JP2003307096A - Method for constructing tunnel - Google Patents

Method for constructing tunnel

Info

Publication number
JP2003307096A
JP2003307096A JP2002114651A JP2002114651A JP2003307096A JP 2003307096 A JP2003307096 A JP 2003307096A JP 2002114651 A JP2002114651 A JP 2002114651A JP 2002114651 A JP2002114651 A JP 2002114651A JP 2003307096 A JP2003307096 A JP 2003307096A
Authority
JP
Japan
Prior art keywords
tunnel
belt conveyor
excavation
excavator
workstation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2002114651A
Other languages
Japanese (ja)
Other versions
JP3831900B2 (en
Inventor
Takashi Kawada
孝志 河田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2002114651A priority Critical patent/JP3831900B2/en
Publication of JP2003307096A publication Critical patent/JP2003307096A/en
Application granted granted Critical
Publication of JP3831900B2 publication Critical patent/JP3831900B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method for constructing a tunnel in which the term of works is shortened by an efficient excavation, excavated muck generated in a facing section is carried out easily and concrete is also placed in an invert at an early stage. <P>SOLUTION: A tunnel is excavated by using a tunnel work station 1, in which the facing section in the tunnel 2 is partitioned into an upper stage 2a and a lower stage 2b and on which a required apparatus such as a drilling machine 8 is loaded. A tunnel sectional outer peripheral section in front of the facing section is drilled by the drilling machine 8 prior to the excavation of the upper stage 2a, and soil is improved by injecting a grout. The upper stage 2a of the tunnel 2 is excavated in a constant length by a self-propelled type first excavator 13, excavated muck is removed by a belt conveyor 16 and a primary lining from a timbering erection to a shotcrete is conducted successively or in parallel with an upper-stage excavating wall surface at the rear of the belt conveyor. The succeeding lower stage 2b is excavated by a second excavator 19, and the primary lining and the construction of the invert are conducted successively or in parallel. <P>COPYRIGHT: (C)2004,JPO

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、トンネルワークス
テーションを用いるトンネル施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel construction method using a tunnel workstation.

【0002】[0002]

【従来の技術】トンネル施工方法としては、従来例えば
自由断面掘削機等の掘削機で切羽部を掘削し、砕けた岩
石や土砂等(掘削ずり)を除去してから同じ手順を繰り
返して掘進する施工方法がある。又、シールド工法と称
される、先端のカッティングヘッドを切羽部に押し当て
て回転させながら掘進する施工方法がある。
2. Description of the Related Art Conventionally, as a tunnel construction method, the face portion is excavated by an excavator such as a free-section excavator, and crushed rocks, earth and sand (excavation) are removed, and then the same procedure is repeated to proceed. There is a construction method. Further, there is a construction method called a shield construction method in which a cutting head at the tip is pressed against a face portion to rotate and excavate.

【0003】ところで、近年環境保全並びにトンネル近
傍にダム等の貯水池が存在する場合、トンネル掘削時、
完成後にトンネル内への湧水を極限まで制限されるトン
ネルが計画されている。このようなトンネルを前記自由
断面掘削機等により掘削する場合は、掘削に先立って切
羽部の数十m(20〜50m位)前方部分を、トンネル
抗内よりボーリングマシンで穿孔し、その穿孔に注入機
により止水のための注入材を注入することにより掘削す
べきトンネル断面外周部の地盤改良を行い、掘削時の地
盤崩壊を防止して安全を確保すると共に、トンネル内へ
の湧水を防止するようにしている。
By the way, in recent years, when there is a reservoir such as a dam near the tunnel due to environmental protection, when excavating the tunnel,
After completion, a tunnel is planned to limit the spring water into the tunnel. When such a tunnel is to be excavated by the free section excavator or the like, prior to the excavation, a front portion of a face of several tens of meters (about 20 to 50 m) is perforated by a boring machine from inside the tunnel and the perforation is performed. By injecting an injection material for water stopping with an injection machine, the ground on the outer periphery of the tunnel section to be excavated is improved to prevent ground collapse during excavation to ensure safety and to prevent spring water from entering the tunnel. I try to prevent it.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、この場
合前工程としてトンネル抗内からボーリングマシンによ
る穿孔作業と注入機による注入作業とを必要とし、この
前工程が終了した後に自由断面掘削機等の掘削機で掘削
するため、掘削の手待ちの状態が発生して掘進作業の進
みが遅くなり、工期が長引く原因になっている。又、掘
削後の掘削ずりを搬出する作業は、複数のベルトコンベ
アを連結状態に組み合わせて搬送すると共に、トンネル
内に敷設したレール上を走行する台車に積み込んで行う
ため非常に煩雑で手間が掛かる。更に、これらベルトコ
ンベアや台車走行用のレールが敷設されていると、トン
ネル内の底面部に形成するインバートのコンクリート打
設工事が早期に着手できない問題がある。一方、シール
ド工法による場合には、上記のような前工程を必要とし
ないので能率良くトンネル掘削することが可能である
が、シールド機械が高価であって施工コストが著しく高
騰する問題がある。
However, in this case, as a pre-process, a boring machine drilling work and a pouring machine injection work are required from the tunnel bore, and after the pre-process is completed, a free-section excavator or the like is excavated. Since the excavation is carried out by a machine, waiting for excavation occurs, which slows down the progress of the excavation work, which is a cause of prolonging the construction period. In addition, the work of carrying out the excavation slide after excavation is carried out by combining a plurality of belt conveyors in a connected state and carrying it and loading it on a trolley running on a rail laid in the tunnel, which is very complicated and troublesome. . Further, when these belt conveyors and rails for traveling the dolly are laid, there is a problem that the invert concrete placing work formed on the bottom portion of the tunnel cannot be started early. On the other hand, when the shield method is used, it is possible to excavate the tunnel efficiently because the above-mentioned pre-process is not required, but there is a problem that the shield machine is expensive and the construction cost is significantly increased.

【0005】本発明は、上記従来の問題点に鑑みなされ
たもので、シールド機械を用いることなく、効率良く掘
進して工期の短縮が図れると共に、切羽部で生じる掘削
ずりの搬出を容易に行え、インバートのコンクリート打
設も早期に行えるようにしたトンネル施工方法を提供す
ることを目的とする。
The present invention has been made in view of the above-mentioned problems of the prior art, and it is possible to efficiently excavate and shorten the construction period without using a shield machine and to easily carry out excavation shear generated in the face portion. , It is an object of the present invention to provide a tunnel construction method that enables invert concrete pouring to be performed at an early stage.

