JPH10325299A - Shield excavation machine and tunnel-lining method by using the same - Google Patents
Shield excavation machine and tunnel-lining method by using the sameInfo
- Publication number
- JPH10325299A JPH10325299A JP9332138A JP33213897A JPH10325299A JP H10325299 A JPH10325299 A JP H10325299A JP 9332138 A JP9332138 A JP 9332138A JP 33213897 A JP33213897 A JP 33213897A JP H10325299 A JPH10325299 A JP H10325299A
- Authority
- JP
- Japan
- Prior art keywords
- self
- hardening filler
- shield excavator
- skin plate
- hardening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、コンクリートやモ
ルタル等の自硬性充填材を採用するシールドトンネル
を、構築するために用いられるシールド掘削機およびそ
れを用いたトンネル覆工方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a shield excavator used for constructing a shield tunnel employing a self-hardening filler such as concrete or mortar, and a tunnel lining method using the same.
【0002】[0002]
【従来の技術】周知のように、例えば軟弱で地下水位が
高いような地盤に対してシールド工法によりトンネルを
施工する場合、一次覆工にはセグメントを使用すること
が一般的であるが、セグメントを用いることに代えて、
シールド機の後方において型枠を組み立ててその型枠と
地山との間に直接的に自硬性硬化材としてコンクリート
を打設充填して覆工壁を形成するというような、いわゆ
るECL工法(ExtrudedConcrete Lining Method)の開
発も進められている。2. Description of the Related Art As is well known, for example, when a tunnel is constructed by a shield method on a soft ground having a high groundwater level, a segment is generally used for a primary lining. Instead of using
The so-called ECL method (Extruded Concrete method) in which a formwork is assembled behind a shield machine and concrete is poured and filled as a hardening material directly between the formwork and the ground to form a lining wall. Lining Method) is also under development.
【0003】ECL工法では、打設されたコンクリート
が硬化して覆工壁が形成された後は地山圧力(土圧およ
び地下水圧)に対して十分に耐え得ることは当然である
が、コンクリートを打設した直後の未硬化コンクリート
によっても地山圧力に対して抗し得るものでなければな
らず、特に地下水圧が高い地山に対してECL工法を適
用する場合には未硬化コンクリートによる十分な止水性
を確保するための方策が不可欠である。このため、本出
願人は先に、コンクリートの打設圧力を地山圧力より常
に高く維持することによって未硬化のコンクリートによ
っても止水性を確保するようにしたECL工法における
シールドトンネルの覆工方法を提供した(特開平4ー1
61599号)。In the ECL method, after the poured concrete is hardened and the lining wall is formed, it is natural that the concrete can sufficiently withstand the ground pressure (earth pressure and groundwater pressure). The uncured concrete must be able to withstand the ground pressure even with the uncured concrete immediately after casting. Especially when applying the ECL method to the ground with high groundwater pressure, sufficient It is essential to take measures to ensure an adequate water stoppage. For this reason, the applicant of the present invention has previously described a method of lining a shield tunnel in the ECL method in which the casting pressure of concrete is always kept higher than the ground pressure so as to secure water stoppage even with uncured concrete. Provided (Japanese Unexamined Patent Publication No.
No. 61599).
【0004】図33および図34はその覆工方法を実施
する際に用いるシールド掘削機Sを示すものである。こ
れは、スキンプレート1の先端部に設けたカッター装置
2により地山Jを掘削するとともに、スキンプレート1
の後方側に鉄筋3を配筋してはそれを覆うように型枠4
を組み立て、その型枠4から反力をとって推進ジャッキ
5により掘進しながら型枠4と地山Jとの間にコンクリ
ートを打設充填することによりトンネル覆工壁Wを形成
するようにしたものである。型枠4の最前部には妻型枠
6が取り付けられるが、その妻型枠6はコンクリート中
に埋設されていく主妻枠6aと型枠4に対して出没する
補助妻枠6bとが組み合わされることによりシールド掘
削機Sの蛇行に追随できるものとされている。符号7は
コンクリートポンプ、8は型枠4に接続されるコンクリ
ート打設管、9はそれらの接続部に設けられているシャ
ッタである。FIG. 33 and FIG. 34 show a shield excavator S used for carrying out the lining method. This is because the ground J is excavated by the cutter device 2 provided at the tip of the skin plate 1 and the skin plate 1 is excavated.
Reinforcing the reinforcing bar 3 on the rear side of the
The tunnel lining wall W is formed by casting concrete between the form 4 and the ground J while excavating with the propulsion jack 5 by taking a reaction force from the form 4 and digging with the propulsion jack 5. Things. A wife formwork 6 is attached to the foremost part of the formwork 4. The wife formwork 6 is composed of a main wife frame 6a buried in concrete and an auxiliary wife frame 6b that appears and disappears from the formwork 4. By this, it is possible to follow the meandering of the shield excavator S. Reference numeral 7 denotes a concrete pump, 8 denotes a concrete casting pipe connected to the formwork 4, and 9 denotes a shutter provided at a connection portion between them.
【0005】また、このシールド掘削機Sにおいては、
図33、図34に示すようにスキンプレート1のテール
部の内側に内筒10を配するとともにそれらの間を径方
向に分割して複数の弓形のコンクリートピストン室11
を設け、それらコンクリートピストン室11内に押出し
ピストン12をシールド掘削機Sの軸線方向にスライド
可能に配置するとともに、その押出しピストン12を駆
動するための圧力保持ジャッキ13を備え、かつ、各押
出しピストン12に打設孔14を設けてそこにコンクリ
ート打設管15を接続することによりコンクリートピス
トン室11内にも打設孔14を通してコンクリートを打
設するように構成している。そして、押出しピストン1
2を通してコンクリートを打設しながら、圧力保持ジャ
ッキ13により押出しピストン12を押出すことによっ
て打設したコンクリートを押圧することにより、打設さ
れたコンクリート圧力Poを地山圧力Pjより高く保持す
るようにしている。[0005] In this shield excavator S,
As shown in FIGS. 33 and 34, the inner cylinder 10 is arranged inside the tail portion of the skin plate 1 and the space between them is divided in the radial direction to form a plurality of arc-shaped concrete piston chambers 11.
Are provided so as to be slidable in the axial direction of the shield excavator S in the concrete piston chambers 11, and are provided with pressure holding jacks 13 for driving the extruding pistons 12; A casting hole 14 is provided in 12, and a concrete casting pipe 15 is connected to the casting hole 14 so that concrete is cast into the concrete piston chamber 11 through the casting hole 14. And the pushing piston 1
2 while the concrete is being poured, the pressed concrete is pushed by pushing out the extruding piston 12 with the pressure holding jack 13 so that the poured concrete pressure Po is kept higher than the ground pressure Pj. ing.
【0006】上記のシールド掘削機Sによるコンクリー
ト打設手順を図35〜図37を参照してさらに詳細に説
明する。図35はコンクリート打設が完了した部分の前
方に新たに鉄筋3および型枠4を組み立てた状態を示す
ものである。この状態では上記のように押出しピストン
12が打設コンクリートを押圧していることによりコン
クリート圧力Poが地山圧力Pjより高く保持されてお
り、したがって地下水が浸入してくることが防止されて
いる。The concrete placing procedure by the shield excavator S will be described in more detail with reference to FIGS. FIG. 35 shows a state where the reinforcing bar 3 and the formwork 4 are newly assembled in front of the portion where the concrete casting has been completed. In this state, since the extrusion piston 12 presses the poured concrete as described above, the concrete pressure Po is maintained higher than the ground pressure Pj, and therefore, the penetration of groundwater is prevented.
【0007】次に、図35の状態から図36に示すよう
に打設管8を通じて最前部の型枠4内にコンクリートを
打設し、その内部でのコンクリート圧力Prが先行打設
されているコンクリート圧力Poと同等あるいはやや高
くなった時点で打設管8のシャッタ9を閉じ、先行の補
助妻枠6bを引き下げて後行打設部分を先行打設部分と
を連通させる。これにより両者の打設コンクリートが一
体化するとともにそれら全体のコンクリート圧力Poが
地山圧力Pjより高いままに保持される。Next, as shown in FIG. 36, concrete is poured from the state shown in FIG. 35 through the casting pipe 8 into the foremost formwork 4, and the concrete pressure Pr inside the concrete is pre-poured. When the pressure becomes equal to or slightly higher than the concrete pressure Po, the shutter 9 of the casting tube 8 is closed, and the preceding auxiliary wive frame 6b is lowered to allow the succeeding casting portion to communicate with the preceding casting portion. As a result, both the cast concretes are integrated, and the concrete pressure Po of the whole is kept higher than the ground pressure Pj.
【0008】続いて、図37に示すように、押出しピス
トン12に設けた打設孔14を通してコンクリートピス
トン室11にコンクリートを打設する。この際、押出し
ピストン12は圧力保持ジャッキ13(図33、図34
参照)により常に後方(図示右方)へ押圧されながらも
コンクリートの打設圧力に打ち負けて漸次前進(図示左
方へ移動)していき、これによりコンクリート圧力Po
が保持される。その後、推進ジャッキ5を作動させてシ
ールド掘削機Sを掘進させた後、推進ジャッキ5を引戻
して新たな鉄筋3の配筋と型枠4の組み立てを行ない、
以上の手順を繰り返して掘進を行なう。Subsequently, as shown in FIG. 37, concrete is poured into the concrete piston chamber 11 through a driving hole 14 formed in the extrusion piston 12. At this time, the pushing piston 12 is connected to the pressure holding jack 13 (FIGS. 33 and 34).
), While being constantly pushed backward (to the right in the figure), gradually defeating the concrete placement pressure (moving to the left in the figure), thereby increasing the concrete pressure Po.
Is held. After that, the propulsion jack 5 is operated to excavate the shield excavator S, and then the propulsion jack 5 is pulled back to re-arrange the reinforcing bars 3 and to form the formwork 4.
Excavation is performed by repeating the above procedure.
【0009】[0009]
【発明が解決しようとする課題】上記工法においては、
圧力保持ジャッキ13および押出しピストン12によっ
て打設コンクリートを押圧することによってコンクリー
ト圧力Poを地山圧力Pjより常に高く保持することによ
り、軟弱で地下水位の高い地山Jであってもコンクリー
ト打設途中における地下水の浸入を防止でき、したがっ
てそのような地山Jに対してもECL工法の採用が可能
となったのであるが、上記の工法および上記工法に用い
られるシールド掘削機Sは、以下の点で改良の余地を残
している。In the above method,
The concrete pressure Po is always kept higher than the ground pressure Pj by pressing the poured concrete by the pressure holding jack 13 and the extruding piston 12, so that even the ground J which is soft and has a high groundwater level is in the middle of the concrete casting. The groundwater infiltration can be prevented, and thus the ECL method can be applied to such ground J. However, the above method and the shield excavator S used in the method are as follows. Leaves room for improvement.
【0010】まず、上記工法およびシールド掘削機Sに
おいては、圧力保持ジャッキ13を用いてコンクリート
を加圧する場合や、シールド掘削機Sを掘進させる場合
には、押し出しピストン12が前後に変位することとな
るが、このとき、押し出しピストン12に設けられた打
設孔14に対して取り付けられたコンクリート打設管1
5も同時に変位することから、あらかじめ、シールド掘
削機Sの内部において、コンクリート打設管15が移動
する部分の空間を開けておく必要があった。First, in the construction method and the shield excavator S, when the concrete is pressurized by using the pressure holding jack 13 or when the shield excavator S is excavated, the pushing piston 12 is displaced back and forth. However, at this time, the concrete casting pipe 1 attached to the casting hole 14 provided in the extrusion piston 12
Since 5 is also displaced at the same time, it is necessary to previously open a space in the shield excavator S where the concrete casting pipe 15 moves.
【0011】また、コンクリート打設管15は、押し出
しピストン12の変位に追随できるように、柔軟性をも
ったホースなどによって構成する必要があり、このよう
にした場合には、コンクリート打設管15が固定でき
ず、ホースが振れたりするなどの不安定な状態が生じ易
くなっていた。Further, the concrete casting pipe 15 needs to be constituted by a flexible hose or the like so as to be able to follow the displacement of the pushing piston 12, and in such a case, the concrete casting pipe 15 is required. Could not be fixed, and an unstable state such as a hose swinging was likely to occur.
【0012】さらには、このようにコンクリート打設管
15がホースによって構成されるため、場合によって
は、コンクリート打設管15の配管が複雑になり、その
内部にコンクリートのつまりなどの不具合が生じ易くな
っていた。Further, since the concrete casting pipe 15 is constituted by a hose as described above, the piping of the concrete casting pipe 15 may be complicated in some cases, and defects such as clogging of the concrete are likely to occur therein. Had become.
【0013】それだけでなく、上記のシールド掘削機S
においては、打設孔14が押し出しピストン12におけ
る断面欠損となり、構造的な弱点となっていた。また、
この弱点を補うために、押し出しピストン12の幅を大
きくして、加圧にも耐える構造とした場合には、シール
ドトンネルのコンクリート覆工の厚さ寸法が大きくな
り、これにより、シールド掘削機Sが大型化し、施工に
際してのコストが嵩むものとなってしまう。In addition, the shield excavator S
In, the driving hole 14 became a cross-sectional defect in the push-out piston 12 and was a structural weak point. Also,
If the width of the push-out piston 12 is increased to compensate for this weak point and the structure is resistant to pressurization, the thickness dimension of the concrete lining of the shield tunnel becomes large, whereby the shield excavator S Is increased in size and the cost for construction is increased.
【0014】本発明は、上記事情に鑑み行われたもので
あり、その目的は、押し出しピストンを構造的に強度な
ものとすることにより、ECL工法によりシールドトン
ネルを構築するにあたって、コンクリート覆工の厚さ寸
法を縮小することができ、これにより、トンネルの建設
コストの低減を図るようなシールド掘削機を提供するこ
とにある。また、別の目的は、自硬性充填材打設管をシ
ールド掘削機側に固定することにより、従来に比べてよ
り信頼性に優れたシールド掘削機およびそれを用いたト
ンネル覆工方法を提供することにある。The present invention has been made in view of the above circumstances, and an object of the present invention is to construct a shield tunnel by an ECL method by making an extrusion piston structurally strong. It is an object of the present invention to provide a shield excavator capable of reducing a thickness dimension, thereby reducing a tunnel construction cost. Another object of the present invention is to provide a shield excavator having higher reliability than before and a tunnel lining method using the same by fixing the self-hardening filler casting pipe to the shield excavator side. It is in.
【0015】[0015]
【課題を解決するための手段】本発明においては、上記
課題を解決するために以下の手段を採用した。すなわ
ち、請求項1記載のシールド掘削機は、先端のカッター
により地盤を掘削しつつ掘削された地盤の周壁を所定の
間隔を空けて型枠により覆い、該型枠と前記周壁との間
に自硬性充填材を打設し、前記周壁の内面を覆工するた
めのシールド掘削機であって、該シールド掘削機のスキ
ンプレートの内周面側には、自硬性充填材充填空間部
が、前記周壁と前記型枠との間の空間に対向するよう形
成され、該自硬性充填材充填空間部は、自硬性充填材注
入部とピストン室とを前記スキンプレートの周方向に互
いに隔てられて備えた構成とされ、該ピストン室の内部
には、前後両方向にスライド自在とされるとともに、前
記スキンプレート側に固定された圧力保持ジャッキによ
って駆動される押し出しピストンが配置され、該自硬性
充填材注入部の内部には、自硬性充填材注入管が配置さ
れることを特徴とする。In the present invention, the following means are employed in order to solve the above-mentioned problems. That is, the shield excavator according to claim 1 covers the peripheral wall of the excavated ground with a form at a predetermined interval while excavating the ground with a cutter at the tip, and automatically mounts the space between the form and the peripheral wall. A shield excavator for casting a hard filler and lining the inner surface of the peripheral wall, wherein a self-hardening filler filling space portion is provided on an inner peripheral surface side of a skin plate of the shield excavator. The self-hardening filler filling space portion is formed so as to face a space between the peripheral wall and the mold, and includes a self-hardening filler injecting portion and a piston chamber separated from each other in a circumferential direction of the skin plate. Inside the piston chamber, an extruding piston slidable in both front and rear directions and driven by a pressure holding jack fixed to the skin plate side is disposed, and the self-hardening filler is injected. Department Inside, characterized in that the self-hardening filling material injection tube is arranged.
【0016】また、請求項2記載のシールド掘削機は、
前記自硬性充填材充填空間部が、前記スキンプレートと
該スキンプレートのテール部の内側に配置された内筒と
の間に形成されるとともに、前記自硬性充填材注入部と
前記ピストン室とが、前記スキンプレートおよび前記内
筒を連結する複数の隔壁によって前記スキンプレートの
周方向に隔てられてなることを特徴としている。The shield excavator according to claim 2 is
The self-hardening filler filling space is formed between the skin plate and an inner cylinder arranged inside a tail part of the skin plate, and the self-hardening filler injection part and the piston chamber are formed between the skin plate and the piston chamber. The skin plate and the inner cylinder are separated from each other in a circumferential direction of the skin plate by a plurality of partition walls.
【0017】また、請求項3記載のシールド掘削機は、
前記ピストン室の内壁面を形成するシリンダ部材が前記
スキンプレートの内周面に一体に固定されることによっ
て前記ピストン室が形成され、互いに隣り合う前記ピス
トン室の間の空間が、前記自硬性充填材注入部とされて
いることを特徴としている。The shield excavator according to claim 3 is
The piston chamber is formed by integrally fixing a cylinder member forming an inner wall surface of the piston chamber to an inner peripheral surface of the skin plate, and a space between the piston chambers adjacent to each other is filled with the self-hardening filler. It is characterized by being a material injection part.
【0018】このようなシールド掘削機においては、自
硬性充填材充填空間部が、自硬性充填材注入部とピスト
ン室とに分割されており、周壁と型枠との間に自硬性充
填材を注入する作業は、自硬性充填材注入部において行
われ、注入した自硬性充填材の圧力を地山圧力よりも高
く保持する作業は、ピストン室において行われることと
なる。したがって、ピストン室内部に設けた押し出しピ
ストンに自硬性充填材打設用の孔を形成する必要がなく
なる。In such a shield excavator, the self-hardening filler filling space is divided into the self-hardening filler injection part and the piston chamber, and the self-hardening filler is filled between the peripheral wall and the formwork. The operation of injecting is performed in the self-hardening filler injecting section, and the operation of maintaining the pressure of the injected self-hardening filler higher than the ground pressure is performed in the piston chamber. Therefore, it is not necessary to form a hole for driving the self-hardening filler in the extrusion piston provided inside the piston chamber.
【0019】請求項4記載のシールド掘削機は、前記自
硬性充填材注入管は、前記スキンプレートに対して固定
されていることを特徴とする。According to a fourth aspect of the present invention, in the shield excavator, the self-hardening filler injection pipe is fixed to the skin plate.
【0020】このシールド掘削機は、上記のような構成
とされているため、自硬性充填材注入管が、押し出しピ
ストンの前後変位に従って動くことがない。Since the shield excavator is configured as described above, the self-hardening filler injection tube does not move in accordance with the longitudinal displacement of the pushing piston.
【0021】請求項5記載のシールド掘削機を用いたト
ンネル覆工方法は、シールド掘削機の先端のカッターに
より地盤を掘削しつつ掘削された地盤の周壁を所定の間
隔を空けて型枠により覆い、該型枠と前記周壁との間に
自硬性充填材を打設し、前記周壁の内面を覆工するシー
ルド掘削機を用いたトンネル覆工方法であって、該シー
ルド掘削機として、スキンプレートの内周面側に、前記
周壁と前記型枠との間の空間に対向するよう自硬性充填
材充填空間部を形成し、該自硬性充填材充填空間部に、
自硬性充填材注入部とピストン室とを形成するととも
に、該ピストン室の内部に、前後両方向にスライド自在
とされる押し出しピストンを配置したものを用い、前記
自硬性充填材注入部の内部に、自硬性充填材注入管を配
置するとともに、該自硬性充填材注入管を前記スキンプ
レート側に固定しておき、トンネルを掘進するに際し、
前記押し出しピストンを後方に移動させて、前記周壁と
前記型枠との間の空間に対して前記自硬性充填材注入管
から注入充填された自硬性充填材を加圧しつつ、前記自
硬性充填材注入管と前記スキンプレートとを一体的に前
進させることを特徴とする。According to a fifth aspect of the present invention, in a tunnel lining method using a shield excavator, a peripheral wall of the excavated ground is covered with a formwork at a predetermined interval while excavating the ground with a cutter at the tip of the shield excavator. A tunnel lining method using a shield excavator for casting a self-hardening filler between the formwork and the peripheral wall and lining the inner surface of the peripheral wall, wherein a skin plate is used as the shield excavator. On the inner peripheral surface side, a self-hardening filler filling space portion is formed so as to face a space between the peripheral wall and the formwork, and in the self-hardening filler filling space portion,
Forming a self-hardening filler injection part and a piston chamber, and using an extrusion piston that is slidable in both front and rear directions inside the piston chamber, inside the self-hardening filler injection part, While arranging a self-hardening filler injection pipe, the self-hardening filler injection pipe is fixed to the skin plate side, and when digging a tunnel,
Moving the extrusion piston backward to press the self-hardening filler injected and filled from the self-hardening filler injection tube into the space between the peripheral wall and the formwork, The injection tube and the skin plate are integrally advanced.
【0022】このシールド掘削機を用いたトンネル覆工
方法によれば、シールド掘削機が前方に掘進する際にお
いて、自硬性充填材注入管がシールド掘削機の中を動く
ことがない。According to the tunnel lining method using the shield excavator, when the shield excavator digs forward, the self-hardening filler injection pipe does not move in the shield excavator.
【0023】[0023]
【発明の実施の形態】以下、本発明に係るシールド掘削
機およびそれを用いたトンネル覆工方法の第一および第
二の実施の形態について、図1ないし図30を参照して
説明する。DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, first and second embodiments of a shield excavator and a tunnel lining method using the same according to the present invention will be described with reference to FIGS.
【0024】[第一の実施の形態]図1は、本発明にお
けるシールド掘削機Spの主要部分を示す図である。こ
のシールド掘削機Spは、基本的に、上述した従来のシ
ールド掘削機Sと同様の構成とされており、これら両者
に共通する構成については同一符号を付すこととする。[First Embodiment] FIG. 1 is a diagram showing a main part of a shield excavator Sp in the present invention. This shield excavator Sp has basically the same configuration as the above-mentioned conventional shield excavator S, and the same reference numerals are given to the components common to both.
【0025】すなわち、図1において、符号1は、地山
JにおいてトンネルTを掘削するためのシールド掘削機
Spのスキンプレートを示しており、2は、スキンプレ
ート1の先端部に設けられて地山Jを掘削するためのカ
ッター装置を、3は、スキンプレート1の後方側に配置
された鉄筋を示している。また4は、鉄筋3をトンネル
Tの内部側から覆うように組み立てられた型枠であり、
型枠4とトンネルTの周壁Twとの間に、コンクリート
やモルタル等の自硬性充填材を打設充填することによ
り、トンネル覆工壁Wが形成される。That is, in FIG. 1, reference numeral 1 denotes a skin plate of a shield excavator Sp for excavating a tunnel T at a ground mountain J, and reference numeral 2 denotes a ground plate provided at the tip of the skin plate 1. A cutter device 3 for excavating the mountain J indicates a reinforcing bar disposed on the rear side of the skin plate 1. Reference numeral 4 denotes a formwork assembled so as to cover the reinforcing bar 3 from the inside of the tunnel T,
The tunnel lining wall W is formed by casting and filling a self-hardening filler such as concrete or mortar between the formwork 4 and the peripheral wall Tw of the tunnel T.
【0026】また、符号5は、推進ジャッキであり、型
枠4から反力を取って、シールド掘削機Spを前進させ
る役割を果たすものである。また、符号6は、型枠4の
最前部に取り付けられた妻型枠であり、妻型枠6は、主
妻枠6aと補助妻枠6bとから構成されたものである。
さらに、符号7は自硬性充填材ポンプを、8は型枠4に
トンネルTの内部側から接続される自硬性充填材打設管
を、9は型枠4と自硬性充填材打設管8との接続部に設
けられているシャッタを示している。Reference numeral 5 denotes a propulsion jack, which plays a role of taking a reaction force from the formwork 4 and moving the shield excavator Sp forward. Reference numeral 6 denotes a wife formwork attached to the forefront of the formwork 4, and the wife formwork 6 is composed of a main wife frame 6a and an auxiliary wife frame 6b.
Further, reference numeral 7 denotes a self-hardening filler pump, 8 denotes a self-hardening filler casting pipe connected to the mold 4 from the inside of the tunnel T, and 9 denotes a mold 4 and a self-hardening filler casting pipe 8. 5 shows a shutter provided at a connection portion between the first and second shutters.
【0027】このシールド掘削機Spが先に示した従来
のシールド掘削機Sと最も異なる点は、スキンプレート
1と、そのテール部の内側に配置された内筒10との間
の空間が、型枠4と周壁Twとの間の空間に対して連通
状態に形成された自硬性充填材充填空間部21とされる
ととともに、自硬性充填材充填空間部21が、自硬性充
填材注入部23と、ピストン室24とに分割されている
点である。さらに、シールド掘削機Spにおいては、上
述の従来のシールド掘削機Sとは異なり、自硬性充填材
注入部23に、自硬性充填材注入管26が、ピストン室
24に、押し出しピストン27が、それぞれ別個に配置
された構成とされている。また、押し出しピストン27
は、ピストン室24内部において前後両方向にスライド
自在とされるとともに、スキンプレート1側に固定され
た圧力保持ジャッキ28によって駆動される構成とされ
ている。The most different point of the shield excavator Sp from the conventional shield excavator S described above is that the space between the skin plate 1 and the inner cylinder 10 disposed inside the tail portion thereof is a mold. The self-hardening filler filling space 21 is formed to be in communication with the space between the frame 4 and the peripheral wall Tw, and the self-hardening filler filling space 21 becomes a self-hardening filler injecting part 23. And the piston chamber 24. Further, in the shield excavator Sp, unlike the above-mentioned conventional shield excavator S, a self-hardening filler injection pipe 26, a self-hardening filler injection pipe 26, a piston chamber 24, and an extrusion piston 27 are respectively provided in the self-hardening filler injection part 23. It is configured to be arranged separately. In addition, the pushing piston 27
Is slidable in both front and rear directions inside the piston chamber 24, and is driven by a pressure holding jack 28 fixed to the skin plate 1 side.
【0028】図1に示したシールド掘削機SpのI−I
断面を示したのが図2である。図中に示すように、自硬
性充填材充填空間部21は、スキンプレート1と内筒1
0とを連結する隔壁30によって、その周方向に分割さ
れており、このうちの一部が自硬性充填材注入部23と
され、また別の一部がピストン室24とされている。I-I of the shield excavator Sp shown in FIG.
FIG. 2 shows a cross section. As shown in the figure, the self-hardening filler-filled space 21 is formed by the skin plate 1 and the inner cylinder 1.
0 is divided in the circumferential direction by a partition wall 30 which connects to a part 0, and a part of the part is a self-hardening filler injection part 23 and another part is a piston chamber 24.
【0029】自硬性充填材注入部23内部には、周壁T
wと型枠4との間に充填された自硬性充填材がシールド
内に浸入することを防ぐための仕切板32が配置される
とともに、仕切板32には打設孔33が設けられ、打設
孔33には自硬性充填材注入管26の先端が挿通され
る。The self-hardening filler injecting portion 23 has a peripheral wall T inside.
A partition plate 32 for preventing the self-hardening filler material filled between w and the mold frame 4 from entering the shield is arranged, and the partition plate 32 is provided with a driving hole 33. The tip of the self-hardening filler injection tube 26 is inserted into the installation hole 33.
【0030】また、ピストン室24の内部には、押し出
しピストン27が配置されるとともに、押し出しピスト
ン27は、シールド掘削機Spの軸線に平行な方向から
圧力保持ジャッキ28によって押圧されることとなる。A pushing piston 27 is arranged inside the piston chamber 24, and the pushing piston 27 is pressed by a pressure holding jack 28 in a direction parallel to the axis of the shield excavator Sp.
【0031】また、図1に示したシールド掘削機Spの
II−II断面を示したのが図3である。図中に示すよ
うに、自硬性充填材注入管26は、自硬性充填材注入部
23にむけてのみ配置され、ピストン室24には配置さ
れない。FIG. 3 shows a section taken along the line II-II of the shield excavator Sp shown in FIG. As shown in the figure, the self-hardening filler injection pipe 26 is arranged only toward the self-hardening filler injection part 23, and is not arranged in the piston chamber 24.
【0032】図4は、図3におけるA−A断面を示した
図であり、圧力保持ジャッキ28および押し出しピスト
ン27を、シールド掘削機Spの軸線方向と直交する方
向から側面視した図である。図中に示すように、押し出
しピストン27には、そのスキンプレート1側と内筒1
0側の周囲にシール部材35が配置されている。また、
押し出しピストンの27の先端面すなわち打設自硬性充
填材を直接的に押圧する面には、圧力センサ36が取り
付けられている。さらに、この圧力センサ36は、圧力
保持ジャッキ28の駆動を制御する制御手段と接続され
ている。FIG. 4 is a view showing a cross section taken along the line AA in FIG. 3, and is a side view of the pressure holding jack 28 and the pushing piston 27 viewed from a direction orthogonal to the axial direction of the shield excavator Sp. As shown in the figure, the push-out piston 27 has its skin plate 1 side and inner cylinder 1
A seal member 35 is arranged around the zero side. Also,
A pressure sensor 36 is attached to the tip end surface of the push-out piston 27, that is, the surface that directly presses the cast hardening filler material. Further, the pressure sensor 36 is connected to control means for controlling the driving of the pressure holding jack 28.
【0033】次に、この圧力保持ジャッキ28の制御機
構の概要を、図5を参照して説明する。図5に示すよう
に、圧力保持ジャッキ28はピストン28aの前後両側
に作動油が供給されることでピストン28aが前後両方
向に駆動されるものとされており、したがってこの圧力
保持ジャッキ28はいずれかの側に作動油が選択的に供
給されることで伸縮して押出しピストン27を前後両方
向に駆動させることができるものとなっている。Next, an outline of a control mechanism of the pressure holding jack 28 will be described with reference to FIG. As shown in FIG. 5, the pressure holding jack 28 is configured such that the hydraulic oil is supplied to both front and rear sides of the piston 28a so that the piston 28a is driven in both front and rear directions. The hydraulic fluid is selectively supplied to the side, and the expansion piston expands and contracts, and the pushing piston 27 can be driven in both front and rear directions.
【0034】また、押し出しピストン27を駆動するた
めの圧力保持ジャッキ28の油圧回路は、油圧ポンプユ
ニット38、圧力保持ジャッキ28に供給する作動油の
圧力を設定するための圧力制御弁39、作動油の供給経
路を切換えて圧力保持ジャッキ28の駆動方向を切換え
るための方向制御弁40、作動油の流量を調節すること
で圧力保持ジャッキ28の伸縮速度を調節するための流
量方向制御弁41および圧力計42から構成されてい
る。The hydraulic circuit of the pressure holding jack 28 for driving the push-out piston 27 includes a hydraulic pump unit 38, a pressure control valve 39 for setting the pressure of hydraulic oil supplied to the pressure holding jack 28, and a hydraulic oil. Control valve 40 for switching the supply path of the pressure holding jack 28 to switch the driving direction of the pressure holding jack 28, a flow direction control valve 41 for adjusting the expansion / contraction speed of the pressure holding jack 28 by adjusting the flow rate of hydraulic oil, and pressure. It consists of a total of 42.
【0035】一方、圧力センサ36は、制御手段43と
接続されており、押出しピストン27によって押圧され
て加圧される自硬性充填材の圧力が刻々と検出されて制
御手段43に入力されるようになっている。なお、圧力
センサ36としては歪み計型の土圧計を用いることが好
適であるが、自硬性充填材圧力を検出できるものであれ
ば他の形式センサも適宜採用可能である。また、本実施
の形態においては各押出しピストン27に2つの圧力セ
ンサ36を設けてその1つを予備としているが、予備は
必ずしも設けることはないし、あるいはそれら2つの圧
力センサ36の双方(もしくはさらに多数の圧力セン
サ)により同時に圧力を検出して検出精度向上を図るよ
うにしても良い。On the other hand, the pressure sensor 36 is connected to the control means 43 so that the pressure of the self-hardening filler material pressed and pressed by the pushing piston 27 is detected every moment and inputted to the control means 43. It has become. It is preferable to use a strain gauge type earth pressure gauge as the pressure sensor 36, but other types of sensors can be appropriately used as long as they can detect the pressure of the self-hardening filler material. Further, in the present embodiment, two pressure sensors 36 are provided for each push-out piston 27 and one of them is used as a spare. However, a spare is not necessarily provided, or both of the two pressure sensors 36 (or furthermore, both of them are provided). The pressure may be simultaneously detected by a number of pressure sensors to improve the detection accuracy.
【0036】さらに、制御手段43は、計装用コンディ
ショナ44およびプログラマブルコントローラ45から
構成されている。計装用コンディショナ44は圧力セン
サ36からの検出信号を取込んでそれを表示するととも
に、自硬性充填材圧力Peの上限値Pe1、下限値Pe2、
およびヒステリシス(不感帯)の設定を行なうためのも
のである。また、プログラマブルコントローラ45は、
計装用コンディショナ44からの指示信号に基づき、上
記の方向制御弁40に制御信号を出力して圧力保持ジャ
ッキ28の作動を制御するものである。Further, the control means 43 comprises an instrumentation conditioner 44 and a programmable controller 45. The instrumentation conditioner 44 takes in the detection signal from the pressure sensor 36 and displays it, and also displays the upper limit Pe1 and the lower limit Pe2 of the self-hardening filler pressure Pe.
And setting of hysteresis (dead zone). Also, the programmable controller 45
A control signal is output to the direction control valve 40 based on an instruction signal from the instrumentation conditioner 44 to control the operation of the pressure holding jack 28.
【0037】次に、自硬性充填材注入管26の構造の詳
細についてを、図6ないし図11を参照して説明する。
図6は、図3におけるB−B断面を示した図であり、自
硬性充填材注入管26の構造を、シールド掘削機Spの
軸線方向と直交する側断面から見たものである。図中に
示すように、自硬性充填材注入管26は、その先端26
aが、内筒10のテール部10aにまでに至るような状
態で、スキンプレート1と内筒10との間に配置されて
いる。Next, the structure of the self-hardening filler injection tube 26 will be described in detail with reference to FIGS.
FIG. 6 is a view showing a cross section taken along the line BB in FIG. 3, and shows the structure of the self-hardening filler injection pipe 26 viewed from a side cross section orthogonal to the axial direction of the shield excavator Sp. As shown in the figure, the self-hardening filler injection pipe 26 has a tip 26
is disposed between the skin plate 1 and the inner cylinder 10 in such a state that a reaches the tail portion 10a of the inner cylinder 10.
【0038】図中に示すように、自硬性充填材注入管2
6は、その先端26aが、仕切板32に設けられた打設
孔33の内部に挿通されており、その胴部26bが、配
管固定用プレート46および配管固定用基礎プレート4
7を介してスキンプレート1に対して固定された構成と
されている。As shown in the figure, the self-hardening filler injection pipe 2
6 has a tip 26a inserted into a driving hole 33 provided in the partition plate 32, and a body portion 26b of which has a pipe fixing plate 46 and a pipe fixing base plate 4.
It is configured to be fixed to the skin plate 1 via the.
【0039】図6におけるc−c断面およびd−d断面
を示したのが、図7および8である。これらの図に示す
ように、自硬性充填材注入管26は、円筒を軸線に沿っ
た平面で2つに分割した形状とされた半割体48,48
から構成されており、これら半割体48,48が、自硬
性充填材の流路49を挟んで相対するように配置される
ことによって、自硬性充填材注入管26が構成されてい
る。FIGS. 7 and 8 show a cc section and a dd section in FIG. 6, respectively. As shown in these figures, the self-hardening filler injection pipe 26 has a shape obtained by dividing a cylinder into two in a plane along an axis, and is divided into two halves 48, 48.
The self-hardening filler injection pipe 26 is formed by arranging these half bodies 48, 48 so as to face each other across the flow path 49 of the self-hardening filler.
【0040】半割体48,48においては、図6に示し
たように、その先端48a、48a側が拡径されること
によりフランジ51,51が形成されており、フランジ
51,51は、図6、7、8に示すように、半割体4
8,48の先端部48a,48aに向かって、その外周
面51a,51aが直線的に縮径する構成とされてい
る。As shown in FIG. 6, flanges 51, 51 are formed by expanding the ends 48a, 48a of the half bodies 48, 48, and the flanges 51, 51 are formed as shown in FIG. , 7, 8 as shown in FIG.
The outer peripheral surfaces 51a, 51a are linearly reduced in diameter toward the distal ends 48a, 48a of the 8, 48.
【0041】さらに、図6、7、8に示すように、仕切
板32に形成された打設孔33の形状は、フランジ5
1,51の外周面51a,51aと相補形状となるよう
に、ロート状とされている。Further, as shown in FIGS. 6, 7 and 8, the shape of the driving hole 33 formed in the partition plate 32 is
1 and 51 are formed in a funnel shape so as to be complementary to the outer peripheral surfaces 51a and 51a.
【0042】図9は、図6におけるe−e断面を示した
図である。図中に示すように、自硬性充填材注入管26
の胴部26bにおいては、半割体48は、接続用プレー
ト48bが設けられた構成とされており、相対するよう
に配置された接続用プレート48b,48bの間には、
パッキン53が配置される構成とされている。接続用プ
レート48b,48b同士は、ボルト54およびナット
55によって連結されており、これによりパッキン53
は、接続用プレート48b,48bによって両側から押
圧される。このため、流路49の水密性が保たれること
となる。FIG. 9 is a view showing an ee section in FIG. As shown in the figure, the self-hardening filler injection pipe 26
In the trunk portion 26b, the half body 48 has a configuration in which a connection plate 48b is provided, and between the connection plates 48b, 48b arranged to face each other.
The packing 53 is arranged. The connection plates 48b, 48b are connected to each other by bolts 54 and nuts 55, so that the packing 53
Is pressed from both sides by the connection plates 48b, 48b. For this reason, the watertightness of the flow channel 49 is maintained.
【0043】図10は、図6におけるf−f断面を示し
た図である。図中に示すように、自硬性充填材注入管2
6を構成する半割体48,48には、それぞれ、配管固
定用プレート46,46が取り付けられており、これら
配管固定用プレート46,46は、スキンプレート1に
固定された配管固定用基礎プレート47に対して、ボル
ト56によって固定されている。これにより、自硬性充
填材注入管26が、スキンプレート1側に固定されるこ
ととなる。FIG. 10 is a diagram showing a section taken along line ff in FIG. As shown in the figure, the self-hardening filler injection pipe 2
The pipe fixing plates 46, 46 are respectively attached to the half bodies 48, 48 constituting the pipe 6, and the pipe fixing plates 46, 46 are pipe fixing base plates fixed to the skin plate 1. 47 is fixed by bolts 56. Thereby, the self-hardening filler injection tube 26 is fixed to the skin plate 1 side.
【0044】図11は、図6におけるg−g断面を示し
た図である。図中に示すように、配管固定用基礎プレー
ト47には、自硬性充填材注入管26を挿通するための
開口部57が設けられているとともに、開口部57の周
囲には、ボルト56(図10参照)を固定するための孔
58が設けられている。孔58には、ボルト56が螺着
できるように雌ネジが切られている。FIG. 11 is a view showing a gg section in FIG. As shown in the figure, the pipe fixing base plate 47 is provided with an opening 57 for inserting the self-hardening filler injection pipe 26, and around the opening 57, a bolt 56 (see FIG. 10) is provided. A female screw is formed in the hole 58 so that the bolt 56 can be screwed therein.
【0045】以上において、シールド掘削機Spの主要
な構成を説明したが、次に図12ないし図15を参照し
て、シールド掘削機Spを用いたトンネルTの覆工方法
について説明する。なお、図12ないし図15において
は、(a)において、ピストン室24およびその近傍を
拡大して示した図を、(b)において、自硬性充填材注
入部23およびその近傍を拡大して示した図を示すこと
とする。The main configuration of the shield excavator Sp has been described above. Next, a method of lining the tunnel T using the shield excavator Sp will be described with reference to FIGS. 12 to 15, (a) shows an enlarged view of the piston chamber 24 and its vicinity, and (b) shows an enlarged view of the self-hardening filler injection part 23 and its vicinity in (b). The figure is shown below.
【0046】まず、図12に示すように、内筒10の内
側において、鉄筋3を組み立てるとともに、この鉄筋3
の内側に型枠4を組立てる。さらに、内筒10と型枠4
との間を閉塞する主妻枠6aを、その一端が内筒10の
内面に接するように配置し、主妻枠6aの他端側に生じ
る型枠4の外面の間の隙間を、型枠4の内側から補助型
枠6bを突出させることにより塞ぐ。また、推進ジャッ
キ5は、型枠4に当接させておき、型枠4から推進ジャ
ッキ5が反力をとることができるようにしておく。この
とき、自硬性充填材圧力P0が地山圧力PJよりも常に高
くなるように、圧力保持ジャッキ28を駆動して押し出
しピストン27により打設自硬性充填材を加圧してお
く。これにより地下水が浸入してくることが防止されて
いる。First, as shown in FIG. 12, the rebar 3 is assembled inside the inner cylinder 10 and the rebar 3
Assemble the formwork 4 inside. Further, the inner cylinder 10 and the mold 4
The main wife frame 6a for closing the space between the main frame 6a and the inner surface of the inner cylinder 10 is disposed so that one end thereof is in contact with the inner surface of the inner cylinder 10. The auxiliary mold 6b is closed by protruding from the inside of the auxiliary mold 4. Further, the propulsion jack 5 is brought into contact with the formwork 4 so that the propulsion jack 5 can take a reaction force from the formwork 4. At this time, the pressure holding jack 28 is driven and the extruded piston 27 pressurizes the cast hardening filler so that the self-hardening filler pressure P0 always becomes higher than the ground pressure PJ. This prevents infiltration of groundwater.
【0047】次に、図13に示すように、型枠4、内筒
10および妻型枠6,6によって囲まれた部分の空間6
0に、打設管8から自硬性充填材Cを打設する。このと
き、トンネルTの周壁Twと型枠4との間に充填された
自硬性充填材Cが、地山圧力PJを上回る所定の圧力Po
を保つように、制御手段43(図5参照)により圧力保
持ジャッキ28を操作しておく。Next, as shown in FIG. 13, the space 6 surrounded by the mold 4, the inner cylinder 10, and the
At 0, the self-hardening filler C is cast from the casting pipe 8. At this time, the self-hardening filler C filled between the peripheral wall Tw of the tunnel T and the formwork 4 has a predetermined pressure Po exceeding the ground pressure PJ.
, The pressure holding jack 28 is operated by the control means 43 (see FIG. 5).
【0048】空間60に自硬性充填材Cが充填され、空
間60内の自硬性充填材Cの圧力Prが、先行打設され
ている自硬性充填材圧力Poと同等あるいはやや高くな
った時点で、図14に示すように、打設管8のシャッタ
9を閉じるとともに、先行の補助妻枠6bを引き下げて
後行打設部分を先行打設部分とを連通させる。これによ
り両者の打設自硬性充填材が一体化されることとなり、
さらに、それら全体の自硬性充填材圧力Poが地山圧力
Pjより高いままに保持されることとなる。When the space 60 is filled with the self-hardening filler C, and the pressure Pr of the self-hardening filler C in the space 60 becomes equal to or slightly higher than the pressure Po of the self-hardening filler previously placed, As shown in FIG. 14, the shutter 9 of the casting pipe 8 is closed, and the preceding auxiliary wive frame 6b is lowered to allow the following casting part to communicate with the preceding casting part. As a result, the casting self-hardening filler material of both is integrated,
Further, the entire self-hardening filler pressure Po is kept higher than the ground pressure Pj.
【0049】図14に示すように、空間60内への自硬
性充填材Cの打設が完了したら、次に、自硬性充填材注
入部23内に配置された自硬性充填材注入管26から、
トンネルTの周壁Twと型枠4との間の空間に、自硬性
充填材Cを打設する。このとき、押出しピストン27
は、圧力保持ジャッキ28により常に後方(図示右方)
へ押圧されるが、自硬性充填材の打設圧力により自硬性
充填材圧力Poが上昇した場合には、制御手段43(図
5参照)によって、圧力保持ジャッキ28の作動を漸次
前進(図示左方へ移動)するように制御し、自硬性充填
材圧力Poを所定の値に保つこととする。As shown in FIG. 14, when the setting of the self-hardening filler C into the space 60 is completed, next, the self-hardening filler injection pipe 26 arranged in the self-hardening filler injection part 23 is used. ,
The self-hardening filler C is cast in a space between the peripheral wall Tw of the tunnel T and the formwork 4. At this time, the pushing piston 27
Is always rearward (right side in the figure) by the pressure holding jack 28.
When the self-hardening filler pressure Po rises due to the driving pressure of the self-hardening filler, the operation of the pressure holding jack 28 is gradually advanced by the control means 43 (see FIG. 5) (see the left side in the figure). ), And the self-hardening filler pressure Po is maintained at a predetermined value.
【0050】制御手段43による圧力保持ジャッキ28
の制御の手順は以下の通りである。まず、あらかじめ計
装用コンディショナ44により自硬性充填材圧力Poの
上限値Po1、下限値Po2、ヒステリシスの設定を行なっ
ておく。それらの値は地山Jの状況等を考慮して適宜設
定すれば良いが、一例をあげれば、上限値Po1を地山圧
力Pj+1.0kgf/cm2、下限値Po2を地山圧力Pj+0.
5kgf/cm2、上限および下限でのヒステリシスをそれぞ
れ0.2kgf/cm2と設定する。Pressure holding jack 28 by control means 43
Is as follows. First, the upper limit value Po1, the lower limit value Po2, and the hysteresis of the self-hardening filler pressure Po are set by the instrumentation conditioner 44 in advance. These values may be appropriately set in consideration of the situation of the ground J, etc., but as an example, the upper limit Po1 is the ground pressure Pj + 1.0 kgf / cm 2 , and the lower limit Po2 is the ground pressure Pj + 0.
5 kgf / cm 2 , and the hysteresis at the upper and lower limits are each set to 0.2 kgf / cm 2 .
【0051】上記のように、自硬性充填材注入管26を
通じて、トンネルTの周壁Twと型枠4との間の空間に
自硬性充填材Cを打設すれば、打設が進むにつれて自硬
性充填材圧力Poは高まっていくこととなる。この自硬
性充填材圧力Poは圧力センサ36により刻々と検出さ
れるとともに、自硬性充填材圧力Poが上限値Po1に達
した時点(各設定値を上記で例示した値に設定した場合
にはPo=Pj+1.0kgf/cm2となった時点)で計装用コ
ンディショナ44からコントローラ45に指示信号が出
力され、コントローラ45は方向制御弁40に制御信号
を出力してそれを圧力保持ジャッキ28を縮退させる方
向に切換える。これにより圧力保持ジャッキ28は徐々
に縮退していき、自硬性充填材圧力Poは上限値Po1か
ら低下していく。As described above, if the self-hardening filler C is cast into the space between the peripheral wall Tw of the tunnel T and the mold 4 through the self-hardening filler injection pipe 26, the self-hardening The filler pressure Po will increase. The self-hardening filler pressure Po is momentarily detected by the pressure sensor 36, and when the self-hardening filler pressure Po reaches the upper limit value Po1 (when each set value is set to the value exemplified above, Po = Pj + 1.0 kgf / cm 2 ), an instruction signal is output from the instrumentation conditioner 44 to the controller 45, and the controller 45 outputs a control signal to the directional control valve 40 to depress the pressure holding jack 28. Switch to the direction in which you want As a result, the pressure holding jack 28 gradually contracts, and the self-hardening filler pressure Po decreases from the upper limit Po1.
【0052】この圧力保持ジャッキ28の縮退は、自硬
性充填材圧力Poがヒステリシス分だけ低下するまで
(上記の場合はPj+0.8kgf/cm2となるまで)継続
し、自硬性充填材圧力Poがその値に達したことが圧力
センサ36により検出されたら、計装用コンディショナ
44からコントローラ45に指示信号が出力され、コン
トローラ45は方向制御弁40に制御信号を出力してそ
れをニュートラルの位置に切換え、圧力保持ジャッキ2
8への作動油の供給を停止してそれをロックする。これ
により自硬性充填材圧力Poの低下が停止することとな
る。The contraction of the pressure holding jack 28 continues until the self-hardening filler pressure Po decreases by the amount of hysteresis (in the above case, Pj + 0.8 kgf / cm 2 ). When the pressure sensor 36 detects that the value has been reached, an instruction signal is output from the instrumentation conditioner 44 to the controller 45, and the controller 45 outputs a control signal to the directional control valve 40 and shifts the control signal to the neutral position. Switching, pressure holding jack 2
Stop supply of hydraulic oil to 8 and lock it. As a result, the decrease in the self-hardening filler pressure Po stops.
【0053】さらに自硬性充填材打設が継続されれば自
硬性充填材圧力Poは再び上昇するが、それに伴い以上
の動作が自動的に繰り返されて自硬性充填材圧力Poは
上限値Po1を越えて上昇することがない。Further, if the setting of the self-hardening filler is continued, the self-hardening filler pressure Po rises again. However, the above operation is automatically repeated, and the self-hardening filler pressure Po becomes the upper limit value Po1. Never rise above.
【0054】以上のようにして圧力保持ジャッキ28に
よって、自硬性充填材圧力Poを所定の値に保ちなが
ら、トンネルTの周壁Twと型枠4との間の空間に、自
硬性充填材Cを打設していくわけであるが、自硬性充填
材Cの打設量が一定の値に達したら、今度は、推進ジャ
ッキ5を作動させてシールド掘削機Spを前方に掘進さ
せる。As described above, while maintaining the self-hardening filler pressure Po at a predetermined value by the pressure holding jack 28, the self-hardening filler C is injected into the space between the peripheral wall Tw of the tunnel T and the formwork 4. When the amount of the self-hardening filler material C reaches a certain value, the propulsion jack 5 is operated to make the shield excavator Sp excavate forward.
【0055】シールド掘削機Spを掘進させる際には、
圧力保持ジャッキ28および押出しピストン27もとも
に前進していくので、自硬性充填材圧力Poは低下する
ことになるが、自硬性充填材圧力Poは、地山圧力PJよ
りも大きい値に保っておく必要があり、このためには、
押出しピストン27により打設自硬性充填材を押圧して
自硬性充填材圧力Poを保持しておかなければならな
い。したがって、この場合には、制御手段43および圧
力保持ジャッキ28を以下のように作動させて後方(図
中右方)へ移動させることとする。When excavating the shield excavator Sp,
Since the pressure holding jack 28 and the pushing piston 27 also advance, the self-hardening filler pressure Po decreases, but the self-hardening filler pressure Po is kept at a value larger than the ground pressure PJ. Need to do this,
The self-hardening filler material must be pressed by the extrusion piston 27 to maintain the self-hardening filler pressure Po. Therefore, in this case, the control means 43 and the pressure holding jack 28 are operated as follows to be moved rearward (to the right in the figure).
【0056】すなわち、掘進につれて低下していく自硬
性充填材圧力Poは圧力センサ36により刻々と検出さ
れ、自硬性充填材圧力Poが下限値Po2に達した時点
(各設定値を上記で例示した値に設定した場合にはPo
=Pj+0.5kgf/cm2となった時点)で計装用コンディ
ショナ44からコントローラ45に指示信号が出力さ
れ、コントローラ45は方向制御弁40に制御信号を出
力して、それを圧力保持ジャッキ28を伸長させる方向
に切換える。これにより圧力保持ジャッキ28は徐々に
伸長して自硬性充填材を加圧していき、自硬性充填材圧
力Poは下限値Po2から上昇していく。自硬性充填材圧
力Poがヒステリシス分だけ上昇するまで(上記例の場
合にはPj+0.7kgf/cm2となるまで)それが継続し、
自硬性充填材圧力Poがその値に達したことが圧力セン
サ36により検出されたら、計装用コンディショナ44
からコントローラ45に指示信号が出力され、コントロ
ーラ45は方向制御弁40に制御信号を出力してそれを
ニュートラルの位置に切換え、圧力保持ジャッキ28へ
の作動油の供給を停止してそれをロックする。これによ
り自硬性充填材圧力Poの上昇はその時点で停止する。
さらに掘進が継続されれば自硬性充填材圧力Poは再び
低下するが、それに伴い以上の動作が自動的に繰り返さ
れて自硬性充填材圧力Poは下限値Po2を越えて低下す
ることがない。That is, the self-hardening filler pressure Po that decreases as the excavation proceeds is detected every moment by the pressure sensor 36, and the self-hardening filler pressure Po reaches the lower limit Po2 (each set value is exemplified above). Po if set to a value
= Pj + 0.5 kgf / cm 2 ), an instruction signal is output from the instrumentation conditioner 44 to the controller 45, and the controller 45 outputs a control signal to the directional control valve 40, and sends it to the pressure holding jack 28. Switch to the extension direction. Accordingly, the pressure holding jack 28 gradually expands to press the self-hardening filler, and the self-hardening filler pressure Po rises from the lower limit Po2. It continues until the self-hardening filler pressure Po rises by the amount of hysteresis (until Pj + 0.7 kgf / cm 2 in the above example),
When the pressure sensor 36 detects that the self-hardening filler pressure Po has reached the value, the instrumentation conditioner 44
Outputs an instruction signal to the controller 45, the controller 45 outputs a control signal to the direction control valve 40, switches it to the neutral position, stops the supply of hydraulic oil to the pressure holding jack 28, and locks it. . Thereby, the rise of the self-hardening filler pressure Po stops at that point.
If the excavation continues, the self-hardening filler pressure Po decreases again. However, the above operation is automatically repeated, and the self-hardening filler pressure Po does not decrease below the lower limit Po2.
【0057】このようにシールド掘削機Spを掘進させ
る際には、以上のようにして、押し出しピストン27を
後方へ移動させて打設自硬性充填材を加圧しつつ、その
一方で、スキンプレート1側に固定された自硬性充填材
注入管26をスキンプレート1とともに一体的に移動さ
せることとする。これにより、トンネル掘進時に自硬性
充填材注入管26がシールド掘削機Sp内を動くことが
なくなる。When the shield excavator Sp is excavated in this way, the extruding piston 27 is moved rearward to press the cast hardening filler material while the skin plate 1 is being pushed. The self-hardening filler injection tube 26 fixed to the side is integrally moved together with the skin plate 1. As a result, the self-hardening filler injection pipe 26 does not move in the shield excavator Sp during tunnel excavation.
【0058】また、このように、トンネルTの掘進を行
ったら、その後に、図15に示すように、推進ジャッキ
5を引戻し、図12に示したように、推進ジャッキ5と
型枠4および鉄筋3との間の空間に、新たな鉄筋3の配
筋と型枠4の組み立てを行なう。また、この場合にも、
常に打設自硬性充填材圧力Poが、地山圧力PJを上回る
ように、圧力保持ジャッキ28を制御して押し出しピス
トン52により打設自硬性充填材を押圧する。After the tunnel T has been dug, the propulsion jack 5 is pulled back as shown in FIG. 15, and the propulsion jack 5, the formwork 4 and the reinforcing bar are formed as shown in FIG. In the space between the reinforcing bars 3, the reinforcing bars 3 are newly arranged and the formwork 4 is assembled. Also in this case,
The pressure holding jack 28 is controlled so that the driven-in hardening filler material is pressed by the pushing piston 52 so that the pressure of the hard-filled filler material Po always exceeds the ground pressure PJ.
【0059】本実施の形態においては、以上の手順を繰
り返してトンネルTの掘進が行なわれることとなる。な
お、上記の制御手段43による圧力保持ジャッキ28制
御動作は電気的に行なわれるから、リリーフ弁等を作動
させることによりり圧力保持ジャッキ28を縮退させる
ようにする場合と比較して、応答性の点で格段に優れた
ものとなっている。したがって、自硬性充填材圧力Po
が急激に変化したような場合であっても圧力保持ジャッ
キ28が速やかに追随して自硬性充填材圧力Poが上限
値Po1あるいは下限値Po2を越えてしまうようなことは
ない。また、上記の手順において、自硬性充填材注入部
23への自硬性充填材打設とシールド機Spの掘進を同
時に行なうようにしてもよいが、この場合に、自硬性充
填材注入部23内における自硬性充填材圧力Poはより
複雑に変化したとしても、圧力センサ36により検出さ
れる実際の自硬性充填材圧力Poに応じて圧力保持ジャ
ッキ28が自ずと最適に作動し、自硬性充填材圧力Po
が上限値Po1を越えて上昇したり下限値Po2を越えて低
下することが確実に防止されることとなる。In this embodiment, the tunnel T is dug by repeating the above procedure. Since the control operation of the pressure holding jack 28 by the control means 43 is performed electrically, the response of the pressure holding jack 28 is reduced as compared with the case where the pressure holding jack 28 is contracted by operating a relief valve or the like. It is much better in that respect. Therefore, the self-hardening filler pressure Po
Does not suddenly follow the pressure holding jack 28 to cause the self-hardening filler pressure Po to exceed the upper limit Po1 or the lower limit Po2. In the above procedure, the setting of the self-hardening filler into the self-hardening filler injecting section 23 and the excavation of the shield machine Sp may be performed at the same time. Even if the self-hardening filler pressure Po changes more complicatedly, the pressure holding jack 28 automatically operates optimally in accordance with the actual self-hardening filler pressure Po detected by the pressure sensor 36, and the self-hardening filler pressure Po
Is reliably prevented from rising above the upper limit Po1 or falling below the lower limit Po2.
【0060】上述のシールド掘削機Spにおいては、ス
キンプレート1と内筒10との間に、周壁Twと型枠4
との間の空間と連通した自硬性充填材注入部23とピス
トン室24とが別個に形成されており、これらのうち、
自硬性充填材注入部23には、自硬性充填材注入管26
が、ピストン室24には、押し出しピストン27が配置
される構成とされている。In the above-described shield excavator Sp, the peripheral wall Tw and the formwork 4 are provided between the skin plate 1 and the inner cylinder 10.
The self-hardening filler injecting part 23 and the piston chamber 24 communicating with the space between the piston and the piston are formed separately.
The self-hardening filler injection section 23 has a self-hardening filler injection pipe 26.
However, the push-out piston 27 is arranged in the piston chamber 24.
【0061】このように、自硬性充填材注入部23とピ
ストン室24とを分離したことにより、押し出しピスト
ン27に自硬性充填材打設のための孔を設ける必要がな
くなり、したがって、押し出しピストン27において断
面欠損が生じることがなく、従来と比較して、押し出し
ピストン27の構造的な強度が高められる。これによ
り、自硬性充填材圧力Poを高い値に設定した場合に
も、押し出しピストン27の幅を大きくして、その構造
的な強度を高める必要がなくなり、トンネルTの覆工厚
さ寸法を、従来技術と比較して小さくすることができ
る。したがって、トンネルTにおいて、同一の内部空間
を確保しようとする場合、従来技術を用いた場合に比べ
てトンネルTの掘削断面積を小さくして、その建設コス
トの低減化を図ることができる。As described above, since the self-hardening filler injecting portion 23 and the piston chamber 24 are separated from each other, it is not necessary to provide the extrusion piston 27 with a hole for casting the self-hardening filler. In this case, no cross-sectional defect occurs, and the structural strength of the push-out piston 27 is increased as compared with the related art. Accordingly, even when the self-hardening filler pressure Po is set to a high value, it is not necessary to increase the width of the extrusion piston 27 to increase its structural strength, and the lining thickness of the tunnel T is reduced. The size can be reduced as compared with the prior art. Therefore, when the same internal space is to be secured in the tunnel T, the excavation cross-sectional area of the tunnel T can be reduced as compared with the case where the conventional technology is used, and the construction cost can be reduced.
【0062】さらに、上述のシールド掘削機Spにおい
ては、自硬性充填材注入管26が、配管固定用プレート
46および配管固定用基礎プレート47を介してスキン
プレート1に固定される構成とされる。これにより、自
硬性充填材注入管26によってトンネルTの周壁Twと
型枠4との間の空間に自硬性充填材Cを打設していく場
合や、シールド掘削機Spを前方に掘進させる場合に
も、自硬性充填材注入管26がシールド掘削機Spの中
を動くことがなく、従来のシールド掘削機Sのように自
硬性充填材打設管15の移動スペースを、その内部に開
けておく必要がなくなる。Further, in the above-mentioned shield excavator Sp, the self-hardening filler injection pipe 26 is configured to be fixed to the skin plate 1 via the pipe fixing plate 46 and the pipe fixing base plate 47. Thereby, when the self-hardening filler C is driven into the space between the peripheral wall Tw of the tunnel T and the formwork 4 by the self-hardening filler injection pipe 26, or when the shield excavator Sp is excavated forward. In addition, the self-hardening filler injection pipe 26 does not move in the shield excavator Sp, and a moving space for the self-hardening filler casting pipe 15 is opened in the inside thereof as in the conventional shield excavator S. No need to keep it.
【0063】また、シールド掘削機Spにおいては、自
硬性充填材注入管26がシールド掘削機Spの中を移動
しないために、自硬性充填材注入管26をフレキシブル
ホースのような柔軟性をもった素材により形成する必要
がなく、自硬性充填材打設時に、ホースが振れたりする
ような不具合が生じない。このように、本実施の形態の
シールド掘削機Spは、従来のものにくらべて、使用性
に優れたものとなる。In the shield excavator Sp, since the self-hardening filler injection pipe 26 does not move in the shield excavator Sp, the self-hardening filler injection pipe 26 has flexibility like a flexible hose. It is not necessary to be formed of a material, and there is no problem that the hose swings when the self-hardening filler is poured. As described above, the shield excavator Sp of the present embodiment is more excellent in usability than the conventional one.
【0064】さらに、シールド掘削機Spは、自硬性充
填材注入管26が、スキンプレート1側に固定されるた
めに、フレキシブルホースなどを用いた配管にくらべ
て、管の配置や形状等が複雑になる懸念が少なく、これ
により、管の内部において自硬性充填材Cが詰まる心配
も減少する。したがって、このシールド掘削機Spは、
従来のものにくらべて、安全性においても優れている。Further, in the shield excavator Sp, since the self-hardening filler injection pipe 26 is fixed to the skin plate 1 side, the arrangement and shape of the pipe are more complicated than the pipe using a flexible hose or the like. Is less likely to occur, thereby reducing the risk of clogging of the self-hardening filler C inside the tube. Therefore, this shield excavator Sp
It is also superior in safety compared to conventional ones.
【0065】また、上述のシールド掘削機Spを用いた
トンネル覆工方法によれば、シールド掘削機Spを前方
に掘進させる際に、自硬性充填材注入管26がシールド
掘削機Spの中を動くことがないため、自硬性充填材注
入管26の移動スペースを、その内部に開けておく必要
がなくなる。これにより、シールド掘削機Sp内部の空
間を有効に利用することができる。According to the tunnel lining method using the above-described shield excavator Sp, when the shield excavator Sp is excavated forward, the self-hardening filler injection pipe 26 moves in the shield excavator Sp. Therefore, there is no need to open a space for moving the self-hardening filler injection pipe 26 therein. As a result, the space inside the shield excavator Sp can be effectively used.
【0066】また、このトンネル覆工方法においては、
自硬性充填材注入管26がスキンプレート1側にあらか
じめ固定されており、トンネルTの掘進時には、ピスト
ン室24において押し出しピストン27により打設自硬
性充填材の押圧が行われるとともに、自硬性充填材注入
部23において、自硬性充填材注入管26がスキンプレ
ート1と一体となって前進する。このような覆工方法を
採用したことにより、自硬性充填材注入管26をフレキ
シブルホースのような柔軟性をもった素材によって形成
しておく必要がなくなる。したがって、自硬性充填材打
設管26が振れたり、その配置や形状等が複雑になるな
どの心配がなく、さらに、管の内部において自硬性充填
材Cが詰まる心配も減少し、シールド掘削機Spの信頼
性が向上することとなる。In this tunnel lining method,
A self-hardening filler injection pipe 26 is fixed to the skin plate 1 side in advance, and when the tunnel T is excavated, the self-hardening filler is pressed by the extrusion piston 27 in the piston chamber 24 and the self-hardening filler is pressed. In the injection part 23, the self-hardening filler injection tube 26 advances integrally with the skin plate 1. By employing such a lining method, it is not necessary to form the self-hardening filler injection pipe 26 from a flexible material such as a flexible hose. Accordingly, there is no fear that the self-hardening filler casting pipe 26 oscillates, the arrangement and the shape thereof become complicated, and the self-hardening filler C is less likely to be clogged inside the pipe. The reliability of Sp is improved.
【0067】以上において、第一の実施の形態を説明し
たが、本発明は上記第一の実施の形態に限定されるもの
ではなく、その主旨を逸脱しない範囲で、上記実施の形
態の構成の一部を以下のように変更することが可能であ
る。Although the first embodiment has been described above, the present invention is not limited to the first embodiment, and the configuration of the above embodiment is not deviated from the gist of the present invention. Some can be changed as follows.
【0068】例えば、図16に示すように、本発明のシ
ールド掘削機Spを、トンネル覆工壁Wに鉄筋が配筋さ
れないようなトンネルT’に適用するようにしてもよ
い。この場合のシールド掘削機Spに係る作用および効
果は、鉄筋の配置を行う手順が省略されることを除け
ば、上記実施の形態と全く同様である。また、図16の
ようにシールド掘削機Spを、トンネルT’の構築に適
用した場合には、内筒10のテール部10aと型枠4と
の間に、ステンレス板などの材料からなるテールシール
62を配置して、シールド掘削機Sp内に自硬性充填材
Cが浸入しないようにすることが好適である。図17
は、このテールシール62の形状を拡大して示した図で
ある。このように、テールシール62は内筒10に対し
て、ボルト63によって接合される。また、テールシー
ル62を用いることによって、内筒10と型枠4との間
に間隙64を形成して、シールド掘削機Spがスムーズ
に移動するようにすることが可能である。For example, as shown in FIG. 16, the shield excavator Sp of the present invention may be applied to a tunnel T ′ in which no reinforcing bars are arranged on the tunnel lining wall W. The operation and effect of the shield excavator Sp in this case are exactly the same as those of the above-described embodiment except that the procedure for arranging the reinforcing bars is omitted. When the shield excavator Sp is applied to the construction of the tunnel T 'as shown in FIG. 16, a tail seal made of a material such as a stainless steel plate is provided between the tail part 10a of the inner cylinder 10 and the formwork 4. It is preferable to arrange 62 to prevent the self-hardening filler material C from entering the shield excavator Sp. FIG.
Is an enlarged view of the shape of the tail seal 62. Thus, the tail seal 62 is joined to the inner cylinder 10 by the bolt 63. Further, by using the tail seal 62, it is possible to form a gap 64 between the inner cylinder 10 and the formwork 4 so that the shield excavator Sp can move smoothly.
【0069】また、図18は、図2に示した上記実施の
形態のシールド掘削機Spのテール部の構成を変形した
場合の例である。なお、図中においては、上記実施の形
態と相違する内筒10とスキンプレート1との間の自硬
性充填材充填空間部21の構成のみが図示されている。FIG. 18 shows an example in which the configuration of the tail of the shield excavator Sp of the above embodiment shown in FIG. 2 is modified. In the drawing, only the configuration of the self-hardening filler filling space 21 between the inner cylinder 10 and the skin plate 1 which is different from the above embodiment is shown.
【0070】図18に示した自硬性充填材充填空間部2
1は、図2に示したものと同様に、隔壁30によってそ
の周方向に分割されており、なおかつ、自硬性充填材注
入管26の配置された自硬性充填材注入部23と、押し
出しピストン27が配置されたピストン室24とを備え
て構成されているが、その他に、自硬性充填材注入管2
6と押し出しピストン27のいずれもが配置されない空
間65を備えた構成とされている。また、図19は、図
18におけるh−h断面を示した図であり、空間65の
テール部には、先端閉塞用プレート66が配置されてお
り、打設された自硬性充填材がシールド掘削機Sp内に
浸入しないような構成とされている。The self-hardening filler filling space portion 2 shown in FIG.
1 is divided in the circumferential direction by a partition wall 30 in the same manner as that shown in FIG. 2, and further includes a self-hardening filler injecting section 23 in which a self-hardening filler injecting pipe 26 is disposed, and an extrusion piston 27. And a piston chamber 24 in which a self-hardening filler injection pipe 2 is provided.
6 and the pushing piston 27 are provided with a space 65 in which neither is arranged. FIG. 19 is a view showing a cross section taken along the line hh in FIG. 18. A plate 66 for closing the tip is disposed at the tail of the space 65, and the poured self-hardening filler material is shielded by excavation. It is configured not to enter the machine Sp.
【0071】自硬性充填材が十分流動性を保っていれ
ば、自硬性充填材の圧力は遠くまで伝播するため、上記
実施の形態のように、自硬性充填材充填空間部21の全
てを自硬性充填材注入部23と押し出しピストン27と
のみによって形成する必要はなく、自硬性充填材充填空
間部21を、図18に示したような構成とすることも可
能である。If the self-hardening filler material has sufficient fluidity, the pressure of the self-hardening filler material propagates far, so that the entire space of the self-hardening filler filling space 21 is self-contained as in the above embodiment. It is not necessary to form only the hard filler injecting portion 23 and the pushing piston 27, and the self-hardening filler filling space 21 may be configured as shown in FIG.
【0072】さらに、図20は、シールド掘削機Sp
を、矩形トンネルを構築するための矩形シールド機とし
て構成した場合の図である。図18と同様に、ここでも
自硬性充填材充填空間部21の構成のみが示されてい
る。図2および図18と同様に、自硬性充填材充填空間
部21は、隔壁30によってその周方向に分割されてお
り、なおかつ、自硬性充填材注入管26の配置された自
硬性充填材注入部23と、押し出しピストン27が配置
されたピストン室24とを備えて構成されている。さら
に、この場合にも、図18に示したものと同様に、自硬
性充填材充填空間部21を自硬性充填材注入管26およ
び押し出しピストン27のいずれもが配置されない空間
65を備えたものとすることも可能である。FIG. 20 shows a shield excavator Sp.
FIG. 1 is a diagram of a case where a rectangular shield machine for constructing a rectangular tunnel is configured. As in FIG. 18, here, only the configuration of the self-hardening filler filling space 21 is shown. As in FIGS. 2 and 18, the self-hardening filler filling space 21 is divided in the circumferential direction by a partition wall 30, and the self-hardening filler injecting part in which the self-hardening filler injection pipe 26 is disposed. 23 and a piston chamber 24 in which an extruding piston 27 is disposed. Further, also in this case, similarly to the one shown in FIG. 18, the self-hardening filler filling space 21 is provided with a space 65 in which neither the self-hardening filler injection pipe 26 nor the pushing piston 27 is arranged. It is also possible.
【0073】[第二の実施の形態]次に、本発明に係る
第二の実施の形態について説明する。以下に説明する第
二の実施の形態は、鉄筋を配筋せずにトンネルを構築す
るためのシールド掘削機およびそれを用いたトンネル覆
工方法についての例であり、前記第一の実施の形態と共
通する構成については同符号を付し、その説明を省略す
る。[Second Embodiment] Next, a second embodiment according to the present invention will be described. The second embodiment described below is an example of a shield excavator for constructing a tunnel without arranging reinforcing bars and a tunnel lining method using the same, and the first embodiment The same reference numerals are given to the same components as those described above, and description thereof will be omitted.
【0074】図21に示すように、地山Jにおいてトン
ネルT’を掘削するためのシールド掘削機Sp’は、ス
キンプレート1の先端部に地山Jを掘削するカッター装
置2を備え、スキンプレート1内には推進ジャッキ5を
備えている。このシールド掘削機Sp’では、スキンプ
レート1の後方側で型枠4が組み立てられ、この型枠4
とトンネルT’の周壁Twとの間に自硬性充填材を打設
充填することにより、無筋(鉄筋の配筋されていない)
トンネル覆工壁W’が形成される構成となっている。As shown in FIG. 21, the shield excavator Sp ′ for excavating the tunnel T ′ in the ground J is provided with a cutter device 2 for excavating the ground J at the tip of the skin plate 1. 1 is provided with a propulsion jack 5. In this shield excavator Sp ', the formwork 4 is assembled on the rear side of the skin plate 1, and this formwork 4
By filling with a self-hardening filler between the inner wall and the peripheral wall Tw of the tunnel T ′, so that no reinforcement (rebar is not arranged)
The tunnel lining wall W 'is formed.
【0075】このシールド掘削機Sp’が前記第一の実
施の形態で示したシールド掘削機Spと最も異なる点
は、シールド掘削機Sp’は、前記第一の実施の形態に
おけるシールド掘削機Spの如く、スキンプレート1の
テール部の内側に内筒10(図1参照)を備えていない
点である。The most different point of the shield excavator Sp ′ from the shield excavator Sp shown in the first embodiment is that the shield excavator Sp ′ is different from the shield excavator Sp in the first embodiment. As described above, the inner plate 10 is not provided inside the tail portion of the skin plate 1 (see FIG. 1).
【0076】すなわち、シールド掘削機Sp’には、ス
キンプレート1のテール部の内側に、自硬性充填材充填
空間部101が型枠4と周壁Twとの間の空間に対して
連通状態に形成されている。図22に示すように、この
自硬性充填材充填空間部101は、自硬性充填材注入部
103とピストン室104とが互いに分割され、これら
がスキンプレート1の周方向において交互に並べられて
配設された構成からなっている。That is, in the shield excavator Sp ′, the self-hardening filler filling space 101 is formed inside the tail of the skin plate 1 so as to communicate with the space between the formwork 4 and the peripheral wall Tw. Have been. As shown in FIG. 22, in the self-hardening filler filling space 101, a self-hardening filler injecting portion 103 and a piston chamber 104 are divided from each other, and these are arranged alternately in the circumferential direction of the skin plate 1. It consists of a set configuration.
【0077】ピストン室104は、スキンプレート1の
内周面に一体に設けられたシリンダ部材105によって
形成されている。シリンダ部材105は、スキンプレー
ト1の内周面に略直交する側壁部105a,105a
と、スキンプレート1の内周面よりも所定寸法内側に位
置する円弧状の内壁部105bとから形成された断面視
略コ字状で、両側端部の側壁部105a,105aがス
キンプレート1の内周面に溶接される等して一体に固定
されている。つまり、ピストン室104は、シリンダ部
材105の側壁部105a,105aおよび内壁部10
5bと、スキンプレート1の内周面とに囲まれて形成さ
れているのである。The piston chamber 104 is formed by a cylinder member 105 provided integrally on the inner peripheral surface of the skin plate 1. The cylinder member 105 includes side wall portions 105a, 105a substantially perpendicular to the inner peripheral surface of the skin plate 1.
And an arc-shaped inner wall portion 105b located inside the inner peripheral surface of the skin plate 1 by a predetermined dimension and having a substantially U-shape in cross section, and the side wall portions 105a, 105a at both side ends are formed of the skin plate 1. It is integrally fixed by welding to the inner peripheral surface. That is, the piston chamber 104 is provided with the side wall portions 105a and 105a of the cylinder member 105 and the inner wall portion 10a.
5 b and the inner peripheral surface of the skin plate 1.
【0078】このピストン室104内には、押し出しピ
ストン27が、前後両方向にスライド自在に配設され、
これがスキンプレート1側に固定された圧力保持ジャッ
キ28によって進退駆動されて、シールド掘削機Sp’
の軸線に平行な方向から押圧できる構成となっている。In the piston chamber 104, a pushing piston 27 is slidably provided in both front and rear directions.
This is driven forward and backward by the pressure holding jack 28 fixed to the skin plate 1 side, and the shield excavator Sp ′ is driven.
Can be pressed from a direction parallel to the axis of
【0079】図23(a)は、図22のシールド掘削機
Sp’のA’−A’断面を、つまり圧力保持ジャッキ2
8および押し出しピストン27をシールド掘削機Sp’
の軸線方向と直交する方向から側面視した図である。図
中に示すように、押し出しピストン27には、そのスキ
ンプレート1側とシリンダ部材105の内壁部105b
側の周囲にシール部材35が配置されている。この圧力
保持ジャッキ28による圧力保持機構、およびそのため
の制御機構は、前記第一の実施の形態で説明した通りで
あり、ここではその説明を省略する。FIG. 23 (a) is a sectional view taken along the line A′-A ′ of the shield excavator Sp ′ shown in FIG.
8 and the extruding piston 27 are connected to the shield excavator Sp '.
FIG. 3 is a side view from a direction orthogonal to the axial direction of FIG. As shown in the figure, the push-out piston 27 has its skin plate 1 side and the inner wall portion 105 b of the cylinder member 105.
A seal member 35 is disposed around the side. The pressure holding mechanism by the pressure holding jack 28 and the control mechanism therefor are as described in the first embodiment, and a description thereof will be omitted here.
【0080】図22に示したように、自硬性充填材充填
空間部101には、シリンダ部材105によって周方向
に間隔を隔てて複数のピストン室104が設けられ、こ
れらピストン室104以外の部分、言い換えると、隣り
合うピストン室104,104間に前記自硬性充填材注
入部103が形成されたこととなる。As shown in FIG. 22, a plurality of piston chambers 104 are provided in the self-hardening filler filling space portion 101 at intervals in the circumferential direction by a cylinder member 105. In other words, the self-hardening filler injection portion 103 is formed between the adjacent piston chambers 104, 104.
【0081】図23(b)は、図22のシールド掘削機
Sp’のB’−B’断面を示している。自硬性充填材注
入部103の内部には、スキンプレート1の後端部位置
に、周壁Twと型枠4との間に充填された自硬性充填材
がシールド内に浸入することを防ぐためのエンドプレー
ト106が設けられている。そして、図23(b)に示
したように、このエンドプレート106には打設孔33
が設けられ、この打設孔33に自硬性充填材注入管26
の先端が挿通されている。図22に示したように、各自
硬性充填材注入管26は、自硬性充填材注入部103に
むけてのみ配置され、ピストン室104には配置されて
いない。FIG. 23 (b) shows a section taken along the line B'-B 'of the shield excavator Sp' of FIG. Inside the self-hardening filler injecting portion 103, at the rear end position of the skin plate 1, a self-hardening filler filled between the peripheral wall Tw and the formwork 4 is prevented from entering the shield. An end plate 106 is provided. Then, as shown in FIG. 23B, the driving holes 33 are formed in the end plate 106.
The self-hardening filler injection pipe 26 is
The tip of is inserted. As shown in FIG. 22, each self-hardening filler injection pipe 26 is disposed only toward the self-hardening filler injection part 103, and is not disposed in the piston chamber 104.
【0082】また、図23(a)および(b)に示した
ように、ピストン室104を構成するシリンダ部材10
5の内壁部105b、および自硬性充填材注入部103
に設けられたエンドプレート106には、それぞれその
内周側の端縁部に、内方で組立てる型枠4との隙間をシ
ールするテールシール107が取り付けられている。Further, as shown in FIGS. 23A and 23B, the cylinder member 10 forming the piston chamber 104
5 and the self-hardening filler injecting section 103
A tail seal 107 for sealing a gap with the formwork 4 to be assembled inward is attached to an end edge on the inner peripheral side of each of the end plates 106 provided at the inner side.
【0083】このような構成のシールド掘削機Sp’で
は、前記第一の実施の形態で示したシールド掘削機Sp
と同様に、地山Jをカッター装置2で掘削し、その後方
のスキンプレート1内で組み上げた型枠4と周壁Twと
の間に自硬性充填材を打設充填することによりトンネル
覆工壁W’(ただし、無筋である)を形成しつつ、推進
ジャッキ5で型枠4に反力をとって掘進方向に推進して
いくことによってトンネルT’を構築していくようにな
っている。In the shield excavator Sp ′ having such a configuration, the shield excavator Sp shown in the first embodiment is used.
In the same manner as described above, the ground J is excavated with the cutter device 2, and the self-hardening filler is poured and filled between the formwork 4 assembled in the skin plate 1 behind and the peripheral wall Tw, thereby forming the tunnel lining wall. The tunnel T 'is constructed by forming a W' (however, it is plain) while taking a reaction force on the form 4 with the propulsion jack 5 and propelling it in the excavation direction. .
【0084】そして、型枠4と周壁Twとの間に自硬性
充填材を打設充填するときには、自硬性充填材注入部1
03の自硬性充填材注入管26から、エンドプレート1
06の後方の型枠4と周壁Twとの間の空間に自硬性充
填材を打設しつつ、ピストン室104内の押し出しピス
トン27を圧力保持ジャッキ28で進退駆動させること
によって、打設した自硬性充填材を押圧して所定以上の
圧力に保持するようになっている。When the self-hardening filler is poured between the mold 4 and the peripheral wall Tw, the self-hardening filler injection section 1
03 from the self-hardening filler injection tube 26, the end plate 1
06, while pushing the self-hardening filler into the space between the formwork 4 and the peripheral wall Tw, the extruding piston 27 in the piston chamber 104 is driven forward and backward by the pressure holding jack 28 to thereby drive the self-hardening filler. The hard filler is pressed to maintain the pressure at or above a predetermined value.
【0085】上述したシールド掘削機Sp’では、スキ
ンプレート1の内周面側に、周壁Twと型枠4との間の
空間と連通した自硬性充填材充填空間部101が配設さ
れ、この自硬性充填材充填空間部101には自硬性充填
材注入部103とピストン室104とが別個に形成され
た構成となっている。これにより、前記第一の実施の形
態と同様に、ピストン室104の押し出しピストン27
に自硬性充填材打設のための孔を設ける必要がなくな
り、断面欠損が生じることがないので押し出しピストン
27の構造的な強度が高められる。したがってトンネル
T’の覆工厚さ寸法を、従来技術と比較して小さくする
ことができ、トンネルT’において同一の内部空間を確
保しようとする場合、従来技術を用いた場合に比べてト
ンネルTの掘削断面積を小さくして、その建設コストの
低減化を図ることができる。In the above-mentioned shield excavator Sp ′, a self-hardening filler filling space 101 communicating with the space between the peripheral wall Tw and the formwork 4 is provided on the inner peripheral surface side of the skin plate 1. The self-hardening filler filling space 101 has a configuration in which a self-hardening filler injecting portion 103 and a piston chamber 104 are separately formed. Thereby, similarly to the first embodiment, the pushing piston 27 of the piston chamber 104 is
It is not necessary to provide a hole for placing a self-hardening filler material in the hole, and there is no occurrence of a sectional defect, so that the structural strength of the push-out piston 27 is increased. Therefore, the lining thickness dimension of the tunnel T 'can be made smaller than that of the conventional technique, and when the same internal space is to be secured in the tunnel T', the tunnel T ' Excavation cross-sectional area can be reduced, and the construction cost can be reduced.
【0086】さらに、上述のシールド掘削機Sp’にお
いては、自硬性充填材注入管26がエンドプレート10
6等を介してスキンプレート1に固定される構成となっ
ており、これにより、前記第一の実施の形態と同様、自
硬性充填材注入管26がシールド掘削機Sp’の中を動
くことがない。したがって、スキンプレート1内の空間
の有効利用が図られるとともに、、使用性および安全性
に優れたものとなる。Further, in the above-described shield excavator Sp ′, the self-hardening filler injection pipe 26 is connected to the end plate 10.
6, the self-hardening filler injection pipe 26 can move in the shield excavator Sp 'as in the first embodiment. Absent. Therefore, the space in the skin plate 1 is effectively used, and the usability and the safety are excellent.
【0087】加えて、上述した第二の実施の形態におけ
るシールド掘削機Sp’は、前記第一の実施の形態にお
けるシールド掘削機Spとは異なり、スキンプレート1
の内周面にその両側端部が固定されたシリンダ部材10
5によってピストン室104が形成された構成となって
いる。前記第一の実施の形態におけるシールド掘削機S
pにおいては、図2に示したように、スキンプレート1
のテール部に内筒10が設けられ、二重構造となってい
る。このようにテール部を二重にして内筒10を製作す
る場合にはその溶接に手間がかかり、特にピストン室2
3の精度を確保するためには、内筒10が大型で、しか
も内筒10とスキンプレート1との間に隔壁30を設置
しなければならないために多大な手間が必要となり、製
作費が嵩む原因となる。これに対して、本第二の実施の
形態におけるシールド掘削機Sp’では、スキンプレー
ト1の内周面にシリンダ部材105を溶接するのみでよ
いので、前記のような問題が発生せず、製作を容易に行
って製作費を低減することが可能となる。さらに、シリ
ンダ部材105に押し出し材や鋳造品等を用い、予め所
定形状に成形しておけば、この効果はより一層顕著なも
のとなる。In addition, the shield excavator Sp ′ in the second embodiment described above differs from the shield excavator Sp in the first embodiment in that the skin plate 1
Member 10 having both ends fixed to the inner peripheral surface of the cylinder
5, the piston chamber 104 is formed. The shield excavator S in the first embodiment
In p, as shown in FIG.
The inner cylinder 10 is provided in the tail part of this, and it has a double structure. In the case where the inner cylinder 10 is manufactured with a double tail as described above, it takes time and effort to weld the inner cylinder 10, and particularly the piston chamber 2.
In order to ensure the accuracy of 3, the inner cylinder 10 is large, and the partition 30 must be installed between the inner cylinder 10 and the skin plate 1. This requires a great deal of labor and increases production costs. Cause. On the other hand, in the shield excavator Sp ′ according to the second embodiment, since only the cylinder member 105 needs to be welded to the inner peripheral surface of the skin plate 1, the above-described problem does not occur, and Can be easily performed, and the manufacturing cost can be reduced. Furthermore, if an extruded material, a cast product, or the like is used for the cylinder member 105 and is formed into a predetermined shape in advance, this effect becomes even more remarkable.
【0088】なお、上記第二の実施の形態においても、
前記第一の実施の形態と同様、他の変形例にも適用可能
である。Note that also in the second embodiment,
As in the first embodiment, the present invention can be applied to other modified examples.
【0089】例えば、図24に示すものは、上記実施の
形態のシールド掘削機Sp’のテール部の構成を変形し
た場合の例である。なお、図中においては、上記実施の
形態と相違する自硬性充填材充填空間部101の構成の
みが図示されている。自硬性充填材充填空間部101
は、図22に示したものと同様に、シリンダ部材105
によってピストン室104が形成され、互いに隣接する
ピストン室104,104間の空間が自硬性充填材注入
部103とされた構成となっているが、その他に、自硬
性充填材注入管26と押し出しピストン27のいずれも
が配置されない空間109を備えている。図25は、図
24におけるh’−h’断面を示した図であり、空間1
09のテール部には、エンドプレート110が配置され
ており、打設された自硬性充填材がシールド掘削機S
p’内に浸入しないような構成とされている。自硬性充
填材が十分流動性を保っていれば、自硬性充填材の圧力
は遠くまで伝播するため、上記実施の形態のように、自
硬性充填材充填空間部101の全てを自硬性充填材注入
部103とピストン室104とのみによって形成する必
要はなく、自硬性充填材充填空間部101を、図24に
示したような構成とすることも可能である。For example, FIG. 24 shows an example in which the configuration of the tail of the shield excavator Sp ′ of the above embodiment is modified. In the figure, only the configuration of the self-hardening filler filling space 101 different from the above embodiment is shown. Self-hardening filler filling space 101
Is similar to the one shown in FIG.
Thus, a piston chamber 104 is formed, and a space between the adjacent piston chambers 104, 104 is configured as a self-hardening filler injection part 103. In addition, a self-hardening filler injection pipe 26 and an extrusion piston 27 is provided with a space 109 in which none is arranged. FIG. 25 is a diagram showing a section taken along the line h′-h ′ in FIG.
The end plate 110 is arranged at the tail of the excavator S09.
The structure is such that it does not penetrate into p '. If the self-hardening filler keeps sufficient fluidity, the pressure of the self-hardening filler propagates far away, so that all of the self-hardening filler filling space 101 is filled with the self-hardening filler as in the above embodiment. It is not necessary to form only the injection part 103 and the piston chamber 104, and the self-hardening filler filling space 101 may have a configuration as shown in FIG.
【0090】さらに、図26に示すものは、シールド掘
削機Sp’を、矩形トンネルを構築するための矩形シー
ルド機として構成した場合の図である。図24と同様
に、ここでも自硬性充填材充填空間部101の構成のみ
が示されている。図22および図24と同様に、自硬性
充填材充填空間部101は、シリンダ部材105によっ
てピストン室104が形成され、互いに隣接するピスト
ン室104,104間の空間が自硬性充填材注入部10
3とされて構成されている。さらに、この場合にも、図
24に示したものと同様に、自硬性充填材充填空間部1
01を自硬性充填材注入管26および押し出しピストン
27のいずれもが配置されない空間109を備えたもの
とすることも可能である。Further, FIG. 26 shows a case where the shield excavator Sp 'is configured as a rectangular shield machine for constructing a rectangular tunnel. As in FIG. 24, here, only the configuration of the self-hardening filler filling space 101 is shown. Similarly to FIGS. 22 and 24, in the self-hardening filler filling space 101, a piston chamber 104 is formed by a cylinder member 105, and the space between the adjacent piston chambers 104, 104 is formed by the self-hardening filler injecting part 10.
3 is configured. Further, also in this case, as in the case shown in FIG.
01 may be provided with a space 109 in which neither the self-hardening filler injection pipe 26 nor the pushing piston 27 is disposed.
【0091】また、図27に示すものは、円形シールド
で、かつ自硬性充填材を打設する部分の覆工厚が厚い場
合に用いるシールド掘削機Sp’として構成した場合の
図である。このシールド掘削機Sp’では、スキンプレ
ート1のテール部の内側に、自硬性充填材充填空間部1
01が型枠4と周壁Twとの間の空間に対して連通状態
に形成されている。この自硬性充填材充填空間部101
は、自硬性充填材注入部103と、断面視円形のシリン
ダ部材112によって形成されたピストン室104と
が、スキンプレート1の周方向において交互に配設され
た構成からなっている。自硬性充填材注入部103は、
互いに隣接するピストン室104,104間に配設さ
れ、この自硬性充填材注入部103には自硬性充填材注
入管26が配されている。図28(a)および(b)に
示すように、このシールド掘削機Sp’には、スキンプ
レート1のテール部の内側にエンドプレート113が設
けられており、シリンダ部材112および自硬性充填材
注入管26は、このエンドプレート113の所定位置に
形成された孔114に固定されている。このように、自
硬性充填材の覆工厚が厚い場合等には、シリンダ部材1
12を筒状とし、これをエンドプレート113等を介し
てスキンプレート1に一体に固定する構成としても良
い。FIG. 27 shows a case where the shield excavator Sp 'is a circular shield and is used when the lining thickness of the portion where the self-hardening filler is to be cast is thick. In this shield excavator Sp ′, the self-hardening filler filling space 1 is provided inside the tail of the skin plate 1.
01 is formed in communication with the space between the mold 4 and the peripheral wall Tw. This self-hardening filler filling space 101
The self-hardening filler injecting portion 103 and the piston chamber 104 formed by the cylinder member 112 having a circular cross section when viewed from the outside are alternately arranged in the circumferential direction of the skin plate 1. The self-hardening filler injecting section 103
The self-hardening filler injection section 103 is provided between the piston chambers 104 adjacent to each other. As shown in FIGS. 28 (a) and (b), this shield excavator Sp ′ is provided with an end plate 113 inside the tail portion of the skin plate 1 to inject the cylinder member 112 and the self-hardening filler. The tube 26 is fixed to a hole 114 formed at a predetermined position of the end plate 113. Thus, when the lining thickness of the self-hardening filler is large, the cylinder member 1
It is also possible to adopt a configuration in which 12 is cylindrical and this is integrally fixed to the skin plate 1 via the end plate 113 and the like.
【0092】ところで、本出願人は、大断面トンネルを
構築するための技術として、例えば特願平9−2748
72号に示す技術を既に提案している。これは、図29
に示すように、例えば断面視略日字状のトンネル構造体
121を構築し、その内方に空間を形成するもので、こ
のトンネル構造体121は、断面視円形の円形シールド
トンネル122と、互いに平行な平面を有した平面シー
ルドトンネル123とが周方向交互に配置され、これら
がその一部を互いに重合させて一体化された構成からな
っている。各平面シールドトンネル123は、その内部
に組み上げる型枠(セグメント)124が、相対向する
2面が平板部124a,124aとされ、これら平板部
124aの両側の2面が、略円弧状の凹部124b,1
24bとなるよう構成された特殊なものである。By the way, the present applicant has proposed a technique for constructing a large-section tunnel, for example, Japanese Patent Application No. 9-2748.
No. 72 has already been proposed. This is shown in FIG.
As shown in the figure, for example, a tunnel structure 121 having a substantially Japanese character in cross section is constructed, and a space is formed inside the tunnel structure 121. The tunnel structure 121 has a circular shield tunnel 122 having a circular cross section and Planar shield tunnels 123 having parallel planes are alternately arranged in the circumferential direction, and these are configured to be integrated by partially overlapping each other. In each plane shield tunnel 123, a formwork (segment) 124 assembled therein has two opposing surfaces as flat plate portions 124a, 124a. , 1
24b.
【0093】本発明に係る技術は、このような大断面ト
ンネルを構成する平面シールドトンネル123の構築に
際して用いるシールド掘削機Sp”にも適用が可能であ
り、図30に示すように、シールド掘削機Sp”は、断
面視矩形のスキンプレート1内で組み上げる特殊形状の
型枠124の凹部124bと周壁Twの間の空間に自硬
性充填材充填空間部125が形成されている。この自硬
性充填材充填空間部125は、自硬性充填材注入部10
3と、断面視円形のシリンダ部材112によって形成さ
れたピストン室104とが、スキンプレート1の周方向
に互いに隔てられて配設された構成からなっている。自
硬性充填材注入部103には自硬性充填材注入管26が
配されている。図28(a)および(b)に示したよう
に、このシールド掘削機Sp”には、スキンプレート1
のテール部の内側に自硬性充填材充填空間部125に対
応したエンドプレート126が設けられており、シリン
ダ部材112および自硬性充填材注入管26は、このエ
ンドプレート126の所定位置に形成された孔127に
固定されている。このように、自硬性充填材の覆工部分
の形状が特殊である場合にも、シリンダ部材112を、
エンドプレート126等を介してスキンプレート1に一
体に固定する構成としても良い。The technique according to the present invention is also applicable to a shield excavator Sp ″ used for constructing a flat shield tunnel 123 constituting such a large-section tunnel. As shown in FIG. In Sp ″, a self-hardening filler filling space portion 125 is formed in a space between the concave portion 124b of the specially-shaped mold frame 124 assembled in the skin plate 1 having a rectangular cross section and the peripheral wall Tw. The self-hardening filler filling space 125 is provided in the self-hardening filler injecting section 10.
3 and a piston chamber 104 formed by a cylinder member 112 having a circular cross section as viewed in the circumferential direction of the skin plate 1. The self-hardening filler injection section 103 is provided with a self-hardening filler injection pipe 26. As shown in FIGS. 28A and 28B, this shield excavator Sp ″ has a skin plate 1
An end plate 126 corresponding to the self-hardening filler filling space 125 is provided inside the tail of the cylinder member 112, and the cylinder member 112 and the self-hardening filler injection pipe 26 are formed at predetermined positions of the end plate 126. It is fixed to the hole 127. As described above, even when the shape of the lining portion of the self-hardening filler is special, the cylinder member 112 is
It may be configured to be integrally fixed to the skin plate 1 via the end plate 126 or the like.
【0094】また、上記第一および第二の実施の形態に
おいて、図9に示したような上記実施の形態の自硬性充
填材注入管26の断面形状を図31や図32のようにし
ても差し支えない。このように、自硬性充填材注入管2
6の断面を楕円形や長方形のような偏平な形状とするこ
とにより、図9に示した円形の場合の流路49と同一あ
るいはそれ以上の断面積を確保しながら、スキンプレー
ト1と内筒10との間の幅寸法を縮小することができ、
これによりトンネルTの覆工厚さを低減して、トンネル
Tの掘削断面積を縮小化することができる。また、自硬
性充填材注入管26を、長方形の形状とした場合には、
硬化後の自硬性充填材を取り出すときに便利なように、
図32に示すように、その内部にテーパー部68を設け
ておくのが好適である。また、図32において示した自
硬性充填材注入管26を構成する半割体48,48とし
ては、溝型鋼を使用することが好適である。Further, in the first and second embodiments, the cross-sectional shape of the self-hardening filler injection pipe 26 of the above embodiment as shown in FIG. 9 may be changed as shown in FIGS. 31 and 32. No problem. Thus, the self-hardening filler injection pipe 2
6 is formed into a flat shape such as an elliptical shape or a rectangular shape, thereby ensuring the same or larger cross-sectional area as the flow path 49 in the case of the circular shape shown in FIG. The width dimension between 10 and can be reduced,
Thereby, the lining thickness of the tunnel T can be reduced, and the excavated cross-sectional area of the tunnel T can be reduced. Further, when the self-hardening filler injection pipe 26 is formed in a rectangular shape,
As convenient when taking out the self-hardening filler after curing,
As shown in FIG. 32, it is preferable to provide a tapered portion 68 in the inside. It is preferable to use channel steel as the half bodies 48, 48 constituting the self-hardening filler injection pipe 26 shown in FIG.
【0095】なお、図31や図32に示すように自硬性
充填材注入管26を形成する場合、自硬性充填材注入管
26を全てに渡って偏平な形状とする必要はなく、自硬
性充填材注入部に挿通される部分だけを図31、図32
に示すような形状とすればよい。この場合、自硬性充填
材注入部に挿通される部分以外を、通常の円形断面によ
って構成し、徐々に断面を楕円形あるいは長方形に変化
させるようにすれば、断面が変化する部分での圧力損失
を防ぐことができる。また、このように自硬性充填材注
入管26を偏平断面とした場合には、円形断面に比較し
て自硬性充填材の圧力損失が大きくなるため、偏平断面
部においては、円形断面部よりも断面積を大きくするこ
とが好適である。When the self-hardening filler injection pipe 26 is formed as shown in FIGS. 31 and 32, the self-hardening filler injection pipe 26 does not need to have a flat shape over the entire body. FIGS. 31 and 32 show only the portion inserted into the material injection portion.
The shape may be as shown in FIG. In this case, if a portion other than the portion inserted into the self-hardening filler injection portion is formed by a normal circular cross section, and the cross section is gradually changed to an elliptical shape or a rectangular shape, the pressure loss at the portion where the cross section changes is obtained. Can be prevented. In addition, when the self-hardening filler injection pipe 26 has a flat cross section, the pressure loss of the self-hardening filler becomes larger as compared with the circular cross section. It is preferable to increase the cross-sectional area.
【0096】これ以外にも、本発明の主旨を逸脱しない
範囲内であれば、いかなる構成を採用しても良く、また
上記したような構成を適宜選択的に組み合わせたものと
しても良いのは言うまでもない。Other than this, any configuration may be adopted as long as it does not depart from the gist of the present invention, and it goes without saying that the above-described configurations may be appropriately combined selectively. No.
【0097】[0097]
【発明の効果】以上説明したように、請求項1に係るシ
ールド掘削機によれば、スキンプレートの内周面側に形
成された自硬性充填材充填空間部が、その周方向に互い
に隔てられた自硬性充填材注入部とピストン室とを備え
て構成されている。さらに、これらのうち、自硬性充填
材注入部には自硬性充填材注入管が、ピストン室には押
し出しピストンが配置された構成となっている。また、
請求項2に係るシールド掘削機によれば、自硬性充填材
充填空間部が、スキンプレートとスキンプレートのテー
ル部の内側に配置された内筒との間に形成されるととも
に、自硬性充填材注入部とピストン室とが、スキンプレ
ートおよび内筒を連結する複数の隔壁によって隔てられ
た構成となっている。本発明のシールド掘削機において
は、このように、自硬性充填材注入部とピストン室とが
分離されており、押し出しピストンに自硬性充填材打設
のための孔を設ける必要がなく、押し出しピストンにお
いて断面欠損が生じない。このため、従来と比較して、
押し出しピストンの構造的な強度が高められ、その結
果、押し出しピストンの幅を小さくして、トンネル覆工
の厚さ寸法を従来技術と比較して縮小化することができ
る。これにより、トンネルの掘削断面積を小さくして、
建設コストの低減化を図ることができる。As described above, according to the shield excavator according to the first aspect, the self-hardening filler filling spaces formed on the inner peripheral surface side of the skin plate are separated from each other in the circumferential direction. And a self-hardening filler injection section and a piston chamber. Further, among these, a self-hardening filler injection tube is arranged in the self-hardening filler injection part, and an extrusion piston is arranged in the piston chamber. Also,
According to the shield excavator according to claim 2, the self-hardening filler filling space is formed between the skin plate and the inner cylinder arranged inside the tail part of the skin plate, and the self-hardening filler is filled. The injection part and the piston chamber are configured to be separated by a plurality of partitions connecting the skin plate and the inner cylinder. In the shield excavator of the present invention, the self-hardening filler injecting section and the piston chamber are separated from each other as described above, and there is no need to provide a hole for driving the self-hardening filler in the extrusion piston, and the extrusion piston No cross-sectional defects occur. For this reason, compared to the past,
The structural strength of the extruded piston is increased, so that the width of the extruded piston can be reduced and the thickness of the tunnel lining can be reduced compared to the prior art. As a result, the excavation cross section of the tunnel is reduced,
Construction costs can be reduced.
【0098】請求項3に係るシールド掘削機によれば、
ピストン室が、その内壁面を形成するシリンダ部材をス
キンプレートの内周面に固定することによって形成さ
れ、互いに隣り合うシリンダ部材間の空間を自硬性充填
材注入部とした構成となっている。これにより、スキン
プレートのテール部に内筒を設けて二重構造とする必要
もなく、シールド掘削機の製作費を低減することが可能
となる。According to the shield excavator of the third aspect,
The piston chamber is formed by fixing a cylinder member that forms the inner wall surface to the inner peripheral surface of the skin plate, and has a configuration in which a space between adjacent cylinder members is a self-hardening filler injection portion. Accordingly, there is no need to provide an inner cylinder at the tail portion of the skin plate to form a double structure, and it is possible to reduce the manufacturing cost of the shield excavator.
【0099】請求項4に係るシールド掘削機において
は、自硬性充填材注入管が、スキンプレートに対して固
定される構成となっている。これにより、自硬性充填材
打設時や、シールド掘削機の掘進時においても、自硬性
充填材注入管がシールド掘削機の中を動くことがなく、
従来のシールド掘削機のように自硬性充填材打設管の移
動スペースを、その内部に開けておく必要がなくなる。
さらに、このシールド掘削機は、自硬性充填材注入管が
シールド掘削機の中を移動しないために、自硬性充填材
注入管をフレキシブルホースのような柔軟性をもった素
材により形成する必要がなく、従来のシールド掘削機の
ように、自硬性充填材打設時に、ホースが振れたりする
ような不具合が生じない。これらのことから、本発明に
よれば、使用性に優れたシールド掘削機が実現されるこ
ととなる。さらに、このシールド掘削機によれば、フレ
キシブルホースなどを用いた配管を用いた従来の装置に
比べて、管の配置や形状等が複雑になる懸念が少なくな
り、これにより、管の内部において自硬性充填材が詰ま
る心配も減少し、その信頼性も向上することとなる。[0099] In the shield excavator according to the fourth aspect, the self-hardening filler injection pipe is fixed to the skin plate. Thereby, even at the time of setting of the self-hardening filler material or at the time of excavation of the shield excavator, the self-hardening filler injection tube does not move in the shield excavator,
It is no longer necessary to provide a space for moving the self-hardening filler casting pipe inside, unlike a conventional shield excavator.
Further, in this shield excavator, since the self-hardening filler injection pipe does not move in the shield excavator, it is not necessary to form the self-hardening filler injection pipe from a flexible material such as a flexible hose. Unlike the conventional shield excavator, there is no such a problem that the hose swings when the self-hardening filler is poured. From these, according to the present invention, a shield excavator excellent in usability is realized. Furthermore, according to this shield excavator, there is less concern that the arrangement and shape of the pipes become complicated as compared with a conventional apparatus using a pipe using a flexible hose or the like. The concern that the hard filler is clogged is reduced, and the reliability is also improved.
【0100】請求項5に係るシールド掘削機を用いたト
ンネル覆工方法においては、シールド掘削機として、ス
キンプレートの内側の自硬性充填材充填空間部に、周壁
と型枠との間の空間に対して連通状態とされた自硬性充
填材注入部とピストン室とが形成され、さらに、ピスト
ン室の内部に、前後両方向にスライド自在とされる押し
出しピストンが配置されたものが用いられる。そして、
トンネルを掘進させる際には、ピストン室において押し
出しピストンにより打設自硬性充填材の押圧が行われる
とともに、自硬性充填材注入部において、自硬性充填材
注入管はスキンプレートと一体となって前進する。この
ように、本発明によれば、自硬性充填材注入管がシール
ド掘削機の中を動くことがないため、自硬性充填材注入
管の移動スペースを、シールド掘削機の内部に開けてお
く必要がなく、その内部空間を有効に利用することが可
能となる。さらに、本発明によれば、自硬性充填材注入
管をフレキシブルホースのような柔軟性をもった素材に
よって形成しておく必要がなくなり、自硬性充填材注入
管が振れたり、その配置や形状等が複雑になるなどの心
配がなく、さらに、管の内部において自硬性充填材が詰
まる心配も減少し、シールド掘削機の信頼性が向上する
こととなる。In the tunnel lining method using the shield excavator according to the fifth aspect, the shield excavator is provided in the space for filling the self-hardening filler inside the skin plate and in the space between the peripheral wall and the formwork. On the other hand, a self-hardening filler injection portion and a piston chamber which are in communication with each other are formed, and an extrusion piston slidable in both front and rear directions is disposed inside the piston chamber. And
When excavating the tunnel, the extruded piston presses the self-hardening filler in the piston chamber, and the self-hardening filler injection tube advances integrally with the skin plate at the self-hardening filler injection part. I do. As described above, according to the present invention, since the self-hardening filler injection pipe does not move in the shield excavator, it is necessary to open a moving space for the self-hardening filler injection pipe inside the shield excavator. And the internal space can be used effectively. Further, according to the present invention, it is not necessary to form the self-hardening filler injection tube from a material having flexibility such as a flexible hose, and the self-hardening filler injection tube oscillates, its arrangement, shape, and the like. There is no need to worry about complexity of the excavator, and further, there is less concern about clogging of the self-hardening filler inside the pipe, and the reliability of the shield excavator is improved.
【図1】 本発明の第一の実施の形態を模式的に示すシ
ールド掘削機の側断面図である。FIG. 1 is a side sectional view of a shield excavator schematically showing a first embodiment of the present invention.
【図2】 図1におけるI−I矢視断面図である。FIG. 2 is a sectional view taken along the line II in FIG.
【図3】 図1におけるII−II矢視断面図である。FIG. 3 is a sectional view taken along the line II-II in FIG.
【図4】 図3におけるA−A矢視断面図である。FIG. 4 is a sectional view taken along the line AA in FIG. 3;
【図5】 図4に示した押し出しピストンおよび圧力保
持ジャッキの制御機構を示す図である。FIG. 5 is a diagram showing a control mechanism of a pushing piston and a pressure holding jack shown in FIG. 4;
【図6】 図3におけるB−B矢視断面図である。FIG. 6 is a sectional view taken along the line BB in FIG. 3;
【図7】 図6におけるc−c矢視断面図である。FIG. 7 is a sectional view taken along the line cc in FIG. 6;
【図8】 図6におけるd−d矢視断面図である。8 is a sectional view taken along the line dd in FIG. 6;
【図9】 図6におけるe−e矢視断面図である。FIG. 9 is a sectional view taken along the line ee in FIG. 6;
【図10】 図6におけるf−f矢視断面図である。10 is a sectional view taken along the line ff in FIG. 6;
【図11】 図6におけるg−g矢視断面図である。11 is a sectional view taken along the line gg in FIG. 6;
【図12】 本発明のシールド掘削機を用いたトンネル
の施工手順を示す側断面図であって、(a)は、シール
ド掘削機におけるピストン室の近傍を示す図、(b)
は、同、自硬性充填材注入部の近傍を示す図である。FIGS. 12A and 12B are side sectional views showing a procedure for constructing a tunnel using the shield excavator of the present invention, wherein FIG. 12A is a view showing the vicinity of a piston chamber in the shield excavator, and FIG.
FIG. 3 is a view showing the vicinity of a self-hardening filler injecting section.
【図13】 本発明のシールド掘削機を用いたトンネル
の施工手順を示す側断面図であって、(a)は、シール
ド掘削機におけるピストン室の近傍を示す図、(b)
は、同、自硬性充填材注入部の近傍を示す図である。FIGS. 13A and 13B are side sectional views showing a procedure for constructing a tunnel using the shield excavator of the present invention, wherein FIG. 13A is a view showing the vicinity of a piston chamber in the shield excavator, and FIG.
FIG. 3 is a view showing the vicinity of a self-hardening filler injecting section.
【図14】 本発明のシールド掘削機を用いたトンネル
の施工手順を示す側断面図であって、(a)は、シール
ド掘削機におけるピストン室の近傍を示す図、(b)
は、同、自硬性充填材注入部の近傍を示す図である。FIG. 14 is a side sectional view showing a procedure for constructing a tunnel using the shield excavator of the present invention, wherein (a) is a view showing the vicinity of a piston chamber in the shield excavator, and (b).
FIG. 3 is a view showing the vicinity of a self-hardening filler injecting section.
【図15】 本発明のシールド掘削機を用いたトンネル
の施工手順を示す側断面図であって、(a)は、シール
ド掘削機におけるピストン室の近傍を示す図、(b)
は、同、自硬性充填材注入部の近傍を示す図である。FIG. 15 is a side sectional view showing a procedure for constructing a tunnel using the shield excavator of the present invention, wherein (a) is a view showing the vicinity of a piston chamber in the shield excavator, and (b).
FIG. 3 is a view showing the vicinity of a self-hardening filler injecting section.
【図16】 本発明の他の実施の形態を示す図であっ
て、本発明のシールド掘削機を、覆工壁に鉄筋が配筋さ
れないトンネルの構築に用いた場合の側断面図である。FIG. 16 is a view showing another embodiment of the present invention, and is a side cross-sectional view when the shield excavator of the present invention is used for constructing a tunnel in which a reinforcing bar is not arranged on a lining wall.
【図17】 図16に示したテールシールを拡大して示
した側断面図である。FIG. 17 is an enlarged side sectional view of the tail seal shown in FIG. 16;
【図18】 本発明の第一の実施の形態の他の一例を示
す図であって、上記第一の実施の形態における自硬性充
填材充填空間部の構成を変更した場合を示す立断面図で
ある。FIG. 18 is a view showing another example of the first embodiment of the present invention, and is an elevational sectional view showing a case where the configuration of the self-hardening filler filling space in the first embodiment is changed. It is.
【図19】 図18におけるh−h矢視断面図である。FIG. 19 is a sectional view taken along the line hh in FIG. 18;
【図20】 本発明の第一の実施の形態の他の一例を示
す図であって、本発明のシールド掘削機を、矩形シール
ド掘削機として構成した場合の自硬性充填材充填空間部
の状態を示す立断面図である。FIG. 20 is a view showing another example of the first embodiment of the present invention, and shows a state of a self-hardening filler filling space portion when the shield excavator of the present invention is configured as a rectangular shield excavator. FIG.
【図21】 本発明の第二の実施の形態を模式的に示す
シールド掘削機の側断面図である。FIG. 21 is a side sectional view of a shield excavator schematically showing a second embodiment of the present invention.
【図22】 前記シールド掘削機の自硬性充填材充填空
間部を示す立断面図である。FIG. 22 is an elevational sectional view showing a self-hardening filler filling space portion of the shield excavator.
【図23】 図22における(a)A’−A’矢視断面
図、(b)B’−B’矢視断面図である。23A is a cross-sectional view taken along the line A′-A ′ in FIG. 22, and FIG. 23B is a cross-sectional view taken along the line B′-B ′ in FIG.
【図24】 本発明の他の実施の形態を示す図であっ
て、上記第二の実施の形態における自硬性充填材充填空
間部の構成を変更した場合を示す立断面図である。FIG. 24 is a view showing another embodiment of the present invention, and is an elevational sectional view showing a case where the configuration of the self-hardening filler filling space in the second embodiment is changed.
【図25】 図24におけるh’−h’矢視断面図であ
る。FIG. 25 is a sectional view taken along the line h′-h ′ in FIG. 24;
【図26】 本発明の第二の実施の形態の他の一例を示
す図であって、本発明のシールド掘削機を、矩形シール
ド掘削機として構成した場合の自硬性充填材充填空間部
の状態を示す立断面図である。FIG. 26 is a view showing another example of the second embodiment of the present invention, and shows a state of a self-hardening filler filling space when the shield excavator of the present invention is configured as a rectangular shield excavator. FIG.
【図27】 同、本発明のシールド掘削機を、覆工厚の
厚い円形シールドトンネルを構築するためのシールド掘
削機として構成した場合の自硬性充填材充填空間部の状
態を示す立断面図である。FIG. 27 is an elevational sectional view showing a state of a self-hardening filler filling space when the shield excavator of the present invention is configured as a shield excavator for constructing a circular shield tunnel having a thick lining; is there.
【図28】 図27における(a)A”−A”矢視断面
図、(b)B”−B”矢視断面図である。28A is a sectional view taken along the line A ″ -A ″ in FIG. 27, and FIG. 28B is a sectional view taken along the line B ″ -B ″ in FIG.
【図29】 本発明の第二の実施の形態のさらに他の一
例を示す図であって、本発明のシールド掘削機を適用し
て構築する大断面トンネルの一例を示す立断面図であ
る。FIG. 29 is a view showing still another example of the second embodiment of the present invention, and is an elevational sectional view showing an example of a large-section tunnel constructed by applying the shield excavator of the present invention.
【図30】 同、本発明のシールド掘削機を、図29に
示したトンネルを構築するためのシールド掘削機として
構成した場合の自硬性充填材充填空間部の状態を示す半
立断面図である。30 is a half-standing sectional view showing the state of the self-hardening filler filling space when the shield excavator of the present invention is configured as a shield excavator for constructing the tunnel shown in FIG. 29. .
【図31】 本発明の他の実施の形態を示す図であっ
て、本発明のシールド掘削機における自硬性充填材注入
管の構成を上記実施の形態から変更した場合の例を示す
断面図である。FIG. 31 is a view showing another embodiment of the present invention, and is a cross-sectional view showing an example in which the configuration of the self-hardening filler injection pipe in the shield excavator of the present invention is changed from the above embodiment. is there.
【図32】 本発明の他の実施の形態を示す図であっ
て、本発明のシールド掘削機における自硬性充填材注入
管の構成を上記実施の形態から変更した場合の例を示す
断面図である。FIG. 32 is a view showing another embodiment of the present invention, and is a cross-sectional view showing an example in which the configuration of the self-hardening filler injection pipe in the shield excavator of the present invention is changed from the above-described embodiment. is there.
【図33】 本発明の従来の技術を示すための図であっ
て、ECL工法を用いてトンネルを構築する際に用いら
れるシールド掘削機を示す側断面図である。FIG. 33 is a view showing a conventional technique of the present invention, and is a side cross-sectional view showing a shield excavator used when constructing a tunnel using the ECL method.
【図34】 同、正面図である。FIG. 34 is a front view of the same.
【図35】 本発明の従来の技術を示すための図であっ
て、上記シールド掘削機を用いてトンネルを構築する際
の手順を示すための側断面図である。FIG. 35 is a view showing a conventional technique of the present invention, and is a side sectional view showing a procedure for constructing a tunnel using the shield excavator.
【図36】 本発明の従来の技術を示すための図であっ
て、上記シールド掘削機を用いてトンネルを構築する際
の手順を示すための側断面図である。FIG. 36 is a view showing a conventional technique of the present invention, and is a side sectional view showing a procedure for constructing a tunnel using the shield excavator.
【図37】 本発明の従来の技術を示すための図であっ
て、上記シールド掘削機を用いてトンネルを構築する際
の手順を示すための側断面図である。FIG. 37 is a view showing a conventional technique of the present invention, and is a side sectional view showing a procedure for constructing a tunnel using the shield excavator.
J 地山 W,W’ トンネル覆工壁 Po 自硬性充填材圧力 Pj 地山圧力 Sp,Sp’,Sp” シールド掘削機 Tw 周壁 1 スキンプレート 2 カッター装置 4,124 型枠 10 内筒 21,101,125 自硬性充填材充填空間部 23,103 自硬性充填材注入部 24,104 ピストン室 26 自硬性充填材注入管 27 押し出しピストン 28 圧力保持ジャッキ 105,112 シリンダ部材 J Chiyama W, W 'Tunnel lining wall Po Self-hardening filler pressure Pj Chiyama pressure Sp, Sp', Sp "Shield excavator Tw Perimeter wall 1 Skin plate 2 Cutter device 4, 124 Formwork 10 Inner cylinder 21, 101 , 125 Self-hardening filler filling space 23, 103 Self-hardening filler injecting part 24, 104 Piston chamber 26 Self-hardening filler injecting pipe 27 Extruding piston 28 Pressure holding jack 105, 112 Cylinder member
───────────────────────────────────────────────────── フロントページの続き (72)発明者 竹中 久 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 浦田 修 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 関 伸司 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Hisashi Takenaka 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation (72) Inventor Osamu Urata 1-2-3 Shibaura, Minato-ku, Tokyo Shimizu Corporation (72) Inventor Shinji Seki 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation
Claims (5)
掘削された地盤の周壁を所定の間隔を空けて型枠により
覆い、該型枠と前記周壁との間に自硬性充填材を充填
し、前記周壁の内面を覆工するためのシールド掘削機で
あって、 該シールド掘削機のスキンプレートの内周面側には、自
硬性充填材充填空間部が、前記周壁と前記型枠との間の
空間に対向するよう形成され、 該自硬性充填材充填空間部は、自硬性充填材注入部とピ
ストン室とを前記スキンプレートの周方向に互いに隔て
られて備えた構成とされ、 該ピストン室の内部には、前後両方向にスライド自在と
されるとともに、前記スキンプレート側に固定された圧
力保持ジャッキによって駆動される押し出しピストンが
配置され、 該自硬性充填材注入部の内部には、自硬性充填材注入管
が配置されることを特徴とするシールド掘削機。1. Excavating the ground with a cutter at the tip and covering a peripheral wall of the ground excavated with a form at a predetermined interval, filling a self-hardening filler between the form and the peripheral wall, A shield excavator for lining an inner surface of the peripheral wall, wherein a self-hardening filler filling space portion is provided between the peripheral wall and the formwork on an inner peripheral surface side of a skin plate of the shield excavator. The self-hardening filler filling space portion is configured to include a self-hardening filler injecting portion and a piston chamber separated from each other in a circumferential direction of the skin plate, and the piston chamber Inside, a pushing piston which is slidable in both front and rear directions and is driven by a pressure holding jack fixed to the skin plate side is arranged. Inside the self-hardening filler injection part, a self-hardening filler is provided. Filling material injection Shield excavator, characterized in that the tubes are arranged.
て、 前記自硬性充填材充填空間部が、前記スキンプレートと
該スキンプレートのテール部の内側に配置された内筒と
の間に形成されるとともに、 前記自硬性充填材注入部と前記ピストン室とが、前記ス
キンプレートおよび前記内筒を連結する複数の隔壁によ
って前記スキンプレートの周方向に隔てられてなること
を特徴とするシールド掘削機。2. The shield excavator according to claim 1, wherein the self-hardening filler filling space is formed between the skin plate and an inner cylinder disposed inside a tail portion of the skin plate. Wherein the self-hardening filler injection section and the piston chamber are separated in a circumferential direction of the skin plate by a plurality of partitions connecting the skin plate and the inner cylinder. Machine.
て、前記ピストン室の内壁面を形成するシリンダ部材が
前記スキンプレートの内周面に一体に固定されることに
よって前記ピストン室が形成され、互いに隣り合う前記
ピストン室の間の空間が、前記自硬性充填材注入部とさ
れていることを特徴とするシールド掘削機。3. The shield excavator according to claim 1, wherein said piston chamber is formed by integrally fixing a cylinder member forming an inner wall surface of said piston chamber to an inner peripheral surface of said skin plate. And a space between the piston chambers adjacent to each other is the self-hardening filler injecting section.
ールド掘削機であって、前記自硬性充填材注入管は、前
記スキンプレートに対して固定されていることを特徴と
するシールド掘削機。4. The shield excavator according to claim 1, wherein the self-hardening filler injection pipe is fixed to the skin plate. .
地盤を掘削しつつ掘削された地盤の周壁を所定の間隔を
空けて型枠により覆い、該型枠と前記周壁との間に自硬
性充填材を充填し、前記周壁の内面を覆工するシールド
掘削機を用いたトンネル覆工方法であって、 該シールド掘削機として、スキンプレートの内周面側
に、前記周壁と前記型枠との間の空間に対向するよう自
硬性充填材充填空間部を形成し、該自硬性充填材充填空
間部に、自硬性充填材注入部とピストン室とを形成する
とともに、該ピストン室の内部に、前後両方向にスライ
ド自在とされる押し出しピストンを配置したものを用
い、 前記自硬性充填材注入部の内部に、自硬性充填材注入管
を配置するとともに、該自硬性充填材注入管を前記スキ
ンプレート側に固定しておき、 トンネルを掘進するに際し、前記押し出しピストンを後
方に移動させて、前記周壁と前記型枠との間の空間に対
して前記自硬性充填材注入管から注入充填された自硬性
充填材を加圧しつつ、 前記自硬性充填材注入管と前記スキンプレートとを一体
的に前進させることを特徴とするシールド掘削機を用い
たトンネル覆工方法。5. Excavating the ground with a cutter at the tip of a shield excavator and covering a peripheral wall of the excavated ground with a form at a predetermined interval, and a self-hardening filler material between the form and the peripheral wall. And a tunnel lining method using a shield excavator for lining the inner surface of the peripheral wall, wherein the shield excavator is provided between the peripheral wall and the formwork on the inner peripheral surface side of a skin plate. A self-hardening filler filling space portion is formed so as to face the space, and a self-hardening filler injecting portion and a piston chamber are formed in the self-hardening filler filling space portion. Using an extrusion piston that is slidable in both directions, a self-hardening filler injection pipe is arranged inside the self-hardening filler injection part, and the self-hardening filler injection pipe is placed on the skin plate side. Fixed to When excavating the tunnel, moving the extrusion piston backward to pressurize the self-hardening filler injected from the self-hardening filler injection pipe into the space between the peripheral wall and the formwork. A tunnel lining method using a shield excavator, wherein the self-hardening filler injection pipe and the skin plate are integrally advanced.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33213897A JP3750040B2 (en) | 1997-03-26 | 1997-12-02 | Shield excavator and tunnel lining method using the same |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9-74179 | 1997-03-26 | ||
JP7417997 | 1997-03-26 | ||
JP33213897A JP3750040B2 (en) | 1997-03-26 | 1997-12-02 | Shield excavator and tunnel lining method using the same |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH10325299A true JPH10325299A (en) | 1998-12-08 |
JP3750040B2 JP3750040B2 (en) | 2006-03-01 |
Family
ID=26415311
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP33213897A Expired - Lifetime JP3750040B2 (en) | 1997-03-26 | 1997-12-02 | Shield excavator and tunnel lining method using the same |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3750040B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009121099A (en) * | 2007-11-13 | 2009-06-04 | Ohbayashi Corp | Cast-in-place lining shield method and shield machine |
JP2009144425A (en) * | 2007-12-14 | 2009-07-02 | Tekken Constr Co Ltd | Shield method by direct placing concrete lining |
JP2014111898A (en) * | 2014-03-28 | 2014-06-19 | Penta Ocean Construction Co Ltd | Device and method for injecting filler |
-
1997
- 1997-12-02 JP JP33213897A patent/JP3750040B2/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009121099A (en) * | 2007-11-13 | 2009-06-04 | Ohbayashi Corp | Cast-in-place lining shield method and shield machine |
JP2009144425A (en) * | 2007-12-14 | 2009-07-02 | Tekken Constr Co Ltd | Shield method by direct placing concrete lining |
JP2014111898A (en) * | 2014-03-28 | 2014-06-19 | Penta Ocean Construction Co Ltd | Device and method for injecting filler |
Also Published As
Publication number | Publication date |
---|---|
JP3750040B2 (en) | 2006-03-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6252842B2 (en) | Construction method of outer shield tunnel | |
JP2007191979A (en) | Element, element joining structure, and element joining method | |
JPH10325299A (en) | Shield excavation machine and tunnel-lining method by using the same | |
JP3765045B2 (en) | Shield tunnel construction method | |
JP3154029B2 (en) | Lining method of shield tunnel | |
JPH11270299A (en) | Large-diametral tunnel and its construction method and shield machine used therefor | |
JPH08144687A (en) | Pipe and pipe loop method by use the same | |
JP2000257392A (en) | Water stopping form and method for constructing tunnel using the same | |
JPH0194199A (en) | Method of constructing concrete lining body into ground and segment containing coarse aggregate used for said construction | |
JP3332507B2 (en) | How to build underground structures | |
JP4829593B2 (en) | Shield machine and shield method using the same | |
JP2990045B2 (en) | Shield machine | |
JPH0462299A (en) | Larger section tunnel and construction method thereof | |
JPH04258495A (en) | Lining work of shield tunnel | |
JPH04247200A (en) | Lining process for shielded tunnel | |
JPH0423994Y2 (en) | ||
JP3783120B2 (en) | Start method of shield excavator | |
JP2002106282A (en) | Construction method for widened tunnel | |
JPH11107690A (en) | Shield excavator and method of lining tunnel | |
JPH04155092A (en) | Joining of tunnel | |
JPH06280470A (en) | Construction method for underground structure | |
JPH10184285A (en) | End form in shield machine | |
JPH04250294A (en) | Lining method of shield tunnel and device thereof | |
JPH08135386A (en) | Lining method of shield tunnel and shield machine | |
JP2002213195A (en) | Tunnel constructing method and shield excavator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20051013 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20051025 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20051122 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111216 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111216 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121216 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121216 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131216 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131216 Year of fee payment: 8 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131216 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141216 Year of fee payment: 9 |
|
EXPY | Cancellation because of completion of term |