JP2009144425A - Shield method by direct placing concrete lining - Google Patents

Shield method by direct placing concrete lining Download PDF

Info

Publication number
JP2009144425A
JP2009144425A JP2007323207A JP2007323207A JP2009144425A JP 2009144425 A JP2009144425 A JP 2009144425A JP 2007323207 A JP2007323207 A JP 2007323207A JP 2007323207 A JP2007323207 A JP 2007323207A JP 2009144425 A JP2009144425 A JP 2009144425A
Authority
JP
Japan
Prior art keywords
concrete
inner mold
lining
shield
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007323207A
Other languages
Japanese (ja)
Inventor
Makoto Kikuchi
眞 菊地
Masaharu Saito
雅春 齋藤
Shigeru Matsuoka
茂 松岡
Keiichi Takamura
圭一 高村
Koji Hatao
浩司 畑生
Mitsuo Chijiiwa
三夫 千々岩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tekken Corp
Original Assignee
Tekken Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tekken Corp filed Critical Tekken Corp
Priority to JP2007323207A priority Critical patent/JP2009144425A/en
Publication of JP2009144425A publication Critical patent/JP2009144425A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a shield method by a direct placing concrete lining which prevents concrete from adhereing to an end frame, suppresses the occurence of trouble when placing the concrete and accordingly achieves the quality improvement of the lining concrete, the improvement of construction speed, and the reduction of construction cost. <P>SOLUTION: In the shield method by the direct placing concrete lining, a new inner form 5a continuous with existing inner forms 5b is assembled into a ring to allow the end form 8 at the inner circumference of a tail part 6 to be slidable thereon inside the tail part 6 of a shield machine, the concrete is placed between the inner form 5 and a natural ground E at the rear of the end frame while propelling the shield machine by reaction force from the inner form 5, and the placing concrete is always pressurized with a predetermined pressure by the end form 8, and further a plurality of concrete placing openings 13 along a tunnel circumferential direction are arranged in the inner form 5 and the concrete is placed through the concrete placing openings 13. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

この発明は、直打ちコンクリートライニングによるシールド工法に関し、さらに詳細には、シールド機を使用してトンネルを掘削するトンネル工法において、シールド機の掘進に伴って施す地山のライニング技術に関する。   The present invention relates to a shield method using direct-cast concrete lining, and more particularly, to a ground lining technique applied as a shield machine is dug in a tunnel method using a shield machine to excavate a tunnel.

シールド工法におけるライニング工法として、シールド機のテール部でコンクリートを打設し、ライニング(覆工)を構築するいわゆる直打ちコンクリートライニング工法(ECL工法:Extrude Concrete Lining 工法)が知られている。この工法によれば、シールド機を推進させながら同時にフレッシュコンクリートを加圧充填して地山に密着させるので、高品質な覆工体を構築できるだけでなく、地盤沈下も抑制できるという利点がある。   As a lining method in the shield method, a so-called direct concrete lining method (ECL method: Extrude Concrete Lining method) is known in which concrete is cast at the tail portion of a shield machine to construct a lining (lining). According to this construction method, fresh concrete is pressurized and filled in close contact with the ground while propelling the shield machine, so that not only a high-quality lining body can be constructed but also ground subsidence can be suppressed.

このような直打ちコンクリートライニング工法において、ライニングコンクリートは次のようにして打設される。すなわち、シールド機のテール部内方で内型枠を組み立て、内型枠から反力をとってシールド機を推進させながら、内型枠と地山との間にコンクリートが打設される。シールド機のテール部内周には内型枠との間を閉塞して摺動するリング状の妻枠が設けられ、この妻枠にコンクリートの打設口が周方向に沿って複数設けられている。コンクリートは配管に設けられたロータリーバルブを介して打設口に順次供給され、各打設口から順次打設される。   In such a direct-concrete concrete lining method, the lining concrete is placed as follows. That is, the inner mold is assembled inside the tail portion of the shield machine, and concrete is placed between the inner mold and the natural ground while propelling the shield machine by taking the reaction force from the inner mold. On the inner periphery of the tail part of the shield machine, there is provided a ring-shaped wife frame that closes and slides between the inner molds, and a plurality of concrete placement openings are provided along the circumferential direction in the wife frame. . The concrete is sequentially supplied to the placement port via a rotary valve provided in the pipe, and is sequentially placed from each placement port.

しかしながら、従来の工法は、妻枠に設けられた打設口を介してコンクリートを打設するため、打設口近傍にコンクリートが付着し、それが成長して打設口を閉塞してしまうという問題がある。また、妻枠が付着コンクリートによって拘束され、コンクリート打設トラブルが発生するという問題がある。さらに、打設口やその配管は定期的に清掃しなければならないが、テール部内方に配置される内型枠の位置によってはこれが邪魔になって清掃が不能になることがあり、清掃が不適切な場合にはコンクリート打設トラブルの原因となる。   However, in the conventional construction method, since concrete is placed through a placement opening provided in the frame, the concrete adheres to the vicinity of the placement opening, and it grows and closes the placement opening. There's a problem. In addition, there is a problem that the concrete frame is troubled because the wife frame is restrained by the adhering concrete. In addition, the installation port and its piping must be cleaned regularly, but depending on the position of the inner mold placed inside the tail, this may interfere with the cleaning, making cleaning impossible. When appropriate, it can cause concrete placement problems.

この出願の発明に関連する先行技術情報としては特許文献1に記載のものがある。しかしながら、特許文献1に記載された技術は、妻枠に袋体を設けて膨らますことにより付着コンクリートを妻枠から分離する、あるいは掻き落とし棒より内型枠の外側から付着コンクリートを掻き落とすものであり、根本的な解決には至らない。
特開2002−295193号公報
As prior art information related to the invention of this application, there is one described in Patent Document 1. However, the technique described in Patent Document 1 separates the adhered concrete from the wife frame by providing a bag body on the wife frame and swells, or scrapes the adhered concrete from the outside of the inner mold frame with a scraping bar. Yes, it does not lead to a fundamental solution.
JP 2002-295193 A

この発明は上記のような技術的背景に基づいてなされたものであって、次の目的を達成するものである。
この発明の目的は、妻枠にコンクリートが付着することがなく、コンクリートの打設トラブルの発生を抑えることができ、これによりライニングコンクリートの品質向上、施工速度の向上、施工コストの縮減を図ることができる、直打ちコンクリートライニングによるシールド工法を提供することにある。
The present invention has been made based on the technical background as described above, and achieves the following object.
The object of the present invention is to prevent the concrete from adhering to the frame and to prevent the occurrence of concrete placing trouble, thereby improving the quality of the lining concrete, improving the construction speed, and reducing the construction cost. It is to provide a shield construction method by direct cast concrete lining.

この発明は上記課題を達成するために、次のような手段を採用している。
すなわち、この発明は、シールド機のテール部の内方で、該テール部の内周に設けられた妻枠が摺接可能なように、既設内型枠と連続する新設内型枠をリング状に組み立て、前記内型枠から反力をとってシールド機を推進させながら、同時に前記妻枠後方における前記内型枠と地山との間にコンクリートを打設し、打設コンクリートを前記妻枠によって所定圧力で常時加圧する直打ちコンクリートライニングによるシールド工法において、
前記内型枠にトンネル周方向に沿った複数のコンクリート打設口を設け、この打設口からコンクリートを打設することを特徴とする直打ちコンクリートライニングによるシールド工法にある。
The present invention employs the following means in order to achieve the above object.
That is, according to the present invention, a new inner mold form continuous with an existing inner mold form is formed in a ring shape so that a wife frame provided on the inner periphery of the tail part can be slidably contacted inside the tail part of the shield machine. While assembling and propelling the shield machine by taking a reaction force from the inner formwork, at the same time, placing concrete between the inner formwork and the ground in the rear of the wifeframe, In the shield method by direct-fired concrete lining that is constantly pressurized at a predetermined pressure by
A direct construction concrete lining shielding method characterized in that a plurality of concrete placement openings are provided in the inner mold frame along the circumferential direction of the tunnel, and concrete is placed through the placement openings.

より具体的には、前記シールド機は前記内型枠の1リング長さごとに推進し、その1リング長さの推進開始と同時に、前記新設内型枠に隣接している最前部の前記既設内型枠の前記打設口からコンクリートを打設する。また、前記複数のコンクリート打設口から同時にコンクリートを打設する。さらに、前記複数のコンクリート打設口は、1つのリング状内型枠に関してトンネル軸方向に複数列設けられている。   More specifically, the shield machine is propelled for each ring length of the inner mold, and at the same time as the one-ring length starts to be propelled, the foremost existing part adjacent to the new inner mold is installed. Concrete is placed from the placement opening of the inner mold. Moreover, concrete is simultaneously placed from the plurality of concrete placement openings. Further, the plurality of concrete placement openings are provided in a plurality of rows in the tunnel axis direction with respect to one ring-shaped inner mold.

この発明によれば、内型枠に設けた打設口からライニングコンクリートを打設するようにしたので、妻枠から打設する場合の問題を一挙に解決することができる。すなわち、妻枠にコンクリートが付着することがなく、コンクリート打設トラブルの発生を抑えることができ、ライニングコンクリートの品質向上、施工速度の向上、施工コストの縮減を図ることができる。   According to the present invention, since the lining concrete is cast from the casting port provided in the inner mold, the problems in the case of casting from the wife frame can be solved at once. That is, the concrete does not adhere to the end frame, the occurrence of a concrete placing trouble can be suppressed, the quality of the lining concrete can be improved, the construction speed can be improved, and the construction cost can be reduced.

この発明の実施形態を図面を参照しながら以下に説明する。まず、図1,図2を参照して、この発明が適用される直打ちコンクリートライニングによるシールド工法の施工手順を概略説明する。   Embodiments of the present invention will be described below with reference to the drawings. First, with reference to FIG. 1 and FIG. 2, the construction procedure of the shield construction method by the direct cast concrete lining to which this invention is applied is demonstrated roughly.

シールド機1は本体胴部(スキンプレート)2の前部に隔壁3を備え、隔壁3とカッター4との間に泥水や泥土などを滞留させるチャンバー5が形成されている。直打ちライニング工法ではライニングコンクリートを打設するために、内型枠5が用いられる。この内型枠は周方向に複数に分割された分割ピースをリング状に組み立てて形成される。本体胴部2の内部にはシールド機1を推進させるための複数の推進ジャッキ7が周方向に沿って配置され、さらに本体胴部2のテール部6の内周には、内型枠5とテール部6との間を閉塞するリング状の妻枠8が内型枠5に対して摺動するように配置されている。妻枠8は周方向に複数配置された妻枠ジャッキ9により押圧され、この妻枠ジャッキ9は図示しないアキュムレータに接続された圧力調整装置10により加圧力が常に所定圧力に維持されるように制御される。   The shield machine 1 is provided with a partition wall 3 at the front of a main body trunk (skin plate) 2, and a chamber 5 is formed between the partition wall 3 and the cutter 4 for retaining muddy water and mud. In the direct lining method, the inner mold 5 is used for placing lining concrete. This inner mold is formed by assembling a plurality of pieces divided in the circumferential direction into a ring shape. A plurality of propulsion jacks 7 for propelling the shield machine 1 are arranged along the circumferential direction inside the main body body 2, and an inner mold 5 and an inner periphery of the tail section 6 of the main body body 2 are arranged. A ring-shaped wife frame 8 that closes between the tail part 6 and the inner mold frame 5 is arranged to slide. The wife frame 8 is pressed by a plurality of wife frame jacks 9 arranged in the circumferential direction, and the wife frame jack 9 is controlled by a pressure adjusting device 10 connected to an accumulator (not shown) so that the applied pressure is always maintained at a predetermined pressure. Is done.

図1(a)は、新設の内型枠5aを組み立て終えた状態を示している。新設内型枠5aはテール部6の内方で既設内型枠5bと連続するように組み立てられる。この新設内型枠5aの組み立て作業中はシールド機1は非推進状態にあるが、妻枠8はシールド機1の非推進状態及び後述する推進状態を含めて常時ライニングコンクリート11を前記の所定圧力で加圧している。   Fig.1 (a) has shown the state which completed the assembly of the newly installed inner mold 5a. The new inner mold 5a is assembled inside the tail portion 6 so as to be continuous with the existing inner mold 5b. The shield machine 1 is in a non-propulsion state during the assembly work of the new internal formwork 5a, but the end frame 8 always keeps the lining concrete 11 at the predetermined pressure including the non-propulsion state of the shield machine 1 and the propulsion state described later. Pressurized with.

新設内型枠5aの組立後、図1(b)に示すように、シールド機1を推進させて掘進を開始する。1工程での掘進長は内型枠5の1リング分長さ(トンネル軸方向長さ)である。シールド機1は推進ジャッキ7の作動により推進され、その際の反力は内型枠5すなわち内型枠5とライニングコンクリート11との摩擦力から得られる。そして、シールド機1の推進に伴って、妻枠8の後方における内型枠5と地山Eとの間にフレッシュコンクリートが打設される。このフレッシュコンクリートは、前記のように妻枠8によって所定圧力で加圧される。フレッシュコンクリートは、この発明により、内型枠5に設けた打設口から打設されるが、その詳細は後述する。   After assembling the new inner form 5a, as shown in FIG. 1 (b), the shield machine 1 is propelled to start excavation. The digging length in one process is the length of one ring of the inner mold 5 (the length in the tunnel axis direction). The shield machine 1 is propelled by the operation of the propulsion jack 7, and the reaction force at that time is obtained from the frictional force between the inner mold 5, that is, the inner mold 5 and the lining concrete 11. Then, along with the propulsion of the shield machine 1, fresh concrete is placed between the inner mold 5 and the natural ground E behind the end frame 8. This fresh concrete is pressurized at a predetermined pressure by the end frame 8 as described above. According to the present invention, fresh concrete is placed from a placement opening provided in the inner mold 5, details of which will be described later.

図2(c)は、シールド機1が内型枠5の1リング長さ分の推進を終えて、停止している状態を示している。このとき、コンクリートの打設も停止しているが、この停止中も前記のように、妻枠8は打設コンクリートを所定圧力で加圧している。   FIG. 2C shows a state in which the shield machine 1 has finished propulsion for one ring length of the inner mold 5 and has stopped. At this time, the placement of the concrete is also stopped, but during this stop, the end frame 8 pressurizes the placed concrete with a predetermined pressure as described above.

シールド機1の停止時には、図2(d)に示すように、推進ジャッキ7を縮めて新設内型枠5aが組み立てられる。この新設内型枠5aは、最後尾にある既設内型枠5bを盛り替えたものである。以下、上記と同様の手順が繰り返される。   When the shield machine 1 is stopped, as shown in FIG. 2D, the propulsion jack 7 is contracted to assemble the new inner form 5a. This new internal formwork 5a is a rearrangement of the existing internal formwork 5b at the end. Thereafter, the same procedure as described above is repeated.

図3は、コンクリートの打設状態を詳細に示している。内型枠5は、前記のように、複数(例えば8分割)の分割ピースで構成され、それらのうち幾つかの分割ピースに、内型枠の長さ方向ほぼ中央に位置するようにコンクリートの打設口13が設けられている。この実施形態では、図4に模式的に示すように、トンネル天端(ポートC1)と両側部(ポートR2,R3,L2,L3)に計5個の打設ポートが配置され、各打設ポート位置に対応した分割ピースに打設口13が設けられている。   FIG. 3 shows the concrete placement state in detail. As described above, the inner mold 5 is composed of a plurality of (for example, eight divisions) divided pieces, and some of the divided pieces are made of concrete so as to be positioned approximately in the center in the length direction of the inner mold. A placement port 13 is provided. In this embodiment, as schematically shown in FIG. 4, a total of five driving ports are arranged at the tunnel top (port C1) and both sides (ports R2, R3, L2, L3). A placement port 13 is provided in the divided piece corresponding to the port position.

コンクリートの圧送管14は各打設ポートごとに設けられ(図4参照)、各圧送管14は二方切換弁15を介して2つの分岐管16a,16bに分岐している。そして、図3に示すように、一方の分岐管16aは新設内型枠5aの打設口13に、また他方の分岐管16bは最前部の既設内型枠5bの打設口13にそれぞれ接続されている。   A concrete pressure feeding pipe 14 is provided for each placement port (see FIG. 4), and each pressure feeding pipe 14 branches into two branch pipes 16 a and 16 b via a two-way switching valve 15. As shown in FIG. 3, one branch pipe 16a is connected to the casting port 13 of the newly installed inner mold 5a, and the other branch pipe 16b is connected to the casting port 13 of the existing inner mold 5b. Has been.

シールド機1の推進開始時、妻枠8は新設内型枠5aに隣接する最前部の既設内型枠5bの打設口13の直前方に位置している。そして、シールド機1が推進すると同時に、その最前部の既設内型枠5bの打設口13からコンクリートの打設が開始される。このコンクリートの打設は、周方向に関して同時すなわち各打設ポートC1,R2,R3,L2,L3から同時打設である。シールド機1が内型枠5の1リング長さ分推進して停止すると、妻枠8は新設内型枠5aの打設ポート13の直前方に位置する。次工程での推進時にはこの新設内型枠5a(次工程では最前部の既設型枠となる)の打設ポート13からコンクリートが打設される。なお、図3において、符合17,18は妻枠8の内外周に配置されたパッキンを示し、妻枠8はこれらパッキン17,18を介して内型枠5及びテール部6に対して摺動する。   At the start of the propulsion of the shield machine 1, the end frame 8 is positioned immediately before the placement port 13 of the foremost existing inner form 5b adjacent to the new inner form 5a. At the same time as the shield machine 1 is propelled, concrete placement is started from the placement opening 13 of the existing inner mold 5b at the forefront. This concrete placement is performed simultaneously in the circumferential direction, that is, from the placement ports C1, R2, R3, L2, and L3. When the shield machine 1 is propelled by one ring length of the inner mold 5 and stopped, the wife frame 8 is positioned immediately before the placing port 13 of the new inner mold 5a. At the time of propulsion in the next process, concrete is cast from the casting port 13 of this newly installed inner form 5a (which will be the existing mold at the foremost part in the next process). In FIG. 3, reference numerals 17 and 18 denote packings arranged on the inner and outer peripheries of the end frame 8, and the end frame 8 slides with respect to the inner mold frame 5 and the tail portion 6 through the packings 17 and 18. To do.

図5は別の実施形態を示している。この実施形態は、打設口が設けられる内型枠5の分割ピースに長さ方向に沿って複数(2個)の打設口13を設けた例である。その結果として、内型枠5の周方向に沿う複数のコンクリート打設口13は、トンネル軸方向に関して前後に2列設けられていることになる。この実施形態の場合、シールド機1の推進開始時に既設型枠5bの前部打設口13からコンクリートの打設が開始され、シールド機1の推進途中で既設型枠5bの前部打設口13から新設型枠5aの後部打設口13に打設位置が切り換えられる。   FIG. 5 shows another embodiment. This embodiment is an example in which a plurality of (two) placement ports 13 are provided along the length direction of the divided piece of the inner mold 5 where the placement ports are provided. As a result, the plurality of concrete placement ports 13 along the circumferential direction of the inner mold 5 are provided in two rows in the front-rear direction in the tunnel axis direction. In the case of this embodiment, the concrete placement starts from the front placement opening 13 of the existing mold 5b when the shield machine 1 starts propulsion, and the front placement opening of the existing mold 5b during the promotion of the shield machine 1 The placement position is switched from 13 to the rear placement opening 13 of the new formwork 5a.

フレッシュコンクリートは、打設後時間経過とともに流動性が低下するので、コンクリートは妻枠8に近い位置で打設することが好ましい。上記実施形態のように、シールド機の推進途中で、すなわち妻枠8の移動途中で打設位置を替えることにより、該妻枠に近い位置でコンクリートを打設することができ、品質の良いライニングを得ることができる。   Since the flowability of fresh concrete decreases with the passage of time after placing, it is preferable that the concrete be placed at a position close to the end frame 8. As in the above embodiment, the concrete can be placed at a position close to the wife frame by changing the placement position during the propulsion of the shield machine, that is, while the wife frame 8 is moving. Can be obtained.

以上のように、この発明によれば、内型枠に設けた打設口からライニングコンクリートを打設するようにしたので、妻枠から打設する場合の問題を一挙に解決することができる。すなわち、妻枠にコンクリートが付着することがなく、コンクリート打設トラブルの発生を抑えることができ、ライニングコンクリートの品質向上、施工速度の向上、施工コストの縮減を図ることができる。   As described above, according to the present invention, since the lining concrete is placed from the placement opening provided in the inner mold, the problems in the case of placing from the wife frame can be solved all at once. That is, the concrete does not adhere to the end frame, the occurrence of a concrete placing trouble can be suppressed, the quality of the lining concrete can be improved, the construction speed can be improved, and the construction cost can be reduced.

この発明による工法の施工手順を示す断面図である。It is sectional drawing which shows the construction procedure of the construction method by this invention. 図1に引き続く施工手順を示す断面図である。It is sectional drawing which shows the construction procedure following FIG. ライニングコンクリートの打設状態を示す断面図である。It is sectional drawing which shows the placement state of lining concrete. 打設ポートを示す模式図である。It is a schematic diagram which shows a placement port. 内型枠の別の実施形態を示す断面図である。It is sectional drawing which shows another embodiment of an inner formwork.

符号の説明Explanation of symbols

1 シールド機
2 本体胴部
5 内型枠
5a 新設内型枠
5b 既設内型枠
6 テール部
7 推進ジャッキ
8 妻枠
9 妻枠ジャッキ
10 圧力調整装置
13 打設口
14 圧送管
15 二方切換弁
16a,16b 分岐管
DESCRIPTION OF SYMBOLS 1 Shield machine 2 Main body trunk | body 5 Inner formwork 5a New internal formwork 5b Existing internal formwork 6 Tail part 7 Propulsion jack 8 Wife frame 9 Wife frame jack 10 Pressure adjusting device 13 Placing port 14 Pressure feed pipe 15 Two-way switching valve 16a, 16b Branch pipe

Claims (4)

シールド機のテール部の内方で、該テール部の内周に設けられた妻枠が摺接可能なように、既設内型枠と連続する新設内型枠をリング状に組み立て、前記内型枠から反力をとってシールド機を推進させながら、同時に前記妻枠後方における前記内型枠と地山との間にコンクリートを打設し、打設コンクリートを前記妻枠によって所定圧力で常時加圧する直打ちコンクリートライニングによるシールド工法において、
前記内型枠にトンネル周方向に沿った複数のコンクリート打設口を設け、この打設口からコンクリートを打設することを特徴とする直打ちコンクリートライニングによるシールド工法。
Assemble the new internal formwork continuous with the existing internal formwork into a ring shape so that the wife frame provided on the inner periphery of the tail part can be slidably contacted inside the tail part of the shield machine. While pushing the reaction machine from the frame and propelling the shield machine, at the same time, the concrete is placed between the inner mold frame and the ground at the rear of the wife frame, and the cast concrete is constantly applied at a predetermined pressure by the wife frame. In the shield construction method by direct hitting concrete lining,
A shield construction method by direct casting concrete lining, wherein a plurality of concrete placement openings are provided in the inner mold frame along the circumferential direction of the tunnel, and concrete is placed through the placement openings.
前記シールド機は前記内型枠の1リング長さごとに推進し、その1リング長さの推進開始と同時に、前記新設内型枠に隣接している最前部の前記既設内型枠の前記打設口からコンクリートを打設することを特徴とする請求項1記載の直打ちコンクリートライニングによるシールド工法。   The shield machine is propelled for each ring length of the inner mold, and at the same time as the propulsion of the one ring length is started, the hitting of the existing inner mold at the frontmost part adjacent to the new inner mold is performed. 2. The shield construction method by direct-casting concrete lining according to claim 1, wherein concrete is cast from the opening. 前記複数のコンクリート打設口から同時にコンクリートを打設することを特徴とする請求項1又は2記載の直打ちコンクリートライニングによるシールド工法。   3. The shield construction method by direct-casting concrete lining according to claim 1, wherein concrete is cast from the plurality of concrete placing ports simultaneously. 前記複数のコンクリート打設口は、1つのリング状内型枠に関してトンネル軸方向に複数列設けられていることを特徴とする請求項1,2又は3記載の直打ちコンクリートライニングによるシールド工法。   The shield method according to claim 1, 2, or 3, wherein the plurality of concrete placement ports are provided in a plurality of rows in the tunnel axis direction with respect to one ring-shaped inner formwork.
JP2007323207A 2007-12-14 2007-12-14 Shield method by direct placing concrete lining Pending JP2009144425A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007323207A JP2009144425A (en) 2007-12-14 2007-12-14 Shield method by direct placing concrete lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007323207A JP2009144425A (en) 2007-12-14 2007-12-14 Shield method by direct placing concrete lining

Publications (1)

Publication Number Publication Date
JP2009144425A true JP2009144425A (en) 2009-07-02

Family

ID=40915347

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007323207A Pending JP2009144425A (en) 2007-12-14 2007-12-14 Shield method by direct placing concrete lining

Country Status (1)

Country Link
JP (1) JP2009144425A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895587A (en) * 2015-05-28 2015-09-09 广西建工集团第五建筑工程有限责任公司 Construction method for pressure pouring of concrete for tunnel secondary lining
CN108442688A (en) * 2018-05-25 2018-08-24 郭新元 One kind pouring mold
JP2018135662A (en) * 2017-02-21 2018-08-30 日本シビックコンサルタント株式会社 Method of holding back-filling material and back-filling injection system used for the same

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5284825A (en) * 1976-01-07 1977-07-14 Obayashi Gumi Kk Method of tunnel upset work in method of shield construction
JPS63181892A (en) * 1987-01-21 1988-07-27 清水建設株式会社 Cast-in-place lining method using mesh reinforcing in method of non-segment-shield construction
JPS63181894A (en) * 1987-01-22 1988-07-27 三井建設株式会社 Shield excavator
JPS63268900A (en) * 1987-04-28 1988-11-07 株式会社小松製作所 Shield for method of cast-in-place lining construction
JPS63300200A (en) * 1987-05-30 1988-12-07 前田建設工業株式会社 Method of cast-in-place lining shielding construction
JPH0333398A (en) * 1989-06-27 1991-02-13 Okumura Corp Lining work for tunnel
JPH09151698A (en) * 1995-09-29 1997-06-10 Shimizu Corp Shield construction method
JPH10325299A (en) * 1997-03-26 1998-12-08 Shimizu Corp Shield excavation machine and tunnel-lining method by using the same

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5284825A (en) * 1976-01-07 1977-07-14 Obayashi Gumi Kk Method of tunnel upset work in method of shield construction
JPS63181892A (en) * 1987-01-21 1988-07-27 清水建設株式会社 Cast-in-place lining method using mesh reinforcing in method of non-segment-shield construction
JPS63181894A (en) * 1987-01-22 1988-07-27 三井建設株式会社 Shield excavator
JPS63268900A (en) * 1987-04-28 1988-11-07 株式会社小松製作所 Shield for method of cast-in-place lining construction
JPS63300200A (en) * 1987-05-30 1988-12-07 前田建設工業株式会社 Method of cast-in-place lining shielding construction
JPH0333398A (en) * 1989-06-27 1991-02-13 Okumura Corp Lining work for tunnel
JPH09151698A (en) * 1995-09-29 1997-06-10 Shimizu Corp Shield construction method
JPH10325299A (en) * 1997-03-26 1998-12-08 Shimizu Corp Shield excavation machine and tunnel-lining method by using the same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895587A (en) * 2015-05-28 2015-09-09 广西建工集团第五建筑工程有限责任公司 Construction method for pressure pouring of concrete for tunnel secondary lining
JP2018135662A (en) * 2017-02-21 2018-08-30 日本シビックコンサルタント株式会社 Method of holding back-filling material and back-filling injection system used for the same
CN108442688A (en) * 2018-05-25 2018-08-24 郭新元 One kind pouring mold

Similar Documents

Publication Publication Date Title
JP5653048B2 (en) Steel pipe for ground reinforcement and method for manufacturing steel pipe for ground reinforcement
JP2009144425A (en) Shield method by direct placing concrete lining
JP5479989B2 (en) Tunnel construction method and shield machine
JP4668667B2 (en) Concrete placing apparatus and tunnel excavator equipped with the apparatus
JP5291024B2 (en) Direct cast concrete method
JP5693123B2 (en) Stop valve device and tunnel excavator equipped with the device
JP2012077504A (en) Tunnel boring machine
JP4203918B2 (en) Triple tube tunnel backfill device
JP5292246B2 (en) Tunnel excavator with switching lining
JP5725691B2 (en) Inner formwork and tunnel excavator provided with the inner formwork
JPH10184278A (en) Bit exchanging method of cutter for shield machine and shield machine
JP4081037B2 (en) Propulsion and shield combination method
JPH04258495A (en) Lining work of shield tunnel
JP3706514B2 (en) Wife formwork device for tunnel excavator
JPH11280379A (en) Inside pushing pipe for pipe jacking method
JP2004068377A (en) Tunnel boring machine and tunnel construction method
JP4970331B2 (en) Formwork piece installation method and formwork piece used in this method
JP3108735B2 (en) Reconstruction method of large diameter sewer
JPH0978981A (en) Tunnel outside lining method
JP3821658B2 (en) Shield device for backfilling pipes
JPH08218788A (en) Cutter-provided segment and horizontal tunnel-excavation method using the segment
JP2001073673A (en) Laying of new conduit and conduit reducing shielding machine therefor
JPH10110600A (en) Back filling excavator and back filling construction method using it
JPH1088970A (en) Semi-shield machine and semi-shield construction method
JP2003328695A (en) Segment and tunnel constructing method using the same

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20101130

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120125

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120306

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120502

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120807

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20121220