JP4915290B2 - Sidewall tunnel construction method and structure - Google Patents

Sidewall tunnel construction method and structure Download PDF

Info

Publication number
JP4915290B2
JP4915290B2 JP2007155616A JP2007155616A JP4915290B2 JP 4915290 B2 JP4915290 B2 JP 4915290B2 JP 2007155616 A JP2007155616 A JP 2007155616A JP 2007155616 A JP2007155616 A JP 2007155616A JP 4915290 B2 JP4915290 B2 JP 4915290B2
Authority
JP
Japan
Prior art keywords
side wall
concrete
tunnel
concrete side
main shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2007155616A
Other languages
Japanese (ja)
Other versions
JP2008308835A (en
Inventor
俊介 宮川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2007155616A priority Critical patent/JP4915290B2/en
Publication of JP2008308835A publication Critical patent/JP2008308835A/en
Application granted granted Critical
Publication of JP4915290B2 publication Critical patent/JP4915290B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

この発明は、側壁導坑式トンネルの構築方法およびその構造に係わり、特に工期の短縮化と工費の低減化とを大幅に図れるようにした側壁導坑式トンネルの改良技術に関する。   The present invention relates to a method for constructing a side wall tunnel and its structure, and more particularly to an improved technique for a side tunnel that greatly shortens the construction period and reduces the construction cost.

従来より、地盤支持力が不足したり、土被りが小さい土砂地山で地表面沈下防止する必要があるような大断面トンネルの構築方法として、側壁導坑式トンネル工法が知られている。図5〜図10はこの側壁導坑式トンネル工法によるトンネル構築方法を示したものであり、図5はその構築途中の状態を示す概略平面図である。また、図6〜図10は図5中にVI−VI線〜X−X線にて示してある各部位の工程別の矢視断面図である。   Conventionally, a side tunnel type tunnel construction method is known as a construction method of a large-section tunnel that needs to prevent ground subsidence in a earth and sand mountain with insufficient ground support force or a small earth covering. 5 to 10 show a tunnel construction method by the side wall tunnel type tunnel construction method, and FIG. 5 is a schematic plan view showing a state during the construction. Moreover, FIGS. 6-10 is sectional drawing by arrow of each site | part shown by the VI-VI line-XX line in FIG.

図5に示すように、側壁導坑式トンネル2にあっては、構築しようとする大断面のトンネル本坑4の掘削に先立って、当該トンネル本坑4の両側部に位置させて一対の側壁導坑6,6を掘削し、その内周面に支保工7とインバート8とを仮設していく(図6参照)。そして、この側壁導坑6,6の形成が終了すると、次にこの一対の側壁導坑6,6内にトンネル本坑4の支保工10を支持するためのコンクリート側壁12を、当該側壁導坑6,6の相互に外側となる壁面に沿わせて形成する(図7参照)。そして、当該コンクリート側壁12,12が硬化してから側壁導坑6,6間上部の地山を掘削して大断面のトンネル本坑4の上半部を掘坑しつつ、両コンクリート側壁12,12の天端間に掛け渡してその掘坑の内周面上側部に支保工10を逐次設置していく(図8参照)。この後、側壁導坑6,6間を掘削してトンネル本坑4の下半部を掘坑して、その底面にインバート14を打設形成していく(図9参照)。爾後、コンクリート側壁12,12と支保工10との内側にインバート14に連続させて二次覆工体のアーチコンクリート16を打設して、トンネル本坑4の内周面に本坑全断面を閉合した強固な覆工体18を形成して側壁導坑式トンネル2を完成させていく(図10参照)。   As shown in FIG. 5, in the side wall tunnel 2, a pair of side walls are positioned on both sides of the tunnel main shaft 4 prior to excavation of the tunnel main shaft 4 having a large cross section to be constructed. The guide shafts 6 and 6 are excavated, and the support 7 and the invert 8 are temporarily installed on the inner peripheral surface thereof (see FIG. 6). Then, when the formation of the side wall guide shafts 6 and 6 is completed, a concrete side wall 12 for supporting the supporting work 10 of the tunnel main shaft 4 is next installed in the pair of side wall guide shafts 6 and 6. 6 and 6 are formed along the outer wall surfaces (see FIG. 7). And after the said concrete side walls 12 and 12 harden | cure, excavating the natural ground of the upper part between the side wall shafts 6 and 6 and excavating the upper half part of the tunnel main pit 4 of a large cross section, both concrete side walls 12 and The support work 10 is sequentially installed on the upper part of the inner peripheral surface of the mine, spanning between 12 top ends (see FIG. 8). Thereafter, the lower half of the tunnel main pit 4 is dug between the side wall guide pits 6 and 6, and an invert 14 is formed on the bottom surface thereof (see FIG. 9). After dredging, the arch concrete 16 of the secondary lining body is placed inside the concrete side walls 12 and 12 and the supporting work 10 continuously to the invert 14, and the entire main shaft cross section is formed on the inner peripheral surface of the tunnel main shaft 4. The closed strong lining body 18 is formed to complete the side wall tunnel 2 (see FIG. 10).

また、コンクリート側壁12の形成にあたっては、図11に示すように移動式の鋼製型枠であるセントル20を設置してコンクリートを打設し、所定長ずつコンクリート側壁12を打ち継いでいくようにしている。ここで、図11では紙面の手前方向にセントル20が移動してコンクリート側壁12を打ち継ぎ形成していく様になっているが、図示するように、セントル20はコンクリート側壁の内面部を区画形成する鋼板製の内面部型板20aと次の打ち継ぎ面となる褄部面を区画形成する鋼板製の褄部型板20bとを有している。そして、これらの型板20a,20bはそれぞれ作業足場を兼用する走行架台21a,21bによって移動可能に支持されている。   Further, in forming the concrete side wall 12, as shown in FIG. 11, a centle 20, which is a movable steel formwork, is placed to cast concrete, and the concrete side wall 12 is cast over by a predetermined length. ing. Here, in FIG. 11, the centle 20 moves toward the front side of the sheet to form the concrete side wall 12, but as shown in the figure, the centle 20 forms the inner surface portion of the concrete side wall. A steel plate inner surface template 20a, and a steel plate flange template 20b that defines and forms a flange surface to be the next joint surface. And these template 20a, 20b is supported so that the movement stand 21a, 21b which also serves as a work scaffold, respectively can move.

褄部型枠20bを支持する走行架台21bは、所定長ずつ先行形成された側壁コンクリート12の基盤部12a上に敷設されたレール22上を走行移動するようになっており、褄部型枠20bの外面側を支持すると共に、内面部型枠20aの端部を支持している。また、内面部型枠20aはその下端部が基盤部12aの側面に当接されて側壁導坑6を横断する鋼材23を介してジャッキ24で押圧支持されるようになっており、このジャッキ23は側壁導坑6の他方側の内壁面で支持反力を得るようになっている。   The traveling platform 21b that supports the buttock formwork 20b travels on the rail 22 that is laid on the base portion 12a of the side wall concrete 12 that is formed in advance by a predetermined length. Is supported on the outer surface side, and the end portion of the inner surface mold 20a is supported. The inner surface form 20a is pressed and supported by a jack 24 via a steel material 23 whose lower end is in contact with the side surface of the base 12a and crosses the side wall guide shaft 6. Is configured to obtain a support reaction force on the inner wall surface on the other side of the side wall guide shaft 6.

そして内面部型枠20aを支持する走行架台21aは、上記鋼材23上に敷設されたレール25上を側壁導坑6の長手方向に走行移動するようになっており、当該鋼材23とジャッキ24及びレール25とは、セントル20がトンネル形成方向の前方に向けて次のコンクリート側壁形成部位に移動される度に、さらにその前方部位に逐次移設されていくようになっている。   And the traveling frame 21a that supports the inner surface part formwork 20a travels on the rail 25 laid on the steel material 23 in the longitudinal direction of the side wall shaft 6, and the steel material 23 and the jack 24 and Each time the centle 20 is moved to the next concrete side wall forming portion toward the front in the tunnel forming direction, the rail 25 is sequentially moved further to the front portion.

なお、このような側壁導坑式トンネルに関する特許文献としては下記の公報等がある。
特開平8−28191号公報 特開平8−184283号公報
Patent documents relating to such side-wall tunnels include the following publications.
JP-A-8-28191 JP-A-8-184283

ところで、上記従来のような側壁導坑式トンネルの構築方法にあっては、コンクリート側壁12を移動式型枠であるセントル20を用いて形成していたので、以下のような課題があった。   By the way, in the construction method of the above-described conventional side-wall tunnel, the concrete side wall 12 is formed by using the centle 20 which is a movable formwork, and thus has the following problems.

(1)内面部型枠20aの下端部を押圧支持する鋼材23及びジャッキ24からなる押圧支持部材が側壁導坑6を横断してインバート7上に設置されるため、当該押圧支持部材が側壁導坑6内の動線を遮断してしまうことになり、側壁導坑6の掘削土砂の後方への搬出や支保工7等の資材の前方への搬入が困難になる。 (1) Since the pressing support member composed of the steel material 23 and the jack 24 that press-supports the lower end portion of the inner surface formwork 20a is installed on the invert 7 across the side-wall guide shaft 6, the pressing support member is connected to the side-wall guide. The flow line in the mine 6 will be cut off, and it will be difficult to carry out the excavated sediment from the side wall guide mine 6 to the rear and to carry materials such as the support 7 forward.

(2)セントル20を前方に移動させながらコンクリート側壁12を打ち継ぎ形成していくので、上記掘削土砂の搬出や資材の搬入のために、セントル20をその都度解体して後方の既構築のトンネル本坑4内まで待避させることは、作業として非常に無駄なことになり、工期が長引くとともに工費も高騰してしまう。 (2) Since the concrete side wall 12 is formed while the centre 20 is moved forward, the centle 20 is dismantled each time and the existing tunnel is constructed in order to carry out the excavated earth and sand. Retreating to the main mine 4 is very wasteful as work, prolonging the construction period and increasing the construction cost.

(3)上記(1),(2)の課題点を有していることから、従来では、先ず側壁導坑をその予定する全線に亘って形成し、これを待ってその後にセントル20を用いてコンクリート側壁を所定長ずつ逐次に形成して、トンネル本坑4の掘削を行わざるを得なかった。従って、コンクリート側壁12の形成と側壁導坑6,6の掘削とを並行して進めることができないので、工期の短縮化を図ることが難しかった。また、側壁導坑6,6を掘削してからトンネル本坑4の全断面を閉合するまでに時間を要してしまい、その早期閉合を望み得なかった。 (3) Since it has the above-mentioned problems (1) and (2), conventionally, the side wall shaft is first formed over the entire line, and after this, the centle 20 is used. Thus, the side walls of the concrete were sequentially formed by a predetermined length, and the tunnel main pit 4 had to be excavated. Accordingly, it is difficult to shorten the construction period because the formation of the concrete side wall 12 and the excavation of the side wall guide shafts 6 and 6 cannot be performed in parallel. Moreover, it took time until the entire cross section of the tunnel main pit 4 was closed after excavating the side wall guide pits 6, 6, and the early closing could not be expected.

本発明は、上記事情に鑑みてなされたものであり、その目的は、側壁導坑に内に形成するコンクリート側壁を、鋼製型枠を用いずに簡易に短時間で形成することができると共に、当該コンクリート側壁の形成に際して、側壁導坑内での切り羽への機材搬入出や掘削土砂の排出を阻害することがなく、側壁導坑の掘削工程とコンクリート側壁の形成工程とを併行して施工することができ、もってトンネル本坑の全断面の早期閉合が図れると共に、工期の短縮化と工費の低減化とを大幅に図れる側壁導坑式トンネルの構築方法およびその構造を提供することにある。   This invention is made | formed in view of the said situation, The objective is that the concrete side wall formed in a side wall guide pit can be easily formed in a short time without using a steel formwork. When forming the concrete side wall, it does not obstruct the loading and unloading of equipment to and from the face blades in the side wall guide pit and the excavation of excavated earth and sand. Therefore, it is intended to provide a method of constructing a side-wall tunnel and a structure thereof that can achieve early closing of the entire cross section of the tunnel main shaft, and can greatly shorten the construction period and reduce the construction cost. .

上記の目的を達成するために、本発明に係る側壁導坑式トンネルの構築方法にあっては、トンネル本坑の掘削に先行して、該トンネル本坑の左右両側部に位置させて一対の側壁導坑を掘削形成していく側壁導坑形成工程と、該一対の側壁導坑内に、該トンネル本坑の支保工を支持するためのコンクリート側壁を所定長に亘って打ち継ぎ形成していくコンクリート側壁形成工程と、該コンクリート側壁の硬化後に、該側壁導坑間を掘削しつつ、該一対のコンクリート側壁上面に掛け渡して該支保工を設置してトンネル本坑を形成していくトンネル本坑形成工程とを備え、該コンクリート側壁形成工程では、該側壁導坑の壁面に該コンクリート側壁の天面部ラインと内面部ラインとを規定する定規材を配置して、該定規材で規定される空間内にコンクリートを複数回に分けて吹き付け施工して多層に充填していくことで所望形状のコンクリート側壁に形成することを特徴とする。   In order to achieve the above object, in the method for constructing a side wall tunnel according to the present invention, prior to excavation of the tunnel main shaft, a pair of side tunnels are located on the left and right sides of the tunnel main shaft. A side wall shaft formation process for excavating and forming a side wall shaft, and a concrete side wall for supporting a support work of the tunnel main shaft is formed in the pair of side wall shafts over a predetermined length. A tunnel book in which a concrete side wall is formed, and after the concrete side wall is hardened, a tunnel main pit is formed by excavating between the side wall guide pits and spanning the upper surfaces of the pair of concrete side walls to install the support. A pit forming step, and in the concrete side wall forming step, a ruler material that defines the top surface line and the inner surface line of the concrete side wall is arranged on the wall surface of the side wall guide mine, and is defined by the ruler material. In the space And construction spraying divides the cleat multiple times, and forming the concrete side walls of the desired shape by gradually filling the multilayer.

ここで、前記定規材は、前記天面部ラインを規定する天面部ラス板と、縦方向に延びて配設されて前記内面部ラインを規定するとともに該ラス板を支持する鉄筋または鋼材と、次の打ち継ぎ面となる褄部に配設された褄部ラス板とを備えている構成となし得る。   Here, the ruler material includes a top surface lath plate that defines the top surface line, a reinforcing bar or steel material that extends in the vertical direction to define the inner surface line and supports the lath plate, and It can be set as the structure provided with the collar lath plate arrange | positioned at the collar part used as the joining surface of.

また、上記の目的を達成するために本発明に係る側壁導坑式トンネル構造にあっては、トンネル本坑の左右両側部に位置されて、所定の高さと厚みとを有してトンネル長方向に沿って連続して打ち継ぎ形成された一対のコンクリート側壁と、該一対のコンクリート側壁の天面部間に掛け渡されて、該トンネル本坑の内周面に沿って設けられた支保工と、該支保工と該コンクリート側壁との内周面を覆って設けられた二次覆工体と、該二次覆工体と一体的に連続形成されて該トンネル本坑の底面に設けられたインバートとを備え、該コンクリート側壁は、該コンクリート側壁の天面部ラインを規定する天面部ラス板と、縦方向に延びて配設されて該コンクリート側壁の内面部ラインを規定するとともに該天面部ラス板を支持する鉄筋または鋼材と、打ち継ぎ面の褄部に配設された褄部ラス板とからなる定規材を有して、該定規材の内部に複数回に分けて吹き付け施工されたコンクリートが多層に充填されて形成されている、ことを特徴とする。   Further, in order to achieve the above object, in the side wall tunnel structure according to the present invention, the tunnel is located at the left and right side portions of the tunnel main shaft and has a predetermined height and thickness. A pair of concrete side walls formed continuously and along the top surface portion of the pair of concrete side walls, and a support work provided along the inner peripheral surface of the tunnel main shaft, A secondary lining body provided to cover the inner peripheral surface of the support and the concrete side wall, and an invert provided on the bottom surface of the tunnel main pit, integrally formed with the secondary lining body. And the concrete side wall includes a top surface lath plate that defines a top surface portion line of the concrete side wall, and is arranged extending in a vertical direction to define an inner surface portion line of the concrete side wall and the top surface portion lath plate. Reinforcing bar or steel material And a ruler material comprising a flange lath plate disposed on the flange portion of the joining surface, and is formed by filling the inside of the ruler material with multiple layers of sprayed concrete. It is characterized by that.

上記のようにしてなる本発明の側壁導坑式トンネルの構築方法及びその構造によれば、移動式の鋼製型枠であるセントルを用いずに、これに代えてコンクリート側壁の天面部ラインと内面部ラインとを規定する定規材を設置して、この定規材の内部空間にコンクリートを吹き付け機で多層に吹き付け充填することで、コンクリート側壁を所定の厚みと高さを有した所望形状に精度良く、しかも容易に形成することができる。また、セントルを用いないので側壁導坑内の動線を遮断してしまうことなくコンクリート側壁を形成していくことができ、もって側壁導坑の掘削土砂等の搬出や、当該側壁導坑の内周面に設ける仮設支保工の資材等の搬入が阻害されることがない。このため、側壁導坑の掘削作業とコンクリート側壁の形成作業、トンネル本坑の掘削形成作業とを逐次に並行して進めていくことができ、もってトンネル本坑全断面の早期閉合が図れるようになって施工の安全性が可及的に向上すると共に、工期の短縮化と工費の削減化とを大幅に図れるようになる。   According to the construction method and the structure of the side wall tunnel of the present invention configured as described above, the center line of the concrete side wall is used instead of the centle, which is a movable steel mold. By installing a ruler material that defines the inner surface line, and spraying and filling concrete into the inner space of this ruler in multiple layers with a spraying machine, the concrete side wall is accurately shaped into a desired shape with a predetermined thickness and height. It can be formed easily and easily. In addition, since no centle is used, a concrete side wall can be formed without interrupting the flow line in the side wall guide mine. Carrying in temporary support materials provided on the surface is not hindered. For this reason, it is possible to proceed with the excavation work of the side wall guide pit, the formation of the concrete side wall, and the excavation formation work of the tunnel main mine one after another, so that the entire section of the tunnel main mine can be closed early. As a result, the construction safety can be improved as much as possible, and the construction period can be shortened and the construction cost can be greatly reduced.

以下に、本発明に係る側壁導坑式トンネルの構築方法及びその構造の好適な一実施の形態について、添付図面に基づいて説明する。   A preferred embodiment of a method for constructing a side-wall tunnel according to the present invention and a structure thereof will be described below with reference to the accompanying drawings.

図1は側壁導坑式トンネルの構築途中状態を概略的に示す概略平断面図である。また、従来例として示した図6〜図10の各断面図は本実施形態にも共通するものであって、それぞれ図1中においてVI−VI線乃至X−X線にて示す部位の矢視断面図となっている。なお従来例と共通する部材には同一の符号を付して説明する。   FIG. 1 is a schematic plan sectional view schematically showing a state in the middle of construction of a side-wall tunnel. Moreover, each sectional view of FIGS. 6 to 10 shown as the conventional example is common to the present embodiment, and each of the sectional views shown by the VI-VI line to the XX line in FIG. It is a sectional view. In addition, the same code | symbol is attached | subjected and demonstrated to the member which is common in a prior art example.

図1に示すように、本発明に係る側壁導坑式トンネルの構築方法にあっては、先ず、最初の工程として、側壁導坑掘削工程とこれに続く支保工設置工程とが順次に行われる。即ち、従来と同様に、構築しようとする大断面のトンネル本坑4の掘削に先立って、当該トンネル本坑4の両側部に位置させて一対の側壁導坑6,6を掘削し、その内周面に支保工7とインバート8とを仮設していく(図6参照)。側壁導坑掘削工程では、所定のトンネル設置計画ラインに沿って掘削機械等を用いて切り羽6aを掘削・ズリ出しして側壁導坑6,6を形成していく。そして、掘削した側壁導坑6,6の内周には、逐次に吹き付コンクリートとH型鋼とからなる支保工7を設置して土砂の崩落の防止を図る。当該吹き付コンクリートは1次吹き付け層と2次吹き層とからなり、H型鋼は1次吹き付け層の内側に沿わせて逐次に建て込んで設置していく。このH型鋼は側壁導坑6の長手方向に所定の間隔を空けて設けられ、当該H型鋼の設置後にそれらの間を埋めるようにして更にコンクリートの2次吹き付けが行われる。つまり、この2次吹き付け層によって吹き付けコンクリート層の強度向上が図られる。   As shown in FIG. 1, in the method for constructing a side wall tunnel according to the present invention, first, as a first process, a side wall tunnel excavation process and a subsequent support installation process are sequentially performed. . That is, as in the prior art, prior to excavation of the tunnel main shaft 4 having a large cross section to be constructed, a pair of side wall guide shafts 6 and 6 are excavated on both sides of the tunnel main shaft 4, Supporting work 7 and invert 8 are temporarily installed on the peripheral surface (see FIG. 6). In the side wall excavation process, the side face guides 6 and 6 are formed by excavating and slipping the face 6a using a drilling machine or the like along a predetermined tunnel installation plan line. And the supporting work 7 which consists of sprayed concrete and H-shaped steel is installed in the inner periphery of the side wall guide pits 6 and 6 excavated in order to prevent the collapse of earth and sand. The sprayed concrete is composed of a primary spray layer and a secondary spray layer, and the H-shaped steel is sequentially built and installed along the inside of the primary spray layer. The H-shaped steel is provided at a predetermined interval in the longitudinal direction of the side wall guide shaft 6, and after the installation of the H-shaped steel, secondary spraying of concrete is further performed so as to be filled between them. That is, the strength of the sprayed concrete layer is improved by the secondary spray layer.

上記側壁導坑6,6の形成が終了すると、次にこの一対の側壁導坑6,6内にコンクリート側壁12を形成するコンクリート側壁形成工程が行われる。このコンクリート側壁形成工程は、側壁導坑6,6の切り羽6aから所定長後方部位に位置した側壁形成域にて、上記側壁導坑掘削工程及びその支保工設置工程とに並行して逐次に行われ、トンネル本坑4の支保工10の脚部10aを支持するためのコンクリート側壁12が形成されていく。当該コンクリート側壁12は側壁導坑6,6の相互に外側となる壁面に沿わされて、トンネル長方向に所定長ずつ打ち継ぎ形成されていく(図7参照)。   When the formation of the side wall guide shafts 6 and 6 is completed, a concrete side wall forming step for forming the concrete side walls 12 in the pair of side wall guide shafts 6 and 6 is then performed. This concrete side wall forming step is performed in parallel with the side wall guide mine excavation step and its support installation step in a side wall formation region located at a predetermined length rear portion from the face 6a of the side wall guide pits 6 and 6. The concrete side wall 12 for supporting the leg part 10a of the support work 10 of the tunnel main pit 4 is formed. The concrete side wall 12 is formed along the wall surfaces which are on the outer sides of the side wall guides 6 and 6, and is formed in a predetermined length in the tunnel length direction (see FIG. 7).

ところで、本発明では、図2の拡大縦断面図に示すように、上記コンクリート側壁12はコンクリート吹き付け機44によるコンクリートの吹き付け施工にて形成される。ここで、当該コンクリート側壁12は支保工10と共にトンネル本坑4の一次覆工体の一部をなすものであって、支保工10の脚部10aを支持して鉛直荷重を負担するため、相応の壁厚と高さとが必要であると共に、支保工10の脚部10aを支持する天端面はその凹凸を極力なくして平坦に形成する必要がある。さらには、爾後に施工される二次覆工体16の被りコンクリート厚をも確保しなければならないので、この二次覆工体16の内面形状に相応させて、コンクリート側壁12の内周面側の形状もある程度精度良く形成する必要がある。しかし、従来において行われていたコンクリート吹き付け施工では、その十分な壁厚と外形形状精度とを確保して形成することが困難だった。   By the way, in the present invention, as shown in the enlarged vertical sectional view of FIG. 2, the concrete side wall 12 is formed by concrete spraying by a concrete sprayer 44. Here, the concrete side wall 12 forms a part of the primary lining body of the tunnel main shaft 4 together with the support work 10 and supports the leg portion 10a of the support work 10 to bear a vertical load. The wall thickness and height are required, and the top end surface that supports the leg portion 10a of the support work 10 needs to be formed flat with as little unevenness as possible. Furthermore, since it is necessary to secure the covering concrete thickness of the secondary lining body 16 to be constructed after dredging, the inner peripheral surface side of the concrete side wall 12 is adapted to the inner surface shape of the secondary lining body 16. It is necessary to form the shape with a certain degree of accuracy. However, in the conventional concrete spraying construction, it has been difficult to secure the sufficient wall thickness and outer shape accuracy.

そこで、本発明では、図示するように、コンクリート側壁12の天面部ラインと内面部ラインとを規定する定規材30を側壁導坑6,6の壁面に沿わせて配置し、この定規材30で規定される空間内にコンクリート40を複数回に分けて多層に吹き付け充填していくことで所望形状のコンクリート側壁12に形成するようにした。   Therefore, in the present invention, as shown in the drawing, a ruler material 30 that defines the top surface line and the inner surface line of the concrete side wall 12 is arranged along the wall surfaces of the side wall guide shafts 6 and 6, The concrete 40 is divided into a plurality of times in a defined space and sprayed and filled in multiple layers to form the concrete side wall 12 having a desired shape.

即ち、上記定規材30は図3の斜視図にも示すように、上記天面部ラインを規定する天面部ラス板32と、上下方向に延びて配設されて前記内面部ラインを規定するとともに上記天面部ラス板32を支持する鉄筋34(または鋼材としても良い)と、次の打ち継ぎ面となる褄部側に配設された褄部ラス板36とを備えている。ここで、上記天面部及び褄部のラス板32,36にはラス金網または無数の孔が開口形成されているパンチングボード等を使用し得るが、本実施形態ではラス金網を採用している。天面部ラス板32は当該天面部位置の壁厚に相応した幅を有して側壁導坑6に沿って所定の長さに亘って設けられるようになっており、複数の鉄筋34によって下面を支持されている。   That is, as shown in the perspective view of FIG. 3, the ruler material 30 is disposed extending in the vertical direction to define the top surface lath plate 32 that defines the top surface portion line, and defines the inner surface portion line. A reinforcing bar 34 (or steel material) for supporting the top surface lath plate 32 and a collar lath plate 36 disposed on the collar side to be the next joining surface are provided. Here, a lath wire mesh or a punching board having an infinite number of holes formed therein can be used for the lath plates 32 and 36 of the top surface portion and the flange portion, but in this embodiment, a lath wire mesh is adopted. The top surface lath plate 32 has a width corresponding to the wall thickness at the position of the top surface portion, and is provided over a predetermined length along the side wall guide shaft 6. It is supported.

上記鉄筋34は上記天面部ラス板32を支持すべく上部側が天面部ラインに沿わされてほぼ水平に折り曲げられて延設されており、その水平延設部34aの先端が側壁導坑6の内壁面に当接されて止着されるようになっている。また、上記水平延設部34aから屈曲して下方に延びる内面部ラインの規定部34bは二次覆工体16の湾曲形状に相応されて湾曲形成されており、下端部は脚部34cとして直線状に形成されて、インバート8の上面にほぼ鉛直に当設して載置されるようになっている。   The rebar 34 is extended along the top surface line so as to support the top surface lath plate 32 and is bent substantially horizontally, and the tip of the horizontally extending portion 34 a is the inner side of the side wall guide shaft 6. It is brought into contact with the wall and fixed. The defining portion 34b of the inner surface line that bends from the horizontal extending portion 34a and extends downward is curved in accordance with the curved shape of the secondary covering body 16, and the lower end portion is straight as a leg portion 34c. It is formed in a shape, and is placed on the upper surface of the invert 8 so as to be placed substantially vertically.

上記鉄筋34は所定のピッチで(1〜3m程度が好ましい)、複数本配設される。図示例にあっては、天面部ラス板32はトンネル長手方向の長さが2mに設定されていて、鉄筋34は1mピッチで2本設けられており、当該天面部ラス板32はその長手方向の中央部と次の打ち継ぎ面側となる一方の端部とが鉄筋34で支持されている。そして、天面部ラス板32は、その側壁導坑6の内方側端32aが当該鉄筋34の内面部ライン規定部34bに沿って下方に所定長折り曲げられてされて角部を覆う垂下部32aが形成されている。また、上記した次の打ち継ぎ面側となる一方の端部に配設された鉄筋34には、これに支持されて褄部を画成するための褄部ラス板36が取り付けられている。   A plurality of the reinforcing bars 34 are arranged at a predetermined pitch (preferably about 1 to 3 m). In the illustrated example, the length of the top surface lath plate 32 in the tunnel longitudinal direction is set to 2 m, and two reinforcing bars 34 are provided at a pitch of 1 m, and the top surface lath plate 32 is in the longitudinal direction. The center portion of the steel plate and one end portion on the side of the next joining surface are supported by the reinforcing bar 34. The top surface lath plate 32 has a drooping portion 32a covering the corner portion by bending the inner side end 32a of the side wall guide shaft 6 downward by a predetermined length along the inner surface portion line defining portion 34b of the reinforcing bar 34. Is formed. Further, the reinforcing bar 34 disposed at one end on the next joining surface side is attached with a flange lath plate 36 supported by the reinforcing bar 34 to define the flange.

そして、このように形成された定規材30は、図4に示すように、既に形成されている後方のコンクリート側壁12の褄部に連続されて側壁導坑6の壁面に止着配置され、当該定規材30と既に形成されている側壁コンクリート12の褄部面とによって区画形成される空間内にコンクリート40が吹き付け充填されて、コンクリート側壁12が所望形状に打ち継ぎ形成されていく。   And the ruler material 30 formed in this way, as shown in FIG. 4, is continuously arranged on the wall of the rear side wall 12 of the rear wall that has already been formed, and is fixedly disposed on the wall surface of the side wall shaft 6. Concrete 40 is sprayed and filled into the space defined by the ruler material 30 and the flange surface of the side wall concrete 12 already formed, and the concrete side wall 12 is formed in a desired shape.

上記コンクリート40の吹き付け充填は、図2の(a)または(b)に示すように、自走車両42上に搭載されたコンクリート吹き付けロボット44によって、定規材30の内部空間内に向けて複数回に分けて行い、段階的にコンクリート層40aを多層に積層しながら所定の厚みと高さとを有した所望する形状に形成していく。また定規材30は埋め殺しにされていく。なお、諸条件の相違によって異なるものになるが、強度面からすると上記コンクリート側壁12に要求される最大壁厚は2.0m程度となる。ここで、図2(a)はその吹き付けコンクリート層40aを斜めにして下部から順次多層に積層充填していく場合を示し、図2(b)はその吹き付けコンクリート層40aを側壁導坑の壁面に沿わせて略鉛直にして多層に積層充填していく場合を示しているが、コンクリート層40aの1回の吹き付け厚みを従来から施工実績のある20cmにすると、図2(b)の場合ではその吹き付け回数は10回前後となり、その吹き付け充填に要する時間は概ね120分程度となる。なお、コンクリート層40aは、図2(a)に示すように、下部から斜めに形成して順次多層に積層充填していくようにする方がその施工上において好ましい。この場合にあって、コンクリート層40aの1回の吹き付け厚みを20cmにすると、コンクリート側壁12の高さが4mを超えていると20数回の吹き付け作業が必要となるが、このように斜めにコンクリート層40aを吹き付け形成して積層していくようにすると、コンクリートの垂れ等が生じ難くなるので、1回の塗布厚みを20cm以上にしてコンクリート層40aを吹き付け形成することができるようになる。つまり、その1回の塗布厚みは実際には40cm程度にまで増大可能であり、よって10数回の塗布作業で済ませることも可能である。また、全塗布量自体は変わりがないので、その塗布時間にはそれほどの差は生じない。   As shown in FIG. 2 (a) or (b), the concrete 40 is sprayed and filled a plurality of times by the concrete spraying robot 44 mounted on the self-propelled vehicle 42 into the interior space of the ruler 30. The concrete layer 40a is formed in a desired shape having a predetermined thickness and height while being laminated in multiple layers step by step. Further, the ruler material 30 is buried. In addition, although it changes with differences in various conditions, from the viewpoint of strength, the maximum wall thickness required for the concrete side wall 12 is about 2.0 m. Here, FIG. 2 (a) shows a case where the sprayed concrete layer 40a is slanted and filled in multiple layers sequentially from the bottom, and FIG. 2 (b) shows the sprayed concrete layer 40a on the wall of the side wall shaft. In the case of FIG. 2 (b), it shows the case of stacking and filling in multiple layers along the vertical direction, but if the spraying thickness of one time of the concrete layer 40a is 20 cm, which has been proven in the past. The number of times of spraying is around 10 times, and the time required for the spraying and filling is approximately 120 minutes. In addition, as shown in FIG. 2A, it is preferable in terms of construction that the concrete layer 40a is formed obliquely from the bottom and sequentially laminated and filled in multiple layers. In this case, if the thickness of one spraying of the concrete layer 40a is 20 cm, if the height of the concrete side wall 12 exceeds 4 m, 20 times of spraying operations are required. If the concrete layer 40a is formed by spraying and stacking, it is difficult for dripping of the concrete and the like. Therefore, the concrete layer 40a can be formed by spraying with a single coating thickness of 20 cm or more. That is, the thickness of one application can actually be increased to about 40 cm, and therefore, it is possible to complete the application work several times. Further, since the total coating amount itself does not change, there is no significant difference in the coating time.

即ち、上記コンクリート側壁12は、当該コンクリート側壁12の天面部ラインを規定する天面部ラス板32と、縦方向に延びて配設されて当該コンクリート側壁12の内面部ラインを規定するとともに上記天面部ラス板32を支持する鉄筋34(または鋼材)と、打ち継ぎ面の褄部に配設された褄部ラス板36とからなる定規材を有し、当該定規材の内部空間には、複数回に分けて吹き付け施工されたコンクリートが多層に充填されて形成されている構造になっている。   That is, the concrete side wall 12 is provided with a top surface lath plate 32 that defines the top surface portion line of the concrete side wall 12 and a longitudinally extending direction so as to define an inner surface portion line of the concrete side wall 12 and the top surface portion. It has a ruler material consisting of a reinforcing bar 34 (or steel material) that supports the lath plate 32 and a heel lath plate 36 disposed on the buttock of the joint surface, and the inner space of the ruler material has a plurality of times. It has a structure in which the concrete that has been sprayed separately is filled with multiple layers.

そして、上記コンクリート側壁形成工程が終了すると、そのコンクリート側壁12の所定の固化養生時間の経過後に、トンネル本坑形成工程が行われる。このトンネル本坑形成工程は、従来と全く同様に、トンネル本坑4の上半部を形成する上半部形成工程(図8参照)と下半部を形成する下半部形成工程(図9参照)との2段階に分けられて行われる。   And if the said concrete side wall formation process is complete | finished, the tunnel main mine formation process will be performed after progress of the predetermined solidification curing time of the concrete side wall 12. FIG. In this tunnel main shaft forming step, the upper half forming step (see FIG. 8) for forming the upper half of the tunnel main shaft 4 and the lower half forming step for forming the lower half (see FIG. The process is divided into two stages.

即ち、上半部形成工程は側壁形成域の後方部に位置する上半部掘削域にて行われ、側壁導坑6,6間上部の地山が掘削されると共に、側壁導坑6,6の天部に仮設された支保工7が撤去される。そして側壁導坑6,6内に形成された一対のコンクリート側壁12,12の天端間に掛け渡されてその掘坑の内周面上側部に沿って支保工10が逐次設置されていく。また、下半部形成工程は上半部掘削域の後方部に位置する下半部掘削域にて行われ、側壁導坑6,6間の地山が掘削されると共に、側壁導坑6,6の側部に仮設された支保工7と底面に仮設されたインバート8とが撤去されてトンネル本坑4の下半部が掘削され、そのトンネル本坑4の底面に本設のインバート14が打設形成されていく。   That is, the upper half forming step is performed in the upper half excavation area located in the rear part of the side wall forming area, and the upper ground between the side wall guides 6 and 6 is excavated and the side wall guides 6 and 6 are excavated. The support work 7 tentatively installed on the top of is removed. And it is spanned between the top end of a pair of concrete side walls 12 and 12 formed in the side wall guide pits 6 and 6, and the support work 10 is sequentially installed along the inner peripheral surface upper part of the mine. In addition, the lower half formation step is performed in the lower half excavation area located in the rear part of the upper half excavation area, and a natural mountain between the side wall tunnels 6 and 6 is excavated, and the side wall tunnel 6, 6 is removed, and the lower half of the tunnel main shaft 4 is excavated, and the main invert 14 is formed on the bottom surface of the tunnel main shaft 4. It will be formed.

そして、トンネル本坑4の下半部の掘削形成が終了すると、この下半部掘削域の後方部に位置する二次覆工形成域にて、二次覆工体形成工程が行われる。この二次覆工体形成工程では、上記コンクリート側壁12,12と支保工10とからなる一次覆工体の内周面に沿って上記インバート14に連続する二次覆工体のアーチコンクリート16が打設形成される。これにより、トンネル本坑4の内周面に本坑全断面を閉合する強固な覆工体18が形成されて、側壁導坑式トンネル2が所定長ずつ逐次に完成されていく(図10参照)。   And if excavation formation of the lower half part of the tunnel main mine 4 is complete | finished, a secondary lining body formation process will be performed in the secondary lining formation area located in the back part of this lower half excavation area. In this secondary lining body forming step, the arch concrete 16 of the secondary lining body that continues to the invert 14 along the inner peripheral surface of the primary lining body composed of the concrete side walls 12, 12 and the support 10 is formed. Casting formed. Thereby, the strong cover body 18 which closes the whole cross section of the main mine is formed on the inner peripheral surface of the tunnel main mine 4, and the side wall tunnel type tunnel 2 is sequentially completed by a predetermined length (see FIG. 10). ).

従って、以上のようにして構築されていく側壁導坑式トンネル2にあっては、側壁導坑6,6内に形成するコンクリート側壁12を、上述してあるような定規材30を用いてコンクリート40の吹き付け施工で形成するので、従来のような移動式の鋼製型枠であるセントル20を用いることなく、当該コンクリート側壁12に要求される形状精度を十分に確保しつつ、所定の厚みと高さとを有した所望形状に形成していくことができる。   Therefore, in the side wall tunnel 2 constructed as described above, the concrete side wall 12 formed in the side wall tunnels 6 and 6 is made of concrete using the ruler 30 as described above. Since it is formed by 40 spraying constructions, it is possible to obtain a predetermined thickness while sufficiently ensuring the shape accuracy required for the concrete side wall 12 without using the centle 20, which is a conventional mobile steel formwork. It can be formed into a desired shape having a height.

また、移動式鋼製型枠のセントル20を用いずに定規材30を埋め殺してコンクリート側壁12,12を打ち継ぎ形成して行くので、従来のように、鋼製型枠の脱型,移動,組み立てといった作業がなくなり、簡易に短時間に施工することができるようになる。しかも、鋼製型枠のセントル20を用いていた従来にあっては、コンクリートを打設してから脱型するまでに1昼夜の待機時間を要していたが、吹き付け施工でコンクリート側壁12を形成すれば、その施工時間は数時間で終わり、直ぐに次の打ち継ぎ施工に取りかかれるので、施工時間の大幅な短縮化を図ることができるようになる。   Further, since the concrete side walls 12 and 12 are formed by burying the ruler material 30 without using the center 20 of the movable steel formwork, the demolding and movement of the steel formwork is performed as in the past. , Work such as assembly is eliminated, and construction can be easily performed in a short time. Moreover, in the conventional case where the steel mold centle 20 was used, a waiting time of one day and night was required from when the concrete was placed to when it was demolded. If it forms, the construction time will be completed in several hours, and it will be immediately started by the next joint construction, Therefore A construction time can be shortened significantly.

さらに、吹き付け施工は自走車両42上に搭載されて自在に移動可能なコンクリート吹き付けロボット44にて行うことができるので、吹き付け施工の終了後にはコンクリート吹き付けロボット44を後方の既構築のトンネル本坑4内等に簡易に待避させ得る。このため、切り羽6a側の側壁導坑掘削域と後方の既構築されたトンネル本坑4内とを結ぶ動線を遮断させずに確保することができる。   Furthermore, since the spraying work can be performed by the concrete spraying robot 44 mounted on the self-propelled vehicle 42 and freely movable, the concrete spraying robot 44 is installed at the rear of the tunnel main shaft in the rear after the spraying work is completed. 4 can be easily saved. For this reason, it is possible to ensure without blocking the flow line connecting the side wall guide mine excavation area on the face 6a side and the inside of the tunnel main mine 4 that has been constructed in the rear.

従って、切り羽6aからの掘削土砂の搬出や、トンネル本坑4側から側壁導坑掘削域内への支保工7等の資材の搬入が阻害されることがなく、側壁導坑6,6の掘削形成工程,コンクリート側壁形成工程,トンネル本坑4の掘削形成工程等の一連の作業を逐次に並行して行うことができるようになる。これ故、従来のようにトンネル本坑4の掘削に先立って側壁導坑6,6をその予定する全線に亘って予め形成しておく必要がなく、側壁導坑6,6の掘削作業を行いながら、当該側壁導坑掘削域よりも所定長後方部位にて、並行してトンネル本坑4の掘削形成作業を行うことができるようになり、もってトンネル本坑4の全断面閉合を可及的早期に行って、施工の安全性の向上を図ることができるようになる。   Therefore, unloading of excavated earth and sand from the cutting face 6a and loading of materials such as the supporting work 7 from the tunnel main pit 4 side into the side wall guide mine excavation area is not hindered, and the side pits 6 and 6 are excavated. A series of operations such as a forming process, a concrete side wall forming process, an excavation forming process of the tunnel main pit 4 and the like can be sequentially performed in parallel. Therefore, it is not necessary to form the side wall guides 6 and 6 in advance over the entire line prior to excavation of the tunnel main shaft 4 as in the prior art, and the side wall guides 6 and 6 are excavated. However, it becomes possible to perform excavation formation work of the tunnel main pit 4 in parallel at a predetermined length rear part from the side wall mine excavation area, so that the entire cross-section of the tunnel main pit 4 can be closed as much as possible. It is possible to improve the safety of construction by going early.

なお、上述した実施の形態では、コンクリート側壁12を形成するにあたって、その1施工ブロック長を2.0mに設定して、定規材30のトンネル長手方向の長さを2.0mに形成してコンクリートの吹き付け施工を行うようにしているが、当該施工ブロック長は6.0m程度まで十分に延長可能であり、その施工ブロック長は諸条件を勘案して任意に設定し得る。   In the above-described embodiment, when the concrete side wall 12 is formed, the construction block length is set to 2.0 m, and the length of the ruler material 30 in the tunnel longitudinal direction is set to 2.0 m. However, the construction block length can be sufficiently extended to about 6.0 m, and the construction block length can be arbitrarily set in consideration of various conditions.

本発明に係る側壁導坑式トンネルの構築途中状態を概略的に示す平断面図である。It is a cross-sectional view schematically showing a state in the middle of construction of the side wall tunnel type tunnel according to the present invention. コンクリート側壁形成工程における一方の側壁導坑の拡大断面図であり、(a)は吹き付けコンクリート層を斜めにして多層に積層していく場合を示し、(b)は吹き付けコンクリート層を側壁導坑に沿わせて略鉛直にして多層に積層していく場合を示している。It is an expanded sectional view of one side wall guide shaft in a concrete side wall formation process, (a) shows the case where a spraying concrete layer is slanted and laminated in a multilayer, (b) shows a spray concrete layer in a side wall guide shaft. It shows a case of being stacked in multiple layers along the vertical direction. 定規材の一例を示す斜視図である。It is a perspective view which shows an example of a ruler material. 側壁導坑内に定規材を設置した状態を示す斜視図である。It is a perspective view which shows the state which installed the ruler material in the side wall guide mine. 従来における側壁導坑式トンネルの構築途中状態を概略的に示す平断面図である。It is a plane sectional view showing roughly the state in the middle of construction of the conventional side wall tunnel. 本発明と従来例とに共通する、図1中と図5中とにVI−VI線にて示す部位の矢視断面図である。FIG. 6 is a cross-sectional view taken along the line VI-VI in FIG. 1 and FIG. 5 that is common to the present invention and the conventional example. 同上、図1中と図5中とにおいてVII−VII線にて示す部位の矢視断面図である。FIG. 7 is a cross-sectional view taken along the line VII-VII in FIG. 1 and FIG. 同上、図1中と図5中とにおいてIIX−IIX線にて示す部位の矢視断面図である。FIG. 6 is a cross-sectional view taken along the line IIX-IIX in FIG. 1 and FIG. 同上、図1中と図5中とにおいてIX−IX線にて示す部位の矢視断面図である。FIG. 6 is a cross-sectional view taken along the line IX-IX in FIG. 1 and FIG. 同上、図1中と図5中とにおいてX−X線にて示す部位の矢視断面図である。FIG. 6 is a cross-sectional view taken along the line XX in FIG. 1 and FIG. 従来のコンクリート側壁形成工程における一方の側壁導坑の拡大断面図である。It is an expanded sectional view of one side wall guide shaft in the conventional concrete side wall formation process.

符号の説明Explanation of symbols

2 側壁導坑式トンネル
4 トンネル本坑
6 側壁導坑
10 トンネル本坑の支保工
10a 支保工脚部
12 コンクリート側壁
14 トンネル本坑のインバート
16 二次覆工体
30 定規材
32 天面部ラス板
34 鉄筋
36 褄部ラス板
2 Side-wall tunnel 4 Tunnel main shaft 6 Side wall tunnel 10 Tunnel main shaft support 10a Support leg 12 Concrete side wall 14 Tunnel main shaft invert 16 Secondary lining body 30 Ruler 32 Top surface lath plate 34 Reinforcing bar 36

Claims (3)

トンネル本坑の掘削に先行して、該トンネル本坑の左右両側部に位置させて一対の側壁導坑を掘削形成していく側壁導坑形成工程と、
該一対の側壁導坑内に、該トンネル本坑の支保工を支持するためのコンクリート側壁を所定長に亘って打ち継ぎ形成していくコンクリート側壁形成工程と、
該コンクリート側壁の硬化後に、該側壁導坑間を掘削しつつ、該一対のコンクリート側壁上面に掛け渡して該支保工を設置してトンネル本坑を形成していくトンネル本坑形成工程とを備えた側壁導坑式トンネルの構築方法であって、
該コンクリート側壁形成工程では、該側壁導坑の壁面に該コンクリート側壁の天面部ラインと内面部ラインとを規定する定規材を配置して、該定規材で規定される空間内にコンクリートを複数回に分けて吹き付け施工して多層に充填していくことで所望形状のコンクリート側壁に形成する、
ことを特徴とする側壁導坑式トンネルの構築方法。
Prior to excavation of the tunnel main shaft, a side wall shaft formation step of excavating and forming a pair of side wall guide shafts located on the left and right sides of the tunnel main shaft,
A concrete side wall forming step in which a concrete side wall for supporting a support work of the tunnel main mine is formed over a predetermined length in the pair of side wall guide shafts;
A tunnel main shaft forming step in which after the concrete side wall is hardened, a tunnel main shaft is formed by excavating between the side wall guide shafts and setting up the support works over the pair of concrete side walls. A method for constructing a side wall tunnel,
In the concrete side wall forming step, a ruler material that defines the top surface line and the inner surface line of the concrete side wall is disposed on the wall surface of the side wall guide shaft, and the concrete is placed in the space defined by the ruler material a plurality of times. Formed on the concrete wall of the desired shape by spraying and filling in multiple layers
A method for constructing a side wall tunnel.
前記定規材が、前記天面部ラインを規定する天面部ラス板と、縦方向に延びて配設されて前記内面部ラインを規定するとともに該ラス板を支持する鉄筋または鋼材と、次の打ち継ぎ面となる褄部に配設された褄部ラス板とを備えていることを特徴とする請求項1に記載の側壁導坑式トンネルの構築方法。   The ruler material is a top surface lath plate that defines the top surface portion line, a reinforcing bar or steel material that extends in the vertical direction to define the inner surface portion line and supports the lath plate, and the next splicing The construction method of the side wall tunnel type tunnel according to claim 1, further comprising a collar lath plate disposed on the collar serving as a surface. トンネル本坑の左右両側部に位置されて、所定の高さと厚みとを有してトンネル長方向に沿って連続して打ち継ぎ形成された一対のコンクリート側壁と、
該一対のコンクリート側壁の天面部間に掛け渡されて、該トンネル本坑の内周面に沿って設けられた支保工と、
該支保工と該コンクリート側壁との内周面を覆って設けられた二次覆工体と、
該二次覆工体と一体的に連続形成されて該トンネル本坑の底面に設けられたインバートとを備えた側壁導坑式トンネル構造であって、
該コンクリート側壁は、該コンクリート側壁の天面部ラインを規定する天面部ラス板と、縦方向に延びて配設されて該コンクリート側壁の内面部ラインを規定するとともに該天面部ラス板を支持する鉄筋または鋼材と、打ち継ぎ面の褄部に配設された褄部ラス板とからなる定規材を有して、該定規材の内部に複数回に分けて吹き付け施工されたコンクリートが多層に充填されて形成されている、
ことを特徴とする側壁導坑式トンネル構造。
A pair of concrete side walls that are located on the left and right sides of the tunnel main shaft, and have a predetermined height and thickness, and are continuously spliced along the tunnel length direction;
Spanned between the top surfaces of the pair of concrete side walls, and a support work provided along the inner peripheral surface of the tunnel main pit,
A secondary lining body provided to cover the inner peripheral surface of the support and the concrete side wall;
A side wall tunnel structure comprising an invert formed continuously with the secondary lining body and provided at the bottom of the tunnel main shaft,
The concrete side wall includes a top surface lath plate that defines the top surface line of the concrete side wall, and a reinforcing bar that extends in the vertical direction to define the inner surface line of the concrete side wall and supports the top surface lath plate. Or it has a ruler material consisting of steel and a lath lath plate arranged at the buttock of the joint surface, and the concrete is sprayed into the ruler material several times and filled in multiple layers Formed,
Sidewall tunnel structure characterized by this.
JP2007155616A 2007-06-12 2007-06-12 Sidewall tunnel construction method and structure Expired - Fee Related JP4915290B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007155616A JP4915290B2 (en) 2007-06-12 2007-06-12 Sidewall tunnel construction method and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007155616A JP4915290B2 (en) 2007-06-12 2007-06-12 Sidewall tunnel construction method and structure

Publications (2)

Publication Number Publication Date
JP2008308835A JP2008308835A (en) 2008-12-25
JP4915290B2 true JP4915290B2 (en) 2012-04-11

Family

ID=40236678

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007155616A Expired - Fee Related JP4915290B2 (en) 2007-06-12 2007-06-12 Sidewall tunnel construction method and structure

Country Status (1)

Country Link
JP (1) JP4915290B2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102226403B (en) * 2011-03-30 2013-11-13 中铁一局集团有限公司 Construction method of large-span subway station main body by using arched cover method and station main body structure
CN102518454B (en) * 2011-12-22 2014-07-23 中铁工程设计咨询集团有限公司 Grating device for underground excavation engineering and manufacture method
CN106640121B (en) * 2017-01-11 2023-06-27 中铁第六勘察设计院集团有限公司 Supporting structure for six-pilot tunnel large-section subway station to pass through existing line
CN106988748B (en) * 2017-03-15 2019-10-29 中铁二院工程集团有限责任公司 High-order parallel heading construction and capacity expansion revamping are the construction method of double line tunnel
CN110219679A (en) * 2019-07-22 2019-09-10 西南交通大学 A kind of soft stratum tunnel lining structure
CN110700841B (en) * 2019-10-30 2021-06-29 中交路桥华南工程有限公司 Double-side-wall guide pit type excavation method for tunnel excavation
CN111365072B (en) * 2020-03-10 2022-02-15 中铁第六勘察设计院集团有限公司 Guide hole exploration structure and method for huge cavern of fractured rock mass
CN114961743A (en) * 2022-06-02 2022-08-30 中铁四局集团第三建设有限公司 Large-section tunnel double-side-wall pit guiding method side-hole synchronous mileage construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2528338B2 (en) * 1987-11-17 1996-08-28 清水建設株式会社 Tunnel support
JPH03279598A (en) * 1990-03-28 1991-12-10 Hazama Gumi Ltd Construction method of large section or superlarge section of tunnel
JPH04297698A (en) * 1991-01-08 1992-10-21 Taisei Corp Support for moving concrete placing form for side-wall and method of moving the form
JP2833482B2 (en) * 1994-07-20 1998-12-09 株式会社大林組 Steel lining structure of tunnel
JP3121736B2 (en) * 1994-12-27 2001-01-09 財団法人先端建設技術センター Sidewall advanced method
JPH09165914A (en) * 1995-12-14 1997-06-24 Ohbayashi Corp Method for placing curved concrete

Also Published As

Publication number Publication date
JP2008308835A (en) 2008-12-25

Similar Documents

Publication Publication Date Title
JP4915290B2 (en) Sidewall tunnel construction method and structure
KR20130113315A (en) A building structure
JP4853429B2 (en) Support structure of lining board, method of supporting lining board
KR101716573B1 (en) The Construction Method of linear curve-shaped non-excavation tunnel with using Forepoling Board and ground reinforcement
JP4881555B2 (en) Construction method of underground structure
KR101840226B1 (en) The guide holes of the form for soil auger dredges
KR101627279B1 (en) Biased soil pressure reinforcement rigid-frame bridge and construction method of the same
JP6148709B2 (en) Road surface lining method in propulsion type open shield method
JP4915291B2 (en) Construction method and structure of concrete side wall
JP5356780B2 (en) Structure, construction method and design method of structure
JP4037187B2 (en) Underground structure construction method and underground structure
KR101479267B1 (en) Method for constructing tunnel by using pipe
KR101871446B1 (en) Underground structure with high accuracy press and longitudinal guide drain
JP2019120115A (en) Method of constructing tunnel lining structure
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
JP6882024B2 (en) Joining structure of precast concrete slab and construction method of precast concrete slab
JP2016199957A (en) Floor preceding method
JP6514739B2 (en) Construction method for forming underground structure and underground structure completed thereby
JP2020176400A (en) Tunnel lining method
KR101884453B1 (en) Pre-climbing core construction method for top-down construction
CN211340823U (en) Supporting system for prefabricated hollow plate used for bearing platform and ground beam side mold
JP4267175B2 (en) Construction method of underground structure
JP2019148108A (en) Bridge pier construction method
JP3323470B2 (en) Concrete placement method in reverse winding method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100520

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110621

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20111227

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120109

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150203

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees