JPH0464697A - Construction of tunneling space - Google Patents

Construction of tunneling space

Info

Publication number
JPH0464697A
JPH0464697A JP2176741A JP17674190A JPH0464697A JP H0464697 A JPH0464697 A JP H0464697A JP 2176741 A JP2176741 A JP 2176741A JP 17674190 A JP17674190 A JP 17674190A JP H0464697 A JPH0464697 A JP H0464697A
Authority
JP
Japan
Prior art keywords
pipe
advanced
ground
excavation
space
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2176741A
Other languages
Japanese (ja)
Other versions
JPH0781486B2 (en
Inventor
Kosuke Matsunaga
松永 孝介
Masato Honda
正人 本多
Sakae Nakai
栄 中井
Kiyoshi Matsushita
清 松下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP2176741A priority Critical patent/JPH0781486B2/en
Publication of JPH0464697A publication Critical patent/JPH0464697A/en
Publication of JPH0781486B2 publication Critical patent/JPH0781486B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE:To improve the extent of tunneling efficiency by tunneling natural ground, constructing two advanced galleries at both sides, and installing plural pieces of arched pipe supports in the natural ground lying between these advanced galleries in making them go along a tunneling space section, then tunneling the lower ground. CONSTITUTION:Two advanced galleries 3, 5 are bored in the tunneling direction of a tunnel 1 at both sides of natural ground 2, and a lot of arched pipe supports 6 are installed in space between both these galleries in making them adjoining to each other along a boring form of the tunnel 1. In addition, the supports 6 are connected to each other with a steel pipe of length L1 and a joint 9, and each guide hook 7a is installed at the left side of this pipe 7 at the specified intervals along the axial direction of the pipe. Then, each guide pipe 7b is installed in parallel with a shaft center of the pipe 7 at the right of this pipe 7, while a slit 7c is installed in the side along the shaft center of the pipe 7, and afterward adjacent pipes 7 are connected via the guide pipe 7b and the guide hook 7a. With this constitution, tunneling and timbering construction can be parallelly performed.

Description

【発明の詳細な説明】 (a)、産業上の利用分野 本発明は、大断面トンネル、地下鉄駅部、地下大空間な
どを構築する際に適用するに好適な掘削空間の構築方法
に関する。
DETAILED DESCRIPTION OF THE INVENTION (a) Industrial Application Field The present invention relates to a method for constructing an excavated space suitable for use in constructing large-section tunnels, subway station areas, large underground spaces, and the like.

(b)、従来の技術 従来、地山強度の低いトンネルの掘削は、トンネル上端
部付近の掘削を先行して当該部分の覆工を構築し、j@
次次リンネル下方向けて掘削を行なってゆく方法が用い
られている。
(b), Conventional technology Conventionally, when excavating a tunnel with low ground strength, excavation near the upper end of the tunnel is preceded by constructing a lining for that part.
A method is used in which excavation is carried out successively downward.

(C)1発明が解決すべき問題点 しかし、こうした方法では、トンネル上端部の掘削が先
行することから、作業スペースが必然的に限られたもの
となり、掘削機械の導入が困難であり、人力による掘削
に頼らさるを得ない不都合が有る。また、トンネルが大
断面化すると天端部地山の崩壊を防止するために細かく
加背割する必要が有り、上記した不都合がより増大する
(C) 1. Problems to be solved by the invention However, in this method, since the upper end of the tunnel is excavated first, the working space is inevitably limited, making it difficult to introduce excavating machines, and using manual labor. There are unavoidable disadvantages in relying on excavation. Further, when the tunnel has a large cross-section, it is necessary to finely add and divide the crown to prevent the ground from collapsing, which further increases the above-mentioned disadvantages.

本発明は、前述の欠点を解消すべく、大断面のトンネル
などの掘削空間を効率良く掘削することの出来る地下空
間の構築方法を提供することを目的とするものである。
SUMMARY OF THE INVENTION In order to eliminate the above-mentioned drawbacks, the present invention aims to provide a method for constructing an underground space that can efficiently excavate an excavated space such as a tunnel with a large cross section.

(d)1問題点を解決するための手段 即ち1本発明は、地山(2)を掘削してトンネルなどの
掘削空間を構築する際に、2本の先進坑(3,5)を、
掘削すべきトンネル(1)などの掘削空間に沿って両側
に構築し、それら先進坑(3,5)間を接続する形で地
山中にアーチ状にパイプ支保工(6)を掘削空間断面に
沿う形で複数個敷設し、そ九ら敷設されたパイプ支保工
(6)の下部の地山(2)を掘削して掘削空間を形成す
るようにして構成される。
(d) Means for Solving Problem 1, ie, 1 This invention provides two advanced shafts (3, 5) when excavating a ground (2) to construct an excavated space such as a tunnel.
Construct pipe supports (6) on both sides along the excavation space such as the tunnel (1) to be excavated, and arch-shaped pipe supports (6) in the ground to connect the advanced shafts (3, 5) to the cross section of the excavation space. A plurality of pipe supports (6) are laid along the pipe, and the ground (2) below the pipe supports (6) is excavated to form an excavation space.

また、本発明は、地山を掘削してトンネルなどの掘削空
間を構築する際に、1本の先進坑(5)を、掘削すべき
トンネル(1)などの掘削空間に沿って構築し、前記先
進坑(5)の反対側の切羽(1a)部分から地山中に、
前記掘削空間の掘削方向に対して斜めに前記先進坑(5
)に向けて、アーチ状にパイプ支保工(6)を掘削空間
断面に沿う形で複数個敷設し、それら敷設されたパイプ
支保工(6)の下部の地山(2)を掘削して掘削空間を
形成するようにして構成される。
Further, the present invention provides that, when excavating the ground to construct an excavated space such as a tunnel, one advanced shaft (5) is constructed along the excavated space such as the tunnel (1) to be excavated, From the face (1a) on the opposite side of the advanced shaft (5) into the ground,
The advanced shaft (5
), lay multiple pipe supports (6) in an arch shape along the cross section of the excavation space, and excavate the ground (2) below the pipe supports (6) that have been laid. It is constructed to form a space.

また、本発明は、地山(2)を掘削して掘削空間を構築
する際に、3本の先進坑(3,5,17)を、掘削すべ
き掘削空間に沿って両側及び上部に構築し、それら先進
坑間を接続する形で地山中にアーチ状にパイプ支保工(
6)を掘削空間断面に沿う形で複数個敷設し、それら敷
設されたパイプ支保工の下部の地山(2)を掘削して掘
削空間を形成するようにして構成される。
In addition, the present invention constructs three advanced shafts (3, 5, 17) on both sides and above the excavation space to be excavated when excavating the earth (2) and constructing the excavation space. Then, arch-shaped pipe supports (
6) are laid along the cross section of the excavated space, and the ground (2) below the laid pipe supports is excavated to form the excavated space.

なお、括弧内の番号などは、図面における対応する要素
を示す便宜的なものであり、従って、本記述は図面上の
記載に限定拘束されるものではない。以下のr(e)、
作用」の欄についても同様である。
Note that numbers in parentheses are for convenience to indicate corresponding elements in the drawings, and therefore, this description is not limited to the descriptions in the drawings. r(e) below,
The same applies to the column "Effect".

(e)0作用 上記した構成により、本発明は、先進坑(3゜5.17
)側からパイプ支保工(6)が敷設され、切羽(1a)
側から該パイプ支保工(6)の構築された部位の地山(
2)が掘削されるように作用する。
(e) 0 effect With the above-described configuration, the present invention has an advanced shaft (3°5.17
) side, pipe shoring (6) is laid, and the face (1a)
From the side, look at the ground (
2) acts so that it is excavated.

また1本発明は、切羽(1a)側の一端から他方の先進
坑(5)に向けてパイプ支保工(6)が構築されるよう
に作用する。
Furthermore, the present invention operates so that the pipe support (6) is constructed from one end of the face (1a) toward the other advanced shaft (5).

(f)、実施例 以下、本発明の実施例を図面に基づき説明する。(f), Example Embodiments of the present invention will be described below based on the drawings.

第1図は本発明の一実施例が適用されたトンネル掘削現
場の断面図、 第2図は第1図の平面図、 第3図は第2図のパイプ支保工部の拡大図、第4図は第
1図のIV−IV線による断面図、第5図はパイプ支保
工の別の施工例を示す断面図。
Fig. 1 is a sectional view of a tunnel excavation site to which an embodiment of the present invention is applied, Fig. 2 is a plan view of Fig. 1, Fig. 3 is an enlarged view of the pipe support section of Fig. 2, and Fig. 4 is an enlarged view of the pipe support section of Fig. 2. The figure is a sectional view taken along the line IV--IV in FIG. 1, and FIG. 5 is a sectional view showing another construction example of pipe shoring.

第6図乃至第9図は本発明を用いたトンネルの掘削方法
の一例を示す図、 第10図は本発明の別の実施例が適用されたトンネルの
掘削現場の平面図、 第11図は本発明の別の実施例が適用されたトンネルの
掘削現場の断面図である。
6 to 9 are diagrams showing an example of a tunnel excavation method using the present invention, FIG. 10 is a plan view of a tunnel excavation site to which another embodiment of the present invention is applied, and FIG. 11 is a diagram showing an example of a tunnel excavation method using the present invention. FIG. 3 is a sectional view of a tunnel excavation site to which another embodiment of the present invention is applied.

