JP2954840B2 - Conveyor trolley for waste removal - Google Patents

Conveyor trolley for waste removal

Info

Publication number
JP2954840B2
JP2954840B2 JP30544794A JP30544794A JP2954840B2 JP 2954840 B2 JP2954840 B2 JP 2954840B2 JP 30544794 A JP30544794 A JP 30544794A JP 30544794 A JP30544794 A JP 30544794A JP 2954840 B2 JP2954840 B2 JP 2954840B2
Authority
JP
Japan
Prior art keywords
conveyor
rail
pillar
truck
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP30544794A
Other languages
Japanese (ja)
Other versions
JPH08135398A (en
Inventor
俊司 増田
幸夫 宮生
優一 中村
章 井出
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumuragumi KK
Original Assignee
Okumuragumi KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumuragumi KK filed Critical Okumuragumi KK
Priority to JP30544794A priority Critical patent/JP2954840B2/en
Publication of JPH08135398A publication Critical patent/JPH08135398A/en
Application granted granted Critical
Publication of JP2954840B2 publication Critical patent/JP2954840B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明はトンネルの掘削時におい
て、掘削されたズリをトンネル内後方に搬出するズリ搬
出用コンベア台車に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a conveyor truck for taking out an excavated waste to the rear of the tunnel when excavating the tunnel.

【0002】[0002]

【従来の技術】トンネル掘削工事においては、発破孔の
穿孔機や作業ケージを備えたガントリと称される装置、
掘削されたズリをベルトコンベア側に寄せ集めるシャフ
ローダと称される掻き寄せ機、ズリを運搬するトロ台
車、掻き寄せ機からトロ台車まで搬送する上記ベルトコ
ンベア、その他、コンクリート吹付機等、多くの作業機
械が使用されている。
2. Description of the Related Art In tunnel excavation work, a device called a gantry equipped with a blasting machine and a work cage,
Many works such as a scraper called a shuffler that collects excavated debris on the belt conveyor side, a trolley that transports debris, the above-mentioned belt conveyor that conveys from the rake to the trolley, and other concrete spraying machines Machines are used.

【0003】そして、ガントリをトンネル切羽面側にま
で移動させて発破孔を穿設した後、該発破孔に爆薬を装
填してガントリの後退後爆破させ、次いでシャフローダ
を前進させて掘削ズリをベルトコンベア側に寄せ集め、
ベルトコンベアによって後方に搬送してトロ台車に積載
し、このズリの排出作業が完了すると支保工の建込、吹
付けコンクリートの施工を行い、再びガントリを切羽ま
で前進させて次の発破作業を行っている。
After the gantry is moved to the tunnel face side to form a blast hole, an explosive is loaded into the blast hole, the gantry is retracted and blasted, and then the shuffler is advanced to move the excavation slip to the belt. Collected on the conveyor side,
After being transported backward by a belt conveyor and loaded on a toro trolley, when the work of discharging this debris is completed, erection work is carried out, construction of shotcrete is carried out, and the gantry is advanced to the face again to perform the next blasting work ing.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記の
ような各種の作業は切羽付近で集中して行われるため、
1つの作業が終了するまで他の作業機械をトンネル後方
に待機させておき、その作業が終了後、次の作業機械を
切羽まで移動させることになる。その際、作業が終了し
た機械と次の作業機械との入れ替えを必要とするが、ト
ンネル内の作業空間が狭いために、2台の作業機械を擦
れ違うように入れ替えを行うと互いに接触して破損等が
生じる虞れがあるばかりでなく、極めて危険な作業であ
り、慎重に入れ替えをしなければならないために作業能
率が著しく低下し、その上、効率のよい大規模な作業機
械を使用することができず、トンネル構築の施工期間が
長くなるという問題点があった。本発明はこのような問
題点を全面的に解消し得るズリ搬出用コンベア台車の提
供を目的とするものである。
However, since the above-mentioned various operations are performed intensively near the face,
Another work machine is kept behind the tunnel until one work is completed, and after the work is completed, the next work machine is moved to the face. At that time, it is necessary to replace the completed machine with the next machine.However, because the working space in the tunnel is narrow, if two machines are replaced so that they are rubbed, they will come into contact with each other and break. In addition to the danger that such work may occur, the work is extremely dangerous and requires careful replacement, which significantly reduces the work efficiency and, in addition, uses an efficient large-scale work machine. However, there was a problem that the construction period of the tunnel construction was prolonged. SUMMARY OF THE INVENTION An object of the present invention is to provide a conveyor for transporting a waste that can completely solve such a problem.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するため
に、本発明のズリ搬出用コンベア台車は、トンネル内に
敷設した軌条上を走行するズリ搬出用コンベア台車であ
って、トンネル底面に狭軌条と該狭軌条を中央にして広
軌条とをトンネル長さ方向に敷設する一方、ズリ搬出用
コンベアの両側枠部に上記狭軌条上を走行可能な第1脚
柱と上記広軌条上を走行可能な第2脚柱とを設け、第1
脚注をコンベアの長さ方向に折り畳み自在にすると共に
第2脚柱を伸縮自在に且つ内外方向に開閉自在にしてこ
れらの第1脚柱と第2脚柱とのいずれかを軌条上で走行
させるように構成しているものである。
In order to achieve the above-mentioned object, the present invention provides a conveyor for transporting slips, which is a conveyor for transporting shears which runs on a rail laid in a tunnel, and has a narrow gauge on a bottom surface of the tunnel. A first rail that can run on the narrow gauge rail and a first rail that can run on the narrow gauge rail on both side frame portions of the conveyor for slip-out while laying the wide rail with the narrow rail and the narrow rail as the center. A possible second pillar and the first
The footnote is foldable in the length direction of the conveyor, and the second pedestal is stretchable and freely openable and closable in the inward and outward directions so that either the first pedestal or the second pedestal travels on the rail. It is configured as follows.

【0006】また、請求項2に記載した発明は、コンベ
ア枠に対する上記第1、第2脚柱の具体的な取付構造を
示すもので、第1脚柱は、その上端部をコンベアの側枠
部に前後方向に回動自在に枢着し、該枢着部から上方に
突出した杆部とコンベアの枠部に装着したジャッキとを
連結してこのジャッキの伸縮動作により起立、折り畳み
自在に構成されている一方、上記第2脚柱は、内端をコ
ンベアの側枠部に垂直軸を介して回動自在に連結した一
定幅の中間部材の外端にその上端部を固着していると共
に上下脚柱部に分割されて上側脚柱部に下側脚柱部をジ
ャッキによって伸縮自在に構成しているものである。
Further, the invention according to claim 2 shows a specific mounting structure of the first and second pillars to the conveyor frame, and the first pillar has an upper end portion which is a side frame of the conveyor. Pivotally attached to the front and rear parts of the conveyor, connecting the rod protruding upward from the pivoted part and the jack mounted on the frame of the conveyor, and standing up and folding by the expansion and contraction of this jack On the other hand, the second pillar has an upper end fixed to an outer end of a fixed width intermediate member having an inner end rotatably connected to a side frame of the conveyor via a vertical shaft. The lower pillar is divided into upper and lower pillars, and the lower pillar is configured to be expandable and contractable by jacks.

【0007】[0007]

【作用】切羽面に発破孔の穿設作業を行う時にはコンベ
ア台車をトンネル後方に待機させてさせておき、ガント
リをトンネル切羽面近傍部まで前進させる。なお、ガン
トリは広軌条上を走行する大型機械であって、本体が正
面門形状に形成されてコンベア台車が通過可能な空間を
有している。そして、穿孔作業と発破孔内への爆薬装填
が完了すれば、ガントリを爆破の影響を受けないコンベ
ア台車の位置まで後退させる。次いで、シャフローダと
コンベア台車を前進させて発破により掘削されたズリの
取り除き作業を行う。
When a blast hole is to be drilled in the face, the conveyor truck is kept behind the tunnel and the gantry is advanced to the vicinity of the face of the tunnel. The gantry is a large-sized machine running on a wide rail, and has a main body formed in a front gate shape, and has a space through which a conveyor truck can pass. Then, when the drilling operation and the loading of the explosive into the blast hole are completed, the gantry is retracted to the position of the conveyor truck which is not affected by the blast. Next, the shuffler and the conveyor trolley are moved forward to carry out work for removing debris excavated by blasting.

【0008】この時、ガントリとシャフローダ及びコン
ベア台車との入れ替え作業を行う。この作業は、まず、
コンベアをその第1脚柱によって狭軌条上を走行可能な
姿勢とし、第2脚柱の長さを短縮させると共にコンベア
の側枠に対して内側に閉じた状態としておく。この状態
でコンベアを前進させてガントリ内を通過させる。一
方、シャフローダは狭軌条上を走行可能な小幅で高さも
低く形成されており、従って、ガントリの空間部を通じ
て通過させてガントリとの入れ替えが行える。
At this time, the gantry is replaced with a shuffler and a conveyor truck. First of all,
The first pedestal is configured to allow the conveyor to run on a narrow rail, to reduce the length of the second pedestal and to be closed inside the side frame of the conveyor. In this state, the conveyor is advanced to pass through the gantry. On the other hand, the shuffler is formed to have a small width and a low height so that it can run on a narrow rail.

【0009】さらに、このシャフローダをコンベアと入
れ替えて切羽近傍の掘削ズリの位置まで前進させる必要
があるので、その際、コンベアの第2脚柱を外方に開放
すると共に伸長させてその下端車輪を広軌条上に載せ、
該第2脚柱によってコンベアを走行可能に支持すると共
にその脚柱部間と脚注高さによって上記ガントリと同様
なシャフローダが通過可能な空間部を形成したのち、第
1脚柱をコンベアの長さ方向に沿うように折り畳み、し
かるのち、シャフローダを狭軌条上を走行させて切羽側
に前進させる。
Further, since it is necessary to replace this shuffler with a conveyor and advance it to the position of the excavation shear near the face, at this time, the second pillar of the conveyor is opened outward and extended to lower the lower end wheel. Put on a wide gauge rail,
The second pedestal supports the conveyor so as to be able to run, and the space between the pedestals and the height of the footnote forms a space through which a shuffler similar to the gantry can pass. The shroud is then run along a narrow gauge rail and advanced toward the face.

【0010】そして、シャフローダによってズリを掻き
寄せながらコンベア上に送り出す一方、トンネル後方よ
り狭軌条上をトロ台車を走行させてガントリ内を通過さ
せたのち、コンベアの第2脚柱の脚柱間にまで前進さ
せ、コンベアによって搬出されるズリを受け取り、トン
ネル後方に排出する。支保工の建込作業は上記ガントリ
を利用して行われ、コンクリートの吹付作業はガントリ
を使用するか或いは狭軌条上を走行可能な別途作業機械
を用いてもよく、いずれにしても、作業機械の入れ替え
時には作業機械の大きさに応じてコンベアの第1脚柱、
第2脚柱を夫々狭軌条、広軌条上に走行可能に立設さ
せ、コンベア台車を狭小状態、拡大状態にして行うもの
である。
[0010] Then, while the shears are sent out onto the conveyor while being scraped by the shuffler, the toro truck is driven on the narrow rail from the rear of the tunnel to pass through the gantry, and then between the pedestals of the second pedestal of the conveyor. Forward to receive the waste carried by the conveyor and discharge it to the rear of the tunnel. The erection work is performed using the gantry, and the concrete spraying operation may be performed using a gantry or a separate working machine capable of traveling on a narrow rail. At the time of replacement of the first pillar of the conveyor, depending on the size of the work machine,
The second pillar is erected so that it can run on a narrow rail and a wide rail, respectively, and the conveyor truck is in a narrow state and an expanded state.

【0011】[0011]

【実施例】本発明の実施例を図面について説明すると、
Aはズリ搬出用コンベア台車で、一定幅を有するベルト
コンベア1と、このベルトコンベア1を張設した平面長
方形状のコンベア枠2と、コンベア枠2の両側枠部21、
21に設けた第1脚柱3、3及び第2脚柱4、4とから構
成されている。一方、トンネルT内の底面には、図3〜
図5に示すように、狭軌条5と、この狭軌条5を中央に
配した広軌条6とがトンネルの長さ方向に敷設されてお
り、上記コンベア台車Aの第1脚柱3、3は狭軌条5上
を、第2脚柱4、4は広軌条上を、夫々走行するように
構成されている。
BRIEF DESCRIPTION OF THE DRAWINGS FIG.
A is a conveyor belt for carrying out the slip, a belt conveyor 1 having a constant width, a flat rectangular conveyor frame 2 on which the belt conveyor 1 is stretched, and both side frame portions 21 of the conveyor frame 2;
It comprises a first pillar 3,3 and a second pillar 4,4 provided on 21. On the other hand, on the bottom surface in the tunnel T, FIG.
As shown in FIG. 5, a narrow rail 5 and a wide rail 6 having the narrow rail 5 arranged at the center are laid in the length direction of the tunnel, and the first pillars 3, 3 of the conveyor truck A are The second pillars 4 and 4 are configured to run on the narrow rail 5 and the second pillars 4 and 4 on the wide rail.

【0012】コンベア台車Aの構造を更に詳しく説明す
ると、ベルトコンベア1は狭軌条5の左右軌条部5a、5a
間の幅に略等しい幅を有し、長さは後述するトロ台車数
台分(図においては3台分)の長さに略等しく形成され
てあり、平面長方形状のコンベア枠2の両側枠部21、21
の前後端部間に回転自在に軸支された従動ローラ11と駆
動ローラ12間に適宜なガイドローラ(図示せず)を介し
て無端状に掛け渡されている。
The structure of the conveyor truck A will be described in more detail. The belt conveyor 1 comprises left and right rail portions 5a, 5a of a narrow rail 5.
It has a width substantially equal to the width between them, and the length is formed substantially equal to the length of several toro trucks (three in the figure) to be described later. Parts 21, 21
Is endlessly wound between a driven roller 11 and a driving roller 12 rotatably supported between the front and rear ends thereof via a suitable guide roller (not shown).

【0013】コンベア枠2は全長に亘って水平な枠体に
形成しておいてもよいが、図1に示すように、従動ロー
ラ11を有する前端側の適宜長さ部分を前方に向かうに従
って下方に傾斜した傾斜枠体2Aに形成し、この傾斜枠体
2Aの後端を水平枠体2Bの前端に上下回動自在に枢着13す
ると共に両枠体2A、2Bの対向上端部間を油圧ジャッキ14
により連結し、該油圧ジャッキ14の伸縮動作によって傾
斜枠体2Aを所望の角度に傾斜させるようにしている。ま
た、傾斜枠体2Aの前端に連結棒15を突設し、使用時にお
いてはこの連結棒15を後述するシャフローダBに連結さ
せるように構成している。
The conveyor frame 2 may be formed as a horizontal frame over its entire length. However, as shown in FIG. 1, an appropriate length of the front end side having the driven roller 11 is gradually lowered toward the front. The inclined frame 2A is formed into a
The rear end of 2A is pivotally connected to the front end of the horizontal frame 2B so as to be vertically rotatable 13 and a hydraulic jack 14 is provided between the opposed upper ends of both frames 2A and 2B.
The inclined frame 2A is inclined at a desired angle by the expansion and contraction operation of the hydraulic jack 14. Further, a connecting rod 15 is protruded from the front end of the inclined frame 2A so that the connecting rod 15 is connected to a later-described shroud B in use.

【0014】上記第1脚柱3、3と上記第2脚柱4、4
は、その下端に回転自在に取付けている車輪7、8を夫
々狭軌条5と広軌条6とに載せてコンベア枠2をトンネ
ル長さ方向に走行自在に支持するものであって、前後一
対の第1脚柱3、3は、その左右脚柱部3a、3a(図3に
示す)の上端部をコンベア枠2の水平枠体2Bの前後部に
おける両側枠部21、21にコンベア枠2の長さ方向に折り
畳み自在に連結している一方、前後一対の第2脚柱4、
4はその左右脚柱部の上端部をコンベア枠2の水平枠体
2Bの前後端部の両側枠部21、21に夫々軌条幅方向に開閉
自在に連結している。
The first pillars 3, 3 and the second pillars 4, 4
The wheels 7 and 8 rotatably mounted on the lower end thereof are mounted on the narrow rail 5 and the wide rail 6, respectively, to support the conveyor frame 2 so as to be able to travel in the tunnel length direction. The first pillars 3 have upper ends of the left and right pillars 3a, 3a (shown in FIG. 3) attached to both side frame portions 21, 21 at the front and rear portions of the horizontal frame 2B of the conveyor frame 2, respectively. While being foldably connected in the length direction, a pair of front and rear second legs 4,
4 is a horizontal frame of the conveyor frame 2 at the upper ends of the left and right pillars.
The two side frame portions 21 at the front and rear ends of the 2B are connected to be openable and closable in the rail width direction, respectively.

【0015】第1脚柱3、3は、その左右脚柱部3a、3a
間の幅を狭軌条5の左右軌条部5a、5a間の幅と同等又は
やゝ幅広く形成していると共に高さ(長さ)は後述する
ガントリCの内部空間をコンベア台車Aが通過可能な高
さに形成されてあり、左右脚柱部3a、3aの上端部をコン
ベア枠2の両側枠部21、21に前後方向に回動自在に枢着
36すると共にこれらの脚柱部3a、3aの上端から上方に向
かって杆部3b、3bを突設し、この杆部3bとコンベア枠2
の枠部21に装着した油圧ジャッキ9のロッド先端とを連
結して油圧ジャッキ9の作動により起立状態からコンベ
ア枠2の枠部21の長さ方向に沿う折り畳み状態となるよ
うに構成されている。なお、図3に示している3cは脚柱
部3a、3aの下端間を連結した連結部材で、この下面両側
部に車輪7が取付けられている。
The first pillars 3, 3 have left and right pillars 3a, 3a.
The width between them is equal to or slightly wider than the width between the right and left rail portions 5a, 5a of the narrow rail 5, and the height (length) of the conveyor truck A can pass through the internal space of the gantry C described later. The upper ends of the left and right pillars 3a, 3a are pivotally attached to the side frames 21, 21 of the conveyor frame 2 so as to be pivotable in the front-rear direction.
36, rods 3b, 3b project upward from the upper ends of the pillars 3a, 3a, and the rod 3b and the conveyor frame 2
The hydraulic jack 9 is connected to the rod end of the hydraulic jack 9 mounted on the frame portion 21 so that the hydraulic jack 9 is operated so that the standing state is brought into a folded state along the length direction of the frame portion 21 of the conveyor frame 2. . Reference numeral 3c shown in FIG. 3 is a connecting member connecting the lower ends of the pillar portions 3a, 3a, and wheels 7 are attached to both sides of the lower surface.

【0016】一方、第2脚柱4、4は第1脚柱3、3の
折り畳みの邪魔にならないように、これらの第1脚柱
3、3から夫々前後方向に小間隔を存したコンベア枠2
の前後端部に配設されている。第2脚柱4、4の左右脚
柱部は図4及び図5に示すように、上側脚柱部4aと該上
側脚柱部4a内に収納可能な下側脚柱部4bとで形成されて
いると共に上側脚柱部4aの上端部内面に一定幅の中間部
材10の外端面を一体に固着し、この中間部材10の内端に
縦筒部材16を固着して該縦筒部材16をコンベア枠2の側
枠部21に突設している上下ブラケット18、19間に支持さ
れた垂直軸17に回動自在に被嵌している。
On the other hand, the second pillars 4, 4 are conveyer frames having a small space in the front-rear direction from the first pillars 3, 3, respectively, so as not to obstruct the folding of the first pillars 3, 3. 2
At the front and rear ends. As shown in FIGS. 4 and 5, the left and right pillars of the second pillars 4, 4 are formed by an upper pillar 4a and a lower pillar 4b that can be stored in the upper pillar 4a. At the same time, the outer end surface of the intermediate member 10 having a fixed width is integrally fixed to the inner surface of the upper end portion of the upper pillar portion 4a, and the vertical cylindrical member 16 is fixed to the inner end of the intermediate member 10 so as to form It is rotatably fitted on a vertical shaft 17 supported between upper and lower brackets 18 and 19 projecting from the side frame portion 21 of the conveyor frame 2.

【0017】さらに、コンベア枠2の下面と上側脚柱部
4aとを油圧ジャッキ20により連結してこの油圧ジャッキ
20のロッドを伸縮させることにより第2脚柱4、4の脚
柱部を中間部材10を介して内外方向に開閉自在とし、開
いた時には左右脚柱部間の幅を広軌条6の左右軌条部6
a、6a間の幅に等しくしてこの広軌条6上でコンベア台
車Aを走行可能に支持するように構成している。また、
左右脚柱部において、下側脚柱部4b内に油圧ジャッキ22
(図4に示す)を収納し、そのピストンロッドの先端を
上側脚柱部4aの上端内部に連結してこの油圧ジャッキ22
の作動により上側脚柱部4aの下端開口部から下側脚柱部
4bを伸縮自在としている。そして、下側脚柱部4bを大き
く伸長させた時の脚柱4の高さを脚柱4、4間の空間部
をシャフローダBが通過可能な高さとし、収縮させた時
の脚柱4の高さをトロ台車Dが通過可能な高さとなるよ
うに構成している。23は油圧ジャッキ9、14、20、22等
に圧油を供給する油圧ユニットで、コンベア枠2の後端
部に搭載されている。
Furthermore, the lower surface of the conveyor frame 2 and the upper pillar portion
4a and a hydraulic jack 20
By expanding and contracting the rod of 20, the pillars of the second pillars 4, 4 can be opened and closed inward and outward via the intermediate member 10, and when opened, the width between the left and right pillars is increased by the left and right rails of the wide rail 6. Part 6
The width is equal to the width between a and 6a, and the conveyor truck A is configured to be movably supported on the wide rail 6. Also,
In the left and right pillars, the hydraulic jack 22 is inserted in the lower pillar 4b.
(Shown in FIG. 4), and the distal end of the piston rod is connected to the inside of the upper end of the upper pedestal portion 4a.
Operation of the lower pillar from the lower end opening of the upper pillar 4a.
4b is flexible. The height of the pillar 4 when the lower pillar 4b is greatly extended is set to a height at which the shuffler B can pass through the space between the pillars 4 and 4, and the height of the pillar 4 when contracted. The height is set so that the toro cart D can pass through. Reference numeral 23 denotes a hydraulic unit that supplies pressure oil to the hydraulic jacks 9, 14, 20, 22, and the like, and is mounted on the rear end of the conveyor frame 2.

【0018】このように構成したズリ搬出用コンベア台
車を使用態様を述べると、発破工法によってトンネルT
を掘削する場合、まず、図2に示すように、トンネルT
の切羽面tの近傍部にまで発破孔の穿孔機24や作業ケー
ジ25を備えたガントリCを前進させる一方、コンベア台
車Aは発破の影響を受けないトンネル後方の適宜位置ま
で後退して待機させておく。
A description will be given of the manner of use of the conveyor belt for carrying out the slip constructed as described above.
When excavating a tunnel, first, as shown in FIG.
The gantry C equipped with the blasting hole punch 24 and the work cage 25 is advanced to the vicinity of the facet t, while the conveyor trolley A is retracted to an appropriate position behind the tunnel which is not affected by the blasting and waits. Keep it.

【0019】ガントリCは、穿孔機24や作業ケージ25を
備えた台板26の四方隅部の下面に上記広軌条6上を走行
する車輪35を有する脚柱部材27を固着してあり、この脚
柱部材27の高さ(長さ)を上記第1脚柱3により狭軌条
5上に支持された時のコンベア台車Aの高さよりも大き
くして、図3に示すように、台板26と左右脚柱部材27、
27間で囲まれた空間部28を上記高さのコンベア台車Aが
通過可能に形成している。
The gantry C has a pillar member 27 having wheels 35 running on the wide rail 6 fixed to the lower surface of the four corners of a base plate 26 provided with a drilling machine 24 and a working cage 25. The height (length) of the pillar member 27 is made larger than the height of the conveyor truck A when supported on the narrow rail 5 by the first pillar 3, and as shown in FIG. And left and right pillar members 27,
The space 28 enclosed by the spaces 27 is formed so that the conveyor truck A having the above height can pass therethrough.

【0020】そして、穿孔機24によって切羽tに複数個
の発破孔を穿設し、この発破孔内に爆薬を装填する作業
が完了すると、このガントリCを爆破の影響を受けない
コンベア台車Aの位置まで後退させたのち、爆破させ
る。次いで、図1に示すように爆破により掘削されたズ
リEを掻き寄せる掻き寄せ具29と、該掻き寄せ具29によ
って掻き寄せたズリEを後方に搬送する上向き傾斜ベル
トコンベア装置30とを備えてなるシャフローダBを切羽
tの近傍部にまで前進させると共に該シャフローダBの
後方までコンベア台車Aを前進させる。
Then, a plurality of blast holes are drilled in the face t by the punch 24, and when the operation of loading the explosive into the blast holes is completed, the gantry C is removed from the conveyor truck A which is not affected by the blast. After retreating to position, blast. Next, as shown in FIG. 1, a scraping tool 29 for scraping the scrap E excavated by the blast and an upwardly inclined belt conveyor device 30 for transporting the scrap E scraped by the scraping tool 29 to the rear are provided. Is moved forward to the vicinity of the face t, and the conveyor truck A is moved forward to the rear of the shuffler B.

【0021】この際、シャフローダBとコンベア台車A
とは別々に前進させてもよいが、図1に示すようにシャ
フローダBの上向き傾斜ベルトコンベア装置30の下面に
ブラケット31を突設しておき、このブラケット31にコン
ベア台車Aの傾斜枠体2Aの連結棒15を連結してシャフロ
ーダBにコンベア台車Aを後続させて両者を一体的に前
進移動させるようにしている。シャフローダBはその前
後左右の車輪32を図4に示すように狭軌条5上を走行さ
せるように構成していると共に、高さは上記第2脚柱3
により広軌条6上に支持された時のコンベア台車Aの脚
柱伸長高さよりも低くしてコンベア台車Aのコンベア枠
2と左右脚柱部3a、3a間で囲まれた空間部33内を通過可
能に形成している。尚、シャフローダBの車輪32の両外
側方にはシャフローダ本体に対して油圧ジャッキ等で上
下方向に高さ調整自在な履帯34が設けられている。
At this time, the shuffler B and the conveyor truck A
1, a bracket 31 is protruded from the lower surface of the upward inclined belt conveyor device 30 of the shuffler B, and the inclined frame 2A of the conveyor truck A is mounted on the bracket 31 as shown in FIG. Are connected to each other so that the conveyor truck A follows the shuffler B and the two are integrally moved forward. The shuffler B is constructed so that its front, rear, left and right wheels 32 run on the narrow rail 5 as shown in FIG.
And lower than the column height of the conveyor truck A when it is supported on the wide rail 6, thereby passing through the space 33 surrounded by the conveyor frame 2 of the conveyor truck A and the left and right pillar portions 3a, 3a. It is formed as possible. A crawler belt 34 whose height can be adjusted vertically by a hydraulic jack or the like with respect to the main body of the shuffler B is provided on both outer sides of the wheels 32 of the shuffler B.

【0022】これらのシャフローダBとコンベア台車A
とを切羽t側に移動させるには、その前方側に上記ガン
トリCが存在するので、このガントリCと前後に入れ替
えなければならない。この入れ替え作業において、ガン
トリCとコンベア台車Aとを入れ替えるには、コンベア
台車Aの第2脚柱4、4の下側脚柱部4bを上側脚柱部4a
内に収縮させることによって該脚柱4の高さを第1脚柱
3の高さよりも短くしたのち、油圧ジャッキ20によって
中間部材10をコンベア枠2の両側枠部21、21に重なるよ
うに折り畳むことによってこれらの第2脚柱4、4をコ
ンベア枠2の両側枠部21、21から下方に吊支した状態に
収め、図3に示すように、第1脚柱3、3を狭軌条5上
に走行自在に載せた状態とする。この状態にしてコンベ
ア台車Aを前進させると、該コンベア台車Aはガントリ
Cの門形状空間部28内を通過し、ガントリCに対して前
後入れ替えが行える。
These shuffler B and conveyor trolley A
In order to move the gantry C to the face t side, the gantry C is present in front of the gantry C, so that the gantry C must be replaced with the gantry C. In this exchange work, in order to exchange the gantry C and the conveyor trolley A, the lower pedestal 4b of the second pedestal 4, 4 of the conveyor trolley A is connected to the upper pedestal 4a.
After the height of the pedestal 4 is made shorter than the height of the first pedestal 3 by contracting inward, the intermediate member 10 is folded by the hydraulic jack 20 so as to overlap the both side frame portions 21, 21 of the conveyor frame 2. As a result, the second pillars 4 are suspended from both side frame parts 21 of the conveyor frame 2 in a downward direction, and the first pillars 3 are narrowed as shown in FIG. It is assumed that it is mounted on the top so that it can run freely. When the conveyor trolley A is moved forward in this state, the conveyor trolley A passes through the inside of the gate-shaped space 28 of the gantry C, and the gantry C can be switched back and forth.

【0023】次に、シャフローダBをコンベア台車Aの
前側に位置させるには、図4に示すように、コンベア台
車Aの第2脚柱4、4の中間部材10を油圧ジャッキ20の
伸長によってコンベア台車Aの両側枠部21、21に対して
直角方向に開放し、左右脚柱部間の幅を広軌条6の左右
軌条部6a、6a間の幅間隔にしたのち、下側脚柱部4bを下
方に伸長させてその下端車輪8を広軌条6上に載せ、さ
らに、コンベア台車Aが所定高さとなるまで下側脚柱部
4bを伸長させる。そうすると、第1脚柱3、3が狭軌条
5から浮き上がるので、この第1脚柱3、3を油圧ジャ
ッキ9のロッドを収縮させることによってコンベア枠2
の長さ方向に沿うように折り畳む。しかるのち、コンベ
ア枠2と第2脚柱4の左右脚柱部間で囲まれた門形状の
空間部33を通じてシャフローダBを通過させれば、コン
ベア台車AとシャフローダBとの入れ替えが可能とな
る。
Next, in order to position the shuffler B on the front side of the conveyor truck A, the intermediate member 10 of the second leg 4, 4 of the conveyor truck A is moved by the extension of the hydraulic jack 20, as shown in FIG. After being opened in a direction perpendicular to both side frame portions 21 and 21 of the bogie A, the width between the left and right pillar portions is set to the width interval between the left and right rail portions 6a and 6a of the wide rail 6, and then the lower pillar portion 4b. Is extended downward, the lower end wheel 8 is placed on the wide rail 6, and the lower pedestal portion is further lowered until the conveyor truck A reaches a predetermined height.
Extend 4b. Then, the first pillars 3, 3 are lifted from the narrow rails 5.
Fold along the length of. Thereafter, if the shuffler B is passed through the gate-shaped space 33 surrounded by the left and right pillars of the conveyor frame 2 and the second pillar 4, the conveyor truck A and the shuffler B can be interchanged. .

【0024】こうして、コンベア台車Aの前側にシャフ
ローダBを位置させたのち、シャフローダBにコンベア
台車Aの前端傾斜枠体2Aを連結させる。この際、コンベ
ア台車Aの第2脚柱4、4の下側脚柱部4bを所望長さ収
縮させてコンベア枠2の下方空間部33の高さをトロ台車
Dが通過可能な高さとし、しかるのち、該コンベア台車
AをシャフローダBに連結させてシャフローダBを狭軌
条5上で、コンベア台車Aを広軌条6上でそれぞれ走行
させながらシャフローダBを切羽近傍部にまで移動させ
る。
After the shuffler B is positioned in front of the conveyor truck A in this manner, the front inclined frame 2A of the conveyor truck A is connected to the shuffler B. At this time, the lower pillars 4b of the second pillars 4, 4 of the conveyor truck A are contracted by a desired length, and the height of the lower space 33 of the conveyor frame 2 is set to a height at which the toro truck D can pass, Thereafter, the conveyor truck A is connected to the shuffler B, and the shuffler B is moved to the vicinity of the face while the conveyor truck A is traveling on the narrow rail 5 and the conveyor truck A is traveling on the wide rail 6.

【0025】そして、シャフローダBの掻き寄せ具29に
よってズリEを掻き寄せながらベルトコンベア装置30の
搬送始端部に載せ、該ベルトコンベア装置30の搬送終端
の下方に臨ませているコンベア台車Aの傾斜枠体2Aのベ
ルトコンベア1上にズリEを移載して傾斜枠体2Aから水
平枠体2Bの後端までベルトコンベア1によって搬送す
る。
Then, the scraper E is scraped by the scraper 29 of the shuffler B and is placed on the transport start end of the belt conveyor device 30 while the conveyor truck A is tilted downward from the transport end of the belt conveyor device 30. The slip E is transferred onto the belt conveyor 1 of the frame 2A and is conveyed by the belt conveyor 1 from the inclined frame 2A to the rear end of the horizontal frame 2B.

【0026】一方、トンネル後方側から上記ガントリC
の空間部28を通過して数台連結したトロ台車Dを狭軌条
5上で前進走行させ、最前部のトロ台車Dをコンベア台
車Aの空間部33内に侵入させて最後部のトロ台車Dをベ
ルトコンベア1のズリ排出端の下方に位置させた状態と
する。この状態でベルトコンベア1によって搬送されて
くるズリEをトロ台車Dに投入、積載し、該トロ台車D
が満杯になると後退させて次のトロ台車Dをベルトコン
ベア1のズリ排出端の下方に臨ませる。こうして全ての
トロ台車DにズリEが積載されると、トロ台車Dをトン
ネル後方のズリ排出部にまで走行させてズリEを排出し
たのち、再び、コンベア台車Aまで移動してズリEの積
み込みを行う。なお、トロ台車Dは狭軌条5上を走行す
る牽引車(図示せず)によって牽引される。
On the other hand, the gantry C
Are moved forward on the narrow rail 5, and the foremost trolley D is made to enter the space 33 of the conveyor trolley A, and the last trolley D is moved. Is located below the shear discharge end of the belt conveyor 1. In this state, the slip E conveyed by the belt conveyor 1 is loaded into the toro cart D, loaded, and
When is full, the toro truck D is moved backward so as to face below the slip discharge end of the belt conveyor 1. When the slip E is loaded on all the toro trucks D, the toro truck D is driven to the slip discharge portion at the rear of the tunnel to discharge the slip E, and then moved to the conveyor truck A again to load the slip E. I do. The toro truck D is towed by a towing vehicle (not shown) running on the narrow rail 5.

【0027】こうして、発破により生じた切羽部のズリ
Eの排出、除去が完了すると、コンベア台車A及びシャ
フローダBを発破の影響を受けないトンネル後方部にま
で後退させて上記同様な操作によりガントリCと入れ替
え、ガントリCを切羽tの近傍部にまで前進させる。そ
して、ガントリCの作業ケージ25を利用して発破により
掘削されたトンネル壁部にコンクリートの吹き付け作業
を行うと共に支保工の建込作業を行い、さらに、上記同
様にして切羽tに発破孔を穿設し、爆薬を装填したの
ち、ガントリCを後退させて爆破させ、以下、上記同様
にシャフローダBによるズリEの掻き寄せとコンベア台
車Aのベルトコンベア1によるトロ台車DへのズリEの
積載を行ってズリEを排出、除去し、この作業を繰り返
し行ってトンネルを掘進するものである。
In this manner, when the discharge and removal of the cutting edge E generated by the blasting are completed, the conveyor truck A and the shuffler B are retracted to the rear portion of the tunnel which is not affected by the blasting, and the gantry C is operated by the same operation as described above. And the gantry C is advanced to the vicinity of the face t. Then, using the work cage 25 of the gantry C, the concrete is sprayed on the tunnel wall excavated by the blasting, the erection work is performed, and the blast hole is drilled in the face t in the same manner as described above. After loading the explosive, the gantry C is retracted and blasted, and thereafter, the scraper E is scraped by the shuffler B and the loading of the slip E to the toro truck D by the belt conveyor 1 of the conveyor truck A is performed as described above. Then, the waste E is discharged and removed, and this operation is repeated to excavate the tunnel.

【0028】一定長のトンネルの掘進に従って、該トン
ネル底面に狭軌条5と広軌条6とを順次継ぎ足して行
き、また、シャフローダBが狭軌条5上で定置した状態
では切羽t近傍部のズリまで掻き寄せできない場合に
は、該シャフローダBの両側履帯34を下動させて車輪32
を狭軌条5から浮き上がらせ、履帯34を駆動操作して狭
軌条5の前端からシャフローダBを前方に移動させるこ
とにより切羽近傍部のズリの掻き寄せを行う。この掻き
寄せ作業が完了すれば、シャフローダBを狭軌条5上ま
で後退させ、履帯34を上動させて車輪32を狭軌条5に載
置させる。なお、以上の実施例における吹き付けコンク
リートの施工は、別な装置によって行うように構成して
もよい。
As the tunnel of a certain length is excavated, the narrow rail 5 and the wide rail 6 are sequentially added to the bottom surface of the tunnel, and when the shuffler B is fixed on the narrow rail 5, the narrow rail 5 is shifted to a position near the face t. If it cannot be scraped, the crawler belts 34 on both sides of the shuffler B are moved down to
Is lifted from the narrow rail 5 and the crawler belt 34 is driven to move the shuffler B forward from the front end of the narrow rail 5 to scrape off the shear near the face. When the scraping operation is completed, the shuffler B is retracted onto the narrow rail 5, the crawler belt 34 is moved upward, and the wheels 32 are mounted on the narrow rail 5. The construction of the shotcrete in the above embodiment may be performed by another device.

【0029】[0029]

【発明の効果】以上のように本発明のズリ搬出用コンベ
ア台車によれば、トンネル内に敷設した軌条上を走行す
るコンベア台車であって、トンネル底面に狭軌条と該狭
軌条を中央にして広軌条とをトンネル長さ方向に敷設す
る一方、ズリ搬出用コンベアの両側枠部に上記狭軌条上
を走行可能な第1脚柱と上記広軌条上を走行可能な第2
脚柱とを設け、第1脚柱をコンベアの長さ方向に折り畳
み自在にすると共に第2脚柱を伸縮自在に且つ内外方向
に開閉自在にしてこれらの第1脚柱と第2脚柱とのいず
れかを軌条上で走行させるように構成しているので、第
1脚柱をコンベアの長さ方向に折り畳む一方、第2脚柱
の左右脚柱部を外側に開放させると共に伸長させること
によって第2脚柱の左右脚柱部間におけるコンベアの下
方空間部を大きくすることができ、従って、該第2脚柱
を介してこのコンベア台車を広軌条上で走行可能にする
一方、狭軌条上を走行移動可能な小型機械や各種設備機
器をコンベアの下方空間部を通過させることによりコン
ベア台車とこれらの小型機械や設備機器との入れ替え作
業が容易に行えるものである。
As described above, according to the present invention, a conveyor truck that runs on a rail laid in a tunnel, and has a narrow rail and a center of the narrow rail on the bottom of the tunnel. A first rail that can run on the narrow rail and a second rail that can run on the wide rail are provided on both side frames of the conveyor for slip-out while laying the wide rail in the tunnel length direction.
The first pillar and the second pillar are provided so that the first pillar can be freely folded in the length direction of the conveyor and the second pillar can be extended and contracted and can be opened and closed inward and outward. Is configured to run on the rail, so that the first pillar is folded in the length direction of the conveyor, while the left and right pillars of the second pillar are opened outward and extended. The space below the conveyor between the left and right pedestals of the second pedestal can be increased, so that the conveyor trolley can run on the wide tier through the second pedestal, while on the narrow rail. By passing small machines and various equipment that can travel on the conveyor through the space below the conveyor, it is possible to easily replace the conveyor truck with these small machines and equipment.

【0030】また、第2脚柱を収縮させると共に内側に
折り畳む一方、第1脚柱を狭軌条上に走行可能に支持さ
せることによってコンベア台車全体の幅及び高さを小さ
くすることができ、従って、広軌条上を走行するガント
リ等の大型機械の空間部をコンベア台車を通過させて大
型機械との入れ替えを容易に行うことができるものであ
り、このように作業機械や設備機器の大きさに応じてコ
ンベアの第1脚柱、第2脚柱を夫々狭軌条、広軌条上に
走行可能に立設させることでコンベア台車を狭小状態、
拡大状態にして狭いトンネル内での各種の機械との入れ
替えが簡単且つ安全に行うことができ、トンネル構築の
施工期間の短縮を図ることができるものである。
Also, the width and height of the entire conveyor truck can be reduced by contracting and folding the second pillar inward while supporting the first pillar on a narrow rail so as to be able to run. The space between large machines such as gantry running on a wide rail can be passed through a conveyor truck, and can be easily replaced with large machines. Accordingly, the first and second pillars of the conveyor are erected so that they can run on narrow rails and wide rails, respectively, so that the conveyor truck is in a narrow state.
It is possible to easily and safely replace various machines in a narrow tunnel in an enlarged state, and to shorten the construction period of the tunnel construction.

【図面の簡単な説明】[Brief description of the drawings]

【図1】シャフローダに連結したコンベア台車の簡略側
面図、
FIG. 1 is a simplified side view of a conveyor truck connected to a shuffler,

【図2】ガントリによって切羽に穿孔している状態の簡
略側面図、
FIG. 2 is a simplified side view of a state where a face is perforated by a gantry,

【図3】ガントリとコンベア台車との入れ替え状態を示
す縦断正面図、
FIG. 3 is a longitudinal sectional front view showing a state in which a gantry and a conveyor cart are replaced.

【図4】シャフローダとコンベア台車との入れ替え状態
を示す縦断正面図、
FIG. 4 is a longitudinal sectional front view showing a state where a shuffler and a conveyor cart are exchanged.

【図5】コンベア台車の空間部内にトロ台車を配設して
いる状態を示す縦断正面図。
FIG. 5 is a longitudinal sectional front view showing a state where a toro truck is arranged in a space of the conveyor truck.

【符号の説明】[Explanation of symbols]

A コンベア台車 1 ベルトコンベア 2 コンベア枠 3 第1脚柱 4 第2脚柱 5 狭軌条 6 広軌条 B シャフローダ C ガントリ D トロ台車 A Conveyor Truck 1 Belt Conveyor 2 Conveyor Frame 3 First Pillar 4 Second Pillar 5 Narrow Rail 6 Wide Rail B Shafuroda C Gantry D Toro Truck

───────────────────────────────────────────────────── フロントページの続き (72)発明者 井出 章 大阪市阿倍野区松崎町2丁目2番2号 株式会社奥村組内 (58)調査した分野(Int.Cl.6,DB名) E21F 13/02 ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Akira Ide 2-2-2 Matsuzaki-cho, Abeno-ku, Osaka-shi Okumura Gumi Co., Ltd. (58) Field surveyed (Int.Cl. 6 , DB name) E21F 13/02

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 トンネル内に敷設した軌条上を走行する
ズリ搬出用コンベア台車であって、トンネル底面に狭軌
条と該狭軌条を中央部にして広軌条とをトンネル長さ方
向に敷設する一方、ズリ搬出用コンベアの両側枠部に上
記狭軌条上を走行可能な第1脚柱と上記広軌条上を走行
可能な第2脚柱とを設け、第1脚柱をコンベアの長さ方
向に折り畳み自在にすると共に第2脚柱を伸縮自在に且
つ内外方向に開閉自在にしてこれらの第1脚柱と第2脚
柱とのいずれかを軌条上で走行させるように構成したこ
とを特徴とするズリ搬出用コンベア台車。
Claims 1. A conveyor truck for carrying out a slip running on a rail laid in a tunnel, wherein a narrow rail and a wide rail with the narrow rail as a center portion are laid in a tunnel length direction on a bottom surface of the tunnel. A first pillar capable of traveling on the narrow rail and a second pillar capable of traveling on the wide rail are provided on both side frame portions of the conveyor for carrying out the slip, and the first pillar is arranged in a longitudinal direction of the conveyor. It is characterized in that it is configured to be freely foldable and the second pedestal can be freely extended and retracted and opened and closed in the inward and outward directions so that either one of the first pedestal and the second pedestal travels on a rail. Conveyor cart for picking up waste.
【請求項2】 上記第1脚柱は、その上端部をコンベア
の側枠部に前後方向に回動自在に枢着し、該枢着部から
上方に突出した杆部とコンベアの枠部に装着したジャッ
キとを連結してこのジャッキの伸縮動作により起立、折
り畳み自在に構成されている一方、上記第2脚柱は、内
端をコンベアの側枠部に垂直軸を介して回動自在に連結
した一定幅の中間部材の外端にその上端部を固着してい
ると共に上下脚柱部に分割されて上側脚柱部に下側脚注
部をジャッキによって伸縮自在に構成していることを特
徴とする請求項1記載のズリ搬出用コンベア台車。
2. The first pillar has an upper end pivotally attached to a side frame of the conveyor so as to be rotatable in the front-rear direction, and a rod projecting upward from the pivot and a frame of the conveyor. The jack is connected to the jack and installed so that it can be raised and folded by the expansion and contraction of the jack. On the other hand, the second pedestal is rotatable at its inner end to the side frame of the conveyor via a vertical shaft. The upper end is fixed to the outer end of the connected intermediate member of a fixed width, and it is divided into upper and lower pillars, and the lower footnote part is configured to be expandable and contractable by jacks on the upper pillar. The conveyor truck for waste discharge according to claim 1, wherein:
JP30544794A 1994-11-14 1994-11-14 Conveyor trolley for waste removal Expired - Fee Related JP2954840B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30544794A JP2954840B2 (en) 1994-11-14 1994-11-14 Conveyor trolley for waste removal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30544794A JP2954840B2 (en) 1994-11-14 1994-11-14 Conveyor trolley for waste removal

Publications (2)

Publication Number Publication Date
JPH08135398A JPH08135398A (en) 1996-05-28
JP2954840B2 true JP2954840B2 (en) 1999-09-27

Family

ID=17945258

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30544794A Expired - Fee Related JP2954840B2 (en) 1994-11-14 1994-11-14 Conveyor trolley for waste removal

Country Status (1)

Country Link
JP (1) JP2954840B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587908A (en) * 2012-02-24 2012-07-18 李小祥 Lateral narrow-array type novel slag removing machine in conveying trough mechanism

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4308370B2 (en) * 1999-06-30 2009-08-05 株式会社熊谷組 Soil removal system
CN112983459B (en) * 2021-03-05 2023-10-17 温州市瓯江引水发展有限公司 Small-section tunnel slag discharging system
CN113622940A (en) * 2021-09-15 2021-11-09 中国华电科工集团有限公司 Drilling and blasting platform frame

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587908A (en) * 2012-02-24 2012-07-18 李小祥 Lateral narrow-array type novel slag removing machine in conveying trough mechanism

Also Published As

Publication number Publication date
JPH08135398A (en) 1996-05-28

Similar Documents

Publication Publication Date Title
CN109736798B (en) Tunneling and anchoring integrated six-arm tunneling and anchoring machine
US4813526A (en) Conveyor
US20170152745A1 (en) Tunnel support installation apparatus
CN111140245B (en) Intelligent tunnel digging and supporting machine and method for rapidly forming tunnel
US5087102A (en) Continuous mining machine
JP2954840B2 (en) Conveyor trolley for waste removal
JPH08170486A (en) Tunnel excavated muck carry-out gantry
JP3174037B2 (en) Center trolley
JP3103285B2 (en) Tunnel excavation method
JP7440929B2 (en) Tunnel construction frame device and construction method using it
JP2524537Y2 (en) Multifunctional tunnel construction equipment
JP4557931B2 (en) Excavator body recovery device in tunnel excavator
JP4118420B2 (en) Tunnel excavation and lining method and its equipment
JP2941608B2 (en) Roadbed changer
CN216341206U (en) Tunnel operation vehicle
JPH05280274A (en) Tunnel construction method
JP3151116B2 (en) Tunnel excavation method and gantry used for this method
JP4986386B2 (en) Descaler for walking beam heating furnace
JP2618798B2 (en) Multi-function excavator
CN114150721B (en) Slagging-off, loading and supporting integrated machine equipment
JP3445440B2 (en) Tunnel construction apparatus and method
JP4698512B2 (en) Method of collecting excavator body in tunnel excavator
SU608965A1 (en) Device for loading rock in mine workings
CN113818718A (en) Tunnel operation vehicle
RU2098632C1 (en) Complex of equipment for repair of mine workings

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 12

Free format text: PAYMENT UNTIL: 20110716

LAPS Cancellation because of no payment of annual fees