TWI623669B - Construction method of advance pavement for preventing underground subsidence before continuous wall construction - Google Patents

Construction method of advance pavement for preventing underground subsidence before continuous wall construction Download PDF

Info

Publication number
TWI623669B
TWI623669B TW105115362A TW105115362A TWI623669B TW I623669 B TWI623669 B TW I623669B TW 105115362 A TW105115362 A TW 105115362A TW 105115362 A TW105115362 A TW 105115362A TW I623669 B TWI623669 B TW I623669B
Authority
TW
Taiwan
Prior art keywords
construction
pavement
pile
continuous wall
support
Prior art date
Application number
TW105115362A
Other languages
Chinese (zh)
Other versions
TW201741529A (en
Inventor
zheng-xiong Hong
Cai-Ming Cai
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to TW105115362A priority Critical patent/TWI623669B/en
Publication of TW201741529A publication Critical patent/TW201741529A/en
Application granted granted Critical
Publication of TWI623669B publication Critical patent/TWI623669B/en

Links

Abstract

一種連續壁施工前防止工地下陷的先行鋪面的施工方法,其主要運用在土質軟弱的施工基地上進行混凝土鋪面施作,使形成安全的施工地坪。本發明主要連續壁施作前先行施打地面開挖用支撐樁,並先行利用該支撐樁作為施工基地的混凝土鋪面的垂直承載支撐,而在原本軟弱地層基地的地表形成炬承載能力的地坪。本發明施工步驟包含:施打支撐樁、支撐樁的樁頂焊固鋼板、於相鄰支撐樁的樁頂與樁頂之間施作格子樑或/及加強鋼筋網、施作鋪面鋼筋網、澆注混凝土形成安全的施工混凝土鋪面,完成能夠防止工地下陷的地坪。該混凝土鋪面即為基地改善後的地坪。後續的施作連續壁工程時,就不需全面性的實施整體地改,只需在導溝邊做重點地改,即可防止該溝槽與挖掘槽發生坍塌的情形,以獲致良好品質的連續壁工程。 The utility model relates to a construction method for preventing the ground from subsiding before continuous wall construction, which is mainly applied to the construction of concrete on a weak construction base to form a safe construction floor. The main continuous wall of the invention is used to excavate support piles for ground excavation first, and use the support piles as a vertical load-bearing support for the concrete pavement of the construction base, and form a torch-bearing capacity floor on the ground of the original weak stratum base. . The construction steps of the present invention include: hitting a supporting pile, welding a steel plate on the pile top of the supporting pile, applying a lattice beam or / and reinforcing steel mesh between the pile top and the pile top of an adjacent supporting pile, applying a pavement reinforcing steel mesh, The concrete is poured to form a safe construction concrete pavement, and a ground floor capable of preventing the work from subsiding is completed. The concrete paving is the improved floor of the base. In the subsequent construction of the continuous wall project, it is not necessary to implement a comprehensive change in a comprehensive manner. Only a major change in the side of the guide trench is required to prevent the trench and the trench from collapsing, so as to obtain a good quality Continuous wall works.

Description

連續壁施工前防止工地下陷的先行鋪面的施工方法 Construction method of advance pavement for preventing underground subsidence before continuous wall construction

本發明涉及一種連續壁施工前防止工地下陷的先行鋪面的施工方法,其主要解決土質軟弱、土壤有液化現象、土壤含有水量高的基地在施作連續壁工程中,防止地層下陷與連續壁挖掘槽坍方的問題。 The invention relates to a construction method of a prior pavement for preventing underground subsidence before construction of a continuous wall, which mainly solves the problem of weak soil, soil liquefaction, and a high water content in the base. The construction of the continuous wall prevents the formation from subsidence and continuous wall excavation Slot collapse problem.

現今連續壁連續壁的基礎越做越深,所以有扶壁、橫隔壁等配套設計。此種有扶壁、橫隔壁配套設計的連續壁施工,會導致施工基地被切割若干個小體,破壞原有施工地坪的完整性,造成軟弱地層的施工環境。 Nowadays, the foundation of continuous wall and continuous wall is getting deeper and deeper, so there are supporting designs such as buttresses and transverse partitions. This type of continuous wall construction with supporting walls and horizontal partitions will cause the construction base to be cut into several small bodies, destroy the integrity of the original construction floor, and cause a weak stratum construction environment.

土壤液化也會造成地層下陷。原本為池塘、水坑,再回填成地面的地層,因含水量高。當重型機具進駐此類施工基地後,也會造成地坪下陷,地下水滲出地表。 Soil liquefaction can also cause formation subsidence. The original layer was a pond or puddle, which was then backfilled into the ground because of its high water content. When heavy machinery enters such construction bases, the ground subsidence will also cause groundwater to seep out of the ground.

在地層軟弱的施工基地進行連續壁施工,必須在導溝邊做樁徑施工,進行地坪改造,避免挖掘時造成導溝或/及挖掘槽坍方。另外,由於施工基地的地層屬軟弱地質,連需必施工前必須做全面地質改良強化工程,增加施工成本,也增加未來開挖時的困難度。假若施工單位的地質改良強化工程不確實,在重型機具進入基地後容易造成地層下陷,甚至令連續壁挖掘槽發生坍方情形。 For continuous wall construction at a weak construction base, pile diameter construction must be done next to the guide trench, and floor reconstruction should be performed to avoid collapse of the guide trench or excavation trench during excavation. In addition, because the stratum of the construction base is weak geology, comprehensive geological improvement and strengthening projects must be done before construction, which increases construction costs and also increases difficulty in future excavations. If the geological improvement and strengthening works of the construction unit are not accurate, the heavy-duty equipment will easily cause the ground to collapse after entering the base, or even cause the continuous wall excavation trough to collapse.

當施工基地發生地坪下陷時,容易損及鄰房建築,增加後續 的法律與賠償事件。地坪下陷時,若有工作人員正在工地工作或操作機具,就會發生傷人或致死的工安事件。連續壁挖掘槽的坍方,就必須回填還需進行地質改良才能重新挖掘,既增加工時,也影響連續壁施工品質。如何在軟弱地質的施工基地上,以安全、可靠的施工方式來必避免地坪下陷,提高連續壁施工品質,是業者汲汲所求者。 When floor subsidence occurs at the construction base, it is easy to damage neighboring buildings and increase follow-up Legal and compensation incidents. When the floor subsides, if a worker is working on the site or operating a machine, a work safety incident that will cause injury or death will occur. The slump of a continuous wall excavation trough must be backfilled and geologically improved before re-digging, which not only increases man-hours but also affects the quality of continuous wall construction. How to avoid floor subsidence and improve the quality of continuous wall construction in a safe and reliable construction method on a weak geological construction base is what the industry seeks.

為了解決前述軟質地層的連續壁施工問題,申請人乃提供一種連續壁施工前防止工地下陷的先行鋪面的施工方法,以提高施工基地的地坪強度,避免發生地坪坍方問題。 In order to solve the problem of continuous wall construction of the aforementioned soft ground, the applicant provided a construction method for preventing the ground from subsiding before continuous wall construction, so as to improve the strength of the construction base and avoid the problem of ground collapse.

本發明所提供之連續壁施工前防止工地下陷的先行鋪面的施工方法,能夠進一步地強化導溝強度,使降低對導溝做樁徑施工的數量,以縮減工期,可降低施工成本。 The construction method of the prior pavement for preventing wall subsidence before construction of the continuous wall provided by the present invention can further strengthen the guide trench strength, reduce the number of pile diameter constructions for the guide trench, reduce the construction period, and reduce construction costs.

本發明所提供之連續壁施工前防止工地下陷的先行鋪面的施工方法,主要在連續壁施作前先行施打地面開挖用支撐樁,並利用該支撐樁作為施工基地的混凝土鋪面的垂直承載支撐,而在原本軟弱地層基地的地表形成炬承載能力的地坪。則施作連續壁工程時,只需在導溝邊做重點地改,即可防止該溝槽與挖掘槽發生坍塌的情形,以獲致良好品質的連續壁工程。 The construction method of the prior pavement for preventing the subsidence of the ground before construction of the continuous wall provided by the present invention is mainly to apply a support pile for ground excavation before the continuous wall is applied, and use the support pile as a vertical bearing for the concrete pavement of the construction base. Support, and a torch bearing floor is formed on the ground of the original weak stratum base. Then, when the continuous wall project is implemented, only a major modification is required at the side of the guide trench to prevent the trench and the excavation trench from collapsing, so as to obtain a continuous wall project of good quality.

本發明施工前先於施工基地上確認建物放樣,連續壁施作設計,以及支撐樁位置與數量。其施工步驟包含:施打支撐樁、支撐樁的樁頂焊固鋼板、於相鄰支撐樁的樁頂與樁頂之間施作格子樑或/及加強鋼筋網、澆注混凝土形成鋪面、完成該混凝土鋪面。該混凝土鋪面即為基地改 善後的地坪。 Before construction, the present invention confirms the setting out of the building on the construction base, the design of the continuous wall construction, and the position and number of support piles. The construction steps include: hitting a supporting pile, welding a steel plate on the pile top of the supporting pile, applying a lattice beam or / and reinforcing steel mesh between the pile top and the pile top of an adjacent supporting pile, pouring concrete to form a pavement, and completing the Concrete paving. The concrete paving is the base modification After the floor.

前述相鄰支撐樁的樁頂與樁頂之間施作格子樑或/及加強鋼筋網,以構成鋪面的內部結構。該支撐樁頂與樁頂端的鋼板,即為施作格子樑/及加強鋼筋網的搭接面與承載點。則該各支撐樁即為該混凝土鋪面的垂直承載支撐。 A lattice beam or / and a reinforcing steel mesh is applied between the pile tops of the aforementioned adjacent support piles and the pile tops to form the internal structure of the pavement. The steel plate on the top of the supporting pile and the top of the pile is the overlap surface and bearing point of the lattice beam and / or reinforcing steel mesh. Each supporting pile is a vertical bearing support of the concrete paving.

該支撐樁上的的鋼板可以是一公尺見方的方形板,也可以直徑一公尺的圓形板。 The steel plate on the supporting pile may be a square plate of one meter square, or a circular plate of one meter in diameter.

憑藉該於相鄰支撐樁的樁頂之間格子樑、加強鋼筋網的高度,來決定鋪面的厚度,以及決定該鋪面的承載能力。 The thickness of the pavement and the bearing capacity of the pavement are determined by the height of the lattice beam between the tops of the adjacent supporting piles and the reinforcing steel mesh.

10‧‧‧連續壁位置 10‧‧‧ continuous wall position

11‧‧‧扶壁位置 11‧‧‧ Fubi position

20‧‧‧支撐樁 20‧‧‧ support pile

21‧‧‧鋼板 21‧‧‧ steel plate

22‧‧‧格子樑 22‧‧‧ lattice beam

23‧‧‧鋼筋網 23‧‧‧ Reinforced Mesh

30‧‧‧土壤 30‧‧‧ Soil

40‧‧‧鋪面 40‧‧‧ Shop Noodles

41‧‧‧鋪面鋼筋網 41‧‧‧ Pavement reinforced mesh

步驟a‧‧‧施打支撐樁 Step a‧‧‧ hit the support pile

步驟b‧‧‧於支撐樁的樁頂焊固鋼板 Step b‧‧‧ Welding steel plate at the top of the supporting pile

步驟c‧‧‧於相鄰支撐樁的樁頂格子樑或/及加強鋼筋 Step c‧‧‧ at the top of the pile on the adjacent supporting pile or / and reinforcing steel

步驟d‧‧‧施作鋪面鋼筋網 Step d‧‧‧ Apply the pavement reinforcement mesh

步驟e‧‧‧澆注混凝土形成鋪面 Step e‧‧‧ Pouring concrete to form a pavement

步驟f‧‧‧完成混凝土鋪面 Step f‧‧‧ Finish the concrete paving

圖一為本發明施工方法的施工流程。 Figure 1 shows the construction process of the construction method of the present invention.

圖二為連續壁施作設計及支撐樁設計工程圖。 Figure 2 is the engineering drawing of continuous wall construction design and support pile design.

圖三為支撐樁打入基地土壤內的剖示圖。 Figure 3 is a sectional view of the supporting pile driving into the soil of the base.

圖四為支撐樁打入基地土壤內的外觀圖。 Figure 4 shows the appearance of the supporting pile driving into the soil of the base.

圖五為支撐樁的樁頂焊固鋼板的外觀圖。 Figure 5 is an external view of a pile top welded steel plate of a supporting pile.

圖六為支撐樁的樁頂焊固鋼板的縱向剖示圖 Figure 6 is a longitudinal sectional view of the pile top welded steel plate of the supporting pile

圖七為支撐樁的樁頂格子樑及加強鋼筋的示意圖。 Fig. 7 is a schematic diagram of a pile top lattice beam and a reinforcing steel bar of a supporting pile.

圖八為支撐樁的樁頂格子樑的縱向剖示圖。 Fig. 8 is a longitudinal sectional view of a lattice beam at the top of a pile.

圖九為混凝土鋪面的剖示圖。 Figure 9 is a sectional view of a concrete pavement.

在連續壁施工時,容易發生地坪下陷的基地,大都屬於地層軟弱的地區,或者是因為基地地形過小或過於狹窄,造成重機過於集中而 造成地坪局部下陷。對於容易發生地坪下陷的基地,必須做全盤地改,以提高地層強度。申請人緣於對基地做全盤地改,會延長工期、增加成本,乃研發一種連續壁施工前防止工地下陷的先行鋪面施工方法。 During continuous wall construction, bases that are prone to subsidence are mostly in areas with weak strata, or because the terrain of the base is too small or too narrow, causing heavy machinery to be concentrated. Cause local subsidence of the floor. For bases that are prone to subsidence, a complete overhaul must be done to improve stratum strength. The applicant is due to the comprehensive renovation of the base, which will prolong the construction period and increase the cost. It is the research and development of a prefabricated pavement construction method to prevent the underground subsidence before the continuous wall construction.

本發明施工方法的主要思維,是在基地上先行鋪設具有高承載能力的鋪面,憑藉該鋪面來承載重型機具,以及強化導溝的強度。 The main idea of the construction method of the present invention is to first lay a pavement with a high bearing capacity on the base, rely on the pavement to carry heavy machinery, and strengthen the strength of the guide channel.

當施工基地的地層為軟弱土壤,若直接將鋪面直接鋪設在地面上,該鋪面必會因地層下陷而破裂,無法達到承載機具以及防止地坪下陷的目的。然而,傳統的連續壁施工在連續壁施工完成後,就會在基地內作地面開挖。地面開挖前要先在基地內放置多數個支撐樁,以支撐連續壁,才可進行地面開挖工程。本發明就是以該各支撐樁提前先行施工作為舖面之底部承載支撐。 When the stratum of the construction base is weak soil, if the pavement is directly laid on the ground, the pavement will rupture due to the subsidence of the stratum, which cannot achieve the purpose of carrying equipment and preventing the subsidence of the ground. However, the traditional continuous wall construction will excavate the ground in the base after the continuous wall construction is completed. Before excavating the ground, a plurality of supporting piles must be placed in the base to support the continuous wall before the ground excavation can be carried out. In the present invention, the advance construction of each supporting pile is used as the bottom bearing support of the pavement.

請參閱圖一及圖二。本發明施工前,先於施工基地上確認建物位置放樣,連續壁施作位置10設計,包含扶壁11位置設計,以及支撐樁20位置與數量。本發明施工步驟: Please refer to Figure 1 and Figure 2. Prior to the construction of the invention, the location of the building is to be staked out on the construction base, and the design of the position 10 of the continuous wall includes the design of the position of the supporting wall 11 and the position and quantity of the supporting pile 20. Construction steps of the present invention:

a.施打支撐樁20: a. Hitting the supporting pile 20:

將各支撐樁20打入基地的土壤30內,如圖三、圖四所示。該各支撐樁20的樁頂高度即為施作混凝土鋪面40(見圖九)的下方高程。 Each support pile 20 is driven into the soil 30 of the base, as shown in FIGS. 3 and 4. The pile top height of each support pile 20 is the lower elevation of the concrete paving 40 (see FIG. 9).

b.於支撐樁20的樁頂焊固鋼板21: b. Welded steel plate 21 on the top of the support pile 20:

該各支撐樁20的樁頂焊固鋼板21,如圖五、圖六所示。該鋼板21可為一公尺見方的方形板,也可以為直徑一公尺的圓形板。該鋼板21的尺寸大小,視施工需要可做適當的改變。 A steel plate 21 is welded to the pile top of each supporting pile 20 as shown in FIGS. 5 and 6. The steel plate 21 may be a square plate with a square of one meter, or a circular plate with a diameter of one meter. The size of the steel plate 21 can be appropriately changed according to construction requirements.

c.於相鄰支撐樁20的樁頂之間施作格子樑22或/及加強鋼筋網23: c. Placing a lattice beam 22 or / and a reinforcing steel mesh 23 between the tops of adjacent support piles 20:

相鄰支撐樁20的樁頂之間施作格子樑22或/及加強鋼筋網23,以構成鋪面的內部結構之一部分,如圖七、圖八所示。該支撐樁20頂端的鋼板21,可做為施作格子樑22、加強鋼筋網23的搭接面,以提高鋪面的結構強度。亦可憑藉該於相鄰支撐樁20的樁頂之間的格子樑22、加強鋼筋網23的高度,來決定混凝土鋪面40的厚度,來提高該混凝土鋪面40的承載能力。 A lattice beam 22 or / and a reinforcing steel mesh 23 are applied between the pile tops of the adjacent support piles 20 to form a part of the internal structure of the pavement, as shown in FIGS. 7 and 8. The steel plate 21 at the top of the support pile 20 can be used as the overlapping surface of the lattice beam 22 and the reinforcing steel mesh 23 to improve the structural strength of the paving. The thickness of the concrete paving 40 can also be determined by the height of the lattice beam 22 and the reinforcing steel mesh 23 between the tops of the adjacent supporting piles 20 to improve the bearing capacity of the concrete paving 40.

d.施作鋪面鋼筋網41: d. Application of pavement reinforced mesh 41:

於前述各支撐樁20樁頂之間所施作格子樑22或/及加強鋼筋網23的上方,施作原設計的鋪面鋼筋網41。 Above the lattice beams 22 or / and the reinforced reinforcing meshes 23 provided between the tops of the aforementioned supporting piles 20, a pavement reinforcing mesh 41 of the original design is applied.

e.澆注混凝土形成鋪面40: e. Pouring concrete to form a pavement 40:

於該施工基地內澆注混凝土,以覆蓋各支撐樁20、格子樑22、加強鋼筋網23、以及原設計的鋪面鋼筋網41,而形成混凝土鋪面40。 Concrete is poured into the construction base to cover each of the supporting piles 20, the lattice beams 22, the reinforcing steel mesh 23, and the pavement steel mesh 41 of the original design to form a concrete pavement 40.

f.完成該混凝土鋪面: f. Finish the concrete paving:

該混凝土鋪面40即為改善後的地坪。 The concrete paving 40 is an improved floor.

本發明所施作完成的鋪面40,其垂直支撐為各支撐樁20。該各支撐樁20為地面順打開挖的支撐結構,其支撐強度設計,已經考慮到地下層完全開挖後,依然能夠保有足夠安全係數的支撐強度。本發明所完成的混凝土鋪面40,除了支撐樁20原本設計的安全支撐係數外,因為地面為未開挖狀態,所以更增加了土壤30對支撐樁20的摩擦支撐。故該混凝土鋪面40的垂直支撐強度有很高的安全係數。 The pavement 40 completed by the present invention is vertically supported by each supporting pile 20. The support piles 20 are support structures that are excavated along the ground. The support strength design has taken into account that the support strength can still be maintained with sufficient safety coefficient after the underground layer is fully excavated. In addition to the safety support factor originally designed for the support pile 20, the concrete paving 40 completed by the present invention increases the frictional support of the soil pile 30 to the support pile 20 because the ground is not excavated. Therefore, the vertical support strength of the concrete paving 40 has a high safety factor.

本發明施作完成的混凝土鋪面40,具有高承載能力,足以承載重型機具的重量,使得基地地坪(混凝土鋪面)不會因機具重量而坍方。亦即,基地地坪會保持強度。 The completed concrete paving 40 of the present invention has a high bearing capacity, which is sufficient to bear the weight of heavy machinery, so that the base floor (concrete paving) will not collapse due to the weight of the machinery. That is, the base floor will maintain strength.

原本在軟弱地層施作連續壁工程,為了防止導溝坍塌,必須在導溝邊多處施作地改樁。在使用本發明方法鋪設混凝土鋪面40的施工基地,因地坪不會坍方,導溝自然就發生坍塌的機率自然大幅降低。因此,業者只需在導溝邊較易發生坍塌處(如轉角處)做局部地改(施作地改樁),自然大幅縮減連續壁施工工期,降低施工成本。 The continuous wall project was originally constructed in weak strata. In order to prevent the diversion trench from collapsing, it is necessary to carry out ground modification piles at multiple sides of the diversion trench. At the construction base where the concrete paving 40 is laid using the method of the present invention, since the floor will not slump, the probability of the guide ditch naturally collapsing is greatly reduced. Therefore, the operator only needs to make local modification (construction of piles) on the side of the guide trench that is prone to collapse (such as corners), naturally reducing the construction period of the continuous wall and reducing the construction cost.

使用本發明工法先行鋪設混凝土鋪面40後,有下列的優點: After the concrete pavement 40 is laid in advance using the method of the present invention, it has the following advantages:

1.混凝土鋪面40能夠承載重型機具,使地坪不會因機具重量而發生下陷或坍塌的情事。 1. The concrete paving 40 can carry heavy machinery, so that the floor will not sag or collapse due to the weight of the machinery.

2.不用作全面地改,可省下全面地改的施工工期,與施工成本。 2. It is not used for comprehensive renovation, which can save the construction period and construction cost of comprehensive renovation.

3.可減少連續壁導溝地改邊樁的數量,可減少施工成本、與縮短施工工期。 3. It can reduce the number of side-wall piles of continuous wall guide trenches, which can reduce the construction cost and shorten the construction period.

4.可減少地坪下陷、連續壁導溝坍方的情形,可減少損鄰的事件。 4. It can reduce the ground subsidence and the collapse of continuous wall guide ditch, and it can reduce the event of damage to the neighbor.

5.由於不易發生地坪下陷、連續壁導溝坍方的情形,進而可提高連續壁的施工品質,使建築物品質獲得保證。 5. As the floor subsidence and the collapse of the continuous wall guide ditch are not easy to occur, the construction quality of the continuous wall can be improved and the quality of the building can be guaranteed.

6.在施工過程中,工地不易發生下陷、坍方的情事,有助於敦親睦鄰,同時可提升企業形象。 6. During the construction process, it is not easy for the construction site to sag and collapse, which can help the neighbors and neighbors, and at the same time enhance the corporate image.

綜上所陳,本發明選擇在連續壁施作前,即先行施打支撐樁20,為一種前所未見的施工思維。本發明利用該支撐樁20作為混凝土鋪面40的垂直承載支撐,也有別於傳統鋪面的結構,也是一種垂直支撐更為可靠的鋪面40。故,憑藉本發明工法所施作的混凝土鋪面40作為基地的地坪,可使軟弱地層的基地也能在安全、可靠的施工過程,獲致良好品質的連續壁工程。 In summary, the present invention chooses to apply the support pile 20 before the continuous wall is applied, which is a construction thought that has never been seen before. The invention uses the supporting pile 20 as a vertical bearing support of the concrete paving 40, which is also different from the traditional paving structure, and is also a paving 40 with more reliable vertical support. Therefore, by virtue of the concrete paving 40 made by the method of the present invention as the floor of the base, the base of the weak stratum can also obtain a continuous wall project of good quality in a safe and reliable construction process.

雖然本發明以實施方式揭露如上,然其並非用以限定本發 明,任何熟悉此項技術的人員,在不脫離本發明的精神和範圍內,可作各種的改動與潤飾,因此本發明的保護範圍當以申請專利範圍所定為准。 Although the present invention is disclosed as above in the embodiments, it is not intended to limit the present invention. It is clear that anyone skilled in the art can make various modifications and retouches without departing from the spirit and scope of the present invention. Therefore, the protection scope of the present invention shall be determined by the scope of the patent application.

Claims (4)

一種連續壁施工前防止工地下陷的先行鋪面的施工方法,其施工前先於施工基地上確認建物位置放樣,連續壁施作設計,以及支撐樁位置與數量;其特徵在:其施工步驟為:a.施打支撐樁:將各支撐樁打入基地的土壤內;各支撐樁的樁頂高度即為施作混凝土鋪面的下方高程;b.於支撐樁的樁頂焊固鋼板:該各支撐樁的樁頂皆焊固鋼板;c.於相鄰支撐樁的樁頂之間施作格子樑或/及加強鋼筋網:相鄰支撐樁的樁頂之間施作格子樑或/及加強鋼筋網,以構成鋪面的內部結構之一部分;該支撐樁頂端的鋼板,即為格子樑、加強鋼筋的搭接面;d.施作鋪面鋼筋網:於前述各支撐樁樁頂之間所施作格子樑或/及加強鋼筋網的上方,施作原設計的鋪面鋼筋網;e.澆注混凝土形成鋪面:於該施工基地內澆注混凝土,以覆蓋各支撐樁、格子樑、鋼筋網而形成混凝土鋪面;f.完成該混凝土鋪面:該混凝土鋪面即為改善後的地坪。A construction method for preventing pavement from falling before construction of a continuous wall. Before construction, confirm the location of the building on the construction base, stake out the design of the continuous wall, and the position and number of support piles. Its characteristics are as follows: The construction steps are as follows: a. Driving support piles: driving each support pile into the soil of the base; the height of the top of each support pile is the lower elevation of the concrete pavement; b. welding the steel plate at the top of the support pile: the support The pile tops of the piles are welded with steel plates; c. The lattice beams and / or reinforced meshes are applied between the pile tops of adjacent supporting piles: the lattice beams and / or reinforcements are applied between the pile tops of adjacent support piles. Net to form part of the internal structure of the pavement; the steel plate at the top of the support pile is the overlapping surface of the lattice beam and reinforced steel; d. The pavement reinforced mesh: applied between the tops of the aforementioned support piles Above the lattice beam or / and reinforced reinforcement mesh, the original design of the pavement reinforcement mesh; e. Pouring concrete to form the pavement: pouring concrete in the construction base to cover each supporting pile, lattice beam, and reinforcing mesh to form a concrete pavement; . Into the concrete pavement: the floor after the concrete pavement shall be improved. 如申請專利範圍第1項所述之連續壁施工前防止工地下陷的先行鋪面施工方法,其步驟b中的鋼板為一公尺見方的方形板。According to the prior paving construction method for preventing wall subsidence before continuous wall construction as described in item 1 of the scope of the patent application, the steel plate in step b is a square meter square. 如申請專利範圍第1項所述之連續壁施工前防止工地下陷的先行鋪面施工方法,其步驟b中的鋼板為直徑一公尺的圓形板。According to the prior paving construction method for preventing continuous subsidence before continuous wall construction described in item 1 of the scope of patent application, the steel plate in step b is a circular plate with a diameter of one meter. 如申請專利範圍第1項所述之連續壁施工前防止工地下陷的先行鋪面施工方法,其步驟c中,憑藉該於相鄰支撐樁的樁頂之間格子樑、加強鋼筋網的高度,來決定鋪面的厚度,以及決定該鋪面的承載能力。According to the prior pavement construction method for preventing the subsidence of the construction site before the continuous wall construction described in item 1 of the scope of the patent application, in step c, relying on the height of the lattice beam between the pile tops of the adjacent supporting piles and the reinforcement steel mesh Decide on the thickness of the pavement and the bearing capacity of the pavement.
TW105115362A 2016-05-18 2016-05-18 Construction method of advance pavement for preventing underground subsidence before continuous wall construction TWI623669B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW105115362A TWI623669B (en) 2016-05-18 2016-05-18 Construction method of advance pavement for preventing underground subsidence before continuous wall construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW105115362A TWI623669B (en) 2016-05-18 2016-05-18 Construction method of advance pavement for preventing underground subsidence before continuous wall construction

Publications (2)

Publication Number Publication Date
TW201741529A TW201741529A (en) 2017-12-01
TWI623669B true TWI623669B (en) 2018-05-11

Family

ID=61230165

Family Applications (1)

Application Number Title Priority Date Filing Date
TW105115362A TWI623669B (en) 2016-05-18 2016-05-18 Construction method of advance pavement for preventing underground subsidence before continuous wall construction

Country Status (1)

Country Link
TW (1) TWI623669B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI753415B (en) * 2020-04-29 2022-01-21 聖陸營造工程股份有限公司 Construction Method of Constructing Continuous Wall Guide Ditch of New Building on the Old Underground Floor Structure

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI651452B (en) * 2018-02-13 2019-02-21 聖陸營造工程股份有限公司 Pavement construction method for preventing floor subsidence before construction of continuous wall and ground wall

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW227029B (en) * 1992-07-14 1994-07-21 Chung Len Engineering Consultant Construction of deep-base, reverse constructing block soil construction

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW227029B (en) * 1992-07-14 1994-07-21 Chung Len Engineering Consultant Construction of deep-base, reverse constructing block soil construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI753415B (en) * 2020-04-29 2022-01-21 聖陸營造工程股份有限公司 Construction Method of Constructing Continuous Wall Guide Ditch of New Building on the Old Underground Floor Structure

Also Published As

Publication number Publication date
TW201741529A (en) 2017-12-01

Similar Documents

Publication Publication Date Title
CN108868778B (en) Non-excavation construction method for large underground structure
CN101967985B (en) Self-propelled inverted arch template construction method
CN107542108B (en) A kind of reverse construction method of building basement structure
CN205742213U (en) Foundation pit supporting construction
CN106088650A (en) A kind of building with brick-concrete structure underground that is applicable to increases method and the building of layer
RU2414563C1 (en) Method to erect multistory subsurface structure
CN111101540B (en) Construction method for passing existing electric power tunnel on open cut tunnel
CN106837341B (en) A kind of Metro construction construction method of shaft wall
CN108678751B (en) Assembly type construction method of shield cutter head manhole by jacking and excavating firstly
TWI623669B (en) Construction method of advance pavement for preventing underground subsidence before continuous wall construction
CN104963348A (en) Soft soil area tower crane foundation construction supporting structure and construction method thereof
CN108457303B (en) Method for newly adding underground parking lot under existing building
CN112627249B (en) Construction method for shallow foundation reinforcement
CN114922195A (en) Construction method of soft soil deep and large foundation pit adjacent to protected object
JP2000291398A (en) Underground structure and construction method therefor
CN114232602A (en) Underground continuous pile construction process
CN112663636A (en) Non-panel reinforced soil ecological slope protection system and construction method thereof
CN104631878B (en) Aluminum casting machine well construction method
Ředina Reconstuction of the historical building foksal 13 and 15 in Warsaw
CN109339827A (en) The excavating construction method of multi-layer underground structure
CN217480236U (en) Pile-plate type retaining wall suitable for high slope
CN113847062B (en) Subway station construction method combining small-diameter jacking pipes with double-layer six-hole piles
CN113931228B (en) Material platform construction method for basement construction
CN115419074B (en) Crawler-type soil conveying and excavating method for ultra-deep foundation pit
CN111254938B (en) Foundation pit supporting structure based on side wall of underground chamber and reverse construction method thereof

Legal Events

Date Code Title Description
MM4A Annulment or lapse of patent due to non-payment of fees