【0006】[0006]

【課題を解決するための手段】上記の目的を達成するた
めに、請求項1の発明は、トンネル切羽部を上下二段に
区分する上部半断面先進掘削工法であって、複数の穿孔
機と注入装置等を搭載したトンネルワークステーション
を用い、上段の掘削に先立って切羽前方で且つトンネル
断面外周部に相当する領域を、前記穿孔機で穿孔し、地
盤改良材を前記注入装置で注入することにより地盤改良
すると共に下段部では第2の掘削機で下段部を掘削し、
その後上段部で第1の掘削機で掘削すると共に下段部で
は一次覆工を施工し、前記工程を順次繰り返してトンネ
ルを構築することを特徴とする。上部半断面先進掘削工
法でトンネルワークステーションを用いて、上段の掘削
に先行してトンネル断面外周部を地盤改良している間に
下段の掘削を行い、上段の掘削をしている時には下段の
覆工を行うので、工程の手待ちがなく効率良く施工を行
うことができ、工期短縮が図れる。
In order to achieve the above object, the invention of claim 1 is an upper half-section advanced excavation method for dividing a tunnel face into upper and lower tiers, which comprises a plurality of piercing machines. Using a tunnel workstation equipped with an injection device or the like, prior to excavation of the upper stage, a region corresponding to the outer peripheral part of the tunnel cross section is drilled with the drilling machine, and the ground improvement material is injected with the injection device. The ground is improved by the method and the second stage excavator excavates the lower stage in the lower stage,
After that, excavation is performed by the first excavator at the upper stage, and primary lining is performed at the lower stage, and the above steps are sequentially repeated to construct a tunnel. Using the tunnel workstation with the upper half-section advanced excavation method, the lower stage is excavated while the outer periphery of the tunnel section is being ground improved prior to the upper stage excavation, and the lower stage is covered when the upper stage is excavated. Since the work is performed, the work can be efficiently performed without waiting for the process, and the work period can be shortened.

【0007】又、請求項2の発明は、前記工程の1サイ
クルの中で、前記トンネルワークステーションの下方空
間部に配したインバート打設装置でインバートを形成す
ることを特徴とする。トンネルワークステーションの下
方空間部に配したインバート打設装置でインバートを形
成するので、ベルトコンベアや台車走行用のレールに関
係なく施工を行うことができ、更に工期短縮が図れる。
The invention according to claim 2 is characterized in that, in one cycle of the process, the invert is formed by an invert placing device arranged in a space below the tunnel workstation. Since the invert is formed by the invert placing device arranged in the lower space of the tunnel workstation, the construction can be performed regardless of the belt conveyor or the rail for traveling the carriage, and the construction period can be further shortened.

【0008】更に、請求項3の発明は、前記第1の掘削
機は、自走により進退しトンネルワークステーションに
対して出入可能であることを特徴とする。第1の掘削機
が自走により進退しトンネルワークステーションに対し
て出入可能となっているため、穿孔・注入作業と掘削の
切替がスムーズに行えることにより、工期短縮が図れ
る。
Furthermore, the invention of claim 3 is characterized in that the first excavator can advance and retreat by self-propelling and can enter and leave the tunnel workstation. Since the first excavator moves forward and backward by itself and can enter and exit the tunnel workstation, the switching between drilling / injection work and excavation can be performed smoothly, which shortens the construction period.

【0009】又、請求項4の発明は、前記トンネルワー
クステーションにはその長さ方向に沿って移動可能なベ
ルトコンベアを設け、このベルトコンベアにより、前記
第1及び第2の掘削機で掘削したずりを後方に搬送して
運搬車両に積載することを特徴とする。トンネルワーク
ステーションに長さ方向に沿って移動可能なベルトコン
ベアを配したので、トンネルワークステーション後方へ
の掘削ずりの搬送が容易である。
Further, in the invention of claim 4, a belt conveyor movable along the length direction is provided in the tunnel workstation, and the first and second excavators are used to excavate by the belt conveyor. It is characterized in that the shear is transported backward and loaded on a transportation vehicle. Since the belt conveyor movable along the length direction is arranged in the tunnel workstation, it is easy to transport the excavated shear to the rear of the tunnel workstation.

【0010】更に、請求項5の発明は、前記トンネルワ
ークステーションには前記第1の掘削機による掘削ずり
を後方に運搬する補助ベルトコンベアが前記ベルトコン
ベアの前方に設けられ、前記補助ベルトコンベアの後端
が前記ベルトコンベアの前端に近接し、補助ベルトコン
ベアの掘削ずりをベルトコンベアに移載できることを特
徴とする。ベルトコンベアに関連して補助ベルトコンベ
アを設けたので、上段の掘削ずりの搬送が容易になり、
上段の掘削を行っている時でも下段の掘削以外の作業が
行える。
Further, in the invention of claim 5, an auxiliary belt conveyor for conveying the excavation shear by the first excavator to the rear is provided in front of the belt conveyor in the tunnel work station, and the auxiliary belt conveyor is The rear end is close to the front end of the belt conveyor, and the digging shear of the auxiliary belt conveyor can be transferred to the belt conveyor. Since an auxiliary belt conveyor is provided in connection with the belt conveyor, it facilitates the transportation of the excavation slide in the upper stage,
Even when excavating the upper tier, operations other than excavating the lower tier can be performed.

【0011】そして、請求項6の発明は、前記ベルトコ
ンベアは、前部材と後部材とから一体に構成され、前部
材は後部材から前方に向かって下向き傾斜可能に取り付
けられていることを特徴とする。ベルトコンベアの前部
材を傾斜可能とすることにより、下段の掘削ずりの搬送
も行え、且つ掘削時以外の一次覆工等での作業の支障と
ならない。
According to a sixth aspect of the present invention, the belt conveyor is integrally formed of a front member and a rear member, and the front member is attached so as to be inclined downward from the rear member toward the front. And By making the front member of the belt conveyor inclinable, the excavation slip in the lower stage can be carried and there is no hindrance to the work in the primary lining etc. other than during excavation.

【0012】[0012]

【発明の実施の形態】次に、本発明に係るトンネル施工
方法の実施形態を添付図面に基づいて説明する。図1
は、トンネル切羽部を上下二段に区分する上部半断面先
進掘削工法であって、複数の穿孔機と注入装置等を搭載
したトンネルワークステーション1を用いてトンネル2
を掘削する場合であり、その上段の掘削に先立って穿孔
作業を行う状態を示す図である。
BEST MODE FOR CARRYING OUT THE INVENTION Next, an embodiment of a tunnel construction method according to the present invention will be described with reference to the accompanying drawings. Figure 1
Is an upper half-section advanced excavation method that divides the tunnel face into upper and lower sections, and uses a tunnel workstation 1 equipped with a plurality of drilling machines and injection equipment to create a tunnel 2
It is a case of excavating, and is a diagram showing a state in which a drilling operation is performed prior to excavation of the upper stage.

