JP2018155020A - Invert pier and tunnel invert construction method - Google Patents

Invert pier and tunnel invert construction method Download PDF

Info

Publication number
JP2018155020A
JP2018155020A JP2017052543A JP2017052543A JP2018155020A JP 2018155020 A JP2018155020 A JP 2018155020A JP 2017052543 A JP2017052543 A JP 2017052543A JP 2017052543 A JP2017052543 A JP 2017052543A JP 2018155020 A JP2018155020 A JP 2018155020A
Authority
JP
Japan
Prior art keywords
invert
work platform
ground
construction
ramp
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017052543A
Other languages
Japanese (ja)
Other versions
JP6663378B2 (en
Inventor
小林 雅彦
Masahiko Kobayashi
雅彦 小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toko Inc
Original Assignee
Toko Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toko Inc filed Critical Toko Inc
Priority to JP2017052543A priority Critical patent/JP6663378B2/en
Publication of JP2018155020A publication Critical patent/JP2018155020A/en
Application granted granted Critical
Publication of JP6663378B2 publication Critical patent/JP6663378B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide an invert pier and a tunnel invert construction method with high construction efficiency.SOLUTION: An invert pier 1 includes a work platform 10 having a casting space S1 for casting invert concrete downward, a front oblique path 20 stretched between the front end of the work platform 10 and the ground, a rear oblique path 30 stretched between the rear end of the work platform 10 and the ground, and a plurality of support legs 40 attached to the lower portion of the work platform 10 to support the work platform 10 away from the ground. The width of the front oblique path 20 is less than half the width of the work platform 10 and the front oblique path 20 can be connected to an arbitrary position in the width direction of the work platform 10.SELECTED DRAWING: Figure 1

Description

本発明は、インバート桟橋およびトンネルインバート施工方法に係り、特に、インバート掘削とインバートコンクリート打設を併行可能な、インバート桟橋およびトンネルインバート施工方法に係る。   The present invention relates to an invert pier and a tunnel invert construction method, and more particularly to an invert pier and a tunnel invert construction method capable of performing invert excavation and invert concrete placement in parallel.

トンネル工事におけるインバート(トンネル床部)の施工は、切羽で発生するズリの搬出や、切羽の支保工、吹付工に係る工事車両がインバート工の施工区間を通行できないため、全体工期に与える影響が大きい。
このため、インバート工の施工区間を跨いで工事車両を通行させるため、架台と昇降用の斜路を備え、トンネルの幅方向へ移動可能なインバート桟橋が採用されている。
この桟橋を坑内の第一側に寄せた位置で、第二側がわの地盤を桟橋の全長に渡って掘削し、続いて桟橋を坑内の第二側へ移動し、第一側がわの地盤を桟橋の全長に渡って掘削し、最後に桟橋を坑内中央に移動し、桟橋上から掘削した地盤上にインバートコンクリートを打設する。打設したインバートコンクリートが硬化したら、インバート桟橋を1スパン分前進させる。
以上の作業を1サイクルとしてこれを繰り返すことで施工を進捗させる。
Construction of invert (tunnel floor) in tunnel construction has an effect on the entire construction period because construction vehicles related to unloading at the face, support work for the face, and spray work cannot pass through the construction section of the invert work. large.
For this reason, in order to pass the construction vehicle across the construction section of the invert work, an invert pier that is equipped with a gantry and a ramp for raising and lowering and is movable in the width direction of the tunnel is adopted.
At the position where this pier is close to the first side of the mine, the second side excavates the ground of the pier over the entire length of the pier, then moves the pier to the second side of the mine, the first side The pier is excavated over the entire length of the pier, and finally the pier is moved to the center of the mine and inverted concrete is placed on the ground excavated from the pier. When the cast invert concrete is hardened, the invert pier is advanced by one span.
Construction is progressed by repeating this as one cycle.

特開平6−108795号公報JP-A-6-108795 特開2003−322000号公報JP 2003-322000 A

しかし、従来技術には次のような欠点がある。
<1>全スパンのインバート掘削が完了するまで、インバートコンクリートの打設に着工できないため、手待ちが多く施工効率が低い。
<2>桟橋全体を坑内の幅方向に移動させる構造上、架台の幅が狭い。よって、コンクリートの打設時、コンクリートミキサー車の側方を工事車両が通過できないので、切羽の施工を中断させる。
<3>切羽の施工速度に対してインバートの施工速度が低いため、全体工期に遅延を生じさせるおそれがある。
However, the prior art has the following drawbacks.
<1> Until invert excavation for all spans is completed, construction of invert concrete cannot be started, so there are many waiting times and construction efficiency is low.
<2> The width of the gantry is narrow due to the structure that moves the entire pier in the width direction of the mine. Therefore, when placing concrete, the construction vehicle cannot pass through the side of the concrete mixer truck, so the construction of the face is interrupted.
<3> Since the construction speed of invert is lower than the construction speed of the working face, there is a risk of delaying the entire construction period.

本発明の目的は、これら従来技術の課題を解決可能なインバート桟橋およびトンネルインバート施工方法を提供することにある。   An object of the present invention is to provide an invert pier and a tunnel invert construction method that can solve the problems of the prior art.

上記のような課題を解決するための本発明のインバート桟橋は、下方にインバートコンクリート打設作業用の打設空間を有する作業架台と、作業架台の前端と地盤との間に掛け渡す前部斜路と、作業架台の後端と地盤との間に掛け渡す後部斜路と、作業架台の下部に付設し、作業架台を地盤から離間支持する複数の支持脚と、を備え、前部斜路の幅は、作業架台の幅の半分以下であり、前部斜路が、作業架台の幅方向における任意の位置に接続可能であることを特徴とする。   An invert pier of the present invention for solving the above-described problems includes a work platform having a placement space for invert concrete placement work below, and a front ramp that spans between the front end of the work platform and the ground. And a rear ramp extending between the rear end of the work platform and the ground, and a plurality of support legs attached to the lower portion of the work platform and supporting the work platform apart from the ground, the width of the front ramp is It is less than half the width of the work platform, and the front ramp is connectable to an arbitrary position in the width direction of the work platform.

本発明のインバート桟橋は、前部斜路が、作業架台の幅方向に沿って摺動自在であってもよい。   In the invert pier of the present invention, the front ramp may be slidable along the width direction of the work platform.

本発明のインバート桟橋は、複数の支持脚が、作業架台の前方に付設する前部支持脚と、作業架台の後方に付設する後部支持脚と、を有し、打設空間が、前部支持脚と後部支持脚との間に形成されてもよい。   The invert pier of the present invention has a front support leg with a plurality of support legs attached to the front of the work platform and a rear support leg attached to the rear of the work platform, and the placement space has a front support. It may be formed between the leg and the rear support leg.

本発明のトンネルインバート施工方法は、インバート桟橋の、前部斜路の先端を施工前の地盤上に、後部斜路の先端を施工後の地盤上に、それぞれ掛け渡した状態において、1)作業架台より切羽側の地盤を先行掘削する工程と、2)作業架台の上部から、作業架台の下方の地盤にインバートコンクリートを打設する工程と、3)インバート桟橋を切羽側へ前進させ、作業架台を、1)工程実施後の掘削区間の上方に位置決めする工程と、を備え、1)工程と、2)工程とを併行した後に、3)工程を行って、これを1施工サイクルとし、1)工程は、1a)前部斜路がトンネル横断方向の第一側に位置した状態で、前部斜路の第二側がわの地盤を掘削する工程と、1b)前部斜路がトンネル横断方向の第二側に位置した状態で、前部斜路の第一側がわの地盤を掘削する工程と、を備え、前部斜路をトンネル横断方向の左右に移動させることで、1a)工程と1b)工程とを、適宜入れ替えて行うことを特徴とする。   The tunnel invert construction method of the present invention is such that in the state where the tip of the front ramp on the Invert pier is placed on the ground before construction and the tip of the rear ramp on the ground after construction, 1) From the work platform A process of excavating the ground on the face side in advance, 2) a process of placing invert concrete on the ground below the work base from the upper part of the work base, and 3) advancing the invert pier to the face side, 1) A step of positioning above the excavation section after the execution of the process is provided, and after the 1) process and the 2) process are performed in parallel, the 3) process is performed and this is defined as one construction cycle. 1a) a step of excavating the ground on the second side of the front ramp with the front ramp located on the first side in the tunnel crossing direction, and 1b) the second ramp of the front ramp in the direction crossing the tunnel. Of the front ramp with the And a step one side drilling a ground of I, by moving the front ramp to left and right tunnel transverse, 1a) and a step and 1b) step, and carrying out interchanged as appropriate.

本発明のインバート桟橋は次の効果の少なくともひとつを備える。
<1>前部斜路が作業架台に対して左右へ移動可能であるため、作業架台の前方における先行掘削が可能である。このため、インバート掘削と、インバートコンクリートの打設を同時併行することができるので、施工効率が著しく高い。
<2>作業架台の幅が広いため、打設作業中のコンクリートミキサー車の側方を工事車両が通過することができる。このため、切羽の作業を中断させることなく、連続してトンネルインバートの施工を行うことができる。
The Invert Pier of the present invention has at least one of the following effects.
<1> Since the front ramp can be moved to the left and right with respect to the work platform, a preceding excavation in front of the work platform is possible. For this reason, since invert excavation and invert concrete placement can be performed simultaneously, construction efficiency is remarkably high.
<2> Since the work platform is wide, the construction vehicle can pass through the side of the concrete mixer truck during the placing work. For this reason, it is possible to continuously perform tunnel inversion without interrupting the work of the face.

本発明のトンネルインバート施工方法は次の効果の少なくともひとつを備える。
<1>施工区間を前後に二分割し、インバート掘削とインバートコンクリートの打設を併行することで、施工時間を圧縮し施工効率を著しく高めることができる。
<2>インバート工の施工効率が上がることによって、切羽−インバート間の悪路区間が短くなる。このため、切羽の施工に係る工事車両の走行性が高まり、工事全体の施工性や安全性が向上する。
The tunnel invert construction method of the present invention has at least one of the following effects.
<1> The construction section is divided into two parts in the front and the rear, and invert excavation and invert concrete placement are performed in parallel, so that the construction time can be reduced and the construction efficiency can be remarkably increased.
<2> The rough road section between the face and the invert is shortened by increasing the construction efficiency of the invert work. For this reason, the runnability of the construction vehicle related to the construction of the face increases, and the workability and safety of the entire construction are improved.

本発明に係るインバート桟橋およびトンネルインバート施工方法の説明図。Explanatory drawing of the invert pier and tunnel invert construction method concerning this invention. 本発明に係るトンネルインバート施工方法の説明図。Explanatory drawing of the tunnel invert construction method which concerns on this invention. 本発明に係るトンネルインバート施工方法の説明図。Explanatory drawing of the tunnel invert construction method which concerns on this invention.

以下、図面を参照しながら本発明のインバート桟橋およびトンネルインバート施工方法について詳細に説明する。
本明細書等において、「前」「後」はそれぞれトンネルの延長方向における切羽側と坑口側を、「上」「下」「左」「右」はインバート桟橋を切羽側に向けて設置した状態における各方位を、意味する。
Hereinafter, the invert pier and tunnel invert construction method of the present invention will be described in detail with reference to the drawings.
In this specification, etc., “front” and “rear” are the face side and pit side in the tunnel extension direction, respectively, and “up”, “down”, “left”, and “right” are the states where the invert pier faces the face side. Each direction in is meant.

[インバート桟橋]
<1>全体の構成(図1)。
本発明のインバート桟橋1は、トンネル工事においてインバートの施工に用いる装置である。
インバート桟橋1は、作業架台10と、作業架台10の前後から地盤に掛け渡される前部斜路20及び後部斜路30と、作業架台10の下部に付設され、作業架台10を地盤より高い位置に支持する複数の支持脚40と、を少なくとも備える。前部斜路20は、作業架台10に対して幅方向に移動可能に接続する。
インバート桟橋1の全長、すなわち前部斜路20の前端から後部斜路30の後端に至る水平投影長さを、インバート工の施工区間の1スパンより長く構成する。
作業架台10の下部と地盤と複数の支持脚40との間に、インバートコンクリート打設作業用の打設空間S1が形成される。
前部斜路20の側辺とトンネルの側壁の間に、インバート掘削作業用の掘削空間S2が形成される。掘削空間S2は、前部斜路20の左右への切り替えに従って左右入れ替わる。
インバート桟橋1を、インバート工の施工区間を跨いで設置することで、上部に工事車両の走行経路を確保しつつ、下部でインバート工を施工することができる。
[Invert Pier]
<1> Overall configuration (FIG. 1).
The invert pier 1 of the present invention is a device used for invert construction in tunnel construction.
The invert pier 1 is attached to the work platform 10, the front ramps 20 and the rear ramps 30 that extend from the front and the back of the work platform 10 to the ground, and the lower part of the work platform 10, and supports the work platform 10 at a position higher than the ground. And a plurality of support legs 40. The front ramp 20 is connected to the work platform 10 so as to be movable in the width direction.
The entire length of the invert pier 1, that is, the horizontal projection length from the front end of the front ramp 20 to the rear end of the rear ramp 30 is configured to be longer than one span of the construction section of the invert work.
A placement space S1 for invert concrete placement work is formed between the lower part of the work platform 10, the ground, and the plurality of support legs 40.
An excavation space S2 for invert excavation work is formed between the side of the front ramp 20 and the side wall of the tunnel. The excavation space S2 is switched left and right in accordance with the left and right switching of the front ramp 20.
By installing the invert pier 1 across the construction section of the invert work, it is possible to construct the invert work at the lower part while securing the travel route of the construction vehicle at the upper part.

<2>作業架台。
作業架台10は、インバートコンクリート打設用の作業台の機能と、工事車両の通行路の機能を兼備する部材である。
本例では、作業架台10として、鋼桁を組んでなる枠体に面材を敷設してなる矩形の構造を採用する。作業架台10の上面両側には、落下防止用の側壁を設ける。
作業架台10の幅は、トンネルの断面幅より小さく、かつ工事車両の通行に十分な幅とする。
工事車両の通行に十分な幅とは、インバートコンクリートの打設時、コンクリートミキサー車が作業架台10の上部から地盤へ生コンクリートを投入するが、この際切羽のズリを運搬するダンプトラックなどがコンクリートミキサー車の側方を通過可能な程度の幅である。すなわち、工事車両における二車線以上を確保するのが望ましい。
これによって、切羽の施工を止めずにインバート工を施工することができる。
本例では、作業架台10の後部に、後部斜路30の後端を上方に吊り上げるための吊りアーム11を設ける。
このほか、作業架台10の床板に、資材を下部に吊り下ろしたり、生コンクリートを投入するための資材投入口を設けてもよい。資材投入口は油圧機構で開閉可能に構成することができる。
<2> Work platform.
The work platform 10 is a member that has both a function of a work table for placing invert concrete and a function of a traffic path of the construction vehicle.
In this example, a rectangular structure in which a face material is laid on a frame made of steel girders is employed as the work platform 10. Side walls for fall prevention are provided on both sides of the upper surface of the work platform 10.
The width of the work platform 10 is set to be smaller than the cross-sectional width of the tunnel and sufficient for passage of the construction vehicle.
The width sufficient for the passage of construction vehicles means that when invert concrete is placed, a concrete mixer truck throws ready-mixed concrete from the top of the work platform 10 into the ground. The width is such that it can pass through the side of the mixer truck. In other words, it is desirable to secure at least two lanes in the construction vehicle.
Thereby, the invert work can be performed without stopping the work of the face.
In this example, a suspension arm 11 for lifting the rear end of the rear ramp 30 upward is provided at the rear of the work platform 10.
In addition to this, the floor plate of the work platform 10 may be provided with a material input port for suspending the material in the lower part or for supplying ready-mixed concrete. The material input port can be configured to be opened and closed by a hydraulic mechanism.

<3>前部斜路。
前部斜路20は、作業架台10の前端と地盤の間に掛け渡す、工事車両の昇降路である。
本例では、前部斜路20として鋼製の面材を採用する。
前部斜路20は、作業架台10に対して、作業架台10の幅方向における任意の位置に接続可能に接続する。
本例では、前部斜路20は、前方の支持脚40から反力を得て、油圧ジャッキにて先端を地盤から持ち上げ可能に構成する(不図示)。これによって、インバート桟橋1の移動時、前部斜路20の先端が地盤に接触するのを避ける。
<3> Front ramp.
The front ramp 20 is a hoistway for a construction vehicle that spans between the front end of the work platform 10 and the ground.
In this example, a steel face material is adopted as the front ramp 20.
The front ramp 20 is connected to the work platform 10 so as to be connectable to an arbitrary position in the width direction of the work platform 10.
In this example, the front ramp 20 is configured such that a reaction force is obtained from the front support leg 40 and the tip can be lifted from the ground by a hydraulic jack (not shown). This avoids the tip of the front ramp 20 coming into contact with the ground when the invert pier 1 is moved.

<3.1>前部斜路の移動機能。
前部斜路20は、作業架台10に対して、作業架台10の幅方向における任意の位置に接続可能に接続される。
本例では、前部斜路20を、作業架台10の前部に設けたレールと、前部斜路20に設けた滑車との組み合わせによって、前部斜路20を幅方向にスライド自在なスライド機構とする。
この場合、前部斜路20の先端に、前部斜路20のスライド移動を補助するスライド台車を付設してもよい。
ただし、前部斜路20の構造はこれに限られず、例えば作業架台10に対して着脱自在に構成し、工程に応じて前部斜路20を作業架台10から取り外して、左右に付け替えてもよい。要は、工程に応じて前部斜路20の作業架台10に対する位置を左右入れ替えできればよい。
<3.1> Front ramp moving function.
The front ramp 20 is connected to the work platform 10 so as to be connectable to an arbitrary position in the width direction of the work platform 10.
In this example, the front ramp 20 is a slide mechanism that is slidable in the width direction by a combination of a rail provided at the front of the work platform 10 and a pulley provided at the front ramp 20. .
In this case, a slide carriage for assisting the sliding movement of the front ramp 20 may be attached to the tip of the front ramp 20.
However, the structure of the front ramp 20 is not limited to this. For example, the front ramp 20 may be configured to be detachable from the work platform 10, and the front ramp 20 may be detached from the work platform 10 and changed to the left and right according to the process. In short, it is only necessary that the position of the front ramp 20 with respect to the work platform 10 can be changed according to the process.

<3.2>前部斜路の幅。
前部斜路20の幅は、作業架台10の幅の半分以下とする。望ましくは作業架台10の幅の半分とする。
これによって、前部斜路20を左右両端へスライドした際、平面視において前部斜路20が重複する面積がなくなるため、掘削区間の全幅が掘削可能となる。
<3.2> The width of the front ramp.
The width of the front ramp 20 is not more than half the width of the work platform 10. Preferably, it is half the width of the work platform 10.
As a result, when the front ramp 20 is slid to the left and right ends, there is no area where the front ramp 20 overlaps in plan view, so that the entire width of the excavation section can be excavated.

<4>後部斜路。
後部斜路30は、作業架台10の後端と地盤の間に掛け渡す、工事車両の昇降路である。
本例では、後部斜路30として鋼製の面材を採用する。後部斜路30の幅は、作業架台10の幅に対応させるのが望ましい。
本例では、後部斜路30の前端を作業架台10の後端にヒンジ接合し、後部斜路30の後端を作業架台10の吊りアーム11によって上方へ吊り上げ可能な構造とする。
後部斜路30を吊りアーム11で上方に吊り上げることで、インバート桟橋1の移動時、後部斜路30の後端が地盤に接触するのを避ける。
<4> Rear ramp.
The rear ramp 30 is a hoistway for a construction vehicle that spans between the rear end of the work platform 10 and the ground.
In this example, a steel face material is adopted as the rear ramp 30. It is desirable that the width of the rear ramp 30 corresponds to the width of the work platform 10.
In this example, the front end of the rear ramp 30 is hinged to the rear end of the work platform 10, and the rear end of the rear ramp 30 can be lifted upward by the suspension arm 11 of the work platform 10.
The rear ramp 30 is lifted upward by the suspension arm 11 to avoid the rear end of the rear ramp 30 coming into contact with the ground when the invert pier 1 is moved.

<5>支持脚。
支持脚40は、作業架台10を下部から支持し、地盤から離間させる部材である。
本例では、作業架台10の下部四隅に各1基ずつ、計4基の支持脚40を設ける。
各支持脚40の下端部には支持台車41を設ける。
各支持脚40には油圧ジャッキなどの昇降装置42を設け、昇降自在とする。
なお、支持台車41と昇降装置42は、支持脚40の必須の構成要素ではなく、公知の各種の支持構造を採用することができる。要は作業架台10を地盤から離間して支持し、インバート桟橋1を切羽方向に前進可能であればよい。
<5> Support leg.
The support leg 40 is a member that supports the work platform 10 from below and separates it from the ground.
In this example, a total of four support legs 40 are provided, one at each of the lower four corners of the work platform 10.
A support carriage 41 is provided at the lower end of each support leg 40.
Each support leg 40 is provided with a lifting device 42 such as a hydraulic jack so that it can be lifted and lowered.
Note that the support carriage 41 and the lifting device 42 are not essential components of the support leg 40, and various known support structures can be employed. In short, it is sufficient that the work platform 10 is supported away from the ground and the invert pier 1 can be advanced in the face direction.

<6>打設空間。
打設空間S1は、インバートコンクリートの打設工程において、型枠の設置、配筋、生コンクリートの投入、養生等の各工程を行うための空間である。
本例では、打設空間S1は、作業架台10の下方であって、4基の支持脚40の間に構成される。これによって、前後に広いスパンの打設空間S1を確保できるため、コンクリート打設に係る各工程の作業性が高まる。
<6> Placed space.
The placement space S <b> 1 is a space for performing various processes such as installation of formwork, bar arrangement, loading of ready-mixed concrete, curing, and the like in the invert concrete placing process.
In this example, the placement space S <b> 1 is formed below the work platform 10 and between the four support legs 40. As a result, it is possible to secure a wide span placement space S1 in the front and rear, and thus the workability of each process related to concrete placement is enhanced.

[トンネルインバート施工方法]
引き続き、本発明のトンネルインバート施工方法について図を参照しながら詳細に説明する。図1〜図3は各工程を模式的に表した説明図である。
[Tunnel invert construction method]
Subsequently, the tunnel invert construction method of the present invention will be described in detail with reference to the drawings. 1-3 is explanatory drawing which represented each process typically.

<1>施工前の状態。
インバート桟橋1は、前部斜路20の先端を施工前の地盤上に、後部斜路30の先端を施工後の地盤上に、それぞれ掛け渡し、前部斜路20をトンネルの横断方向における第一側に位置させる。
<1> State before construction.
The invert pier 1 spans the front ramp 20 on the ground before construction and the rear slope 30 on the ground after construction, and the front ramp 20 on the first side in the crossing direction of the tunnel. Position.

<2>第二側の先行掘削(図1)。
作業架台10より切羽側の地盤を先行掘削する。
トンネル幅方向の中央より前部斜路20の第二側がわの掘削空間S2を所定深さまで掘削する。
<2> Advance excavation on the second side (FIG. 1).
The ground on the face side from the work platform 10 is excavated in advance.
The excavation space S2 on the second side of the front ramp 20 from the center in the tunnel width direction is excavated to a predetermined depth.

<3>第一側の先行掘削(図2)。
第二側がわの掘削空間S2を掘削後、前部斜路20を第二側へスライド移動する。
引き続き、前部斜路20の第一側がわの掘削空間S2を所定深さまで掘削する。
<3> First excavation on the first side (FIG. 2).
After excavating the excavation space S2 on the second side, the front ramp 20 is slid to the second side.
Subsequently, the excavation space S2 on the first side of the front ramp 20 is excavated to a predetermined depth.

<4>インバートコンクリート打設(図2)。
前サイクルで先行掘削した作業架台10下方の地盤上に、配筋と型枠の設置を行い、作業架台10の上部に配置したコンクリートミキサー車から下方の地盤へ生コンクリートを投入する。
この際、作業架台10の底面から型枠の浮き上がり防止の反力を取ることができる。
続いて、コンクリートの硬化を待ち、脱型、養生を行う。
説明の便宜上、先行掘削をインバートコンクリート打設の前に記載したが、実際は、先行掘削とインバートコンクリート打設は、施工区間を前後にずらした状態で同時に行う。
必要に応じて、インバートコンクリートの埋め戻しを行う。
<4> Invert concrete placement (FIG. 2).
Reinforcement and formwork are installed on the ground below the work platform 10 that has been excavated in the previous cycle, and the ready-mixed concrete is put into the lower ground from the concrete mixer truck disposed on the work platform 10.
At this time, it is possible to take a reaction force to prevent the formwork from lifting from the bottom surface of the work platform 10.
Subsequently, the concrete is hardened, demolded and cured.
For convenience of explanation, the preceding excavation has been described before the invert concrete placement, but in fact, the prior excavation and the invert concrete placement are performed simultaneously with the construction section being shifted back and forth.
If necessary, backfill invert concrete.

<5>インバート桟橋の前進(図3)。
前部斜路20の先端を油圧ジャッキで押し上げて地盤の上方へ持ち上げる。
後部斜路30の後端を吊りアーム11で地盤の上方へ吊り上げる。
インバート桟橋1をバックホウ等の工事車両で牽引して、1スパン分切羽側に前進させる。ここで、1スパンとは先行掘削による掘削距離と実質的に同一の距離である。
これによって作業架台10が、先行掘削による掘削区間の上方に位置決めされる。
なお、インバート桟橋1の前進方法は牽引に限らず、油圧モータで自走する方法や、支持脚40を油圧ジャッキで短縮してから切羽側へ前進させた後に伸長し、前後の支持脚40でこれを繰り返すことで前進する方法などを採用してもよい。これらは公知技術であるのでここでは詳述しない。
自走式であっても牽引式であっても、要はトンネルの延長方向に沿って前進できればよい。
<5> Advance of Invert Pier (Fig. 3).
The tip of the front ramp 20 is pushed up with a hydraulic jack and lifted above the ground.
The rear end of the rear ramp 30 is lifted by the suspension arm 11 above the ground.
Pull the Invert Pier 1 with a construction vehicle such as a backhoe and advance it to the face side by one span. Here, one span is substantially the same distance as the excavation distance by the preceding excavation.
Thereby, the work platform 10 is positioned above the excavation section by the preceding excavation.
In addition, the advance method of the invert pier 1 is not limited to towing, but is a method of self-propelling with a hydraulic motor, or the support leg 40 is shortened with a hydraulic jack and then extended to the face side, and then extended with the front and rear support legs 40. You may employ | adopt the method of moving forward by repeating this. Since these are known techniques, they will not be described in detail here.
Regardless of whether it is self-propelled or towed, it suffices if it can move forward along the direction of tunnel extension.

<6>各工程の繰り返し。
以上<2>から<5>の工程を1サイクルとして、これを繰り返しながらインバート桟橋1を切羽側へ移動させることで、インバート工を進捗させる。
なお、<2><3>工程における第一側と第二側は、施工上の便宜に併せて適宜入れ替えて行う。
本発明のトンネルインバートの施工方法は、インバート工の施工区間を掘削区間と打設区間に前後に分割し、インバートコンクリートの打設と、インバート掘削とを前後で併行しながら進行することができる。従って、インバート工の施工効率が著しく高い。
<6> Repeat each step.
The process from <2> to <5> is set as one cycle, and the invert work is advanced by moving the invert pier 1 to the face side while repeating this.
It should be noted that the first side and the second side in the <2><3> steps are appropriately exchanged for convenience of construction.
In the tunnel invert construction method of the present invention, the construction section of the invert work is divided into the excavation section and the placement section, and the invert concrete placement and the invert excavation can be performed in parallel. Therefore, the construction efficiency of invert work is remarkably high.

<7>施工効率の対比。
以下に、本発明のトンネルインバートの施工方法と従来技術の施工効率の対比表を示す。
<7> Comparison of construction efficiency.
Below, the comparison table of the construction efficiency of the tunnel invert of this invention and the construction efficiency of a prior art is shown.

Figure 2018155020

本発明のトンネルインバートの施工方法は、従来技術の1スパンを前後2サイクルに分割して施工し、2サイクル目の掘削を1サイクル目のインバート打設と同時に行うことによって、施工時間を圧縮することができる。本例では、従来技術に対して作業時間が35単位から28単位へ20%削減されている。
施工長が1スパン10.5mのインバート施工において、従来は、1週間に3サイクルの施工が限界であった。よって、[10.5m×3回/週×4週間=126m(月進)]となる。
これに対し、本発明のトンネルインバートの施工方法は、1週間に5サイクルの施工が可能であるため、[10.5m×5回/週×4週間=210m(月進)]となる。
本工事の進捗が発破により月進150mとすると、従来技術では、施工の進捗に伴い切羽とインバート部の距離が広がり(毎月24m)全体工期に悪影響を及ぼす。これに対し、本発明のトンネルインバートの施工方法は、切羽との距離を一定以内に確保でき、工事全体の急速施工を可能とする。
Figure 2018155020

The tunnel invert construction method of the present invention divides one span of the prior art into two cycles before and after, and compresses the construction time by performing excavation at the second cycle simultaneously with invert placement at the first cycle. be able to. In this example, the working time is reduced by 20% from 35 units to 28 units compared to the prior art.
In an invert construction with a construction length of 10.5 m per span, conventionally, the construction of three cycles per week was the limit. Therefore, [10.5 m × 3 times / week × 4 weeks = 126 m (monthly advance)].
On the other hand, since the tunnel invert construction method of the present invention can construct five cycles in one week, [10.5 m × 5 times / week × 4 weeks = 210 m (monthly advance)].
If the progress of this construction is 150 m / month due to blasting, with the conventional technology, the distance between the face and the invert portion will increase with the progress of construction (24 m per month), which will adversely affect the entire construction period. On the other hand, the tunnel invert construction method of the present invention can ensure the distance from the face within a certain range, and enables rapid construction of the entire construction.

1 インバート桟橋
10 作業架台
11 吊りアーム
20 前部斜路
30 後部斜路
40 支持脚
41 支持台車
42 昇降装置
S1 打設空間
S2 掘削空間
C インバートコンクリート
DESCRIPTION OF SYMBOLS 1 Invert pier 10 Work stand 11 Suspension arm 20 Front slope 30 Rear slope 40 Support leg 41 Support carriage 42 Lifting device S1 Placing space S2 Excavation space C Invert concrete

Claims (4)

トンネルインバート施工用のインバート桟橋であって、
下方にインバートコンクリート打設作業用の打設空間を有する作業架台と、
前記作業架台の前端と地盤との間に掛け渡す前部斜路と、
前記作業架台の後端と地盤との間に掛け渡す後部斜路と、
前記作業架台の下部に付設し、前記作業架台を地盤から離間支持する複数の支持脚と、を備え、
前記前部斜路の幅は、前記作業架台の幅の半分以下であり、
前記前部斜路が、前記作業架台の幅方向における任意の位置に接続可能であることを特徴とする、
インバート桟橋。
Invert pier for tunnel invert construction,
A work platform having a placement space for invert concrete placement work below;
A front ramp extending between the front end of the work platform and the ground;
A rear ramp extending between the rear end of the work platform and the ground;
A plurality of support legs attached to the lower part of the work platform and supporting the work platform apart from the ground,
The width of the front ramp is less than half the width of the work platform;
The front ramp is connectable to any position in the width direction of the work platform,
Invert pier.
前記前部斜路が、前記作業架台の幅方向に沿って摺動自在であることを特徴とする、請求項1に記載のインバート桟橋。   The invert pier according to claim 1, wherein the front ramp is slidable along a width direction of the work platform. 前記複数の支持脚は、前記作業架台の前方に付設する前部支持脚と、前記作業架台の後方に付設する後部支持脚と、を有し、前記打設空間は、前記前部支持脚と前記後部支持脚との間に形成されることを特徴とする、請求項1または2のいずれか一項に記載のインバート桟橋。   The plurality of support legs include a front support leg attached to the front of the work base and a rear support leg attached to the rear of the work base, and the placement space includes the front support leg and The invert pier according to claim 1, wherein the invert pier is formed between the rear support legs. 請求項1乃至3のいずれか一項に記載のインバート桟橋を用いるトンネルインバート施工方法であって、
前記インバート桟橋の、前部斜路の先端を施工前の地盤上に、後部斜路の先端を施工後の地盤上に、それぞれ掛け渡した状態において、
1)前記作業架台より切羽側の地盤を先行掘削する工程と、
2)前記作業架台の上部から、前記作業架台の下方の地盤にインバートコンクリートを打設する工程と、
3)前記インバート桟橋を切羽側へ前進させ、前記作業架台を、前記1)工程実施後の掘削区間の上方に位置決めする工程と、を備え、
前記1)工程と、前記2)工程とを併行した後に、前記3)工程を行って、これを1施工サイクルとし、
前記1)工程は、
1a)前記前部斜路がトンネル横断方向の第一側に位置した状態で、前記前部斜路の第二側がわの地盤を掘削する工程と、
1b)前記前部斜路がトンネル横断方向の第二側に位置した状態で、前記前部斜路の第一側がわの地盤を掘削する工程と、を備え、
前記前部斜路をトンネル横断方向の左右に移動させることで、前記1a)工程と前記1b)工程とを、適宜入れ替えて行うことを特徴とする、
トンネルインバート施工方法。
A tunnel invert construction method using the invert pier according to any one of claims 1 to 3,
In the state where the tip of the front ramp on the invert pier is over the ground before construction and the tip of the rear ramp on the ground after construction,
1) preceding excavation of the ground on the face side from the work platform;
2) From the upper part of the work platform, placing invert concrete on the ground below the work platform;
3) a step of advancing the invert pier to the face side and positioning the work platform above the excavation section after the execution of the step 1),
After the 1) step and the 2) step are performed in parallel, the 3) step is performed, and this is defined as one construction cycle.
Step 1)
1a) a step of excavating the ground on the second side of the front ramp with the front ramp located on the first side in the tunnel crossing direction;
1b) in a state where the front ramp is located on the second side in the tunnel crossing direction, the first side of the front ramp includes excavating the ground of the ground,
By moving the front ramp to the left and right in the direction crossing the tunnel, the steps 1a) and 1b) are performed as appropriate interchanged.
Tunnel invert construction method.
JP2017052543A 2017-03-17 2017-03-17 Tunnel invert construction method Active JP6663378B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017052543A JP6663378B2 (en) 2017-03-17 2017-03-17 Tunnel invert construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017052543A JP6663378B2 (en) 2017-03-17 2017-03-17 Tunnel invert construction method

Publications (2)

Publication Number Publication Date
JP2018155020A true JP2018155020A (en) 2018-10-04
JP6663378B2 JP6663378B2 (en) 2020-03-11

Family

ID=63716148

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017052543A Active JP6663378B2 (en) 2017-03-17 2017-03-17 Tunnel invert construction method

Country Status (1)

Country Link
JP (1) JP6663378B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020111879A (en) * 2019-01-08 2020-07-27 株式会社東宏 Pier for drilling
CN115233734A (en) * 2022-09-20 2022-10-25 山西路桥市政工程有限公司 Municipal tunnel construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06173574A (en) * 1992-12-11 1994-06-21 Saga Kogyo Kk Excavation method for bottom floor in tunnel
JPH08177396A (en) * 1994-12-26 1996-07-09 Kumagai Gumi Co Ltd Tunnel invert construction method and scaffold board device for tunnel invert construction
JPH08338006A (en) * 1995-06-14 1996-12-24 Fukudagumi:Kk Pier for construction work in tunnel
JP2002004791A (en) * 2000-06-21 2002-01-09 Ohbayashi Corp Method of work for tunnel invert
JP2003322000A (en) * 2002-05-01 2003-11-14 Gifu Kogyo Co Ltd Tunnel invert construction method by movable pier and the movable pier
JP2009209526A (en) * 2008-02-29 2009-09-17 Taisei Corp Tunnel construction method
EP3112585A1 (en) * 2015-07-01 2017-01-04 Great Ocean Constructions Ltd A tunneling machinery and a method of providing a concrete tunnel base

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06173574A (en) * 1992-12-11 1994-06-21 Saga Kogyo Kk Excavation method for bottom floor in tunnel
JPH08177396A (en) * 1994-12-26 1996-07-09 Kumagai Gumi Co Ltd Tunnel invert construction method and scaffold board device for tunnel invert construction
JPH08338006A (en) * 1995-06-14 1996-12-24 Fukudagumi:Kk Pier for construction work in tunnel
JP2002004791A (en) * 2000-06-21 2002-01-09 Ohbayashi Corp Method of work for tunnel invert
JP2003322000A (en) * 2002-05-01 2003-11-14 Gifu Kogyo Co Ltd Tunnel invert construction method by movable pier and the movable pier
JP2009209526A (en) * 2008-02-29 2009-09-17 Taisei Corp Tunnel construction method
EP3112585A1 (en) * 2015-07-01 2017-01-04 Great Ocean Constructions Ltd A tunneling machinery and a method of providing a concrete tunnel base

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020111879A (en) * 2019-01-08 2020-07-27 株式会社東宏 Pier for drilling
JP7121664B2 (en) 2019-01-08 2022-08-18 株式会社東宏 drilling jetty
CN115233734A (en) * 2022-09-20 2022-10-25 山西路桥市政工程有限公司 Municipal tunnel construction method
CN115233734B (en) * 2022-09-20 2022-11-29 山西路桥市政工程有限公司 Municipal tunnel construction method

Also Published As

Publication number Publication date
JP6663378B2 (en) 2020-03-11

Similar Documents

Publication Publication Date Title
JP6837394B2 (en) Invert pier and tunnel invert construction method
JP5890060B1 (en) Bridge dismantling method using erection girder
JP2018155020A (en) Invert pier and tunnel invert construction method
JP4559370B2 (en) Girder erection method by erection gutter from the side of bridge
CN107059511B (en) Paving device capable of automatically moving steel rail
JP2006336259A (en) Tunnel invert construction method and movable pier
JP4318042B2 (en) Tunnel construction method
JP2011202406A (en) Method of assembling and disassembling movable working device for bridge
JP2018154995A (en) Concrete casting method on inclined surface and movable form device
JP3103284B2 (en) Tunnel excavation shearing gantry
JP2003232196A (en) Tunnel invert construction method and device for the same
JP3400954B2 (en) Mobile stage for tunnel reconstruction and tunnel reconstruction method using the same
JP3356048B2 (en) Construction method of elevated structure using building girder
JP3103285B2 (en) Tunnel excavation method
JP2539151B2 (en) Excavation method for bottom floor in tunnel
JP2023119948A (en) Floor slab replacement method and boom inversion type floor slab erection machine
JP2017031583A (en) Invert construction method, tunnel construction method and tunnel telpher crane
JP3822525B2 (en) Tunnel invert construction method using mobile jetty and mobile jetty
CN108217448A (en) A kind of integrated bridge floor device for hoisting for composite beam construction
JP7466368B2 (en) Deck replacement method
JP6449637B2 (en) Building construction method
JP2001173386A (en) Concrete placing equipment using invert formwork and method therefor
JP4080226B2 (en) Mobile jetty
JP2011080298A (en) Tunnel excavating equipment
JP2004244138A (en) Earth and sand leveling device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20181112

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190805

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190813

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190924

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200204

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200214

R150 Certificate of patent or registration of utility model

Ref document number: 6663378

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250