JP2849605B2 - Large section tunnel and its construction method - Google Patents

Large section tunnel and its construction method

Info

Publication number
JP2849605B2
JP2849605B2 JP2171938A JP17193890A JP2849605B2 JP 2849605 B2 JP2849605 B2 JP 2849605B2 JP 2171938 A JP2171938 A JP 2171938A JP 17193890 A JP17193890 A JP 17193890A JP 2849605 B2 JP2849605 B2 JP 2849605B2
Authority
JP
Japan
Prior art keywords
tunnel
shield
section
tunnels
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2171938A
Other languages
Japanese (ja)
Other versions
JPH03250195A (en
Inventor
広志 風間
嘉信 井上
義昭 根上
紀治 三宅
篤 傳田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP2171938A priority Critical patent/JP2849605B2/en
Publication of JPH03250195A publication Critical patent/JPH03250195A/en
Application granted granted Critical
Publication of JP2849605B2 publication Critical patent/JP2849605B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は大断面トンネルおよびその構築方法に係わ
り、特に、大断面トンネルを構築するトンネル構造体を
複数本のシールドトンネルにより先行構築するようにし
た大断面トンネルおよびその構築方法に関する。
Description: TECHNICAL FIELD The present invention relates to a large-section tunnel and a method for constructing the same, and more particularly, to a method for constructing a large-section tunnel by using a plurality of shield tunnels in advance. And a method for constructing the same.

〔従来の技術〕[Conventional technology]

トンネルの構築方法としては既に様々なものが提供さ
れているが、特にシールド工法は硬岩以外のあらゆる地
山に適用でき、しかも地上施設に影響を与えず、地下深
部の施工が可能である等の利点を有するため、近年特に
その施工実績が増加している。
A variety of tunnel construction methods have already been provided, but in particular, the shield method can be applied to all types of ground except hard rock, and it does not affect ground facilities and can be constructed deep underground. In recent years, in particular, the construction results have increased.

ところで、近年、地下の利用ニーズが高まり、それに
伴いトンネルをもその大断面化が要求されてきている。
By the way, in recent years, underground use needs have been increased, and accordingly, a tunnel having a large cross section has been required.

そして、上記シールドトンネルも、このようなトンネ
ルの大断面化の要求に応えるべく大口径のものが施工さ
れるようになってきており、最近では外径14m以上とな
るシールド機も計画されている。
Also, the above-mentioned shield tunnel is being constructed with a large diameter in order to respond to the demand for such a large cross section of the tunnel, and a shield machine having an outer diameter of 14 m or more has recently been planned. .

〔発明が解決しようとする課題〕[Problems to be solved by the invention]

ところで、上記のようにシールドトンネルの大断面化
を図ろうとすると、当然のことながらそれに用いるシー
ルド機が大形化することとなる。
By the way, if an attempt is made to increase the cross section of the shield tunnel as described above, the size of the shield machine used for the tunnel will naturally increase.

しかしながら、シールド機はその掘削径が大径となる
と、一般に、W=2.5D2〜3.5D2(ただし、D:シールド機
外径、W:シールド機重量)の関係で重量が増加すると言
われており、このように大形化されたシールド機は単に
重量が極めて重くなるばかりでなく、製作,仮組み,運
搬,現場組立,現場設備等のあらゆる面で人手およびコ
ストが急激に嵩むものとなる。また、特にこのような超
大形シールド機においては、工場設備等の関係で、試運
転の実施さえ極めて困難な状況にあるのが現状となって
いる。
However, it is generally said that when the excavation diameter of a shield machine becomes large, the weight increases due to the relationship of W = 2.5D 2 to 3.5D 2 (where D: outer diameter of the shield machine, W: weight of the shield machine). Such a large-sized shield machine not only becomes extremely heavy, but also requires a lot of manpower and cost in all aspects such as production, temporary assembly, transportation, on-site assembly, and on-site equipment. Become. In addition, especially in such an ultra-large shield machine, it is currently very difficult to even perform a trial run due to factory equipment and the like.

本発明は上記の事情に鑑みてなされたもので、シール
ド工法の利点を有効に活用することにより、高品質かつ
低コストにてトンネルの大断面化を図れる大断面トンネ
ルおよびその構築方法を提供することを目的とするもの
である。
The present invention has been made in view of the above circumstances, and provides a large-sized tunnel capable of achieving a large-sized tunnel at a high quality and at low cost by effectively utilizing the advantages of the shield method, and a method of constructing the same. The purpose is to do so.

〔課題を解決するための手段〕[Means for solving the problem]

請求項1に記載した発明は、アーチ状または筒状に形
成され地山の土圧に抗して内部空間を形成するトンネル
構造体と、該トンネル構造体の内側に形成されるトンネ
ル空間とからなる大断面トンネルであって、前記トンネ
ル構造体は、構築すべきトンネルの長手方向に形成され
互いに隣接する多数のシールドトンネルにより構成さ
れ、かつ隣接形成された二つの前記シールドトンネルの
うち、いずれか一方のシールドトンネルの覆工体の一部
が切削され、ここに他方のシールドトンネルの覆工体が
位置して形成されることにより、これらシールドトンネ
ルが互いに重合して一体化されていることを特徴とする
ものである。
The invention described in claim 1 includes a tunnel structure formed in an arch shape or a cylindrical shape and forming an internal space against the earth pressure of the ground, and a tunnel space formed inside the tunnel structure. Wherein the tunnel structure is formed of a number of shield tunnels formed in the longitudinal direction of the tunnel to be constructed and adjacent to each other, and one of the two shield tunnels formed adjacent to each other. A part of the lining body of one shield tunnel is cut and the lining body of the other shield tunnel is formed and positioned here, so that these shield tunnels are integrated and integrated with each other. It is a feature.

また、請求項2に記載した発明は、請求項1記載の大
断面トンネルにおいて、前記覆工体の内部に硬化充填材
が充填されてなるものである。
According to a second aspect of the present invention, in the large-section tunnel according to the first aspect, a hardening filler is filled inside the lining body.

請求項3に記載した発明は、地山内に多数本のシール
ドトンネルを径方向に連設することによりアーチ状また
は筒状のトンネル構造体を先行構築した後、地山の該ト
ンネル構造体により囲まれた部分を掘削することにより
構築する大断面トンネルの構築方法であって、前記シー
ルドトンネルを、シールド機を掘進させる第1工程と、
シールド機により形成された掘削穴の壁面を覆工する第
2工程とにより構築し、かつ前記トンネル構造体は、前
記シールドトンネルを一つ置きに先行構築した後、それ
ら先行シールドトンネルの間に後行シールドトンネルを
形成することにより構築し、しかも該後行シールドトン
ネルの第1工程は、前記先行シールドトンネルの覆工体
の一部を地山と共に切削しながら行うことを特徴とする
ものである。
According to the third aspect of the present invention, an arched or cylindrical tunnel structure is preliminarily constructed by connecting a large number of shield tunnels in the ground in the radial direction and then surrounded by the tunnel structure of the ground. A method for constructing a large-section tunnel constructed by excavating a shielded part, wherein a first step of excavating a shield machine with the shield tunnel,
And a second step of lining the wall surface of the excavation hole formed by the shield machine, and the tunnel structure is constructed in advance of every other shield tunnel, and then between the preceding shield tunnels. The first shield tunnel is constructed by forming a row shield tunnel, and the first step of the subsequent shield tunnel is performed while cutting a part of the lining body of the preceding shield tunnel together with the ground. .

また、請求項4に記載した発明は、請求項3記載の大
断面トンネルの構築方法において、前記シールドトンネ
ルを、シールド機を掘進させる第1工程と、シールド機
により形成された掘削穴の壁面を覆工する第2工程と、
前記覆工体の内部に硬化充填材を充填する第3工程と、
により構築することを特徴とするものである。
According to a fourth aspect of the present invention, in the method for constructing a large-section tunnel according to the third aspect, the shield tunnel is formed by a first step of excavating a shield machine and a wall surface of an excavation hole formed by the shield machine. A second step of lining;
A third step of filling the inside of the lining body with a hardening filler,
It is characterized by being constructed by:

〔作用〕[Action]

請求項1の大断面トンネルによれば、トンネル構造体
をシールドトンネルにより構成するため、該トンネル構
造体の先行構築が可能となる。また、多数のシールドト
ンネルを構造的に一体化することで、トンネル構造体の
高剛性化、および高い遮水性を期待できる。
According to the large-section tunnel according to the first aspect, since the tunnel structure is constituted by the shield tunnel, the preceding construction of the tunnel structure becomes possible. In addition, by structurally integrating a large number of shield tunnels, high rigidity and high water shielding of the tunnel structure can be expected.

請求項2の大断面トンネルでは、トンネル構造体のさ
らなる強度向上が図れる。
In the large-section tunnel according to the second aspect, the strength of the tunnel structure can be further improved.

請求項3の大断面トンネルの構築方法によれば、請求
項1記載の大断面トンネルを確実に実現することができ
る。しかも、トンネル構造体を大断面トンネルの掘削に
先行して完成させるため、地山掘削時に支保工等の付帯
作業を実施する必要がない。また、トンネル構造体をシ
ールドトンネルにより構成するため、シールド工法の適
用可能なあらゆる地山に適用することができる。
According to the method for constructing a large-section tunnel according to the third aspect, the large-section tunnel according to the first aspect can be reliably realized. In addition, since the tunnel structure is completed prior to excavation of the large-section tunnel, it is not necessary to carry out additional work such as support work when excavating the ground. In addition, since the tunnel structure is constituted by a shield tunnel, the present invention can be applied to any ground to which the shield method can be applied.

請求項4の大断面トンネルの構築方法は、請求項2記
載の大断面トンネルを実現する。
The method for constructing a large-section tunnel according to claim 4 realizes the large-section tunnel according to claim 2.

〔実施例〕〔Example〕

以下、本発明の実施例を図面を参照しながら説明す
る。
Hereinafter, embodiments of the present invention will be described with reference to the drawings.

第1図は本発明の請求項1に係る大断面トンネルの第
一実施例を示すものである。
FIG. 1 shows a first embodiment of a large-section tunnel according to claim 1 of the present invention.

この大断面トンネル(以下、“トンネル”と略称す
る)1は、全体として筒状に形成され地山Gの土圧に抗
して内部空間を形成するトンネル構造体2と、該トンネ
ル構造体2の内部に形成されるトンネル空間3と、から
構成されている。
This large-section tunnel (hereinafter abbreviated as “tunnel”) 1 includes a tunnel structure 2 which is formed in a cylindrical shape as a whole and forms an internal space against the earth pressure of the ground G, and a tunnel structure 2 And a tunnel space 3 formed in the inside of the vehicle.

前記トンネル構造体2は、構築すべきトンネル1の長
手方向に形成され互いに隣接する多数のシールドトンネ
ル4,4,…により構成されている。本実施例においては、
これらシールドトンネル4,4,…が径方向に環状に配設さ
れることにより、このトンネル構造体2は、全体的に断
面円形の筒状を成している。
The tunnel structure 2 is formed of a large number of shield tunnels 4 formed adjacent to each other in the longitudinal direction of the tunnel 1 to be constructed. In this embodiment,
By arranging these shield tunnels 4, 4,... In a ring shape in the radial direction, the tunnel structure 2 has a cylindrical shape with a circular cross section as a whole.

前記トンネル構造体2を構成する各シールドトンネル
4は、第2図に示すように、多数のセグメント5,5,…に
より組み立てられた筒状構造体6と、該筒状構造体6の
背面側に後打ちされたコンクリートあるいはモルタル等
の硬化充填材(裏込め硬化充填材)7とから成る覆工体
20により覆工されたものとなっている。ただしここで、
前記筒状構造体6の、シールド機によって掘削された掘
削穴8の内径に対する径は、通常一般のシールドトンネ
ルと比べた場合に極めて小径のものとなっている。
As shown in FIG. 2, each of the shield tunnels 4 constituting the tunnel structure 2 has a cylindrical structure 6 assembled by a large number of segments 5, 5,. Body comprising a hardening filler (backfill hardening filler) 7, such as concrete or mortar, which is post-punched
It is lining by 20. But where
The diameter of the cylindrical structure 6 with respect to the inner diameter of the excavation hole 8 excavated by the shield machine is extremely small as compared with a general shield tunnel.

また、前記各シールドトンネル4は、隣り合うシール
ドトンネル4との離間寸法がシールドトンネル4自身の
外径より小さく設定されており、これにより、互いに隣
接するシールドトンネル4の覆工体20を構成する前記裏
込め硬化充填材7どうしは互いに重合したものとなって
いる。そして、これにより、各シールドトンネル4,4,…
の裏込め硬化充填材7(覆工体20)は連続して一体化さ
れたものとなっている。
Further, each of the shield tunnels 4 is set such that a distance between the shield tunnels 4 adjacent thereto is smaller than an outer diameter of the shield tunnels 4 themselves, thereby forming a lining body 20 of the shield tunnels 4 adjacent to each other. The backfill hardening fillers 7 are polymerized with each other. And by this, each shield tunnel 4,4,…
The backfill hardening filler 7 (lining body 20) is continuously integrated.

なお、上記構成となるトンネル1の外径はここでは20
〜40m、また、各シールドトンネル4の外径はおよそ0.7
〜4mのものとしている。
The outer diameter of the tunnel 1 having the above configuration is 20 here.
~ 40m, and the outer diameter of each shield tunnel 4 is about 0.7
~ 4m.

次に、本発明の請求項3に係る発明、すなわち上記構
造となる前記トンネル1の構築方法の一例について第3
図ないし第7図を参照して説明する。
Next, the invention according to claim 3 of the present invention, that is, an example of the method of constructing the tunnel 1 having the above structure, will be described in the third section.
This will be described with reference to FIGS.

前記トンネル1を構築するには、初めに、多数のシー
ルドトンネル4,4,…より成るトンネル構造体2を地山G
内に先行構築する。トンネル構造体2の構築は下記の工
程により行う。
To construct the tunnel 1, first, a tunnel structure 2 composed of a number of shield tunnels 4, 4,.
Build ahead in The construction of the tunnel structure 2 is performed by the following steps.

すなわちまず、第1図に示した完成時において互いに
隣接するシールドトンネル4,4,…のうち、一つ置きに配
列されるもの(先行シールドトンネル4A)を先行構築す
る(第3図参照)。
That is, first, of the shield tunnels 4, 4,... Adjacent to each other at the time of completion shown in FIG. 1, those that are alternately arranged (preceding shield tunnels 4A) are pre-constructed (see FIG. 3).

これら先行シールドトンネル4Aの構築は、通常一般の
シールド工法と同要領により行うことができる。すなわ
ち第7図に示すように、シールド機10を、その前面に設
けたカッタ11により地山Gを掘削しながら推進させると
ともに、シールド機10の後方にて掘削穴8内に円弧状の
セグメント5,5,…をリング状に組み上げて行き、筒状構
造体6を形成していく。ただし、この場合、前記シール
ド機10としてテールボイドの極めて大きいものを使用
し、これにより筒状構造体6は、掘削穴8内径に対して
小径に形成されたものとなっている。筒状構造体6が形
成された部分については、その背面側空隙すなわち筒状
構造体6と掘削穴8との間に前記裏込め硬化充填材7を
打設する。これによって覆工体20が完成される。なお、
同第7図中矢印は、裏込め硬化充填材7の打設状態を示
すものである。
The construction of these leading shield tunnels 4A can be performed in the same manner as a normal shield method. That is, as shown in FIG. 7, the shield machine 10 is propelled while excavating the ground G by the cutter 11 provided on the front surface thereof, and the arc-shaped segment 5 is inserted into the excavation hole 8 behind the shield machine 10. , 5,... Are assembled in a ring shape to form a tubular structure 6. However, in this case, an extremely large tail void is used as the shield machine 10, whereby the tubular structure 6 is formed to have a smaller diameter than the inner diameter of the excavation hole 8. In the portion where the tubular structure 6 is formed, the backfill hardening filler 7 is cast in the space on the back side, that is, between the tubular structure 6 and the excavation hole 8. Thereby, the lining body 20 is completed. In addition,
The arrows in FIG. 7 indicate the state of the backfill hardening filler 7 being placed.

上記方法により、第4図に示すように先行シールドト
ンネル4A,4A,…が地山G内に形成されたならば、次い
で、それら各先行シールドトンネル4Aの間に後行シール
ドトンネル4B,4B,…を形成する。
If the preceding shield tunnels 4A, 4A,... Are formed in the ground G as shown in FIG. 4 by the above method, then, the subsequent shield tunnels 4B, 4B, ... is formed.

第5図に示すように、後行シールドトンネル4Bの形成
工程も前記先行シールドトンネル4Aと同様である。ただ
し、先行シールドトンネル4A,4A,…の離間距離は上述し
た如くシールドトンネル4自身の径寸法よりも小さく設
定されているので、2本の先行シールドトンネル4A,4A
間に後行シールドトンネル4Bを形成する際には、地山G
と共に、両側の先行シールドトンネル4A,4Aを構成する
前記裏込め硬化充填材7の一部をも同時に掘削するもの
とする。その際、先行シールドトンネル4Aを構成する前
記筒状構造体6が小径に形成されているので、この筒状
構造体6と干渉することなく裏込め硬化充填材7のみを
切削することが可能である。
As shown in FIG. 5, the forming process of the succeeding shield tunnel 4B is the same as that of the preceding shield tunnel 4A. However, since the distance between the preceding shield tunnels 4A, 4A,... Is set smaller than the diameter of the shield tunnel 4 itself as described above, the two preceding shield tunnels 4A, 4A
When forming the subsequent shield tunnel 4B in between,
At the same time, a part of the backfill hardening filler 7 constituting the preceding shield tunnels 4A on both sides is excavated at the same time. At this time, since the cylindrical structure 6 constituting the preceding shield tunnel 4A is formed with a small diameter, it is possible to cut only the backfill hardening filler 7 without interfering with the cylindrical structure 6. is there.

そして、上記の如くシールド機10にて2つの先行シー
ルドトンネル4A,4A間を掘削するとともに、その掘削穴
8′内に筒状構造体6を組み立ててゆき、その後その背
面側に裏込め硬化充填材7を打設すれば、第6図に示す
ように、先行シールドトンネル4A,4A,…と連続した後行
シールドトンネル4B,4,…が形成され、これによりトン
ネル構造体2が構築される。
Then, as described above, the shield machine 10 excavates between the two preceding shield tunnels 4A, 4A, assembles the cylindrical structure 6 in the excavation hole 8 ', and then backfills the backside with hardening filling. When the material 7 is cast, as shown in FIG. 6, the following shield tunnels 4B, 4,... That are continuous with the preceding shield tunnels 4A, 4A,. .

ところで、本工法では、このように先行シールドトン
ネル4Aの裏込め硬化充填材7の一部を、後行シールドト
ンネル4Bを形成する際に地山と共にシールド機10にて切
削するため、先行シールドトンネル4Aを構成する裏込め
硬化充填材7としては、初期強度が小さく、経時的にそ
の強度が大となるような性状のものを使用することがよ
り望ましい。他の手段としては、例えば、先行シールド
トンネル4Aの裏込め硬化充填材7として凝結遅延コンク
リートを使用し、後行シールドトンネル4Bの施工後に、
先行シールドトンネル4A内に高温空気(例えば70℃以
上)を送り込み所要の強度を確保する、等の方法を採る
ことも可能である。その際、高温空気の供給は、筒状構
造体6の内部空間を利用することができる。なお、後行
シールドトンネル4B用の裏込め硬化充填材7は高強度コ
ンクリートとすることが望ましい。
By the way, in the present construction method, a part of the backfill hardening filler 7 of the preceding shield tunnel 4A is cut by the shield machine 10 together with the ground when forming the following shield tunnel 4B. As the backfill hardening filler 7 constituting 4A, it is more desirable to use one having such properties that the initial strength is small and the strength increases with time. As another means, for example, using setting delay concrete as backfill hardening filler 7 of the preceding shield tunnel 4A, after the construction of the following shield tunnel 4B,
It is also possible to adopt a method of sending high-temperature air (for example, 70 ° C. or more) into the preceding shield tunnel 4A to secure a required strength. At that time, the supply of the high-temperature air can utilize the internal space of the tubular structure 6. The backfill hardening filler 7 for the trailing shield tunnel 4B is preferably made of high-strength concrete.

そして、上記の如く、シールドトンネル4,4,…により
トンネル構造体2が構築されたならば、地山Gにおける
該トンネル構造体2により囲繞された部分を掘削して前
記トンネル空間3を形成すれば、第1図の如き目的とす
るトンネル1が完成する。トンネル構造体2の内部地山
の掘削は、通常一般に使用される掘削機によって行う
が、前記トンネル構造体2が既に構築され、これにより
地山Gが支持されているので、支保工等は一切設ける必
要はない。
When the tunnel structure 2 is constructed by the shield tunnels 4, 4,... As described above, the portion of the ground G surrounded by the tunnel structure 2 is excavated to form the tunnel space 3. For example, the target tunnel 1 as shown in FIG. 1 is completed. Excavation of the ground inside the tunnel structure 2 is performed by a generally used excavator. However, since the tunnel structure 2 has already been constructed and the ground G is supported by the excavator, no support work or the like is required. No need to provide.

上記トンネル1によれば、トンネル構造体2を、小径
なる多数のシールドトンネル4,4,…により構成するた
め、大断面なるトンネル空間3を確実に形成することが
できる。しかも、トンネル構造体2を構成して連設され
た各シールドトンネル4は、それらシールドトンネル4
を構成する覆工体20が互いにオーバーラップすることに
より一体化されているので、トンネル構造体2を極めて
高強度で、かつ遮水性に優れたものとすることができ
る。さらに、このように、トンネル構造体2がシールド
トンネルにより構成されるものであるため、シールド工
法を適用できる全ての地山に適用することができる。し
かも、使用するシールド機10は極めて小形のもので済む
ため、シールド機に係るコストの大幅な低減化が図れ
る。このため、複数台のシールド機10を用いて効率的な
施工を図ることもできる。
According to the tunnel 1, since the tunnel structure 2 is constituted by a large number of shield tunnels 4, 4,... Having a small diameter, a tunnel space 3 having a large cross section can be reliably formed. In addition, each of the shield tunnels 4 that constitute the tunnel structure 2 and are connected to each other,
Are integrated by overlapping with each other, so that the tunnel structure 2 can have extremely high strength and excellent water shielding. Further, as described above, since the tunnel structure 2 is configured by the shield tunnel, it can be applied to all grounds to which the shield method can be applied. In addition, since the shield machine 10 to be used can be very small, the cost of the shield machine can be significantly reduced. For this reason, efficient construction can be achieved using a plurality of shield machines 10.

また、上記の構築方法によれば、上記構成となるトン
ネル1を確実かつ効率的に実現することが可能となる。
さらに、トンネル構造体2をトンネル空間3に先行して
構築するため、トンネル空間3の掘削時には既に地山G
の安定が完全に図られており、大断面を支保工等を必要
とすることなく、容易かつ能率的に掘削することができ
る。
Further, according to the above construction method, it is possible to realize the tunnel 1 having the above configuration reliably and efficiently.
Furthermore, since the tunnel structure 2 is constructed prior to the tunnel space 3, the ground G
Therefore, it is possible to excavate a large section easily and efficiently without requiring a support or the like.

なお、上記トンネル1の構築方法において、前記先行
シールドトンネル4A,4A,…は、必ずしもそれらの全数を
形成した後に後行シールドトンネル4Bを形成しなければ
ならないものではなく、後行シールドトンネル4Bは、少
なくとも2本の並設される先行シールドトンネル4A,4A
が形成された時点でそれら先行シールドトンネル4A間に
順次形成していってもよい。
In the above tunnel 1 construction method, the preceding shield tunnels 4A, 4A,... Do not necessarily have to form the subsequent shield tunnel 4B after all of them are formed. , At least two side-by-side leading shield tunnels 4A, 4A
May be sequentially formed between the preceding shield tunnels 4A at the time of formation.

次に、第8図は本発明の請求項2に係るトンネルの一
実施例を示したものである。本図において、前記実施例
と同じ構成要素には同符号を付してその説明を省略す
る。
Next, FIG. 8 shows an embodiment of the tunnel according to claim 2 of the present invention. In the figure, the same components as those in the above embodiment are denoted by the same reference numerals, and the description thereof will be omitted.

本実施例に係るトンネル1′は、上記トンネル1にお
いて、前記シールドトンネル4を構成する前記覆工体20
の内部空間内に、コンクリートあるいはモルタル等の硬
化充填材9を中実に充填したものである。
The tunnel 1 'according to the present embodiment is different from the tunnel 1 in that the lining body 20 constituting the shield tunnel 4 is provided.
Is solid filled with a hardening filler 9 such as concrete or mortar.

このトンネル1′によれば、トンネル構造体2の剛性
をさらに向上させることができる。
According to the tunnel 1 ', the rigidity of the tunnel structure 2 can be further improved.

前記トンネル1′を構築するには、前実施例における
トンネル1の構築工程において、上記の如く先行シール
ドトンネル4Aに続いて後行シールドトンネル4Bを形成し
た後、それら各シールドトンネル4,4,…の覆工体20内
(筒状構造体6内)に硬化充填材9を打設する。あるい
はまた、先行シールドトンネル4Aについては、後行シー
ルドトンネル4Bの形成前においてその覆工体20内(筒状
構造体6内)に硬化充填材9を充填してもよい。
To construct the tunnel 1 ', in the construction process of the tunnel 1 in the previous embodiment, after forming the following shield tunnel 4B following the preceding shield tunnel 4A as described above, each of the shield tunnels 4, 4,. The hardening filler 9 is cast in the lining body 20 (in the tubular structure 6). Alternatively, with respect to the preceding shield tunnel 4A, the hardening filler 9 may be filled in the lining body 20 (in the tubular structure 6) before the formation of the following shield tunnel 4B.

第9図は、トンネル構造体2の他の構成例を示したも
ので、上記各実施例に示したものと同じ構成要素には同
符号を付してある。
FIG. 9 shows another example of the structure of the tunnel structure 2, and the same components as those shown in the above embodiments are denoted by the same reference numerals.

本例のものは、後行シールドトンネル4Bを構成する筒
状構造体6を、先行シールドトンネル4Aを構成する筒状
構造体6よりも大径のものとしている。後行シールドト
ンネル4Bは、先行シールドトンネル4Aのように、形成後
において側壁部を切削されることがないので、このよう
に大径の筒状構造体6を形成してもよい。
In this example, the tubular structure 6 constituting the succeeding shield tunnel 4B has a larger diameter than the tubular structure 6 constituting the preceding shield tunnel 4A. Unlike the preceding shield tunnel 4A, the trailing shield tunnel 4B does not have its side walls cut after formation, so the large-diameter tubular structure 6 may be formed in this way.

さらに、第10図は、トンネル構造体2の別の他の構成
例を示したものである。上記各実施例に示したものと同
じ構成要素には同符号を付してある。
Further, FIG. 10 shows another example of another configuration of the tunnel structure 2. The same components as those described in the above embodiments are denoted by the same reference numerals.

上記各実施例で示したシールドトンネル4,4,…の覆工
体20が、筒状構造体6および裏込め硬化充填材7により
成る、いわゆるセグメント覆工法によって構成されたも
のであったのに対し、本実施例のものでは、各シールド
トンネル4,4,…の覆工体20が、場所打ちコンクリート14
により構成されたものとなっている。すなわち、この場
合、覆工体20は、セグメントを用いない場所打ちライニ
ング工法により形成されたものとなっている。本実施例
に係るトンネル構造体2では、隣接するシールドトンネ
ル4どうしにおいて、前記場所打ちコンクリート14(覆
工体20)が互いにオーバーラップしたものとなってい
る。
The lining body 20 of the shield tunnels 4, 4,... Shown in each of the above-described embodiments was formed by a so-called segment lining method comprising the cylindrical structure 6 and the backfill hardening filler 7. On the other hand, in the present embodiment, the lining body 20 of each shield tunnel 4, 4,.
It is constituted by. That is, in this case, the lining body 20 is formed by the cast-in-place lining method without using segments. In the tunnel structure 2 according to this embodiment, the cast-in-place concrete 14 (the lining body 20) overlaps with each other in the adjacent shield tunnels 4.

その他の構成は上記各実施例に示したものと同じであ
る。
Other configurations are the same as those shown in the above embodiments.

また、本実施例における前記トンネル構造体2を形成
するには、上記のものと同様、先行シールドトンネル4
A,4A,…を先行構築した後、それら先行シールドトンネ
ル4Aの間に、該先行シールドトンネル4Aの前記場所打ち
コンクリート14の一部を切削しながら後行シールドトン
ネル4B,4B,…を構築してゆけばよい。
In addition, in order to form the tunnel structure 2 in the present embodiment, similarly to the above, the leading shield tunnel 4 is formed.
After the preceding construction of A, 4A, ..., the following shield tunnels 4B, 4B, ... are constructed between the preceding shield tunnels 4A while cutting a part of the cast-in-place concrete 14 of the preceding shield tunnel 4A. I just need to go.

本発明に係るシールドトンネル4,4,…は、上記の如く
場所打ちライニング工法により形成してもよく、また、
その他の覆工法により形成してもよい。またさらには、
例えばシールドトンネル4,4,…のうち、先行シールドト
ンネル4A,4A,…のみをセグメント覆工法により形成し、
後行シールドトンネル4B,4B,…を場所打ちライニング工
法によって形成するといったように、異なるシールド工
法を併用しても構わない。何れのものであっても、それ
ら隣接形成されたシールドトンネル4の覆工体20の一部
が重合されることにより、各シールドトンネル4,4,…が
一体化され、それにより強固なトンネル構造体2を実現
することができる。
The shield tunnels 4, 4, ... according to the present invention may be formed by the cast-in-place lining method as described above,
It may be formed by another lining method. Or even more
For example, of the shield tunnels 4,4, ..., only the preceding shield tunnels 4A, 4A, ... are formed by the segment lining method,
Different shield construction methods may be used in combination, such as forming the trailing shield tunnels 4B, 4B, ... by a cast-in-place lining method. In any case, the shield tunnels 4, 4,... Are integrated by partly overlapping the lining body 20 of the shield tunnel 4 formed adjacent thereto, thereby forming a strong tunnel structure. The body 2 can be realized.

また、第10図に示した前記トンネル構造体2におい
て、シールドトンネル4を構成する覆工体20の内部空間
に、上述の如く前記硬化充填材9(図示せず)を中実に
充填しても勿論よい。
Further, in the tunnel structure 2 shown in FIG. 10, even if the hardened filler 9 (not shown) is solidly filled in the inner space of the lining body 20 constituting the shield tunnel 4 as described above. Of course.

なお、上記各実施例においては、トンネル1,1′(ト
ンネル構造体2)を共に断面円形のものとして説明した
が、本発明に係る大断面トンネルは断面円形のものに限
定されるものではなく、馬蹄形、半円形、あるいはその
他の断面形状に形成することも無論可能である。その場
合には、連設する各シールドトンネル4,4,…の形成位置
(重なり位置)を、これらシールドトンネル4によって
形成されるトンネル構造体2が所定の断面形状となるよ
う決定すればよい。
In each of the above embodiments, both the tunnels 1 and 1 '(tunnel structure 2) have been described as having a circular cross section. However, the large cross section tunnel according to the present invention is not limited to a circular cross section. Of course, it is also possible to form a horseshoe, a semicircle, or other cross-sectional shapes. In this case, the formation position (overlapping position) of each of the shield tunnels 4, 4,... To be connected may be determined so that the tunnel structure 2 formed by the shield tunnels 4 has a predetermined cross-sectional shape.

また、上記各実施例においては、トンネル構造体2が
縦断面において筒状に閉環された構成のものを説明した
が、本発明に係る大断面トンネルは、例えば第11図に示
すように、トンネル空間3の一部(図示例のものは上半
部)のみを前記トンネル構造体2により構成するように
してもよい。その場合、トンネル底部(インバート部)
には、コンクリート12を打設するようにしてもよく、さ
らには、該コンクリート12を図示しないロックボルトで
補強するようにしてもよい。
Further, in each of the above-described embodiments, the tunnel structure 2 is described as having a configuration in which the tunnel structure is closed in a cylindrical shape in a vertical cross section. Only a part (the upper half in the illustrated example) of the space 3 may be constituted by the tunnel structure 2. In that case, the bottom of the tunnel (invert part)
Then, the concrete 12 may be cast, and the concrete 12 may be reinforced with a lock bolt (not shown).

〔発明の効果〕〔The invention's effect〕

以上説明したとおり、請求項1に係る大断面トンネル
によれば、トンネル構造体を小径なる多数のシールドト
ンネルにより構成するため、大断面のトンネル空間を確
実に形成することができる。しかも、トンネル構造体を
構成して連設される各シールドトンネルは、それらシー
ルドトンネルを構成する覆工体が互いにオーバーラップ
することにより一体化され、これによりトンネル構造体
を極めて高強度で、かつ遮水性に優れたものとすること
ができる。さらに、このようにトンネル構造体がシール
ドトンネルにより構成されるものであるため、シールド
工法を適用できる全ての地山に適用することができ、し
かも、使用するシールド機は極めて小形のもので済むた
め、シールド機に係るコストの大幅な低減化が図れる。
このため、複数台のシールド機を用いて効率的な施工を
図ることもできる。
As described above, according to the large-section tunnel according to the first aspect, since the tunnel structure is constituted by a large number of shield tunnels having small diameters, a tunnel space having a large section can be reliably formed. Moreover, the shield tunnels that are continuously formed to form the tunnel structure are integrated by overlapping the linings that form the shield tunnels, thereby making the tunnel structure extremely strong and It can be excellent in water blocking. Furthermore, since the tunnel structure is constituted by a shield tunnel as described above, it can be applied to all grounds to which the shield method can be applied, and furthermore, the shield machine to be used can be extremely small. In addition, the cost of the shield machine can be significantly reduced.
For this reason, efficient construction can be achieved using a plurality of shield machines.

また、請求項2に係る大断面トンネルによれば、請求
項1に係る大断面トンネルにおけるトンネル構造体の剛
性をさらに向上させることができ、以てより強固な大断
面トンネルを実現することができる。
Further, according to the large-section tunnel according to the second aspect, the rigidity of the tunnel structure in the large-section tunnel according to the first aspect can be further improved, so that a stronger large-section tunnel can be realized. .

また、請求項3に係る大断面トンネルの構築方法によ
れば、上記請求項1に係る大断面トンネルを確実かつ効
率的に実現することができる。さらに、トンネル構造体
をトンネル空間に先行して構築するため、トンネル空間
の掘削前に予め掘削地山の安定を図ることができ、大断
面を支保工等を用いることなく容易かつ能率的に掘削す
ることができる。
According to the method for constructing a large-section tunnel according to the third aspect, the large-section tunnel according to the first aspect can be reliably and efficiently realized. Furthermore, since the tunnel structure is constructed ahead of the tunnel space, the excavation site can be stabilized in advance before the tunnel space is excavated, and a large section can be easily and efficiently excavated without using a support or the like. can do.

そして、上記請求項2の大断面トンネルは請求項4に
記載した構築方法により実現することができる。
The large-section tunnel according to the second aspect can be realized by the construction method described in the fourth aspect.

【図面の簡単な説明】[Brief description of the drawings]

第1図は本発明の請求項1に係る大断面トンネルの一実
施例を示す正面断面図、第2図は当実施例によるトンネ
ル構造体を示す部分正面断面図、第3図ないし第6図は
当実施例に係るトンネル構造体の構築方法を説明するも
ので、それぞれトンネル構造体の部分正面大断面、第7
図はトンネル構造体を構成するシールドトンネルの構築
状態を示す側断面図、第8図は本発明の請求項3に係る
大断面トンネルの一実施例を示す正面大断面、第9図は
トンネル構造体の他の構成例を示す部分正面大断面、第
10図はトンネル構造体の別の他の構成例を示す部分正面
断面図、第11図は大断面トンネルのその他の構成例を示
す部分正面断面図である。 G……地山、1,1′……大断面トンネル、 2……トンネル構造体、 3……トンネル空間、 4……シールドトンネル、 4A……先行シールドトンネル、 4B……後行シールドトンネル、 9……硬化充填材、10……シールド機、 20……覆工体。
FIG. 1 is a front sectional view showing an embodiment of a large-section tunnel according to claim 1 of the present invention, FIG. 2 is a partial front sectional view showing a tunnel structure according to the present embodiment, and FIGS. 7 illustrates a method of constructing a tunnel structure according to the present embodiment.
FIG. 8 is a side sectional view showing a construction state of a shield tunnel constituting a tunnel structure, FIG. 8 is a front large section showing an embodiment of a large section tunnel according to claim 3 of the present invention, and FIG. 9 is a tunnel structure. Partial front large cross section showing another configuration example of the body,
FIG. 10 is a partial front sectional view showing another configuration example of the tunnel structure, and FIG. 11 is a partial front sectional view showing another configuration example of the large-section tunnel. G: Mt. Chiyama, 1,1 ': Large tunnel, 2: Tunnel structure, 3: Tunnel space, 4: Shield tunnel, 4A: Shield tunnel, 4B: Shield tunnel, 9 ... hardened filler, 10 ... shield machine, 20 ... lining body.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 三宅 紀治 東京都中央区京橋2丁目16番1号 清水 建設株式会社内 (72)発明者 傳田 篤 東京都中央区京橋2丁目16番1号 清水 建設株式会社内 (56)参考文献 特開 平2−144499(JP,A) (58)調査した分野(Int.Cl.6,DB名) E21D 13/02 E21D 9/00 E21D 9/06 301────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Kiharu Miyake 2-16-1 Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Atsushi Denda 2-161 Kyobashi, Chuo-ku, Tokyo Shimizu (56) References JP-A-2-144499 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E21D 13/02 E21D 9/00 E21D 9/06 301

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】アーチ状または筒状に形成され地山の土圧
に抗して内部空間を形成するトンネル構造体と、該トン
ネル構造体の内側に形成されるトンネル空間とからなる
大断面トンネルであって、 前記トンネル構造体は、構築すべきトンネルの長手方向
に形成され互いに隣接する多数のシールドトンネルによ
り構成され、かつ隣接形成された二つの前記シールドト
ンネルのうち、いずれか一方のシールドトンネルの覆工
体の一部が切削され、ここに他方のシールドトンネルの
覆工体が位置して形成されることにより、これらシール
ドトンネルが互いに重合して一体化されていることを特
徴とする大断面トンネル。
1. A tunnel having a large cross section comprising: a tunnel structure formed in an arched or cylindrical shape and forming an internal space against the earth pressure of the ground; and a tunnel space formed inside the tunnel structure. The tunnel structure is formed of a number of shield tunnels formed in the longitudinal direction of a tunnel to be constructed and adjacent to each other, and one of the two shield tunnels formed adjacent to each other. A part of the lining body is cut, and the lining body of the other shield tunnel is formed and positioned here, so that these shield tunnels are overlapped and integrated with each other. Cross section tunnel.
【請求項2】請求項1記載の大断面トンネルにおいて、
前記覆工体の内部に硬化充填材が中実に充填されてなる
ことを特徴とする大断面トンネル。
2. The large-section tunnel according to claim 1,
A large-section tunnel, wherein a hardened filler is solidly filled inside the lining body.
【請求項3】地山内に多数本のシールドトンネルを径方
向に連設することによりアーチ状または筒状のトンネル
構造体を先行構築した後、地山の該トンネル構造体によ
り囲まれた部分を掘削することにより構築する大断面ト
ンネルの構築方法であって、 前記シールドトンネルは、シールド機を掘進させる第1
工程と、シールド機により形成された掘削穴の壁面を覆
工する第2工程と、により構築し、 かつ、前記トンネル構造体は、前記シールドトンネルを
一つ置きに先行構築した後、それら先行シールドトンネ
ルの間に後行シールドトンネルを形成することにより構
築し、しかも、該後行シールドトンネルの第1工程は、
前記先行シールドトンネルの覆工体の一部を地山と共に
切削しながら行うことを特徴とする大断面トンネルの構
築方法。
3. An arched or tubular tunnel structure is pre-constructed by connecting a large number of shield tunnels in the ground in the radial direction, and then a portion of the ground surrounded by the tunnel structure is removed. A method for constructing a large-section tunnel constructed by excavating, wherein the shield tunnel includes a first tunnel for excavating a shield machine.
And a second step of lining a wall surface of the excavation hole formed by the shield machine. The tunnel structure is constructed by precedingly constructing every other shield tunnel, It is constructed by forming a trailing shield tunnel between tunnels, and the first step of the trailing shield tunnel is:
A method for constructing a large-section tunnel, characterized in that a part of a lining body of the preceding shield tunnel is cut together with a ground.
【請求項4】請求項3記載の大断面トンネルの構築方法
において、前記シールドトンネルを、シールド機を掘進
させる第1工程と、シールド機により形成された掘削穴
の壁面を覆工する第2工程と、前記覆工体の内部に硬化
充填材を充填する第3工程と、により構築することを特
徴とする大断面トンネルの構築方法。
4. A method for constructing a tunnel having a large cross section according to claim 3, wherein a first step of excavating a shield machine in the shield tunnel and a second step of lining a wall surface of an excavation hole formed by the shield machine. And a third step of filling the inside of the lining body with a hardening filler.
JP2171938A 1990-01-11 1990-06-29 Large section tunnel and its construction method Expired - Fee Related JP2849605B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2171938A JP2849605B2 (en) 1990-01-11 1990-06-29 Large section tunnel and its construction method

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2-4074 1990-01-11
JP407490 1990-01-11
JP2171938A JP2849605B2 (en) 1990-01-11 1990-06-29 Large section tunnel and its construction method

Publications (2)

Publication Number Publication Date
JPH03250195A JPH03250195A (en) 1991-11-07
JP2849605B2 true JP2849605B2 (en) 1999-01-20

Family

ID=26337797

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2171938A Expired - Fee Related JP2849605B2 (en) 1990-01-11 1990-06-29 Large section tunnel and its construction method

Country Status (1)

Country Link
JP (1) JP2849605B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100426320B1 (en) * 2000-11-28 2004-04-08 구영숙 Process for constructing a structure for excavation in underground
JP6191814B2 (en) * 2013-03-19 2017-09-06 株式会社大林組 Construction method of large section tunnel
JP6884897B2 (en) * 2020-02-07 2021-06-09 戸田建設株式会社 Tunnel structure manufacturing method and water stoppage method

Also Published As

Publication number Publication date
JPH03250195A (en) 1991-11-07

Similar Documents

Publication Publication Date Title
JP2816397B2 (en) Method of expanding and reducing diameter of tunnel
JP6147818B2 (en) Large section tunnel construction method and large section lining body
JP2788953B2 (en) Structure of tunnel structure
JP6127193B1 (en) Construction method of large section underground structure
JP2869877B2 (en) Tunnel merging method and branching method
JP6257814B1 (en) Construction method of large section underground structure
JP2849605B2 (en) Large section tunnel and its construction method
JP2788952B2 (en) Large section tunnel
JP2942874B2 (en) How to join tunnels
JP6062098B1 (en) Construction method of large section underground structure
JP4760548B2 (en) Side-by-side tunnel structure and its construction method
JP2899661B2 (en) Large section tunnel and its construction method
JPH0464697A (en) Construction of tunneling space
JP2788956B2 (en) How to join tunnels
JP2788957B2 (en) How to join tunnels
JP4730607B2 (en) Construction method of shield tunnel
JP2818839B2 (en) Tunnel merging method and branching method
JP3584416B2 (en) Tunnel and its construction method
JP3482625B2 (en) Large section tunnel and construction method
JP2018204310A (en) Underground widened portion construction method
JPH0548840B2 (en)
JP3900686B2 (en) Underground structure and its construction method
JP3900684B2 (en) Construction method for underground structures
JP3608135B2 (en) Construction method of large section tunnel
JP2700261B2 (en) How to build an underground space

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091113

Year of fee payment: 11

LAPS Cancellation because of no payment of annual fees