【0013】トンネルワークステーション1は、正面か
ら見て略門型に形成された第1の架台3と、この第1の
架台3の後部に連結して同じく略門型に形成された第2
の架台4とから組み立てられている。第1の架台3は、
図3のように所定の間隔(約6m)をあけて対設された
下部材3aと、その上に立設された複数の支柱3bと、
支柱3b間に取り付けられた斜材3cと、支柱3bによ
り支持固定された平板状の上部材3dとから一体に構成
され、全長は約35〜40mとなっている。下部材3a
の前端部近傍の下部には無端履帯5が対設されてトンネ
ル2の上段2a面を走行できるようにしてある。
The tunnel workstation 1 has a first frame 3 formed in a substantially gate shape when viewed from the front, and a second frame formed in a substantially gate shape connected to the rear portion of the first frame 3.
It is assembled from the gantry 4 and. The first mount 3 is
As shown in FIG. 3, a lower member 3a that is installed oppositely at a predetermined interval (about 6 m), and a plurality of columns 3b that are erected on the lower member 3a.
The diagonal member 3c attached between the columns 3b and the flat plate-shaped upper member 3d supported and fixed by the columns 3b are integrally formed, and the total length is about 35 to 40 m. Lower member 3a
An endless crawler belt 5 is provided in the lower portion near the front end of the tunnel so that it can travel on the upper surface 2a of the tunnel 2.

【0014】第2の架台4は、所定の間隔(約5m)を
あけて対設された下部材4aと、その上に立設された複
数の支柱4bと、これらの支柱4bにより支持固定され
た平板上の上部材4cとから一体に構成され、全長は約
15〜20mとなっている。第2の架台4の前端部は、
第1の架台3の後端部に連結固定され、下部材4aの前
端部近傍の下部と後端部近傍の下部にはそれぞれ車輪6
が取り付けられ、トンネル2内に敷設したレール7上を
走行できるようにしてある。これにより、トンネルワー
クステーション1は、前記無端履帯5と車輪6とを介し
て全体が安定良く支持されると共に、前後方向に移動可
能となっている。
The second pedestal 4 is provided with a lower member 4a which is installed oppositely with a predetermined space (about 5 m), a plurality of columns 4b standing on the lower member 4a, and supported and fixed by these columns 4b. The upper member 4c on the flat plate is integrally formed, and the total length is about 15 to 20 m. The front end of the second mount 4 is
The lower frame 4a is connected and fixed to the rear end of the first pedestal 3, and the wheels 6 are attached to the lower part near the front end and the lower part near the rear end of the lower member 4a.
Is attached so that it can run on the rail 7 laid in the tunnel 2. As a result, the tunnel workstation 1 as a whole is stably supported via the endless crawler belt 5 and the wheels 6, and is movable in the front-rear direction.

【0015】又、第1の架台3には、穿孔作業に必要な
複数の穿孔機8(図示の例では4台)が搭載されてお
り、そのうちの2台は図3のように前記下部材3aを側
方に延長形成した延長部上にそれぞれ配設され、且つ延
長部上に敷設したガイドレール9上を前後方向に移動で
きるように構成されている。他の2台は前記上部材3d
上にそれぞれ配設され、且つ上部材3d上に敷設したガ
イドレール9上を前後方向に移動できるように構成され
ている。
Further, a plurality of punching machines 8 (four in the illustrated example) necessary for punching work are mounted on the first frame 3, two of which are the lower members as shown in FIG. 3a are arranged on respective extension portions formed by extending sideways, and are configured to be movable in the front-rear direction on a guide rail 9 laid on the extension portions. The other two are the upper member 3d
The guide rails 9 are respectively disposed on the upper member 3d and laid on the upper member 3d so as to be movable in the front-rear direction.

【0016】各穿孔機8の後部には注入装置10(図
1)がそれぞれ搭載され、穿孔機8で切羽部前方で且つ
トンネル断面外周部に相当する領域を穿孔した後に、注
入装置10から穿孔内に注入材(止水目的の地盤改良材
或は固化材)を注入して地盤改良できるようにしてあ
る。
An injection device 10 (FIG. 1) is mounted on the rear portion of each punching machine 8, and after the punching machine 8 punches a region in front of the face and corresponding to the outer periphery of the tunnel cross section, the punching device 10 punches the hole. An injection material (a ground improvement material or a solidification material for the purpose of stopping water) is injected into the interior so that the ground can be improved.

【0017】又、図3のように第1の架台3の上部材3
d上には、コンクリート吹付機11が2つの穿孔機8の
間に挟まれるようにして中央部に配設され、作業用ケー
ジ12が2つの穿孔機8の外側にそれぞれ位置するよう
にして両側部に配設され、これらのコンクリート吹付機
11、作業用ケージ12もガイドレールを介して前後方
向に移動可能に構成されている。
Further, as shown in FIG. 3, the upper member 3 of the first frame 3 is
On the d, the concrete spraying machine 11 is arranged in the central part so as to be sandwiched between the two punching machines 8, and the working cages 12 are located outside the two punching machines 8 respectively. The concrete spraying machine 11 and the working cage 12 are also configured to be movable in the front-rear direction via guide rails.

【0018】更に、第1の架台3の前方部内には、図1
及び図3に示すように自由断面掘削機である第1の掘削
機13が待機しており、この第1の掘削機13は自由に
掘削方向が変えられるブーム型であって、無端履帯13
aにより自走可能に形成され、掘削作業時には図2のよ
うに前進して第1の架台3より前方に現れ、穿孔作業時
には後退して第1の架台3の空間内に格納する。つま
り、第1の掘削機13は自走により進退し、トンネルワ
ークステーション1に対して出入可能となっている。
Further, in the front part of the first pedestal 3, in FIG.
Also, as shown in FIG. 3, the first excavator 13 which is a free-section excavator is on standby, and the first excavator 13 is a boom type in which the excavation direction can be freely changed.
It is formed so as to be self-propelled by a, moves forward as shown in FIG. 2 during excavation work and appears in front of the first pedestal 3, and retracts during perforation work and is stored in the space of the first pedestal 3. That is, the first excavator 13 can move forward and backward by self-propelling, and can enter and exit the tunnel workstation 1.

【0019】この第1の掘削機13の後端部には補助ベ
ルトコンベア14が昇降機構15を介して取り付けられ
ている。補助ベルトコンベア14は、上段の掘削作業時
には図2のようにベルトコンベア16に近接し、上段の
穿孔作業時には図1のように昇降機構15により上昇さ
せてベルトコンベア16とは離れるようになっている。
An auxiliary belt conveyor 14 is attached to the rear end portion of the first excavator 13 via an elevating mechanism 15. The auxiliary belt conveyer 14 comes close to the belt conveyer 16 as shown in FIG. 2 during the upper digging work, and is lifted by the elevating mechanism 15 and separates from the belt conveyer 16 as shown in FIG. 1 during the upper piercing work. There is.

【0020】ベルトコンベア16は、前部材16aと後
部材16bとから一体に構成され、前部材16aは前記
補助ベルトコンベア14と近接可能に形成されると共
に、図1のように後部材16bから前方に向かって下向
き傾斜可能に取り付けられている。
The belt conveyor 16 is formed integrally with a front member 16a and a rear member 16b. The front member 16a is formed so as to be close to the auxiliary belt conveyor 14, and the front member 16b is connected to the front member 16b as shown in FIG. It is attached so that it can be tilted downward toward.

【0021】このベルトコンベア16は、前後方向に移
動可能に形成されており、即ち図1及び図5のように前
記第2の架台4における上部材4cの下面側に一対の支
持レール17が固定され、この支持レール17に対して
前記後部材16bが摺動自在に支持されている。支持レ
ール17の前方部は上部材4cに固定されていないた
め、第1の架台3における前記下部材3aとの間にステ
ー(図略)等を介して固定する。
The belt conveyor 16 is formed so as to be movable in the front-back direction, that is, as shown in FIGS. 1 and 5, a pair of support rails 17 are fixed to the lower surface side of the upper member 4c of the second mount 4. The rear member 16b is slidably supported on the support rail 17. Since the front portion of the support rail 17 is not fixed to the upper member 4c, it is fixed to the lower member 3a of the first frame 3 via a stay (not shown) or the like.

【0022】ベルトコンベア16の前部材16aは、図
1のように前方寄りの両側を電動チェーンブロック18
で支持し、その電動チェーンブロック18は第1の架台
3の下部材3aに対してそれぞれ摺動可能に取り付ける
と好ましい。電動チェーンブロック18により前部材1
6aをほぼ水平状態に安定良く保持すると共に、前部材
16aを前方に向かって下向き傾斜させる時にも安定良
く保持することができる。
As shown in FIG. 1, the front member 16a of the belt conveyor 16 has electric chain blocks 18 on both sides toward the front.
It is preferable that the electric chain block 18 be slidably attached to the lower member 3a of the first frame 3 respectively. The front member 1 by the electric chain block 18
6a can be stably held in a substantially horizontal state, and can be stably held even when the front member 16a is inclined downward toward the front.

【0023】第2の掘削機19は所要の大きさのブレー
カーやバックホーであり、トンネル2の下段2bの切羽
部を掘削する。掘削ずりは前記下向き傾斜させたベルト
コンベア16の前部材16aに載せ、ベルトコンベア1
6によって後方に搬送し、搬出用トラック等の運搬車両
Dに積載する。
The second excavator 19 is a breaker or backhoe of a required size, and excavates the face of the lower stage 2b of the tunnel 2. The excavation slide is mounted on the front member 16a of the belt conveyor 16 which is inclined downward, and the belt conveyor 1
It is transported to the rear by 6 and loaded on a transportation vehicle D such as an unloading truck.

【0024】20はインバート打設装置であり、第2の
掘削機19で掘削した後にトンネル下面にインバートを
形成する。このインバート打設装置20は、自走可能に
形成されてインバート型枠20aを所定の箇所に据え付
けると共に、このインバート型枠20a内にコンクリー
トを打設してインバートを連結状態に順次形成できるよ
うにしてある。
Reference numeral 20 denotes an invert placing device, which forms an invert on the lower surface of the tunnel after excavating by the second excavator 19. The invert placing device 20 is formed so as to be self-propelled so that the invert form 20a is installed at a predetermined position, and concrete is placed in the invert form 20a so that the inverts can be sequentially formed in a connected state. There is.

【0025】前記第2の架台4の後端部には、急結剤供
給装置21とコンクリート吹付機22とが搭載されてい
る。これらはトンネル2の内面に形成された覆工の隙間
を塞いで外部からの湧水を防ぐために使用される。
At the rear end of the second pedestal 4, a quick-setting agent supply device 21 and a concrete spraying machine 22 are mounted. These are used to close the gap of the lining formed on the inner surface of the tunnel 2 and prevent spring water from the outside.

【0026】トンネルワークステーション1での作業員
の往来と安全を確保するために、図4及び図5のように
第1の架台3の下部材3a及び第2の架台4の下部材4
aに通路23、24をそれぞれ取り付け、これらの通路
23、24の外側には柵23a、24aをそれぞれ設け
て転落を防止するようにしてある。又、通路23と通路
24とを連絡するための階段25を設け、第1の架台3
の中間部には通路23と上部材3dの上面とを連絡する
ための階段26を設け、更に、第1の架台3における上
部材3dの前方部及び第2の架台4における上部材4c
の周囲にも柵3e、4dをそれぞれ設けて作業員の安全
対策を施してある。
In order to ensure the traffic and safety of workers at the tunnel workstation 1, as shown in FIGS. 4 and 5, the lower member 3a of the first pedestal 3 and the lower member 4 of the second pedestal 4 are used.
Passageways 23 and 24 are attached to a, respectively, and fences 23a and 24a are respectively provided outside these passageways 23 and 24 to prevent the fall. In addition, a staircase 25 for connecting the passage 23 and the passage 24 is provided, and the first mount 3
A staircase 26 for connecting the passage 23 and the upper surface of the upper member 3d is provided in the middle portion of the upper member 3d, and the front portion of the upper member 3d of the first mount 3 and the upper member 4c of the second mount 4 are further provided.
Fences 3e and 4d are also provided around the area to provide worker safety measures.

【0027】このように構成されたトンネルワークステ
ーション1で、トンネル2を掘削施工する方法について
説明する。この方法は図1、図2に示すように上部半断
面先進掘削工法であり、トンネル2の切羽部はその上半
部を上段2aに、下半部を下段2bにそれぞれ区分し、
上段2aの切羽部は第1の掘削機13により、下段2b
の切羽部は第2の掘削機19によりそれぞれ掘削を行
う。
A method for excavating and constructing the tunnel 2 in the tunnel workstation 1 thus constructed will be described. This method is an advanced half section advanced excavation method as shown in FIGS. 1 and 2, and the face part of the tunnel 2 is divided into an upper half 2a and a lower half 2b.
The cutting face of the upper stage 2a is moved by the first excavator 13 to the lower stage 2b.
The face part of each is excavated by the second excavator 19.

【0028】先行するトンネル2の上段2aにおいて
は、第1の掘削機13でトンネル2の掘進方向に一定長
掘削した後、その掘削ずりの排除を行い、その後方の上
段の掘削壁面に支保工の建て込みからコンクリート吹き
付けまでの一次覆工を順次或は並行して行い、後行する
下段2bにおいても下半部とインバート部の掘削、上半
部と同様の一次覆工、インバートの施工を順次或は並行
して行う。このように掘削作業から一次覆工、インバー
ト作業までを繰り返し行うことでトンネル2を掘削して
行く。
In the upper stage 2a of the preceding tunnel 2, after excavating the first excavator 13 for a certain length in the excavation direction of the tunnel 2, the excavation shear is eliminated and the excavation wall surface in the upper stage behind is supported. The primary lining from the erection of concrete to the concrete spraying is performed sequentially or in parallel, and in the subsequent lower stage 2b, excavation of the lower half and the invert part, the same primary lining as the upper half, and the construction of the invert. Sequentially or in parallel. In this way, the tunnel 2 is excavated by repeating the excavation work, the primary lining work, and the inversion work.

【0029】第1の掘削機13で上段2aの切羽部を掘
削する前に、図1のように穿孔作業を行う。前記トンネ
ルワークステーション1に搭載された複数の穿孔機8を
それぞれ前進させ、切羽前方で且つトンネル断面外周部
に相当する領域を穿孔した後に、注入装置10から各穿
孔内に注入材を注入し、地盤を改良する。この地盤改良
の範囲を図6に示す。この図では、トンネル周囲を地盤
改良するものであるが、必要に応じトンネル掘削部領域
まで地盤改良してもよいし、全周でなくても良い。この
時に空いている穿孔機8を利用して切羽周辺の掘削壁面
にロックボルト(図略)を打設していてもよい。穿孔作
業時には前記第1の掘削機13は第1の架台3の空間内
に格納して待機させておく。
Before excavating the face of the upper stage 2a by the first excavator 13, a boring operation is performed as shown in FIG. After advancing a plurality of punching machines 8 mounted on the tunnel workstation 1 and punching a region in front of the face and corresponding to the outer peripheral portion of the tunnel cross section, an injecting material is injected into each of the perforating holes from the injection device 10, Improve the ground. The range of this ground improvement is shown in FIG. In this figure, the ground around the tunnel is improved. However, the ground may be improved up to the tunnel excavation area or may not be the entire circumference if necessary. At this time, a rock bolt (not shown) may be driven on the excavated wall surface around the face using the piercing machine 8 which is vacant. At the time of drilling work, the first excavator 13 is stored in the space of the first gantry 3 and stands by.

【0030】一方、上段2aの穿孔作業時に並行して下
段2bでは、第2の掘削機19により切羽部の一定長の
掘削と、インバート掘削とが行われる。これらの掘削に
より生じた掘削ずりは、ベルトコンベア16の下向き傾
斜させた前部材16aに載せられると共に、後部材16
bを経て後方に搬送され、ベルトコンベア16の端部に
位置付けられた搬出用トラック等の運搬車両Dに積み込
まれる。
On the other hand, in parallel with the drilling work of the upper stage 2a, in the lower stage 2b, the second excavator 19 excavates the face portion of a constant length and inverts excavation. The excavation shear generated by these excavations is placed on the front member 16a that is inclined downward of the belt conveyor 16, and
It is conveyed rearward through b and is loaded on a transportation vehicle D such as an unloading truck positioned at the end of the belt conveyor 16.

【0031】前記注入材による地盤改良が完了した時点
で、各穿孔機8を後退させて元の位置に復帰させ、図2
のように第1の掘削機13を前進させて第1の架台3の
前方に位置させ、切羽部の一定長の掘削を行う。この
時、ベルトコンベア16は前部材16aを前記電動チェ
ーンブロック18で吊り上げて後部材16bとほぼ水平
で直線状態となるようにし、且つ前記支持レール17に
沿って前進移動させ、前部材16aを掘削機13の後部
に取り付けられた補助ベルトコンベア14に近接させ
る。これにより、掘削ずりは補助ベルトコンベア14及
びベルトコンベア16を介して後方に搬送されると共
に、ベルトコンベア16の端部に位置付けた運搬車両D
に積み込まれる。
When the ground improvement by the injection material is completed, each boring machine 8 is retracted and returned to its original position.
As described above, the first excavator 13 is moved forward to be positioned in front of the first gantry 3, and excavation of the face portion with a constant length is performed. At this time, the belt conveyor 16 lifts the front member 16a by the electric chain block 18 so that the front member 16a is substantially horizontal and linear with the rear member 16b, and is moved forward along the support rail 17 to excavate the front member 16a. It is brought close to an auxiliary belt conveyor 14 attached to the rear of the machine 13. As a result, the excavation shear is conveyed rearward through the auxiliary belt conveyor 14 and the belt conveyor 16, and the transportation vehicle D positioned at the end of the belt conveyor 16
Be loaded into.

【0032】掘削ずりの排出後に第1の掘削機13を自
走によりバックさせ、第1の架台3上で後方に待機させ
ていた作業用ケージ12を前進させてトンネルワークス
テーション1の前端から掘削壁面に臨ませる。そして、
露出した掘削壁面に穿孔機8でロックボルト(図略)を
打設する。その後、一次覆工のために分割された支保工
や金網を適宜の手段で搬送し、作業用ケージ12上で作
業員が掘削壁面に対する支保工の建て込みと既設支保工
との間に金網張り作業を行う。この後、第1の架台3上
に待機させていたコンクリート吹付機11を支保工建て
込み部まで前進させてコンクリートの吹き付けを行って
上半部の一次覆工作業を完了する。
After the excavation shear is discharged, the first excavator 13 is automatically propelled back, and the work cage 12, which has been standing by backward on the first platform 3, is moved forward to excavate from the front end of the tunnel workstation 1. Face the wall. And
A rock bolt (not shown) is driven by the boring machine 8 on the exposed excavation wall surface. After that, the support and wire nets divided for the primary lining are conveyed by an appropriate means, and the worker installs the support on the excavation wall on the work cage 12 and installs the wire net between the existing support. Do the work. After that, the concrete spraying machine 11 waiting on the first pedestal 3 is advanced to the support construction part to spray the concrete, and the primary lining work of the upper half part is completed.

【0033】一方、下段2bにおいても上半部と同様に
下半部の一次覆工作業が行われ、これと並行して前記イ
ンバート掘削部にインバート型枠20aをセットし、イ
ンバート打設装置20によりコンクリートを打設してイ
ンバートを形成する。
On the other hand, in the lower stage 2b as well, the primary lining work of the lower half is performed similarly to the upper half, and in parallel with this, the invert form 20a is set in the invert excavating section and the invert placing device 20 is installed. To place concrete to form an invert.

【0034】尚、インバートの形成は、トンネルワーク
ステーション1の下方空間部を利用してインバート打設
装置20で行うので、上段の穿孔・注入、上下段の切羽
の掘削から一次覆工までの1サイクル分の作業の中で行
えばよい。又、本実施の形態では、下段の掘削時には上
段は穿孔・注入作業を行っているが、上段の掘削以外の
ロックボルトや一次覆工作業を行っていてもよい。
The formation of the invert is performed by the invert placing device 20 utilizing the space below the tunnel workstation 1, so that the steps from the upper stage piercing / injecting, the upper and lower face excavation to the primary lining are performed. It can be done in the cycle work. Further, in the present embodiment, the drilling / injecting work is performed on the upper stage when excavating the lower stage, but the lock bolt and the primary lining work other than the excavating process on the upper stage may be performed.

【0035】トンネル2内の壁面覆工及びインバートが
構築された後、トンネル2の底面部における前記レール
7の前方に新規レールを接続して継ぎ足す。この新規レ
ールの敷設後に、トンネルワークステーション1全体を
一定長前進させる。第1の架台3下の無端履帯5が上段
2a面を移動し、同時に第2の架台4下の車輪6がレー
ル7上を走行することにより、トンネルワークステーシ
ョン1を円滑に前進移動させることができる。このトン
ネルワークステーション1の前進移動に伴って、第1の
掘削機13、第2の掘削機19、インバート打設装置2
0もそれぞれ所定距離だけ前進移動させる。
After the wall lining and the invert inside the tunnel 2 are constructed, a new rail is connected to the front side of the rail 7 on the bottom surface of the tunnel 2 and added. After laying this new rail, the entire tunnel workstation 1 is advanced by a certain length. The endless crawler belt 5 under the first gantry 3 moves on the surface of the upper stage 2a, and at the same time, the wheels 6 under the second gantry 4 travel on the rails 7, whereby the tunnel workstation 1 can be smoothly moved forward. it can. With the forward movement of the tunnel workstation 1, the first excavator 13, the second excavator 19, and the invert placing device 2
0 is also moved forward by a predetermined distance.

【0036】又、トンネルワークステーション1の前進
移動の際に、既設の覆工内壁面においてわずかな隙間等
がある場合には、前記急結材供給装置21又は/及びコ
ンクリート吹付機22により即座に補修することが可能
である。従って、外部からの湧水を防ぐことができる。
そして、上記のようなサイクルを繰り返し行うことによ
りトンネル2を掘進するのである。尚、本実施の形態で
は第1の掘削機13を自由断面掘削機としたが、これに
限定されるものではない。又、第2の掘削機19につい
ても同様である。
When the tunnel workstation 1 is moved forward, if there is a slight gap or the like on the inner wall surface of the existing lining, the quick-linking material supply device 21 and / or the concrete spraying machine 22 immediately It can be repaired. Therefore, spring water from the outside can be prevented.
Then, the tunnel 2 is dug by repeating the above cycle. Although the first excavator 13 is a free-section excavator in the present embodiment, the present invention is not limited to this. The same applies to the second excavator 19.

【0037】[0037]

【発明の効果】以上説明したように、請求項1の発明に
よれば、トンネル切羽部を上下二段に区分する上部半断
面先進掘削工法であって、複数の穿孔機と注入装置を搭
載したトンネルワークステーションを用い、上段の掘削
に先立って切羽前方で且つトンネル断面外周部に相当す
る領域を、前記穿孔機で穿孔し、地盤改良材を前記注入
装置で注入することにより地盤改良すると共に下段部で
は第2の掘削機で下段部を掘削し、その後上段部で第1
の掘削機で掘削すると共に下段部では一次覆工を施工
し、前記工程を順次繰り返してトンネルを構築するの
で、上部半断面先進掘削工法でトンネルワークステーシ
ョンを用いて、上段の掘削に先行してトンネル断面外周
部を地盤改良している間に下段の掘削を行い、上段の掘
削をしている時には下段の覆工を行うため、工程の手待
ちがなく効率良く施工することができ、工期短縮が図れ
る効果を奏する。
As described above, according to the invention of claim 1, it is an upper half-section advanced excavation method for dividing a tunnel face into upper and lower tiers, and is equipped with a plurality of piercing machines and an injection device. Using a tunnel workstation, a region corresponding to the front of the cutting face and the outer periphery of the tunnel cross section is drilled with the drilling machine before the excavation of the upper stage and the ground improvement material is injected with the injection device to improve the ground and the lower stage. Section excavates the lower section with a second excavator and then the first section with the upper section.
Excavating with the excavator and performing the primary lining at the lower part, and repeating the above steps to build the tunnel, use the tunnel workstation with the upper half-section advanced excavation method to precede the upper part excavation. The lower tier is excavated while the outer periphery of the tunnel cross section is being improved, and the lower lining is performed when the upper tier is excavated, enabling efficient construction without waiting for the process and shortening the construction period. The effect that can be achieved.

【0038】又、請求項2の発明によれば、前記工程の
1サイクルの中で、前記トンネルワークステーションの
下方空間部に配したインバート打設装置でインバートを
形成する施工方法であり、トンネルワークステーション
の下方空間部に配したインバート打設装置でインバート
を形成するため、ベルトコンベアや台車走行用のレール
に関係なく施工を行うことができ、更に工期短縮が図れ
る。
According to a second aspect of the invention, there is provided a construction method for forming an invert by an invert placing device arranged in a space below the tunnel work station in one cycle of the process. Since the invert is placed by the invert placing device arranged in the space below the station, the construction can be performed regardless of the belt conveyor or the rail for traveling the carriage, and the construction period can be further shortened.

【0039】更に、請求項3の発明によれば、前記第1
の掘削機は、自走により進退しトンネルワークステーシ
ョンに対して出入可能なため、即ち第1の掘削機が自走
により進退しトンネルワークステーションに対して出入
可能となっているため、穿孔・注入作業と掘削の切替が
スムーズに行え、工期短縮が図れる。
Further, according to the invention of claim 3, the first
Excavator can move forwards and backwards to and from the tunnel workstation by self-propelling, that is, the first excavator can move forwards and backwards to enter and leave the tunnel workstation. Switching between work and excavation can be done smoothly, and the construction period can be shortened.

【0040】又、請求項4の発明によれば、前記トンネ
ルワークステーションにはその長さ方向に沿って移動可
能なベルトコンベアを設け、このベルトコンベアによ
り、前記第1及び第2の掘削機で掘削したずりを後方に
搬送して運搬車両に積載する施工方法であり、トンネル
ワークステーションに長さ方向に沿って移動可能なベル
トコンベアを配したので、トンネルワークステーション
後方への掘削ずりの搬送が容易となる。
Further, according to the invention of claim 4, the tunnel work station is provided with a belt conveyer which is movable along the length direction thereof, and by this belt conveyer, the first and second excavators can be operated. This is a construction method in which the excavated skid is transported to the rear and loaded on a transport vehicle.Because a belt conveyor that can move along the length direction was arranged in the tunnel workstation, the transport of the excavated skid to the rear of the tunnel workstation is possible. It will be easy.

【0041】更に、請求項5の発明によれば、前記トン
ネルワークステーションには前記第1の掘削機による掘
削ずりを後方に運搬する補助ベルトコンベアが前記ベル
トコンベアの前方に設けられ、前記補助ベルトコンベア
の後端が前記ベルトコンベアの前端に近接し、補助ベル
トコンベアの掘削ずりをベルトコンベアに移載できるの
で、ベルトコンベアに関連して設けた補助ベルトによ
り、上段の掘削ずりの搬送が容易となり、上段の掘削を
行っている時でも下段の掘削以外の作業が行える。
Further, according to the invention of claim 5, an auxiliary belt conveyor for conveying the excavation shear by the first excavator to the rear is provided in front of the belt conveyor in the tunnel workstation, and the auxiliary belt is provided. Since the rear end of the conveyor is close to the front end of the belt conveyor and the excavation shear of the auxiliary belt conveyor can be transferred to the belt conveyor, the auxiliary belt provided in association with the belt conveyor facilitates the transportation of the upper excavation shear. Even when excavating the upper tier, work other than excavating the lower tier can be performed.

【0042】そして、請求項6の発明は、前記ベルトコ
ンベアは、前部材と後部材とから一体に構成され、前部
材は後部材から前方に向かって下向き傾斜可能に取り付
けられているので、ベルトコンベアの前部材を傾斜可能
とすることにより、下段の掘削ずりの搬送も行え、且つ
掘削時以外の一次覆工等の作業の支障とならない利点が
ある。
According to a sixth aspect of the present invention, the belt conveyor is integrally formed of a front member and a rear member, and the front member is attached so as to be inclined downward from the rear member toward the front. By making the front member of the conveyor inclinable, there is an advantage that the excavation slip in the lower stage can be carried and there is no hindrance to work such as primary lining except during excavation.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係るトンネル施工方法の実施形態を示
すもので、上段の掘削に先立って行われる穿孔作業時で
の概略側面図である。
FIG. 1 shows an embodiment of a tunnel construction method according to the present invention, and is a schematic side view during a boring operation performed prior to excavation of an upper stage.

【図2】本発明に係るトンネル施工方法の実施形態を示
すもので、穿孔作業に伴う地盤改良後に行われる上段の
掘削作業時での概略側面図である。
FIG. 2 shows an embodiment of a tunnel construction method according to the present invention, and is a schematic side view at the time of excavation work of the upper stage performed after the ground improvement accompanying the drilling work.

【図3】図1におけるA−A線概略断面図である。3 is a schematic cross-sectional view taken along the line AA in FIG.

【図4】図1におけるB−B線概略断面図である。FIG. 4 is a schematic cross-sectional view taken along the line BB in FIG.

【図5】図1におけるC−C線概略断面図である。5 is a schematic cross-sectional view taken along the line CC in FIG.

【図6】上段の掘削に先立って切羽前方のトンネル断面
外周部を地盤改良する例を示すもので、(a)は地盤改
良領域の側面図、(b)は地盤改良領域の正面図であ
る。
FIG. 6 is a view showing an example of ground improvement of the tunnel cross-section outer peripheral portion in front of the face prior to excavation of the upper stage, (a) is a side view of the ground improvement area, and (b) is a front view of the ground improvement area. .

【符号の説明】[Explanation of symbols]

1…トンネルワークステーション 2…トンネル 2a…上段 2b…下段 3…第1の架台 4…第2の架台 5…無端履帯 6…車輪 7…レール 8…穿孔機 9…ガイドレール 10…注入装置 11…コンクリート吹付機 12…作業用ケージ 13…第1の掘削機 14…補助ベルトコンベア 15…昇降機構 16…ベルトコンベア 16a…前部材 16b…後部材 17…支持レール 18…電動チェーンブロック 19…第2の掘削機 20…インバート打設装置 21…急結剤供給装置 22…コンクリート吹付機 23、24…通路 25、26…階段 1 ... Tunnel workstation 2 ... tunnel 2a ... upper 2b ... bottom 3 ... The first mount 4 ... Second mount 5 ... Endless track 6 ... wheels 7 ... Rail 8 ... Punching machine 9 ... Guide rail 10 ... Injection device 11 ... Concrete spraying machine 12 ... Work cage 13 ... The first excavator 14 ... Auxiliary belt conveyor 15 ... Lifting mechanism 16 ... Belt conveyor 16a ... Front member 16b ... rear member 17 ... Support rail 18 ... Electric chain block 19 ... Second excavator 20 ... Invert placement device 21 ... Fastener supply device 22 ... Concrete spraying machine 23, 24 ... passage 25, 26 ... stairs

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】トンネル切羽部を上下二段に区分する上部
半断面先進掘削工法であって、複数の穿孔機と注入装置
等を搭載したトンネルワークステーションを用い、上段
の掘削に先立って切羽前方で且つトンネル断面外周部に
相当する領域を、前記穿孔機で穿孔し、地盤改良材を前
記注入装置で注入することにより地盤改良すると共に下
段部では第2の掘削機で下段部を掘削し、その後上段部
で第1の掘削機で掘削すると共に下段部では一次覆工を
施工し、前記工程を順次繰り返してトンネルを構築する
ことを特徴とするトンネル施工方法。
1. An upper half-section advanced excavation method for dividing a tunnel face into upper and lower tiers, which uses a tunnel workstation equipped with a plurality of piercing machines, an injection device, etc., in front of the face prior to digging the upper face. And, the area corresponding to the tunnel cross-section outer peripheral portion is pierced by the piercing machine, and the ground is improved by injecting the ground improvement material by the injection device, and the lower tier is excavated by the second digging machine, A tunnel construction method characterized by excavating with a first excavator at the upper stage and then performing a primary lining at the lower stage, and repeating the above steps to construct a tunnel.
【請求項2】前記工程の1サイクルの中で、前記トンネ
ルワークステーションの下方空間部に配したインバート
打設装置でインバートを形成することを特徴とする請求
項1に記載のトンネル施工方法。
2. The tunnel construction method according to claim 1, wherein in one cycle of the process, an invert is formed by an invert placing device arranged in a space below the tunnel workstation.
【請求項3】前記第1の掘削機は、自走により進退しト
ンネルワークステーションに対して出入可能であること
を特徴とする請求項1又は請求項2に記載のトンネル施
工方法。
3. The tunnel construction method according to claim 1, wherein the first excavator is capable of advancing and retreating by self-propelling and being able to move in and out of a tunnel workstation.
【請求項4】前記トンネルワークステーションにはその
長さ方向に沿って移動可能なベルトコンベアを設け、こ
のベルトコンベアにより、前記第1及び第2の掘削機で
掘削したずりを後方に搬送して運搬車両に積載すること
を特徴とする請求項1から請求項3いずれか1項に記載
のトンネル施工方法。
4. The tunnel workstation is provided with a belt conveyor movable along its length, and the belt conveyor conveys the skid excavated by the first and second excavators backward. The tunnel construction method according to any one of claims 1 to 3, wherein the tunnel construction method is to load the transportation vehicle.
【請求項5】前記トンネルワークステーションには前記
第1の掘削機による掘削ずりを後方に運搬する補助ベル
トコンベアが前記ベルトコンベアの前方に設けられ、前
記補助ベルトコンベアの後端が前記ベルトコンベアの前
端に近接し、補助ベルトコンベアの掘削ずりをベルトコ
ンベアに移載できることを特徴とする請求項4に記載の
トンネル施工方法。
5. The tunnel work station is provided with an auxiliary belt conveyor for transporting the excavation shear by the first excavator to the rear, in front of the belt conveyor, and the rear end of the auxiliary belt conveyor is the belt conveyor. The tunnel construction method according to claim 4, wherein the excavation shear of the auxiliary belt conveyor can be transferred to the belt conveyor in the vicinity of the front end.
【請求項6】前記ベルトコンベアは、前部材と後部材と
から一体に構成され、前部材は後部材から前方に向かっ
て下向き傾斜可能に取り付けられていることを特徴とす
る請求項4又は請求項5に記載のトンネル施工方法。
6. The belt conveyor according to claim 4, wherein the belt conveyor is integrally formed of a front member and a rear member, and the front member is attached so as to be inclined downward from the rear member toward the front. Item 5. The tunnel construction method according to item 5.
JP2002114651A 2002-04-17 2002-04-17 Tunnel construction method Expired - Fee Related JP3831900B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002114651A JP3831900B2 (en) 2002-04-17 2002-04-17 Tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002114651A JP3831900B2 (en) 2002-04-17 2002-04-17 Tunnel construction method

Publications (2)

Publication Number Publication Date
JP2003307096A true JP2003307096A (en) 2003-10-31
JP3831900B2 JP3831900B2 (en) 2006-10-11

Family

ID=29396379

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002114651A Expired - Fee Related JP3831900B2 (en) 2002-04-17 2002-04-17 Tunnel construction method

Country Status (1)

Country Link
JP (1) JP3831900B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009041198A (en) * 2007-08-06 2009-02-26 Furukawa Rock Drill Co Ltd Tunnel work truck
CN102359381A (en) * 2011-06-27 2012-02-22 湖南五新重型装备有限公司 Material distribution machine of tunnel lining trolley and tunnel lining trolley
CN112483126A (en) * 2020-11-04 2021-03-12 中铁十九局集团第五工程有限公司 Construction method of underground excavation air duct of composite stratum with upper soft part and lower hard part
CN114183172A (en) * 2021-11-22 2022-03-15 中铁十六局集团第三工程有限公司 Large-deformation tunnel construction method based on safety step
CN114483054A (en) * 2022-03-07 2022-05-13 中铁隧道局集团有限公司 Non-explosive excavation construction method for pilot tunnel in upper soft and lower hard stratum

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611109B (en) * 2018-11-05 2019-12-24 青岛市地铁一号线有限公司 Advanced control method and system for disaster source of tunnel TBM construction broken zone

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009041198A (en) * 2007-08-06 2009-02-26 Furukawa Rock Drill Co Ltd Tunnel work truck
CN102359381A (en) * 2011-06-27 2012-02-22 湖南五新重型装备有限公司 Material distribution machine of tunnel lining trolley and tunnel lining trolley
CN102359381B (en) * 2011-06-27 2013-08-14 湖南五新重型装备有限公司 Material distribution machine of tunnel lining trolley and tunnel lining trolley
CN112483126A (en) * 2020-11-04 2021-03-12 中铁十九局集团第五工程有限公司 Construction method of underground excavation air duct of composite stratum with upper soft part and lower hard part
CN114183172A (en) * 2021-11-22 2022-03-15 中铁十六局集团第三工程有限公司 Large-deformation tunnel construction method based on safety step
CN114483054A (en) * 2022-03-07 2022-05-13 中铁隧道局集团有限公司 Non-explosive excavation construction method for pilot tunnel in upper soft and lower hard stratum

Also Published As

Publication number Publication date
JP3831900B2 (en) 2006-10-11

Similar Documents

Publication Publication Date Title
CN101403305B (en) Construction method for tunnel continuous mucking, lining and excavation synchronization
US6848748B2 (en) Mining system with drilling, loading, conveyor, and support
CN106223967A (en) A kind of great burying rectangle or class Rectangular Tunnel shield-tunneling construction device and method
EA025603B1 (en) Underground mining
JP4181980B2 (en) Tunnel construction method
JP3831900B2 (en) Tunnel construction method
JP2017048588A (en) Excavated object carrying-out system and carrying-out method
US3590590A (en) Tunnel building
JP3103285B2 (en) Tunnel excavation method
JP6549411B2 (en) Floor construction method of shield tunnel
JP4113007B2 (en) Widening method of existing tunnel
JP4281983B2 (en) Tunnel excavation method using advanced shaft
JP3151116B2 (en) Tunnel excavation method and gantry used for this method
US4396313A (en) Method of forming flooring in tunnels
RU2103507C1 (en) Method and cutter-loader machine for development of seam deposits of minerals
JP3996597B2 (en) Open shield machine and open shield method using it
JP2618798B2 (en) Multi-function excavator
JP7162687B2 (en) Muddy transport system and tunnel excavation method
JP3357654B2 (en) Gantry used for tunnel excavation method
JP2996096B2 (en) Large section tunnel excavator
RU22186U1 (en) MINING INSTALLATION
JP3441016B2 (en) Tunnel construction equipment
JP2762140B2 (en) Construction method of underground continuous wall based on underground tunnel
KR100354997B1 (en) Digging through work and movement footing device for digging through the same time top and bottom a tunnel
JP3243727B2 (en) Tunnel excavation method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040129

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060620

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060706

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120728

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees