JP3121736B2 - Sidewall advanced method - Google Patents

Sidewall advanced method

Info

Publication number
JP3121736B2
JP3121736B2 JP06325676A JP32567694A JP3121736B2 JP 3121736 B2 JP3121736 B2 JP 3121736B2 JP 06325676 A JP06325676 A JP 06325676A JP 32567694 A JP32567694 A JP 32567694A JP 3121736 B2 JP3121736 B2 JP 3121736B2
Authority
JP
Japan
Prior art keywords
advanced
shaft
side wall
tunnel
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP06325676A
Other languages
Japanese (ja)
Other versions
JPH08184283A (en
Inventor
孝 酒井
満朗 肥後
義昭 石田
勝 中村
照夫 酒井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Komatsu Ltd
Maeda Corp
Sato Kogyo Co Ltd
Original Assignee
Komatsu Ltd
Maeda Corp
Sato Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Komatsu Ltd, Maeda Corp, Sato Kogyo Co Ltd filed Critical Komatsu Ltd
Priority to JP06325676A priority Critical patent/JP3121736B2/en
Publication of JPH08184283A publication Critical patent/JPH08184283A/en
Application granted granted Critical
Publication of JP3121736B2 publication Critical patent/JP3121736B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明はトンネル工法、特に本坑
施工前に導坑を先進させる側壁導坑先進工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel construction method and, more particularly, to a side-wall tunnel construction method for advancing a shaft before construction of a main shaft.

【0002】[0002]

【従来の技術】側壁導坑を施工する技術としては、矢板
工法やNATM(ニューオーストリアントンネリングメ
ソッド)による山岳工法と、トンネル円形断面のTBM
(トンネルボーリングマシーン)による工法との2つの
工法が考えられる。
2. Description of the Related Art Techniques for constructing a side wall tunnel include a mountain construction method using a sheet pile method, a NATM (New Austrian tunneling method), and a TBM having a circular cross section of a tunnel.
(Tunnel boring machine) and two other methods.

【0003】TBMによる側壁導坑の場合は、図7に示
すように、まず本坑50となるトンネル断面の両側壁下
部に円形の先進導坑51を掘削するものである。すなわ
ち、この工法では先進導坑を本坑の側壁下部に余掘り
(ハッチングの箇所)が掘削断面の半分程になるよう掘
削しておき、掘削箇所内に相対するコンクリート壁52
を構築し、これらコンクリート壁上にアーチ状のH鋼と
コンクリート吹付けによる支保は必要によってはこれに
加えて地盤改良のロックボルト54を打ちながら、設計
断面の本坑トンネル50を掘削していく。
[0003] In the case of a side wall tunnel using the TBM, as shown in FIG. 7, a circular advanced shaft 51 is first excavated at the lower part of both side walls of a tunnel section to become a main shaft 50. In other words, in this method, the advanced shaft is dug below the side wall of the main shaft so that the excess digging (hatched portion) is about half of the digging section, and the opposing concrete wall 52
The arched H-steel and concrete blasting on these concrete walls are used to support the concrete wall, and in addition to this, while excavating the ground improvement rock bolts 54, the main tunnel 50 having the designed cross section is excavated. .

【0004】[0004]

【発明が解決しようとする課題】しかし、上記山岳工法
による側壁導坑先進の場合、トンネル断面形状の設定に
任意性はあるものの、TBMに較べて掘削能率が悪く、
先進導坑の両側の壁に架けわたすアーチ状の支保の基礎
となるコンクリート壁を打設しなければならず、これの
型枠の設置や養生によって工期が長くなり、また掘削の
ための余掘り量やコンクリートの使用量が増大し、現在
では効率の悪い工法となっている。
However, in the case of the advanced side wall tunnel by the mountain method, although the setting of the tunnel sectional shape is arbitrary, the excavating efficiency is lower than that of the TBM.
A concrete wall that serves as a foundation for an arch-shaped support spanning the walls on both sides of the advanced shaft must be cast, and the installation and curing of this formwork lengthens the construction period, and also requires extra drilling for excavation The amount of concrete and the amount of concrete used has increased, and it is now an inefficient method of construction.

【0005】そこで、TBM工法による側壁導坑先進の
場合であるが、TBMのカッター面が円形であるため
に、本坑の断面に対してかなりの部分余掘するか、仮り
に本坑に内接して掘削するにも先進導坑が本坑に対して
点で内接するために、先進導坑が本坑支保を兼用するこ
とはできず先進導坑として有効性が期待できない。
[0005] Therefore, in the case of advanced side wall tunneling by the TBM method, since the cutter surface of the TBM is circular, a considerable portion is dug into the cross section of the main pit, or if the inside of the main pit is temporarily buried. Since the advanced shaft is inscribed at a point with the main shaft even when drilling in contact with the main shaft, the advanced shaft cannot be used as a support for the main shaft, and its effectiveness as an advanced shaft cannot be expected.

【0006】本発明では、上記従来工法の欠点を解消せ
んとしたものであり、その目的とするところは掘削効率
を上げ、安全性を確保するためにTBM工法やシールド
工法、またはこれらを兼ねるフルシールドTBM工法を
採用し、しかもこれら従来工法よりも余掘量を低くした
側壁導坑先進工法を提供せんとする。
In the present invention, the above-mentioned drawbacks of the conventional method have been solved. The object of the present invention is to increase the excavation efficiency and to secure safety by using a TBM method, a shield method, or a combination of these methods. The aim is to provide an advanced sidewall tunneling method that employs the shielded TBM method and has a reduced amount of excavation compared to these conventional methods.

【0007】本発明の他の目的は、本坑断面に対して点
ではなく、線状に内接した先進導坑を掘削することによ
り掘削量を低減して、しかも導坑の一部線状部分に本坑
の支保又は覆工部の一部を兼用できるようにした側壁導
坑先進工法を提供せんとする。
Another object of the present invention is to reduce the amount of excavation by excavating an advanced shaft that is inscribed in a line rather than a point with respect to the cross section of the shaft, and to reduce the amount of excavation. The aim is to provide a side wall tunnel advanced construction method that can be used as a part of the main shaft support or lining part.

【0008】[0008]

【課題を解決するための手段】本発明は上記の目的に基
づいてなされたものであり、その要旨は、本坑掘削前
に、当該本坑のトンネル断面の側壁付近に先進導坑を掘
削する側壁導坑先進工法において、前記先進導坑の側壁
部を前記本坑の側壁部とそれぞれの側壁断面がほぼ内接
して線状に重合するように、TBM,シールドマシー
ン,またはフルシールドTBMにおける円形カッタドラ
ムを掘進方向の左右いずれかに傾斜することで前記先進
導坑を縦長の楕円形断面に掘削することを特徴とする側
壁導坑先進工法にある。
SUMMARY OF THE INVENTION The present invention has been made based on the above object, and the gist of the present invention is to excavate an advanced shaft near the side wall of a tunnel section of the main pit before excavating the main pit. In the side wall shaft advanced construction method, the TBM and the shield machine are so constructed that the side wall of the advanced shaft is linearly overlapped with the side wall of the main shaft so that the respective cross sections of the side walls are substantially inscribed.
Or Cutter Cutter in Full Shield TBM
The advanced tunnel method is characterized in that the advanced tunnel is excavated into a vertically long elliptical cross section by inclining the shaft to the left or right in the excavation direction .

【0009】上記本坑の掘削工法には、機械掘削するも
のならば、TBM,NATMなどで代表される山岳工法
やシールド工法など工法の種類を問わないが、先進導坑
についてはTBM,シールドマシーン,フルシールドT
BM(TBMにシールドマシーンを兼ねたもの)におけ
る円形カッター面の左右のいずれかを掘進方向に傾斜さ
せることにより、トンネル断面を縦長の楕円形として掘
する。
[0009] In the drilling method of the above-mentioned Honko, if those that mechanical drilling, TBM, but not any type of construction methods, such as mountain method and shield method typified by such as NATM, advanced pilot tunnel
About TBM, Shield Machine , Full Shield T
The tunnel section is excavated as a vertically long elliptical shape by inclining either the left or right of the circular cutter surface in the BM (the TBM also serves as a shield machine) in the excavation direction .

【0010】また、上記先進導坑と本坑のそれぞれの側
壁両側の重合部分が線状になるとは、大円が小円を内接
している場合では点接触となるが、略大円に楕円形の小
円を内接すると重なる部分が線状になることを示し、こ
の線状に重なった部分をもって本坑を掘削していく。
[0010] When the overlapping portions on both sides of each of the advanced shaft and the main shaft become linear, point contact occurs when a great circle inscribes a small circle, but an ellipse is formed into a substantially large circle. When the small circle of the shape is inscribed, it shows that the overlapping part becomes linear, and the main pit is excavated with the linearly overlapping part.

【0011】本発明の別の特徴としては、前記先進導坑
の掘削による、該坑の側部重合部の支保工を後で掘削す
る本坑の側壁支保の一部を兼ねるようにしたことにあ
る。
Another feature of the present invention is that the support of the side overlapping portion of the advanced shaft by excavation of the advanced shaft is also used as a part of the side wall support of the main shaft to be excavated later. is there.

【0012】本発明の更に別の特徴としては、前記先進
導坑の掘削による、該坑の側部重合部の覆工を後に掘削
する本坑の側壁覆工の一部を兼ねるようにしたこと。
[0012] Still another feature of the present invention is that the lining of a side overlapping portion of the pit due to the excavation of the advanced shaft is also used as a part of the side wall lining of a main pit to be excavated later. .

【0013】[0013]

【作用】本発明では、まず設計の本坑トンネル側壁下部
に線状に重合状態で内接するように、TBMなどの円形
カッタドラムを掘進方向の左右いずれかに傾斜すること
で、縦長の楕円断面の先進導坑を掘削し、その先進導坑
の重合上端部間に接続して、支保又は覆工することによ
り、本坑の余掘りをできるだけなくし、先進導坑の一部
支保又は覆工が本坑のこれらの一部を兼ねるようにす
る。
According to the present invention, a circular shape such as a TBM is first inscribed in a linearly overlapping state at the lower part of the designed tunnel shaft side wall.
Incline the cutter drum to the left or right in the direction of excavation
Excavation of an advanced shaft with a vertically long elliptical cross-section, connecting between the overlapping upper ends of the advanced shaft, and supporting or lining it to minimize the overburden of the main shaft, Part supports or linings will also serve as part of these pits.

【0014】[0014]

【実施例】以下に本発明に用いる一例としてのTBMの
概略を図2乃至第4によって説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The outline of a TBM as an example used in the present invention will be described below with reference to FIGS.

【0015】TBM(A矢印)のカッタ面1に、多数の
切削カッタ2を配置し、この面は平面図で示すように左
にθ角傾斜した状態で電動モータ6で回転するカッタド
ラム3により、縦長楕円形断面の先進導坑を掘削できる
ようにしている。
A large number of cutting cutters 2 are arranged on a cutter surface 1 of a TBM (arrow A), and this surface is rotated by an electric motor 6 while being inclined to the left by an angle θ as shown in a plan view. It allows drilling of an advanced shaft with a vertical elliptical cross section.

【0016】カッタドラム3の後部のカッタヘッドサポ
ート7は、その左右を油圧シリンダ12,13により伸
縮可能とし、その伸長によってサポート14,15を坑
壁に圧接するようにしており、この左右のサポート1
4,15の圧接力を自動制御で調整することにより、カ
ッタヘッドを傾斜させて掘削することによりカッタヘッ
ドを左右方向にずれるのを抑えてトンネル線形を一定に
保つ。
The cutter head support 7 at the rear of the cutter drum 3 is configured such that its left and right sides can be expanded and contracted by hydraulic cylinders 12 and 13, and the supports 14 and 15 are pressed against the pit wall by the extension thereof. 1
By automatically adjusting the press-contact forces of 4 and 15, the cutter head is tilted and excavated to prevent the cutter head from shifting in the left-right direction, thereby keeping the tunnel alignment constant.

【0017】メインビーム11には、スラストジャッキ
4,5を介在してグリッパ8を連結し、グリッパ8はグ
リッパジャッキ9で伸縮可能にしている。
A gripper 8 is connected to the main beam 11 with thrust jacks 4 and 5 interposed therebetween, and the gripper 8 can be extended and contracted by a gripper jack 9.

【0018】一方、ボックス型のメインビーム11の中
に掘削ズリを搬送するためのベルトコンベヤ(図示せ
ず)が溝状に配設されている。
On the other hand, a belt conveyor (not shown) for transporting excavation debris into the box-shaped main beam 11 is provided in a groove shape.

【0019】なお、カッタヘッドサポート7の上部に
は、油圧シリンダ16を介してルーフサポート17があ
り、TBM掘進が上下に曲折しないようにしている。
A roof support 17 is provided above the cutter head support 7 via a hydraulic cylinder 16 to prevent the TBM excavation from bending up and down.

【0020】上記構成からなるTBMを用いた本発明で
ある側壁導坑先進工法を以下に説明する。
The advanced side wall tunneling method of the present invention using the TBM having the above-described structure will be described below.

【0021】まず、二車線以上の車道または路線の線路
としての比較的大口径の本坑トンネル計画路線に沿って
と施工する前に、本坑20のトンネル断面の両側壁下部
となる箇所に、側壁下部の一部と線状に重合するように
内接する縦長楕円形の先進導坑21,22を掘削する。
First, before constructing along a relatively large-diameter main shaft tunnel planned line as a two-lane or more lane or a line of a line, at a location which is to be a lower portion on both side walls of the tunnel cross section of the main shaft 20, Excavation of vertically long elliptical advanced shafts 21 and 22 inscribed so as to linearly overlap with a part of the lower part of the side wall.

【0022】掘削にあたっては、グリッパジャッキ9を
伸長してグリッパ8を坑壁19に圧接して反力を取り、
スラストジャッキ4,5の伸長力でカッタ面1を切羽に
押し付けて、カッタドラム3を電動モータ6で回転しな
がら、トンネルを掘進していく。スラストジャツキ4,
5が1ストローク分伸びると掘削を中断し、リヤーサポ
ート10を伸長・接地してから、グリッパ8を収縮して
から伸長しているスラストジャッキ4,5を収縮するこ
とにより、グリッパ8を前進させ、再びグリッパ8を伸
長して坑壁19に押し当ててからカッタドラム3を回転
させて掘進していく。
In excavation, the gripper jack 9 is extended to press the gripper 8 against the pit wall 19 to take a reaction force.
The cutter surface 1 is pressed against the face by the extension force of the thrust jacks 4 and 5, and the cutter drum 3 is rotated by the electric motor 6 to excavate the tunnel. Thrust jack 4,
When 5 is extended by one stroke, excavation is interrupted, the rear support 10 is extended and grounded, and then the gripper 8 is contracted, and then the extending thrust jacks 4 and 5 are contracted to advance the gripper 8. Then, the gripper 8 is again extended and pressed against the pit wall 19, and then the cutter drum 3 is rotated to excavate.

【0023】掘削したズリは、カッタドラム3によりす
くい上げられて、その先端がドラム内部に位置する第1
段コンベヤ11上に落下し、トンネル後方に排出され
る。
The excavated debris is scooped up by the cutter drum 3 and has a first end located inside the drum.
It falls on the step conveyor 11 and is discharged to the rear of the tunnel.

【0024】掘削されたトンネル(図1の)は、支保
工エレクタ(図示せず)によりH鋼を坑壁19の円周に
沿ってリング状に支保していき、その後H鋼を含む坑壁
面にコンクリートを吹き付ける。トンネル地盤の性状に
よっては、上記コンクリート吹き付けに代え、セグメン
トをエレクタ(図示せず)によってトンネル周方向に巻
回する(図1の)。
In the excavated tunnel (FIG. 1), the H steel is supported in a ring shape along the circumference of the pit wall 19 by a support erector (not shown), and thereafter the pit wall including the H steel is formed. Spray concrete. Depending on the properties of the tunnel ground, instead of the above-mentioned concrete spraying, the segments are wound in the circumferential direction of the tunnel by an erector (not shown) (see FIG. 1).

【0025】その後、本坑の掘削に際しては、上半部を
掘削していくが(図1の)、この掘削にしたがって先
進導坑21,22のセグメントまたは支保を撤去、ある
いはこれらをズリと共に切削しながら、本坑20の側壁
と重なる部分の両側壁の上端間をH鋼23で支保する
か、セグメント24を巻回していく(図1の,図6又
は図5)。
Thereafter, when excavating the main shaft, the upper half is excavated (FIG. 1), and the segments or supports of the advanced shafts 21 and 22 are removed according to the excavation, or these are cut together with the slip. Meanwhile, between the upper ends of both side walls of the portion overlapping with the side wall of the main shaft 20, the H steel 23 is supported or the segment 24 is wound (FIG. 1, FIG. 6 or FIG. 5).

