JP2001311181A - Structure of swing post section in working machine - Google Patents
Structure of swing post section in working machineInfo
- Publication number
- JP2001311181A JP2001311181A JP2000132374A JP2000132374A JP2001311181A JP 2001311181 A JP2001311181 A JP 2001311181A JP 2000132374 A JP2000132374 A JP 2000132374A JP 2000132374 A JP2000132374 A JP 2000132374A JP 2001311181 A JP2001311181 A JP 2001311181A
- Authority
- JP
- Japan
- Prior art keywords
- swing post
- boss
- swing
- boss portion
- post
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Landscapes
- Component Parts Of Construction Machinery (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、作業機械のスイン
グポスト部の構造、さらに詳しくは、油圧ショベルなど
の作業機械の機体本体に揺動自在に取付けられ、作業装
置が連結されるスイングポストの部分の構造に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a swing post of a working machine, and more particularly to a swing post of a swing post which is swingably attached to a body of a working machine such as a hydraulic shovel and to which a working device is connected. Regarding the structure of the part.
【0002】[0002]
【従来の技術】図5及び図6を参照して説明すると、典
型的な作業機械である例えば油圧ショベルは、機体本体
50に実質上鉛直方向に延びる軸線51を中心に揺動自
在に取付けられるスイングポスト52を備え、スイング
ポスト52には作業装置54が連結されている。2. Description of the Related Art Referring to FIGS. 5 and 6, a typical work machine, for example, a hydraulic shovel is mounted on a body 50 so as to be swingable about an axis 51 extending substantially vertically. A swing post 52 is provided, and a working device 54 is connected to the swing post 52.
【0003】作業装置54は、腕部材、バケットのごと
き作業具、腕部材及び作業具を駆動する油圧シリンダな
どを備えている。作業装置については後の発明の実施の
形態において詳述されている。作業装置54と機体本体
50との間には、作業装置54に備えられる油圧シリン
ダなどアクチュエータの数に応じた複数個の可撓配管で
ある油圧ホース56がスイングポスト52を介して配設
されている。The working device 54 includes an arm member, a working tool such as a bucket, a hydraulic cylinder for driving the arm member and the working tool, and the like. The working device is described in detail in an embodiment of the present invention. A hydraulic hose 56 which is a plurality of flexible pipes corresponding to the number of actuators such as a hydraulic cylinder provided in the working device 54 is disposed between the working device 54 and the body 50 via a swing post 52. I have.
【0004】スイングポスト52は機体本体50に、上
連結部58及び下連結部60の二個所で取付けられ、油
圧ホース56は上連結部58と下連結部60の間を通過
して配設されている。スイングポスト52は、スイング
ポスト52に形成されるブラケット53と機体本体50
に形成されるブラケット(図示していない)との間に取
付けられる伸縮自在なアクチュエータである揺動作動シ
リンダ62によって揺動させられる。A swing post 52 is attached to the body 50 at two locations, an upper connection portion 58 and a lower connection portion 60, and a hydraulic hose 56 is disposed so as to pass between the upper connection portion 58 and the lower connection portion 60. ing. The swing post 52 includes a bracket 53 formed on the swing post 52 and an airframe main body 50.
Is swingable by a swinging cylinder 62 which is a telescopic actuator attached to a bracket (not shown) formed on the front side.
【0005】スイングポスト52は鋳物によって一体に
形成され、機体本体50の上連結部58及び下連結部6
0を含むスイングポスト取付部は種々の鋼製部材を相互
に溶接して一体に形成されている。上連結部58は、ス
イングポスト52から水平方向に突出する一対のボス部
52a、52bの間に機体本体50から突出するボス部
50aが挟まれ軸線51上にピン62が挿通されて形成
され、下連結部60は、機体本体50から水平方向に突
出する一対のボス部50b、50cの間にスイングポス
ト52から突出するボス部52cが挟まれ軸線51上に
ピン64が挿通されて形成されている。[0005] The swing post 52 is integrally formed by casting, and has an upper connecting portion 58 and a lower connecting portion 6 of the body 50.
The swing post mounting portion including the "0" is formed integrally by welding various steel members to each other. The upper connecting portion 58 is formed by inserting a pin 62 on the axis 51 with a boss 50a projecting from the body 50 sandwiched between a pair of bosses 52a and 52b projecting horizontally from the swing post 52. The lower connecting portion 60 is formed by a boss 52c projecting from the swing post 52 being sandwiched between a pair of bosses 50b and 50c projecting horizontally from the body 50, and a pin 64 being inserted through the axis 51. I have.
【0006】[0006]
【発明が解決しようとする課題】上述したとおりの形態
の従来の作業機械のスイングポスト部の構造には、次の
とおりの解決すべき問題がある。The structure of the swing post portion of the conventional working machine of the above-described type has the following problems to be solved.
【0007】(1)製造:上連結部58及び下連結部6
0は、機体本体50から三個のボス部50a、50b、
50cが、スイングポスト52から三個のボス部52
a、52b、52cがそれぞれ水平方向に突出されピン
62、64によって連結される構造であるので、製造に
あたっては六個のボス部を鋳物によりあるいは板部材を
溶接して平行に成形するのが、またピン62及び64が
挿通されるそれぞれの軸受孔を同一の軸線51上に機械
加工するのが容易でない。そのために、種々の溶接治
具、加工治具、加工機械など、製造のための特別な手段
が用意される。また、構成部品の点数も多い。したがっ
て、製造のコストが高くなる問題がある。(1) Manufacturing: upper connecting portion 58 and lower connecting portion 6
0 denotes three bosses 50a, 50b,
50c is the three bosses 52 from the swing post 52.
Since a, 52b and 52c are projected in the horizontal direction and connected by pins 62 and 64, the six bosses are formed in parallel by casting or by welding plate members in manufacturing. Further, it is not easy to machine the respective bearing holes into which the pins 62 and 64 are inserted on the same axis 51. For this purpose, special means for manufacturing are prepared, such as various welding jigs, processing jigs, and processing machines. Also, the number of components is large. Therefore, there is a problem that manufacturing cost is increased.
【0008】(2)強度:上連結部58及び下連結部6
0を構成する上述の六個のボス部は、スイングポスト5
2及び機体本体50から櫛歯状に突出しており、これら
ボス部各々の上下方向の間は連結されていない開放され
た開断面である。したがって、機体本体50とスイング
ポスト52の連結部の強度の確保が難しい問題がある。(2) Strength: upper connecting portion 58 and lower connecting portion 6
The above-mentioned six bosses constituting the swing post 5
2 and the boss portion protrude from the body 50 in a comb shape. Therefore, there is a problem that it is difficult to secure the strength of the connecting portion between the body 50 and the swing post 52.
【0009】本発明は上記事実に鑑みてなされたもの
で、その技術的課題は、作業機械の機体本体と機体本体
に揺動自在に取付けられ作業装置が連結されるスイング
ポストとの連結部の、製造を容易にし、部品点数を少な
くし、また強度を向上させることができる、作業機械の
スイングポスト部の構造を提供することである。SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned circumstances, and a technical problem thereof is that a body portion of a working machine and a connecting portion of a swing post which is swingably attached to the body body and to which a working device is connected are connected. It is an object of the present invention to provide a structure of a swing post portion of a working machine, which can facilitate manufacture, reduce the number of parts, and improve strength.
【0010】[0010]
【課題を解決するための手段】請求項1に記載された発
明は、機体本体のボス部に実質上鉛直方向に配設される
軸部材を介し揺動自在に取付けられ作業装置が連結され
るスイングポストと、このスイングポストを介し機体本
体と作業装置の間に配設される可撓配管とを備える作業
機械において、該軸部材は該ボス部を貫通し、該スイン
グポストはこのボス部の上下に位置し該軸部材が挿通さ
れる上ボス部及び下ボス部を備え、該可撓配管は下ボス
部の下方を通過し機体本体及びスイングポスト各々の中
に通されている、ことを特徴とする作業機械のスイング
ポスト部の構造である。According to the first aspect of the present invention, a working device is connected to a boss of a body of a vehicle body through a shaft member disposed substantially vertically so as to be swingable. In a working machine including a swing post and a flexible pipe provided between the machine body and the working device via the swing post, the shaft member penetrates the boss, and the swing post is An upper boss portion and a lower boss portion, which are positioned vertically and through which the shaft member is inserted, wherein the flexible pipe passes under the lower boss portion and passes through each of the body body and the swing post. It is a structure of a swing post part of a working machine which is a feature.
【0011】そして、連結部を一つにし配管はその下方
を通過させることにより、機体本体のボス部を閉断面の
揺動軸線の方向に延びる構造にし、これをスイングポス
トの上下のボス部で挟み込むようにして、連結部の強度
を確保し、構造を簡単にし、製造を容易にする。Then, the connecting portion is made into one, and the pipe is made to pass below the connecting portion, so that the boss portion of the body body extends in the direction of the swing axis of the closed section, and this is formed by the upper and lower boss portions of the swing post. By sandwiching, the strength of the connecting portion is ensured, the structure is simplified, and the manufacturing is facilitated.
【0012】請求項2に記載された発明は、請求項1記
載のスイングポスト部の構造において、該下ボス部の下
方には、スイングポスト及び/又は機体本体に設けられ
下ボス部との間に該配管を通す空間を形成するフランジ
部が備えられている。According to a second aspect of the present invention, in the structure of the swing post portion according to the first aspect, a lower portion of the swing post and / or a lower boss portion provided on the body body below the lower boss portion. Is provided with a flange portion that forms a space through which the pipe passes.
【0013】そして、配管を下ボス部とフランジ部の間
を通すことにより、障害物などとの接触による配管の損
傷を防止する。By passing the pipe between the lower boss and the flange, damage to the pipe due to contact with an obstacle or the like is prevented.
【0014】請求項3に記載された発明は、請求項2記
載のスイングポスト部の構造において、スイングポスト
の該フランジ部は、スイングポストを揺動させる伸縮自
在なアクチュエータの取付部と一体になっている。According to a third aspect of the present invention, in the structure of the swing post portion according to the second aspect, the flange portion of the swing post is integrated with a mounting portion of a telescopic actuator that swings the swing post. ing.
【0015】そして、フランジ部によってスイングポス
トの揺動アクチュエータ取付部の補強も行う。Further, the swing post mounting portion of the swing post is reinforced by the flange portion.
【0016】請求項4に記載された発明は、請求項1か
ら3までのいずれかに記載のスイングポスト部の構造に
おいて、機体本体の、該ボス部を含むスイングポスト取
付部は鋳物により形成されている。According to a fourth aspect of the present invention, in the structure of the swing post portion according to any one of the first to third aspects, the swing post mounting portion including the boss portion of the body of the body is formed by casting. ing.
【0017】そして、機体本体とスイングポストとの連
結部の限られたスペースで、スイングポスト取付部分の
製作をさらに容易にし、また強度を向上させる。[0017] In a limited space of the connecting portion between the body and the swing post, the manufacture of the swing post mounting portion is further facilitated and the strength is improved.
【0018】[0018]
【発明の実施の形態】以下、本発明に従って構成された
作業機械のスイングポスト部の構造を、典型的な作業機
械である油圧ショベルにおける好適実施形態を図示して
いる添付図面を参照して、さらに詳細に説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The structure of a swing post of a working machine constructed in accordance with the present invention will be described below with reference to the accompanying drawings, which show a preferred embodiment of a hydraulic shovel as a typical working machine. This will be described in more detail.
【0019】図1及び図2を参照して説明すると、全体
を番号2で示すスイングポストは、油圧ショベル4の機
体本体6のボス部8に、実質上鉛直の方向(図1及び図
2の上下方向)に延びる軸線10上を貫通する軸部材で
あるピン11を介し揺動自在に取付けられ、作業装置1
2がスイングポスト2に連結されている。Referring to FIGS. 1 and 2, the swing post, generally designated by the reference numeral 2, is mounted on the boss 8 of the body 6 of the excavator 4 in a substantially vertical direction (see FIGS. 1 and 2). The work device 1 is swingably mounted via a pin 11 which is a shaft member that penetrates an axis 10 extending in the vertical direction.
2 is connected to the swing post 2.
【0020】スイングポスト2は、ボス部8の上下に位
置しピン11が挿通される上ボス部2a及び下ボス部2
bを備えている。機体本体6と作業装置12との間に
は、スイングポスト2を介し複数個の可撓配管である油
圧ホース14が下ボス部2bの下方を通過して機体本体
6及びスイングポスト2各々の中に通されている。The swing post 2 is located above and below the boss 8 and has an upper boss 2a and a lower boss 2 through which the pin 11 is inserted.
b. A plurality of hydraulic hoses 14, which are flexible pipes, pass below the lower boss 2 b between the body 6 and the working device 12 through the swing post 2, and are located inside the body 6 and the swing post 2. Has been passed through.
【0021】作業装置12は、スイングポスト2に上下
方向に揺動自在に支持されるブーム12a、スイングポ
スト2とブーム12aとの間に介在されるブーム作動シ
リンダ12b、ブーム12aの先端に上下方向に揺動自
在に支持されるアーム12c、ブーム12aとアーム1
2cとの間に介在されるアーム作動シリンダ12d、ア
ーム12cの先端に上下方向に揺動自在に支持されるバ
ケット12e、及びアーム12cとバケット12eとの
間に介在されるバケット作動シリンダ12fを備えてい
る。この作業装置12は本発明において新規特徴を構成
するものではなく、それ自体は周知のものである。The working device 12 includes a boom 12a supported by the swing post 2 so as to be swingable in a vertical direction, a boom operating cylinder 12b interposed between the swing post 2 and the boom 12a, and a vertical direction at a tip of the boom 12a. 12c, boom 12a and arm 1 that are swingably supported on
An arm operating cylinder 12d interposed between the arm 12c and the arm 12c, a bucket 12e supported at the tip of the arm 12c to be vertically swingable, and a bucket operating cylinder 12f interposed between the arm 12c and the bucket 12e. ing. The working device 12 does not constitute a novel feature of the present invention, and is known per se.
【0022】図2とともに図3を参照して説明すると、
スイングポスト2は鋳物により一体に形成されている。
側面から見て(図2)チャンネル形状(コ字形状)に形
成され、その開口部2cに機体本体6のボス部8が位置
付けられ、開口部2cの上側に上ボス部2aが、下側に
下ボス部2bが形成されている。上ボス部2a及び下ボ
ス部2bには軸線10を中心にして軸受孔2d及び2e
がそれぞれ形成されている。上ボス部2aの上方には軸
受孔を備え二股状に形成されるブラケット2fが備えら
れている。開口部2cの背面(図2において左側の面)
の下ボス部2bの側に軸受孔を備え二股状に形成される
ブラケット2gが備えられている。さらに、スイングポ
スト2の下部の一方の側面に軸受孔を備え二股状に形成
されるブラケット2hが形成されている。Referring to FIG. 3 together with FIG. 2,
The swing post 2 is integrally formed by casting.
When viewed from the side (FIG. 2), it is formed in a channel shape (U-shape), the boss 8 of the body main body 6 is positioned in the opening 2c, and the upper boss 2a is located above the opening 2c and the boss 8 is located below the opening 2c. A lower boss 2b is formed. Bearing holes 2d and 2e are provided around the axis 10 in the upper boss 2a and the lower boss 2b.
Are formed respectively. Above the upper boss 2a, a bracket 2f having a bearing hole and having a forked shape is provided. Back surface of opening 2c (left surface in FIG. 2)
A bracket 2g having a bearing hole on the side of the lower boss portion 2b and having a forked shape is provided. Further, a bracket 2h having a bearing hole on one side surface of a lower portion of the swing post 2 and formed in a forked shape is formed.
【0023】ブラケット2fに作業装置12のブーム1
2aが、ブラケット2gにブーム作動シリンダ12bが
それぞれ連結されている。ブラケット2hは、スイング
ポスト2を揺動させるアクチュエータの取付部である
(揺動アクチュエータについては後述する)。The boom 1 of the working device 12 is mounted on the bracket 2f.
2a, the boom operating cylinder 12b is connected to the bracket 2g. The bracket 2h is a mounting portion of an actuator that swings the swing post 2 (the swing actuator will be described later).
【0024】スイングポスト2の下ボス部2bの下方に
は、下ボス部2bとの間に空間3を形成するように舌状
に突出するフランジ部2kが形成されている。フランジ
部2kは、ブラケット2hと連結され一体に成形されて
いる。Below the lower boss 2b of the swing post 2, there is formed a flange 2k projecting like a tongue so as to form a space 3 with the lower boss 2b. The flange portion 2k is connected to the bracket 2h and is integrally formed.
【0025】スイングポスト2は、油圧ホース14を通
すことができる中空部2mを備えている。中空部2m
は、下ボス部2bとフランジ部2kの間に開口する一方
の開口2n、及び上ボス部2aとブラケット2fの間に
開口する他方の開口2pを備えている。The swing post 2 has a hollow portion 2m through which the hydraulic hose 14 can pass. Hollow 2m
Is provided with one opening 2n opened between the lower boss 2b and the flange 2k, and the other opening 2p opened between the upper boss 2a and the bracket 2f.
【0026】機体本体6は、種々の鋼製部材を相互に溶
接して一体に形成され、ボス部8を含むスイングポスト
取付部9は鋳物により一体に形成されている。ボス部8
は軸線10方向に延びる厚肉の円筒状に形成され、軸線
10方向の長さはスイングポスト2の上ボス部2a及び
下ボス部2bの間に軸線10を中心に揺動自在に、また
軸受としての強度を確保する長さに規定されている。ボ
ス部8には軸線10上に軸受孔8aが形成されている。
ボス部8の下方には、スイングポスト2の下ボス部2b
との間に上述の空間3を形成するように舌状に突出する
フランジ部9aが形成されている。フランジ部9aは、
スイングポスト2に備えられるフランジ部2kと軸線1
0方向において実質上同一の面に備えられ、またフラン
ジ部2kとスイングポスト2が揺動するときに干渉しな
いように凹状に形成されている。スイングポスト取付部
9の内部には油圧ホース14を通すことができる中空部
9bが形成されており、ボス部8とフランジ部9aの間
にはその開口9cが形成されている。The body 6 is formed integrally by welding various steel members to each other, and the swing post mounting portion 9 including the boss portion 8 is integrally formed by casting. Boss part 8
Is formed in a thick cylindrical shape extending in the direction of the axis 10, and the length in the direction of the axis 10 is swingable about the axis 10 between the upper boss 2 a and the lower boss 2 b of the swing post 2. The length is specified to ensure the strength. The boss 8 has a bearing hole 8 a formed on the axis 10.
Below the boss 8, a lower boss 2b of the swing post 2 is provided.
A flange portion 9a projecting like a tongue is formed so as to form the space 3 described above. The flange portion 9a
Flange part 2k provided on swing post 2 and axis 1
The flange portion 2k and the swing post 2 are provided on substantially the same surface in the 0 direction, and are formed in a concave shape so as not to interfere when the swing portion 2 swings. A hollow portion 9b through which the hydraulic hose 14 can pass is formed inside the swing post mounting portion 9, and an opening 9c is formed between the boss portion 8 and the flange portion 9a.
【0027】上述のように構成されたスイングポスト2
及び機体本体6は、機体本体6のボス部8にスイングポ
スト2の上ボス部2a及び下ボス部2bが軸線10上に
整合され、ピン11が挿通されて連結され、スイングポ
スト2のブラケット2hと機体本体6に備えられるブラ
ケット(図示していない)の間に、スイングポスト2を
揺動させるための伸縮自在なアクチュエータである揺動
作動シリンダ16が取付けられる。Swing post 2 configured as described above
Further, the upper boss portion 2a and the lower boss portion 2b of the swing post 2 are aligned on the axis 10 with the boss portion 8 of the fuselage body 6, the pins 11 are inserted and connected, and the bracket 2h of the swing post 2 is attached. A swinging cylinder 16, which is a telescopic actuator for swinging the swing post 2, is mounted between the body and a bracket (not shown) provided on the body 6.
【0028】前述の作業装置12の三個の油圧シリン
ダ、すなわちブーム作動シリンダ12b、アーム作動シ
リンダ12d、バケット作動シリンダ12f各々に圧油
を給排するために、少なくとも六本の油圧ホース14
が、機体本体6の油圧制御装置(図示していない)と作
業装置12の間にスイングポスト2を介して配設されて
いる。油圧ホース14は、機体本体6の中空部9bから
開口9cを通り、スイングポスト2の下ボス部2bとフ
ランジ部9a及びフランジ部2kの間の空間3を通過
し、スイングポスト2の開口2nから中空部2mに入り
開口2pから作業装置12のブーム12aの基部に抜
け、作業装置12の油圧シリンダの各々に接続される。At least six hydraulic hoses 14 are provided for supplying and discharging hydraulic oil to each of the three hydraulic cylinders of the working device 12, namely, the boom operating cylinder 12b, the arm operating cylinder 12d, and the bucket operating cylinder 12f.
Are arranged between the hydraulic control device (not shown) of the body 6 and the working device 12 via the swing post 2. The hydraulic hose 14 passes through the opening 9 c from the hollow portion 9 b of the body 6, passes through the space 3 between the lower boss portion 2 b of the swing post 2 and the flange portion 9 a and the flange portion 2 k, and passes through the opening 2 n of the swing post 2. After entering the hollow portion 2m, it passes through the opening 2p to the base of the boom 12a of the working device 12, and is connected to each of the hydraulic cylinders of the working device 12.
【0029】図1〜図3を参照して上述したとおりの作
業機械のスイングポスト部の構造の作用を説明する。The operation of the swing post structure of the working machine as described above will be described with reference to FIGS.
【0030】(1)製造:機体本体6とスイングポスト
2の連結部を、従来の二個所から一個所にし、スイング
ポスト2を介し配設される油圧ホース14をその連結部
の下方を通過するように配設したから、連結部の成形ま
た機械加工は容易になり、特別な溶接治具、加工治具、
加工機械などの必要がなくなり、構成部品の点数が少な
くなり、製造コストが高い問題を除くことができる。(1) Manufacture: The connection between the body 6 and the swing post 2 is changed from the conventional two to one, and the hydraulic hose 14 provided via the swing post 2 passes below the connection. It is easy to mold and machine the connecting part because of the special arrangement of welding jig, processing jig,
The need for a processing machine or the like is eliminated, the number of components is reduced, and the problem of high manufacturing costs can be eliminated.
【0031】(2)強度:機体本体6とスイングポスト
2の連結部を、機体本体6から閉断面で軸受の長さを十
分に確保することができるボス部8を突出させ、これを
スイングポスト2の上ボス部2a及び下ボス部2bで挟
む構造にしたから、連結部に十分な強度を容易に確保す
ることができる。(2) Strength: The boss 8 which can secure a sufficient length of the bearing in a closed cross section from the body 6 is projected from the body 6 and the connecting portion between the body 6 and the swing post 2. Since the structure is sandwiched between the upper boss 2a and the lower boss 2b, it is possible to easily secure sufficient strength at the connecting portion.
【0032】(3)可撓配管の保護:作業機械において
異物などとの接触により損傷を受けやすい可撓配管であ
る油圧ホース14を、機体本体6とスイングポスト2の
連結部においては下ボス部2bとフランジ部2k、9c
で形成される空間3を通すようにしたから、油圧ホース
14を十分、適切に、また簡単な構造で保護することが
できる。さらに、油圧ホース14を機体本体6及びスイ
ングポスト2の中空部9c、2mを通すようにしたか
ら、異物などによる損傷から油圧ホース14を確実に保
護することができる。(3) Protection of the flexible pipe: A hydraulic hose 14 which is a flexible pipe which is easily damaged by contact with foreign matter or the like in a working machine is connected to a lower boss portion at a connecting portion between the body 6 and the swing post 2. 2b and flanges 2k, 9c
The hydraulic hose 14 can be sufficiently and appropriately protected with a simple structure because the space 3 formed by the space 3 is made to pass through. Further, since the hydraulic hose 14 is made to pass through the hollow portions 9c and 2m of the body 6 and the swing post 2, it is possible to reliably protect the hydraulic hose 14 from damage due to foreign matter or the like.
【0033】(4)揺動シリンダ取付部の補強:下ボス
部2bの下方に形成されるフランジ部2kを揺動作動シ
リンダ16の取付部であるブラケット2hに一体的につ
なげたから、ブラケット2hを補強することができる。(4) Reinforcement of the swing cylinder mounting portion: The flange portion 2k formed below the lower boss portion 2b is integrally connected to the bracket 2h, which is the mounting portion of the swing motion cylinder 16, so that the bracket 2h is connected. Can be reinforced.
【0034】以上、本発明を実施の形態に基づいて詳細
に説明したが、本発明は上記の実施の形態に限定される
ものではなく、本発明の範囲内においてさまざまな変形
あるいは修正ができるものである。As described above, the present invention has been described in detail based on the embodiments. However, the present invention is not limited to the above-described embodiments, and can be variously modified or modified within the scope of the present invention. It is.
【0035】(1)機体本体のスイングポスト取付部:
本発明の実施の形態においては、機体本体6のスイング
ポスト取付部9は鋳物により一体に形成されているが、
図4に示すように上下二枚の板部材18a、18bの間
に厚肉円筒18cを一体に溶接し閉断面のボス部18を
形成するなど、鋼製部材を適宜に溶接して取付部9を構
成してもよい。(1) Swing post mounting part of the body of the machine:
In the embodiment of the present invention, the swing post mounting portion 9 of the body body 6 is integrally formed by casting.
As shown in FIG. 4, the steel member is appropriately welded, such as by integrally welding a thick cylinder 18c between the upper and lower two plate members 18a and 18b to form a boss 18 having a closed cross section. May be configured.
【0036】(2)スイングポスト:さらに、スイング
ポスト2も鋳物により一体に形成されているが、これも
鋼製部材を適宜に溶接して構成してもよい。(2) Swing post: Further, the swing post 2 is also integrally formed by casting, but this may also be constituted by appropriately welding steel members.
【0037】(3)フランジ部:本発明の実施の形態に
おいては、スイングポスト2の下方にスイングポスト2
からフランジ部2kが、機体本体6からフランジ部9a
がそれぞれ突出し備えられているが、作業機械の種類、
稼働形態などによって、スイングポスト2又は機体本体
6のいずれか一方にだけ備えるようにしてもよい。ま
た、フランジ部9aとフランジ部2kとは実質上同一の
面に備えられているが、同一面でなく軸線10の方向
(上下方向)において重なるようにしてもよい。(3) Flange: In the embodiment of the present invention, the swing post 2
From the body portion 6 to the flange portion 9a.
Are protruding respectively, but the type of work machine,
Depending on the operation mode or the like, only one of the swing post 2 and the body 6 may be provided. Further, although the flange portion 9a and the flange portion 2k are provided on substantially the same surface, they may be overlapped not in the same surface but in the direction of the axis 10 (vertical direction).
【0038】(4)可撓配管:本発明の実施の形態にお
いては、可撓配管として油圧ホース14が配設されてい
るが、可撓配管は作業装置の種類、形態に応じて、水ホ
ース、電気ケーブルなどであってもよい。(4) Flexible piping: In the embodiment of the present invention, the hydraulic hose 14 is provided as the flexible piping, but the flexible piping is a water hose depending on the type and form of the working device. Or an electric cable.
【0039】[0039]
【発明の効果】本発明に従って構成された作業機械のス
イングポスト部の構造によれば、作業機械の機体本体と
機体本体に揺動自在に取付けられ作業装置が連結される
スイングポストとの連結部の、製造を容易にし、部品点
数を少なくし、また強度を向上させることができる、作
業機械のスイングポスト部の構造が提供される。According to the structure of the swing post portion of the working machine constituted according to the present invention, the connecting portion between the body of the working machine and the swing post to which the working device is connected so as to be swingably attached to the body. In addition, the present invention provides a structure of a swing post of a working machine, which can facilitate manufacture, reduce the number of parts, and improve strength.
【図1】本発明に従って構成されたスイングポスト部の
構造を備える典型的な作業機械である油圧ショベルの側
面図。FIG. 1 is a side view of a hydraulic shovel, which is a typical work machine having a swing post structure configured according to the present invention.
【図2】図1のスイングポストの部分の拡大図。FIG. 2 is an enlarged view of a part of a swing post shown in FIG. 1;
【図3】図2のA−A矢印方向に見たスイングポストの
部分の底面図。FIG. 3 is a bottom view of a portion of the swing post as viewed in the direction of arrows AA in FIG. 2;
【図4】機体本体のスイングポスト取付部の他の形態を
示す断面図。FIG. 4 is a cross-sectional view showing another embodiment of the swing post mounting portion of the body of the machine.
【図5】従来のスイングポストポスト部の側面図。FIG. 5 is a side view of a conventional swing post post.
【図6】図5のB−B矢印方向に見た平面図。FIG. 6 is a plan view as seen in the direction of arrows BB in FIG. 5;
2:スイングポスト 2a:上ボス部 2b:下ボス部 2h:ブラケット(アクチュエータ取付部) 2k:フランジ部 6:機体本体 8:ボス部 9:スイングポスト取付部 9c:フランジ部 11:軸部材 12:作業装置 14:油圧ホース(可撓配管) 18:ボス部 50:機体本体 52:スイングポスト 2: Swing post 2a: Upper boss portion 2b: Lower boss portion 2h: Bracket (actuator mounting portion) 2k: Flange portion 6: Airframe body 8: Boss portion 9: Swing post mounting portion 9c: Flange portion 11: Shaft member 12: Working device 14: Hydraulic hose (flexible piping) 18: Boss 50: Airframe main body 52: Swing post
Claims (4)
設される軸部材を介し揺動自在に取付けられ作業装置が
連結されるスイングポストと、このスイングポストを介
し機体本体と作業装置の間に配設される可撓配管とを備
える作業機械において、 該軸部材は該ボス部を貫通し、該スイングポストはこの
ボス部の上下に位置し該軸部材が挿通される上ボス部及
び下ボス部を備え、該可撓配管は下ボス部の下方を通過
し機体本体及びスイングポスト各々の中に通されてい
る、ことを特徴とする作業機械のスイングポスト部の構
造。1. A swing post, which is swingably attached to a boss portion of a fuselage body via a shaft member disposed substantially vertically and to which a working device is connected, and a body body and a working device are connected via the swing post. A shaft member penetrating through the boss portion, and the swing post is located above and below the boss portion and an upper boss portion through which the shaft member is inserted. And a lower boss portion, wherein the flexible pipe passes below the lower boss portion and passes through the body body and the swing post, respectively.
及び/又は機体本体に設けられ下ボス部との間に該配管
を通す空間を形成するフランジ部が備えられている、請
求項1記載の作業機械のスイングポスト部の構造。2. A flange provided below the lower boss portion and provided on the swing post and / or the body of the machine to form a space through which the pipe passes between the lower boss portion and the lower boss portion. Structure of the swing post part of the working machine described.
ングポストを揺動させる伸縮自在なアクチュエータの取
付部と一体になっている、請求項2記載の作業機械のス
イングポスト部の構造。3. The structure of the swing post portion of the working machine according to claim 2, wherein the flange portion of the swing post is integrated with a mounting portion of a telescopic actuator that swings the swing post.
スト取付部は鋳物により形成されている、請求項1から
3までのいずれかに記載の作業機械のスイングポスト部
の構造。4. The swing post structure for a working machine according to claim 1, wherein the swing post mounting portion including the boss portion of the body of the machine body is formed by casting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000132374A JP2001311181A (en) | 2000-05-01 | 2000-05-01 | Structure of swing post section in working machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000132374A JP2001311181A (en) | 2000-05-01 | 2000-05-01 | Structure of swing post section in working machine |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2001311181A true JP2001311181A (en) | 2001-11-09 |
Family
ID=18641091
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000132374A Withdrawn JP2001311181A (en) | 2000-05-01 | 2000-05-01 | Structure of swing post section in working machine |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2001311181A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1462576A2 (en) * | 2003-03-24 | 2004-09-29 | Komatsu Ltd | Piping arrangement for swing type hydraulic excavators |
-
2000
- 2000-05-01 JP JP2000132374A patent/JP2001311181A/en not_active Withdrawn
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1462576A2 (en) * | 2003-03-24 | 2004-09-29 | Komatsu Ltd | Piping arrangement for swing type hydraulic excavators |
EP1462576A3 (en) * | 2003-03-24 | 2004-10-13 | Komatsu Ltd | Piping arrangement for swing type hydraulic excavators |
US6898878B2 (en) | 2003-03-24 | 2005-05-31 | Komatsu Ltd. | Piping arrangement for swing type hydraulic excavators |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20140027290A (en) | Arm for construction machinery | |
KR20060043739A (en) | Construction machine | |
JP2003213727A (en) | Revolving frame for construction machine | |
US20220136207A1 (en) | Rotary working vehicle | |
JP2001311181A (en) | Structure of swing post section in working machine | |
EP4079973A1 (en) | Pipe protection unit for a work machine | |
JP2004108055A (en) | Working device of construction machine | |
JP6013286B2 (en) | Work equipment boom | |
JPH10331184A (en) | Working machine for hydraulic shovel | |
JP2000230241A (en) | Working machine structure of revolving working vehicle | |
JP4940189B2 (en) | Backhoe boom structure | |
JP2000273904A (en) | Piping structure of rotating work machine | |
JPH03180628A (en) | Front structure for construction machine | |
JP2000230251A (en) | Work machine structure for turning work vehicle | |
EP3978689B1 (en) | Construction machine | |
JP2011184920A (en) | Working arm for construction machinery | |
JP4005429B2 (en) | Swivel construction machine | |
JP2009133084A (en) | Offset boom type front device | |
JP7217823B2 (en) | swivel work vehicle | |
JP2000345582A (en) | Operating device | |
JP7369311B2 (en) | turning work vehicle | |
JP4648357B2 (en) | Swivel construction machine | |
JP2000204592A (en) | Step attaching construction for construction machine | |
JP2613141B2 (en) | Construction machine swivel frame | |
JPH0732605Y2 (en) | Hydraulic circuit in power excavator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20070703 |