JPH08184283A - Advanced excavation work of guide tunnel in side wall - Google Patents

Advanced excavation work of guide tunnel in side wall

Info

Publication number
JPH08184283A
JPH08184283A JP6325676A JP32567694A JPH08184283A JP H08184283 A JPH08184283 A JP H08184283A JP 6325676 A JP6325676 A JP 6325676A JP 32567694 A JP32567694 A JP 32567694A JP H08184283 A JPH08184283 A JP H08184283A
Authority
JP
Japan
Prior art keywords
advanced
tunnel
side wall
excavated
side walls
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6325676A
Other languages
Japanese (ja)
Other versions
JP3121736B2 (en
Inventor
Takashi Sakai
孝 酒井
Mitsuo Higo
満朗 肥後
Yoshiaki Ishida
義昭 石田
Masaru Nakamura
勝 中村
Teruo Sakai
照夫 酒井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Komatsu Ltd
Maeda Corp
Sato Kogyo Co Ltd
Hazama Ando Corp
Advanced Construction Technology Center ACTEC
Original Assignee
Hazama Gumi Ltd
Komatsu Ltd
Maeda Corp
Sato Kogyo Co Ltd
Advanced Construction Technology Center ACTEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd, Komatsu Ltd, Maeda Corp, Sato Kogyo Co Ltd, Advanced Construction Technology Center ACTEC filed Critical Hazama Gumi Ltd
Priority to JP06325676A priority Critical patent/JP3121736B2/en
Publication of JPH08184283A publication Critical patent/JPH08184283A/en
Application granted granted Critical
Publication of JP3121736B2 publication Critical patent/JP3121736B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE: To dispense with overbreak, by excavating advanced guide tunnels so as to make vertically long elliptical forms so that the advanced guide tunnels are superposed with the main tunnel side wall in the peripheral lines. CONSTITUTION: Vertically long elliptic advanced guide tunnels 21, 22 inscribing a part of the lower part of the side wall so as to superpose with each other in the peripheral line, are excavated at the lower positions of both side walls of the main tunnel 20 section. The excavated tunnel 1 is supported to form a ring along the circumstance of the tunnel wall by H-shaped steels and protected by sprayed concrete on the wall face. Thereafter, on excavating the main tunnel, the space between the upper ends of both side walls of the superposed parts of the main tunnel side walls is supported by H-shaped steel members or wound with segments 4, while the segments or supports of the advanced guide tunnels 21, 22 are re moved or cut with muck in parallel with excavation of the upper half. Subsequently, on constructing the main tunnel invert in excavation of the lower half, the H-shaped members of the advanced tunnels are used or concrete is placed between the lower ends of both side walls of segments or PC concrete slabs are laid down. In this way, the side walls of the main tunnel are used in common at the superposed part with the advanced tunnels and only the upper part and the lower invert part as the rest may be excavated.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はトンネル工法、特に本坑
施工前に導坑を先進させる側壁導坑先進工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel construction method, and more particularly, to a sidewall guideway advanced construction method for advancing a guideway before the main shaft construction.

【0002】[0002]

【従来の技術】側壁導坑を施工する技術としては、矢板
工法やNATM(ニューオーストリアントンネリングメ
ソッド)による山岳工法と、トンネル円形断面のTBM
(トンネルボーリングマシーン)による工法との2つの
工法が考えられる。
2. Description of the Related Art As a technique for constructing a side wall tunnel, a sheet pile method, a mountain construction method by NATM (New Austrian tunneling method), and a TBM with a circular tunnel section are used.
There are two possible construction methods, the (tunnel boring machine) construction method.

【0003】TBMによる側壁導坑の場合は、図7に示
すように、まず本坑50となるトンネル断面の両側壁下
部に円形の先進導坑51を掘削するものである。すなわ
ち、この工法では先進導坑を本坑の側壁下部に余掘り
(ハッチングの箇所)が掘削断面の半分程になるよう掘
削しておき、掘削箇所内に相対するコンクリート壁52
を構築し、これらコンクリート壁上にアーチ状のH鋼と
コンクリート吹付けによる支保は必要によってはこれに
加えて地盤改良のロックボルト54を打ちながら、設計
断面の本坑トンネル50を掘削していく。
In the case of a side wall tunnel by TBM, as shown in FIG. 7, first, a circular advanced tunnel 51 is excavated at the lower portions of both side walls of the tunnel section which becomes the main tunnel 50. That is, in this method, the advanced tunnel is excavated in the lower part of the side wall of the main shaft so that the overexcavation (hatching point) is about half of the excavation section, and the concrete wall 52 facing the excavation point
The construction of the main tunnel 50 with the designed cross section is performed by building an arched H steel and supporting concrete by spraying concrete on these concrete walls, in addition to this, striking rock bolts 54 for ground improvement. .

【0004】[0004]

【発明が解決しようとする課題】しかし、上記山岳工法
による側壁導坑先進の場合、トンネル断面形状の設定に
任意性はあるものの、TBMに較べて掘削能率が悪く、
先進導坑の両側の壁に架けわたすアーチ状の支保の基礎
となるコンクリート壁を打設しなければならず、これの
型枠の設置や養生によって工期が長くなり、また掘削の
ための余掘り量やコンクリートの使用量が増大し、現在
では効率の悪い工法となっている。
However, in the case of the side wall digging advanced by the above-mentioned mountain construction method, although the tunnel cross-sectional shape is arbitrary, the excavation efficiency is lower than that of the TBM,
It is necessary to place concrete walls that form the basis of arch-shaped supports spanning the walls on both sides of the advanced tunnel, and the construction period of this formwork and curing will prolong the construction period. The amount of waste and the amount of concrete used have increased, and the method is now inefficient.

【0005】そこで、TBM工法による側壁導坑先進の
場合であるが、TBMのカッター面が円形であるため
に、本坑の断面に対してかなりの部分余掘するか、仮り
に本坑に内接して掘削するにも先進導坑が本坑に対して
点で内接するために、先進導坑が本坑支保を兼用するこ
とはできず先進導坑として有効性が期待できない。
Therefore, in the case of the side wall mine advanced by the TBM method, since the cutter surface of the TBM is circular, a considerable part of the cross section of the main mine is overexposed, or if it is temporarily laid inside the main pit. Even when excavating in contact, the advanced guideway is inscribed at a point with respect to the main shaft, so the advanced guideway cannot also serve as the main shaft support, and the effectiveness as the advanced guideway cannot be expected.

【0006】本発明では、上記従来工法の欠点を解消せ
んとしたものであり、その目的とするところは掘削効率
を上げ、安全性を確保するためにTBM工法やシールド
工法、またはこれらを兼ねるフルシールドTBM工法を
採用し、しかもこれら従来工法よりも余掘量を低くした
側壁導坑先進工法を提供せんとする。
The present invention is intended to solve the above-mentioned drawbacks of the conventional method, and its purpose is to improve the excavation efficiency and ensure the safety, or the TBM method or the shield method, or a full-scale method that combines these methods. The shield TBM method is adopted, and the side wall digging advanced method with the amount of excess digging lower than these conventional methods is provided.

【0007】本発明の他の目的は、本坑断面に対して点
ではなく、線状に内接した先進導坑を掘削することによ
り掘削量を低減して、しかも導坑の一部線状部分に本坑
の支保又は覆工部の一部を兼用できるようにした側壁導
坑先進工法を提供せんとする。
Another object of the present invention is to reduce the amount of excavation by excavating an advanced guideway that is inscribed linearly instead of a point with respect to the section of the main shaft. The side wall tunnel advanced construction method, which can be used as part of the support or lining of the main pit, will be provided.

【0008】[0008]

【課題を解決するための手段】本発明は上記の目的に基
づいてなされたものであり、その要旨は、本坑掘削前
に、当該本坑のトンネル断面の側壁付近に先進導坑を掘
削する側壁導坑先進工法において、前記先進導坑の側壁
部を前記本坑の側壁部とそれぞれの側壁断面が内接して
線状に重合するように、該先進導坑を縦長の楕円形断面
に掘削することを特徴とする側壁導坑先進工法にある。
The present invention has been made based on the above object, and the gist thereof is to excavate an advanced tunnel near the side wall of the tunnel section of the main shaft before excavating the main shaft. In the sidewall guideway advanced construction method, the advanced guideway is excavated into a vertically elongated elliptical cross section so that the side wall portion of the advanced guideway and the side wall section of the main shaft are inscribed and linearly overlap each other. It is in the advanced method of side wall tunneling.

【0009】上記先進導坑や本坑の掘削工法には、機械
掘削するものならば、TBM,NATMなどで代表され
る山岳工法やシールド工法など工法の種類を問わない
が、TBM,シールド,フルシールドTBM(TBMに
シールドマシーンを兼ねたもの)における円形カッター
面の左右のいずれかを掘進方向に傾斜させることによ
り、トンネル断面を縦長の楕円形として掘削する工法が
好適である。
As for the method of excavating the above-mentioned advanced tunnel or main shaft, if it is a machine excavation, there is no limitation on the type of method such as the mountain construction method represented by TBM, NATM or the shield construction method. A method of excavating the tunnel cross section as a vertically elongated elliptical shape by inclining either the left or right of the circular cutter surface of the shield TBM (which also serves as a shield machine for the TBM) is suitable.

【0010】また、上記先進導坑と本坑のそれぞれの側
壁両側の重合部分が線状になるとは、大円が小円を内接
している場合では点接触となるが、略大円に楕円形の小
円を内接すると重なる部分が線状になることを示し、こ
の線状に重なった部分をもって本坑を掘削していく。
In addition, the fact that the overlapping portions on both side walls of the advanced tunnel and the main tunnel are linear means that when the large circle is inscribed in the small circle, it is point contact, but it is an ellipse into a substantially large circle. It is shown that when the small circle of the shape is inscribed, the overlapping part becomes linear, and the main shaft is excavated with this linearly overlapping part.

【0011】本発明の別の特徴としては、前記先進導坑
の掘削による、該坑の側部重合部の支保工を後で掘削す
る本坑の側壁支保の一部を兼ねるようにしたことにあ
る。
Another feature of the present invention is that the excavation of the advanced tunnel also serves as a part of the side wall support of the main shaft for excavating the lateral overlapping portion of the shaft. is there.

【0012】本発明の更に別の特徴としては、前記先進
導坑の掘削による、該坑の側部重合部の覆工を後に掘削
する本坑の側壁覆工の一部を兼ねるようにしたこと。
Still another feature of the present invention is that the excavation of the advanced tunnel also serves as a part of the side wall lining of the main tunnel which is subsequently excavated for the lining of the side overlapped portion of the tunnel. .

【0013】[0013]

【作用】本発明では、まず設計の本坑トンネル側壁下部
に線状に重合状態で内接して縦長の楕円断面の先進導坑
を掘削し、その先進導坑の重合上端部間に接続して、支
保又は覆工することにより、本坑の余掘りをできるだけ
なくし、先進導坑の一部支保又は覆工が本坑のこれらの
一部を兼ねるようにする。
In the present invention, first, an advanced tunnel having a vertically elongated elliptical cross section is excavated in a linearly overlapped state in the lower part of the side wall of the main tunnel of the design, and connected between the superposed upper ends of the advanced tunnel. , By supporting or lining the main pit, the excess digging of the main pit should be eliminated as much as possible so that a part of the advanced guide pit or lining also serves as a part of the main pit.

【0014】[0014]

【実施例】以下に本発明に用いる一例としてのTBMの
概略を図2乃至第4によって説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An outline of a TBM as an example used in the present invention will be described below with reference to FIGS.

【0015】TBM(A矢印)のカッタ面1に、多数の
切削カッタ2を配置し、この面は平面図で示すように左
にθ角傾斜した状態で電動モータ6で回転するカッタド
ラム3により、縦長楕円形断面の先進導坑を掘削できる
ようにしている。
A large number of cutting cutters 2 are arranged on the cutter surface 1 of the TBM (arrow A), and this surface is inclined by an angle θ to the left by a cutter drum 3 rotated by an electric motor 6 as shown in the plan view. , It is possible to excavate an advanced tunnel with an oval cross section.

【0016】カッタドラム3の後部のカッタヘッドサポ
ート7は、その左右を油圧シリンダ12,13により伸
縮可能とし、その伸長によってサポート14,15を坑
壁に圧接するようにしており、この左右のサポート1
4,15の圧接力を自動制御で調整することにより、カ
ッタヘッドを傾斜させて掘削することによりカッタヘッ
ドを左右方向にずれるのを抑えてトンネル線形を一定に
保つ。
The cutter head support 7 at the rear part of the cutter drum 3 can be expanded and contracted on the left and right sides by hydraulic cylinders 12 and 13, and the supports 14 and 15 are pressed against the pit wall by the extension thereof. 1
By adjusting the pressure contact forces of 4 and 15 by automatic control, tilting the cutter head to excavate the cutter head and suppressing the displacement of the cutter head in the left-right direction, the tunnel alignment is kept constant.

【0017】メインビーム11には、スラストジャッキ
4,5を介在してグリッパ8を連結し、グリッパ8はグ
リッパジャッキ9で伸縮可能にしている。
A gripper 8 is connected to the main beam 11 with thrust jacks 4 and 5 interposed therebetween, and the gripper 8 can be expanded and contracted by a gripper jack 9.

【0018】一方、ボックス型のメインビーム11の中
に掘削ズリを搬送するためのベルトコンベヤ(図示せ
ず)が溝状に配設されている。
On the other hand, in the box-shaped main beam 11, a belt conveyor (not shown) for transporting the excavation gap is arranged in a groove shape.

【0019】なお、カッタヘッドサポート7の上部に
は、油圧シリンダ16を介してルーフサポート17があ
り、TBM掘進が上下に曲折しないようにしている。
A roof support 17 is provided above the cutter head support 7 via a hydraulic cylinder 16 to prevent the TBM excavation from bending up and down.

【0020】上記構成からなるTBMを用いた本発明で
ある側壁導坑先進工法を以下に説明する。
The side wall tunneling advanced method of the present invention, which uses the TBM having the above structure, will be described below.

【0021】まず、二車線以上の車道または路線の線路
としての比較的大口径の本坑トンネル計画路線に沿って
と施工する前に、本坑20のトンネル断面の両側壁下部
となる箇所に、側壁下部の一部と線状に重合するように
内接する縦長楕円形の先進導坑21,22を掘削する。
First, before construction is carried out along a relatively large-diameter main tunnel tunnel planned route as a roadway of two or more lanes or a route, at a location which becomes lower parts of both side walls of the tunnel section of the main tunnel 20, The vertically elongated elliptical advanced tunnels 21 and 22 are inscribed so as to linearly overlap with a part of the lower portion of the side wall.

【0022】掘削にあたっては、グリッパジャッキ9を
伸長してグリッパ8を坑壁19に圧接して反力を取り、
スラストジャッキ4,5の伸長力でカッタ面1を切羽に
押し付けて、カッタドラム3を電動モータ6で回転しな
がら、トンネルを掘進していく。スラストジャツキ4,
5が1ストローク分伸びると掘削を中断し、リヤーサポ
ート10を伸長・接地してから、グリッパ8を収縮して
から伸長しているスラストジャッキ4,5を収縮するこ
とにより、グリッパ8を前進させ、再びグリッパ8を伸
長して坑壁19に押し当ててからカッタドラム3を回転
させて掘進していく。
When excavating, the gripper jack 9 is extended to press the gripper 8 against the pit wall 19 to take a reaction force,
The cutter face 1 is pressed against the face by the extension force of the thrust jacks 4 and 5, and the tunnel is advanced while the cutter drum 3 is rotated by the electric motor 6. Thrust jack 4,
When 5 extends by one stroke, excavation is interrupted, the rear support 10 is extended and grounded, the gripper 8 is contracted, and then the thrust jacks 4 and 5 that are extended are contracted to advance the gripper 8. Then, the gripper 8 is extended again and pressed against the pit wall 19, and then the cutter drum 3 is rotated to advance.

【0023】掘削したズリは、カッタドラム3によりす
くい上げられて、その先端がドラム内部に位置する第1
段コンベヤ11上に落下し、トンネル後方に排出され
る。
The excavated slit is scooped up by the cutter drum 3 and the tip thereof is located inside the drum.
It drops onto the corrugated conveyor 11 and is discharged to the rear of the tunnel.

【0024】掘削されたトンネル(図1の)は、支保
工エレクタ(図示せず)によりH鋼を坑壁19の円周に
沿ってリング状に支保していき、その後H鋼を含む坑壁
面にコンクリートを吹き付ける。トンネル地盤の性状に
よっては、上記コンクリート吹き付けに代え、セグメン
トをエレクタ(図示せず)によってトンネル周方向に巻
回する(図1の)。
In the excavated tunnel (shown in FIG. 1), H steel is supported in a ring shape along the circumference of the pit wall 19 by a supporting erector (not shown), and then the pit wall containing H steel. Spray concrete onto. Depending on the property of the tunnel ground, instead of concrete spraying, the segment is wound in the tunnel circumferential direction by an erector (not shown) (in FIG. 1).

【0025】その後、本坑の掘削に際しては、上半部を
掘削していくが(図1の)、この掘削にしたがって先
進導坑21,22のセグメントまたは支保を撤去、ある
いはこれらをズリと共に切削しながら、本坑20の側壁
と重なる部分の両側壁の上端間をH鋼23で支保する
か、セグメント24を巻回していく(図1の,図6又
は図5)。
After that, when excavating the main shaft, the upper half part is excavated (FIG. 1), but according to this excavation, the segments or supports of the advanced tunnels 21 and 22 are removed or they are cut together with the slit. Meanwhile, the H steel 23 is used to support the upper ends of the both side walls of the portion that overlaps the side wall of the main shaft 20 or the segment 24 is wound (FIG. 1, FIG. 6 or FIG. 5).

【0026】続いて、本坑の下半部を掘削するが、この
場合の本坑インバート施工は、上記先進導坑のH鋼か、
セグメント24の両側壁の下端間にコンクリートを打設
していくか、PCコンクリート版を敷設していくことに
より行なう(図1の)。
Subsequently, the lower half of the main shaft is excavated. In this case, the main shaft invert construction is carried out by using the H steel of the above-mentioned advanced shaft,
This is done by placing concrete between the lower ends of both side walls of the segment 24 or by laying a PC concrete slab (see FIG. 1).

【0027】このようにして、本坑20の側壁部は先進
導坑21と重合する部分で兼用されており、残りは本坑
の上部と下部インバートを施工するだけでよい。
In this way, the side wall portion of the main shaft 20 is also used as a portion that overlaps with the advanced guide shaft 21, and the rest only needs to be constructed by the upper and lower inverts of the main shaft.

【0028】なお、上記H鋼および吹付けコンクリート
による支保、又はセグメントによる支保の上からコンク
リートによる二次覆工を行なうこともできる。
It is also possible to carry out secondary lining with concrete from the support with the H steel and sprayed concrete, or the support with segments.

【0029】[0029]

【発明の効果】以上述べたように、上記構成からなる本
発明工法は、先進導坑と本坑側壁部とをトンネル周方向
に線状に重ね合わせたので、以下のような効果が期待で
きる。
As described above, in the method of the present invention having the above structure, the advanced tunnel and the side wall of the main tunnel are linearly overlapped in the tunnel circumferential direction, and therefore the following effects can be expected. .

【0030】 先進導坑の一部と本坑側壁部の掘削ラ
インとを線状に合わせることができ、掘削ロス(底盤幅
確保のための余掘分)が生じない。
A part of the advanced tunnel and the excavation line on the side wall of the main tunnel can be aligned linearly, and excavation loss (excess excavation for securing the bottom plate width) does not occur.

【0031】 導坑支保(吹付+鋼製支保工、又はセ
グメント)を一部本坑側壁部支保と兼用できるため、経
済的である。
It is economical because part of the guide shaft support (spraying + steel support or segment) can also be used as the main shaft side wall support.

【0032】 従来TBMで、図7で示す先進導坑を
掘削し、その掘削部にコンクリート壁52を構築して、
その上部に支保を組み立てていく場合のように、コンク
リート壁52と支保の当接部におけるような最終構造物
に応力集中が生じず安定した構造物となる。なお、TB
Mの持つ急速施工性が発揮でき、機械掘削のため、肌落
ち等に対する安全性が向上する。
With the conventional TBM, the advanced tunnel shown in FIG. 7 is excavated, and the concrete wall 52 is constructed in the excavated portion,
As in the case of assembling the support on the upper part of the concrete wall 52, the final structure such as the contact portion between the concrete wall 52 and the support does not have stress concentration, and the structure is stable. In addition, TB
M's rapid workability can be exhibited, and machine excavation improves safety against skin loss.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1は、本発明工法の施工手段を示すトンネル
断面の説明図である。
FIG. 1 is an explanatory view of a tunnel cross section showing a construction means of a method of the present invention.

【図2】図2は、本発明工法に用いるTBMの概略側面
図である。
FIG. 2 is a schematic side view of a TBM used in the method of the present invention.

【図3】図3は、図2の平面図である。FIG. 3 is a plan view of FIG.

【図4】図4は、図2及び図3のカッタードラムの正面
図である。
FIG. 4 is a front view of the cutter drum of FIGS. 2 and 3.

【図5】図5は、本発明工法における先進導坑の一部
(セグメント)を本坑支保の一部に兼用した状態を示す
説明図である。
FIG. 5 is an explanatory view showing a state in which a part (segment) of the advanced tunnel in the method of the present invention is also used as a part of the main shaft support.

【図6】図6は、先進導坑セグメントの上方に本坑の支
保を施工した一例を示す部分説明図である。
FIG. 6 is a partial explanatory view showing an example in which the main shaft is supported above the advanced tunnel segment.

【図7】図7は、従来の側壁導坑先進工法のトンネル断
面の説明図である。
FIG. 7 is an explanatory view of a tunnel cross section of a conventional sidewall digging advanced method.

【符号の説明】[Explanation of symbols]

A TBM 1 カッタ面 4,5 スラストジャッキ 6 電動モータ 7 カッタヘッドサポート 8 グリッパ 10 リアサポート 19 先進導坑の坑壁 20 本坑 21,22 先進導坑 〜 本発明工法の手順 A TBM 1 Cutter surface 4, 5 Thrust jack 6 Electric motor 7 Cutter head support 8 Gripper 10 Rear support 19 Advanced tunnel shaft wall 20 Main shaft 21, 22 Advanced shaft ~ Procedure of the method of the present invention

───────────────────────────────────────────────────── フロントページの続き (71)出願人 000201478 前田建設工業株式会社 東京都千代田区富士見2丁目10番26号 (72)発明者 酒井 孝 東京都文京区音羽2−10−2 音羽NSビ ル7F 財団法人先端建設技術センター内 (72)発明者 肥後 満朗 東京都港区北青山2−5−8 株式会社間 組内 (72)発明者 石田 義昭 東京都中央区日本橋本町四丁目12番20号 佐藤工業株式会社内 (72)発明者 中村 勝 大阪府枚方市上野3−1−1 株式会社小 松製作所大阪工場内 (72)発明者 酒井 照夫 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 ─────────────────────────────────────────────────── ─── Continued Front Page (71) Applicant 000201478 Maeda Construction Co., Ltd. 2-1026 Fujimi, 2-chome, Chiyoda-ku, Tokyo (72) Inventor Takashi Sakai 2-10-2 Otowa NS Bunkyo-ku, Tokyo Otowa NS Building 7F Inside Advanced Technology Center (72) Inventor Mitsuro Higo 2-5-8 Kitaoaoyama, Minato-ku, Tokyo Incorporation (72) Inventor Yoshiaki Ishida 4-12-20 Nihonbashihoncho, Chuo-ku, Tokyo Sato Industry Co., Ltd. (72) Inventor Masaru Nakamura 3-1-1 Ueno, Hirakata-shi, Osaka Komatsu Ltd. Osaka Plant (72) Teruo Sakai, Fujimi 2-1026, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 本坑掘削前に、当該本坑のトンネル断面
の側壁付近に先進導坑を掘削する側壁導坑先進工法にお
いて、 前記先進導坑の側壁部を前記本坑の側壁部とそれぞれの
側壁断面がほぼ内接して線状に重合するように、該先進
導坑を縦長の楕円形断面に掘削することを特徴とする側
壁導坑先進工法。
1. A sidewall guideway advanced construction method for excavating an advanced guideway near a sidewall of a tunnel cross section of the main shaft before excavating the main shaft, wherein a side wall portion of the advanced guide shaft and a side wall portion of the main shaft are respectively formed. A method for advanced side wall pit construction, wherein the advanced pit is excavated in a vertically elongated elliptical cross-section so that the side wall cross-sections of the above are substantially inscribed and polymerized linearly.
【請求項2】 前記先進導坑の掘削による、該坑の側部
重合部の支保工を後で掘削する本坑の側壁支保の一部を
兼ねるようにしたことを特徴とする請求項1に記載の側
壁導坑先進工法。
2. The support of the side overlapped portion of the advanced tunnel by excavation is also used as a part of the side wall support of the main tunnel to be excavated later. Described side wall mine advanced construction method.
【請求項3】 前記先進導坑の掘削による、該坑の側部
重合部の覆工を後で掘削する本坑の側壁覆工の一部を兼
ねるようにしたことを特徴とする請求項1に記載の側壁
導坑先進工法。
3. The lining of the side overlapped portion of the advanced tunnel due to excavation of the advanced tunnel also serves as a part of the side wall lining of the main pit to be subsequently drilled. The advanced method of side wall tunneling described in.
JP06325676A 1994-12-27 1994-12-27 Sidewall advanced method Expired - Fee Related JP3121736B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP06325676A JP3121736B2 (en) 1994-12-27 1994-12-27 Sidewall advanced method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP06325676A JP3121736B2 (en) 1994-12-27 1994-12-27 Sidewall advanced method

Publications (2)

Publication Number Publication Date
JPH08184283A true JPH08184283A (en) 1996-07-16
JP3121736B2 JP3121736B2 (en) 2001-01-09

Family

ID=18179477

Family Applications (1)

Application Number Title Priority Date Filing Date
JP06325676A Expired - Fee Related JP3121736B2 (en) 1994-12-27 1994-12-27 Sidewall advanced method

Country Status (1)

Country Link
JP (1) JP3121736B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008308836A (en) * 2007-06-12 2008-12-25 Ohbayashi Corp Construction method for concrete sidewall and its structure
JP2008308835A (en) * 2007-06-12 2008-12-25 Ohbayashi Corp Construction method for sidewall pilot tunnel type tunnel and its structure
JP2014190038A (en) * 2013-03-27 2014-10-06 Nippon Civic Engineering Consultant Co Ltd Widening tunnel construction method and widening shield machine
CN107130977A (en) * 2017-06-27 2017-09-05 长江勘测规划设计研究有限责任公司 Super-span dome hollow be oriented in underground nuclear reactor cavern excavates structure and excavation method
CN109162723A (en) * 2018-11-01 2019-01-08 中铁十八局集团有限公司 A kind of more pilot tunnel tunnel temporary steel support Demolition Construction methods of big cross section
CN112392496A (en) * 2020-10-20 2021-02-23 中铁隧道局集团有限公司 Method for drilling tunnel face by using TBM pipe shed drilling machine

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008308836A (en) * 2007-06-12 2008-12-25 Ohbayashi Corp Construction method for concrete sidewall and its structure
JP2008308835A (en) * 2007-06-12 2008-12-25 Ohbayashi Corp Construction method for sidewall pilot tunnel type tunnel and its structure
JP2014190038A (en) * 2013-03-27 2014-10-06 Nippon Civic Engineering Consultant Co Ltd Widening tunnel construction method and widening shield machine
CN107130977A (en) * 2017-06-27 2017-09-05 长江勘测规划设计研究有限责任公司 Super-span dome hollow be oriented in underground nuclear reactor cavern excavates structure and excavation method
CN107130977B (en) * 2017-06-27 2023-10-10 长江勘测规划设计研究有限责任公司 Hollow guide excavation structure and excavation method for ultra-large span dome of underground nuclear reactor cavity
CN109162723A (en) * 2018-11-01 2019-01-08 中铁十八局集团有限公司 A kind of more pilot tunnel tunnel temporary steel support Demolition Construction methods of big cross section
CN112392496A (en) * 2020-10-20 2021-02-23 中铁隧道局集团有限公司 Method for drilling tunnel face by using TBM pipe shed drilling machine

Also Published As

Publication number Publication date
JP3121736B2 (en) 2001-01-09

Similar Documents

Publication Publication Date Title
CN105041328B (en) It is a kind of for big horse-shoe tunnel can cast-in-place supporting shield machine
CN208885287U (en) Circumferential direction digs shield mechanism
CN109026035A (en) Tunnel circumferential direction variable cross-section digs method
JPH08184283A (en) Advanced excavation work of guide tunnel in side wall
JP3631908B2 (en) How to expand roads, highways or railway tunnels without blocking traffic
JP3076207B2 (en) Top shaft advanced construction method
KR100381669B1 (en) Head jacking shield tunneling apparatus and method
CN109869151A (en) Realize the work compound method of working face mining and protection coal pillar recycling
JP4113007B2 (en) Widening method of existing tunnel
RU2096621C1 (en) Method for driving deep tunnels in loose ground
Van Walsum Mechanical pre-cutting, a rediscovered tunneling technique
JPH0464697A (en) Construction of tunneling space
KR200175135Y1 (en) Head jacking shield tunneling apparatus
Hulme et al. Bored tunneling for Singapore metro
JPH08109788A (en) Jumbo for excavating center-advanced rear-widened type tunnel
Bougard The mechanical pre-cutting method
CN214787382U (en) Open-type TBM propulsion system
JPS61207793A (en) Contruction of tunnel by advance timbering
JP3560669B2 (en) Large section tunnel lining method
Ogasawara et al. Removal of the utility tunnel by shield method to build the underground expressway
JPH0776988A (en) Preliminary construction method for tunnel facing front bedrock
JPH0525993A (en) Arch shell constructing method in work preceding tunnelling
JP2873503B2 (en) Ground support system in tunnel excavation
JPH08165899A (en) Tunnel lining method using timbering concurrently serving as reinforcing bar
CN112796770A (en) Tunnel forming method

Legal Events

Date Code Title Description
S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees