TW227029B - Construction of deep-base, reverse constructing block soil construction - Google Patents

Construction of deep-base, reverse constructing block soil construction

Info

Publication number
TW227029B
TW227029B TW81105562A TW81105562A TW227029B TW 227029 B TW227029 B TW 227029B TW 81105562 A TW81105562 A TW 81105562A TW 81105562 A TW81105562 A TW 81105562A TW 227029 B TW227029 B TW 227029B
Authority
TW
Taiwan
Prior art keywords
digging
construction
support
ground
wall
Prior art date
Application number
TW81105562A
Other languages
Chinese (zh)
Inventor
Jyh-Yi Jang
Original Assignee
Chung Len Engineering Consultant
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chung Len Engineering Consultant filed Critical Chung Len Engineering Consultant
Priority to TW81105562A priority Critical patent/TW227029B/en
Application granted granted Critical
Publication of TW227029B publication Critical patent/TW227029B/en

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

Construction of digging basement, especially suitable for pebble ground layers, such ground construction is easily collapsed, the ground water can be controlled by point wells, the construction can be operated in dependently without constructing block wall; the construction has 5 steps as follows; (A) investigating ground features: containing water permeability, coherence, inner friction angle and support condition of basement; assuring digging depth, side ground pressure and water level of point well at each step; (B) assuring point well water level and water-extracting ability: assuring water level can decrease to under ground water level at each step; (C) middle support construction: constructing temporary perpendicular steel support or permanent steel support; (D) building temporary reverse block wall after each step of digging: calculating digging depth of each step, building temporary reverse block wall after digging step to protect wall face line to stabilize digging face; the block wall containing steel fiber concrete or spraying sludge in the thickness of t=7-30cm to protect digging surface without collapse and against ground pressure; (E) level supporting: applying oil-press jack to support steel support and to resist side ground pressure and the collapse of block wall; permanent level support applying steel concrete as wall plate at each digging stage as inner support system to maintain the stability of digging wall and to avoid the replacement of side direction.
TW81105562A 1992-07-14 1992-07-14 Construction of deep-base, reverse constructing block soil construction TW227029B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW81105562A TW227029B (en) 1992-07-14 1992-07-14 Construction of deep-base, reverse constructing block soil construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW81105562A TW227029B (en) 1992-07-14 1992-07-14 Construction of deep-base, reverse constructing block soil construction

Publications (1)

Publication Number Publication Date
TW227029B true TW227029B (en) 1994-07-21

Family

ID=51348409

Family Applications (1)

Application Number Title Priority Date Filing Date
TW81105562A TW227029B (en) 1992-07-14 1992-07-14 Construction of deep-base, reverse constructing block soil construction

Country Status (1)

Country Link
TW (1) TW227029B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI623669B (en) * 2016-05-18 2018-05-11 Construction method of advance pavement for preventing underground subsidence before continuous wall construction
TWI649480B (en) * 2017-06-09 2019-02-01 林培元 Composite retaining support method for full (semi) reverse engineering pre-operation
TWI651452B (en) * 2018-02-13 2019-02-21 聖陸營造工程股份有限公司 Pavement construction method for preventing floor subsidence before construction of continuous wall and ground wall

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI623669B (en) * 2016-05-18 2018-05-11 Construction method of advance pavement for preventing underground subsidence before continuous wall construction
TWI649480B (en) * 2017-06-09 2019-02-01 林培元 Composite retaining support method for full (semi) reverse engineering pre-operation
TWI651452B (en) * 2018-02-13 2019-02-21 聖陸營造工程股份有限公司 Pavement construction method for preventing floor subsidence before construction of continuous wall and ground wall

Similar Documents

Publication Publication Date Title
CN101672041B (en) Top-down construction method of large underground structure outer wall
DE69836339D1 (en) LATERAL FORMWORK ASSEMBLY FOR MANUFACTURING THE PLASTERING OF A CONCRETE CONCRETE CONCRETE
Clough et al. A study of earth loadings on floodway retaining structures in the 1971 San Fernando Valley earthquake
TW227029B (en) Construction of deep-base, reverse constructing block soil construction
Lancaster The process of building the Colosseum: the site, materials, and construction techniques
SE9001934D0 (en) CONCRETE FORM AND METHOD FOR THE CONSTRUCTION OF A BASIC CONSTRUCTION TO A HOUSING INCLUDING SUCH BANKS
CN101597903A (en) A kind of construction method of cylindrical slurry core pile that is used for pattern foundation pit supporting structure
KR20210053497A (en) Fileless-up wall demolition method
CN214090006U (en) Basement lateral wall post-cast strip block structure
Avigad A building inscription of the Emperor Justinian and the Nea in Jerusalem (preliminary note)
CN215367999U (en) Assembled energy-conserving building wall component
CN212427155U (en) Tongue-and-groove type prefabricated underground continuous wall structure
CN108625384A (en) A kind of construction method of deep strong permeable layer base pit dewatering structure
CN209798764U (en) Foundation pit structure
Arutyunyan Deformations of gypsofied soils in the bases of building and structures in Erevan
Ndoro Restoration of dry-stone walls at the Great Zimbabwe archaeological site
CN116043857B (en) Claw-shaped buttress steel frame and fertilizer tank earthwork excavation method
CN215801685U (en) Civil engineering strutting arrangement
CN210341886U (en) Underground continuous wall prevention of seepage water structure
JPS56125526A (en) Construction of vertical wall of concrete structure underground and machinery and tool therefor
JPS6316535B2 (en)
Lew et al. Up and down construction of a 17-story building
Rijal et al. Vulnerability Assessment of All Saints’ Church-a Unique Heritage Building in Bengaluru
King Byzantine and Islamic sites in northern and eastern Jordan
Baker et al. Complex high-rise foundation design and construction