TW227029B - Construction of deep-base, reverse constructing block soil construction - Google Patents
Construction of deep-base, reverse constructing block soil constructionInfo
- Publication number
- TW227029B TW227029B TW81105562A TW81105562A TW227029B TW 227029 B TW227029 B TW 227029B TW 81105562 A TW81105562 A TW 81105562A TW 81105562 A TW81105562 A TW 81105562A TW 227029 B TW227029 B TW 227029B
- Authority
- TW
- Taiwan
- Prior art keywords
- digging
- construction
- support
- ground
- wall
- Prior art date
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Construction of digging basement, especially suitable for pebble ground layers, such ground construction is easily collapsed, the ground water can be controlled by point wells, the construction can be operated in dependently without constructing block wall; the construction has 5 steps as follows; (A) investigating ground features: containing water permeability, coherence, inner friction angle and support condition of basement; assuring digging depth, side ground pressure and water level of point well at each step; (B) assuring point well water level and water-extracting ability: assuring water level can decrease to under ground water level at each step; (C) middle support construction: constructing temporary perpendicular steel support or permanent steel support; (D) building temporary reverse block wall after each step of digging: calculating digging depth of each step, building temporary reverse block wall after digging step to protect wall face line to stabilize digging face; the block wall containing steel fiber concrete or spraying sludge in the thickness of t=7-30cm to protect digging surface without collapse and against ground pressure; (E) level supporting: applying oil-press jack to support steel support and to resist side ground pressure and the collapse of block wall; permanent level support applying steel concrete as wall plate at each digging stage as inner support system to maintain the stability of digging wall and to avoid the replacement of side direction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW81105562A TW227029B (en) | 1992-07-14 | 1992-07-14 | Construction of deep-base, reverse constructing block soil construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW81105562A TW227029B (en) | 1992-07-14 | 1992-07-14 | Construction of deep-base, reverse constructing block soil construction |
Publications (1)
Publication Number | Publication Date |
---|---|
TW227029B true TW227029B (en) | 1994-07-21 |
Family
ID=51348409
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
TW81105562A TW227029B (en) | 1992-07-14 | 1992-07-14 | Construction of deep-base, reverse constructing block soil construction |
Country Status (1)
Country | Link |
---|---|
TW (1) | TW227029B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI623669B (en) * | 2016-05-18 | 2018-05-11 | Construction method of advance pavement for preventing underground subsidence before continuous wall construction | |
TWI649480B (en) * | 2017-06-09 | 2019-02-01 | 林培元 | Composite retaining support method for full (semi) reverse engineering pre-operation |
TWI651452B (en) * | 2018-02-13 | 2019-02-21 | 聖陸營造工程股份有限公司 | Pavement construction method for preventing floor subsidence before construction of continuous wall and ground wall |
-
1992
- 1992-07-14 TW TW81105562A patent/TW227029B/en active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI623669B (en) * | 2016-05-18 | 2018-05-11 | Construction method of advance pavement for preventing underground subsidence before continuous wall construction | |
TWI649480B (en) * | 2017-06-09 | 2019-02-01 | 林培元 | Composite retaining support method for full (semi) reverse engineering pre-operation |
TWI651452B (en) * | 2018-02-13 | 2019-02-21 | 聖陸營造工程股份有限公司 | Pavement construction method for preventing floor subsidence before construction of continuous wall and ground wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101672041B (en) | Top-down construction method of large underground structure outer wall | |
DE69836339D1 (en) | LATERAL FORMWORK ASSEMBLY FOR MANUFACTURING THE PLASTERING OF A CONCRETE CONCRETE CONCRETE | |
Clough et al. | A study of earth loadings on floodway retaining structures in the 1971 San Fernando Valley earthquake | |
TW227029B (en) | Construction of deep-base, reverse constructing block soil construction | |
Lancaster | The process of building the Colosseum: the site, materials, and construction techniques | |
SE9001934D0 (en) | CONCRETE FORM AND METHOD FOR THE CONSTRUCTION OF A BASIC CONSTRUCTION TO A HOUSING INCLUDING SUCH BANKS | |
CN101597903A (en) | A kind of construction method of cylindrical slurry core pile that is used for pattern foundation pit supporting structure | |
KR20210053497A (en) | Fileless-up wall demolition method | |
CN214090006U (en) | Basement lateral wall post-cast strip block structure | |
Avigad | A building inscription of the Emperor Justinian and the Nea in Jerusalem (preliminary note) | |
CN215367999U (en) | Assembled energy-conserving building wall component | |
CN212427155U (en) | Tongue-and-groove type prefabricated underground continuous wall structure | |
CN108625384A (en) | A kind of construction method of deep strong permeable layer base pit dewatering structure | |
CN209798764U (en) | Foundation pit structure | |
Arutyunyan | Deformations of gypsofied soils in the bases of building and structures in Erevan | |
Ndoro | Restoration of dry-stone walls at the Great Zimbabwe archaeological site | |
CN116043857B (en) | Claw-shaped buttress steel frame and fertilizer tank earthwork excavation method | |
CN215801685U (en) | Civil engineering strutting arrangement | |
CN210341886U (en) | Underground continuous wall prevention of seepage water structure | |
JPS56125526A (en) | Construction of vertical wall of concrete structure underground and machinery and tool therefor | |
JPS6316535B2 (en) | ||
Lew et al. | Up and down construction of a 17-story building | |
Rijal et al. | Vulnerability Assessment of All Saints’ Church-a Unique Heritage Building in Bengaluru | |
King | Byzantine and Islamic sites in northern and eastern Jordan | |
Baker et al. | Complex high-rise foundation design and construction |