JP2996096B2 - Large section tunnel excavator - Google Patents

Large section tunnel excavator

Info

Publication number
JP2996096B2
JP2996096B2 JP6162078A JP16207894A JP2996096B2 JP 2996096 B2 JP2996096 B2 JP 2996096B2 JP 6162078 A JP6162078 A JP 6162078A JP 16207894 A JP16207894 A JP 16207894A JP 2996096 B2 JP2996096 B2 JP 2996096B2
Authority
JP
Japan
Prior art keywords
segment
tunnel
drilling
lining
section tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP6162078A
Other languages
Japanese (ja)
Other versions
JPH0828176A (en
Inventor
武則 山嵜
恭三 須山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP6162078A priority Critical patent/JP2996096B2/en
Publication of JPH0828176A publication Critical patent/JPH0828176A/en
Application granted granted Critical
Publication of JP2996096B2 publication Critical patent/JP2996096B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、切羽の掘削から覆工
までの作業を一台で行なえるようにした大断面トンネル
掘進機に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a large section tunneling machine capable of performing operations from excavation of a face to lining.

【0002】[0002]

【従来の技術】大断面トンネルを掘削する場合、従来で
は一般に多連ジャンボ等の掘削機械によって切羽を削孔
し、装薬を仕掛けて破砕し、あるいは、該削孔にクサビ
状の削岩機を挿入して割岩し、これらにより、発生した
ズリをズリかき用バックホウ,ズリ積機,ダンプトラッ
クなどの重機により坑口側に排出し、次いで吹付けコン
クリートなどによりトンネル内面を覆工する作業が繰り
返される。
2. Description of the Related Art In the case of excavating a tunnel with a large cross section, a drilling machine such as a multiple jumbo drilling machine generally drills a face, mounts a charge and crushes the drill, or inserts a wedge-shaped rock drill into the drilling hole. The rocks are inserted into the rocks, and the generated waste is discharged to the pit side by heavy equipment such as a backhoe for scraping, a shear loader, a dump truck, etc., and then the work of lining the inside of the tunnel with shotcrete is repeated. It is.

【0003】[0003]

【発明が解決しようとする課題】したがって、この種の
作業では重機の輻輳が避けられず、作業停滞の原因とな
るとともに、吹付けコンクリートにより粉塵が発生し、
作業環境が悪化する原因となる。
Therefore, congestion of heavy equipment is inevitable in this type of work, causing work stagnation, and dust is generated by shotcrete.
It causes the working environment to deteriorate.

【0004】そこでこの発明は以上の課題に着目してな
されたものであって、切羽面の削孔、掘削ズリの排出及
び覆工迄の作業を一台で行なえるようにし、これにより
急速施工を可能とした大断面トンネル掘進機を提供する
ことを目的とする。
Accordingly, the present invention has been made in view of the above-mentioned problems, and is capable of performing operations up to drilling of a face face, discharging of excavation debris, and lining with one unit, thereby achieving rapid construction. It is an object of the present invention to provide a large section tunnel excavator that has made it possible.

【0005】またこの発明は、覆工に際し粉塵の発生が
なく、これにより作業環境の悪化を防止することを他の
目的とする。
Another object of the present invention is to prevent dust from being generated at the time of lining, thereby preventing the working environment from deteriorating.

【0006】[0006]

【課題を解決するための手段】この発明は、かかる目的
を達成するためになされたものであって、大断面トンネ
ルの削孔用の多数の削孔機を先端に設けるとともに、ズ
リ排出機構を備えた躯体と、該機体上に前記トンネルの
断面形状に沿ったアーチ形をなして配置され、かつ周面
にセグメントを設置するセグメント組立架台と、該組立
架台を前記トンネル内面に向けて押付ける押付け機構と
を備えたことを特徴とする大断面トンネル掘進機、をそ
の要旨とするものである。
DISCLOSURE OF THE INVENTION The present invention has been made to achieve the above object, and provides a large number of drilling machines for drilling a large-section tunnel at a tip thereof, and a mechanism for discharging a shear. A skeleton provided, a segment assembling pedestal arranged on the fuselage in an arch shape along the cross-sectional shape of the tunnel, and a segment installed on the peripheral surface, and pressing the assembled pedestal toward the inner surface of the tunnel A large section tunnel excavator characterized by having a pressing mechanism is provided.

【0007】なお、この発明で定義するセグメントは、
場所打ち用の転用型枠も含むものであり、場所打ちコン
クリートの注入及び固化後に撤去し、転用することも可
能である。
The segments defined in the present invention are:
It also includes a diversion formwork for cast-in-place, and can be removed and cast after casting and solidification of cast-in-place concrete.

【0008】[0008]

【作用】以上の構成によるこの発明の大断面トンネル掘
進機にあっては、機体先端に設けたドリルジャンボによ
り削孔を行ない、ズリ排出機構により掘削ズリを機体後
方に排出する作業と同時に、セグメント組立架台上に架
設されたセグメントをトンネル内面に据付固定すること
によって覆工を行なう。このセグメント組立方式によれ
ば吹付けコンクリートによる粉塵発生がない。
In the tunnel tunnel machine having a large cross section according to the present invention having the above-described structure, drilling is performed by a drill jumbo provided at the tip of the machine body, and at the same time as the operation of discharging the drilling machine to the rear of the machine body by the machine tool, a segment discharging operation is performed. The lining is performed by installing and fixing the segments installed on the assembly base to the inner surface of the tunnel. According to this segment assembling method, dust is not generated by shotcrete.

【0009】[0009]

【実施例】以下この発明の実施例を図面を用いて詳細に
説明する。図1ないし図5はこの発明の第一実施例を示
し、図1はこの発明にかかるトンネル掘進機の縦断面
図、図2は同横断面図である。
Embodiments of the present invention will be described below in detail with reference to the drawings. 1 to 5 show a first embodiment of the present invention. FIG. 1 is a longitudinal sectional view of a tunnel machine according to the present invention, and FIG. 2 is a transverse sectional view of the same.

【0010】図1,2において、1は中硬岩〜硬岩等の
比較的地山が良好な地盤E内を楕円状の変形円断面形状
をなして掘削される(例えば幅20m,断面積230m
2 に至る)大断面トンネルであり、このトンネル1の切
羽面1aの上半部はこの発明に係る大断面トンネル掘進
機2により掘削される。
In FIGS. 1 and 2, reference numeral 1 denotes an excavation (eg, a width of 20 m, a cross-sectional area of 20 m, and a cross-sectional area of an elliptical deformed circular cross-section) in a ground E having relatively good ground such as medium hard rock to hard rock. 230m
2 ), and the upper half of the face 1a of the tunnel 1 is excavated by the large section tunnel machine 2 according to the present invention.

【0011】トンネル掘進機2は、トンネル1の上半部
のアーチ形状に対応して断面略凸形に枠組みされたフレ
ーム形状であって、下面前後左右のそれぞれに自走用の
一対の履帯3を備えた機体4と、機体4の先端に多段か
つ多連に突設配置された多数のドリルジャンボ(削孔
機)5と、機体4の先端下部に配置されたズリ掻き寄せ
装置6と、ズリ掻き寄せ装置6の後部に連設され、後端
を機体4の後部に位置させたズリ排出用のベルトコンベ
ア7とを備えている。
The tunnel machine 2 has a frame shape with a substantially convex cross-section corresponding to the arch shape of the upper half of the tunnel 1. A pair of self-propelled crawler belts 3 are provided on the front, rear, left and right sides of the lower surface, respectively. , A plurality of drill jumbo (drilling machine) 5 protrudingly arranged at the tip of the body 4 in multiple stages and multiples, and a scraper scraping device 6 arranged at a lower part of the tip of the body 4. A belt conveyor 7 is provided at a rear portion of the scraping device 6 and has a rear end located at a rear portion of the machine body 4 for discharging a shear.

【0012】そして、機体4の上部はトンネル1の上部
アーチ形状に沿った断面形状のカバー8で覆われ、この
カバー8上には、これとほぼ同一のアーチ形断面形状で
あって1セグメント分の長さのセグメント組立架台9が
前後移動可能に配置されている。
The upper part of the fuselage 4 is covered with a cover 8 having a cross-sectional shape along the upper arch shape of the tunnel 1. The cover 8 has substantially the same arch-shaped cross-sectional shape as that of one segment. The length of the segment assembly base 9 is set to be movable back and forth.

【0013】また、カバー8上には複数の軌条10が前
後方向に沿って敷設され、組立架台9の下部に設けた車
輪11を前記軌条10に沿って転動させることで組立架
台9はカバー8上を前後移動可能となっている。なお、
この移動方式としては牽引方式や自走行車輪方式のいず
れも採用できる。
A plurality of rails 10 are laid on the cover 8 along the front-rear direction, and the wheels 11 provided at the lower part of the assembly base 9 are rolled along the rails 10 so that the assembly base 9 is covered. 8 can be moved back and forth. In addition,
As the moving method, any of a towing method and a self-propelled wheel method can be adopted.

【0014】機体4の先端上部には前記カバー8を貫通
する複数の押付け手段、すなわち昇降用油圧ジャッキ1
2が配置され、これら油圧ジャッキ12は前記組立架台
9の前進位置でこれの内面に当接し、組立架台9をトン
ネル1の天井面アーチ形状に沿って押し上げる。
A plurality of pressing means penetrating the cover 8, that is, the lifting hydraulic jack 1
2, the hydraulic jacks 12 abut against the inner surface of the assembling gantry 9 at the forward position thereof, and push up the assembling gantry 9 along the arch shape of the ceiling surface of the tunnel 1.

【0015】さらに機体4の内部には、前記各ドリルジ
ャンボ5の前進後退,横移動及び削孔回転させるための
駆動ユニット14,油圧ユニット15,電源設備16及
び裏込め注入装置17などが配置されている。裏込め注
入装置17には注入パイプ18が接続され、その先端を
後述するセグメントの内外を貫通して突設配管できるよ
うにしている。
Further, a drive unit 14, a hydraulic unit 15, a power supply unit 16, a back-filling injection device 17, and the like for moving the drill jumbo 5 forward and backward, laterally moving and drilling are arranged inside the body 4. ing. An injection pipe 18 is connected to the back-filling injection device 17, and the distal end of the injection pipe 18 penetrates the inside and outside of a segment, which will be described later, so as to be able to protrude.

【0016】さらにまたトンネル掘進機2の後部にはセ
グメント積込み用のクレーン19が配置されている。こ
のクレーン19は、図1,図3に示すように、両側をト
ンネル1内地盤上に敷設された軌条20に沿って移動可
能な門形クレーンであって、その上部側は前記組立架台
9よりも一段高く、かつアーチ断面に形成され、そのア
ーチ状部19aに沿って走行可能なトロリー21の下部
に位置する搬送用台車22上に搭載された各セグメント
ピース23aを吊り上げ、機体4上の後部に位置する組
立架台9上に移設するものである。
Further, a crane 19 for loading the segments is arranged at the rear of the tunnel machine 2. This crane 19 is a portal crane movable on both sides along a rail 20 laid on the ground in the tunnel 1 on both sides as shown in FIGS. Each segment piece 23a mounted on a transport trolley 22 located at the lower part of a trolley 21, which is formed one step higher and has an arch cross section and can travel along the arched portion 19a, is lifted, and a rear portion on the body 4 is lifted. Is moved to the assembly stand 9 located at the position shown in FIG.

【0017】そして、前記組立架台9の両端部9aは、
図4に示すように、リフト機構(図略)を介して伸縮可
能となっており、両端部9aを縮少した状態で前記クレ
ーン19から〜に示す順で各セグメントピース23
aを組立架台9上に架設し、全てのセグメントピース2
3aの搭載が完了したのなら、両端部9aを伸張させ、
各セグメントピース23aを径方向に接合し、一体のセ
グメント23に組立てる。
Then, both ends 9a of the assembling base 9 are
As shown in FIG. 4, each of the segment pieces 23 can be extended and contracted via a lift mechanism (not shown) in the order shown from the crane 19 with both ends 9a contracted.
a on the assembling gantry 9 and all the segment pieces 2
When the mounting of 3a is completed, both ends 9a are extended,
Each segment piece 23a is joined in the radial direction and assembled into an integral segment 23.

【0018】接合に際しての位置決め機構として図5に
示すように各セグメントピース23aの端面にピン24
a及びほぞ孔24bを形成しておくことによって組立架
台9の両端の9aの縮少によりそれぞれが互いに嵌合し
つつ接合するため、精度良く接合できる。
As shown in FIG. 5, a pin 24 is attached to the end face of each segment piece 23a as a positioning mechanism for joining.
By forming the mortise holes 24a and the tenon holes 24b, the joints 9 are fitted together with each other due to the reduction of the diameters 9a at both ends of the assembling pedestal 9, so that the joining can be performed with high precision.

【0019】また、接合後にセグメントピース23a同
士を連結するためには、一般にはボルトボックスをセグ
メントピースの内周面側に設けるのであるが、この実施
例では同図5に示すように、ボルトボックス25をセグ
メントピース23aの外周側に形成しておき、このボル
トボックス25同士をボルトナットを介して接合するこ
とによって隣合うセグメントピース23a同士を連結
し、セグメント23が形成される。
In order to connect the segment pieces 23a to each other after joining, a bolt box is generally provided on the inner peripheral side of the segment piece. In this embodiment, as shown in FIG. 25 is formed on the outer peripheral side of the segment piece 23a, and the bolt boxes 25 are joined to each other via bolt nuts to connect the adjacent segment pieces 23a to form the segment 23.

【0020】このボルトナットの締結は、組立架台9の
後退位置での作業であるため、常に定位置作業となる。
したがって、例えば機体4の後部にセグメントボルト締
結ロボットを配置しておけば、これの駆動によりセグメ
ント23の搭載作業終了後自動的に締結作業を行なうこ
とができる。
Since the fastening of the bolt and nut is performed at the retracted position of the assembling pedestal 9, it is always performed at a fixed position.
Therefore, if, for example, a segment bolt fastening robot is arranged at the rear part of the body 4, the fastening work can be automatically performed after the mounting work of the segment 23 is completed by driving the robot.

【0021】なお、各セグメントピース23aのうち組
立架台9の両端に位置させるセグメントピース23a
(図4の,)は図6(a),(b)に示すように外
側ピース23a−1に対し内側ピース23a−2を伸縮
可能に嵌合したものとし、これの縮小状態で組立架台9
に架設し、トンネル内面にセットした状態で、内側ピー
ス23a−1を引きだし、この引き出し端を地盤上に着
地させれば、セグメント23の自立性を得られ、覆工作
業中組立架台9により支持する必要はなくなる。
The segment pieces 23a located at both ends of the assembling pedestal 9 among the segment pieces 23a
4A and 4B, the inner piece 23a-2 is fitted to the outer piece 23a-1 so as to be extendable and contractable as shown in FIGS. 6A and 6B.
When the inner piece 23a-1 is pulled out in a state where the inner piece 23a-1 is set on the inner surface of the tunnel and the drawn end lands on the ground, the independence of the segment 23 is obtained, and the segment 23 is supported by the assembly base 9 during the lining work. You don't have to.

【0022】次に以上のトンネル掘進機2による切羽の
掘削から覆工までの手順について説明する。
Next, the procedure from excavation of the face to lining by the tunnel machine 2 will be described.

【0023】まず、機体4が切羽面1aに対向して停止
している状態で、図1中想像線で示す待機位置にあるド
リルジャンボ5を前進させて切羽面1aに所定の深さ及
びパターンで削孔する。
First, in a state where the fuselage 4 is stopped facing the face 1a, the drill jumbo 5 at the standby position indicated by the imaginary line in FIG. 1 is advanced to a predetermined depth and pattern on the face 1a. Drill with

【0024】次いで各ドリルジャンボ5を前記待機位置
まで後退させ、装薬を装填し、切羽面1aを発破により
掘削する。次いで、掘削により生じた掘削ズリをズリ掻
き寄せ装置6により掻き寄せ、ベルトコンベア7を通じ
て機体4の後方に搬送し、コンベア7の後端に待機する
図示しないズリ運搬車,ダンプトラック等の輸送手段に
順次受け渡し、これらを通じて坑外に排出する。
Next, each drill jumbo 5 is retracted to the standby position, a charge is charged, and the face 1a is excavated by blasting. Next, the excavated scrap generated by the excavation is scraped by the scraping scraping device 6, conveyed to the rear of the machine body 4 through the belt conveyor 7, and transport means such as a not-shown scrap truck or dump truck waiting at the rear end of the conveyor 7. And sequentially discharged to the outside of the mine.

【0025】一方、以上の作業と平行して、機体4の後
部位置に待機している組立架台9上にクレーン19を通
じて順次セグメントピース23aを架設し、この位置で
セグメント23の組立を行なう。
On the other hand, in parallel with the above operation, the segment pieces 23a are sequentially erected through the crane 19 on the assembling stand 9 waiting at the rear position of the body 4, and the segments 23 are assembled at this position.

【0026】掘削作業終了を待って、セグメント23を
保持した組立架台9を切羽面1a側に前進させ、前進停
止位置で油圧ジャッキ12を一斉に伸長側に駆動し、組
立架台9をトンネル1の天井面に押し付けることによっ
て組み上がったセグメント23を天井面に位置させる
(図2参照)。なお、このセグメント23に後続するセ
グメント23´との接続はボルト等の締結部材を介して
接続される。
After completion of the excavation work, the assembly base 9 holding the segment 23 is advanced to the face 1a side, and the hydraulic jacks 12 are simultaneously driven to the extension side at the advance stop position to move the assembly base 9 to the tunnel 1 side. The segment 23 assembled by pressing against the ceiling surface is positioned on the ceiling surface (see FIG. 2). The connection with the segment 23 'following the segment 23 is made via a fastening member such as a bolt.

【0027】次いで両端のセグメントピース23aの内
側ピース23a−2を引きだし、その引き出し端を地盤
上に固定すればセグメント23は自立する。この状態で
組立架台9を再び後部待機位置に移動させ、裏込め注入
用パイプ18をセグメント23に接続し、裏込め注入装
置17を駆動して裏込材26を地盤内部に注入すれば、
覆工を終了する。
Next, if the inner piece 23a-2 of the segment piece 23a at both ends is pulled out and its drawn end is fixed on the ground, the segment 23 becomes independent. In this state, the assembling pedestal 9 is moved to the rear standby position again, the backfilling pipe 18 is connected to the segment 23, and the backfilling device 17 is driven to inject the backing material 26 into the ground.
Finish the lining.

【0028】前記組立架台9の後退後、あるいはこの覆
工作業完了後機体4を一掘削分前進させることにより、
再び前記と同様のサイクルで掘削から覆工を行なうこと
ができる。なお、前記切羽面における削孔作業、その後
の装薬の装填作業は、覆工作業,裏込材26の注入作業
等と並行して行うことができる。
After retreating the assembling pedestal 9 or after completing the lining work, the body 4 is advanced by one excavation,
Again, excavation to lining can be performed in the same cycle as described above. The drilling operation on the face face and the subsequent charging operation of the charge can be performed in parallel with the lining operation, the filling operation of the backing material 26, and the like.

【0029】なお、本実施例では覆工用にセグメント2
3を用いたが、これに換えて場所打ち用の転用型枠を用
いても良く、この場合には、場所打ちコンクリートの注
入及び固化後に該型枠を撤去し、転用することができ
る。
In this embodiment, the segment 2 is used for lining.
Although the casting mold 3 was used, a casting mold for cast-in-place may be used instead. In this case, the casting cast-in and solidification of the cast-in-place concrete can be removed and the cast can be diverted.

【0030】また前記各実施例では上半部専用としてあ
るが、同様な機構により限定上半掘削、下半掘削、補助
ベンチ付き全断面掘削にも適用可能である。
In each of the above embodiments, the upper half is exclusively used. However, the same mechanism can be applied to limited upper half excavation, lower half excavation, and full-section excavation with an auxiliary bench.

【0031】[0031]

【発明の効果】以上各実施例により詳細に説明したよう
に、この発明にかかる大断面トンネル掘進機にあって
は、大断面トンネルの削孔用の多数の削孔機を先端に設
けるとともに、ズリ排出機構を備えた機体と、該機体上
に前記トンネルの断面形状に沿ったアーチ形をなして配
置され、かつ周面にセグメントを設置するセグメント組
立架台と、該組立架台を前記トンネル内面に向けて押付
ける押付け機構とを備えたものであるから、機体先端に
設けたドリルジャンボにより削孔を行ない、ズリ排出機
構により掘削ズリを機体後方に排出する作業と同時に、
セグメント組立架台上に架設されたセグメントをトンネ
ル内面に据付固定することによって覆工を行なうため、
掘削毎のズリだしや、覆工のための重機の輻輳がなく、
急速施工が可能となる。
As described in detail in the above embodiments, in the large section tunnel excavator according to the present invention, a large number of drilling machines for drilling a large section tunnel are provided at the tip thereof. A fuselage equipped with a shear discharge mechanism, a segment assembly gantry arranged on the fuselage in an arch shape along the cross-sectional shape of the tunnel, and a segment installed on a peripheral surface, and the assembly gantry mounted on the inner surface of the tunnel. Since it is equipped with a pressing mechanism that presses toward the machine, drilling is performed by the drill jumbo provided at the tip of the fuselage, and the
In order to perform lining by installing and fixing the segment built on the segment assembly base to the inner surface of the tunnel,
There is no slippage for each excavation or congestion of heavy equipment for lining,
Rapid construction becomes possible.

【0032】またこの発明では、セグメント組立方式に
しているため、吹付けコンクリートによる粉塵発生がな
く、作業環境を良好に保持することができるほか、機械
式に組立てるため、作業の安全性が確保できるなどの利
点がある。
Further, according to the present invention, since the segment assembling method is employed, dust is not generated by sprayed concrete, the working environment can be maintained well, and since the assembly is performed mechanically, the safety of work can be ensured. There are advantages such as.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明の第一実施例による大断面トンネル掘
進機の側断面図である。
FIG. 1 is a side sectional view of a large section tunnel excavator according to a first embodiment of the present invention.

【図2】同横断面図である。FIG. 2 is a cross-sectional view of the same.

【図3】セグメント積込み用クレーンの正面図である。FIG. 3 is a front view of a segment loading crane.

【図4】組立架台に対するセグメントピースの架設手順
を示す説明図である。
FIG. 4 is an explanatory view showing a procedure for installing a segment piece on an assembly base.

【図5】セグメントピースの部分斜視図である。FIG. 5 is a partial perspective view of a segment piece.

【図6】(a)はセグメント両端部に位置するセグメン
トピースの断面図である。(b)は(a)のB−B線断
面図である。
FIG. 6A is a sectional view of a segment piece located at both ends of a segment. (B) is a sectional view taken along line BB of (a).

【符号の説明】[Explanation of symbols]

1 大断面トンネル 1a 切羽面 2 大断面トンネル掘進機 4 機体 5 ドリルジャンボ(削孔機) 6 ズリ掻き寄せ装置 7 ベルトコンベア 9 セグメント組立架台 12 昇降用油圧ジャッキ(押付け機構) 23 セグメント DESCRIPTION OF SYMBOLS 1 Large-section tunnel 1a Face face 2 Large-section tunnel excavator 4 Airframe 5 Drill jumbo (drilling machine) 6 Scraping device 7 Belt conveyor 9 Segment assembly stand 12 Hydraulic jack for lifting (pressing mechanism) 23 segment

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.6,DB名) E21D 9/00 E21D 11/40 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 6 , DB name) E21D 9/00 E21D 11/40

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 大断面トンネルの削孔用の多数の削孔機
を先端に設けるとともに、ズリ排出機構を備えた機体
と、該機体上に前記トンネルの断面形状に沿ったアーチ
形をなして配置され、かつ周面にセグメントを設置する
セグメント組立架台と、該組立架台を前記トンネル内面
に向けて押付ける押付け機構とを備えたことを特徴とす
る大断面トンネル掘進機。
1. A machine body provided with a large number of drilling machines for drilling a large-section tunnel at its tip and having a shear discharge mechanism, and an arched shape on the machine body along the cross-sectional shape of the tunnel. A large section tunnel excavator, comprising: a segment assembling gantry that is arranged and installs a segment on a peripheral surface; and a pressing mechanism that presses the assembling gantry toward the inner surface of the tunnel.
JP6162078A 1994-07-14 1994-07-14 Large section tunnel excavator Expired - Fee Related JP2996096B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6162078A JP2996096B2 (en) 1994-07-14 1994-07-14 Large section tunnel excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6162078A JP2996096B2 (en) 1994-07-14 1994-07-14 Large section tunnel excavator

Publications (2)

Publication Number Publication Date
JPH0828176A JPH0828176A (en) 1996-01-30
JP2996096B2 true JP2996096B2 (en) 1999-12-27

Family

ID=15747673

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6162078A Expired - Fee Related JP2996096B2 (en) 1994-07-14 1994-07-14 Large section tunnel excavator

Country Status (1)

Country Link
JP (1) JP2996096B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109372517A (en) * 2018-09-28 2019-02-22 北京交通大学 One kind is suitable for wearing water supplying pipe construction method under upper soft lower hard compound stratum tunnel

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CZ304723B6 (en) * 2012-07-10 2014-09-10 Čeněk Hořava Tunnel making method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109372517A (en) * 2018-09-28 2019-02-22 北京交通大学 One kind is suitable for wearing water supplying pipe construction method under upper soft lower hard compound stratum tunnel

Also Published As

Publication number Publication date
JPH0828176A (en) 1996-01-30

Similar Documents

Publication Publication Date Title
JP4181980B2 (en) Tunnel construction method
JP2996096B2 (en) Large section tunnel excavator
JP3355235B2 (en) Tunnel construction method and device
CN113446020B (en) Hole-expansion-free type in-hole disassembly method for open TBM host
JP5528049B2 (en) Tunnel drilling equipment
JP3831900B2 (en) Tunnel construction method
JP4281983B2 (en) Tunnel excavation method using advanced shaft
JP2854227B2 (en) Form-mounted gantry jumbo
JP2573882B2 (en) Tunnel rapid construction method and its drilling equipment
JP3512012B2 (en) How to excavate
JP2956486B2 (en) Forming equipment for lining tunnel arches
JP2869876B2 (en) Construction method and device for inclined tunnel
JP3151116B2 (en) Tunnel excavation method and gantry used for this method
JP2791261B2 (en) Multi-function excavator
JP3543633B2 (en) Tunnel drilling rig
JPH02210189A (en) Shield machine
JP3441016B2 (en) Tunnel construction equipment
JP5279676B2 (en) Box assembly equipment
JP3357654B2 (en) Gantry used for tunnel excavation method
JP4845504B2 (en) Tunnel excavation method using a ramp device for tunnel excavation
JP4172330B2 (en) Widening equipment and widening method for existing tunnels
JPH06257377A (en) Tunnel construction method and device therefor
JP3153852B2 (en) Tunnel lining equipment
JP3438208B2 (en) Tunnel construction equipment
JP2645319B2 (en) Tunnel excavator

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071029

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081029

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091029

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091029

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101029

Year of fee payment: 11

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101029

Year of fee payment: 11

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111029

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121029

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121029

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131029

Year of fee payment: 14

LAPS Cancellation because of no payment of annual fees