【0026】続いて、本坑の下半部を掘削するが、この
場合の本坑インバート施工は、上記先進導坑のH鋼か、
セグメント24の両側壁の下端間にコンクリートを打設
していくか、PCコンクリート版を敷設していくことに
より行なう(図1の)。
Subsequently, the lower half of the main shaft is excavated. In this case, the invert construction of the main shaft is performed by using the H steel of the advanced shaft,
This is performed by placing concrete between the lower ends of both side walls of the segment 24 or laying a PC concrete slab (FIG. 1).

【0027】このようにして、本坑20の側壁部は先進
導坑21と重合する部分で兼用されており、残りは本坑
の上部と下部インバートを施工するだけでよい。
In this manner, the side wall of the main shaft 20 is also used as a portion overlapping with the advanced shaft 21, and the rest only needs to be constructed with the upper and lower inverts of the main shaft.

【0028】なお、上記H鋼および吹付けコンクリート
による支保、又はセグメントによる支保の上からコンク
リートによる二次覆工を行なうこともできる。
The secondary lining with concrete can be performed on the support with the H steel and the shotcrete or the support with the segments.

【0029】[0029]

【発明の効果】以上述べたように、上記構成からなる本
発明工法は、先進導坑側壁部を本坑側壁部に対してそれ
ぞれの壁断面がほぼ内接して線状に重ね合わせるよう
に、TBMなどの円形カッタドラムを左右のいずれかに
傾斜して掘削したので、以下のような効果が期待でき
る。
As described above, according to the method of the present invention having the above-described structure, the advanced shaft shaft side wall is shifted with respect to the main shaft side wall .
Each wall section is substantially inscribed so that superimposed linear
And a circular cutter drum such as TBM on either side
The following effects can be expected due to the excavation at an angle.

【0030】 先進導坑の一部と本坑側壁部の掘削ラ
インとを線状に合わせることができ、掘削ロス(底盤幅
確保のための余掘分)が生じない。
A part of the advanced shaft and the excavation line on the side wall of the main shaft can be linearly aligned, and no excavation loss (excessive excavation for securing the bottom width) does not occur.

【0031】 導坑支保(吹付+鋼製支保工、又はセ
グメント)を一部本坑側壁部支保と兼用できるため、経
済的である。
It is economical because a part of the shaft support (spray + steel support or segment) can also be partially used as the main shaft side wall support.

【0032】 従来TBMで、図7で示す先進導坑を
掘削し、その掘削部にコンクリート壁52を構築して、
その上部に支保を組み立てていく場合のように、コンク
リート壁52と支保の当接部におけるような最終構造物
に応力集中が生じず安定した構造物となる。なお、TB
Mの持つ急速施工性が発揮でき、機械掘削のため、肌落
ち等に対する安全性が向上する。
With the conventional TBM, an advanced shaft shown in FIG. 7 is excavated, and a concrete wall 52 is constructed in the excavated portion.
As in the case of assembling the support on the upper portion, a stable structure is obtained without stress concentration in the final structure such as the contact portion between the concrete wall 52 and the support. Note that TB
The rapid workability of M can be exhibited, and the safety against skin fall etc. is improved due to mechanical excavation.

【図面の簡単な説明】[Brief description of the drawings]

【図1】図1は、本発明工法の施工手段を示すトンネル
断面の説明図である。
FIG. 1 is an explanatory view of a tunnel section showing construction means of the method of the present invention.

【図2】図2は、本発明工法に用いるTBMの概略側面
図である。
FIG. 2 is a schematic side view of a TBM used in the method of the present invention.

【図3】図3は、図2の平面図である。FIG. 3 is a plan view of FIG. 2;

【図4】図4は、図2及び図3のカッタードラムの正面
図である。
FIG. 4 is a front view of the cutter drum shown in FIGS. 2 and 3;

【図5】図5は、本発明工法における先進導坑の一部
(セグメント)を本坑支保の一部に兼用した状態を示す
説明図である。
FIG. 5 is an explanatory view showing a state in which a part (segment) of an advanced shaft is used also as a part of a main shaft support in the method of the present invention.

【図6】図6は、先進導坑セグメントの上方に本坑の支
保を施工した一例を示す部分説明図である。
FIG. 6 is a partial explanatory view showing an example in which a main shaft support is constructed above an advanced shaft segment.

【図7】図7は、従来の側壁導坑先進工法のトンネル断
面の説明図である。
FIG. 7 is an explanatory view of a cross section of a tunnel in a conventional side wall shaft advanced construction method.

【符号の説明】[Explanation of symbols]

A TBM 1 カッタ面 4,5 スラストジャッキ 6 電動モータ 7 カッタヘッドサポート 8 グリッパ 10 リアサポート 19 先進導坑の坑壁 20 本坑 21,22 先進導坑 〜 本発明工法の手順 A TBM 1 cutter surface 4, 5 thrust jack 6 electric motor 7 cutter head support 8 gripper 10 rear support 19 advanced tunnel shaft 20 main shaft 21, 22 advanced shaft-procedure of the method of the present invention

───────────────────────────────────────────────────── フロントページの続き (73)特許権者 000201478 前田建設工業株式会社 東京都千代田区富士見2丁目10番26号 (72)発明者 酒井 孝 東京都文京区音羽2−10−2 音羽NS ビル7F 財団法人先端建設技術センタ ー内 (72)発明者 肥後 満朗 東京都港区北青山2−5−8 株式会社 間組内 (72)発明者 石田 義昭 東京都中央区日本橋本町四丁目12番20号 佐藤工業株式会社内 (72)発明者 中村 勝 大阪府枚方市上野3−1−1 株式会社 小松製作所大阪工場内 (72)発明者 酒井 照夫 東京都千代田区富士見二丁目10番26号 前田建設工業株式会社内 (56)参考文献 特開 平6−294279(JP,A) 特開 平4−353192(JP,A) (58)調査した分野(Int.Cl.7,DB名) E21D 9/00 E21D 13/00 - 13/04 E21D 11/40 ──────────────────────────────────────────────────続 き Continuing on the front page (73) Patent holder 000201478 Maeda Construction Industry Co., Ltd. 2-10-26 Fujimi, Chiyoda-ku, Tokyo (72) Inventor Takashi Sakai 2-10-2 Otowa, Bunkyo-ku, Tokyo Otowa NS Building 7F Inside the Advanced Construction Technology Center (72) Inventor Mitsuhiro Higo 2-5-8 Kitaaoyama, Minato-ku, Tokyo Inside Mazumi Co., Ltd. (72) Inventor Yoshiaki Ishida 4-12-20 Nihonbashi Honcho, Chuo-ku, Tokyo Inside Sato Kogyo Co., Ltd. (56) References JP-A-6-294279 (JP, A) JP-A-4-353192 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) E 21D 9/00 E21D 13/00-13/04 E21D 11/40

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 本坑掘削前に、当該本坑のトンネル断面
の側壁付近に先進導坑を掘削する側壁導坑先進工法にお
いて、 前記先進導坑の側壁部を前記本坑の側壁部とそれぞれの
側壁断面がほぼ内接して線状に重合するように、TB
M,シールドマシーン,またはフルシールドTBMにお
ける円形カッタドラムを掘進方向の左右いずれかに傾斜
することで前記先進導坑を縦長の楕円形断面に掘削する
ことを特徴とする側壁導坑先進工法。
1. A method for excavating an advanced shaft near a side wall of a tunnel cross section of a main shaft before excavating the main shaft, wherein a side wall portion of the advanced shaft is respectively connected to a side wall portion of the main shaft. TB so that the side wall cross-section of
M, shield machine or full shield TBM
The circular cutter drum to the left or right in the direction of excavation
And thereby excavating the advanced shaft into a vertically long elliptical cross section.
【請求項2】 前記先進導坑の掘削による、該坑の側部
重合部の支保工を後で掘削する本坑の側壁支保の一部を
兼ねるようにしたことを特徴とする請求項1に記載の側
壁導坑先進工法。
2. The method according to claim 1, wherein the support of the side overlap portion of the pit by excavation of the advanced shaft also serves as a part of a side wall support of the main pit to be excavated later. Sidewall tunnel advanced construction method described.
【請求項3】 前記先進導坑の掘削による、該坑の側部
重合部の覆工を後で掘削する本坑の側壁覆工の一部を兼
ねるようにしたことを特徴とする請求項1に記載の側壁
導坑先進工法。
3. The lining of a side overlap portion of the pit due to excavation of the advanced shaft is also used as a part of a side wall lining of a main pit to be excavated later. Sidewall advanced construction method described in 1.
JP06325676A 1994-12-27 1994-12-27 Sidewall advanced method Expired - Fee Related JP3121736B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP06325676A JP3121736B2 (en) 1994-12-27 1994-12-27 Sidewall advanced method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP06325676A JP3121736B2 (en) 1994-12-27 1994-12-27 Sidewall advanced method

Publications (2)

Publication Number Publication Date
JPH08184283A JPH08184283A (en) 1996-07-16
JP3121736B2 true JP3121736B2 (en) 2001-01-09

Family

ID=18179477

Family Applications (1)

Application Number Title Priority Date Filing Date
JP06325676A Expired - Fee Related JP3121736B2 (en) 1994-12-27 1994-12-27 Sidewall advanced method

Country Status (1)

Country Link
JP (1) JP3121736B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4915291B2 (en) * 2007-06-12 2012-04-11 株式会社大林組 Construction method and structure of concrete side wall
JP4915290B2 (en) * 2007-06-12 2012-04-11 株式会社大林組 Sidewall tunnel construction method and structure
JP6249620B2 (en) * 2013-03-27 2017-12-20 日本シビックコンサルタント株式会社 Widening tunnel construction method and widening shield machine
CN107130977B (en) * 2017-06-27 2023-10-10 长江勘测规划设计研究有限责任公司 Hollow guide excavation structure and excavation method for ultra-large span dome of underground nuclear reactor cavity
CN109162723A (en) * 2018-11-01 2019-01-08 中铁十八局集团有限公司 A kind of more pilot tunnel tunnel temporary steel support Demolition Construction methods of big cross section
CN112392496B (en) * 2020-10-20 2023-03-28 中铁隧道局集团有限公司 Method for drilling tunnel face by using TBM pipe shed drilling machine

Also Published As

Publication number Publication date
JPH08184283A (en) 1996-07-16

Similar Documents

Publication Publication Date Title
CN104196538A (en) Combined type double-shield tunneling machine
CN109026035A (en) Tunnel circumferential direction variable cross-section digs method
CN208885287U (en) Circumferential direction digs shield mechanism
CN109026034A (en) Circumferential direction digs shield mechanism and circumferential direction digs method
JP3121736B2 (en) Sidewall advanced method
JP4730610B2 (en) Tunnel excavation method and tunnel liner
US6315496B1 (en) Method of lining a tunnel and apparatus for performing the same
JPH0835391A (en) Preceding leg reinforcing type fore piling method by heading
KR100381669B1 (en) Head jacking shield tunneling apparatus and method
JP2833482B2 (en) Steel lining structure of tunnel
JP3076207B2 (en) Top shaft advanced construction method
JP2002266598A (en) Shield tunneling method, large-sectional tunnel, method for constructing the same, and shield machine
JP5012149B2 (en) Ground support structure and ground support method
JPH0464697A (en) Construction of tunneling space
RU2096621C1 (en) Method for driving deep tunnels in loose ground
KR100601399B1 (en) Messer shield excavator apparatus with separated messer plate and excavation method using the same
Bougard The mechanical pre-cutting method
KR200175135Y1 (en) Head jacking shield tunneling apparatus
Van Walsum Mechanical pre-cutting, a rediscovered tunneling technique
JPH08165895A (en) Excavating method for large-cross section tunnel
JPS6145036B2 (en)
JPH05156900A (en) Method and segment for lowering underground water level in constructing segment type tunnel
Hulme et al. Bored tunneling for Singapore metro
JP2520036B2 (en) Construction method of large section underground cavity and large section tunnel
SU1465584A1 (en) Method of constructing a tunnel under existing structure

Legal Events

Date Code Title Description
S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees