JP2005090109A - Erection method of bridge, and upper work unit for bridge - Google Patents

Erection method of bridge, and upper work unit for bridge Download PDF

Info

Publication number
JP2005090109A
JP2005090109A JP2003325971A JP2003325971A JP2005090109A JP 2005090109 A JP2005090109 A JP 2005090109A JP 2003325971 A JP2003325971 A JP 2003325971A JP 2003325971 A JP2003325971 A JP 2003325971A JP 2005090109 A JP2005090109 A JP 2005090109A
Authority
JP
Japan
Prior art keywords
floor slab
bridge
superstructure
steel
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2003325971A
Other languages
Japanese (ja)
Inventor
Yoshihisa Toyama
義久 遠山
Yoichi Kobayashi
洋一 小林
Hiroshi Kasai
寛 河西
Naoki Tomizawa
直樹 富澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Konoike Construction Co Ltd
Original Assignee
Sumitomo Metal Industries Ltd
Konoike Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd, Konoike Construction Co Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP2003325971A priority Critical patent/JP2005090109A/en
Publication of JP2005090109A publication Critical patent/JP2005090109A/en
Withdrawn legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide an erection method of a bridge and an upper work unit for the bridge for erecting the bridge in a place where a sufficient working yard cannot be secured around, like a bridge laid over a road, a track or a river. <P>SOLUTION: The whole length of a steel floor slab girder 1 is constructured by gradually stretching the steel floor slab girder 1 in an erected direction while constructing it. The steel floor slab girder 1 is constructed of a central floor slab part 1A and side floor slab parts 1B, 1B located on both sides, in an orthogonal direction to the erected direction. The side floor slab parts 1B, 1B are connected to both side parts of the central floor slab part 1A so that they can be rotated respectively in the orthogonal direction to the erected direction and bent onto the upper side of the central floor slab part 1A. The steel floor slab girder 1 is stretched in a state of the side floor slab parts 1B, 1B being bent to the upper side of the central floor slab part 1A. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本願発明は、例えば道路や線路、あるいは河川などの上に架け渡される橋梁のように、周囲に充分な作業ヤードを確保できない場所に橋梁を架設する橋梁の架設工法および橋梁の上部工ユニットに関するものである。   The present invention relates to a bridge construction method and a bridge superstructure unit for constructing a bridge in a place where a sufficient work yard cannot be secured around, such as a bridge over a road, a railroad, or a river. It is.

例えば、道路の上に高架橋を架け渡す場合、桁下空間は歩行者や車両の往来があり、桁下空間に充分な作業空間を確保できない。   For example, when a viaduct is bridged over a road, there is a traffic of pedestrians and vehicles in the underarm space, and a sufficient work space cannot be secured in the underarm space.

このような場合の橋桁の架設工法として、道路の片側または両側で橋桁をブロック状に構築しながら、道路の上に徐々に送り出して橋桁の全長を構築する送り出し工法が一般に知られている。   As a construction method of the bridge girder in such a case, a feeding construction method is generally known in which the bridge girder is constructed in a block shape on one side or both sides of the road and is gradually fed onto the road to construct the full length of the bridge girder.

本工法は歩行者や車両の通行を規制したり、工事を歩行者や車両の少ない深夜などに限定する必要がない等のメリットがある。   This construction method has the merits of restricting the traffic of pedestrians and vehicles and not having to limit the construction to midnight with few pedestrians and vehicles.

なお、河川などに応急的に架設される橋梁の架設工法として、橋梁の上部工を架設方向と直交する方向に折り畳めるように構築された応急橋が知られている(特許文献1)
特開平7−259015号公報
In addition, as an erection method of a bridge that is erected on a river or the like, an emergency bridge that is constructed so that the upper part of the bridge is folded in a direction orthogonal to the erection direction is known (Patent Document 1).
Japanese Patent Laid-Open No. 7-259015

しかし、送り出し工法は、手延べ機の設置・撤去、台車等の仮設備や地組みするためのクレーンの配置等のための施工ヤードとしてかなり広いスペースを確保する必要がある等の課題があった。   However, the delivery method has problems such as the need to secure a fairly large space as a construction yard for the installation and removal of hand-rollers, temporary equipment such as carts, and the placement of cranes for grounding. .

また、ブロック状に構築した上部工を順次道路の上に送り出して上部工の全長を構築するため、上部工の構築と送り出しとを交互に行う必要があり、このため工事が煩雑化するだけでなく、施工管理が面倒である等の課題があった。   Also, since the superstructure constructed in blocks is sent out sequentially onto the road to construct the full length of the superstructure, it is necessary to alternately construct and send the superstructure, which only complicates the construction. However, there were problems such as troublesome construction management.

また、特許文献1に記載された応急橋は、上部工の吊り上げおよび吊り下ろしと同時に、上部工を自動的にかつ安全に展開および折り畳みできるように構成されたもので、送り出し工法に適用できるものではない。   The emergency bridge described in Patent Document 1 is constructed so that the superstructure can be automatically and safely expanded and folded at the same time as the superstructure is lifted and suspended, and can be applied to the feeding method. is not.

請求項1記載の橋梁の架設工法は、橋梁の上部工を構築しながら架設方向に徐々に送り出して前記上部工の全長を構築する橋梁の架設工法において、前記上部工をその架設方向と直交する方向に折り曲げて送り出すことを特徴とするものである。   The bridge erection method according to claim 1 is a bridge erection method in which a bridge superstructure is constructed by constructing a bridge superstructure and gradually sending it out in the erection direction to construct the entire length of the superstructure. It is characterized by being bent in a direction and sent out.

本願発明は、特に橋梁の上部工をその架設方向と直交する方向に折り曲げて(上部工の幅方向端部を折り曲げて)架設方向に送り出すことにより、周囲に充分な作業ヤードを確保できないような場所であっても、周辺環境に悪影響を与えることなく、きわめて短期間でかつ効率的に橋梁を架設することができるものである。   In the present invention, in particular, it is not possible to secure a sufficient work yard around the bridge by bending the superstructure of the bridge in a direction perpendicular to the installation direction (bending the widthwise end of the superstructure) and sending it out in the installation direction. Even in places, bridges can be erected in a very short period of time without adversely affecting the surrounding environment.

なお、この場合の上部工としては、例えばH形鋼などからなる複数の主桁と横梁とからなる躯体の上に床鋼板を敷設する等して構築される鋼床版桁が軽量でかつ施工性にすぐれているが、施工的に可能であれば、使用材料により鉄筋コンクリート桁、構造形式によりトラス桁などであってもよい。   In this case, as the superstructure, for example, a steel floor slab girder constructed by laying a floor steel plate on a frame consisting of a plurality of main girders made of H-shaped steel or the like and a cross beam is light and constructed. Although it is excellent in performance, a reinforced concrete girder may be used depending on the material used, and a truss girder may be used depending on the structure if it is possible in terms of construction.

請求項2記載の橋梁の上部工ユニットは、橋梁の上部工を構築しながら架設方向に徐々に送り出して前記上部工の全長が構築される橋梁に用いられる橋梁の上部工ユニットであって、前記橋梁の架設方向と直交する方向に中央床版部とその両側に位置する側床版部とから構成され、かつ前記側床版部は前記中央床版部の側部に架設方向と直交する方向に折り曲げ可能に連結されてなることを特徴とするものである。   The bridge superstructure unit according to claim 2 is a bridge superstructure unit used for a bridge in which the overall length of the superstructure is constructed by gradually sending out in the erection direction while constructing the bridge superstructure, It is composed of a central floor slab portion and side floor slab portions located on both sides thereof in a direction orthogonal to the bridge erection direction, and the side floor slab portion is perpendicular to the erection direction on the side of the central floor slab portion. It is connected to be able to be bent.

本願発明の場合、例えば中央床版部の両側部にそれぞれ側床版部を架設方向と直交する方向に回転自在に連結することにより、側床版部を架設方向と直交する方向に折り曲げ可能な構造とすることができる。   In the case of the present invention, for example, the side floor slab portion can be bent in a direction orthogonal to the installation direction by connecting the side floor slab portion to both sides of the central floor slab portion in a direction orthogonal to the installation direction. It can be a structure.

請求項1記載の橋梁の架設工法は、橋梁の上部工を構築しながら架設方向に徐々に送り出して前記上部工の全長を構築する橋梁の架設工法において、特に前記上部工をその架設方向と直交する方向に折り曲げて送り出すことにより、作業ヤードとして必要な周囲のスペースを極力少なくすることができるとともに、周辺環境に悪影響を与えることなく、きわめて短期間でかつ効率的に橋梁を架設することができる。また、上部工を一時的に支えるベント等の支保工材の小型化、省力化をも図ることができる。   The bridge erection method according to claim 1 is a bridge erection method in which the entire length of the superstructure is constructed by gradually feeding it in the erection direction while constructing the superstructure of the bridge. In particular, the superstructure is orthogonal to the erection direction. By bending it in the direction to be sent out, the space required as a work yard can be reduced as much as possible, and a bridge can be erected in a very short period of time without adversely affecting the surrounding environment. . In addition, the support material such as a vent that temporarily supports the superstructure can be reduced in size and labor can be saved.

請求項2記載の橋梁の上部工ユニットは、橋梁の上部工を構築しながら架設方向に徐々に送り出して前記上部工の全長が構築される橋梁に用いられる橋梁の上部工ユニットであり、特に前記橋梁の架設方向と直交する方向に中央床版部とその両側に位置する側床版部とから構成され、かつ前記側床版部は前記中央床版部の側部に架設方向と直交する方向に折り曲げ可能に連結されて、ユニット化されているため、荷揚げ、組立ておよび送り出し等の作業をきわめて効率的に行うことができる。   The superstructure unit of a bridge according to claim 2 is a superstructure unit of a bridge used for a bridge in which the full length of the superstructure is constructed by gradually sending out in the construction direction while constructing the superstructure of the bridge, It is composed of a central floor slab portion and side floor slab portions located on both sides thereof in a direction orthogonal to the bridge erection direction, and the side floor slab portion is perpendicular to the erection direction on the side of the central floor slab portion. Since they are connected in a foldable manner and unitized, operations such as unloading, assembling and delivery can be performed very efficiently.

図1と図2は、本願発明の一例を示し、図1(a),(b)において、符号1は橋梁の上部工として構築された鋼床版桁、2は鋼床版桁1を支える下部工として構築された橋脚である。   1 and 2 show an example of the present invention. In FIGS. 1 (a) and 1 (b), reference numeral 1 denotes a steel deck slab constructed as a superstructure of a bridge, and 2 supports a steel deck slab 1. It is a pier constructed as a substructure.

鋼床版桁1は軽量でかつ施工性にすぐれ、H形鋼などからなる複数の主桁1aと横梁1bとかなる躯体の上に床鋼板1cを敷設し、さらに床鋼板1cの下面部に複数の補強リブ1dを突設することに構築され、一定長さのブロック状にユニット化されている。なお、床鋼板1cの上にはアスファルト舗装1eが施されている。   The steel slab girder 1 is light in weight and excellent in workability, and a floor steel plate 1c is laid on a frame made up of a plurality of main girders 1a and cross beams 1b made of H-shaped steel, etc. It is constructed by projecting the reinforcing rib 1d, and is unitized into a block of a certain length. In addition, asphalt pavement 1e is given on the floor steel plate 1c.

また、鋼床版桁1はその架設方向と直交する方向に中央床版部1Aとその両側に位置する側床版部1B,1Bとから構築され、側床版部1B,1Bは中央床版部1Aの両側部にそれぞれ架設方向と直交する方向に回転して中央床版部1Aの上側に折り曲げることが可能なように連結されている。   The steel floor slab girder 1 is constructed from a central floor slab portion 1A and side floor slab portions 1B, 1B located on both sides thereof in a direction orthogonal to the erection direction. The side floor slab portions 1B, 1B are central floor slabs. It is connected to both side portions of the portion 1A so as to be able to be bent to the upper side of the central floor slab portion 1A by rotating in the direction orthogonal to the installation direction.

また、中央床版部1Aと側床版部1B,1Bはそれぞれ現地に別々に搬入された後、現地にて仮組みされ、架設時、図1(b)に図示するように両側の側床版部1B,1Bは中央床版部1Aの上側に折り曲げられ、さらに橋脚2,2間に架け渡された後、図1(a)に図示するように両側の側床版部1B,1Bは中央床版部1Aの両側に水平に下ろされる構造になっている。   Further, the central floor slab part 1A and the side floor slab parts 1B and 1B are separately carried into the site and then temporarily assembled at the site, and when installed, as shown in FIG. After the plate portions 1B and 1B are bent to the upper side of the central floor plate portion 1A and further bridged between the piers 2 and 2, the side floor plate portions 1B and 1B on both sides as shown in FIG. It is structured to be lowered horizontally on both sides of the central floor slab portion 1A.

なお、この場合の中央床版部1Aは平行に配置された2本の主桁1a,1aの上に床鋼板1cを敷設することにより構築され、側床版部1B,1Bは1本の主桁1aの上に床鋼板1cを敷設することにより構築され、いずれも床鋼版1cの下面部に複数の補強リブ1eが突設されている。   In this case, the central floor slab portion 1A is constructed by laying a floor steel plate 1c on two main girders 1a, 1a arranged in parallel, and the side floor slab portions 1B, 1B are one main slab portion. It is constructed by laying a floor steel plate 1c on the girder 1a, and in each case, a plurality of reinforcing ribs 1e are projected from the lower surface of the floor steel plate 1c.

図2(a)〜(c)は鋼床版桁の架設工法を示し、図に基いて架設工法を説明する。   2 (a) to 2 (c) show a construction method of a steel deck spar, and the construction method will be described with reference to the drawings.

(1) 最初に、中央床版部1A、側床版部1B,1Bをそれぞれトレーラー3によって別々
に現地に搬入する。
(1) First, the central floor slab part 1A and the side floor slab parts 1B, 1B are separately carried into the site by the trailer 3, respectively.

(2) 次に、事前施工にて構築された鋼床版桁4の上を作業ヤードとして利用し、鋼床版桁
4の上に中央床版部1A、側床版部1B,1Bをそれぞれクレーン5によって荷揚げする。なお、荷揚げに際し、桁下空間を作業ヤードとして一部占有することとなるが、桁下空間が道路などの場合には、図2(b)に図示するようにトレーラー3とクレーン5を架設方向に縦列配置とすることにより占有部分を道路の中央分離帯幅程度にして極力少なくするものとする。
(2) Next, the steel slab girder 4 constructed in advance construction is used as a work yard, and the central slab part 1A and the side slab parts 1B and 1B are respectively placed on the steel slab girder 4. Unload by crane 5. When unloading, a part of the under-sparing space is occupied as a work yard. However, when the under-sparing space is a road or the like, as shown in FIG. As a result, the occupied portion is made to be about the width of the median strip of the road to minimize the occupied portion.

また、クレーン5を支持するアウトリガー(図省略)は道路に突出することとなるが、クレーン5は極力短時間の間に限り、道路にさせることにより歩行者や車の往来を妨げないようする。   Further, the outrigger (not shown) that supports the crane 5 protrudes on the road, but the crane 5 is made to be on the road for a short time as much as possible so as not to prevent the traffic of pedestrians and vehicles.

(3) 次に、鋼床版桁4の上に予め配置された台車6の上で中央床版部1Aと側床版部1B
,1Bとを仮組みして鋼床版桁1の1ブロックを構築する。この場合、特に両側の側床版部1B,1Bは、図2(c)に図示するように中央床版部1Aの上に折り曲げておくものとし、また中央床版部1Aと両側の側床版部1B,1Bとの連結部は仮締めとし、それ以外の部分は本締めとする。
(3) Next, the central floor slab part 1A and the side floor slab part 1B on the cart 6 previously arranged on the steel floor slab girder 4
, 1B are temporarily assembled to construct one block of the steel deck girder 1. In this case, the side floor slab portions 1B and 1B on both sides are bent on the central floor slab portion 1A as shown in FIG. 2 (c), and the central floor slab portion 1A and the side floor slabs on both sides are folded. The connecting portions with the plate portions 1B and 1B are temporarily tightened, and the other portions are permanently tightened.

(4) 次に、こうして仮組みされた鋼床版桁1のブロック同士をその架設方向に架設分連結
しておき、送り出し装置7によって鋼床版桁1を架設方向に少しずつ送り出す。この場合、特に鋼床版桁1のみを送り出し、手延べ機は施工ヤードを広く必要とするため用いないものとする。このため、送り出した鋼床版桁1はベント8を架設方向に所定間隔おきに配置して支持する。この場合、各ベント8と鋼床版桁1との間にジャッキ9を介在する。
(4) Next, the blocks of the steel deck spar 1 temporarily assembled in this way are connected to each other in the erection direction, and the steel slab girder 1 is sent out little by little in the erection direction by the delivery device 7. In this case, only the steel slab girder 1 is sent out, and the hand-roller is not used because it requires a wide construction yard. For this reason, the fed steel deck spar 1 supports the vents 8 by arranging them at predetermined intervals in the installation direction. In this case, a jack 9 is interposed between each vent 8 and the steel deck spar 1.

(5) こうして送り出した鋼床版桁1が所定の位置に到達したら、各ベンド8の上に設置さ
れたジャッキ9をジャッキダウンして鋼床版桁1を所定の位置に架設する。また、中央床版部1Aの上に折り畳まれた側床版部1B,1Bを中央床版部1Aの両側に水平に降ろす。
(5) When the steel deck slab 1 sent out in this way reaches a predetermined position, the jack 9 installed on each bend 8 is jacked down and the steel deck slab 1 is installed at a predetermined position. Further, the side floor slab parts 1B and 1B folded on the central floor slab part 1A are lowered horizontally on both sides of the central floor slab part 1A.

この場合、側床版部1B,1Bはウィンチ(図省略)で支持したり、水平ジャッキ(図省略)で押したりして調整しながら中央床版部1Aの両側に水平に降ろす。そして、中央床版部1Aと側鋼床版部1B,1Bとの連結部の本締めと中央床版部1Aおよび側鋼床版部1Bの塗装を行う。   In this case, the side floor slab portions 1B and 1B are lowered horizontally on both sides of the central floor slab portion 1A while being supported by a winch (not shown) or pushed by a horizontal jack (not shown). Then, final fastening of the connecting portion between the central floor slab portion 1A and the side steel floor slab portions 1B and 1B and coating of the central floor slab portion 1A and the side steel floor slab portion 1B are performed.

本願発明は、例えば道路や線路、あるいは河川などの上に架け渡される橋梁のように、周囲に充分な作業ヤードを確保できない場所で、周辺環境に悪影響を与えることなく、きわめて短期間でかつ効率的に橋梁を架設することができる。   The invention of the present application is a place where a sufficient work yard cannot be secured around, such as a bridge over a road, a railroad, or a river, for example, and it is extremely short and efficient without adversely affecting the surrounding environment. A bridge can be erected.

鋼床版桁の一例を示し、(a)は展開された状態を示す断面図、(b)は折り曲げられた状態を示す断面図である。An example of a steel deck slab is shown, (a) is a sectional view showing a developed state, (b) is a sectional view showing a folded state. 橋梁の架設工法の一例を示し、(a)は側面図、(b)は平面図、(c)は折り曲げられた鋼床版桁の断面図である。An example of the construction method of a bridge is shown, (a) is a side view, (b) is a plan view, and (c) is a sectional view of a bent steel deck slab.

符号の説明Explanation of symbols

1 鋼床版桁(上部工)
1A 中央床版部
1B 側床版部
1a 主桁
1b 横梁
1c 床鋼板
1d 補強リブ
1e アスファルト舗装
2 橋脚(下部工)
3 トレーラー
4 既設鋼床版桁
5 クレーン
6 台車
7 送り出し装置
8 ベント
9 ジャッキ
1 Steel deck girder (superstructure)
1A Central floor slab part 1B Side floor slab part 1a Main girder 1b Cross beam 1c Floor steel plate 1d Reinforcement rib 1e Asphalt pavement 2 Pier (under construction)
3 Trailer 4 Existing steel slab girder 5 Crane 6 Carriage 7 Delivery device 8 Vent 9 Jack

Claims (2)

橋梁の上部工を構築しながら架設方向に徐々に送り出して前記上部工の全長を構築する橋梁の架設工法において、前記上部工をその架設方向と直交する方向に折り曲げて送り出すことを特徴とする橋梁の架設工法。   A bridge erection method in which the entire length of the superstructure is constructed by gradually sending it out in the construction direction while constructing the superstructure of the bridge, wherein the superstructure is bent and sent out in a direction perpendicular to the construction direction. Erection method. 橋梁の上部工を構築しながら架設方向に徐々に送り出して前記上部工の全長が構築される橋梁に用いられる橋梁の上部工ユニットであって、前記橋梁の架設方向と直交する方向に中央床版部とその両側に位置する側床版部とから構成され、かつ前記側床版部は前記中央床版部の側部に架設方向と直交する方向に折り曲げ可能に連結されてなることを特徴とする橋梁の上部工ユニット。
A bridge superstructure unit used for a bridge in which the overall length of the superstructure is constructed by gradually sending it out in the construction direction while constructing the superstructure of the bridge, and a central floor slab in a direction perpendicular to the construction direction of the bridge And a side floor slab portion located on both sides thereof, and the side floor slab portion is connected to a side portion of the central floor slab portion so as to be bendable in a direction perpendicular to the installation direction. Bridge superstructure unit.
JP2003325971A 2003-09-18 2003-09-18 Erection method of bridge, and upper work unit for bridge Withdrawn JP2005090109A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003325971A JP2005090109A (en) 2003-09-18 2003-09-18 Erection method of bridge, and upper work unit for bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003325971A JP2005090109A (en) 2003-09-18 2003-09-18 Erection method of bridge, and upper work unit for bridge

Publications (1)

Publication Number Publication Date
JP2005090109A true JP2005090109A (en) 2005-04-07

Family

ID=34456280

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003325971A Withdrawn JP2005090109A (en) 2003-09-18 2003-09-18 Erection method of bridge, and upper work unit for bridge

Country Status (1)

Country Link
JP (1) JP2005090109A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007046376A (en) * 2005-08-11 2007-02-22 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Construction method of bridge, superstructure work of the bridge and expansion device
JP2007321476A (en) * 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Bridge and its construction method
JP2012237176A (en) * 2011-05-13 2012-12-06 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Method and structure for rebuilding bridge pier
JP2018109313A (en) * 2017-01-05 2018-07-12 鹿島建設株式会社 Prefabricated structure construction method and prefabricated structure
CN110904863A (en) * 2019-12-09 2020-03-24 中铁第五勘察设计院集团有限公司 Beam changing method with foldable beam changing machine

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007046376A (en) * 2005-08-11 2007-02-22 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Construction method of bridge, superstructure work of the bridge and expansion device
JP4673699B2 (en) * 2005-08-11 2011-04-20 三菱重工鉄構エンジニアリング株式会社 Bridge construction method, bridge superstructure and deployment device
JP2007321476A (en) * 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Bridge and its construction method
JP4704279B2 (en) * 2006-06-01 2011-06-15 三菱重工鉄構エンジニアリング株式会社 Bridge construction method
JP2012237176A (en) * 2011-05-13 2012-12-06 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Method and structure for rebuilding bridge pier
JP2018109313A (en) * 2017-01-05 2018-07-12 鹿島建設株式会社 Prefabricated structure construction method and prefabricated structure
CN110904863A (en) * 2019-12-09 2020-03-24 中铁第五勘察设计院集团有限公司 Beam changing method with foldable beam changing machine
CN110904863B (en) * 2019-12-09 2021-06-25 中铁第五勘察设计院集团有限公司 Beam changing method with foldable beam changing machine

Similar Documents

Publication Publication Date Title
JP6004353B2 (en) Replacement method of concrete floor slab for elevated road
US5960502A (en) Method and mechanism for erection of prefabricated modular deck of viaducts, motorway flyovers and the like
JP6180376B2 (en) Main girder provision method in composite girder floor slab replacement method, composite girder floor slab replacement method, and main girder provision structure in composite girder floor slab replacement method
KR20090098180A (en) Method for broadening width of existing bridge without temporary road
JP2003253623A (en) Rebuilding construction method for bridge beam
JP2008025195A (en) Construction method of cable-stayed bridge
JP5184248B2 (en) Construction method of level crossing
JP4901178B2 (en) Steel / concrete composite rigid frame bridge construction method
KR101404481B1 (en) Bridge construction method using road decking panel at limited space for girder manufacturing
JP2020090785A (en) Widening structural body, widening structure, floor slab widening construction method, and floor slab renewal method
JP2005090109A (en) Erection method of bridge, and upper work unit for bridge
JP2005290889A (en) Structure of depressed road and its execution method
JP2007270566A (en) Protective structure and its construction method
JP5613294B1 (en) Bridge repair method
JP2000017618A (en) Replacement method of concrete bridge to steel bridge
JP6889010B2 (en) Bridge construction method
JP3954905B2 (en) Three-dimensional crossing method of plane intersection and viaduct
JP4005955B2 (en) Bridge, bridge erection method, and decorative plate used for the bridge
JP2006112086A (en) Structure of bridge and method for rebuilding bridge
JP6944900B2 (en) Construction method of linear structure
JP2005090108A (en) Erection method of bridge
JP2005220526A (en) Overhead crossing and its construction method
JP4526941B2 (en) Bridge floor slab erection method and floor slab carrier
KR200300023Y1 (en) multi-span continuous prestressed concrete girder bridge structure rigidly joined to pier
JPH0312172B2 (en)

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20061205