JP2001059393A - Method and device for constructing horizontal shaft - Google Patents

Method and device for constructing horizontal shaft

Info

Publication number
JP2001059393A
JP2001059393A JP11235158A JP23515899A JP2001059393A JP 2001059393 A JP2001059393 A JP 2001059393A JP 11235158 A JP11235158 A JP 11235158A JP 23515899 A JP23515899 A JP 23515899A JP 2001059393 A JP2001059393 A JP 2001059393A
Authority
JP
Japan
Prior art keywords
outer shell
excavation
gantry
excavation work
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11235158A
Other languages
Japanese (ja)
Other versions
JP4034481B2 (en
Inventor
Yutaka Kashima
豊 加島
Norio Kondo
紀夫 近藤
Katsumitsu Miyazawa
勝光 宮澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiho Construction Co Ltd
Original Assignee
Daiho Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiho Construction Co Ltd filed Critical Daiho Construction Co Ltd
Priority to JP23515899A priority Critical patent/JP4034481B2/en
Publication of JP2001059393A publication Critical patent/JP2001059393A/en
Application granted granted Critical
Publication of JP4034481B2 publication Critical patent/JP4034481B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a horizontal shaft constructing method which can efficiently, safely and easily construct a horizontal shaft of large section, and can be applied irrespective of the properties of the ground. SOLUTION: An outer shell 1 to surround an area to excavate a horizontal shaft is formed, an excavation working base 3 having an excavation space demarcated in multiple stages in the vertical direction by a plurality of floor slabs 4 is installed within the inner side 2 to be excavated of the outer shell 1, an excavator 8 is arranged in a traveling manner on the floor slabs 4 in each excavation space 5 of the excavation base 3, and after the excavation base 3 is fixed, the inner side 2 of the outer shell is excavated by the excavator 8, the inner side 2 is excavated to the specified depth, and then, the excavation base 3 is unfixed, the excavation base 3 is advanced, and an earth retaining supporting 26 is assembled backward of the excavation base 3 to construct the horizontal shaft.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、道路や河川下を横
断する構築物を構築するための横坑構築方法と、この方
法を実施するための横坑構築装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a cross shaft construction method for constructing a structure crossing a road or under a river, and a cross shaft construction apparatus for performing the method.

【0002】[0002]

【従来の技術】この種横坑を構築する従来技術として
は、先進導坑や、開放型シールド工法、シールドメッセ
ル工法等がある。
2. Description of the Related Art Conventional techniques for constructing this type of horizontal shaft include an advanced shaft, an open shield method, a shield Messel method, and the like.

【0003】図10は先進導坑において、上半先進導坑
の施工状態を示す。
FIG. 10 shows the construction of an upper shaft in an advanced shaft.

【0004】この図10に示す先進導坑では、パイプル
ーフ41と、これの前面に設置された作業構台42と、
掘削機であるバックホウ43と、掘削土砂を搬出するベ
ルトコンベア44の列と、土砂コンテナ45と、各種資
材や掘削土砂を搬送するクレーン46等を用いて施工す
る。なお、図10において、47は掘削された上半先進
導坑、48は組み立てられた土留め支保工を示す。
In the advanced shaft shown in FIG. 10, a pipe roof 41, a work gantry 42 installed in front of the pipe roof 41,
The construction is performed using a backhoe 43 as an excavator, a row of belt conveyors 44 for carrying out excavated earth and sand, an earth and sand container 45, and a crane 46 for transporting various materials and excavated earth and sand. In FIG. 10, reference numeral 47 denotes an excavated upper half advanced shaft, and reference numeral 48 denotes an assembled earth retaining support.

【0005】そして、この先進導坑では、小さい断面の
先進導坑、側方先進導坑または上半・下半先進導坑を先
行して施工後、それぞれの先進導坑や側方先進導坑の土
留め支保工を連結させ、大きく拡げて大断面の横坑を構
築する。
In this advanced shaft, an advanced shaft with a small cross section, a lateral advanced shaft, or an upper half and a lower half advanced shaft are preceded by construction, and then the respective advanced shafts and lateral advanced shafts are constructed. The earth retaining supports will be connected to each other, and will be greatly expanded to construct a large cross section shaft.

【0006】図11は開放型シールド工法による横坑の
施工状態を示す。
FIG. 11 shows the construction of a horizontal shaft by the open shield method.

【0007】この図11に示す工法では、作業室51
と、カッティングエッジ52と、これのシールドジャッ
キ53と、フェースジャッキ54と、掘削土砂を搬出す
るベルトコンベア55と、作業台56と、支保工を組み
立てるエレクタ57等を使用して実施する。
[0007] In the construction method shown in FIG.
This is performed using a cutting edge 52, a shield jack 53 thereof, a face jack 54, a belt conveyor 55 for carrying out excavated earth and sand, a work table 56, and an erector 57 for assembling a support.

【0008】また、この開放型シールドは、シールド前
面が開放されているもので、切羽の押さえはフェースジ
ャッキ54で行い、掘進機の外殻とフレームは一体化し
ており、岩盤のカッティングエッジ52以外ではシール
ドジャッキ53のみで構成されている。
In this open type shield, the front face of the shield is open, the face is held down by a face jack 54, and the outer shell and frame of the excavator are integrated with each other. Is composed of only the shield jack 53.

【0009】しかして、この開放型シールド工法では、
カッティングエッジ52を地山に押し込み、刃口部の下
で切羽を小部分ずつ掘削し、矢板とフェースジャッキ5
4で山止めを行いながら全断面を掘削する。
However, in this open shield method,
The cutting edge 52 is pushed into the ground, and the cutting face is excavated little by little under the cutting edge.
Excavate the entire cross section while performing the stop in step 4.

【0010】他方、シールドメッセル工法では、特殊な
断面形(普通のシートパイルに似たような断面形)をし
たメッセ鋼矢板(幅20〜40cm,長さ3.5〜6.
0m程度)をジャッキを利用して地山に圧入し、鋼矢板
の庇護の下に、鋼矢板の内側の地山を掘削する工法であ
る。そして、隣接するメッセル鋼矢板相互の連結を考慮
して、互いに噛み合うような構造となっている。
On the other hand, in the shielded messel construction method, a messe steel sheet pile having a special cross-sectional shape (cross-sectional shape similar to a normal sheet pile) (width: 20 to 40 cm, length: 3.5 to 6.5 mm).
(About 0 m) is pressed into the ground using a jack, and the ground inside the steel sheet pile is excavated under the protection of the steel sheet pile. And, in consideration of the connection between adjacent Messel steel sheet piles, they are structured to mesh with each other.

【0011】[0011]

【発明が解決しようとする課題】ところで、前記先進導
坑は作業箇所が多いため、狭い導坑内でのずりや、コン
クリートなどの運搬に競合が多く、作業工程が複雑で、
工程管理が難しいという問題がある。また、作業空間が
狭いため、大型掘削機の使用が制限され、施工期間が長
くなる問題があり、施工に危険を伴う問題もあった。さ
らに、小さい断面の先進導坑や側方導坑を複数個施工
し、それぞれの土留め支保工を連結させ、大きく切り拡
げて大断面の横坑を構築するようにしているため、特殊
な技量・技能を持った作業員を多く必要とする問題があ
り、危険の度合いも大きいという問題もあった。
However, since the advanced pit has many work sites, there are many competitions for shearing in narrow pits and transport of concrete and the like, and the work process is complicated.
There is a problem that process management is difficult. In addition, since the work space is small, the use of a large excavator is restricted, and there is a problem that the construction period is prolonged, and there is a problem that the construction is dangerous. In addition, multiple advanced shafts and side shafts with small cross sections are constructed, and the earth retaining supports are connected to each other. -There was a problem that many skilled workers were required, and there was also a problem that the degree of danger was large.

【0012】一方、前記開放型シールド工法では、地山
が堅く、刃口の貫入が困難な場合は先堀りを行う必要が
あり、地表沈下を招くおそれがあった。
On the other hand, in the above-mentioned open shield construction method, when the ground is hard and it is difficult to penetrate the cutting edge, it is necessary to perform excavation, and there is a possibility that the surface will sink.

【0013】他方、シールドメッセル工法では、この工
法の適応土質は自立できる地質であり、しかも地山を緩
めないため、ある程度メッセル矢先を貫入させて掘削で
きる地層でなければならず、堅い岩盤には適さないとい
う問題がある。
On the other hand, in the shielded messel construction method, the soil suitable for this construction method is a geological structure capable of being self-sustaining, and in order not to loosen the ground, it must be a stratum capable of penetrating the messel arrowhead to some extent and excavating. There is a problem that is not suitable.

【0014】本発明は、上記の事情に鑑みなされたもの
で、その目的とするところは、大断面の横坑を能率よ
く、安全にかつ容易に施工でき、しかも地盤の性状を問
わず適用でき、さらに特殊な技量・技能を必要とせずに
掘削でき、かつ土留め支保工の組み立ても特殊な技量・
技能および機械器具を要せずに施工可能な横坑構築方法
を提供することにある。
The present invention has been made in view of the above circumstances, and an object of the present invention is to efficiently, safely and easily construct a large cross-section shaft, and to apply it regardless of the properties of the ground. The drilling can be performed without the need for special skills and skills.
It is an object of the present invention to provide a cross shaft construction method that can be constructed without the need for skills and machinery.

【0015】また、本発明の他の目的は、より一層安全
に横坑を掘削し得る横坑構築方法を提供することにあ
る。
Another object of the present invention is to provide a method for constructing a cross shaft capable of excavating a cross shaft more safely.

【0016】さらに、本発明の他の目的は、横坑の掘削
作業、土留め支保工の組み立て作業を機械化し、省力化
を図るとともに、前記横坑構築方法を的確に実施し得る
横坑構築装置を提供することにある。
Further, another object of the present invention is to mechanize the excavation work of the cross shaft and the assembling work of the earth retaining structure to save labor, and to construct the cross shaft capable of appropriately implementing the cross shaft construction method. It is to provide a device.

【0017】[0017]

【課題を解決するための手段】前記目的を達成するた
め、本発明横坑構築方法では、横坑32を掘削すべき領
域を取り囲む外殻1を形成し、この外殻1の掘削すべき
外殻内部2に対して、掘削作業空間5を有する掘削作業
構台3を設置し、前記外殻内部2を掘削機8を介し所定
延長まで掘削したのち、掘削作業構台3を前進させ、前
記掘削作業構台3の後方で土留め支保工26を組み立
て、横坑32を構築するようにしている。
In order to achieve the above object, according to the cross shaft construction method of the present invention, the outer shell 1 surrounding the area where the cross shaft 32 is to be excavated is formed, and the outer shell 1 to be excavated is formed. A digging work gantry 3 having a digging work space 5 is set in the shell inside 2, and after digging the outer shell inside 2 to a predetermined length via an excavator 8, the digging work gantry 3 is advanced and the digging work is performed. The earth retaining shoring 26 is assembled behind the gantry 3 to construct the horizontal shaft 32.

【0018】また、前記目的を達成するため、本発明横
坑構築方法では、外殻内部2に対して、複数の床版4に
より上下方向に多段に区画形成された掘削作業空間5を
有する掘削作業構台3を設置し、この掘削作業構台3の
各掘削作業空間5に床版4上を走行可能に掘削機8を配
置し、前記掘削作業構台3を固定した後、掘削機8によ
り外殻内部2を掘削する前に、外殻1の外周部の地山に
外殻内部2への浸水を防止する止水処理を施し、外殻内
部2には切羽の崩壊を防止しかつ切羽を自立保持するた
めの地盤改良を行うようにしている。
In order to achieve the above object, according to the cross shaft construction method of the present invention, an excavation work space 5 having a plurality of floor slabs 4 formed in a multi-tiered manner in an up-down direction with respect to an inner shell 2 is provided. After the work gantry 3 is installed, an excavator 8 is arranged in each digging work space 5 of the digging work gantry 3 so as to be able to run on the floor slab 4, and the digging work gantry 3 is fixed. Before excavating the interior 2, the ground around the outer periphery of the outer shell 1 is subjected to a water stoppage treatment to prevent infiltration into the interior 2 of the outer shell, and the inner surface 2 of the outer shell is prevented from collapsing and the face becomes independent. We are trying to improve the ground to maintain it.

【0019】さらに、前記目的を達成するため、本発明
横坑構築装置では横坑32を掘削すべき領域を取り囲む
ように形成された外殻1と、複数の床版4により上下方
向に多段に区画形成された掘削作業空間5を有する掘削
作業構台3と、この掘削作業構台3の各掘削作業空間5
において床版4上を走行可能に配置された複数台の掘削
機8と、掘削作業時には前記掘削作業構台3を固定し、
推進時には同掘削作業構台3の固定を解除する固定・解
放手段と、前記掘削機8から掘削土砂を受け取り、坑外
へ搬出する掘削土砂搬出手段と、前記掘削作業構台3を
推進させる複数本の推進ジャッキ13と、これら推進ジ
ャッキ13が反力を得る反力手段と、土留め支保工材2
5の把持装置18を有し、かつ少なくとも上下,左右方
向への移動および旋回可能に構成され、掘削された坑内
において掘削作業構台3の後方で土留め支保工26を組
み立てる支保工組み立て装置16と、土留め支保工26
や、これの組み立てに必要な資材を搬入し、前記支保工
組み立て装置16に引き渡す支保工組み立て資材搬入手
段とを装備している。
Further, in order to achieve the above object, in the horizontal shaft construction apparatus of the present invention, an outer shell 1 formed so as to surround an area where a horizontal shaft 32 is to be excavated, and a plurality of floor slabs 4 are provided in multiple stages in the vertical direction. Excavation work gantry 3 having sectioned digging work space 5, and each digging work space 5 of this digging work gantry 3
A plurality of excavators 8 arranged so as to be able to travel on the floor slab 4 and the excavation work gantry 3 during excavation work,
At the time of propulsion, fixing / releasing means for releasing the fixation of the excavating work gantry 3, excavating earth and sand carrying means for receiving excavated earth and sand from the excavator 8 and carrying it out of the mine, and a plurality of Propulsion jack 13, reaction force means for obtaining a reaction force by these propulsion jacks 13, earth retaining support material 2
And a supporter assembling device 16 that has a gripper 18 and is configured to be able to move and turn at least vertically and horizontally and to assemble the earth retaining supporter 26 behind the excavation work gantry 3 in the excavated mine. , Earth retaining support 26
Also, a supporter assembly material carrying means for carrying in materials necessary for assembling the supporter and transferring the material to the supporter assembly device 16 is provided.

【0020】[0020]

【発明の実施の形態】以下、本発明の実施例を図面に基
づいて説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0021】図1〜図9は本発明の一実施例を示すもの
で、図1は横坑構築装置における掘削作業・土留め支保
工組み立て作業・本体構築状態を示す縦断側面図、図2
の左半部は図1のA−A線,右半部は図1のB−B線断
面図、図3は図1のE部分の拡大図、図4,図5および
図6は横坑構築方法の第1,第2および第3段階の説明
図であって,当該段階における縦断側面図、図7は図6
のF−F線断面図、図8は図6のG−G線断面図、図9
の左半部は図1のC−C線,右半部は図1のD−D線断
面図である。
FIGS. 1 to 9 show an embodiment of the present invention. FIG. 1 is a longitudinal sectional side view showing a state of excavation work, earth retaining support assembling work, and main body construction state in a horizontal shaft construction apparatus, and FIG.
1 is a sectional view taken along the line AA in FIG. 1, the right half is a sectional view taken along the line BB in FIG. 1, FIG. 3 is an enlarged view of a portion E in FIG. 1, and FIGS. FIG. 7 is an explanatory view of the first, second, and third stages of the construction method, and is a vertical side view at that stage, and FIG.
8 is a sectional view taken along line FF of FIG. 9, FIG. 8 is a sectional view taken along line GG of FIG.
1 is a cross-sectional view taken along line CC of FIG. 1, and the right half is a cross-sectional view taken along line DD of FIG.

【0022】これらの図に示す実施例において、横坑構
築装置は外殻1と、掘削作業構台3と、掘削機8と、掘
削作業構台3の固定・解放手段である支保工ジャッキ9
と、掘削土砂搬出手段である幅広のベルトコンベア12
の列と、掘削作業構台3の推進ジャッキ13と、推進ジ
ャッキ13の反力手段である反力構台14や反力金物1
5と、土留め支保工材の把持装置18を有する支保工組
み立て装置16と、土留め支保工材などを搬入する支保
工組み立て資材搬入手段である天井走行式ホイストクレ
ーン(以下、「ホイスト」という。)22などを装備し
ている。
In the embodiment shown in these figures, the horizontal shaft construction apparatus comprises an outer shell 1, an excavating work gantry 3, an excavator 8, and a support jack 9 which is a means for fixing and releasing the excavating work gantry 3.
And a wide belt conveyor 12 which is a means for carrying out excavated earth and sand.
, The propulsion jack 13 of the excavation work gantry 3, the reaction force gantry 14, which is a reaction force means of the propulsion jack 13, and the reaction force hardware 1.
5, an assembling apparatus 16 having a retaining device 18 for holding a retaining material, and an overhead traveling hoist crane (hereinafter, referred to as a "hoist") serving as a supporting and assembling material carrying means for carrying the retaining material and the like. .) 22 and so on.

【0023】なお、図1および図2において、前後方向
をX−X、これと直交する左右方向をY−Y、上下方向
をZ−Z、左右方向の軸回りの旋回をαとしている。
In FIGS. 1 and 2, the front-back direction is XX, the right-left direction orthogonal to this is Y-Y, the up-down direction is ZZ, and the turning around the left-right axis is α.

【0024】前記外殻1は、パイプルーフ工法,外殻先
行のシールドまたは推進工法等で形成されるが、この実
施例ではパイプルーフ工法で形成されている。
The outer shell 1 is formed by a pipe roof method, a shield preceding the outer shell or a propulsion method. In this embodiment, the outer shell 1 is formed by a pipe roof method.

【0025】前記パイプルーフ工法は、比較的土被りが
浅く、しかも地上には道路または建物など沈下を許さな
い構造物がある場合や、未固結地質および断層破砕帯な
ど、軟弱な地質の箇所にトンネルを掘削する場合に、既
設構造物に対する防護処理や、山の緩みを極力軽減する
処置として用いられる工法である。
[0025] The pipe roof method has a relatively shallow earth cover, and there is a structure such as a road or a building on the ground which does not allow subsidence, or a place with soft geology such as unconsolidated geology or a fault crush zone. This method is used to protect existing structures when excavating tunnels, and to minimize the loosening of mountains.

【0026】そして、このパイプルーフ工法は横坑の掘
削に先立って、掘削断面の外周に沿ってある一定の間隔
をおいて鋼管をボーリングまたは圧入によって挿入し、
掘削すべき横坑の形状に合わせて鋼管の列により屋根
(ルーフ)を形成し、また横坑の掘削に伴ってこのルー
フ状の鋼管を支保工で直接支持し、掘削による地山の緩
みを抑止するとともに、地表への影響を少なくして安全
に施工するための工法である。
In this pipe roof construction method, prior to the excavation of the horizontal shaft, steel pipes are inserted by boring or press-fitting at a certain interval along the outer periphery of the excavated cross section.
A roof (roof) is formed by rows of steel pipes according to the shape of the horizontal shaft to be excavated, and the roof-shaped steel pipes are directly supported by supports with the excavation of the horizontal shaft, and loosening of the ground due to excavation is performed. This is a construction method to prevent deterrence and reduce the influence on the ground surface and to perform construction safely.

【0027】前記掘削作業構台3は、鋼製の骨組み構造
であり、複数段に敷設された床版4により、掘削作業空
間5が上下方向Z−Zに多段に区画形成されている。ま
た、各段の掘削作業空間5には、正面から見て、左右方
向Y−Yに所定の間隔をおいて筋交い6が張設されてい
る。さらに、掘削作業構台3は図1に示すように、沓構
造7上を前進移動するように配置されている。
The digging work gantry 3 is a steel frame structure, and digging work spaces 5 are formed in multiple stages in the vertical direction ZZ by floor slabs 4 laid in a plurality of stages. Also, in the excavation work space 5 of each step, a brace 6 is stretched at predetermined intervals in the left-right direction YY when viewed from the front. Further, as shown in FIG. 1, the excavation work gantry 3 is arranged to move forward on the shoe structure 7.

【0028】前記掘削機8には、バックホウを用いてい
る。また、掘削機8は掘削作業構台3の各段の掘削作業
空間5に配置されていて、外殻内部2を掘削するように
なっている。そして、各掘削機8は当該段の床版4上を
自由に走行する。なお、掘削機8が当該段において左右
方向Y−Yに移動するときは、前記筋交い6を盛り替え
る。
A backhoe is used for the excavator 8. The excavator 8 is arranged in the excavation work space 5 of each stage of the excavation work gantry 3 so as to excavate the inside 2 of the outer shell. Then, each excavator 8 freely travels on the floor slab 4 of the corresponding stage. When the excavator 8 moves in the left-right direction Y-Y at this stage, the brace 6 is changed.

【0029】前記掘削作業構台の固定・解放手段である
支保工ジャッキ9は、スプレッダ10の外面に複数個の
ローラ11を設けて構成されている。この支保工ジャッ
キ9は、図2に示すように、前記掘削作業構台3の外側
部と上部とに複数本ずつ装備されている。これらの支保
工ジャッキ9は、地山の掘削時には外殻1の内部に掘削
作業構台3を協働して固定し、掘削作業構台3の推進時
には同掘削作業構台3の固定を解除するとともに、複数
個のローラ11により外殻1を支持しながら掘削作業構
台3を推進させるようにしている。
The support jack 9, which is a means for fixing and releasing the excavating work gantry, comprises a plurality of rollers 11 provided on the outer surface of a spreader 10. As shown in FIG. 2, a plurality of the shoring jacks 9 are provided on the outer side and the upper part of the excavation work gantry 3. These support jacks 9 cooperate and fix the excavation work gantry 3 inside the outer shell 1 when excavating the ground, release the fixation of the excavation work gantry 3 when propelling the excavation work gantry 3, The excavation work gantry 3 is propelled while supporting the outer shell 1 with a plurality of rollers 11.

【0030】前記掘削土砂搬出手段であるベルトコンベ
ア12の列は、図1から分かるように、掘削機8から掘
削土砂を受け取り、その掘削土砂を坑外に搬出するよう
になっている。
As shown in FIG. 1, the row of the belt conveyor 12 serving as the excavated earth and sand discharging means receives the excavated earth and sand from the excavator 8 and carries the excavated earth and sand out of the pit.

【0031】前記推進ジャッキ13は、図1および図2
に示すように、掘削作業構台3の後側において、下部と
上部とにそれぞれ複数本ずつ設置されている。そして、
掘進初期の段階では図3に示すように、下部および上部
の推進ジャッキ13共、反力構台14に反力を取って掘
削作業構台3を推進させ、掘削作業構台3が坑内深くま
で推進されたのちは、図1に示すように、下部の推進ジ
ャッキ13は反力金物15に反力を取り、上部の推進ジ
ャッキ13は土留め支保工26や後述の本体構築27等
に反力を取り、下部と上部の推進ジャッキ13が協働し
て掘削作業構台3を推進させる。
The propulsion jack 13 is shown in FIGS.
As shown in the figure, a plurality of excavating work gantry 3 are installed at the lower side and the upper side, respectively. And
In the initial stage of the excavation, as shown in FIG. 3, the lower and upper propulsion jacks 13 propelled the excavation work gantry 3 by applying a reaction force to the reaction force gantry 14, and the excavation work gantry 3 was propelled deep inside the mine. Thereafter, as shown in FIG. 1, the lower propulsion jack 13 takes a reaction force on the reaction hardware 15, and the upper propulsion jack 13 takes a reaction force on the earth retaining support 26, a main body construction 27 described below, and the like. The lower and upper propulsion jacks 13 cooperate to propel the excavation work gantry 3.

【0032】前記支保工ジャッキ9および推進ジャッキ
13は、油圧回路に接続され、遠隔操作されるようにな
っている。
The shoring jack 9 and the propulsion jack 13 are connected to a hydraulic circuit and are remotely operated.

【0033】前記支保工組み立て装置16は、装置本体
17と、土留め支保工材の把持装置18と、上下移動用
レール19と、左右移動用レール20と、斜め移動用レ
ール(図示せず)と、旋回用レール21とを備えてい
る。前記装置本体17は、上下方向に伸縮可能に構成さ
れている。また、装置本体17は上下移動用レール1
9、左右移動用レール20および斜め移動用レールに沿
って上下方向Z−Z、左右方向Y−Yおよび斜め方向に
移動可能に構成され、かつ旋回用レール21に沿って旋
回αし得るように構成されている。前記土留め支保工材
の把持装置18は、装置本体17の背面上部に取り付け
られている。そして、この支保工組み立て装置16は図
1から分かるように、土留め支保工材25の把持装置1
8を後方に配しかつ左右移動用レール20を介して前記
掘削作業構台3の後部に取り付けられている。しかし
て、この支保工組み立て装置16は把持装置18により
土留め支保工材25を把持し、必要により上下方向Z−
Z、左右方向Y−Y、斜め方向に移動し、かつ旋回αを
して土留め支保工26を組み立て得るように構成されて
いる。
The shoring and assembling apparatus 16 includes an apparatus main body 17, an earth retaining shoring material holding device 18, a vertical moving rail 19, a left and right moving rail 20, and an oblique moving rail (not shown). And a turning rail 21. The device main body 17 is configured to be able to expand and contract in the vertical direction. Further, the apparatus main body 17 is provided with the vertical moving rail 1.
9, so as to be movable in the vertical direction Z-Z, the horizontal direction Y-Y and the diagonal direction along the left-right moving rail 20 and the diagonal moving rail, and to be able to turn α along the turning rail 21. It is configured. The retaining device 18 for retaining the earth retaining material is attached to an upper rear portion of the device main body 17. As can be seen from FIG. 1, the supporter assembling device 16 is a holding device 1 for the earth retaining supporter 25.
8 is arranged rearward and attached to the rear of the excavation work gantry 3 via a rail 20 for moving left and right. Then, this supporter assembling apparatus 16 grips the earth retaining supporter 25 by the gripper 18 and, if necessary,
It is configured to be able to move in the Z, left-right direction YY, diagonal directions and make a turn α to assemble the earth retaining support 26.

【0034】前記支保工組み立て資材搬入手段であるホ
イスト22は、図1に示すように、本体構築27に架設
された天井走行レール23に沿って、前後方向X−Xに
走行し、坑口から坑内に土留め支保工材25や組み立て
に必要な資材を搬入し、前記支保工組み立て装置16に
引き渡すようになっている。
As shown in FIG. 1, the hoist 22 as the support material assembling material carrying means travels in the front-rear direction XX along the ceiling traveling rail 23 erected on the main body construction 27, The shoring support material 25 and materials necessary for assembly are carried in to the shoring and assembling device 16.

【0035】次に、前述のごとく構成した横坑構築装置
の作用に関連して、本発明横坑構築方法の一例を説明す
る。
Next, an example of the cross shaft construction method of the present invention will be described in relation to the operation of the cross shaft construction apparatus configured as described above.

【0036】まず、横坑を掘削すべき領域を取り囲む外
殻1を形成する。この外殻1を形成するには、パイプル
ーフ工法,外殻先行のシールドまたは推進工法等により
行うが、この実施例ではパイプルーフ工法により外殻1
を形成している。
First, an outer shell 1 surrounding an area where a horizontal shaft is to be excavated is formed. The outer shell 1 is formed by a pipe roof method, a shield preceding the outer shell or a propulsion method. In this embodiment, the outer shell 1 is formed by the pipe roof method.
Is formed.

【0037】また、必要により外殻1の外周部の地山
に、外殻内部2への浸水を防止する止水処理を施すため
の薬液注入を行う。その薬液を注入した地山を図7に符
号2′で示す。
Further, if necessary, a chemical solution is injected into the ground at the outer peripheral portion of the outer shell 1 to perform a water stopping process for preventing water from entering the inner portion 2 of the outer shell. The ground into which the chemical has been injected is indicated by reference numeral 2 'in FIG.

【0038】さらに、外殻内部2には切羽の崩壊を防止
しかつ切羽を自立保持するための地盤改良を行うため、
全断面薬液注入を行う。
Further, in order to improve the ground for preventing the face from collapsing and maintaining the face independently,
Inject chemical solution in all sections.

【0039】ついで、鋼製でかつ骨組み構造で、複数段
(3段)の床版4により、上下方向Z−Zに複数段(4
段)の掘削作業空間5を有する掘削作業構台3を組み立
て、各段の掘削作業空間5の左右方向Y−Yに、筋交い
6を張設し、図4に示すように、その掘削作業構台3を
外殻1の前面に設置する。
Next, a plurality of (three-step) floor slabs 4 made of steel and having a framed structure are provided in a plurality of steps (4
The digging work gantry 3 having the digging work space 5 of the (stage) is assembled, and a brace 6 is stretched in the left-right direction Y-Y of the digging work space 5 of each stage, and as shown in FIG. Is placed in front of the outer shell 1.

【0040】また、前記掘削作業構台3の各掘削作業空
間5には、掘削機8を配置する。
An excavator 8 is arranged in each excavation work space 5 of the excavation work gantry 3.

【0041】さらに、反力構台14を組み立て、図3に
示すように、その反力構台14を掘削作業構台3の後方
に設置する。
Further, the reaction force gantry 14 is assembled, and the reaction force gantry 14 is installed behind the excavation work gantry 3 as shown in FIG.

【0042】前述のごとく掘削作業構台3および反力構
台14を設置したうえで、掘削作業構台3の各掘削作業
空間5に配置された掘削機8により外殻内部2の地山を
掘削する。かかる外殻内部2の地山の掘削に際しては、
掘削作業構台3の各掘削作業空間5の掘削機8を前後方
向X−Xおよび左右方向Y−Yに移動させ、上段の上部
から中段、下段へと掘削進捗が平均的になるようにし
て、例えば深度50cm位まで掘削する。そして、各段
の掘削作業空間5に配置された掘削機8を左右方向Y−
Yに移動させるときは、筋交い6を盛り替える。
After the excavation work gantry 3 and the reaction force gantry 14 are installed as described above, the ground inside the outer shell 2 is excavated by the excavator 8 arranged in each excavation work space 5 of the excavation work gantry 3. When excavating the ground inside the outer shell 2,
The excavator 8 of each excavation work space 5 of the excavation work gantry 3 is moved in the front-rear direction XX and the left-right direction YY so that the excavation progress is averaged from the upper part of the upper part to the middle part and the lower part, For example, excavation is performed to a depth of about 50 cm. Then, the excavator 8 arranged in the excavation work space 5 of each stage is moved in the left-right direction Y-
When moving to Y, brace 6 is changed.

【0043】前記掘削作業構台3の下部には、この掘削
作業構台3の切羽側への推進移動を容易にするため、鉄
板による沓構造7を敷設する。
Under the excavating work gantry 3, a shoe structure 7 made of an iron plate is laid to facilitate the propulsion movement of the excavating gantry 3 toward the face.

【0044】このようにして、外殻内部2を例えば50
cm位の所定深度まで掘進したのち、掘削初期の段階で
は反力構台14に反力を取って推進ジャッキ13により
掘削作業構台3を切羽側へ前進させる。
In this manner, the inside 2 of the outer shell is
After digging to a predetermined depth of about cm, in the initial stage of digging, a reaction force is applied to the reaction force gantry 14 and the excavation work gantry 3 is advanced to the face side by the propulsion jack 13.

【0045】掘削作業構台3が外殻内部2の坑内に入る
まで掘削が進んだときは、図5に示すように、掘削作業
時には複数本の支保工ジャッキ9をそれぞれ伸長させ、
各支保工ジャッキ9のスプレッダ10に設けられた複数
個のローラ11を外殻1の内側に押し付け、外殻1に掘
削作業構台3を固定する。
When excavation has proceeded until the excavation work gantry 3 enters the inside of the hull inside the outer shell 2, as shown in FIG. 5, a plurality of support jacks 9 are extended during the excavation work, respectively.
A plurality of rollers 11 provided on a spreader 10 of each support jack 9 are pressed against the inside of the outer shell 1 to fix the excavation work gantry 3 to the outer shell 1.

【0046】また、外殻内部2を所定深度まで掘進した
のち、掘削作業構台3の後方で、支保工組み立て装置1
6により土留め支保工26を組み立てる。この土留め支
保工26の組み立て作業時には、作業員の補助作業足場
として、上下,左右移動可能な昇降作業台(図示せず)
を使用する。土留め支保工材25や支保工組み立て資材
は、クレーン(図示せず)等を用いて坑外から坑口に搬
入する。
After the inside of the outer shell 2 has been dug to a predetermined depth, the shoring assembly device 1
6 to assemble the earth retaining support 26. At the time of assembling the earth retaining support 26, an ascending and descending work platform (not shown) that can be moved up and down and left and right is used as an auxiliary work platform for the worker.
Use The earth retaining shoring material 25 and the shoring assembling material are carried into the wellhead from outside the mine using a crane (not shown) or the like.

【0047】土留め支保工26の組み立てに当たって
は、支保工組み立て装置16に設けられた把持装置18
により土留め支保工材25や支保工組み立て資材を把持
し、組み立て装置本体17を上下移動用レール19、左
右移動用レール20および旋回用レール21に沿って組
み立てに必要な位置に移動させて行い、図4に示すよう
に、土留め支保工26を組み立てる。
When assembling the earth retaining shoring 26, the holding device 18 provided in the shoring assembling device 16 is used.
By holding the earth retaining support material 25 and the support assembling material, the assembling apparatus main body 17 is moved along the vertical movement rail 19, the horizontal movement rail 20, and the turning rail 21 to a position required for assembly. As shown in FIG. 4, the earth retaining shoring 26 is assembled.

【0048】掘削が外殻内部2の深くまで進んだとき
は、掘削土砂24を搬出するベルトコンベア12を必要
により複数台組み合わせて設置する。
When the excavation has proceeded deep into the inside of the outer shell 2, a plurality of belt conveyors 12 for carrying out the excavated soil 24 are installed in combination as necessary.

【0049】ついで、図2に示すように、掘削作業構台
3の各掘削作業空間5内に配置された掘削機8により外
殻内部2の地山を掘削し、その掘削土砂24をベルトコ
ンベア12の列により坑外に搬出し、掘削を続ける。
Next, as shown in FIG. 2, the ground inside the outer shell 2 is excavated by an excavator 8 arranged in each excavation work space 5 of the excavation work gantry 3, and the excavated soil 24 is conveyed to the belt conveyor 12. Rows carry off the mine and continue excavation.

【0050】外殻内部2の地山を再び所定の深度まで延
長して掘削したときは、支保工ジャッキ9をそれぞれ縮
小させ、掘削作業構台3の固定を解除し、各支保工ジャ
ッキ9のスプレッダ10に設けられたローラ11により
外殻1を支持しながら推進させ得るようにする。
When the ground inside the outer shell 2 is extended to the predetermined depth again and excavated, the support jacks 9 are respectively reduced, the fixing of the excavation work gantry 3 is released, and the spreader jacks of the respective support jacks 9 are spread. The outer shell 1 can be propelled while being supported by the rollers 11 provided on the outer shell 1.

【0051】また、掘削された外殻内部2の下部側に、
推進ジャッキ用の反力金物15を固定する。そして、下
部の推進ジャッキ13は反力金物15に反力を取り、上
部の推進ジャッキ13は土留め支保工26などの外殻1
に固定された構造体に反力を取って掘削作業構台3を前
進させる。このとき、各支保工ジャッキ9のスプレッダ
10に設けられたローラ11により外殻1を支持しつつ
掘削作業構台3を容易に移動させることができる。
Further, on the lower side of the excavated shell inner portion 2,
The reaction hardware 15 for the propulsion jack is fixed. The lower propulsion jack 13 applies a reaction force to the reaction hardware 15, and the upper propulsion jack 13 applies the outer shell 1 such as the earth retaining support 26.
The excavation work gantry 3 is advanced by taking a reaction force to the structure fixed to the digging work gantry 3. At this time, the excavation work gantry 3 can be easily moved while the outer shell 1 is supported by the rollers 11 provided on the spreaders 10 of the respective support jacks 9.

【0052】さらに掘削作業が進んで、1スパン分の構
造物を構築する距離、例えば約7〜8mまで進捗させた
のち、図6に示すように組み立てられた複数本の土留め
支保工26にわたって本体構築27を行う。
Excavation work proceeds further, and after advancing to a distance for constructing a structure for one span, for example, about 7 to 8 m, a plurality of earth retaining supports 26 assembled as shown in FIG. The main body construction 27 is performed.

【0053】この本体構築27は、下床版28と、この
実施例では上下2段の側壁29,30と、上床版31を
築造して行う。
The main body construction 27 is performed by constructing a lower floor slab 28, in this embodiment, upper and lower two side walls 29, 30 and an upper floor slab 31.

【0054】前記本体構築27を行ったのち、その内部
にホイスト用の天井走行レール23を架設し、この天井
走行レール23に、前後方向X−Xに走行自在にホイス
ト22を装架する。
After the main body 27 has been constructed, a hoist ceiling travel rail 23 is installed inside the main body 27, and the hoist 22 is mounted on the ceiling travel rail 23 so as to be able to travel in the front-rear direction XX.

【0055】そして、前記ホイスト22により坑口側か
ら坑内に土留め支保工材25や支保工組み立て資材を搬
入し、支保工組み立て装置16における把持装置18に
引き渡し、支保工組み立て装置16により土留め支保工
26を組み立てる。
Then, the earth retaining support material 25 and the material for the assembling work are carried into the pit from the wellhead side by the hoist 22 and delivered to the gripping device 18 in the assembling and assembling apparatus 16. Assembly 26 is assembled.

【0056】以上のように、この実施例によれば、
(1)支保工ジャッキ9を伸長させることによる掘削作
業構台3の固定、(2)掘削作業構台3の各段の掘削作
業空間5に配置された掘削機8による外殻内部2の地山
の掘削、(3)ベルトコンベア12の列による掘削土砂
24の坑外への搬出、(4)支保工ジャッキ9を縮小さ
せることによる掘削作業構台3の固定の解除、(5)推
進ジャッキ13による掘削作業構台3の前進、(6)ホ
イスト22による土留め支保工材25および支保工組み
立て資材の搬入・支保工組み立て装置16の把持装置1
8への引き渡し、(7)支保工組み立て装置16による
土留め支保工26の組み立て、(8)複数本にわたる土
留め支保工26への本体構築27の築造、の作業を繰り
返して行い、所期の横坑32の構築を行う。
As described above, according to this embodiment,
(1) fixation of the excavation work gantry 3 by extending the shoring jack 9; (2) the ground inside the outer shell 2 by the excavator 8 arranged in the excavation work space 5 of each stage of the digging work gantry 3 Excavation, (3) unloading of excavated earth and sand 24 by the row of belt conveyor 12, (4) release of fixing of excavation work gantry 3 by reducing support jack 9, (5) excavation by propulsion jack 13 Advancement of the work gantry 3; (6) Gripping device 1 of loading / supporting assembling device 16 for loading / supporting assembling material 25 and supporting assembling material by hoist 22
8 and (7) assembling the earth retaining shoring 26 by the shoring assembling apparatus 16 and (8) constructing the main body construction 27 on the plurality of earth retaining shorings 26. Of the horizontal shaft 32 is constructed.

【0057】なお、万が一の地山の崩壊に備えて、大規
模な地山崩壊が起こらないように、各作業床の中間に棚
(図示せず)を設ける。また、場合によっては、掘削作
業構台3の前方に、地山切羽を押さえるフェースジャッ
キ(これも図示せず)を装備する。
In preparation for the collapse of the ground, a shelf (not shown) is provided in the middle of each work floor so that a large-scale collapse of the ground does not occur. In some cases, a face jack (also not shown) for holding the ground face is provided in front of the excavation work gantry 3.

【0058】前述のごとく、この実施例では横坑32を
掘削すべき領域を外殻1により取り囲み、この外殻1の
掘削すべき外殻内部2に対して、複数の床版4により上
下方向Z−Zに多段に区画形成された掘削作業空間5を
有する掘削作業構台3を設置し、この掘削作業構台3の
各掘削作業空間5に、床版4上を走行可能に掘削機8を
配置し、これら上下方向Z−Zに複数台配置された掘削
機8により外殻内部2を直接掘削するようにしているの
で、大断面の横坑32を容易に掘削することができる
し、地盤の性状を問わず適用することができる。
As described above, in this embodiment, the area where the horizontal shaft 32 is to be excavated is surrounded by the outer shell 1, and the inside 2 of the outer shell 1 where the excavation is to be excavated is covered by the plurality of floor slabs 4 in the vertical direction. A digging work gantry 3 having a digging work space 5 formed in multiple stages in ZZ is installed, and an excavator 8 is arranged in each digging work space 5 of the digging work gantry 3 so as to be able to travel on a floor slab 4. Since the inside 2 of the outer shell is directly excavated by the plurality of excavators 8 arranged in the vertical direction Z-Z, the horizontal shaft 32 having a large cross section can be easily excavated, and Applicable regardless of properties.

【0059】また、この実施例では掘削作業構台3の上
下方向Z−Zに多段に区画形成された各掘削作業空間5
に配置された複数台の掘削機8により外殻内部2の地山
を掘削し、その掘削土砂24を坑外に搬出し、所定深度
まで掘削後、掘削作業構台3を切羽側へ前進させ、掘削
作業構台3の後方で土留め支保工26を組み立て、その
組み立てられた複数本の土留め支保工26にわたって本
体構築27を築造するようにしており、作業工程が単純
で、工程管理も簡単であり、作業広間を広く取ることが
できるため、作業がしやすい点で、大断面の横坑32を
効率よく構築でき、したがって施工期間を短縮できる
し、横坑32の掘削作業および土留め支保工26の組み
立て作業共、特殊な技量・技能、機械器具を要すること
なく構築できるし、外殻内部2の地山の掘削時には掘削
作業構台3を固定するようにしており、しかも土留め支
保工26の組み立て作業を広い空間で行い得る点で、地
山の掘削作業や土留め支保工26の組み立て作業を安全
に遂行することができる。
In this embodiment, each excavation work space 5 formed in multiple stages in the vertical direction ZZ of the excavation work gantry 3 is formed.
Excavation of the ground inside the outer shell 2 is carried out by a plurality of excavators 8 arranged in the ground, the excavated earth 24 is carried out of the mine, and after excavation to a predetermined depth, the excavation work gantry 3 is advanced to the face side, The earth retaining shoring 26 is assembled behind the excavation work gantry 3, and the main body construction 27 is constructed over the assembled plurality of earth retaining shorings 26, so that the working process is simple and the process management is easy. In addition, since the work hall can be widened, the work can be easily performed, so that the cross section 32 having a large cross section can be efficiently constructed, and therefore, the construction period can be shortened. 26 can be constructed without the need for special skills, skills, and machinery, and the excavation work gantry 3 is fixed when excavating the ground inside the outer shell 2, and the earth retaining support 26 Assembling In that it can be carried out the work in a wide space, it is possible to safely carry out the assembly work of excavation work and earth retaining 支保 Engineering 26 of the natural ground.

【0060】また、この実施例では外殻内部2の掘削開
始前に、外殻1の外周部の地山に外殻内部2への止水処
理を施すための薬液注入を行い、外殻内部2には切羽の
崩壊を防止しかつ切羽を自立保持するための地盤改良を
行うため、全断面薬液注入を行っているので、より一層
安全に横坑32を掘削することができる。
Further, in this embodiment, before starting the excavation of the inside of the outer shell 2, a chemical solution is injected into the ground around the outer periphery of the outer shell 1 to perform a water stopping process on the inner surface of the outer shell 2. In No. 2, the chemical liquid is injected in all cross-sections in order to prevent the collapse of the face and to improve the ground for maintaining the face independently, so that the horizontal shaft 32 can be excavated even more safely.

【0061】さらに、この実施例では横坑32を掘削す
べき領域を取り囲むように形成された外殻1と、複数の
床版4により上下方向Z−Zに多段に区画形成された掘
削作業空間5を有する掘削作業構台3と、掘削作業構台
3の各掘削作業空間5に配置されかつ床版4上を走行可
能に配置された複数台の掘削機8と、掘削作業時には掘
削作業構台3を固定し、推進時には掘削作業構台3の固
定を解除する支保工ジャッキ9と、掘削機8から掘削土
砂24を受け取り、坑外に搬出するベルトコンベア12
の列と、掘削作業構台3を推進させる複数本の推進ジャ
ッキ13と、土留め支保工材25の把持装置18を有
し、かつ少なくとも上下方向Z−Z,左右方向Y−Y,
斜め方向への移動および左右方向Y−Yの軸回りの旋回
αを行い得るように構成され、しかも掘削作業構台3の
後方で土留め支保工26を組み立てる支保工組み立て装
置16と、土留め支保工材25やこれの組み立てに必要
な資材を搬入し、支保工組み立て装置16に引き渡すホ
イスト22とを装備しているので、横坑32の掘削作
業、土留め支保工26の組み立て作業を機械化し、省力
化を図ることができるし、横坑構築方法を的確に実施す
ることができる。
Further, in this embodiment, an outer shell 1 formed so as to surround an area where the horizontal shaft 32 is to be excavated, and an excavating work space partitioned in multiple stages in the vertical direction ZZ by a plurality of floor slabs 4. 5, a plurality of excavators 8 arranged in each excavation work space 5 of the excavation work gantry 3 so as to be able to travel on the floor slab 4, and the excavation work gantry 3 during the excavation work. A fixing jack 9 for fixing and releasing the fixing of the excavating work gantry 3 at the time of propulsion, and a belt conveyor 12 for receiving excavated earth and sand 24 from the excavator 8 and carrying it out of the mine.
, A plurality of propulsion jacks 13 for propelling the excavation work gantry 3, and a gripping device 18 for the earth retaining support material 25, and at least the vertical direction ZZ, the horizontal direction YY,
A shoring assembling device 16 configured to perform a diagonal movement and a turning α around the axis in the left-right direction Y-Y, and to assemble the shoring support 26 behind the digging work gantry 3; Since it is equipped with the hoist 22 which carries in the work material 25 and the materials necessary for assembling the same and transfers it to the shoring and assembling apparatus 16, the excavation work of the horizontal shaft 32 and the assembling work of the earth retaining shoring 26 are mechanized. Therefore, labor saving can be achieved, and the cross shaft construction method can be implemented accurately.

【0062】そして、この実施例では各支保工ジャッキ
9のスプレッダ10に、複数個のローラ11を設けてい
るので、掘削作業構台3の固定を解除した推進時に、前
記ローラ11によって外殻1を支持しながら掘削作業構
台3を推進させることができる。
In this embodiment, the spreader 10 of each support jack 9 is provided with a plurality of rollers 11, so that when the excavation work gantry 3 is released from being fixed, the outer shell 1 is moved by the rollers 11. The excavation work gantry 3 can be propelled while being supported.

【0063】なお、本発明において、各部の具体的な構
造は図面に示すものに限らず、所期の機能を有するもの
であればよい。
In the present invention, the specific structure of each part is not limited to that shown in the drawings, but may be any as long as it has a desired function.

【0064】[0064]

【発明の効果】以上説明したように、本発明横坑構築方
法では、横坑32を掘削すべき領域を取り囲む外殻1を
形成し、この外殻1の掘削すべき外殻内部2に対して、
掘削作業空間5を有する掘削作業構台3を設置し、掘削
機8により外殻内部2の地山を直接掘削するようにして
いるので、大断面の横坑32を容易に掘削し得る効果が
あり、地盤の性状を問わず、適用することができるとい
う効果がある。
As described above, according to the cross shaft construction method of the present invention, the outer shell 1 surrounding the area where the cross shaft 32 is to be excavated is formed, and the outer shell 1 of the outer shell 1 to be excavated is formed. hand,
Since the excavation work gantry 3 having the excavation work space 5 is installed and the excavator 8 directly excavates the ground inside the outer shell 2, there is an effect that the horizontal shaft 32 having a large cross section can be easily excavated. There is an effect that it can be applied regardless of the properties of the ground.

【0065】また、本発明横坑構築方法では、掘削作業
構台3の上下方向Z−Zに多段に区画形成された各掘削
作業空間5に配置された掘削機8により外殻内部2を掘
削し、所定延長まで掘削したのち、掘削作業構台3を前
進させ、この掘削作業構台3の後方で土留め支保工26
を組み立て、横坑32を構築するようにしている。その
結果、作業工程が単純で、工程管理も簡単であり、作業
空間を広く取ることができるため、作業がしやすい点
で、横坑32を効率よく構築でき、したがって施工期間
を短縮し得る効果があり、横坑32の掘削作業および土
留め支保工26の組み立て作業共、特殊な技量・技能、
特殊な機械器具を要することなく構築できるという効果
がある。
Further, in the cross shaft construction method of the present invention, the inside of the outer shell 2 is excavated by the excavator 8 disposed in each excavation work space 5 formed in multiple stages in the vertical direction ZZ of the excavation work gantry 3. After digging to a predetermined extension, the digging work gantry 3 is advanced, and the earth retaining support 26
To assemble the shaft 32. As a result, the work process is simple, the process management is simple, and the work space can be widened, so that the work can be easily performed, so that the horizontal shaft 32 can be efficiently constructed, and the construction period can be shortened. Both the excavation work of the horizontal shaft 32 and the assembling work of the earth retaining shoring 26 have special skills and skills,
There is an effect that it can be constructed without requiring special machinery and equipment.

【0066】また、本発明横坑構築方法では、外殻内部
2の掘削時には掘削作業構台3を固定するようにしてお
り、しかも外殻内部2を所定延長まで掘削したのち、掘
削作業構台3の固定を解除したうえで前進させ、この掘
削作業構台3の後方の、広い作業空間で土留め支保工2
6を組み立てるようにしている点で、地山の掘削作業や
土留め支保工26の組み立て作業を安全に遂行し得る効
果がある。
In the method of constructing the cross shaft according to the present invention, the excavation work gantry 3 is fixed when excavating the inside of the outer shell 2. After releasing the fixation, the ship is moved forward, and the earth retaining shoring 2 is provided in a wide working space behind the digging work gantry 3.
6 has an effect that the excavation work of the ground and the assembling work of the earth retaining support 26 can be safely performed.

【0067】また、本発明横坑構築方法では、外殻内部
2の掘削開始前に、外殻1の外周部の地山に、外殻内部
2への浸水を防止する止水処理を施し、外殻内部2には
切羽の崩壊を防止しかつ切羽を自立保持するための地盤
改良を行うようにしているので、横坑32をより一層安
全に掘削し得る効果がある。
Further, in the cross shaft construction method of the present invention, before excavation of the inside of the outer shell 2 is started, the ground around the outer periphery of the outer shell 1 is subjected to a water stoppage treatment for preventing infiltration into the inner shell 2. Since the outer shell interior 2 is made to improve the ground to prevent collapse of the face and to maintain the face independently, there is an effect that the horizontal shaft 32 can be excavated more safely.

【0068】さらに、本発明横坑構築装置では、横坑3
2を掘削すべき領域を取り囲むように形成された外殻1
と、複数の床版4により上下方向Z−Zに多段に区画形
成された掘削作業空間5を有する掘削作業構台3と、こ
の掘削作業構台3の各掘削作業空間5において床版4上
を走行可能に配置された複数台の掘削機8と、掘削作業
時には前記掘削作業構台3を固定し、推進時には同掘削
作業構台3の固定を解除する固定・解放手段と、前記掘
削機8から掘削土砂24を受け取り、坑外に搬出する掘
削土砂搬出手段と、前記掘削作業構台3を推進させる複
数本の推進ジャッキ13と、これら推進ジャッキ13が
反力を得る反力手段と、土留め支保工材25の把持装置
18を有し、かつ少なくとも上下,左右方向への移動お
よび旋回可能に構成され、掘削された坑内において掘削
作業構台3の後方で土留め支保工26を組み立てる支保
工組み立て装置16と、土留め支保工25や、これの組
み立てに必要な資材を搬入し、前記支保工組み立て装置
16に引き渡す支保工組み立て資材搬入手段とを装備し
ているので、横坑32の掘削作業、土留め支保工26の
組み立て作業を機械化し、省力化を図り得る効果があ
り、前記本発明横坑構築方法を的確に実施し得る効果を
も有する。
Further, in the horizontal shaft construction apparatus of the present invention, the horizontal shaft 3
An outer shell 1 formed so as to surround an area to be excavated 2
A digging work gantry 3 having a plurality of digging work spaces 5 formed in multiple stages in the vertical direction ZZ by a plurality of floor slabs 4, and traveling on the slab 4 in each of the digging work spaces 5 of the digging work gantry 3 A plurality of excavators 8 arranged so as to be capable of being fixed; a fixing / releasing means for fixing the excavation work gantry 3 during excavation work and releasing the fixation of the excavation work gantry 3 during propulsion; 24, receiving means 24 for carrying out the excavated earth and sand, a plurality of propulsion jacks 13 for propelling the excavation work gantry 3, reaction force means for obtaining a reaction force by the propulsion jacks 13, and earth retaining support materials A shoring assembling device 1 having 25 gripping devices 18 and capable of moving and turning at least vertically and horizontally, and assembling the earth retaining shoring 26 behind the excavation work gantry 3 in an excavated mine. And the earth retaining shoring 25 and the material necessary for assembling the earth retaining shovel 25 and the means for transferring the shoring assembling material to be transferred to the shoring and assembling apparatus 16 are provided. There is an effect that the assembling work of the clasp support 26 can be mechanized to save labor, and also has an effect that the above-described cross shaft construction method of the present invention can be accurately executed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例を示すもので、横坑構築装置
における掘削作業・土留め支保工組み立て作業・本体構
築状態を示す縦断側面図である。
FIG. 1 shows an embodiment of the present invention, and is a vertical sectional side view showing an excavation operation, an earth retaining support assembling operation, and a main body construction state in a horizontal shaft construction apparatus.

【図2】左半部は図1のA−A線断面図、右半部は図1
のB−B線断面図である。
2 is a cross-sectional view taken along the line AA of FIG. 1 in the left half, and FIG.
FIG. 7 is a sectional view taken along line BB of FIG.

【図3】図1のE部分の拡大図である。FIG. 3 is an enlarged view of a portion E in FIG. 1;

【図4】本発明横坑構築方法の第1段階の説明図であ
る。
FIG. 4 is an explanatory diagram of a first stage of the cross shaft construction method of the present invention.

【図5】同横坑構築方法の第2段階の説明図である。FIG. 5 is an explanatory diagram of a second stage of the horizontal shaft construction method.

【図6】同横坑構築方法の第3段階の説明図である。FIG. 6 is an explanatory diagram of a third stage of the horizontal shaft construction method.

【図7】図6のF−F線断面図である。FIG. 7 is a sectional view taken along line FF of FIG. 6;

【図8】図6のG−G線断面図である。FIG. 8 is a sectional view taken along line GG of FIG. 6;

【図9】左半部は図1のC−C線断面図、右半部は図1
のD−D線断面図である。
9 is a cross-sectional view taken along the line CC of FIG. 1 in the left half, and FIG.
FIG. 4 is a sectional view taken along line DD of FIG.

【図10】従来技術の説明図であって、先進導坑におい
て、上半先進導坑の施工状態を示す図である。
FIG. 10 is an explanatory view of a conventional technique, and is a view showing a construction state of an upper half advanced shaft in an advanced shaft.

【図11】他の従来技術の説明図であって、解放型シー
ルド工法による横坑の施工状態を示す図である。
FIG. 11 is an explanatory view of another conventional technique, and is a view showing a construction state of a horizontal shaft by an open shield method.

【符号の説明】[Explanation of symbols]

1 外殻 2 外殻内部 3 掘削作業構台 4 掘削作業構台の床版 5 掘削作業空間 8 掘削機 9 掘削作業構台の固定・解放手段である支保工ジャ
ッキ 10 支保工ジャッキのスプレッダ 11 スプレッダに設けられた複数個のローラ 12 掘削土砂搬出手段であるベルトコンベア 13 推進ジャッキ 14 反力手段である反力構台 15 反力手段である反力金物 16 支保工組み立て装置 17 組み立て装置本体 18 土留め支保工材の把持装置 19 上下移動用レール 20 左右移動用レール 21 旋回用レール 22 支保工組み立て資材搬入手段であるホイスト 23 ホイストの天井走行レール 25 土留め支保工材 26 土留め支保工 27 本体構築 28 本体構築の下床版 29,30 本体構築の側壁 31 本体構築の上床版 32 横坑
DESCRIPTION OF SYMBOLS 1 Outer shell 2 Outer shell inside 3 Excavation work gantry 4 Floor slab of excavation work gantry 5 Excavation work space 8 Excavator 9 Shoring jack which is a fixing and releasing means of excavating work gantry 10 Spreader of shoring jack 11 Provided on spreader A plurality of rollers 12 a belt conveyor as an excavated earth and sand unloading means 13 a propulsion jack 14 a reaction force gantry as a reaction force means 15 a reaction force hardware 16 as a reaction force means 16 support assembling apparatus 17 assembling apparatus body 18 earth retaining support material Gripping device 19 vertical moving rail 20 left / right moving rail 21 turning rail 22 hoist as hoisting assembling material carrying means 23 hoist ceiling running rail 25 earth retaining material 26 earth retaining material 27 body construction 28 body construction Lower floor slab 29,30 Side wall of main body construction 31 Upper floor slab of main body construction 32 Horizontal shaft

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.7 識別記号 FI テーマコート゛(参考) E21D 11/40 E21D 11/40 A (72)発明者 宮澤 勝光 東京都中央区新川1丁目24番4号 大豊建 設株式会社内 Fターム(参考) 2D054 AC20 BA22 DA02 FA02 2D055 BA09 BB03 GA04 GB01 GB07──────────────────────────────────────────────────の Continued on the front page (51) Int.Cl. 7 Identification symbol FI Theme coat ゛ (Reference) E21D 11/40 E21D 11/40 A (72) Inventor Katsumitsu Miyazawa 1-4-4 Shinkawa, Chuo-ku, Tokyo F-term (reference) in Taihoken Corporation 2D054 AC20 BA22 DA02 FA02 2D055 BA09 BB03 GA04 GB01 GB07

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 横坑(32)を掘削すべき領域を取り囲
む外殻(1)を形成し、 この外殻(1)の掘削すべき外殻内部(2)に対して、
掘削作業空間(5)を有する掘削作業構台(3)を設置
し、前記外殻内部(2)を掘削機(8)を介し所定延長
まで掘削したのち、掘削作業構台(3)を前進させ、前
記掘削作業構台(3)の後方で土留め支保工(26)を
組み立て、横坑(32)を構築することを特徴とする横
坑構築方法。
An outer shell (1) surrounding an area in which a shaft (32) is to be excavated is formed, and the outer shell (2) of the outer shell (1) is excavated.
A digging work gantry (3) having a digging work space (5) is installed, and after excavating the inside of the outer shell (2) to a predetermined length through an excavator (8), the digging work gantry (3) is advanced, A method for constructing a cross shaft, comprising assembling an earth retaining support (26) behind the excavation work gantry (3) and constructing a cross shaft (32).
【請求項2】 外殻内部(2)に対して、複数の床版
(4)により上下方向に多段に区画形成された掘削作業
空間(5)を有する掘削作業構台(3)を設置し、この
掘削作業構台(3)の各掘削作業空間(5)に床版
(4)上を走行可能に掘削機(8)を配置し、前記掘削
作業構台(3)を固定した後、掘削機(8)により外殻
内部(2)を掘削する前に、外殻(1)の外周部の地山
に外殻内部(2)への浸水を防止する止水処理を施し、
外殻内部(2)には切羽の崩壊を防止しかつ切羽を自立
保持するための地盤改良を行うことを特徴とする請求項
1記載の横坑構築方法。
2. An excavation work gantry (3) having an excavation work space (5) partitioned into a plurality of stages in a vertical direction by a plurality of floor slabs (4) is installed inside the outer shell (2); An excavator (8) is arranged in each excavation work space (5) of the excavation work gantry (3) so as to be able to run on the floor slab (4), and the excavation work gantry (3) is fixed. Before excavating the inside of the outer shell (2) according to 8), the ground around the outer periphery of the outer shell (1) is subjected to a water stoppage treatment to prevent infiltration into the inner shell (2),
The cross shaft construction method according to claim 1, wherein soil improvement is performed inside the outer shell (2) to prevent collapse of the face and maintain the face independently.
【請求項3】 横坑(32)を掘削すべき領域を取り囲
むように形成された外殻(1)と、 複数の床版(4)により上下方向に多段に区画形成され
た掘削作業空間(5)を有する掘削作業構台(3)と、 この掘削作業構台(3)の各掘削作業空間(5)におい
て床版(4)上を走行可能に配置された複数台の掘削機
(8)と、 掘削作業時には前記掘削作業構台(3)を固定し、推進
時には同掘削作業構台(3)の固定を解除する固定・解
放手段と、 前記掘削機(8)から掘削土砂を受け取り、坑外へ搬出
する掘削土砂搬出手段と、 前記掘削作業構台(3)を推進させる複数本の推進ジャ
ッキ(13)と、これら推進ジャッキ(13)が反力を
得る反力手段と、 土留め支保工材(25)の把持装置(18)を有し、か
つ少なくとも上下,左右方向への移動および旋回可能に
構成され、掘削された坑内において掘削作業構台(3)
の後方で土留め支保工(26)を組み立てる支保工組み
立て装置(16)と、 土留め支保工材(25)や、これの組み立てに必要な資
材を搬入し、前記支保工組み立て装置(16)に引き渡
す支保工組み立て資材搬入手段と、を装備していること
を特徴とする横坑構築装置。
3. An excavation work space formed in a vertical multi-tiered manner by an outer shell (1) formed so as to surround an area where a horizontal shaft (32) is to be excavated, and a plurality of floor slabs (4). An excavation work gantry (3) having a digging work gantry (5); and a plurality of excavators (8) arranged so as to be able to travel on a floor slab (4) in each digging work space (5) of the digging work gantry (3). Fixing and releasing means for fixing the excavating work gantry (3) during excavation work and releasing the fixing of the excavating work gantry (3) during propulsion; receiving excavated earth and sand from the excavator (8); Excavated earth and sand unloading means for unloading, a plurality of propulsion jacks (13) for propelling the excavation work gantry (3), reaction force means for obtaining a reaction force by these propulsion jacks (13), and earth retaining support materials ( 25) having a gripping device (18) and at least up and down, left and right Excavation work gantry (3) configured to be movable and swivel in the direction and excavated in the mine
A shoring assembly device (16) for assembling an earth retaining shoring (26) at the back of the pier, a soil retaining shoring material (25), and materials necessary for assembling the same, are carried in, and the shoring assembling device (16) And a means for carrying in assembling materials to be delivered to a mine shaft.
JP23515899A 1999-08-23 1999-08-23 Horizontal shaft construction method and horizontal shaft construction device Expired - Fee Related JP4034481B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23515899A JP4034481B2 (en) 1999-08-23 1999-08-23 Horizontal shaft construction method and horizontal shaft construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23515899A JP4034481B2 (en) 1999-08-23 1999-08-23 Horizontal shaft construction method and horizontal shaft construction device

Publications (2)

Publication Number Publication Date
JP2001059393A true JP2001059393A (en) 2001-03-06
JP4034481B2 JP4034481B2 (en) 2008-01-16

Family

ID=16981920

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23515899A Expired - Fee Related JP4034481B2 (en) 1999-08-23 1999-08-23 Horizontal shaft construction method and horizontal shaft construction device

Country Status (1)

Country Link
JP (1) JP4034481B2 (en)

Also Published As

Publication number Publication date
JP4034481B2 (en) 2008-01-16

Similar Documents

Publication Publication Date Title
JP7125550B2 (en) SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH
CN109555528B (en) Pass through that high angle is inverse to rush rich water richness sand tomography tunnel excavation and method for protecting support
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
RU2141030C1 (en) Device for construction of mine shafts
JP3155471B2 (en) Tunnel construction method and tunnel support structure
JP2833482B2 (en) Steel lining structure of tunnel
JPH04213695A (en) Segment for shield tunnel
JP3602998B2 (en) Tunnel construction method and tunnel
JP2594864B2 (en) Widening method of underground tunnel
JP2762133B2 (en) How to build a large architectural space underground
JP2001003677A (en) Workstation type tunnel widening device and method
JP2001059393A (en) Method and device for constructing horizontal shaft
JPH0464697A (en) Construction of tunneling space
JP2933476B2 (en) Underground pipe laying method
JPH02176093A (en) Vertical shaft for shield construction
JP2003307096A (en) Method for constructing tunnel
JP3082799B2 (en) Tunnel drilling rig
JP2762140B2 (en) Construction method of underground continuous wall based on underground tunnel
CN111075453A (en) Excavation method for reducing tunnel deformation and mud inrush and water inrush
JP2932197B2 (en) Excavation method for large or very large tunnel
JPH0726877A (en) Construction method of underground structure
JP2700694B2 (en) How to build a large architectural space underground
JPH06102954B2 (en) Vertical shaft construction method
CN107575256A (en) Material for shallow-buried sector transports system and Shallow Section earth's surface reinforcement means
JP3440661B2 (en) Tunnel protection method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060406

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071015

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071023

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071025

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101102

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101102

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111102

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121102

Year of fee payment: 5

LAPS Cancellation because of no payment of annual fees