JP3103285B2 - Tunnel excavation method - Google Patents

Tunnel excavation method

Info

Publication number
JP3103285B2
JP3103285B2 JP06334154A JP33415494A JP3103285B2 JP 3103285 B2 JP3103285 B2 JP 3103285B2 JP 06334154 A JP06334154 A JP 06334154A JP 33415494 A JP33415494 A JP 33415494A JP 3103285 B2 JP3103285 B2 JP 3103285B2
Authority
JP
Japan
Prior art keywords
bench
tunnel
gantry
excavated
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP06334154A
Other languages
Japanese (ja)
Other versions
JPH08165881A (en
Inventor
徳夫 高橋
勉 五十嵐
靖俊 萩原
栄吉 桔梗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP06334154A priority Critical patent/JP3103285B2/en
Publication of JPH08165881A publication Critical patent/JPH08165881A/en
Application granted granted Critical
Publication of JP3103285B2 publication Critical patent/JP3103285B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明はトンネル切羽部を上段ベ
ンチと下段ベンチとに区分して夫々のベンチの切羽地盤
を掘削する、所謂二段ベンチカット工法によってトンネ
ルを掘進するトンネル掘削方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel excavation method in which a tunnel face is divided into an upper bench and a lower bench, and the ground of each bench is excavated. It is.

【0002】[0002]

【従来の技術】従来から、二段ベンチカット工法によっ
てトンネルを掘削する場合、まず、上段ベンチの切羽地
盤を掘削して掘削土砂の搬出後、該ベンチ部の掘削壁面
に対する支保工の組立て、金網の張設、コンクリートの
吹付作業を順次施工して一時覆工を行い、次いで、下段
ベンチの切羽地盤の掘削作業を行い、上段ベンチと同様
に掘削壁面に対する支保工の組立て、金網の張設、コン
クリートの吹付作業を順次施工して一時覆工を行ってい
る。さらに、下段ベンチの後方におけるトンネル底面に
インバートの掘削を行い、該インバートにコンクリート
を打設すると共に後方において二次覆工のコンクリート
を打設してトンネルを築造している。
2. Description of the Related Art Conventionally, when a tunnel is excavated by a two-stage bench-cutting method, first, a cutting ground of an upper bench is excavated, and excavated earth and sand are carried out. Construction work, concrete spraying work is sequentially performed to perform temporary lining, and then excavation work is performed on the face ground of the lower bench. Temporary lining is being carried out by sequentially spraying concrete. Further, an invert is excavated on the bottom of the tunnel behind the lower bench, concrete is poured into the invert, and concrete for secondary lining is cast behind the invert to construct a tunnel.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上記の
ような二段ベンチカット工法によるトンネル掘削によれ
ば、上段ベンチにおいて、その切羽の掘削作業から掘削
地盤に対するコンクリートの吹付作業までの一連の作業
を行ったのち、下段ベンチに対する掘削作業から掘削地
盤に対するコンクリートの吹付作業に移るものであるか
ら、トンネル掘削の作業性が悪くて長期間の工期を必要
とする問題点がある。
However, according to the tunnel excavation by the two-stage bench cut method as described above, a series of operations from the excavation of the face to the spraying of concrete on the excavated ground are performed on the upper bench. After performing the operation, the operation shifts from excavation work on the lower bench to spraying concrete on the excavation ground. Therefore, there is a problem that the workability of tunnel excavation is poor and a long construction period is required.

【0004】このような問題点は、上段ベンチと下段ベ
ンチとの切羽地盤の掘削を同時に行い、夫々の掘削土砂
をダンプトラック等の土砂運搬車によって搬出するよう
にすれば解消し得るが、作業空間が狭いトンネル内にお
いて土砂運搬車を掘削現場近くまで走行させると、土砂
運搬車が複湊して危険であり、その上、後方側における
インバートの掘削作業やコンクリートの打設作業にも支
障を来たすことになって、実際上は同時掘削が困難であ
る。
[0004] Such a problem can be solved by excavating the face ground of the upper bench and the lower bench at the same time and carrying out the excavated soil by a soil transport vehicle such as a dump truck. If the soil carrier is driven near the excavation site in a tunnel with a narrow space, the soil carrier will be mixed and dangerous, and in addition, the invert excavation work and concrete placement work on the rear side will be hindered. As a result, simultaneous drilling is difficult in practice.

【0005】本発明はこのような問題点に鑑みてなされ
たもので、その目的とするところは上段ベンチと下段ベ
ンチとの切羽地盤に対する土砂の掘削から掘削壁面に対
する一次覆工コンクリート吹付け作業までの一連の工
程、およびインバートに対するコンクリート打設作業を
並行して実施可能とし、トンネルの掘削作業が能率よく
行えるトンネルの掘削方法を提供するにある。
[0005] The present invention has been made in view of the above-mentioned problems, and an object thereof is from excavation of earth and sand to the face ground of an upper bench and a lower bench to spraying of primary lining concrete on an excavated wall surface. It is an object of the present invention to provide a method of excavating a tunnel in which a series of steps and a concrete placing operation for an invert can be performed in parallel, and a tunnel excavating operation can be performed efficiently.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明のトンネルの掘削方法は、トンネル切羽部を
上段ベンチと下段ベンチとに区分して両ベンチの切羽地
盤を掘削することによりトンネルを掘進する方法であっ
て、前端側脚柱を上記上段ベンチ上に走行自在に支持さ
せると共に後側脚柱を切羽部後方のインバートコンクリ
ート上に走行自在に支持させてなるガントリーにベルト
コンベア等の掘削土砂運搬装置を吊支し、上記上段ベン
チと下段ベンチの切羽地盤を掘削した土砂を上記運搬装
置によってトンネル後方に搬送してガントリーの後端側
に待機している土砂運搬車に搬出すると共に土砂の搬出
後、上下段ベンチの掘削壁面に対する支保工の建込みか
らコンクリートの吹付けまでの一次覆工を並行して行
い、さらに、ガントリーの下方において上記既設インバ
ートコンクリートに接して新たなインバートの掘削とイ
ンバートコンクリートの打設を行うことを特徴とするも
のである。
In order to achieve the above object, a method for excavating a tunnel according to the present invention comprises dividing a tunnel face into an upper bench and a lower bench and excavating the face ground of both benches. A method of excavating a tunnel, wherein a front end pillar is movably supported on the upper bench, and a rear pillar is movably supported on inverted concrete behind a cutting face. The excavated sediment transporting device is suspended, and the excavated soil of the upper and lower benches is conveyed to the rear of the tunnel by the transporting device, and is carried out to the sediment transporting vehicle waiting at the rear end of the gantry. After carrying out the earth and sand, the primary lining from the installation of the support to the excavation wall of the upper and lower benches to the spraying of the concrete was carried out in parallel. Below the over is characterized in carrying out the pouring drilling and invert concrete new inverted in contact with the existing invert concrete.

【0007】上記方法において、請求項2に記載したよ
うに、上段ベンチの切羽地盤の掘削工程と下段ベンチの
切羽地盤の掘削工程とを同時に行い、上段ベンチの掘削
土砂を下段ベンチ上に搬出、堆積させて下段ベンチの掘
削地盤と共に上記ガントリに吊支した運搬装置によりト
ンネル後方に搬送してもよく、また、請求項3に記載し
たように、上段ベンチの切羽地盤の掘削土砂を上記運搬
装置によってトンネル後方に搬送したのち、下段ベンチ
の切羽地盤の掘削土砂を上記運搬装置によりトンネル後
方に搬出してもよい。なお、請求項4に記載した発明は
上記ガントリーに支保材等の運搬用トロリーを走行自在
に配設した構造としている。
In the above method, the excavation process of the face ground of the upper bench and the excavation process of the face ground of the lower bench are simultaneously performed, and the excavated earth and sand of the upper bench is carried out to the lower bench. The excavated soil of the face ground of the upper bench may be transported to the rear of the tunnel by a transport device suspended from the gantry together with the excavated ground of the lower bench. , The excavated earth and sand on the face ground of the lower bench may be carried out to the rear of the tunnel by the above-mentioned transport device. The invention described in claim 4 has a structure in which a trolley for transporting a support material or the like is movably disposed on the gantry.

【0008】[0008]

【作用】掘削土砂運搬装置を配設したガントリーを上段
ベンチ上とインバートコンリート上との間に架設状態で
走行自在に配設し、両ベンチ上で掘削機によって掘削し
た土砂をガントリーに設けた運搬装置によって該ガント
リーの後端にまで搬出する。その際、両ベンチの切羽地
盤の掘削作業を同時に行い、それぞれの掘削土砂をガン
トリーに配設した運搬装置によって搬出する。また、上
段ベンチ側の掘削土砂を下段ベンチ上に落としこみ、下
段ベンチ側から運搬装置によって搬出することもでき
る。なお、上段ベンチ側の掘削土砂を運搬装置によって
搬出したのち下段ベンチ側の掘削土砂を搬出してもよ
い。
[Function] A gantry equipped with an excavated earth and sand transport device is movably installed in a state of being erected between the upper bench and the invert concrete, and the earth and sand excavated by an excavator on both benches is installed in the gantry. It is carried out to the rear end of the gantry by the device. At that time, the excavation work of the face of both benches is performed at the same time, and each excavated earth and sand is carried out by the transport device arranged in the gantry. Also, the excavated earth and sand on the upper bench side can be dropped onto the lower bench, and can be carried out from the lower bench side by a transport device. The excavated earth and sand on the lower bench side may be carried out after the excavated earth and sand on the upper bench side are carried out by the transport device.

【0009】この掘削土砂の搬出は、上段ベンチ上から
インバートコンクリート上に亘って走行自在に設置して
いるガントリーに沿って行われるので、この土砂搬出作
業に邪魔されることなく、ガントリーの下方空間部にお
いてインバートに対する型枠の組立、コンクリートの打
設作業が並行して行える。また、上段ベンチ側の掘削土
砂の排出後、該上段ベンチの掘削壁面に支保工の建込み
からコンクリートの吹付けまでの一次覆工を行う一方、
下段ベンチ側においては掘削土砂の排出後、上段ベンチ
側に並行して掘削壁面に支保工の建込みからコンクリー
トの吹付けまでの一次覆工を行う。
Since the excavated earth and sand is carried out along the gantry which is installed so as to be able to travel from the upper bench to the invert concrete, the space below the gantry is not hindered by the earth and sand unloading operation. The assembly of the formwork for the invert and the concrete placement work can be performed in parallel at the section. Also, after discharging the excavated earth and sand on the upper bench side, while performing the primary lining from the construction of the support to the spraying of concrete on the excavation wall of the upper bench,
After the excavated earth and sand is discharged on the lower bench side, primary lining is performed in parallel with the upper bench side from the installation of the support to the spraying of concrete on the excavated wall.

【0010】[0010]

【実施例】本発明の実施例を図面について説明すると、
図1に示すように、トンネルTの切羽部の上半を上段ベ
ンチ1に、下半を下段ベンチ2にそれぞれ区分し、これ
らの上下段ベンチ1、2の切羽地盤をトンネルTの掘進
方向に一定長、掘削したのち、該掘削土砂の排除を行
い、土砂の排除後、上下段ベンチ1、2の掘削壁面に支
保工の建込みからコンクリートの吹付けまでの一次覆工
3を並行して行う一方、下段ベンチ2の後方側における
トンネル底面においてはインバート4の掘削からコンク
リート5の打設作業を上記掘削土砂の排除から一次覆工
3の施工作業に並行して行う。
BRIEF DESCRIPTION OF THE DRAWINGS FIG.
As shown in FIG. 1, the upper half of the face portion of the tunnel T is divided into an upper bench 1 and the lower half is divided into a lower bench 2, and the cutting ground of the upper and lower benches 1 and 2 is moved in the tunnel T excavation direction. After excavating for a certain length, the excavated earth and sand is removed, and after excluding the earth and sand, the primary lining 3 from the installation of the support to the spraying of the concrete on the excavated wall of the upper and lower benches 1 and 2 is performed in parallel. On the other hand, on the tunnel bottom surface behind the lower bench 2, the work of digging the invert 4 and placing the concrete 5 is performed in parallel with the work of the primary lining 3 from removing the excavated earth and sand.

【0011】そして、上記上下段ベンチ1、2に対する
切羽地盤の一定長(支保工間隔の距離であって約1m)
の掘削から一次覆工3までの作業工程を1サイクルとし
て5〜10サイクル分とこのサイクル分間に施工されるイ
ンバート4の掘削からコンクリート打設までの作業工程
とを1スパンの施工長さとして順次そのスパン間に上記
作業工程を繰り返し行うことによってトンネルを掘削し
ていくものである。
A fixed length of the cutting ground relative to the upper and lower benches 1 and 2 (a distance of the support work is about 1 m).
The work process from excavation to the primary lining 3 as one cycle is 5 to 10 cycles, and the work process from excavation of the invert 4 to casting of concrete, which is performed during this cycle, is sequentially set as a construction length of one span. The tunnel is excavated by repeatedly performing the above-described operation steps during the span.

【0012】上段ベンチ1の切羽地盤の掘削は、先端に
カッタ6aを有するアーム6bを上下回動自在に設けている
と共に該アーム6bの後端側にベルトコンベア6cを設けて
なるカッタローダ6によって行い、上記アーム6bにはカ
ッタ6aによって掘削された土砂(ずり)を掻き上げてベ
ルトコンベア6cに搬送するチエーンコンベア(図示せ
ず)が設けられている。一方、下段ベンチ2の切羽地盤
の掘削はバックホー(ショベル機)からなる掘削・積込
機7によって行う。
The excavation of the face ground of the upper bench 1 is performed by a cutter loader 6 having an arm 6b having a cutter 6a at the tip thereof, which is rotatable up and down, and a belt conveyor 6c provided at the rear end of the arm 6b. The arm 6b is provided with a chain conveyor (not shown) for scraping earth and sand excavated by the cutter 6a and transporting it to a belt conveyor 6c. On the other hand, excavation of the face ground of the lower bench 2 is performed by an excavator / loader 7 composed of a backhoe (shovel machine).

【0013】また、掘削土砂をトンネルTの切羽地盤か
らトンネル後方に搬送するには、ガントリ8に配設して
いる運搬装置9によって行う。ガントリ8は上段ベンチ
1から既に打設されたインバートコンクリート5の上方
間に亘ってトンネルの長さ方向に架設状態で配設される
水平な長尺枠体81の前端に脚柱82を、後端部に該脚注82
よりも長い脚柱83を一体的に設けてなるものである。上
記長尺枠体81は、図1〜図3に示すように、トンネルT
の上方両側部に水平に配設された上下一対の水平桁材8
4、85間を長さ方向に適宜間隔毎に縦桁86によって一体
に連結すると共に上側の桁材84、84間を横桁87によって
一体に連結してなる構造を有する。
The excavated earth and sand is conveyed from the face of the tunnel T to the rear of the tunnel by a conveying device 9 provided on the gantry 8. The gantry 8 is provided with a pillar 82 at the front end of a horizontal long frame 81 which is erected in the length direction of the tunnel from above the upper bench 1 to above the inverted concrete 5 which has already been cast. The footnote 82 at the end
A longer pillar 83 is provided integrally. The long frame 81 is, as shown in FIGS.
A pair of upper and lower horizontal beams 8 horizontally arranged on both upper sides of
The structure has a structure in which the space between 4 and 85 is integrally connected by a vertical beam 86 at appropriate intervals in the length direction, and the upper beam members 84 and 84 are integrally connected by a horizontal beam 87.

【0014】ガントリ8の長尺枠体81を支持する前端側
の上記短い脚柱82は、図2に示すように、最前端の横桁
87の両側端から垂下状態に固着されてあり、これらの両
側脚柱82、82の下端に上段ベンチ1の水平な底面上を走
行する無限履帯シューからなる走行体88を装着してい
る。この走行体88はモータ88a によって駆動される。そ
して、両側脚柱82、82と横桁87とで形成される門形状の
空間部は上記カッターローダ5が自由に出入りできる大
きさに形成されている。
As shown in FIG. 2, the short pillar 82 at the front end supporting the long frame 81 of the gantry 8 is provided at the foremost horizontal girder.
A running body 88 composed of an infinite crawler shoe that runs on the horizontal bottom surface of the upper bench 1 is attached to the lower ends of both side pillars 82, 82. The running body 88 is driven by a motor 88a. The gate-shaped space formed by the both-side pillars 82, 82 and the cross beam 87 is formed in such a size that the cutter loader 5 can freely enter and exit.

【0015】一方、ガントリ8の長尺枠体81を支持する
後方側の上記長い脚柱83は、図1及び図3に示すよう
に、長尺枠体81の中央からうしろ寄りの位置における横
桁87の両側端に上端を固着してなる前側脚柱83、83と、
後端近傍部の横桁87の両側端に上端を固着してなる後側
脚柱83、83とからなり、これら後方側の前後脚柱83の下
端には、既に打設されたインバートコンクリート5上に
敷設されているレール10上を走行する車輪89が回転自在
に軸支されている。なお、この車輪89は長尺枠体81の適
所に設置した駆動モータ(図示せず)によって積極的に
回転駆動させられるように構成している。
On the other hand, as shown in FIG. 1 and FIG. 3, the long pillar 83 on the rear side supporting the long frame 81 of the gantry 8 is located at a position slightly behind the center of the long frame 81. With front legs 83, 83 having upper ends fixed to both ends of the cross beam 87,
Rear pillars 83, 83 having upper ends fixed to both ends of the cross beam 87 near the rear end thereof, and at the lower ends of these rear front and rear pillars 83, the already-inverted concrete 5 Wheels 89 running on rails 10 laid thereon are rotatably supported. The wheels 89 are configured to be positively driven to rotate by a drive motor (not shown) provided at an appropriate position on the long frame 81.

【0016】ガントリ8に配設した運搬装置9は、一例
としてベルトコンベア91を長尺枠体81に移動自在に吊支
してなる構造を有する。具体的には、図1、図3に示す
ように、長尺枠体81の横桁87の中央部両側下面に、長尺
枠体81の略全長に亘って吊支用レール92、92を固着し、
これらの吊支用レール92、92に複数個の門型支持フレー
ム93を車輪94を介して走行可能に吊支すると共に適宜間
隔毎に並設したこれらの門型支持フレーム93、93・・・
93の下端部をベルトコンベア91の後半部を内装している
後側水平コンベア枠95の両側面に一体的に固着してい
る。さらに、この後側水平コンベア枠95の前端にはベル
トコンベア91の前半部を内装している前側傾動コンベア
枠96の後端を上下方向に回動自在に枢着97し、該傾動コ
ンベア枠96に固着した枠体98にチエーンブロック99の下
端を固定し、このチエーンブロック99の上端を上記吊支
用レール92、92に沿って走行する車輪94に連結した構造
としている。なお、18は傾動コンベア枠96の前端に装着
しているホッパーである。
The transporting device 9 disposed on the gantry 8 has a structure in which, for example, a belt conveyor 91 is movably supported by a long frame 81. Specifically, as shown in FIGS. 1 and 3, suspension support rails 92, 92 are provided on the lower surfaces on both sides of the center of the cross beam 87 of the long frame 81 over substantially the entire length of the long frame 81. Sticks,
A plurality of gate-shaped support frames 93 are supported on these suspension-support rails 92, 92 so as to be able to travel via wheels 94, and are juxtaposed at appropriate intervals.
The lower end of 93 is integrally fixed to both side surfaces of a rear horizontal conveyor frame 95 that houses the rear half of the belt conveyor 91. Further, at the front end of the rear horizontal conveyor frame 95, the rear end of a front tilting conveyor frame 96 which houses the front half of the belt conveyor 91 is pivotally mounted 97 so as to be vertically rotatable. The lower end of the chain block 99 is fixed to a frame 98 fixed to the frame 98, and the upper end of the chain block 99 is connected to the wheels 94 running along the suspension rails 92. Reference numeral 18 denotes a hopper attached to the front end of the tilting conveyor frame 96.

【0017】従って、車輪94を適宜な駆動機構(図示せ
ず)を介して回転させることにより門型支持フレーム93
及びチエーンブロック99と一体的にベルトコンベア91を
内装している前後コンベア枠95、96を吊支用レール92、
92に沿ってガントリ8の長さ方向に移動可能に構成して
いると共にチエーンブロック99を操作することによって
傾動コンベア枠96を後側水平コンベア枠95に対して、下
向き傾斜状態から水平状態にまで起伏するように構成し
ている。なお、門型支持フレーム93やチエーンブロック
99の上端は、当然のことながら車輪94から直接吊支され
ているのではなく、車輪94を回転自在に軸支した軸受部
材11に一体に連結している。また、ベルトコンベア91も
その後側水平コンベア枠95の後端部に配設したモータ等
の駆動手段(図示せず)によって無端状に走行駆動させ
られるものである。このベルトコンベア91の長さは、上
記下段ベンチ2からガントリ8の後端に達する長さに形
成されている。
Therefore, by rotating the wheels 94 via an appropriate drive mechanism (not shown), the gate-shaped support frame 93 is rotated.
And the front and rear conveyor frames 95, 96 which integrally incorporate the belt conveyor 91 with the chain block 99, the suspension support rail 92,
The tiltable conveyor frame 96 is configured to be movable in the length direction of the gantry 8 along 92 and by operating the chain block 99 from the downward inclined state to the horizontal state with respect to the rear horizontal conveyor frame 95. It is configured to undulate. In addition, the gate type support frame 93 and the chain block
Naturally, the upper end of 99 is not directly hung from the wheel 94, but is integrally connected to the bearing member 11 which rotatably supports the wheel 94. The belt conveyor 91 is also driven to run endlessly by driving means (not shown) such as a motor disposed at the rear end of the rear horizontal conveyor frame 95. The length of the belt conveyor 91 is formed to extend from the lower bench 2 to the rear end of the gantry 8.

【0018】また、ガントリ8には運搬装置9の両側方
においてガントリ8の長さ方向に走行するトロリー12、
12を配設している。このトロリー12は、長尺枠体81の横
桁87の中央部両側下面に、長尺枠体81の略全長に亘って
トロリー吊支用レール13を固着し、適宜な駆動機構(図
示せず)によって該レール13に沿って前後方向に走行
し、支保工や金網、或いは型枠等の搬送、吊支を行うも
のである。さらに、ガントリ8の長尺枠体81上には全長
に亘って上部レール14が敷設されてあり、このレール14
上の前側にコンクリート吹付機15を後側に換気用軸流フ
ァン16をそれぞれ走行自在に配設している。また、ガン
トリ8の長尺枠体81の前端上部両側には図2に示すよう
に、作業ケージ17を設けている。
The gantry 8 has trolleys 12 running on both sides of the transport device 9 in the longitudinal direction of the gantry 8,
12 are arranged. In this trolley 12, a trolley suspension support rail 13 is fixed to the lower surface on both sides of the central portion of the cross beam 87 of the long frame 81 over substantially the entire length of the long frame 81, and an appropriate drive mechanism (not shown) ) Travels along the rail 13 in the front-rear direction, and carries and supports a shoring, a wire mesh, a formwork, or the like. Further, an upper rail 14 is laid on the long frame 81 of the gantry 8 over its entire length.
A concrete spraying machine 15 is provided on the upper front side and a ventilation axial fan 16 is provided on the rear side so as to be freely movable. Also, as shown in FIG. 2, a work cage 17 is provided on both upper sides of the front end of the long frame body 81 of the gantry 8.

【0019】このように構成したガントリ8は上段ベン
チ1から既設のインバートコンクリート5間に亘って水
平に架設状態で配設され、その前後脚柱82、83をそれぞ
れ上段ベンチ1の水平底面と既設のインバートコンクリ
ート5上に走行自在に設置してあり、この状態にしてト
ンネルの掘削時における掘削土砂の搬出等を行うもので
あって、次に、そのトンネル掘削の作業順序をガントリ
8と上段ベンチ1、下段ベンチ2、インバート4の各部
の作業工程に区分して図示した図9に基づいて説明する
The gantry 8 constructed as described above is horizontally installed from the upper bench 1 to the existing invert concrete 5 and its front and rear pillars 82 and 83 are respectively connected to the horizontal bottom surface of the upper bench 1 and the existing bottom. In this state, the excavated earth and sand are carried out during the excavation of the tunnel in this state. Next, the work order of the excavation of the tunnel is determined by the gantry 8 and the upper bench. 1, the lower bench 2, and the invert 4 will be described with reference to FIG.

【0020】まず、1スパン分のインバートコンクリー
ト5の硬化が完了すると、該インバートコンクリート5
上にガントリ8を支保工間隔(約1m)だけ前進させ
る。以下、この前進を1サイクルとして、5〜10サイク
ル繰り返すことにより、上記既設のインバートコンクリ
ート5上をガントリ8の後側脚柱83の車輪89が走行する
ことになる。一方、ガントリ8の前側脚柱82の走行体88
は駆動モータ88a によって上段ベンチ1の水平底面上を
次のサイクル分だけ前進する。
First, when hardening of the invert concrete 5 for one span is completed, the invert concrete 5
The gantry 8 is advanced upward by the support interval (about 1 m). Hereinafter, this forward movement is defined as one cycle, and by repeating 5 to 10 cycles, the wheels 89 of the rear leg 83 of the gantry 8 run on the existing inverted concrete 5. On the other hand, the traveling body 88 of the front pillar 82 of the gantry 8
Is advanced by the drive motor 88a on the horizontal bottom surface of the upper bench 1 for the next cycle.

【0021】一方、ガントリ8の後方側に待機させてい
た運搬装置9をレール92に沿って前進させ、前側の傾動
コンベア枠96が下段ベンチ2の後端部上に達した時に該
傾動コンベア枠96を下方に回動させてその前端を下段ベ
ンチ2の後端部上に設置させた状態とする。そして、上
下段ベンチ1、2においてはその切羽地盤をそれぞれカ
ッターローダ6と掘削・積込機7によって同時に掘削
し、上段ベンチ1の掘削土砂をカッターローダ6のベル
トコンベア6cによって後方から下段ベンチ2上に落下、
堆積させる。
On the other hand, the transporting device 9 waiting on the rear side of the gantry 8 is advanced along the rail 92, and when the front tilting conveyor frame 96 reaches above the rear end of the lower bench 2, the tilting conveyor frame 96 is moved. 96 is rotated downward so that its front end is set on the rear end of the lower bench 2. Then, in the upper and lower benches 1 and 2, the cutting ground is simultaneously excavated by the cutter loader 6 and the excavator / loader 7, respectively, and the excavated earth and sand of the upper bench 1 is removed from the lower bench 2 by the belt conveyor 6c of the cutter loader 6 from behind. Falling on,
Deposit.

【0022】この上段ベンチ1側の掘削地盤を下段ベン
チ2側の掘削土砂と共に掘削・積込機7によって運搬装
置9の傾動コンベア枠96の前端に装着しているホッパー
18に投入し、該ホッパー18の開口下端に臨ませている運
搬装置9のベルトコンベア91の搬送始端に上載させて傾
動コンベア枠96内から水平コンベア枠95内を通じてガン
トリ8の後端側に搬送し、ガントリ8の後端に待機して
いるダンプトラック等の運搬車19に移載してトンネル後
方に搬出する。
The excavated ground on the upper bench 1 side together with the excavated earth and sand on the lower bench 2 side is mounted on the front end of the tilting conveyor frame 96 of the conveyor 9 by the excavator / loader 7.
18 and is loaded on the transfer start end of the belt conveyor 91 of the transfer device 9 facing the lower end of the opening of the hopper 18 and transferred from the tilting conveyor frame 96 to the rear end side of the gantry 8 through the horizontal conveyor frame 95. Then, it is transferred to a transport vehicle 19 such as a dump truck waiting at the rear end of the gantry 8, and is carried out behind the tunnel.

【0023】こうして、上下段ベンチ1、2の切羽地盤
が、支保工間隔に相当するトンネル長さ分だけ掘削、排
除されると、これらの上下段ベンチ1、2の掘削壁面に
一次覆工3を行う。この一次覆工のための分割された支
保工や金網はガントリ8の後方から該ガントリ8に配設
しているトロリー12、12によって上下段ベンチ1、2側
に搬送し、作業ケージ17上で作業員が掘削壁面に対する
支保工の建込みと支保工頂面部に対する既設支保工との
間に金網張設作業を行った後、ガントリ8の前端部上面
に配置している吹付機15によって支保工の厚みまでコン
クリートの吹付けを行うことによって一次覆工作業が完
了する。
In this way, when the face ground of the upper and lower benches 1 and 2 is excavated and removed by the tunnel length corresponding to the support interval, the primary lining 3 is formed on the excavation wall surface of the upper and lower benches 1 and 2. I do. The divided shoring and wire mesh for the primary lining are transported from the rear of the gantry 8 to the upper and lower benches 1 and 2 by the trolleys 12 and 12 arranged on the gantry 8, and are placed on the work cage 17. After the worker performs wire mesh work between the erection work on the excavation wall and the existing shoring work on the top face of the shoring work, the shoring work is carried out by the spraying machine 15 arranged on the upper surface of the front end of the gantry 8. The primary lining work is completed by spraying concrete up to the thickness.

【0024】なお、下段ベンチ2側においては、一次覆
工3を行う前に、運搬装置9の傾動コンベア枠96をチエ
ーンブロック99によって吊り上げて後方側の水平コンベ
ア枠95と同じく水平状態にしたのち、一次覆工作業の邪
魔にならないように運搬装置9全体をガントリ8の後方
側に移動、待機させておく。また、吹付機15によりコン
クリートの吹付け時には粉塵が発生するので、上段ベン
チ1側に対する吹付作業後、連続的に下段ベンチ2側に
対する吹付作業を行うことが望ましい。
On the lower bench 2 side, before the primary lining 3 is performed, the tilting conveyor frame 96 of the transporting device 9 is lifted by the chain block 99 to be in a horizontal state like the horizontal conveyor frame 95 on the rear side. Then, the entire transport device 9 is moved to the rear side of the gantry 8 and kept in standby so as not to hinder the primary lining work. Further, dust is generated when the concrete is sprayed by the spraying machine 15, and therefore, it is desirable to continuously perform the spraying operation on the lower bench 2 after the spraying operation on the upper bench 1 side.

【0025】こうして上下段ベンチ1、2に対する切羽
地盤の掘削から一次覆工までの1サイクルの作業工程が
終了すると、再び、上記同様にしてガントリ8の前進と
共に支保工間隔分の切羽地盤の掘削から一次覆工までの
1サイクル分の作業を行い、この作業工程を5〜10サイ
クル繰り返し行う。
When the work process of one cycle from excavation of the face ground to the upper and lower benches 1 and 2 to the primary lining is completed in this way, the excavation of the face ground for the support interval together with the advance of the gantry 8 in the same manner as described above. From 1 to the primary lining, and this process is repeated for 5 to 10 cycles.

【0026】一方、インバート部においては、上記5〜
10サイクルの作業工程と並行して最初のサイクル前に既
設のインバートコンクリート5の前端側に連続して1ス
パン分掘削しておいたインバート4に対するコンクリー
トの打設作業を行う。この作業は、前回打設したインバ
ートコンクリート5の硬化後に該インバートコンクリー
ト5から取り外した型枠20をガントリ8に配設している
トロリー12によって懸吊し、上記インバート4の上方ま
で搬送したのち、降下させて設置する。
On the other hand, in the inverting section,
In parallel with the ten-cycle work process, a concrete placing operation is performed on the invert 4 that has been continuously excavated for one span on the front end side of the existing invert concrete 5 before the first cycle. In this work, the formwork 20 removed from the invert concrete 5 after the previously cast invert concrete 5 has hardened is suspended by the trolley 12 arranged on the gantry 8 and transported to above the invert concrete 4. Set it down.

【0027】この型枠20は、図1、図4及び図5に示す
ように、トンネル長さ方向に長い両側水平桁21、21間を
長さ方向に適宜間隔毎に並設した複数本の梁22によって
一体に連結していると共に桁21、21の前端部下面に妻型
枠23を一体に垂下してあり、この妻型枠23から前方に突
出した桁21の前端部にジャッキによって伸縮自在の脚体
24を取付けていると共に桁21の後端部にもジャッキによ
って伸縮自在なローラ25付き脚体26を取付けている。さ
らに、並設した梁22の両側端に側壁型枠27、27を装着し
てあり、また、桁21、21間の適所に凹溝状の通路形成用
型枠28を妻型枠23から後方に向かって配設している。
As shown in FIGS. 1, 4 and 5, this formwork 20 has a plurality of horizontal girders 21, 21 which are long in the length direction of the tunnel and are juxtaposed at appropriate intervals in the length direction. At the same time, they are integrally connected by beams 22, and a wand form 23 is suspended from the underside of the front ends of the girders 21 and 21, and the front end of the girder 21 projecting forward from this wive form 23 is expanded and contracted by jacks. Free leg
At the same time, a leg 26 with a roller 25 is attached to the rear end of the spar 21 by a jack. Further, side wall forms 27, 27 are mounted on both side ends of the juxtaposed beams 22, and a groove-shaped passage forming form 28 is provided at an appropriate position between the girders 21, 21 from the end form 23 to the back. It is arranged toward.

【0028】このように構成した型枠20をインバート4
の所定に位置に合わせてその前側脚体24を下段ベンチ2
近傍部におけるインバート4の前端底面に設置する一
方、後側脚体26を既設インバートコンクリート5の前端
部上に設置し、両脚体24、26によって高さ調整をして妻
型枠23等を掘削面の所定部位に密接させる。しかるのち
ガントリ8の後方側からコンクリートミキサー車等によ
ってインバート4内にコンクリート5aを打設するもので
ある。
[0028] The mold 20 constructed as described above is mounted on an invert 4
Position the front leg 24 in the lower bench 2
The rear leg 26 is set on the front end of the existing invert concrete 5 while being installed on the bottom surface of the front end of the invert 4 in the vicinity and the height is adjusted by the two legs 24 and 26 to excavate the wife form 23 and the like. Close to a predetermined part of the surface. Thereafter, concrete 5a is poured into the invert 4 from behind the gantry 8 by a concrete mixer truck or the like.

【0029】この打設コンクリート5aの養生中、硬化す
るまでの間であって、上記上下段ベンチ1、2に対する
1スパン分の一次覆工3の形成後、下段ベンチ2の底部
を掘削・積込機7によってトンネル形状に湾曲状に堀下
げて次の1スパン分のインバートを掘削する。この掘削
土砂は掘削しながら上記運搬装置5によって後方に搬出
してもよいが、掘削量が比較的少ないので、一旦、下段
ベンチ2上に堆積させておき、該下段ベンチ2の切羽地
盤の掘削土砂と共に運搬装置5によって搬出することが
できる。なお、図5に示すように、一次覆工3と上記側
壁型枠27、27との間の厚み部分30には、トンネル後方に
おいて二次覆工が施工される。
During the curing of the poured concrete 5a, until the concrete is hardened, and after forming the primary lining 3 for one span with respect to the upper and lower benches 1, 2, the bottom of the lower bench 2 is excavated and piled. The excavator 7 is excavated in a curved shape in a tunnel shape by the insertion machine 7 to excavate an invert for the next one span. This excavated earth and sand may be carried backward by the above-mentioned transport device 5 while excavating, but since the excavation amount is relatively small, the excavated earth and sand is temporarily deposited on the lower bench 2, and excavation of the face ground of the lower bench 2 is performed. It can be carried out by the transport device 5 together with the earth and sand. As shown in FIG. 5, a secondary lining is applied to the thickness portion 30 between the primary lining 3 and the side wall forms 27, 27 at the rear of the tunnel.

【0030】上記のように、上下段ベンチ1、2に対す
る切羽地盤の掘削から一次覆工3の作業工程を数サイク
ル順次行って1スパン分のトンネルを掘進する一方、こ
の作業と並行して1スパン分の長さ部分に既設インバー
トコンクリート5に連続して下段ベンチ2側にインバー
トの掘削からコンクリート打設までの作業を行い、この
単位スパンのトンネル形成とインバートコンクリート5
の施工を順次繰り返し行ってトンネルを築造していくも
のである。コンクリートを打設したインバートにはコン
クリートの硬化後、ガントリ8の走行用レール10が継ぎ
足して敷設される。
As described above, the work process of the primary lining 3 from the excavation of the face ground to the upper and lower benches 1 and 2 is sequentially performed for several cycles to excavate the tunnel for one span, and at the same time, From the excavation of the invert to the concrete placement on the lower bench 2 side, the work is continued from the existing invert concrete 5 to the length of the span, and the tunnel formation of this unit span and the invert concrete 5
The construction of the tunnel is carried out by repeating the construction in sequence. After the concrete is hardened, the running rail 10 of the gantry 8 is laid on the invert into which the concrete is cast.

【0031】なお、以上の実施例において、ガントリ8
に1基の運搬装置9を吊支し、この運搬装置9の傾動コ
ンベア枠96の前端を下段ベンチ2の後端上に配置させて
該下段ベンチ2上に落とされた上段ベンチ1側の掘削土
砂と共に下段ベンチ2側の掘削土砂を運搬装置9によっ
て後方に搬出するようにしたが、図6に示すように、ガ
ントリ8に2基の運搬装置9a、9bを配設しておき、一方
の運搬装置9aによって上段ベンチ1側の掘削土砂を、他
方の運搬装置9bに下段ベンチ2側の掘削土砂を同時に搬
出するようにしてもよい。
In the above embodiment, the gantry 8
, And a front end of a tilting conveyor frame 96 of the conveyance device 9 is arranged on a rear end of the lower bench 2, and excavation of the upper bench 1 dropped on the lower bench 2 is performed. The excavated earth and sand on the lower bench 2 side together with the earth and sand is carried out rearward by the transporting device 9, but as shown in FIG. 6, two transporting devices 9a and 9b are provided in the gantry 8 and one of the transporting devices 9a and 9b is provided. The excavated earth and sand on the upper bench 1 side and the excavated earth and sand on the lower bench 2 side may be simultaneously conveyed to the other conveying device 9b by the transport device 9a.

【0032】図10は上下段ベンチ1、2に対する別な掘
削方法の作業工程図を示すもので、上記実施例において
は上下段ベンチ1、2の切羽地盤の掘削を同時に行った
が、この方法においては上段ベンチ1の切羽地盤を支保
工間隔分、掘削して運搬装置9により後方に搬出したの
ち、下段ベンチ2の切羽地盤を支保工間隔分、掘削して
運搬装置9により後方に搬出する点に特徴を有している
ものである。
FIG. 10 shows a working process diagram of another excavation method for the upper and lower benches 1 and 2. In the above embodiment, the excavation of the face ground of the upper and lower benches 1 and 2 was performed simultaneously. In, after excavating the face ground of the upper bench 1 for the support interval and transporting it rearward by the transport device 9, excavating the face ground of the lower bench 2 for the support interval and transporting it rearward by the transport device 9. It is characterized by points.

【0033】即ち、運搬装置9の傾動コンベア枠96をチ
エーンブロック99によって水平状態にまで持ち上げ、そ
の状態で運搬装置9をレール92に沿って前進させてコン
ベア枠96の前端部を上段ベンチ1の後端部に臨ませ、カ
ッタローダ6によって掘削した土砂をホッパー18に投入
してベルトコンベア91により後方に搬出する。次いで運
搬装置9を後退させて傾動コンベア枠96をチエーンブロ
ック99によって下方に傾斜させ、その下傾端を下段ベン
チ2の後端部上に位置させた状態にして掘削・積込機7
により掘削した下段ベンチ2の切羽地盤の土砂を運搬装
置9のベルトコンベア91によって後方に搬出するもので
ある。
That is, the tilting conveyor frame 96 of the conveying device 9 is lifted up to a horizontal state by the chain block 99, and in this state, the conveying device 9 is advanced along the rail 92, and the front end of the conveyor frame 96 is moved to the upper bench 1 The earth and sand excavated by the cutter loader 6 are put into the hopper 18 and conveyed backward by the belt conveyor 91 while facing the rear end. Next, the transporting device 9 is retracted, the tilting conveyor frame 96 is tilted downward by the chain block 99, and the excavating / loading machine 7 is set in a state where the lower tilting end is positioned on the rear end of the lower bench 2.
The earth and sand on the face ground of the lower bench 2 excavated by the above is carried out rearward by the belt conveyor 91 of the conveying device 9.

【0034】上下段ベンチ1、2の土砂の排除が終わる
と、夫々の掘削壁面に上記実施例と同様にして支保工の
搬送、建込、金網取付、コンクリート吹付けによる一次
覆工を行う。この工程を1サイクルとして上記実施例で
述べたように、1スパン分の一次覆工作業と、インバー
トコンクリート5の打設を行う。その他の作業工程等は
図9の作業工程と同様である。この方法によれば、下段
ベンチ2の切羽地盤の掘削量が多い場合に適し、上段ベ
ンチ1側の掘削土砂と共に排除すると作業時間が長時間
に亘るという問題点を回避し得るものである。また、上
段ベンチ1側の掘削時には、傾動コンベア枠96を水平状
態に持ち上げているので、下段ベンチ2での作業空間が
広くなり、インバート型枠20の移動、組立、コンクリー
トの打設作業が上段ベンチ1の掘削時に容易に且つ安全
に行うことができる。
When the removal of the earth and sand from the upper and lower benches 1 and 2 is completed, the respective excavated walls are subjected to the transport of the support, the building, the wire mesh installation, and the primary lining by spraying the concrete in the same manner as in the above embodiment. This process is defined as one cycle, and as described in the above embodiment, the primary lining work for one span and the casting of the inverted concrete 5 are performed. Other working steps and the like are the same as the working steps in FIG. According to this method, it is suitable when the amount of excavation of the face ground of the lower bench 2 is large, and if the excavated soil is removed together with the excavated earth and sand on the side of the upper bench 1, it is possible to avoid the problem that the working time is long. In addition, when the upper bench 1 is excavated, the tilting conveyor frame 96 is lifted in a horizontal state, so that the work space on the lower bench 2 is widened, and the movement, assembly, and concrete casting work of the invert form 20 are performed in the upper stage. When the bench 1 is excavated, it can be easily and safely performed.

【0035】図7、図8は運搬装置9の別な例を示すも
ので、上記実施例においてはベルトコンベア91によって
構成し、このコンベア枠95、96をガントリ8の長尺枠体
81に走行自在に吊支したが、この例においては、長尺枠
体81の上端下面両側部に該枠体81の全長に亘って固定し
てなる吊支用レール31、31に電動チエーンブロック32を
備えたトロリー33を走行自在に吊支し、これらのトロリ
ー33に底部が開閉自在なバケットよりなる運搬装置9'を
懸吊してなるものである。このように、ベルトコンベア
91からなる運搬装置9に代えて、バケットよりな運搬装
置9'を採用すると、ベルトコンベアでは搬出が困難な水
を含んだ掘削土砂の搬送が可能となるものである。その
他の構造及び作用は上記図1で示したガントリと同じで
ある。
FIGS. 7 and 8 show another example of the transport device 9. In the above-mentioned embodiment, the transport device 9 is constituted by a belt conveyor 91, and the conveyor frames 95 and 96 are elongated frames of the gantry 8.
In this example, the electric chain block is attached to suspension rails 31, 31 fixed on both sides of the upper end lower surface of the long frame 81 over the entire length of the frame 81. A trolley 33 provided with 32 is supported so as to be able to travel freely, and a transporting device 9 ′ composed of a bucket whose bottom can be freely opened and closed is hung on these trolleys 33. Thus, the belt conveyor
If a transporting device 9 ′ composed of buckets is used instead of the transporting device 9 consisting of 91, it is possible to transport excavated earth and sand containing water, which is difficult to carry out with a belt conveyor. Other structures and operations are the same as those of the gantry shown in FIG.

【0036】[0036]

【発明の効果】以上のように本発明のトンネルの掘削方
法によれば、トンネル切羽部を上段ベンチと下段ベンチ
とに区分して両ベンチの切羽地盤を掘削することにより
トンネルを掘進する方法であって、前端側脚柱を上記上
段ベンチ上に走行自在に支持させると共に後側脚柱を切
羽部後方のインバートコンクリート上に走行自在に支持
させてなるガントリーにベルトコンベア等の掘削土砂運
搬装置を吊支し、上記上段ベンチと下段ベンチの切羽地
盤を掘削した土砂を上記運搬装置によってトンネル後方
に搬送してガントリーの後端側に待機している土砂運搬
車に搬出すると共に土砂の搬出後、上下段ベンチの掘削
壁面に対する支保工の建込みから一次コンクリート覆工
を並行して行い、さらに、ガントリーの下方において上
記既設インバートコンクリートに接して新たなインバー
トの掘削とインバートコンクリートの打設を行うことを
特徴とするものであるから、上段ベンチ上から既設のイ
ンバートコンクリート上に亘って架設状態に配設してい
るガントリに配設した運搬装置によって上下段ベンチの
切羽地盤の掘削土砂を夫々連続的に円滑にトンネル後方
側に搬出することができると共に、上下段ベンチの掘削
壁面に対する支保工の建込みからクンクリートの吹付け
までの一次覆工を並行して行うので、トンネルの掘削作
業が能率よく行え、工期を著しく短縮し得るものであ
る。
As described above, according to the tunnel excavation method of the present invention, the tunnel face is divided into an upper bench and a lower bench, and the tunnel is excavated by excavating the face of both benches. A gantry having a front-end-side pedestal movably supported on the upper bench and a rear-side pedestal supported on invert concrete behind the face section is provided with an excavated sediment transport device such as a belt conveyor. Suspension, transport the sediment excavated the face ground of the upper bench and the lower bench to the rear of the tunnel by the transport device and carry it out to the sediment transport vehicle waiting on the rear end side of the gantry, and after carrying out the sediment, The primary concrete lining was carried out in parallel with the erection of the excavation walls of the upper and lower benches, and the existing invert was installed below the gantry. Since it is characterized by excavating new inverts and placing invert concrete in contact with concrete, it is installed in a gantry that is erected from the upper bench to the existing invert concrete. The excavated soil on the face ground of the upper and lower benches can be continuously and smoothly carried out to the rear side of the tunnel by the transport equipment installed, and the kuncrete spraying from the erection work on the excavation wall of the upper and lower benches Since the primary lining is performed in parallel, the excavation work of the tunnel can be performed efficiently, and the construction period can be significantly reduced.

【0037】さらに、ガントリはその前端側脚柱を上記
上段ベンチ上に走行自在に支持させると共に後側脚柱を
切羽部後方のインバートコンクリート上に走行自在に支
持させているので、上下段ベンチの掘削壁面に対する一
定長の一次覆工工程毎にその長さに応じて前進させなが
ら能率良く掘削土砂の搬出が行なえると共に、ガントリ
の下方空間部において、インバートの掘削作業やインバ
ートに対する型枠の組立、コンクリートの打設作業を行
うものであるから、掘削土砂の搬出作業に支障を生じさ
せることなく、上下段ベンチ側に対する一次覆工作業と
並行してインバートコンクリートの造成が可能となり、
トンネル掘削の作業能率を一層向上させることができる
ものである。
Further, the gantry has its front end pedestal movably supported on the upper bench and its rear pedestal movably supported on the invert concrete behind the cutting face. Efficient removal of excavated earth and sand can be carried out efficiently while advancing according to the length of the primary lining process for a fixed length on the excavated wall, and excavation work of the invert and assembly of a formwork for the invert in the space below the gantry Because it is the work of placing concrete, it is possible to create inverted concrete in parallel with the primary lining work on the upper and lower benches, without hindering the work of carrying out excavated earth and sand,
The operation efficiency of tunnel excavation can be further improved.

【0038】また、ガントリに支保工等の運搬用トロリ
ーを走行自在に配設しておくことによって、トンネル後
方側から該ガントリを通じて上記上下段ベンチ側に一次
覆工に必要な部材を容易に且つ効率よく搬送することが
でき、その上、インバートに対するコンクリート打設用
型枠の吊支や組立てにも使用することができて、作業性
が向上するものである。
Further, by disposing a transport trolley such as a supporter on the gantry so as to be freely movable, members necessary for the primary lining can be easily and easily provided on the upper and lower benches from the rear side of the tunnel through the gantry. It can be transported efficiently, and can also be used for suspending and assembling a concrete casting formwork with respect to the invert, thereby improving workability.

【図面の簡単な説明】[Brief description of the drawings]

【図1】トンネル掘削状態を示す簡略縦断側面図、FIG. 1 is a simplified longitudinal side view showing a tunnel excavation state;

【図2】その前端側の拡大縦断正面図、FIG. 2 is an enlarged vertical sectional front view of the front end side;

【図3】その中間部分の拡大縦断正面図、FIG. 3 is an enlarged vertical sectional front view of an intermediate portion thereof;

【図4】インバートに対する型枠設置状態を示す縦断側
面図、
FIG. 4 is a longitudinal sectional side view showing a form setting state with respect to an invert;

【図5】その一部切欠縦断正面図、FIG. 5 is a partially cut-out longitudinal front view,

【図6】二基の運搬装置を装備したガントリの簡略側面
図、
FIG. 6 is a simplified side view of a gantry equipped with two transport devices,

【図7】運搬装置としてバケットを用いてのトンネル掘
削状態を示す簡略縦断側面図、
FIG. 7 is a simplified longitudinal side view showing a tunnel excavation state using a bucket as a transport device,

【図8】その拡大縦断正面図、FIG. 8 is an enlarged vertical sectional front view thereof,

【図9】トンネル掘削の作業工程を示すブロック図、FIG. 9 is a block diagram showing a work process of tunnel excavation;

【図10】トンネル掘削の別な作業工程を示すブロック
図。
FIG. 10 is a block diagram showing another operation process of tunnel excavation.

【符号の説明】[Explanation of symbols]

T トンネル 1 上段ベンチ 2 下段ベンチ 3 一次覆工 4 インバート 5 インバートコンクリート 6 カッターローダ 7 掘削・積込機 8 ガントリ 9 運搬装置 82 前側脚柱 83 後側脚柱 T Tunnel 1 Upper Bench 2 Lower Bench 3 Primary Lining 4 Invert 5 Invert Concrete 6 Cutter Loader 7 Excavator / Loader 8 Gantry 9 Transporter 82 Front Leg 83 Rear Leg

───────────────────────────────────────────────────── フロントページの続き (72)発明者 桔梗 栄吉 大阪市阿倍野区松崎町2丁目2番2号 株式会社奥村組内 (56)参考文献 特開 昭56−73795(JP,A) 特開 昭49−15225(JP,A) (58)調査した分野(Int.Cl.7,DB名) E21D 9/12 E21D 9/10 E21D 9/00 ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Eikichi Kikyo 2-2-2 Matsuzakicho, Abeno-ku, Osaka-shi Okumura Gumi Co., Ltd. (56) References JP-A-56-73795 (JP, A) JP-A-49 -15225 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) E21D 9/12 E21D 9/10 E21D 9/00

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 トンネル切羽部を上段ベンチと下段ベン
チとに区分して両ベンチの切羽地盤を掘削することによ
りトンネルを掘進する方法であって、前端側脚柱を上記
上段ベンチ上に走行自在に支持させると共に後側脚柱を
切羽部後方のインバートコンクリート上に走行自在に支
持させてなるガントリーにベルトコンベア等の掘削土砂
運搬装置を吊支し、上記上段ベンチと下段ベンチの切羽
地盤を掘削した土砂を上記運搬装置によってトンネル後
方に搬送してガントリーの後端側に待機している土砂運
搬車に搬出すると共に土砂の搬出後、上下段ベンチの掘
削壁面に対する支保工の建込みから一次コンクリート覆
工を並行して行い、さらに、ガントリーの下方において
上記既設インバートコンクリートに接して新たなインバ
ートの掘削とインバートコンクリートの打設を行うこと
を特徴とするトンネルの掘削方法。
1. A method for digging a tunnel by dividing a tunnel face portion into an upper bench and a lower bench, and excavating the face ground of both benches, wherein a front pillar on a front end side can run on the upper bench. The excavated earth and sand transporting device such as a belt conveyor is hung on a gantry that supports the rear leg on the invert concrete behind the face part so that it can run freely, and excavates the face ground of the upper bench and the lower bench. The conveyed sediment is transported to the rear of the tunnel by the above-mentioned transport device and is carried out to the sediment transport vehicle waiting at the rear end of the gantry. The lining was performed in parallel, and a new invert was excavated and inverted in contact with the existing invert concrete below the gantry. A method for excavating a tunnel, comprising casting concrete.
【請求項2】 上段ベンチの切羽地盤の掘削と下段ベン
チの切羽地盤の掘削とを同時に行い、上段ベンチの掘削
土砂を下段ベンチ上に搬出、堆積させて下段ベンチの掘
削地盤と共に上記ガントリに吊支した運搬装置によりト
ンネル後方に搬送することを特徴とする請求項1記載の
トンネルの掘削方法。
2. The excavation of the face ground of the upper bench and the excavation of the face ground of the lower bench are carried out at the same time, and the excavated earth and sand of the upper bench is carried out to the lower bench, deposited and suspended on the gantry together with the excavated ground of the lower bench. 2. The tunnel excavation method according to claim 1, wherein the tunnel is transported to the rear of the tunnel by a supported transport device.
【請求項3】 上段ベンチの切羽地盤の掘削土砂を上記
運搬装置によってトンネル後方に搬送したのち、下段ベ
ンチの切羽地盤の掘削土砂を上記運搬装置によりトンネ
ル後方に搬出することを特徴とする請求項1記載のトン
ネルの掘削方法。
3. The excavated soil of the face ground of the upper bench is transported to the rear of the tunnel by the transport device, and the excavated soil of the face ground of the lower bench is transported to the rear of the tunnel by the transport device. The tunnel excavation method according to claim 1.
【請求項4】 上記ガントリーに支保工等の運搬用トロ
リーを走行自在に配設していることを特徴とする請求項
1記載のトンネルの掘削方法。
4. The tunnel excavation method according to claim 1, wherein a transport trolley such as a shoring is movably disposed on the gantry.
JP06334154A 1994-12-15 1994-12-15 Tunnel excavation method Expired - Lifetime JP3103285B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP06334154A JP3103285B2 (en) 1994-12-15 1994-12-15 Tunnel excavation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP06334154A JP3103285B2 (en) 1994-12-15 1994-12-15 Tunnel excavation method

Publications (2)

Publication Number Publication Date
JPH08165881A JPH08165881A (en) 1996-06-25
JP3103285B2 true JP3103285B2 (en) 2000-10-30

Family

ID=18274145

Family Applications (1)

Application Number Title Priority Date Filing Date
JP06334154A Expired - Lifetime JP3103285B2 (en) 1994-12-15 1994-12-15 Tunnel excavation method

Country Status (1)

Country Link
JP (1) JP3103285B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015154975A (en) * 2010-06-18 2015-08-27 李輝LI, Hui Penis sizing-up training system

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58150576A (en) * 1982-03-03 1983-09-07 Sumitomo Chem Co Ltd Novel 1,2,4-oxadiazole derivative
JP2899880B1 (en) * 1998-04-09 1999-06-02 大成建設株式会社 Tunnel construction equipment
CN107989620B (en) * 2017-12-28 2020-01-31 中铁五局集团第四工程有限责任公司 Construction method of three-hole small-spacing tunnel
CN108374663B (en) * 2018-02-01 2020-12-01 中铁十二局集团有限公司 Twice-molding construction method for sandy gravel geological tunnel
CN113530553B (en) * 2021-06-25 2022-07-05 中铁十一局集团汉江重工有限公司 Three-step construction process based on tunnel excavation and support integrated trolley
CN113931660B (en) * 2021-10-25 2024-04-09 四川省交通建设集团股份有限公司 Reserved single-side-wall soil column method suitable for pilot tunnel-free method of multi-arch tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015154975A (en) * 2010-06-18 2015-08-27 李輝LI, Hui Penis sizing-up training system

Also Published As

Publication number Publication date
JPH08165881A (en) 1996-06-25

Similar Documents

Publication Publication Date Title
US5257471A (en) Excavator for forming underground continuous wall
JP3103284B2 (en) Tunnel excavation shearing gantry
JP3103285B2 (en) Tunnel excavation method
JP6837394B2 (en) Invert pier and tunnel invert construction method
JP3356048B2 (en) Construction method of elevated structure using building girder
JP2003269074A (en) Extension method of existing tunnel
JP3151116B2 (en) Tunnel excavation method and gantry used for this method
JP3831900B2 (en) Tunnel construction method
JP2899880B1 (en) Tunnel construction equipment
JP3357654B2 (en) Gantry used for tunnel excavation method
JP4080226B2 (en) Mobile jetty
JP3194190B2 (en) Open shield machine
JP2018155020A (en) Invert pier and tunnel invert construction method
JP4142397B2 (en) Tunnel invert construction method using mobile jetty and mobile jetty
JP2954840B2 (en) Conveyor trolley for waste removal
JP4118420B2 (en) Tunnel excavation and lining method and its equipment
JPS59185236A (en) Method and apparatus for continuous and vertical excavation and soil-moving work
JP7503355B2 (en) Tunnel construction method
JP3249390B2 (en) Tunnel opening method and dismantling device used in the method
JP6650350B2 (en) Debris unloading device and construction method using the same
JPS5834619B2 (en) Excavation method
JP2652042B2 (en) Underground vertical excavation equipment
JP2022125772A (en) Tunnel construction method
JP2022125774A (en) Tunnel construction method
JPH0726570A (en) Pipeline laying method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090825

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120825

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120825

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150825

Year of fee payment: 15

EXPY Cancellation because of completion of term