KR100297436B1 - Methods for constructing a backfill of concrete structures - Google Patents

Methods for constructing a backfill of concrete structures Download PDF

Info

Publication number
KR100297436B1
KR100297436B1 KR1020000012851A KR20000012851A KR100297436B1 KR 100297436 B1 KR100297436 B1 KR 100297436B1 KR 1020000012851 A KR1020000012851 A KR 1020000012851A KR 20000012851 A KR20000012851 A KR 20000012851A KR 100297436 B1 KR100297436 B1 KR 100297436B1
Authority
KR
South Korea
Prior art keywords
concrete structure
backfill
compaction
concrete
filling
Prior art date
Application number
KR1020000012851A
Other languages
Korean (ko)
Other versions
KR20000030738A (en
Inventor
노한성
김성환
최영철
Original Assignee
정숭렬
한국도로공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 정숭렬, 한국도로공사 filed Critical 정숭렬
Priority to KR1020000012851A priority Critical patent/KR100297436B1/en
Publication of KR20000030738A publication Critical patent/KR20000030738A/en
Application granted granted Critical
Publication of KR100297436B1 publication Critical patent/KR100297436B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

본 발명은 도로, 철도, 지하철, 공항, 대규모 부지 조성 공사와 같은 토목공사에 사용되는 콘크리트 구조물의 뒷채움 시공 방법에 관한 것으로, 특히 혼합 골재 대신에 일반 토사를 이용한 콘크리트 구조물의 뒷채움 시공 방법에 관한 것이다.The present invention relates to a backfill construction method for concrete structures used in civil works, such as roads, railways, subways, airports, large-scale site construction work, and more particularly, to a backfill construction method for concrete structures using general soil instead of mixed aggregates. .

Description

콘크리트 구조물의 뒷채움 시공 방법{METHODS FOR CONSTRUCTING A BACKFILL OF CONCRETE STRUCTURES}METHODS FOR CONSTRUCTING A BACKFILL OF CONCRETE STRUCTURES}

본 발명은 도로, 철도, 지하철, 공항, 대규모 부지 조성 공사와 같은 토목공사에 사용되는 콘크리트 구조물의 뒷채움 시공 방법에 관한 것이다.The present invention relates to a backfill construction method for concrete structures used in civil engineering works such as roads, railways, subways, airports, large-scale site construction work.

콘크리트 구조물의 뒷채움부는 부등침하가 발생할 가능성이 높다. 또한, 진동 장비를 다짐에 부적절하게 사용할 경우에는 콘크리트 구조물에 손상을 줄 수 있다.The backfill of concrete structures is likely to cause unequal settlement. In addition, improper use of vibration equipment in compaction can damage concrete structures.

이를 해결하기 위하여 제안된 것이 보조기층재라 불리는 자갈과 모래 등의 혼합 골재로 뒷채움을 시공하는 방법이다.In order to solve this problem, the proposed method is to construct the backfill with mixed aggregate such as gravel and sand called auxiliary base material.

도 1은 종래의 제 1실시예에 따른 콘크리트 구조물의 뒷채움 시공을 개략적으로 도시한 단면도이고, 도 2는 도 1의 콘크리트 구조물의 뒷채움 시공 순서도이다. 도 1 및 도 2에 도시한 바와 같이, 먼저 콘크리트 구조물(10)을 설치한 후 혼합 골재로 뒷채움 시공할 수 있도록 터파기 작업을 한다. 이때 뒷채움부(14,14')에 성토된 혼합 골재를 미진동으로 다짐하기 위해, 뒷채움부(14,14')의 하단 폭(a, a'), 즉 노체(16)와 콘크리트 구조물(10)의 외벽간의 최단거리(a) 또는 노체(16')와 콘크리트 구조물(10)의 외벽간의 최단거리(a')를 0.5m 가 되도록 터파기 작업을 한다. 또한, 뒷채움부(14,14')와 접하는 노체(16,16')는 비탈면으로 형성하여, 뒷채움 시공된 혼합 골재의 중량이 콘크리트 구조물(10)에 쐐기형의 집중 하중이 작용하지 않도록 한다.1 is a cross-sectional view schematically showing the backfill construction of a concrete structure according to the first embodiment of the prior art, Figure 2 is a backfill construction flow chart of the concrete structure of FIG. As shown in Figure 1 and 2, first install the concrete structure 10, and then work the trench to be backfilled with a mixed aggregate. At this time, the bottom width (a, a ') of the back filling portion (14, 14'), that is, the furnace body 16 and the concrete structure (10) in order to compact the mixed aggregate deposited in the back filling portion (14, 14 ') with micro vibrations The shortest distance (a) between the outer wall of the c) or the furnace 16 'and the shortest distance (a') between the outer wall of the concrete structure 10 is to be dug to make 0.5m. In addition, the furnace body (16, 16 ') in contact with the back filling portion (14, 14') is formed in the slope, so that the weight of the mixed aggregate back-filled so that the wedge-shaped concentrated load does not act on the concrete structure (10).

터파기 작업을 한 후, 지반을 일정 깊이로 굴착하고 잡석을 포설하여 콘크리트 구조물(10)을 설치해야 할 위치에 기초부(12)를 형성한다.After the excavation work, the ground is excavated to a certain depth and rubble is laid to form the foundation 12 at the position where the concrete structure 10 should be installed.

기초부(12)가 형성된 위치에 콘크리트 구조물(10)을 설치한다.The concrete structure 10 is installed at the position where the foundation part 12 is formed.

콘크리트 구조물(10)을 설치한 후, 뒷채움부(14,14')에 혼합 골재를 채우면서 다짐을 한다. 이때 다짐 정도가 일층 다짐 두께 20㎝ 내지 30㎝, 상대다짐밀도 95%{본 명세서의 발명의 상세한 설명 및 청구범위에 사용된 이 수치는 모두 KS F 2312(흙의 다짐시험방법)에 의한 수치이다} 이상, 지지력계수 30kgf/㎤{본 명세서의 발명의 상세한 설명 및 청구범위에 사용된 이 수치는 모두 KS F 2301(도로의 평판재하시험법)에 의한 수치이다} 이상이 되도록 다짐을 한다. 이러한 다짐이 뒷채움부(14,14')를 채울 때까지 반복적으로 시행하여 뒷채움 시공을 완료한다.After installing the concrete structure (10), while filling the aggregate aggregate in the back-filling portion (14, 14 ') to compact. At this time, the degree of compaction is 20 cm to 30 cm in one compaction thickness, 95% relative compaction density {These values used in the detailed description and claims of the present invention are all numerical values according to KS F 2312 (the soil compaction test method). } In the above, the load capacity factor of 30 kgf / cm 3 (the values used in the detailed description and claims of the present invention are all determined by KS F 2301 (Road Flat Load Test)} is determined. This compaction is performed repeatedly until the back fill portion 14,14 'is filled to complete the back fill construction.

그러나, 전술한 혼합 골재는 자갈, 모래 등의 혼합 골재로서, 뒷채움부의 채움 재료로는 우수하나 고가이다. 따라서, 그 사용량을 적게 하기 위하여 혼합 골재의 다짐 시 전술한 바와 같이 뒷채움부의 공간 체적을 될 수 있는 한 작게 하여야 하나, 이로 인해 다짐이 불량해 질 수 있다. 또한, 지나치게 안전한 설계가 되면 혼합 골재의 사용량이 증가하고 이에 따라 공사비가 상승되는 문제점이 있다. 더욱이, 천연 골재의 사용이 증가하게 되므로 천연 골재의 과다 사용에 따른 환경 파괴라는 문제점이 나타나게 된다.However, the above-mentioned mixed aggregate is a mixed aggregate such as gravel, sand, etc., which is excellent as a filling material for the back fill portion but is expensive. Therefore, in order to reduce the amount used, the compaction of the mixed aggregate should be made as small as possible, as described above, in the compaction, but this may result in poor compaction. In addition, if the design is too safe, there is a problem in that the amount of the mixed aggregate increases and thus the construction cost increases. Moreover, since the use of natural aggregates increases, there is a problem of environmental destruction caused by excessive use of natural aggregates.

한편, 도 3은 종래의 제 2실시예에 따른 콘크리트 구조물의 뒷채움 시공을개략적으로 도시한 단면도이고, 도 4는 도 3의 콘크리트 구조물의 뒷채움 시공 순서도이다. 도 3 및 도 4에 도시한 바와 같이, 종래의 제 2실시예에 따른 콘크리트 구조물의 뒷채움 시공 방법은 전술한 종래의 제 1실시예에 따른 콘크리트 구조물의 뒷채움 시공 방법과 거의 유사하다. 즉, 터파기 작업, 기초부 형성, 콘크리트 구조물 설치, 혼합 골재로 뒷채움 시공 및 완료하는 단계로 이루어진다. 또한, 뒷채움부(24)의 하단 폭(b)도 최소 0.5m가 되도록 터파기 작업을 한다.On the other hand, Figure 3 is a cross-sectional view schematically showing the backfill construction of a concrete structure according to a second embodiment of the prior art, Figure 4 is a backfill construction flow chart of the concrete structure of FIG. 3 and 4, the backfill construction method of the concrete structure according to the second conventional embodiment is almost similar to the backfill construction method of the concrete structure according to the first conventional embodiment described above. In other words, the excavation work, forming the foundation, installing the concrete structure, backfilling construction and completion of the mixed aggregate consists of the steps. In addition, the bottom width b of the backfill portion 24 is minimum. Dig to 0.5m.

그러나 전술한 종래의 제 1실시예와는 달리, 콘크리트 구조물(20)은 기초부(22)와 일체로 설치된다는 점과, 잡석 대신 콘크리트로 기초부(22)를 형성하되, 기초부(22)가 콘크리트 구조물(20) 뿐만 아니라 뒷채움부(24)도 지지할 수 있도록 형성된다는 점에서 차이가 있다.However, unlike the first exemplary embodiment described above, the concrete structure 20 is installed integrally with the base portion 22, and forms the base portion 22 with concrete instead of rubble, but the base portion 22 Is different in that it is formed to support not only the concrete structure 20 but also the back filling portion 24.

본 발명은 전술한 문제점을 해결하기 위하여 안출된 것으로서, 천연 골재의 사용량을 줄일 뿐만 아니라 경제적인 시공을 할 수 있는 콘크리트 구조물의 뒷채움 시공 방법을 제공함에 그 목적이 있다.The present invention has been made to solve the above-described problems, and an object of the present invention is to provide a method for backfilling concrete structures that can be economically constructed as well as reducing the amount of natural aggregate.

전술한 목적을 달성하기 위한 본 발명은 노체와 콘크리트 구조물 사이에 형성된 뒷채움부를 뒷채움 시공하는 방법에 있어서, 상기 콘크리트 구조물을 지지할 수 있는 구조물 기초부와 상기 뒷채움부를 지지할 수 있는 다짐 기초부를 형성하는 단계와, 상기 구조물 기초부에 설치된 상기 콘크리트 구조물의 외벽에 충격완화재를 부착하는 단계와, 상기 뒷채움부에 일반 토사를 성토하고 다짐하는 단계를 포함하여 이루어진다.In order to achieve the above object, the present invention provides a method for backfilling a backfill portion formed between a furnace body and a concrete structure, the method comprising: forming a structure base portion capable of supporting the concrete structure and a compaction foundation portion capable of supporting the backfill portion. And attaching a shock absorber to an outer wall of the concrete structure installed at the foundation of the structure, and filling and compacting general soil in the backfill portion.

본 발명의 다른 특징은 노체와 콘크리트 구조물 사이에 형성된 뒷채움부를 뒷채움 시공하는 방법에 있어서, 콘크리트로 상기 콘크리트 구조물과 상기 뒷채움부를 지지할 수 있는 기초부를 상기 콘크리트 구조물과 일체로 형성하는 단계와, 상기 콘크리트 구조물의 외벽에 충격완화재를 부착하는 단계와, 상기 뒷채움부에 일반 토사를 성토하고 다짐하는 단계를 포함하여 이루어진다.Another feature of the present invention is a method for backfilling a backfill portion formed between a furnace body and a concrete structure, the method comprising: forming a base part integral with the concrete structure to support the concrete structure and the backfill portion with concrete, and the concrete And attaching the impact buffer to the outer wall of the structure, and filling and compacting the general soil in the backfill portion.

전술한 구성에서, 상기 다짐 기초부의 폭은 3.0m 이상으로 이루어진 것이 바람직하다.In the above configuration, it is preferable that the width of the compaction base is made of 3.0 m or more.

상기 뒷채움부를 지지할 수 있는 기초부의 폭은 3.0m 이상으로 이루어진 것이 바람직하다.The width of the base that can support the backfill is preferably made of 3.0m or more.

상기 충격완화재는 발포성 폴리스티렌(Expanded PolyStyrene; EPS)재질의 패널로 이루어지며, 이 경우에 그 두께는 5㎝ 내지 20㎝의 두께로 이루어진 것이 바람직하다.The shock absorber is made of a panel made of Expanded Polystyrene (EPS), and in this case, the thickness is preferably 5 cm to 20 cm.

상기 뒷채움부에 일반 토사를 성토하고 다짐하는 단계에서는 일반 토사의 상대다짐밀도는 90% 이상, 일반 토사의 지지력계수는 15kgf/㎤ 이상이 되도록 하는 것이 바람직하다.In the step of filling and compacting general soil in the backfill portion, the relative compaction density of general soil sand is preferably 90% or more, and the bearing coefficient of general soil sand is 15 kgf / cm 3 or more.

도 1은 종래의 제 1실시예에 따른 콘크리트 구조물의 뒷채움 시공을 개략적으로 도시한 단면도.1 is a cross-sectional view schematically showing the backfill construction of a concrete structure according to a first embodiment of the prior art.

도 2는 도 1의 콘크리트 구조물의 뒷채움 시공 순서도.Figure 2 is a backfill construction flowchart of the concrete structure of Figure 1;

도 3은 종래의 제 2실시예에 따른 콘크리트 구조물의 뒷채움 시공을 개략적으로 도시한 단면도.Figure 3 is a schematic cross-sectional view showing the backfill construction of a concrete structure according to a second embodiment of the prior art.

도 4는 도 3의 콘크리트 구조물의 뒷채움 시공 순서도.Figure 4 is a backfill construction flowchart of the concrete structure of Figure 3;

도 5는 본 발명의 제 1실시예에 따른 콘크리트 구조물의 뒷채움 시공을 개략적으로 도시한 단면도.Figure 5 is a schematic cross-sectional view showing the backfill construction of a concrete structure according to the first embodiment of the present invention.

도 6은 도 5의 콘크리트 구조물의 뒷채움 시공 순서도.6 is a backfill construction flowchart of the concrete structure of FIG.

도 7은 본 발명의 제 2실시예에 따른 콘크리트 구조물의 뒷채움 시공을 개략적으로 도시한 단면도.Figure 7 is a schematic cross-sectional view showing the backfill construction of a concrete structure according to a second embodiment of the present invention.

도 8은 도 7의 콘크리트 구조물의 뒷채움 시공 순서도.8 is a backfill construction flowchart of the concrete structure of FIG.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

100,200 : 콘크리트 구조물 110,110',210 : 충격완화재100,200: concrete structure 110,110 ', 210: shock absorber

120 : 구조물 기초부 150,150' : 다짐 기초부120: structure foundation 150,150 ': compaction foundation

140,140',240 : 뒷채움부 160,160',260 : 노체140,140 ', 240: backfill 160,160', 260: nobody

220 : 기초부220: foundation

현재 사용되고 있는 혼합 골재는 전술한 바와 같이 뒷채움재로서의 특성은 우수하나 환경 또는 경제적 측면에서 많은 문제점을 노출하고 있다.As described above, the mixed aggregate currently used has excellent properties as a backfill material, but exposes many problems in terms of environment or economy.

따라서, 본 발명자는 혼합 골재의 대체 재료를 연구한 결과 본 발명에 이르게 되었다. 즉, 콘크리트 구조물의 뒷채움 시공 시 혼합 골재 대신에 현장에서 파낸 토사나 노상토와 같은 일반 토사를 사용하되, 일반 토사의 다짐을 혼합 골재와 동일한 다짐밀도가 되도록 충분히 다져 주면 노체, 뒷채움부 및 콘크리트 구조물의 위 부분에 성토되는 포장부 등에 의하여 토압이 작용하더라도 밀도 변화가 발생하지 않아 콘크리트 구조물의 인접한 부분에서 부등침하가 발생하지 않을 것이라는 점에 착안하여 본 발명을 완성할 수 있게 되었다. 그러한 다짐 조건으로서 일반 토사를 상대다짐밀도 90% 이상, 바람직하게는 95% 이상이 되도록 다짐하면 된다는 조건을 찾아내었다. 그러나 상대다짐밀도 90% 이상, 바람직하게는 95% 이상이 되도록 다짐하기 위해서는 큰 충격하중으로 다짐을 하여야 하나 그 때 발생하는 충격하중에 의하여 콘크리트 구조물에 커다란 압력이 작용하게 되어 콘크리트 구조물에 크랙이 발생하는 등의 문제점이 발생하였다. 이건 발명에서는 이러한 문제점을 해결하기 위한 기술적 수단으로서 콘크리트 구조물의 외벽에 탄성재인 충격완화재를 부착한 후 다짐 시공하는 구성이 채택된 것이다.Therefore, the present inventors have come to the present invention as a result of studying alternative materials for mixed aggregates. In other words, when constructing the backfill of concrete structures, instead of mixed aggregates, use general soils such as excavated soils or subgrade soils, but if the compaction of the general soil is compacted to the same compaction density as the mixed aggregates, the furnace, backfill and concrete structure The present invention can be completed by paying attention to the fact that even if the earth pressure is applied by the pavement part deposited on the upper part, the density change does not occur and thus no sedimentation will occur in the adjacent part of the concrete structure. As such compaction conditions, it was found that the general earth and sand may be compacted so as to have a relative compaction density of 90% or more, preferably 95% or more. However, in order to be compacted to have a relative compaction density of 90% or more, preferably 95% or more, the compacting force must be compacted, but a large pressure is applied to the concrete structure by the impact load generated at that time, causing cracks in the concrete structure. Problems such as that occurred. In this invention, as a technical means for solving this problem is to adopt a configuration for compacting after attaching the impact buffer material elastic material to the outer wall of the concrete structure.

이하에는 첨부한 도면을 참조하여 본 발명의 바람직한 실시예에 대해서 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail a preferred embodiment of the present invention.

도 5는 본 발명의 제 1실시예에 따른 콘크리트 구조물의 뒷채움 시공을 개략적으로 도시한 단면도이고, 도 6은 도 5의 콘크리트 구조물의 뒷채움 시공 순서도이다. 도 5 및 도 6에 도시한 바와 같이, 전술한 종래의 제 1실시예와 같이 터파기 작업을 하되, 일반 토사를 사용하는 경우에는 소형진동장비로 소요의 다짐을 확보하기 어려우므로 대형진동장비로 다짐 작업을 위하여 도 5에 도시한 바와 같이, 뒷채움부(140,140')의 하단 폭(A, A'), 즉 노체(160)와 콘크리트 구조물(100)의 외벽간의 최단거리(A) 또는 노체(160')와 콘크리트 구조물(100)의 외벽간의 최단거리(A')를 3.0m 이상이 되도록 터파기 작업을 하여 뒷채움부(140,140')의 공간 체적을 크게 한다. 물론 소형진동장비를 사용하여 소요의 다짐정도를 확보할 수 있으면 3.0m 이하로 해도 좋다.5 is a cross-sectional view schematically showing the backfill construction of a concrete structure according to the first embodiment of the present invention, Figure 6 is a backfill construction flow chart of the concrete structure of FIG. As shown in Figure 5 and Figure 6, the same as the first embodiment of the prior art, but the work, but when using the general earth and sand as a large vibration equipment because it is difficult to secure the compaction of small vibration equipment As shown in FIG. 5 for the compaction operation, the bottom widths A and A 'of the rear filling parts 140 and 140', that is, the shortest distance A or the furnace body between the furnace body 160 and the outer wall of the concrete structure 100, are shown. 160 ') and the shortest distance (A') between the outer wall of the concrete structure 100 to the trench to be 3.0m or more to increase the space volume of the back-filling parts (140,140 '). Of course, it can be less than 3.0m if the compact vibration equipment can secure the required compaction degree.

터파기 작업을 한 후, 지반을 일정 깊이로 굴착하고 잡석을 포설하여 콘크리트 구조물(100)을 지지한 구조물 기초부(120)와 뒷채움부(140,140')를 지지하는 다짐 기초부(150,150')를 형성하되, 다짐 기초부(150,150')는 전술한 뒷채움부(140,140')의 하단 폭(A,A')과 같게 형성된다. 다짐 기초부(150,150')는 배수 및 뒷채움부를 지지하면서 일반 토사의 다짐 시 반력 작용에 의해 다짐 효율을 높이기 위해 시공된다. 구조물 기초부(120)와 다짐 기초부(150,150')는 동일한 구조로 시공될 수도 있다.After the excavation work, excavating the ground to a certain depth and laying rubble to support the structure foundation 120 supporting the concrete structure 100 and the compaction foundations 150 and 150 'supporting the back filling portions 140 and 140'. Forming, but the compaction base 150, 150 'is formed to be equal to the bottom width (A, A') of the above-described back-filling portion (140, 140 '). Compaction base (150,150 ') is constructed to increase the compaction efficiency by the reaction force during the compaction of the general soil while supporting the drain and backfill. The structure foundation 120 and the compaction foundation 150 and 150 ′ may be constructed in the same structure.

구조물 기초부(120)와 다짐 기초부(150,150')를 형성한 후, 전술한 종래의 제 1실시예와 같이 구조물 기초부(120)에 콘크리트 구조물(100)을 설치한다. 즉, 철근을 조립하고 거푸집을 설치하여 콘크리트를 타설하고 양생시킨 후 거푸집을 제거하며, 필요한 경우 방수 처리를 하거나 배수로를 형성한다.After the structure foundation 120 and the compaction foundation 150 and 150 ′ are formed, the concrete structure 100 is installed in the structure foundation 120 as in the first embodiment described above. In other words, reinforcing bars and installing formwork to pour concrete and cure, remove formwork, and if necessary, waterproofing or drainage.

콘크리트 구조물(100)을 설치한 후, 본 발명의 제 1실시예에서는 바로 일반 토사로 뒷채움 시공하지 않고 콘크리트 구조물(100)의 외벽에 충격완화재(110,110')를 각각 부착한다. 전술한 바와 같이, 일반 토사를 상대다짐밀도 90% 이상, 바람직하게는 95% 이상이 되도록 다짐하기 위해서는 일반 토사에 큰 충격하중과 진동하중이 작용하도록 다짐 작업을 해야 한다. 이때 발생한 충격하중과 진동하중은 콘크리트 구조물(100)에 균열과 같은 콘크리트 구조물의 손상을 유발시킬 수 있다. 따라서, 충격완화재(110,110')는 이때 발생하는 충격하중과 진동하중으로부터 콘크리트 구조물(100)을 보호하기 위하여 콘크리트 구조물(100)의 외벽에 부착된다.After the concrete structure 100 is installed, in the first embodiment of the present invention, the impact buffers 110 and 110 ′ are attached to the outer walls of the concrete structure 100 without backfilling with general soil. As described above, in order to compact the general soil to have a relative compaction density of 90% or more, preferably 95% or more, a compaction work must be performed so that a large impact load and a vibration load act on the general soil. The impact load and the vibration load generated at this time may cause damage to the concrete structure such as cracks in the concrete structure 100. Therefore, the shock absorbers 110 and 110 ′ are attached to the outer wall of the concrete structure 100 to protect the concrete structure 100 from the impact and vibration loads generated at this time.

전술한 충격완화재(110,110')는 충격흡수성이 우수한 탄성재로서 플라스틱재 또는 발포성 폴리스티렌 (Expanded PolyStyrene; EPS)재, 바람직하게는 발포성 폴리스티렌(EPS)재의 패널을 사용한다. 또한, 충격완화재(110,110')는 5 내지 20㎝의 두께, 바람직하게는 10㎝의 두께를 사용하는데, 그 두께가 5cm 미만이면 충격흡수율이 나쁘고, 두께가 20cm를 초과하게 되면 비경제적일 수 있다.The above-described shock absorber (110, 110 ') uses a panel of plastic or expanded polystyrene (EPS) material, preferably expanded polystyrene (EPS) material as an elastic material having excellent shock absorption. In addition, the impact buffer (110, 110 ') uses a thickness of 5 to 20cm, preferably 10cm, if the thickness is less than 5cm, the shock absorption is bad, if the thickness exceeds 20cm can be uneconomical have.

콘크리트 구조물(100)에 충격완화재(110,110,)를 부착한 후, 뒷채움부(140,140')에 일반 토사를 성토하고 다짐을 한다. 이때 일반 토사는 다짐 두께 20㎝ 내지 30㎝, 상대다짐밀도는 90% 이상, 바람직하게는 95% 이상, 지지력계수는 15kgf/㎤ 이상이 되도록 다짐을 한다. 이러한 다짐이 뒷채움부(140,140')를 채울 때까지 반복적으로 시행하여 뒷채움 시공을 완료한다.After attaching the shock absorbing material (110, 110,) to the concrete structure 100, the general earth and sand in the back-filling portion (140, 140 ') and compacts. At this time, the general soil is compacted so that the compaction thickness is 20cm to 30cm, the relative compaction density is 90% or more, preferably 95% or more, and the bearing capacity factor is 15 kgf / cm 3 or more. This compaction is performed repeatedly until the back fill portions 140 and 140 'are filled to complete the back fill construction.

한편, 도 7은 본 발명의 제 2실시예에 따른 콘크리트 구조물의 뒷채움 시공을 개략적으로 도시한 단면도이고, 도 8은 도 7의 콘크리트 구조물의 뒷채움 시공 순서도이다. 도 7 및 도 8에 도시한 바와 같이, 본 발명의 제 2실시예에 따른 콘크리트 구조물의 뒷채움 시공 방법은 전술한 본 발명의 제 1실시예에 따른 콘크리트 구조물의 뒷채움 시공 방법과 거의 유사하다. 즉, 도 8에 도시한 바와 같이, 뒷채움부(240)의 하단 폭(B), 즉 콘크리트 구조물(200)의 외벽과 노체(260) 사이의 최단거리를 3.0m 이상이 되도록 터파기 작업을 한다. 터파기 작업을 한 후, 콘크리트 구조물(200)과 뒷채움(240)을 지지할 수 있는 기초부(220)를 형성한다. 다음, 기초부(220)에 콘크리트 구조물(200)을 설치한다. 기초부(220)에 설치된 콘크리트 구조물(200)의 외벽에 충격완화재(210)를 부착한다. 그 다음에, 일반 토사로 뒷채움 시공 및 완료하는 단계로 이루어진다.On the other hand, Figure 7 is a cross-sectional view schematically showing the backfill construction of a concrete structure according to a second embodiment of the present invention, Figure 8 is a backfill construction flow chart of the concrete structure of FIG. As shown in Figure 7 and 8, the method of backfilling the concrete structure according to the second embodiment of the present invention is almost similar to the method of backfilling the concrete structure according to the first embodiment of the present invention described above. That is, as shown in Figure 8, the bottom width (B) of the back filling portion 240, that is, the digging operation so that the shortest distance between the outer wall of the concrete structure 200 and the furnace body 260 is more than 3.0m. . After the digging operation, the foundation 220 is formed to support the concrete structure 200 and the back filling 240. Next, the concrete structure 200 is installed on the base portion 220. The shock absorber 210 is attached to the outer wall of the concrete structure 200 installed on the base portion 220. Then, the backfill construction and completion of the general soil.

그러나 전술한 본 발명의 제 1실시예와는 달리, 콘크리트 구조물(200)은 기초부(220)와 일체로 설치된다는 점과, 잡석 대신 콘크리트로 기초부(220)를 형성하되, 기초부(220)가 콘크리트 구조물(200) 뿐만 아니라, 뒷채움부(240)를 지지할 수 있도록 일체로 형성된다는 점에서 차이가 있다.However, unlike the first embodiment of the present invention described above, the concrete structure 200 is installed integrally with the base portion 220, and forms the base portion 220 with concrete instead of rubble, but the base portion 220 ) Differs in that it is integrally formed to support the backfill 240 as well as the concrete structure 200.

본 발명에 따른 콘크리트 구조물의 뒷채움 시공 방법은 전술한 실시예에 국한되지 않고 본 발명의 기술 사상이 허용하는 범위 내에서 다양하게 변형하여 실시할 수 있다.The backfill construction method of the concrete structure according to the present invention is not limited to the above-described embodiment can be carried out in various modifications within the range allowed by the technical idea of the present invention.

이상에서 설명한 바와 같은 본 발명의 콘크리트 구조물의 뒷채움 시공 방법에 따르면, 뒷채움 시공 시 혼합 골재를 사용하지 않고 현장에서 파낸 토사 또는 노상토와 같은 일반 토사를 사용할 수 있는 효과가 있다.According to the backfill construction method of the concrete structure of the present invention as described above, there is an effect that can be used for general soil, such as soil excavation or subgrade soil excavated in the field without using the mixed aggregate during the backfill construction.

Claims (10)

노체와 콘크리트 구조물 사이에 형성된 뒷채움부를 뒷채움 시공하는 방법에 있어서,In the method of backfilling the backfill formed between the furnace body and the concrete structure, 상기 콘크리트 구조물을 지지할 수 있는 구조물 기초부와 상기 뒷채움부를 지지할 수 있는 다짐 기초부를 형성하는 단계와,Forming a structure base part capable of supporting the concrete structure and a compaction base part capable of supporting the backfill part; 상기 구조물 기초부에 설치된 상기 콘크리트 구조물의 외벽에 충격완화재를 부착하는 단계와,Attaching a shock absorber to an outer wall of the concrete structure installed at the foundation of the structure; 상기 뒷채움부에 일반 토사를 성토하고 다짐하는 단계를 포함하여 이루어진 것을 특징으로 하는 콘크리트 구조물의 뒷채움 시공 방법.Backfill construction method of the concrete structure, characterized in that comprising the step of filling the general earth and sand to the backfill. 제 1 항에 있어서, 상기 다짐 기초부의 폭은 3.0m 이상으로 이루어진 것을 특징으로 하는 콘크리트 구조물의 뒷채움 시공 방법.The method of claim 1, wherein the compaction base has a width of 3.0 m or more. 제 2 항에 있어서, 상기 충격완화재는 발포성 폴리스티렌(Expanded PolyStyrene; EPS)재질의 패널로 이루어진 것을 특징으로 콘크리트 구조물의 뒷채움 시공 방법.The method of claim 2, wherein the shock absorber is made of expanded polystyrene (EPS) panel. 제 3 항에 있어서, 상기 충격완화재는 5㎝ 내지 20㎝의 두께로 이루어진 것을 특징으로 하는 콘크리트 구조물의 뒷채움 시공 방법.The method of claim 3, wherein the impact buffer is made of a thickness of 5cm to 20cm. 제 1 항 내지 제 4 항 중 어느 한 항에 있어서, 상기 뒷채움부에 일반 토사를 성토하고 다짐하는 단계에서는 일반 토사의 상대다짐밀도는 90% 이상, 일반 토사의 지지력계수는 15 kgf/㎤ 이상이 되도록 한 것을 특징으로 하는 콘크리트 구조물의 뒷채움 시공 방법.The method of any one of claims 1 to 4, wherein in the step of filling and compacting general soil in the backfill portion, the relative compaction density of general soil sand is 90% or more, and the bearing coefficient of general soil sand is 15 kgf / cm3 or more. Backfill construction method of the concrete structure, characterized in that as possible. 노체와 콘크리트 구조물 사이에 형성된 뒷채움부를 뒷채움 시공하는 방법에 있어서,In the method of backfilling the backfill formed between the furnace body and the concrete structure, 콘크리트로 상기 콘크리트 구조물과 상기 뒷채움부를 지지할 수 있는 기초부를 상기 콘크리트 구조물과 일체로 형성하는 단계와,Forming a base part integral with the concrete structure capable of supporting the concrete structure and the backfill portion with concrete; 상기 콘크리트 구조물의 외벽에 충격완화재를 부착하는 단계와,Attaching a shock absorber to an outer wall of the concrete structure; 상기 뒷채움부에 일반 토사를 성토하고 다짐하는 단계를 포함하여 이루어진 것을 특징으로 하는 콘크리트 구조물의 뒷채움 시공 방법.Backfill construction method of the concrete structure, characterized in that comprising the step of filling the general earth and sand to the backfill. 제 6 항에 있어서, 상기 뒷채움부를 지지할 수 있는 기초부의 폭은 3.0m 이상으로 이루어진 것을 특징으로 하는 콘크리트 구조물의 뒷채움 시공 방법.The method of claim 6, wherein the base portion capable of supporting the backfill portion has a width of 3.0 m or more. 제 7 항에 있어서, 상기 충격완화재는 발포성 폴리스티렌(Expanded PolyStyrene; EPS)재질의 패널로 이루어진 것을 특징으로 콘크리트 구조물의 뒷채움 시공 방법.8. The method of claim 7, wherein the impact buffer is made of expanded polystyrene (EPS) panel. 제 8 항에 있어서, 상기 충격완화재는 5㎝ 내지 20㎝의 두께로 이루어진 것을 특징으로 하는 콘크리트 구조물의 뒷채움 시공 방법.9. The method of claim 8, wherein the impact buffer is made of a thickness of 5 cm to 20 cm. 제 6 항 내지 제 9 항 중 어느 한 항에 있어서, 상기 뒷채움부에 일반 토사를 성토하고 다짐하는 단계에서는 일반 토사의 상대다짐밀도는 90% 이상, 일반 토사의 지지력계수는 15 kgf/㎤ 이상이 되도록 한 것을 특징으로 하는 콘크리트 구조물의 뒷채움 시공 방법.10. The method according to any one of claims 6 to 9, wherein in the step of filling and compacting general soil in the backfill portion, the relative compaction density of general soil sand is 90% or more, and the bearing coefficient of general soil sand is 15 kgf / cm3 or more. Backfill construction method of the concrete structure, characterized in that as possible.
KR1020000012851A 2000-03-14 2000-03-14 Methods for constructing a backfill of concrete structures KR100297436B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020000012851A KR100297436B1 (en) 2000-03-14 2000-03-14 Methods for constructing a backfill of concrete structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020000012851A KR100297436B1 (en) 2000-03-14 2000-03-14 Methods for constructing a backfill of concrete structures

Publications (2)

Publication Number Publication Date
KR20000030738A KR20000030738A (en) 2000-06-05
KR100297436B1 true KR100297436B1 (en) 2001-11-03

Family

ID=19655124

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020000012851A KR100297436B1 (en) 2000-03-14 2000-03-14 Methods for constructing a backfill of concrete structures

Country Status (1)

Country Link
KR (1) KR100297436B1 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020025856A (en) * 2001-12-28 2002-04-04 이기홍 Prevention of approach slab settlement by applying non-com paction abutment backfilling method
KR20040086017A (en) * 2003-03-31 2004-10-08 박성언 Drainage method for civil engineering works using fiber filters and, latticelike block and gunny bag product made by using foaming resin pellets
KR101005469B1 (en) * 2010-07-29 2011-01-05 주식회사 남광이앤씨 The method which expands the pedestrian passage
CN110499775B (en) * 2019-08-26 2024-05-31 上海建工二建集团有限公司 Bearing platform foundation backfill structure and construction method
CN111074907A (en) * 2019-11-21 2020-04-28 中铁六局集团有限公司 Construction method for backfilling concrete
CN114960692B (en) * 2022-06-14 2024-04-26 鞍山三冶建筑工程有限公司 Backfilling method for reducing influence of water on basement exterior wall

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000008476A (en) * 1998-07-14 2000-02-07 유현식 Construction method of laying culvert paving expanded polysterene block

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000008476A (en) * 1998-07-14 2000-02-07 유현식 Construction method of laying culvert paving expanded polysterene block

Also Published As

Publication number Publication date
KR20000030738A (en) 2000-06-05

Similar Documents

Publication Publication Date Title
Terashi et al. Ground improvement-state of the art
Han et al. Use of geogrid-reinforced and pile-supported earth structures
CN103958780B (en) The method for forming cementing retaining wall
CN106884433A (en) Control vibrations pile pulling causes the structure of underground structure depression and control depression method
CN109914173A (en) Foam lightweight soil pours platform back structure and its construction method in Expressway Extension Project
KR100816382B1 (en) A stone column reinforced with uniformly graded permeable concrete and method for it
KR100603140B1 (en) The structure construction method of having used geogrid reinforced stone column and this
KR100297436B1 (en) Methods for constructing a backfill of concrete structures
KR20090105548A (en) Cut and Cover Tunnels by useing CSP and Geotextile and the Construction Method thereof
CN110453687B (en) Protection structure of subway station foundation pit excavation pipeline and construction method
CN114164726B (en) Local deep excavation backfill structural roadbed and rapid construction method
CN113494074B (en) Building foundation treatment method for area with liquefied soil bearing stratum
JPH05287723A (en) Method for constructing foundation ground of road, etc., onto poor subsoil
JPS62260919A (en) Small pile for reinforcing foundation ground to earthquake
CN215052842U (en) Column hammer ramming method pore-forming reinforcement pile composite foundation structure
CN209555946U (en) A kind of reparation structure that high embankment collapses
Bathurst et al. Earth retaining structures and reinforced slopes
CN111287041A (en) Novel soil retaining structure in limited space and construction process thereof
KR100705715B1 (en) embankment method of backfill construction
CN109972654A (en) A kind of high barricade of J-type anchor pole and its construction method
KR20060132227A (en) Geogrid reinforced stone column and stone column method of construction
KR100536429B1 (en) Block structure of inorganic porous material and laying method using that
JP3101371B2 (en) Temporary backfill method
CN216194920U (en) Large immersed tube tunnel backfill structure with seismic isolation performance
JP3155456B2 (en) Pile structure to be joined to floor slab connected to foam resin material, and construction method of pile structure

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130503

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20140502

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20150430

Year of fee payment: 15

FPAY Annual fee payment

Payment date: 20160428

Year of fee payment: 16

FPAY Annual fee payment

Payment date: 20170502

Year of fee payment: 17

FPAY Annual fee payment

Payment date: 20190502

Year of fee payment: 19