present invention is vertically supported by each support pile 20. The support piles 20 are support structures for the ground to open and excavate, and the support strength design thereof has been considered to maintain the support strength with sufficient safety factor after the underground layer is completely excavated. The concrete pavement 40 completed by the present invention not only has the safety support coefficient originally designed by the support pile 20, but also increases the friction support of the soil 30 to the support pile 20 because the ground is in an unexcavated state. Therefore, the vertical support strength of the concrete pavement 40 has a high safety factor.

本發明施作完成的混凝土鋪面40,具有高承載能力,足以承載重型機具的重量,使得基地地坪(混凝土鋪面)不會因機具重量而坍方。亦即,基地地坪會保持強度。 The concrete pavement 40 which is completed by the present invention has high load carrying capacity and is sufficient to carry the weight of the heavy machine so that the base floor (concrete paving) does not collapse due to the weight of the implement. That is, the base floor will maintain its strength.

原本在軟弱地層施作連續壁工程,為了防止導溝坍塌,必須在導溝邊多處施作地改樁。在使用本發明方法鋪設混凝土鋪面40的施工基地,因地坪不會坍方,導溝自然就發生坍塌的機率自然大幅降低。因此,業者只需在導溝邊較易發生坍塌處(如轉角處)做局部地改(施作地改樁),自然大幅縮減連續壁施工工期,降低施工成本。 Originally applied to the continuous wall project in the weak stratum, in order to prevent the guide groove from collapsing, it is necessary to apply the ground to the pile at several locations along the guide groove. In the construction base where the concrete pavement 40 is laid by the method of the present invention, since the floor does not collapse, the probability of the guide groove naturally collapsing is naturally greatly reduced. Therefore, the operator only needs to make a partial change (applied to the ground) in the collapse of the guide groove (such as the corner), which naturally reduces the construction period of the continuous wall and reduces the construction cost.

使用本發明工法先行鋪設混凝土鋪面40後,有下列的優點: After laying the concrete pavement 40 first by using the method of the present invention, the following advantages are obtained:

1.混凝土鋪面40能夠承載重型機具,使地坪不會因機具重量而發生下陷或坍塌的情事。 1. The concrete pavement 40 can carry heavy machinery so that the floor does not sag or collapse due to the weight of the implement.

2.不用作全面地改,可省下全面地改的施工工期,與施工成本。 2. It is not used for comprehensive reform, which can save the construction period and construction cost of comprehensively reformed.

3.可減少連續壁導溝地改邊樁的數量,可減少施工成本、與縮短施工工期。 3. It can reduce the number of side-strained piles in continuous wall guide ditch, which can reduce construction cost and shorten construction period.

4.可減少地坪下陷、連續壁導溝坍方的情形,可減少損鄰的事件。 4. It can reduce the situation of floor subsidence and continuous wall guide ditch, which can reduce the incidents that damage the neighbors.

5.由於不易發生地坪下陷、連續壁導溝坍方的情形,進而可提高連續壁的施工品質,使建築物品質獲得保證。 5. Since the floor subsidence and the continuous wall guide groove are not easy to occur, the construction quality of the continuous wall can be improved, and the quality of the building can be ensured.

6.在施工過程中,工地不易發生下陷、坍方的情事,有助於敦親睦鄰,同時可提升企業形象。 6. During the construction process, the construction site is not prone to sag and squatting, which helps the neighbors and neighbors, and at the same time enhances the corporate image.

綜上所陳,本發明選擇在連續壁施作前,即先行施打支撐樁20,為一種前所未見的施工思維。本發明利用該支撐樁20作為混凝土鋪面40的垂直承載支撐,也有別於傳統鋪面的結構,也是一種垂直支撐更為可靠的鋪面40。故,憑藉本發明工法所施作的混凝土鋪面40作為基地的地坪,可使軟弱地層的基地也能在安全、可靠的施工過程,獲致良好品質的連續壁工程。 In summary, the present invention selects the support pile 20 before the continuous wall is applied, which is an unprecedented construction thinking. The present invention utilizes the support pile 20 as a vertical load-bearing support for the concrete pavement 40, and also has a structure different from the conventional pavement, and is also a more reliable pavement 40 for vertical support. Therefore, by using the concrete pavement 40 applied by the method of the present invention as a base floor, the base of the weak formation can also obtain a good quality continuous wall project in a safe and reliable construction process.

雖然本發明以實施方式揭露如上,然其並非用以限定本發 明,任何熟悉此項技術的人員,在不脫離本發明的精神和範圍內,可作各種的改動與潤飾,因此本發明的保護範圍當以申請專利範圍所定為准。 Although the present invention has been disclosed above in the embodiments, it is not intended to limit the present invention. It is to be understood that any person skilled in the art can make various modifications and changes without departing from the spirit and scope of the invention, and the scope of the invention is defined by the scope of the patent application.

步驟a‧‧‧施打支撐樁 Step a‧‧‧ hitting support pile

步驟b‧‧‧於支撐樁的樁頂焊固鋼板 Step b‧‧‧ Welded steel plate at the top of the pile

步驟c‧‧‧於相鄰支撐樁的樁頂之間施作格子樑或/及加強鋼筋網 Step c‧‧‧ Applying lattice beams or/and reinforcing meshes between the pile tops of adjacent support piles

步驟d‧‧‧施作鋪面鋼筋網 Step d‧‧‧ applied as a pavement mesh

步驟e‧‧‧澆注混凝土形成鋪面 Step e‧‧‧casting concrete to form a pavement

步驟f‧‧‧完成該混凝土鋪面 Step f‧‧‧ Complete the concrete pavement

Claims (4)

一種連續壁施工前防止工地下陷的先行鋪面的施工方法,其施工前先於施工基地上確認建物位置放樣,連續壁施作設計,以及支撐樁位置與數量;其施工步驟為:a.施打支撐樁:將各支撐樁打入基地的土壤內;各支撐樁的樁頂高度即為施作混凝土鋪面的下方高程;b.於支撐樁的樁頂焊固鋼板:該各支撐樁的樁頂皆焊固鋼板;c.於相鄰支撐樁的樁頂之間施作格子樑或/及加強鋼筋網:相鄰支撐樁的樁頂之間施作格子樑或/及加強鋼筋網,以構成鋪面的內部結構之一部分;該支撐樁頂端的鋼板,即為格子樑、加強鋼筋的搭接面;d.施作鋪面鋼筋網:於前述各支撐樁樁頂之間所施作格子樑或/及加強鋼筋網的上方,施作原設計的鋪面鋼筋網;e.澆注混凝土形成鋪面:於該施工基地內澆注混凝土,以覆蓋各支撐樁、格子樑、鋼筋網而形成混凝土鋪面;f.完成該混凝土鋪面:該混凝土鋪面即為改善後的地坪。 A construction method for preventing premature sag of a building before continuous wall construction, which is to confirm the position of the building site, the design of the continuous wall, and the position and quantity of the supporting pile before the construction; the construction steps are: a. Support pile: the support piles are driven into the soil of the base; the pile top height of each support pile is the lower elevation of the concrete pavement; b. The pile top welded steel plate of the support pile: the pile top of each support pile All welded steel plates; c. Lattice beams or/and reinforced meshes are placed between the pile tops of adjacent support piles: lattice beams or/and reinforcing meshes are applied between the pile tops of adjacent support piles to form a part of the internal structure of the pavement; the steel plate at the top of the support pile is the lattice joint of the lattice beam and the reinforcing steel; d. the pavement reinforcement mesh is applied: the lattice beam is applied between the tops of the aforementioned support piles or / And reinforcing the upper part of the steel mesh, applying the original design of the pavement reinforcement mesh; e. pouring the concrete to form the pavement: pouring concrete in the construction base to cover the support piles, the lattice beam and the steel mesh to form a concrete pavement; f. completing the mixing Condensate Pavement: The concrete pavement is the floor after improvement. 如申請專利範圍第1項所述之連續壁施工前防止工地下陷的先行鋪面施工方法,其步驟b中的鋼板為一公尺見方的方形板。 For example, in the prior art, the method for constructing the pre-construction method for preventing the underground subsidence before the continuous wall construction according to the first aspect of the patent application, the steel plate in the step b is a square plate of one square square. 如申請專利範圍第1項所述之連續壁施工前防止工地下陷的先行鋪面施工方法,其步驟b中的鋼板為直徑一公尺的圓形板。 For the prior paving construction method for preventing underground subsidence before continuous wall construction as described in the first paragraph of the patent application, the steel plate in the step b is a circular plate having a diameter of one meter. 如申請專利範圍第1項所述之連續壁施工前防止工地下陷的先行鋪面施工方法,其步驟c中,憑藉該於相鄰支撐樁的樁頂之間格子樑、加強鋼筋網的高度,來決定鋪面的厚度,以及決定該鋪面的承載能力。 For the first paving construction method for preventing underground subsidence before continuous wall construction as described in the first aspect of the patent application, in step c, by means of the lattice beam between the pile tops of adjacent supporting piles and the height of the reinforcing mesh, Determine the thickness of the pavement and determine the carrying capacity of the pavement.
TW105115362A 2016-05-18 2016-05-18 Construction method of advance pavement for preventing underground subsidence before continuous wall construction TWI623669B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW105115362A TWI623669B (en) 2016-05-18 2016-05-18 Construction method of advance pavement for preventing underground subsidence before continuous wall construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW105115362A TWI623669B (en) 2016-05-18 2016-05-18 Construction method of advance pavement for preventing underground subsidence before continuous wall construction

Publications (2)

Publication Number Publication Date
TW201741529A true TW201741529A (en) 2017-12-01
TWI623669B TWI623669B (en) 2018-05-11

Family

ID=61230165

Family Applications (1)

Application Number Title Priority Date Filing Date
TW105115362A TWI623669B (en) 2016-05-18 2016-05-18 Construction method of advance pavement for preventing underground subsidence before continuous wall construction

Country Status (1)

Country Link
TW (1) TWI623669B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI651452B (en) * 2018-02-13 2019-02-21 聖陸營造工程股份有限公司 Pavement construction method for preventing floor subsidence before construction of continuous wall and ground wall

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI753415B (en) * 2020-04-29 2022-01-21 聖陸營造工程股份有限公司 Construction Method of Constructing Continuous Wall Guide Ditch of New Building on the Old Underground Floor Structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW227029B (en) * 1992-07-14 1994-07-21 Chung Len Engineering Consultant Construction of deep-base, reverse constructing block soil construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI651452B (en) * 2018-02-13 2019-02-21 聖陸營造工程股份有限公司 Pavement construction method for preventing floor subsidence before construction of continuous wall and ground wall

Also Published As

Publication number Publication date
TWI623669B (en) 2018-05-11

Similar Documents

Publication Publication Date Title
CN205742213U (en) Foundation pit supporting construction
CN104846840B (en) A kind of shallow embedding reinforcement of soft soil integrated pipe canal device and construction method
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN106088127A (en) Open caisson construction method
CN110004919B (en) Foundation pit enclosure construction method used in pipeline influence range
CN108277818A (en) Basement top-down method Combined tower crane foundation structure and construction method
CN105178327A (en) Composite retaining structure of foundation pit project and construction method thereof
CN110159294B (en) Construction method for lengthening open cut tunnel at tunnel junction section of high and steep terrain bridge
CN108678751B (en) Assembly type construction method of shield cutter head manhole by jacking and excavating firstly
CN111305027B (en) Rapid repairing construction method and repairing structure for subsidence of karst area pavement
CN106013053A (en) Steel sheet pile support construction method for building underground garage open caisson
WO2023213117A1 (en) Widening structure and construction method for existing subgrade embankment wall section near river
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN207331740U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN102071698A (en) Construction method of beddings of foundation downward overturn beam and pile cap
CN101215840B (en) Airplane type foundation reinforcing and prestressing method
CN206800370U (en) It is a kind of to excavate the continuous side wall supporting and retaining system protective construction in underground without fertile groove
CN113417300A (en) Slope support system and construction method thereof
TW201741529A (en) Method for constructing advanced pavement for preventing construction site collapse before construction of diaphragm wall in which support piles are first established and grid beams are welded to tops of the piles for supporting grouting and forming of a concrete pavement thereon
CN110241863B (en) Soft soil foundation pit excavation process pipe gallery deformation control device and control method thereof
CN115897600A (en) Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area
CN212642730U (en) Collapsible loess area tunnel passes people's air defense structure
CN211395691U (en) Structure for improving vertical supporting node

Legal Events

Date Code Title Description
MM4A Annulment or lapse of patent due to non-payment of fees