JP5131742B2 - Foundation construction method for revetment structures - Google Patents

Foundation construction method for revetment structures Download PDF

Info

Publication number
JP5131742B2
JP5131742B2 JP2007217692A JP2007217692A JP5131742B2 JP 5131742 B2 JP5131742 B2 JP 5131742B2 JP 2007217692 A JP2007217692 A JP 2007217692A JP 2007217692 A JP2007217692 A JP 2007217692A JP 5131742 B2 JP5131742 B2 JP 5131742B2
Authority
JP
Japan
Prior art keywords
ground
layer
revetment
block
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2007217692A
Other languages
Japanese (ja)
Other versions
JP2009052217A (en
Inventor
多克 和木
正美 折笠
昭則 小林
義晴 山下
浩 中野
充 野々田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Road Co Ltd
Taisei Rotec Corp
Original Assignee
Nippon Road Co Ltd
Taisei Rotec Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Road Co Ltd, Taisei Rotec Corp filed Critical Nippon Road Co Ltd
Priority to JP2007217692A priority Critical patent/JP5131742B2/en
Publication of JP2009052217A publication Critical patent/JP2009052217A/en
Application granted granted Critical
Publication of JP5131742B2 publication Critical patent/JP5131742B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/30Landfill technologies aiming to mitigate methane emissions

Landscapes

  • Revetment (AREA)
  • Processing Of Solid Wastes (AREA)

Description

本発明は、入江の内部や大きな湾内の海域の一部を、所定の広さに仕切るように構築して、その仕切られた区画を廃棄物投棄処理場として供するための、仕切護岸の構築方法に関し、特に、海底地盤上に構造物を立設する際の、支持基礎の構築方法に関する。   The present invention relates to a partition revetment construction method for constructing a part of a sea area inside a cove or a large bay so as to be partitioned into a predetermined area and providing the partitioned section as a waste disposal treatment site. In particular, the present invention relates to a method for constructing a support foundation when a structure is erected on the seabed.

一般に、大きな湾の内部や外海の荒波の影響を受けにくい海域の一部を、護岸により区分した処分場として構築し、この処分場の内部と外海との間で水が流通しないように区切っている。そして、処分場の中に堆積される廃棄物と、その廃棄物に接触して汚染された水を、仕切った区画の内部に封じ込めて、外海に流れ出さないようにするために、仕切護岸を構築して閉じ込めている。このような仕切護岸において、護岸構造物の底部と支持層としての海底地盤の表面との間で、遮水性を良好に維持可能とするために、海底地盤の上にアスファルト混合物の層を構築し、構造物を載置する基礎や構造物の底面と地盤の表面との接する面の間で、遮水性を維持させるように構成している。(例えば、特許文献1を参照)。
特開2006−204965
Generally, a part of the sea area that is not easily affected by rough waves in the large bay or the open sea is constructed as a disposal site that is divided by revetment, and separated so that water does not flow between the inside of this disposal site and the open sea. Yes. In order to contain the waste accumulated in the disposal site and the water contaminated by contact with the waste inside the partitioned compartment, a partition revetment is installed to prevent it from flowing into the open sea. Constructed and confined. In such a partition revetment, a layer of asphalt mixture is constructed on the seabed ground in order to maintain good water shielding between the bottom of the revetment structure and the surface of the seabed ground as a support layer. In addition, it is configured to maintain water shielding between the foundation on which the structure is placed and the surface where the bottom surface of the structure is in contact with the surface of the ground. (For example, see Patent Document 1).
JP 2006-204965 A

前記従来例のように、遮水性を向上させるように地盤改良処理を行った海底地盤に、溝状の凹部を掘削して、その凹部の底部に構造物を支持するために、アスファルトやコンクリートの層を構築することが一般に行われている。ところが、アスファルトやコンクリート層の表面を、セルフレベリング性を利用し、その表面を平坦にするためには、打設量に見合った広い面積を確保することが必要となる。   In order to support the structure at the bottom of the recess by excavating a groove-like recess in the seabed ground that has been improved to improve water-imperviousness as in the conventional example, asphalt or concrete It is common practice to build layers. However, in order to make the surface of the asphalt or concrete layer flat using the self-leveling property, it is necessary to secure a wide area corresponding to the placement amount.

また、前記遮水層を構築するに際して使用されるアスファルト混合物は、ストレートアスファルトに石粉や細かい砂等を混合したものが用いられており、狭い隙間に充填する場合にも空間が生じないように、流動性が良好な性質を発揮できるものとして用いられる。ところが、前記流動性の良好な状態に作成されたアスファルト混合物は、その単位ボリューム当たりの単価が、陸上で道路舗装等に使用されるアスファルト混合物に比べて、数倍もしくは十数倍と、非常に高価なものとなっている。さらに、アスファルト使用量が陸上用に比較して多いという他に、アスファルト混合物を海上で施工するために、特殊な作業用船舶を多く使用することや、潜水作業員に頼らなければならないこと等の、作業条件が異なってもいる。   In addition, the asphalt mixture used when constructing the water shielding layer is a mixture of straight asphalt mixed with stone powder, fine sand, etc., so that space does not occur even when filling a narrow gap, It is used as a material that can exhibit good fluidity. However, the asphalt mixture prepared with the above good fluidity has a unit price per unit volume of several times or a dozen times as much as the asphalt mixture used for road pavement etc. on land. It is expensive. In addition to the fact that the amount of asphalt used is higher than that for land use, in order to construct the asphalt mixture at sea, many special work vessels are used, and it is necessary to rely on diving workers. The working conditions are also different.

それに加えて、作業環境が劣悪で、天候の影響を受けやすいことや、作業効率が非常に良くないことが多い等の、海上や海中での作業に伴う各種の条件が大きく影響していることもある。しかしながら、近年の経済環境の影響は、埋立地の造成等の工事のコストを低減させなければならない、という方向に向かっている。そのような要求に対して、仕切護岸の構築等の仕事においても、その強度と遮水性等の特性を損なうことなしに、施工コストを低減させる工法を開発することが要求されているのが現状である。   In addition, various conditions associated with work at sea and in the sea, such as poor work environment, being easily affected by the weather, and often very poor work efficiency. There is also. However, the influence of the economic environment in recent years is heading toward the need to reduce the cost of construction such as the creation of landfills. In response to such demands, even in work such as construction of partition revetments, it is currently required to develop construction methods that reduce construction costs without compromising properties such as strength and water barrier properties. It is.

本発明は、前記仕切護岸での遮水処理を有効に行い得て、遮水層の施工コストを低減させても、信頼性の高い遮水部としての性能を、従来の仕切護岸と同等に維持することが可能な工法を提供することを目的としている。   The present invention can effectively perform the water shielding treatment at the partition revetment, and even if the construction cost of the water shielding layer is reduced, the performance as a highly reliable water shielding portion is equivalent to that of the conventional partition revetment. The purpose is to provide a method that can be maintained.

本発明は、海底地盤上にケーソンのような構造物を列状に構築して海域を所定の広さに仕切り、前記仕切られた内部の区画に廃棄物を投棄するための仕切護岸の構築工法に関する。
請求項1の発明は、 前記仕切護岸を構築するに際しては、最初に、前記構造物を設置する地盤を不透水性改良地盤とする処理を施してから、前記不透水性地盤とする地盤改良を行った地盤に凹溝を構築し、
次いで、前記凹溝の底部の表面凹凸を解消するために、コンクリートを前記凹溝の底部表面に打設して下部充填層を構築し、
前記下部充填層の上に所定の厚さのブロック状部材を一定の間隔で敷き並べて前記構造物の支持層を設け、前記ブロック状部材の間と前記構造物を立設する凹溝の底部表面を埋めるようにアスファルト混合物を打設して、前記下部充填層と一体に働く遮水層とする工程を順次施工し、
次に、前記凹溝に護岸本体となる前記構造物を列状に立設してから、前記構造物の基部と前記凹溝の間の隙間を埋めるように、アスファルト混合物を充満させる処理を行って、前記構造物の基部と不透水性地盤の遮水層とを一体化するように、遮水処理を施したことを特徴とする。
The present invention is a construction method of a partition revetment for constructing caisson-like structures in a row on the seabed, partitioning the sea area into a predetermined area, and dumping waste into the partitioned internal compartment About.
In the invention of claim 1, when constructing the partition revetment, firstly, the ground where the structure is to be installed is treated as an impermeable ground, and then the ground improvement is performed as the impermeable ground. Build a ditch in the ground you went,
Next, in order to eliminate surface irregularities at the bottom of the groove, concrete is cast on the bottom surface of the groove to construct a lower packed bed,
A bottom surface of a concave groove between which the block-like members are erected and between which the block-like members are erected is provided by arranging block-like members having a predetermined thickness on the lower filling layer at regular intervals. Asphalt mixture is placed so as to fill, and a process of making a water-impervious layer that works integrally with the lower filling layer is sequentially applied,
Next, the structure that forms the revetment main body is erected in a row in the groove, and then the asphalt mixture is filled so as to fill a gap between the base of the structure and the groove. In addition, a water shielding treatment is performed so that the base of the structure and the water shielding layer of the impermeable ground are integrated.

請求項2の発明は、前記凹溝の底面に前記構造物の支持層として施工する前記下部充填層の上に、多数の貫通孔を縦横に設けたブロック状部材を一定の間隔で敷き並べて、前記構造物の支持層を構築した上に前記構造物を列状に立設してから、
前記構造物の基部と凹溝との間に遮水材を充満させる処理を行って、地盤と構造物との間に隙間を生じさせないようにして、地盤と構造物とを一体化した遮水性を発揮させる仕切護岸として構築することを特長とする。
In the invention of claim 2, on the bottom filling layer constructed as a support layer of the structure on the bottom surface of the concave groove, block-like members provided with a large number of through-holes are arranged at regular intervals, After constructing the support layer of the structure and standing the structure in a row,
A water-impervious structure that integrates the ground and the structure so as not to create a gap between the ground and the structure by performing a treatment to fill the water-impervious material between the base of the structure and the groove. It is constructed as a partition revetment that demonstrates

前述したように構造物を立設させて保持するための基礎を構築するに際して、支持基盤の表面に凹凸が残っていても、その地盤上に構築する構造物に対しては、平らに形成した支持面上に立設できるので、護岸構造物の構築工事を容易に行うことができる。そして、支持基盤の構造物を支持する上面に対して、構造物の底面が隙間なく接するように構築でき、海底での作業であっても、潜水作業員による施工能率を向上させることができる。さらに、基礎として打設するコンクリート層の表面が、正しく平らでなかったとしても、その上に施工するアスファルト層により、構造物の底面との間で隙間が形成されることがなく、基礎と構造物の底面との間での遮水性を損なうことがなくなる。   As described above, when constructing the foundation for standing and holding the structure, even if unevenness remains on the surface of the support base, the structure constructed on the ground was formed flat. Since it can be erected on the support surface, the construction of the revetment structure can be done easily. And it can construct | assemble so that the bottom face of a structure may contact | connect without a clearance gap with respect to the upper surface which supports the structure of a support base, and can improve the construction efficiency by a diving worker even if it is a work on the seabed. Furthermore, even if the surface of the concrete layer to be placed as a foundation is not flat correctly, no gap is formed between the bottom of the structure by the asphalt layer to be constructed on the foundation and the structure. No loss of water barrier between the bottom of the object.

さらに、構造物構築場所に配置するブロック状部材は、任意の断面形状で貫通孔を有するものや孔を有しないものを用いて、構造物を支持させるとともに、その周囲にアスファルト混合物を打設することにより、遮水層を容易に構築できる。また、前記ブロック状部材に代えて、アスファルトマット等を積層して設けることができるので、現場で入手可能な材料を用いてアスファルト混合物の中に位置させて、構造物の支持層を遮水層として容易に構築できる。   Furthermore, the block-like member to be arranged at the structure construction site is one that has a through-hole with an arbitrary cross-sectional shape or one that does not have a hole, supports the structure, and places an asphalt mixture around it. Thus, the water shielding layer can be easily constructed. In addition, since the asphalt mat or the like can be provided in place of the block-like member, it is positioned in the asphalt mixture using a material available on the site, and the support layer of the structure is a water shielding layer. Can be easily constructed.

図示される例にしたがって、本発明の実施例の構成を説明するが、以下に説明する実施例は、廃棄物を埋めて投棄する海域を区画するために、ケーソン等の既製の護岸構造物を列設して護岸を構築する例を用いて説明している。前記仕切護岸を構築する海底地盤では、地盤上に立設して構築するケーソン等の護岸構造物を、従来の工法を用いる場合と同様に、所定の手順にしたがって構築して、支持基礎の上に立設して構築することができる。
なお、本工法を適用するに際しては、前記支持基盤や海底地盤に対しても、護岸と同様な遮水性を発揮させる処理を施して対応させている。
According to the illustrated example, the configuration of the embodiment of the present invention will be described. In the embodiment described below, a ready-made revetment structure such as a caisson is used to divide a sea area where waste is buried and dumped. This is explained using an example of building a revetment by lining up. In the submarine ground where the partition revetment is constructed, a revetment structure such as a caisson constructed by standing on the ground is constructed according to a predetermined procedure in the same manner as when using a conventional construction method, It can be built by standing up.
In addition, when applying this construction method, it is made to respond | correspond to the said support base and the seabed ground also by performing the process which exhibits the water impermeability similar to a seawall.

前記仕切護岸を、廃棄物埋立地の区画として用いる場合に、1列状に並べて立設するケーソン等の構造物の接続部の部分で、遮水性を良好に維持できるように遮水処理を行っている。また、前記仕切護岸を構成する際には、構造物を立設する地盤上に、遮水性を発揮するシートやマット等を敷設して、地盤表面を覆うとともに、構造物の底面との間に隙間が生じないように処理し、構造物を地盤上に安定支持させるようにする。そして、前述したように構成することによって、護岸に対して局部的に外部から大きな力が作用したとしても、列状に構築したケーソンが大きく移動されたり、ケーソンの接続部に充填している遮水材に大きな変形が生じることがなく、遮水壁としての性能を、長期間に亘って維持できる構造物とすることが、可能にされることを以下に説明している。   When the partition revetment is used as a section of a waste landfill site, a water shielding treatment is performed so that water shielding can be maintained well at a connection portion of a structure such as a caisson arranged in a row. ing. Further, when configuring the partition revetment, a sheet or mat exhibiting water shielding is laid on the ground where the structure is erected to cover the ground surface and between the bottom surface of the structure. It is processed so that no gap is generated, and the structure is stably supported on the ground. By configuring as described above, even if a large force is locally applied to the revetment from the outside, the caisson constructed in a row is greatly moved or the caisson connecting portion is filled. It will be described below that it is possible to make the structure capable of maintaining the performance as a water-impervious wall for a long period of time without causing significant deformation in the water material.

図1に説明する例は、陸上で所定の大きさに作成したケーソン2……を用い、構築現場で列状に並べた各ケーソンの間には、遮水材を充満させる処理を行って、遮水処理層3を設ける。そして、前記護岸1の埋立地側の側面には、必要に応じて遮水材の層を設け、護岸本体とその側面とに亘って遮水処理を施して、仕切護岸1として構築する場合を説明している。前記仕切護岸1を構築するために、従来より護岸や防波堤等として用いられている例と同様に、ケーソン2を用いている。前記ケーソン2としては、コンクリート製や鋼製のもの、鋼製の躯体の表面にコンクリートの被覆を設けたハイブリッド製等の、任意の構造の構造物を用いることや、大きなコンクリートブロック状のもの等を用いることができる。   The example illustrated in FIG. 1 uses a caisson 2 created on land with a predetermined size, and between each caisson arranged in a line at the construction site, a process of filling a water shielding material is performed. A water shielding layer 3 is provided. And the side of the revetment side of the revetment 1 is provided with a layer of a water-impervious material if necessary, and is constructed as a partition revetment 1 by applying a water-impervious treatment across the revetment main body and its side. Explains. In order to construct the partition revetment 1, the caisson 2 is used in the same manner as in the examples conventionally used as a revetment or a breakwater. The caisson 2 is made of concrete or steel, or is made of a structure having an arbitrary structure such as a hybrid made of steel with a concrete covering on the surface of a steel casing, or a large concrete block-like one. Can be used.

前記ケーソン2を海底地盤上に列設して、護岸1を構築するために、ケーソンを立設する部分に対応させて、海底地盤10の所定の範囲に亘って、地盤改良処理を行った遮水処理層11を構築する。そして、その地盤を上から掘削して溝状の掘削凹部12を形成し、その掘削凹部12の底部に、構造物を支持する基礎構造物を構築する。
前記基礎構造物は、掘削した凹溝12の底面13の不陸(凹凸)を解消するように。コンクリートを打設して下部充填層14を構築し、そのコンクリート層の上面を平らに均して、構造物を立設させるための支持層20を構築させるようにする。
In order to construct the revetment 1 by laying the caissons 2 on the seabed ground, the ground improvement process was performed over a predetermined range of the seabed ground 10 corresponding to the part where the caisson was erected. The water treatment layer 11 is constructed. Then, the ground is excavated from above to form a groove-shaped excavation recess 12, and a foundation structure that supports the structure is constructed at the bottom of the excavation recess 12.
The foundation structure is configured to eliminate unevenness (unevenness) on the bottom surface 13 of the excavated concave groove 12. The lower filling layer 14 is constructed by placing concrete, and the upper surface of the concrete layer is flattened to construct the support layer 20 for erecting the structure.

なお、前記掘削凹部12の溝の底面の凹凸は、海底での工事を潜水作業員が行う際に、地盤表面をできるだけ平らにすることが求められるのであるが、実際には、海底での工事であり、その作業性の問題等から、平面性等の条件に多くを期待することは困難である。そこで、前記構造物の底面が接する支持部での地盤表面に、凹凸が大きく現れることを防止して、その後に遮水工の施工する効果を、より良好に発揮できるようにするために、コンクリートを打設した支持層として、下部充填層14を追加して施工すれば良いことになる。   It should be noted that the unevenness on the bottom surface of the groove of the excavation recess 12 is required to make the ground surface as flat as possible when a submarine worker performs the work on the seabed. Therefore, it is difficult to expect a large amount of conditions such as flatness due to the problem of workability. Therefore, in order to prevent the unevenness from appearing greatly on the ground surface at the support portion with which the bottom surface of the structure is in contact, and to make it possible to more effectively demonstrate the effect of construction of a water shielding work, As a support layer in which is placed, the lower filling layer 14 may be added and applied.

前記支持層としての下部充填層14は、構造物を支持する掘削凹部12の溝の底面に対して、掘削の際に生じた不陸(凹凸)を修正するために設けている。そして、地盤に掘削した凹部12の底面(構造物支持面)と、前記構造物の底面との間に、隙間が生じないように、前記支持層を位置させている。また、前記所定の深さに掘削して、溝状に構築した凹部12の位置させる地盤では、その凹部を含む海陸側の両側の所定の範囲まで、地中に所定の深さまで遮水材を注入する等の、遮水処理を行った地盤改良部11を設けている。したがって、護岸1を構築する地盤の地質が、透水性のある地盤もしくは砂地であったとしても、前記地盤改良部11を設けたことで、不透水層とすることができる。   The lower filling layer 14 as the support layer is provided on the bottom surface of the groove of the excavation recess 12 that supports the structure to correct unevenness (unevenness) generated during excavation. And the said support layer is located so that a clearance gap may not arise between the bottom face (structure support surface) of the recessed part 12 excavated in the ground, and the bottom face of the said structure. In addition, in the ground where the recess 12 constructed by excavating to the predetermined depth and having the groove shape is positioned, a water shielding material is inserted into the ground to a predetermined depth up to a predetermined range on both sides of the sea land including the recess. The ground improvement part 11 which performed the water shielding process, such as injecting, is provided. Therefore, even if the geology of the ground for constructing the revetment 1 is a water-permeable ground or sandy ground, it is possible to form an impermeable layer by providing the ground improvement portion 11.

前述したように、護岸を構築する位置での海底地盤を、不透水性の性質を持たせる処理を施してから、前記下部充填層14の上に、ケーソンの底部を支持する支持層20を設け、その支持層20の上面に、構造物としてのケーソンの底面(フーチング)4を密着させるようにして、水を通さないように一体化させる。前記支持層20としては、厚さが15cm程度のアスファルトマットを敷設して構成する例が図1に説明されており、その支持層20に対して、構造物の重量により押圧する作用を加えるようにする。そして、前記マットを挟んでケーソンを立設することで、地盤とケーソンの間では、アスファルトマットの層の上下に接するところの、ケーソン底板と下部層の各々の面との間でも、遮水性を良好に発揮可能にしている。   As described above, after the seabed ground at the position where the revetment is constructed is subjected to the treatment of making it impermeable, the support layer 20 that supports the bottom of the caisson is provided on the lower filling layer 14. The bottom surface (footing) 4 of the caisson as a structure is brought into close contact with the upper surface of the support layer 20 so as to be integrated so as not to allow water to pass therethrough. As the support layer 20, an example in which an asphalt mat having a thickness of about 15 cm is laid is illustrated in FIG. 1, and the support layer 20 is pressed by the weight of the structure. To. And by standing the caisson between the mats, the water barrier between the ground and the caisson is also provided between the caisson bottom plate and the lower layer where the asphalt mat layer touches the top and bottom. It is possible to demonstrate well.

前記図1に説明した例とは別に、図2に示す例では、掘削凹部12の底面13の上に、均しコンクリート層を下部充填層14として施工し、さらに、その充填層14の上に設ける遮水層を、アスファルト層21で構成している。前記アスファルト層21としては、図3にも説明するように、厚さがHで巾がW、長さLをケーソンの長さ等に合わせて構成したブロック状部材22を所定の間隔で敷設して設ける。   In the example shown in FIG. 2, apart from the example described in FIG. 1, the leveled concrete layer is applied as the lower filling layer 14 on the bottom surface 13 of the excavation recess 12, and further on the filling layer 14. The water shielding layer to be provided is composed of the asphalt layer 21. As described above with reference to FIG. 3, the asphalt layer 21 is formed by laying block-shaped members 22 each having a thickness H, a width W, and a length L according to the length of the caisson at predetermined intervals. Provide.

そして、前記ブロック状部材22の厚さを目盛り部材として用い、その部材に対応させた高さにアスファルトを打設して、図2に説明しているように、長く形成したブロック状部材22をアスファルト混合物と一体化させて、アスファルト層21として構築するのである。前記ブロック状部材22として実際には、厚さH=15cm、W=30cm程度とし、長さLを海中で潜水作業員が扱い得る程度に形成し、前記長いブロック状部材22を下部充填層14の上面に、所定の間隔を持たせるように並べて敷設する。   Then, the thickness of the block-shaped member 22 is used as a scale member, and asphalt is placed at a height corresponding to the member, and as shown in FIG. It is integrated with the asphalt mixture and constructed as an asphalt layer 21. The block-like member 22 is actually formed with a thickness H of about 15 cm and W = 30 cm, and a length L that can be handled by a diving worker in the sea. Are laid side by side so as to have a predetermined interval.

そして、図2に説明しているように、ブロック状部材22を含む底部全体に、前記ブロック状部材22の厚さ(H)を基準として、アスファルト混合物を打設して、ブロック状部材を含むアスファルト層を、複合支持層23とした支持層20を構築する。前記ブロック状部材22を、アスファルト層を構築する際のスケールとして用いる場合に、そのブロック状部材22の周囲部分で、後で打設するアスファルトとの間で、隙間が生じたりする欠陥が生じるということが懸念される。そこで、前記ブロック状部材22の下部や、周囲に隙間が生じないようにするために、図4に示すように、ブロック状部材に縦横、斜め方向等に貫通させた孔を設けておいて、アスファルトが隙間なく充満されるようにすれば良いと考えられる。   Then, as illustrated in FIG. 2, the asphalt mixture is placed on the entire bottom including the block-shaped member 22 on the basis of the thickness (H) of the block-shaped member 22 to include the block-shaped member. The support layer 20 having the asphalt layer as the composite support layer 23 is constructed. When the block-like member 22 is used as a scale for constructing an asphalt layer, there is a defect that a gap occurs between the block-like member 22 and the asphalt to be placed later. There is concern. Therefore, in order to prevent a gap from being generated in the lower part of the block-like member 22 or in the periphery thereof, as shown in FIG. It is considered that asphalt should be filled without gaps.

前記ブロック状部材22に上下に貫通させた孔を設けることは、前記ブロック状部材を製造する際に、アスファルト混合物の中に所定の太さの棒等を押し込んでおき、成型した後でその棒を引き抜く等の処理を施して作ることができる。その他に、ブロック状部材22を所定の形状のものとして形成した後に、パイプ等を差し込んで孔を明ける等の手法を用いて製作しても良い。前記ブロック状部材22に形成する孔は、図4(a)に示すように、任意の径の丸孔22aを、任意の間隔で設けることができるが、その孔22aは、流動性を有するアスファルトが十分に通る程度の、大きさを有するものとすることは当然である。また、前記貫通孔は、同図(b)に示すように、丸い孔でも良いが、その他に、同図(c)のように、四角断面の孔22bでも良い。その他に、断面が楕円形の孔であったり、長方形の角断面の孔として構成しても良いことは勿論である。   Providing the block-shaped member 22 with a vertically penetrating hole means that, when the block-shaped member is manufactured, a rod having a predetermined thickness is pushed into the asphalt mixture and the rod is formed after molding. It can be made by applying a process such as pulling out. In addition, after the block-shaped member 22 is formed in a predetermined shape, it may be manufactured using a technique such as inserting a pipe or the like to make a hole. As shown in FIG. 4 (a), the holes formed in the block-shaped member 22 can be provided with round holes 22a having an arbitrary diameter at arbitrary intervals. The holes 22a are formed asphalt having fluidity. Of course, it should be large enough to pass. Further, the through hole may be a round hole as shown in FIG. 5B, but may alternatively be a hole 22b having a square cross section as shown in FIG. In addition, it is needless to say that the hole may have an elliptical cross section or a rectangular square cross section.

なお、前記図示するブロック状部材22としては、特に、アスファルト混合物をブロック状に成型したものに限定されるものではなく、ゴムや任意のプラスチック材料を用いて作成しても良い。前記ブロック状部材をプラスチック材料で作成する例では、ゴム等と同様な弾性を有するものであれば、その周囲に打設するアスファルトとともに、その上に構築した構造物の重量により押圧されて変形するので、支持層14の上面と構造物の底面との間で、隙間が生じないように維持できることになる。   The block-shaped member 22 shown in the figure is not particularly limited to one obtained by molding an asphalt mixture into a block shape, and may be made using rubber or any plastic material. In the example in which the block-shaped member is made of a plastic material, if it has elasticity similar to that of rubber or the like, it is deformed by being pressed by the weight of the structure built on it as well as asphalt placed around it. Therefore, it can maintain so that a clearance gap may not arise between the upper surface of the support layer 14, and the bottom face of a structure.

また、前記ブロック状部材に設ける孔は、ブロックの上下方向に貫通させるように形成するとともに、ブロックの両側の側面にも貫通させる状態に孔を設けておくと良い。さらに、前記貫通孔の各々は、水平、垂直に設けるのみでなしに、斜めにブロックを貫通させる孔も設けておくことで、支持層20に打設したアスファルト混合物が、前記ブロック状部材に設けている孔を通って、ブロック状部材の側部に空隙があった場合に、その空隙にも充満されるように補助する。また、このブロック状部材に設けている孔を、任意の大きさに形成することで、アスファルト混合物に含まれている固形物のうち、比較的大きいサイズの塊や、液体、空気の泡等を、それが邪魔にならない位置に移動させたり、外部に向けて排出させたりすることができる。したがって、前記ブロック状の部材に孔を設けておくことで、アスファルト混合物を充満させた遮水層では、アスファルト混合物による遮水層としての性質に悪影響を及ぼすような異物が、好ましくない位置に混入されたまま残されることはなくなる。   Further, the hole provided in the block-like member is formed so as to penetrate in the vertical direction of the block, and the hole may be provided so as to penetrate through the side surfaces on both sides of the block. Further, each of the through holes is not only provided horizontally and vertically, but also provided with a hole through which the block is inclined, so that the asphalt mixture placed in the support layer 20 is provided in the block-like member. If there is a gap on the side of the block-like member through the hole, the gap is assisted. In addition, by forming the holes provided in this block-shaped member to an arbitrary size, among the solids contained in the asphalt mixture, relatively large lumps, liquid, air bubbles, etc. , It can be moved to a position where it does not get in the way, or it can be discharged to the outside. Therefore, by providing a hole in the block-shaped member, in the water shielding layer filled with the asphalt mixture, foreign substances that adversely affect the properties of the water shielding layer due to the asphalt mixture are mixed in unfavorable positions. No longer left behind.

前述したように、ブロック状部材に対して、任意の方向に貫通させた孔を多数設けたことにより、図5に説明するように、構造物を設置する凹部の下面で、下部充填層14として設けたコンクリート層で、クラック14Aが生じて隙間が形成された場合でも、容易に対応させることが可能となる。つまり、下部充填層14に生じたクラック14Aによる隙間に向けて、支持層20のアスファルト混合物が、クラック14Aの隙間に向けて流れ、隙間を塞ぐ作用が自動的に行われるので、隙間がそのまま残ることがないようにして、遮水層としての性質を損なわないように保護できる。   As described above, by providing a large number of holes penetrating the block-shaped member in an arbitrary direction, the lower filling layer 14 is formed on the lower surface of the concave portion where the structure is installed, as illustrated in FIG. Even when a crack 14A is generated and a gap is formed in the provided concrete layer, it can be easily handled. That is, the asphalt mixture of the support layer 20 flows toward the gap of the crack 14A toward the gap due to the crack 14A generated in the lower filling layer 14, and the gap is automatically closed, so that the gap remains as it is. In this way, it can be protected so as not to impair the properties of the water shielding layer.

図6に示す例は、前記図2、5に説明した例とは異なり、下部充填層14と構造物2の底面との間に、アスファルトマットを敷き込んで、支持層23を構成した場合を説明しているものである。この例において、アスファルトマットは、その構成・構造が特に限定されるものではなく、任意の厚さのものを重ねて設けることができ、その巾と長さ等も、その施工現場の状況に合わせて選択できる。   The example shown in FIG. 6 differs from the example described in FIGS. 2 and 5 in the case where the support layer 23 is configured by laying an asphalt mat between the lower filling layer 14 and the bottom surface of the structure 2. It is what is being explained. In this example, the structure and structure of the asphalt mat is not particularly limited, and can be provided with a stack of arbitrary thickness. The width and length of the asphalt mat also matches the situation at the construction site. Can be selected.

そして、前記任意の厚さのマットを下部充填層14の全面を覆うように、または、構造物2の底面に対応させた広さで施工し、その側面とマット層23、23の間に、アスファルト混合物を打設する。前述したように構成したことで、前記マット層の上下のマット間とマット層の中間部に対して、前記打設するアスファルト混合物を充満させて一体化し、構造物2の底部材4の下面が、下部充填層14の上に隙間なく立設されるようになる。
なお、前記図6に説明する例において、アスファルトマット部材23は、構造物としてのケーソンを列設する長さ方向に、連続させるように配置するが、それ等のマットの長さ方向の接続部に対しても、アスファルト混合物を充填して隙間を埋めることで、一体のものとすることができる。
Then, the mat having an arbitrary thickness is applied so as to cover the entire surface of the lower filling layer 14 or in an area corresponding to the bottom surface of the structure 2, and between the side surface and the mat layers 23, 23, Place the asphalt mixture. By being configured as described above, the asphalt mixture to be placed is filled and integrated between the upper and lower mats of the mat layer and the middle portion of the mat layer, and the lower surface of the bottom member 4 of the structure 2 is Then, it comes to stand on the lower filling layer 14 without a gap.
In the example illustrated in FIG. 6, the asphalt mat member 23 is arranged so as to be continuous in the length direction in which the caisson as the structure are arranged. On the other hand, it can be made integral by filling the asphalt mixture and filling the gap.

また、前記ブロック状部材22を含めて、アスファルト混合物を打設した層20を構築するに際して、前記ブロック状部材22の下面や側部に、アスファルト混合物が充満されないままで、隙間21aが生じるような状態が発生することもあると考えられる。しかしながら、そのような空気を含んだ空間部が残るような状態でも、前記空隙部が位置する部分で、その周囲のアスファルト混合物がブロック状部材に設けている孔22a、22c等を通って、その隙間21aに向けて移動される。それと同時に、空隙部にある空気もブロック状部材に設けている孔を通って排出されて、自動的に空隙部をアスファルトに置き換える作用が行われ、隙間がそのまま残らないように処理される。   Further, when the layer 20 in which the asphalt mixture is cast including the block-shaped member 22 is constructed, a gap 21a is generated on the lower surface or side portion of the block-shaped member 22 without being filled with the asphalt mixture. It is thought that a situation may occur. However, even in a state where such a space containing air remains, in the portion where the gap is located, the surrounding asphalt mixture passes through the holes 22a, 22c, etc. provided in the block-like member, It is moved toward the gap 21a. At the same time, the air in the gap is also discharged through the hole provided in the block-like member, and the action of automatically replacing the gap with asphalt is performed, so that the gap is not left as it is.

さらに、前記ブロックに対して所定の径の孔を上下に貫通させて設けておくことで、下部充填層14の上にアスファルト混合物の層を構築する際に、前記ブロックの下部と側面等にも、隙間なくアスファルトを充満させる処理を施すことができるものとなる。
また、前記ブロック状部材を内部に含んで、一体化するように含むアスファルト混合物の層を構築することに加えて、前記支持層20の他に、溝の側面等の任意の面に対して、薄いアスファルトのシートを敷設することで、凹部の側面を保護する手段を設けることが可能である。そして、前記掘削凹部12に設ける支持層20に追加して、シート状のものを敷設する場合には、プラスチック製もしくはゴムの任意の厚さのシートを用いて、凹溝の任意の面を保護するように敷設することができる。
Furthermore, by providing a hole with a predetermined diameter vertically through the block, when building an asphalt mixture layer on the lower packed bed 14, it is also provided on the lower and side surfaces of the block. It becomes possible to perform a process of filling asphalt without gaps.
Further, in addition to constructing a layer of the asphalt mixture including the block-shaped member inside and integrating the block-shaped member, in addition to the support layer 20, for any surface such as a side surface of the groove, By laying a thin asphalt sheet, it is possible to provide means for protecting the side surface of the recess. When a sheet-like material is laid in addition to the support layer 20 provided in the excavation recess 12, any surface of the groove is protected by using a sheet of plastic or rubber having an arbitrary thickness. Can be laid.

なお、前述したように、構造物を立設して設ける仕切護岸に対しては、それを構築する海底地盤に凹溝を掘削して、その凹溝の底部分に残る凹凸をカバーするように、任意の厚さでコンクリート層を構築して、そのコンクリート層の表面を均すことで、その上に立設する構造物の底面を安定させて位置決めできる。また、前記コンクリート層の上にアスファルト混合物の層を所定の厚さで構築することで、仕切護岸として立設する構造物の底面を、安定した状態で位置決めできる。さらに、前記アスファルト混合物の層を構築する際に、一定の間隔で配置したブロック状部材を用いて、アスファルト混合物の層の厚さを規定することで、前記アスファルト混合物の層を一定の厚さで構築でき、その作業を容易に行うことが可能となる。   In addition, as described above, for the partition revetment provided by standing a structure, a groove is excavated in the seabed ground that constructs it, and the unevenness remaining at the bottom of the groove is covered. By constructing a concrete layer with an arbitrary thickness and leveling the surface of the concrete layer, the bottom surface of the structure standing on the concrete layer can be stably positioned. Further, by constructing the asphalt mixture layer with a predetermined thickness on the concrete layer, the bottom surface of the structure standing as a partition revetment can be positioned stably. Further, when the asphalt mixture layer is constructed, the thickness of the asphalt mixture layer is regulated by using block-like members arranged at regular intervals, whereby the asphalt mixture layer has a constant thickness. Can be constructed, and the work can be easily performed.

廃棄物処分場を区画する仕切護岸の構造を説明する断面図である。It is sectional drawing explaining the structure of the partition revetment which divides a waste disposal site. 護岸の下部と地盤の関係を示す説明図である。It is explanatory drawing which shows the relationship between the lower part of a revetment and the ground. ブロック状部材の構成の説明図である。It is explanatory drawing of a structure of a block-shaped member. ブロック状部材に設ける貫通孔の説明図で、同図(a)は断面を、(b)および(c)は、孔の形状を示す平面図である。It is explanatory drawing of the through-hole provided in a block-shaped member, The figure (a) is a cross section, (b) and (c) are top views which show the shape of a hole. 構造物の下部での遮水層の補修の作用の説明図である。It is explanatory drawing of the effect | action of repair of the impermeable layer in the lower part of a structure. 図2とは異なる支持層の説明図である。It is explanatory drawing of the support layer different from FIG.

符号の説明Explanation of symbols

1 護岸、 2 ケーソン、 10 海底地盤、 11 地盤改良処理層、
12 掘削凹部、 13 底面、 14 下部充填層、
15 側部遮水材充填層、 20 支持層、 21 アスファルト層、
22 ブロック状部材、 23 マット層。
1 revetment, 2 caisson, 10 submarine ground, 11 ground improvement treatment layer,
12 excavation recess, 13 bottom surface, 14 lower packed bed,
15 side impermeable layer packing layer, 20 support layer, 21 asphalt layer,
22 block-like members, 23 mat layers.

Claims (2)

海底地盤上にケーソンのような構造物を列状に構築して海域を所定の広さに仕切り、前記仕切られた内部の区画に廃棄物を投棄するための仕切護岸の構築工法であって、
前記仕切護岸を構築するに際しては、最初に、前記構造物を設置する地盤を不透水性改良地盤とする処理を施してから、前記不透水性地盤とする地盤改良を行った地盤に凹溝を構築し、
次いで、前記凹溝の底部の表面凹凸を解消するために、コンクリートを前記凹溝の底部表面に打設して下部充填層を構築し、
前記下部充填層の上に所定の厚さのブロック状部材を一定の間隔で敷き並べて前記構造物の支持層を設け、前記ブロック状部材の間と前記構造物を立設する凹溝の底部表面を埋めるようにアスファルト混合物を打設して、前記下部充填層と一体に働く遮水層とする工程を順次施工し、
次に、前記凹溝に護岸本体となる前記構造物を列状に立設してから、前記構造物の基部と前記凹溝の間の隙間を埋めるように、アスファルト混合物を充満させる処理を行って、前記構造物の基部と不透水性地盤の遮水層とを一体化するように、遮水処理を施したことを特徴とする仕切護岸の護岸構造物の基礎構築工法。
It is a construction method of a partition revetment for constructing caisson-like structures in a row on the seabed ground and partitioning the sea area into a predetermined area, and dumping waste into the partitioned internal compartment,
When constructing the partition revetment, firstly, the ground where the structure is to be installed is treated as an impermeable improved ground, and then a groove is formed in the ground that has been improved into the impermeable ground. Build and
Next, in order to eliminate surface irregularities at the bottom of the groove, concrete is cast on the bottom surface of the groove to construct a lower packed bed,
A bottom surface of a concave groove between which the block-like members are erected and between which the block-like members are erected is provided by arranging block-like members having a predetermined thickness on the lower filling layer at regular intervals. Asphalt mixture is placed so as to fill, and a process of making a water-impervious layer that works integrally with the lower filling layer is sequentially applied,
Next, the structure that forms the revetment main body is erected in a row in the groove, and then the asphalt mixture is filled so as to fill a gap between the base of the structure and the groove. In addition, a foundation construction method for a revetment structure of a partition revetment , wherein a water impermeability treatment is performed so that a base portion of the structure and a water impervious layer of an impermeable ground are integrated .
前記凹溝の底面に前記構造物の支持層として施工する前記下部充填層の上に、多数の貫通孔を縦横に設けたブロック状部材を一定の間隔で敷き並べて、前記構造物の支持層を構築した上に前記構造物を列状に立設してから、
前記構造物の基部と凹溝との間に遮水材を充満させる処理を行って、地盤と構造物との間に隙間を生じさせないようにして、地盤と構造物とを一体化した遮水性を発揮させる仕切護岸として構築することを特長とする請求項1に記載の仕切護岸の護岸構造物の基礎構築工法。
On the bottom filling layer to be constructed as a support layer of the structure on the bottom surface of the concave groove, block-like members provided with a large number of through holes are arranged at regular intervals, and the support layer of the structure is provided. After building the above structure in a row,
A water-impervious structure that integrates the ground and the structure so as not to create a gap between the ground and the structure by performing a treatment to fill the water-impervious material between the base of the structure and the groove. The foundation construction method of the revetment structure of a partition revetment according to claim 1 , characterized in that it is constructed as a partition revetment that exerts its effect .
JP2007217692A 2007-08-24 2007-08-24 Foundation construction method for revetment structures Active JP5131742B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007217692A JP5131742B2 (en) 2007-08-24 2007-08-24 Foundation construction method for revetment structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007217692A JP5131742B2 (en) 2007-08-24 2007-08-24 Foundation construction method for revetment structures

Publications (2)

Publication Number Publication Date
JP2009052217A JP2009052217A (en) 2009-03-12
JP5131742B2 true JP5131742B2 (en) 2013-01-30

Family

ID=40503524

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007217692A Active JP5131742B2 (en) 2007-08-24 2007-08-24 Foundation construction method for revetment structures

Country Status (1)

Country Link
JP (1) JP5131742B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5977604B2 (en) * 2012-06-27 2016-08-24 ワールドエンジニアリング株式会社 Construction method of impermeable revetment

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4293435B2 (en) * 2002-08-28 2009-07-08 ワールドエンジニアリング株式会社 Construction method of managed revetment
JP2004211533A (en) * 2002-11-12 2004-07-29 Mitsubishi Heavy Ind Ltd Revetment for reclamation and its construction method
JP4761780B2 (en) * 2005-01-25 2011-08-31 ワールドエンジニアリング株式会社 Construction method of impermeable layer

Also Published As

Publication number Publication date
JP2009052217A (en) 2009-03-12

Similar Documents

Publication Publication Date Title
JP4761780B2 (en) Construction method of impermeable layer
WO2014205495A1 (en) Wall seal system
CN112252336A (en) Construction method for backfilling foundation trench of premixed fluidized solidified soil
JP4979228B2 (en) Additional construction method of impermeable layer
JP4293435B2 (en) Construction method of managed revetment
JP5093862B2 (en) Construction method of impermeable layer
JP6854479B2 (en) Liquefaction countermeasure structure for underground structures
JP2004204581A (en) Water sealing method for controlled revetment
JP4410572B2 (en) Construction method of revetment for landfill
JP5131742B2 (en) Foundation construction method for revetment structures
JP5099709B2 (en) Construction method of managed revetment
JP5728206B2 (en) Construction method of partition revetment
JP2008080325A (en) Method of constructing impervious layer
JP4822375B2 (en) Water-blocking structure of revetment
JP4315620B2 (en) Impermeable treatment method for managed waste landfill revetment
JP4761386B2 (en) Construction method of impermeable walls
JP2003113608A (en) Impervious wall structure and impervious bank protection structure using the same
JP6259271B2 (en) Caisson installation method and underground column body group
JP2011084868A (en) Reclaimed land partition revetment using caisson
JP4596469B2 (en) Landfill partition revetment
JP2005171505A (en) Partition bulkhead
JP4749444B2 (en) Impermeable layer connection method
JP4606454B2 (en) Construction method of managed revetment
JP6013889B2 (en) Upper concrete impermeable structure of revetment impermeable wall
JP3806641B2 (en) Construction method of underground structure and underground structure

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100524

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100526

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100705

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20101224

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110124

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110802

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110913

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120620

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120709

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20121031

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20121031

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151116

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 5131742

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250