トンネル1の掘削現場は、第1図に示すように、トンネ
ル1が掘削される予定の地山2の両側に先進坑3.5が
掘削されており、先進坑3.5は、トンネル1の掘削方
向に沿って、図中紙面と直角方向に形成されている。先
進坑3.5間には第1図及び第2図に示すように、トン
ネルの掘削形状に沿ってアーチ状にパイプ支保工6が形
成されており、パイプ支保工6は、第2図に示すように
トンネルの掘削方向である矢印A方向に対して直交する
方向に、互いに隣接する形で多数敷設されている。
At the excavation site of tunnel 1, as shown in Figure 1, advanced shafts 3.5 are excavated on both sides of the ground 2 where tunnel 1 is planned to be excavated. It is formed along the excavation direction and perpendicular to the plane of the paper in the figure. As shown in Figures 1 and 2, between the advanced shafts 3 and 5, a pipe support 6 is formed in an arch shape along the excavated shape of the tunnel. As shown, a large number of tunnels are laid adjacent to each other in a direction perpendicular to the direction of arrow A, which is the tunnel excavation direction.

各パイプ支保工6は、第2図及び第4図に示すように、
断面が円形で、長さがLlに形成された複数の鋼管パイ
プ7が継手9を介して直列に接続されており、各鋼管パ
イプ7の第4図左側面には、ガイドフック7aが鋼管パ
イプの軸心方向に沿って所定の間隔で植設されている。
Each pipe support 6 is, as shown in FIGS. 2 and 4,
A plurality of steel pipes 7 having a circular cross section and a length Ll are connected in series through a joint 9, and a guide hook 7a is attached to the left side of each steel pipe 7 in FIG. are implanted at predetermined intervals along the axial direction of the

鋼管パイプ7の第4図右方にはガイド管7bが鋼管パイ
プの軸心方向に沿って設けられており、ガイド管7bの
側面にはスリット7Cが鋼管パイプの軸心方向に沿って
穿設されている。第4図左方の鋼管パイプ7Aのガイド
管7bのスリット7Cには、鋼管パイプ7Aに隣接して
敷設された鋼管パイプ7Bのガイドフック7aが嵌入係
合しており、更に鋼管パイプ71のガイド管7bのスリ
ット7Cには、鋼管パイプ7Bに隣接して敷設された鋼
管パイプ7I)のガイドフック7aが嵌入係合し、以後
順次、隣接する鋼管パイプ7はガイド管7b及びガイド
フック7aを介して接続されている。
A guide pipe 7b is provided on the right side of the steel pipe 7 in FIG. has been done. The guide hook 7a of the steel pipe 7B laid adjacent to the steel pipe 7A is fitted into the slit 7C of the guide pipe 7b of the steel pipe 7A on the left side of FIG. The guide hook 7a of the steel pipe 7I laid adjacent to the steel pipe 7B is fitted into the slit 7C of the pipe 7b, and the adjacent steel pipes 7 are sequentially inserted through the guide pipe 7b and the guide hook 7a. connected.

トンネル1の掘削現場は、以上のような構成を有するの
で、トンネルの掘削に際しては、まず、地山2に5第1
図に示すように、図中左方の先進坑3から、既に敷設さ
れた状態のパイプ支保工6の内、第2図最上方の支保工
6に沿って、先端に掘削ビットllaが回転跣動自在に
装着された掘削機11を、対向する先進坑5に向けて発
進させる。この際、掘削機11は鋼管パイプ7と略同様
の直径及び長さを有しており、掘削機11の後方には長
さLlなる鋼管パイプ7を1本、継手9を介して接続し
ておく。
The excavation site of tunnel 1 has the above configuration, so when excavating the tunnel, first,
As shown in the figure, from the advanced shaft 3 on the left side of the figure, the excavation bit lla is rotated along the uppermost pipe support 6 in Figure 2 among the pipe supports 6 that have already been laid. The movably mounted excavator 11 is launched toward the opposing advanced mine 5. At this time, the excavator 11 has approximately the same diameter and length as the steel pipe 7, and one steel pipe 7 having a length Ll is connected to the rear of the excavator 11 via a joint 9. put.

この状態で、第6図に示すように、鋼管パイプ7の後端
を矢印B方向に押圧すると共に、掘削機11のビットl
laを回転させて掘削機11をいまだ掘削されていない
トンネルの断面形状に沿ってアーチ形に進行させるが、
鋼管パイプ7は、第4図に示すように、ガイドフック7
aを既にアーチ状に敷設された状態の、第2図下方のパ
イプ支保工6の鋼管パイプ7のガイド管7bにスリット
7cを介して接続しているので、掘削機11に接続され
た鋼管パイプ7は、既設のパイプ支保工6にガイドされ
る形で、第1図に示すように、アーチ状に対向する先進
坑5方向に円滑に移動する。
In this state, as shown in FIG. 6, while pressing the rear end of the steel pipe 7 in the direction of arrow B,
The excavator 11 is advanced in an arch shape along the cross-sectional shape of the tunnel that has not yet been excavated by rotating la.
As shown in FIG. 4, the steel pipe 7 is attached to a guide hook 7.
a is connected to the guide pipe 7b of the steel pipe 7 of the pipe shoring 6 shown in the lower part of FIG. 7 is guided by the existing pipe support 6 and smoothly moves in the direction of the advanced shaft 5 facing in an arch shape, as shown in FIG.

なお、掘削機11が所定距離L1だけ進行したところで
、鋼管パイプ7の後方に更に新たな鋼管パイプ7を継手
9を介して接続する。こうして、第7図に示すように、
先端の掘削機11が対向する先進坑5に到達したところ
で、掘削機11を鋼管パイプ7から取外すと、地山2内
には、新たに鋼管パイプ7からなるパイプ支保工6が敷
設されたこととなる。なお、掘削機11の掘進に際して
は。
Note that when the excavator 11 has traveled a predetermined distance L1, a new steel pipe 7 is further connected to the rear of the steel pipe 7 via a joint 9. In this way, as shown in Figure 7,
When the excavator 11 at the tip reaches the opposing advanced shaft 5, when the excavator 11 is removed from the steel pipe 7, a new pipe support 6 made of the steel pipe 7 has been laid in the ground 2. becomes. Note that when the excavator 11 excavates.

掘削機11にも鋼管パイプ7と同様のガイドフックを装
着して、既設の隣接するパイプ支保工6のガイド管7b
を掘進の際のガイトレールとして使用することも当然可
能であり、更に、第2図に示すように、既設のパイプ支
保工6のガイド管7b内に牽引ワイヤ12を通し、先端
を掘削機11又は鋼管パイプ7のガイドフック73など
に接続し、他端を先進坑5内に設置されたウィンチで牽
引して、掘削機11の掘削動作を支援するように構成す
ることも可能である。
The excavator 11 is also equipped with a guide hook similar to the steel pipe 7, and the guide pipe 7b of the existing adjacent pipe support 6 is installed.
Of course, it is also possible to use it as a guide rail during excavation.Furthermore, as shown in FIG. It is also possible to connect it to the guide hook 73 of the steel pipe 7 and tow the other end with a winch installed in the advanced shaft 5 to support the excavation operation of the excavator 11.

こうして、1本のパイプ支保工6が敷設されたところで
、更に、今回敷設したパイプ支保工6の第2図上方に掘
削機11により新たなパイプ支保工6を敷設してゆく。
Once one pipe support 6 has been laid in this way, a new pipe support 6 is further laid by the excavator 11 above the pipe support 6 that was laid this time in FIG.

所定本数の支保工6が敷設されたところで、第8図に示
すように新たに敷設された支保工6の下部に側壁コンク
リート13.13を打設し、支保工の構築を完了させる
。なお、この際、周囲の地山2を補強するために、敷設
の完了したパイプ支保工6の内部から周囲の地山2に地
盤改良剤などを注入して地山2を補強することも可能で
あり、更にはm管パイプ7内にコンクリートを充填した
り補強部材を設置して支保工6自体の強度を向上させる
ことも可能である。
When a predetermined number of shoring structures 6 have been laid, as shown in FIG. 8, side wall concrete 13.13 is placed at the bottom of the newly laid shoring structures 6 to complete the construction of the shoring structures. At this time, in order to reinforce the surrounding ground 2, it is also possible to inject a ground improvement agent or the like into the surrounding ground 2 from inside the pipe support 6 that has been completely laid. Furthermore, it is also possible to improve the strength of the shoring 6 itself by filling the m-pipe 7 with concrete or installing reinforcing members.

こうして、地山2を支持するパイプ支保工6が側壁コン
クリート13と共に構築されたところで、第8図に示す
ように、パイプ支保工6下部の地山2の掘削を、第2図
下方の切羽1a側から重機などを用いて行なうが、この
際、地山2は既にパイプ支保工6により支持されている
ので、支保工6内部の地山を重機などを用いて大掛かり
に掘削したとしても、地山2が変形したりトンネルが落
盤するような事態が生じるようなことはなく、円滑かつ
迅速にトンネル1掘削することが出来る。
In this way, when the pipe support 6 supporting the ground 2 has been constructed together with the side wall concrete 13, as shown in FIG. This is done from the side using heavy equipment, but at this time, the ground 2 is already supported by the pipe support 6, so even if the ground inside the support 6 is excavated extensively using heavy equipment, etc. The tunnel 1 can be excavated smoothly and quickly without deformation of the mountain 2 or collapse of the tunnel.

また、トンネル1の掘削と並行して、先進坑3゜5側で
は引き続き、前述の掘削機11を用いた新たなパイプ支
保工6の敷設動作が地山2に対して行なわれ、トンネル
1の切羽1a側からの掘削動作と先進坑3.5側からの
支保工の敷設動作が同時並行的に、効率良く行なわれる
。パイプ支保工6の構築された部位に対応した切羽1a
の掘削が完了したところで、第9図に示すように、側壁
コンクリート13.13を接続する形でインバート16
を構築し、当該部分のトンネルの構築を完了する。
In addition, in parallel with the excavation of the tunnel 1, on the advanced shaft 3.5 side, a new pipe support 6 is being laid on the ground 2 using the aforementioned excavator 11, and the tunnel 1 is being excavated. The excavation operation from the face 1a side and the shoring operation from the advanced shaft 3.5 side are performed simultaneously and efficiently. Face 1a corresponding to the constructed part of pipe support 6
When the excavation of 13 is completed, as shown in Fig.
, and complete the construction of that part of the tunnel.

なお、上述の実施例は、パイプ支保工6を、第4図に示
すように、隣接する支保工6同士を間隔を置くことなく
、相互に接触した状態で敷設した場合について述べたが
、地山2の状態などに応じて、第5図に示すように、ト
ンネル掘削方向に所定の間隔L2を形成する形で敷設す
るように構成することも当然可能である。なお、この場
合には隣接する支保工6.6間の地山2の崩壊を防止す
るために、必要に応じて地盤改良剤15などを注入して
周囲地山2を補強するようにする。
In addition, in the above-mentioned embodiment, as shown in FIG. Depending on the condition of the mountain 2, as shown in FIG. 5, it is of course possible to construct the tunnel so that it is laid at a predetermined interval L2 in the tunnel excavation direction. In this case, in order to prevent the collapse of the ground 2 between the adjacent supports 6.6, the surrounding ground 2 is reinforced by injecting a ground improvement agent 15 or the like as necessary.

なお、上述の実施例は、パイプ支保工6を。In addition, in the above-mentioned embodiment, the pipe support 6 is used.

第2図に示すように、トンネルの掘削方向(矢印六方向
)に対して直角な方向、即ちトンネル断面方向に平行に
敷設した場合について述べたが、パイプ支保工6の敷設
方向は、トンネルの断面方向に平行な方向に限らず1例
えば第10図に示すように、トンネル断面方向に対して
角度θだけ傾けた形で敷設することも可能である。こう
した方法を用いると、パイプ支保工6の敷設に際して、
掘削機11の発進位置を図中左端の切羽18部分から図
中斜め上方に向けて行なうことが可能となるので、先進
坑5を、掘削機11が発進した切羽18部分の反対側、
即ち掘削機11が到達する側の、第10図右側だけに設
ければよいので、極めて経済的な施工が可能となる。
As shown in Fig. 2, we have described the case where the pipe support 6 is laid in a direction perpendicular to the tunnel excavation direction (six arrow directions), that is, parallel to the tunnel cross-sectional direction. It is not limited to the direction parallel to the cross-sectional direction, but it is also possible to lay the tunnel in a direction inclined at an angle θ with respect to the cross-sectional direction of the tunnel, as shown in FIG. 10, for example. When using this method, when laying the pipe support 6,
Since the starting position of the excavator 11 can be directed diagonally upward in the figure from the leftmost part of the face 18 in the figure, the advanced shaft 5 can be moved to the side opposite to the part of the face 18 from which the excavator 11 started.
That is, since it is necessary to provide only the right side in FIG. 10, which is the side where the excavator 11 reaches, extremely economical construction is possible.

また、先進坑を、上記した他に、例えば、第11図に示
すように、トンネル1の両側及び上部に掘削しておき、
パイプ支保工6を先進坑3.17間及び17.5間に敷
設するようにすると、度に掘削機11により掘削する距
離が短くなるので、掘削機11によるパイプ支保工6の
敷設作業を容易かつ高精度に行なうことが出来る。
Further, in addition to the above-mentioned advanced shafts, for example, as shown in FIG.
When the pipe support 6 is laid between the advanced pits 3.17 and 17.5, the distance to be excavated by the excavator 11 each time is shortened, so the work of laying the pipe support 6 by the excavator 11 is facilitated. And it can be performed with high precision.

更に、上述の実施例は1本発明をトンネルの掘削に適用
した場合について述べたが、本発明はトンネルの掘削に
限らず、地山中に大断面の空間を掘削する必要の有る全
ての場合に適用が可能であり、地下鉄の駅部の構築、地
下空間の構築など各種の場合に施工が可能である。
Furthermore, although the above-mentioned embodiment describes a case in which the present invention is applied to tunnel excavation, the present invention is not limited to tunnel excavation, but can be applied to any case where it is necessary to excavate a space with a large cross section in the ground. It can be applied to various cases such as construction of subway stations and underground spaces.

また、パイプ支保工6を構成する鋼管パイプ7は断面が
円形のほかに、四角形など任意の形状のものが使用可能
である。
Further, the steel pipe 7 constituting the pipe support 6 may have a circular cross section or any other shape such as a rectangular cross section.

(g)0発明の詳細 な説明したように本発明によれば、地山を掘削してトン
ネルなどの掘削空間を構築する際に、2本の先進坑3.
5を、掘削すべきトンネル1などの掘削空間に沿って両
側に構築し、それら先進坑3.5間を接続する形で地山
2中にアーチ状にパイプ支保工6を掘削空間断面に沿う
形で複数個敷設し、それら敷設されたパイプ支保工6の
下部の地山2を掘削して掘削空間を形成するようにして
構成したので、地山2は、その掘削時には既にパイプ支
保工6により支持された状態となっているので、重機に
よる掘削を行なっても落盤などの危険性がなく、効率よ
く掘削作業を行なうことが出来る。また、パイプ支保工
6の敷設作業は先進坑3.5側で、地山の掘削作業は切
羽側で行なわれるので、従来、交互に行なわれてきた。
(g) 0 Detailed Description of the Invention According to the present invention, two advanced shafts 3.
5 are constructed on both sides along the excavation space such as the tunnel 1 to be excavated, and pipe supports 6 are arranged in an arch shape in the ground 2 along the cross section of the excavation space to connect these advanced shafts 3.5. The structure is such that a plurality of pipe supports 6 are laid in a shape, and the ground 2 under the laid pipe supports 6 is excavated to form an excavation space. Since it is in a state where it is supported by, there is no risk of cave-ins even when excavating with heavy equipment, and the excavation work can be carried out efficiently. Furthermore, since the work of laying the pipe support 6 is done on the advanced shaft 3.5 side and the work of excavating the ground is done on the face side, conventionally they have been done alternately.

切羽の掘削作業と支保工の構築作業を、同時並行的に行
なうことが可能となり、掘削空間の構築を効率よく行な
うことが出来る。
It becomes possible to perform the excavation work of the face and the construction work of the shoring at the same time, making it possible to construct the excavated space efficiently.

更に、地山を掘削してトンネルなどの掘削空間を構築す
る際に、1本の先進状5を、掘削すべきトンネル1など
の掘削空間に沿って構築し、前記先進状5の反対側の切
羽18部分から地山中に、前記掘削空間の掘削方向に対
して斜めに前記先進状5に向けて、アーチ状にパイプ支
保工6を掘削空間断面に沿う形で複数個敷設し、それら
敷設されたパイプ支保工6の下部の地山2を掘削して掘
削空間を形成するようにして構成すると、上記した効果
に加えて1本の先進状5により掘削空間の掘削が可能と
なり、極めて経済的な施工が可能となる。
Furthermore, when excavating the ground to construct an excavated space such as a tunnel, one advanced shape 5 is constructed along the excavated space such as the tunnel 1 to be excavated, and the advanced shape 5 is constructed on the opposite side of the advanced shape 5. A plurality of pipe supports 6 are laid in the ground from the face 18 part in an arch shape along the cross section of the excavation space, diagonally with respect to the excavation direction of the excavation space, toward the advanced shape 5. If the ground 2 at the bottom of the pipe support 6 is excavated to form an excavation space, in addition to the above-mentioned effects, it becomes possible to excavate the excavation space with one advanced structure 5, which is extremely economical. construction becomes possible.

また、地山を掘削して掘削空間を構築する際に、3本の
先進状3.5.17を、掘削すべき掘削空間に沿って両
側及び上部に構築し、そわら先進状3.17及び17.
5間を接続する形で地山中にアーチ状にパイプ支保工6
を掘削空間断面に沿う形で複数個敷設し、そわら敷設さ
れたパイプ支保工の下部の地山2を掘削して掘削空間を
形成するようにして構成すると、掘削機11により一度
に掘削する距離を短くすることが出来るので、パイプ支
保工6を精度よく容易に敷設することが出来る。
In addition, when excavating the ground and constructing an excavation space, three advanced shapes 3.5.17 are constructed on both sides and above the excavation space to be excavated, and the Sowara advanced shape 3.17 and 17.
Pipe shoring in an arch shape in the ground connecting between 5 and 6
If a plurality of pipes are laid along the cross-section of the excavated space, and the ground 2 below the pipe shoring that has been gently laid is excavated to form the excavated space, the distance excavated at one time by the excavator 11 is Since the length can be shortened, the pipe support 6 can be easily laid with high precision.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例が適用されたトンネル掘削現
場の断面図、 第2図は第1図の平面図。 第3図は第2図のパイプ支保工部の拡大図、第4図は第
1回のIV−IV線による断面図、第5図はパイプ支保
工の別の施工例を示す断面図。 第6図乃至第9図は本発明を用いたトンネルの掘削方法
の一例を示す図。 第10図は本発明の別の実施例が適用されたトンネルの
掘削現場の平面図。 第11図は本発明の別の実施例が適用されたトンネルの
掘削現場の断面図である。 第4図 1・・・・・・掘削空間(トンネル) 1a・・・・・・切羽 2・・・・地山 3.5.17・・・・・・先進状 6・・・・パイプ支保工 第5図 呂願人     三井建設株式会社 代理人  弁理士  相1) 伸二 第6図 U) 禰トーーーー
FIG. 1 is a sectional view of a tunnel excavation site to which an embodiment of the present invention is applied, and FIG. 2 is a plan view of FIG. 1. FIG. 3 is an enlarged view of the pipe shoring part in FIG. 2, FIG. 4 is a sectional view taken along the first line IV-IV, and FIG. 5 is a sectional view showing another example of pipe shoring construction. 6 to 9 are diagrams showing an example of a tunnel excavation method using the present invention. FIG. 10 is a plan view of a tunnel excavation site to which another embodiment of the present invention is applied. FIG. 11 is a sectional view of a tunnel excavation site to which another embodiment of the present invention is applied. Fig. 4 1...Excavation space (tunnel) 1a...Face 2...Ground 3.5.17...Advanced state 6...Pipe support Engineering Figure 5 Ro Ganto Mitsui Construction Co., Ltd. Agent Patent Attorney Phase 1) Shinji Figure 6 U) Neto

Claims (3)

【特許請求の範囲】[Claims] (1)、地山を掘削して掘削空間を構築する際に、2本
の先進坑を、掘削すべき掘削空間に沿って両側に構築し
、 それら先進坑間を接続する形で地山中にアーチ状にパイ
プ支保工を掘削空間断面に沿う形で複数個敷設し、 それら敷設されたパイプ支保工の下部の地山を掘削して
掘削空間を形成するようにして構成した掘削空間の構築
方法。
(1) When excavating the ground and constructing an excavation space, two advanced pits are constructed on both sides along the excavation space to be excavated, and these advanced pits are connected into the ground. A method for constructing an excavation space in which a plurality of pipe supports are laid in an arch shape along the cross section of the excavation space, and the ground beneath the laid pipe supports is excavated to form an excavation space. .
(2)、地山を掘削して掘削空間を構築する際に、1本
の先進坑を、掘削すべき掘削空間に沿って構築し、 前記先進坑の反対側の切羽部分から地山中に、前記掘削
空間の掘削方向に対して斜めに前記先進坑に向けて、ア
ーチ状にパイプ支保工を掘削空間断面に沿う形で複数個
敷設し、 それら敷設されたパイプ支保工の下部の地山を掘削して
掘削空間を形成するようにして構成した掘削空間の構築
方法。
(2) When excavating the ground to construct an excavation space, one advanced pit is constructed along the excavation space to be excavated, and from the face part on the opposite side of the advanced pit into the ground, A plurality of pipe supports are laid in an arch shape along the cross section of the excavation space toward the advanced shaft diagonally with respect to the excavation direction of the excavation space, and the ground beneath the laid pipe supports is A method of constructing an excavation space configured by excavating to form an excavation space.
(3)、地山を掘削して掘削空間を構築する際に、3本
の先進坑を、掘削すべき掘削空間に沿って両側及び上部
に構築し、 それら先進坑間を接続する形で地山中にアーチ状にパイ
プ支保工を掘削空間断面に沿う形で複数個敷設し、 それら敷設されたパイプ支保工の下部の地山を掘削して
掘削空間を形成するようにして構成した掘削空間の構築
方法。
(3) When excavating the ground and constructing an excavation space, three advanced pits are constructed on both sides and above the excavation space to be excavated, and these advanced pits are connected to each other. The excavation space is constructed by laying multiple arch-shaped pipe supports in the mountain along the cross section of the excavation space, and excavating the ground beneath the laid pipe supports to form the excavation space. Construction method.
JP2176741A 1990-07-04 1990-07-04 How to build a tunnel Expired - Fee Related JPH0781486B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2176741A JPH0781486B2 (en) 1990-07-04 1990-07-04 How to build a tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2176741A JPH0781486B2 (en) 1990-07-04 1990-07-04 How to build a tunnel

Publications (2)

Publication Number Publication Date
JPH0464697A true JPH0464697A (en) 1992-02-28
JPH0781486B2 JPH0781486B2 (en) 1995-08-30

Family

ID=16018988

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2176741A Expired - Fee Related JPH0781486B2 (en) 1990-07-04 1990-07-04 How to build a tunnel

Country Status (1)

Country Link
JP (1) JPH0781486B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07259477A (en) * 1994-03-23 1995-10-09 Tekken Constr Co Ltd Structure of tunnel, its construction and construction device
KR100399804B1 (en) * 2001-07-19 2003-09-29 (주)내경엔지니어링 Construction method for 2arch tunnel
JP2006322222A (en) * 2005-05-19 2006-11-30 Metropolitan Expressway Public Corp Construction method of large-sectional tunnel
JP2010090608A (en) * 2008-10-08 2010-04-22 Taisei Corp Method for constructing underground space and structure of the underground space
CN102518454A (en) * 2011-12-22 2012-06-27 中铁工程设计咨询集团有限公司 Grating device for underground excavation engineering and manufacture method
CN106640155A (en) * 2017-01-19 2017-05-10 中铁工程装备集团有限公司 Large-span underground space structure and construction method thereof
CN112962666A (en) * 2021-02-07 2021-06-15 北京市政路桥股份有限公司 Prefabricated pipe gallery moving device and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5374727A (en) * 1976-12-15 1978-07-03 Kajima Corp Underground cavity tunneling method
JPS5547200B2 (en) * 1977-01-21 1980-11-28
JPS57201493A (en) * 1981-06-03 1982-12-09 Kubota Ltd Construction of passage

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5374727A (en) * 1976-12-15 1978-07-03 Kajima Corp Underground cavity tunneling method
JPS5547200B2 (en) * 1977-01-21 1980-11-28
JPS57201493A (en) * 1981-06-03 1982-12-09 Kubota Ltd Construction of passage

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07259477A (en) * 1994-03-23 1995-10-09 Tekken Constr Co Ltd Structure of tunnel, its construction and construction device
KR100399804B1 (en) * 2001-07-19 2003-09-29 (주)내경엔지니어링 Construction method for 2arch tunnel
JP2006322222A (en) * 2005-05-19 2006-11-30 Metropolitan Expressway Public Corp Construction method of large-sectional tunnel
JP2010090608A (en) * 2008-10-08 2010-04-22 Taisei Corp Method for constructing underground space and structure of the underground space
CN102518454A (en) * 2011-12-22 2012-06-27 中铁工程设计咨询集团有限公司 Grating device for underground excavation engineering and manufacture method
CN106640155A (en) * 2017-01-19 2017-05-10 中铁工程装备集团有限公司 Large-span underground space structure and construction method thereof
CN112962666A (en) * 2021-02-07 2021-06-15 北京市政路桥股份有限公司 Prefabricated pipe gallery moving device and construction method

Also Published As

Publication number Publication date
JPH0781486B2 (en) 1995-08-30

Similar Documents

Publication Publication Date Title
JP4958035B2 (en) Shield roof construction method
JP4803429B2 (en) Construction method of underground cavity
CN107060803B (en) Tunnel construction method by utilizing pipe curtain grouting
CN109707399B (en) Tunnel exit supporting structure and construction method thereof
KR101244257B1 (en) Method for digging tunnel
JP2006322222A (en) Construction method of large-sectional tunnel
CN109026035A (en) Tunnel circumferential direction variable cross-section digs method
JPH0462292A (en) Diameter widening method and reducing method of tunnel
JPH035600A (en) Method and device for constructing branch and connection part of shield tunnel and its segment
JP4317322B2 (en) Arch support structure
JPH04343995A (en) Middle part covering structure of juxtaposed tunnels
JP3966334B2 (en) Method for forming communication part of parallel shield tunnel and its communication part structure
JPH0464697A (en) Construction of tunneling space
JP5012149B2 (en) Ground support structure and ground support method
KR100926501B1 (en) Roof and shield tunneling construction method (rsm) and tunnel structure
CN211116042U (en) Temporary supporting sheath arch for tunnel in upper soft and lower hard stratum
JP3121736B2 (en) Sidewall advanced method
JP2942874B2 (en) How to join tunnels
KR100601399B1 (en) Messer shield excavator apparatus with separated messer plate and excavation method using the same
JPH05280296A (en) Large scale underground structure and construction method thereof
JP4730608B2 (en) segment
JP2516582B2 (en) Tunnel construction method
CN115773135A (en) Large pipe shed space arrangement method for small curve segment shallow-buried underground excavation channel
JP6720765B2 (en) Construction method of large section tunnel
KR100558260B1 (en) Messer shield excavating apparatus and messer shield method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees