EP3210847B1 - Method and system for operating a confined track section with a number of points assembled therein - Google Patents

Method and system for operating a confined track section with a number of points assembled therein Download PDF

Info

Publication number
EP3210847B1
EP3210847B1 EP16156826.6A EP16156826A EP3210847B1 EP 3210847 B1 EP3210847 B1 EP 3210847B1 EP 16156826 A EP16156826 A EP 16156826A EP 3210847 B1 EP3210847 B1 EP 3210847B1
Authority
EP
European Patent Office
Prior art keywords
route
points
integrated
switch
switches
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Revoked
Application number
EP16156826.6A
Other languages
German (de)
French (fr)
Other versions
EP3210847A1 (en
Inventor
Rolf Weber
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Siemens Mobility AG
Original Assignee
Siemens Mobility AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=55442664&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=EP3210847(B1) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Siemens Mobility AG filed Critical Siemens Mobility AG
Priority to EP16156826.6A priority Critical patent/EP3210847B1/en
Publication of EP3210847A1 publication Critical patent/EP3210847A1/en
Application granted granted Critical
Publication of EP3210847B1 publication Critical patent/EP3210847B1/en
Revoked legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B61RAILWAYS
    • B61LGUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
    • B61L17/00Switching systems for classification yards
    • B61L17/02Details, e.g. indicating degree of track filling
    • B61L17/023Signalling; Signals with multiple indicating means
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B61RAILWAYS
    • B61LGUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
    • B61L11/00Operation of points from the vehicle or by the passage of the vehicle
    • B61L11/08Operation of points from the vehicle or by the passage of the vehicle using electrical or magnetic interaction between vehicle and track
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B61RAILWAYS
    • B61LGUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
    • B61L9/00Illumination specially adapted for points, form signals, or gates
    • B61L9/04Illumination specially adapted for points, form signals, or gates electric

Definitions

  • the present invention relates to a method and a system for operating a self-contained track area with a number of switches arranged therein.
  • the DE 199 05 916 A1 discloses the setting of a route from the vehicle when entering the maneuvering area and the signaling of this route on the switches.
  • the present invention is therefore based on the object of specifying a method and a system for operating a delimited track area with a number of switches arranged therein, which allow a certain degree of safety to be guaranteed and at the same time a certain degree of flexibility to offer the changeover of switches in the delimited track area.
  • the second signaling elements it is apparent to the shunting staff, for example, if one or more points are or are currently set for a desired vehicle. It is then the responsibility of the personnel operating in the track area to determine whether the position of a switch is changed if it is signaled at the same time by the second signaling elements that this switch is being changed for a set route.
  • the first and the second signaling element can also be integrated, for example, in a single light source and signal the desired statement by coding the display, such as fast or slow flashing.
  • At least one switch integrated in the route is signaled optically and / or acoustically by the second signaling elements that this at least one switch is to be used for a route to be set.
  • the staff in the track area can be signaled in advance of the construction of the route that a strain on this at least one switch is imminent for a route to be set. It is then also at the discretion of the staff in the track area to decide whether this switch at least one turnout should now be changed, or whether the load on the route is first waited for and the change is only made after the route has been dissolved.
  • At least one in the Track integrated switch is optically and / or acoustically signaled by the second signaling elements that this at least one switch for the set route should no longer be used and thus the route can be at least partially resolved. This gives the staff in the track area the information that a switch is now available again for an individual, independent change after being used for a track.
  • this color code could also be used in the first signaling elements which signal the position of the switch.
  • the "DEFLECTED" position could, for example, be shown in red to indicate the stress on the switch in the deflected position for a set travel path. Similarly, with the rest of the above Color codes are traversed.
  • Figure 1 shows a schematic representation of a switch W in undeflected position (a) and deflected position (b).
  • the position of the switch W is indicated by two first display elements 2a, 2b.
  • These first display elements 2a, 2b are located directly next to the switch W in the track ballast 4.
  • These first display elements 2a, 2b are also known in technical jargon as dwarf signals and / or turnout signals.
  • a second display element 6 is now arranged in the immediate vicinity of the first display elements 2a, 2b in the track ballast 4, which, in the case of the lighting shown here, signals that this switch W is currently being used to provide a route and thus a changeover by hand how this can be done by shunting personnel, for example, can lead to a safety problem.
  • FIG. 2 shows a schematic representation of a track area 8, in which a plurality of switches (only switches W1 to W6 are entered) are integrated.
  • each switch is equipped with the first and second display elements 2a, 2b, 6 shown in FIG.
  • a route 10 has now been drawn in and set by an actuating unit 12 while using switches W1 to W6.
  • the second display elements 6 have also been drawn in as a shining light bulb symbol. This signals that the associated switch for the set travel path 10 is claimed.
  • the shunting personnel working in the track area 8 is reliably signaled that when one of the switches W1 to W6 is adjusted, the currently set travel path 10 is no longer guaranteed (safe). It is therefore at the discretion of the shunting staff whether a possible turnout should take place.
  • a test unit likewise integrated in the actuating unit 12 can check the current positions of the switches required for the route.
  • the second display elements of the corresponding switches can already be made to flash.
  • the corresponding second display elements 6 light up permanently. Only when the route 10 can be broken again can the second display elements 6 again start flashing to signal that the corresponding switch is no longer used for a set route.
  • a different flashing frequency can also be used to signal whether the associated switch is in the phase of the route 10 to be set or to be released.

Description

Die vorliegende Erfindung bezieht sich auf ein Verfahren und ein System zum Betreiben eines in sich abgegrenzten Gleisbereichs mit einer Anzahl von darin angeordneten Weichen.The present invention relates to a method and a system for operating a self-contained track area with a number of switches arranged therein.

In sich abgrenzte Gleisbereiche bestehen beispielsweise in Form von Rangierbereichen, Depot-Bereichen, bestimmten Bereichen eines Bahnhofs und dergleichen. In derartigen in sich abgrenzten Gleisbereichen befindet sich in der Regel eine Vielzahl von Weichen, für die das Bedürfnis besteht sie flexibel umstellen zu können, zum Beispiel vor Ort durch das Rangierpersonal. Daneben gibt es aber auch den Bedarf, zum Beispiel regelmässig wiederkehrende Fahrwege innerhalb des in sich abgegrenzten Gleisbereichs unter Inanspruchnahme von mehreren Weichen und der für den Fahrweg entsprechend vorbestimmten Weichenlage einstellen zu können. Bei kleineren Bahnunternehmungen und in kleinen Rangierbereichen wird das Einstellen der Weichen lokal durch das Rangierpersonal in eigener Verantwortung durchgeführt. Es besteht daher das Bedürfnis die Weichen auf zwei grundlegende Arten stellen zu können:

  1. a) einzelne Weichen individuell durch das Rangierpersonal umstellen zu können; und
  2. b) mehrere Weichen in Folge einstellen zu können, um einen geschlossenen Fahrweg durch den Gleisbereich bzw. eines Teils davon zu bilden.
Defined track areas exist, for example, in the form of shunting areas, depot areas, certain areas of a train station and the like. In such delimited track areas there are usually a large number of switches for which there is a need to be able to change them flexibly, for example on site by the shunting staff. In addition, there is also the need, for example, to be able to set regularly recurring routes within the delimited track area using several switches and the switch position predefined for the route. In the case of smaller railway companies and in small shunting areas, the shunting staff is responsible for setting the points locally. There is therefore a need to set the course in two basic ways:
  1. a) individual switches can be changed individually by the shunting staff; and
  2. b) being able to set several switches in a row in order to form a closed route through the track area or a part thereof.

Heutzutage ist es möglich, bei grösseren Gleisbereichen durch ein Stellwerk vorbestimmte Fahrwege zuzulassen. Die am Fahrweg beteiligten Weichen werden dann vom Stellwerk derart gestellt, dass Kollisionen mit anderen Fahrzeugen ausgeschlossen werden. So sind zum Beispiel Rangiersignale vorgesehen, die von einem Lokführer ein Halten verlangen. Sind jedoch derartige Fahrwege eingestellt, lässt das Stellwerk keine Weichenumstellung für jede der am Fahrweg beteiligten Weichen zu. Natürlich ist es leicht ersichtlich, dass hierdurch die Flexibilität der betrieblichen Abläufe unterbunden wird. Gleichzeitig bietet diese Vorgehensweise jedoch eine maximale Sicherheit zur Vermeidung von Kollisionen oder Entgleisungen und dergleichen.Nowadays, it is possible to allow predetermined routes through a signal box for larger track areas. The turnouts involved in the route are then set by the signal box in such a way that collisions with other vehicles are excluded. For example, shunting signals are provided that require an engine driver to stop. However, if such routes are set, the interlocking does not allow the switch to be changed for each of the switches involved in the route. Of course, it is easy to see that this prevents the flexibility of operational processes. At the same time, this approach offers a maximum Security to avoid collisions or derailments and the like.

Die DE 199 05 916 A1 offenbart die Einstellung eines Fahrweges vom Fahrzeug aus bei Einfahrt in den Rangierbereich und die Signalisierung dieses Fahrweges an den Weichen.The DE 199 05 916 A1 discloses the setting of a route from the vehicle when entering the maneuvering area and the signaling of this route on the switches.

Der vorliegenden Erfindung liegt daher die Aufgabe zugrunde, ein Verfahren und ein System zum Betreiben eines in sich abgegrenzten Gleisbereichs mit einer Anzahl von darin angeordneten Weichen anzugeben, welche es erlauben, ein gewisses Mass an Sicherheit zu garantieren und gleichzeitig auch ein gewisses Mass an Flexibilität bei der Umstellung von Weichen in dem in sich abgegrenzten Gleisbereich anzubieten.The present invention is therefore based on the object of specifying a method and a system for operating a delimited track area with a number of switches arranged therein, which allow a certain degree of safety to be guaranteed and at the same time a certain degree of flexibility to offer the changeover of switches in the delimited track area.

Diese Aufgabe wird bezüglich des Verfahrens erfindungsgemäss durch ein Verfahren zum Betreiben eines in sich abgegrenzten Gleisbereichs mit einer Anzahl von darin angeordneten Weichen, welches die folgenden Verfahrensschritte umfasst:

  1. a) Einstellen eines Fahrweges unter Inanspruchnahme der in den Fahrweg integrierten Weichen und einer für die Weichen dieses Fahrwegs vorbestimmten Weichenlage;
  2. b) Überprüfen der aktuellen Lage der in den Fahrweg integrierten Weichen und ggfs. Verstellen der Weichen in die für diesen Fahrweg vorbestimmten Weichenlagen;
  3. c) Anzeigen der Weichenlage durch erste Signalisierungselemente jeweils an jeder der in den Fahrweg integrierten Weichen; und
  4. d) Optisches und/oder akustisches Signalisieren durch zweite Signalisierungselemente an mindestens einer in den Fahrweg integrierten Weiche, dass diese mindestens eine Weiche für einen eingestellten Fahrweg in Anspruch genommen ist.
With regard to the method, this object is achieved according to the invention by a method for operating a delimited track area with a number of switches arranged therein, which comprises the following method steps:
  1. a) setting a route using the points integrated in the route and a predetermined position for the points of this route;
  2. b) checking the current position of the switches integrated in the guideway and, if necessary, adjusting the switches to the switch positions predetermined for this guideway;
  3. c) display of the turnout position by first signaling elements in each case on each of the turnouts integrated into the route; and
  4. d) Optical and / or acoustic signaling by means of second signaling elements on at least one switch integrated in the route that this at least one switch is used for a set route.

Bezüglich des Systems wird diese Aufgabe erfindungsgemäss durch ein System zum Betreiben eines in sich abgegrenzten Gleisbereichs mit einer Anzahl von darin angeordneten Weichen gelöst, umfassend:

  1. a) eine Stelleinrichtung zum Einstellen eines Fahrweges unter Inanspruchnahme der in den Fahrweg integrierten Weichen und zum Einstellen einer für die Weichen dieses Fahrwegs vorbestimmten Weichenlage;
  2. b) eine Prüfeinrichtung zum Überprüfen der aktuellen Lage der in den Fahrweg integrierten Weichen und ggfs. Verstellen der Weichen in den für diesen Fahrweg vorbestimmten Weichenlagen durch die Stelleinrichtung;
  3. c) erste Signalisierungselemente zum Anzeigen der Weichenlage jeweils an jeder der in den Fahrweg integrierten Weichen; und
  4. d) zweite Signalisierungselemente zum optischen und/oder akustischen Signalisieren an einer in den Fahrweg integrierten Weiche, dass diese Weichen für einen eingestellten Fahrweg in Anspruch genommen sind.
With regard to the system, this object is achieved according to the invention by a system for operating a delimited track area with a number of switches arranged therein, comprising:
  1. a) an actuating device for setting a route using the switches integrated in the route and for setting a predetermined switch position for the switches of this route;
  2. b) a test device for checking the current position of the switches integrated in the route and, if necessary, adjusting the switches in the switch positions predetermined for this route by the Setting device;
  3. c) first signaling elements for displaying the turnout position on each of the turnouts integrated into the route; and
  4. d) second signaling elements for optical and / or acoustic signaling on a switch integrated in the route that these switches are used for a set route.

Auf diese Weise wird nun eine sehr gute Balance zwischen den Sicherheitsanforderungen und den Wünschen nach Flexibilität bei der Weichenumstellung erzielt. Dank der zweiten Signalisierungselemente ist es beispielsweise für das Rangierpersonal ersichtlich, wenn aktuell eine oder mehrere Weichen für einen gewünschten Fahrzeug eingestellt ist bzw. sind. Es liegt dann in der Verantwortungsgewalt des im Gleisbereich agierenden Personals, ob die Lage einer Weiche umgestellt wird, wenn gleichzeitig durch die zweiten Signalisierungselemente signalisiert ist, dass diese Weiche für eine eingestellten Fahrweg verändert wird. Das erste und das zweite Signalisierungselement können auch beispielsweise in eine einzige Lichtquelle integriert sein und durch die Codierung der Anzeige, wie zum Beispiel schnelles oder langsames Blinken, die gewünschte Aussage signalisieren.In this way, a very good balance between the safety requirements and the wishes for flexibility when switching the points is achieved. Thanks to the second signaling elements, it is apparent to the shunting staff, for example, if one or more points are or are currently set for a desired vehicle. It is then the responsibility of the personnel operating in the track area to determine whether the position of a switch is changed if it is signaled at the same time by the second signaling elements that this switch is being changed for a set route. The first and the second signaling element can also be integrated, for example, in a single light source and signal the desired statement by coding the display, such as fast or slow flashing.

In einer vorteilhaften Ausgestaltung der vorliegenden Erfindung kann es vorgesehen sein, dass an mindestens einer in den Fahrweg integrierte Weiche durch die zweiten Signalisierungselemente optisch und/oder akustisch signalisiert wird, dass diese mindestens eine Weiche für einen einzustellenden Fahrweg in Anspruch genommen werden soll. Auf diese Weise kann dem Personal im Gleisbereich bereits im Vorfeld des Aufbaus des Fahrwegs signalisiert werden, dass eine Beanspruchung dieser mindestens einen Weiche für einen einzustellenden Fahrweg unmittelbar bevorsteht. Auch liegt es dann im Ermessen des Personals im Gleisbereich zu entscheiden, ob diese mindestens eine Weiche nun noch umgestellt werden soll, oder ob zunächst die Beanspruchung für den Fahrweg abgewartet und die Umstellung dann erst nach der Auflösung dieses Fahrwegs vorgenommen wird.In an advantageous embodiment of the present invention it can be provided that at least one switch integrated in the route is signaled optically and / or acoustically by the second signaling elements that this at least one switch is to be used for a route to be set. In this way, the staff in the track area can be signaled in advance of the construction of the route that a strain on this at least one switch is imminent for a route to be set. It is then also at the discretion of the staff in the track area to decide whether this switch at least one turnout should now be changed, or whether the load on the route is first waited for and the change is only made after the route has been dissolved.

In einer weiteren vorteilhaften Ausgestaltung der vorliegenden Erfindung kann es vorgesehen sein, dass an mindestens einer in den Fahrweg integrierten Weiche durch die zweiten Signalisierungselemente optisch und/oder akustisch signalisiert wird, dass diese mindestens eine Weiche für den eingestellten Fahrweg nicht länger in Anspruch genommen werden soll und somit der Fahrweg zumindest teilweise aufgelöst werden kann. Damit erhält das Personal im Gleisbereich hier die Information, dass eine Weiche nun mehr nach einer Beanspruchung für einen Fahrweg nun wieder für eine individuelle eigenverantwortliche Umstellung zur Verfügung steht.In a further advantageous embodiment of the present invention, it can be provided that at least one in the Track integrated switch is optically and / or acoustically signaled by the second signaling elements that this at least one switch for the set route should no longer be used and thus the route can be at least partially resolved. This gives the staff in the track area the information that a switch is now available again for an individual, independent change after being used for a track.

In der Regel sind die ersten und zweiten Signalisierungselemente optischer Art, damit beispielsweise auch aus mässiger Entfernung, wie z.B. von einem Führerstand einer Lok aus, die Lage der Weiche und ggfs. ihre Beanspruchung für einen Fahrweg erkennbar ist. Im Besonderen die zweiten Signalisierungselemente können unterschiedlich ausgestaltet sein. So kann beispielsweise eine einfache zusätzliche Lichtquelle vorgesehen sein, deren Leuchten die Beanspruchung einer Weiche für einen Fahrweg anzeigt. Es könnte aber auch ein Ampelsystem vorgesehen sein, wobei mit:

  1. a) "GRÜN" signalisiert wird, dass die Weiche frei ist; und/oder
  2. b) "ROT" signalisiert wird, dass die Weiche für einen Fahrweg in Anspruch genommen ist; und/oder
  3. c) "GELB" signalisiert wird, dass die Weiche für einen Fahrweg in Anspruch genommen wird; und/oder
  4. d) "GELB blinkend" signalisiert wird, dass die Weiche für einen Fahrweg in Anspruch genommen war und nun wieder frei wird.
As a rule, the first and second signaling elements are optical, so that, for example, the position of the switch and, if necessary, its stress on a route can also be seen from a moderate distance, such as from a driver's cab of a locomotive. In particular, the second signaling elements can be designed differently. For example, a simple additional light source can be provided, the lights of which indicate the use of a switch for a route. However, a traffic light system could also be provided, with:
  1. a) "GREEN" is signaled that the switch is free; and or
  2. b) "RED" is signaled that the switch is used for a route; and or
  3. c) "YELLOW" indicates that the switch is being used for a route; and or
  4. d) "YELLOW flashing" indicates that the switch was used for a route and is now free again.

Falls zusätzliche Leuchtelemente für diese Signalisierung vermieden werden sollen, könnte dieser Farbcode auch in den ersten Signalisierungselementen, die die Lage der Weiche signalisieren, zum Einsatz kommen. Die Stellung "ABGELENKT" könnte beispielsweise mit roter Farbe dargestellt sein, um die Beanspruchung der Weiche in abgelenkter Stellung für einen eingestellten Fahrweg anzuzeigen. Analog könnte mit den übrigen o.g. Farbcodes verfahren werden.If additional lighting elements for this signaling are to be avoided, this color code could also be used in the first signaling elements which signal the position of the switch. The "DEFLECTED" position could, for example, be shown in red to indicate the stress on the switch in the deflected position for a set travel path. Similarly, with the rest of the above Color codes are traversed.

Vorteilhafte Ausgestaltungen der vorliegenden Erfindung werden nachfolgend detailliert mit Bezug auf die anhängenden Zeichnungen erläutert. Dabei zeigt:

Fig. 1
in schematischer Darstellung eine Weiche mit ersten und zweiten Anzeigeelementen für die beiden möglichen Stellungen der Weiche; und
Fig. 2
in schematischer Darstellung einen Gleisbereich mit darin integrierten Weichen mit den ersten und zweiten Anzeigeelementen gemäss Figur 1.
Advantageous embodiments of the present invention are explained in detail below with reference to the attached drawings. It shows:
Fig. 1
a schematic representation of a switch with first and second display elements for the two possible positions of the switch; and
Fig. 2
a schematic representation of a track area with switches integrated therein with the first and second display elements according to Figure 1 ,

Figur 1 zeigt in schematischer Darstellung eine Weiche W in nichtabgelenkte Lage (a) und abgelenkter Lage (b). Die Stellung der Weiche W wird durch zwei erste Anzeigeelemente 2a, 2b angezeigt. Diese ersten Anzeigeelemente 2a, 2b befinden sind unmittelbar neben der Weiche W im Gleisschotter 4. Diese ersten Anzeigeelemente 2a, 2b sind im Fachjargon auch als Zwergsignale und/oder Weichensignale bekannt. Zusätzlich ist aber nun ein zweites Anzeigeelement 6 in unmittelbarer Nähe zu den ersten Anzeigeelementen 2a, 2b im Gleisschotter 4 angeordnet, dass im Fall des hier gezeigten Aufleuchtens signalisiert, dass diese Weiche W aktuell für eine Bereitstellung eines Fahrwegs beansprucht wird und damit ein Umstellen von Hand, wie dies beispielsweise durch Rangierpersonal vorgenommen werden kann, zu einem Sicherheitsproblem führen kann. Figure 1 shows a schematic representation of a switch W in undeflected position (a) and deflected position (b). The position of the switch W is indicated by two first display elements 2a, 2b. These first display elements 2a, 2b are located directly next to the switch W in the track ballast 4. These first display elements 2a, 2b are also known in technical jargon as dwarf signals and / or turnout signals. In addition, however, a second display element 6 is now arranged in the immediate vicinity of the first display elements 2a, 2b in the track ballast 4, which, in the case of the lighting shown here, signals that this switch W is currently being used to provide a route and thus a changeover by hand how this can be done by shunting personnel, for example, can lead to a safety problem.

Figur 2 zeigt in schematischer Darstellung einen Gleisbereich 8, in den eine Vielzahl von Weichen (eingetragen sind nur die Weichen W1 bis W6) integriert. Jede Weiche ist aber prinzipiell mit den in Figur 1 gezeigten ersten und zweiten Anzeigeelementen 2a, 2b, 6 ausgestattet. Mit einer dickeren Linie ist in der Figur 2 nun ein Fahrweg 10 eingezeichnet und von einer Stelleinheit 12 unter Beanspruchung der Weichen W1 bis W6 eingestellt worden. Aus diesem Grund sind auch die zweiten Anzeigeelemente 6 als leuchtendes Glühlampensymbol eingezeichnet worden. Damit wird signalisiert, dass die zugehörige Weiche für den eingestellten Fahrweg 10 beansprucht ist. Somit ist beispielsweise das in dem Gleisbereich 8 tätige Rangierpersonal sicher signalisiert, dass bei der Verstellung einer der Weichen W1 bis W6 der aktuell eingestellte Fahrweg 10 nicht mehr garantiert (sicher) ist. Es liegt daher im Ermessen des Rangierpersonal, ob ein allfälliger Weichenumlauf erfolgen soll. Figure 2 shows a schematic representation of a track area 8, in which a plurality of switches (only switches W1 to W6 are entered) are integrated. In principle, however, each switch is equipped with the first and second display elements 2a, 2b, 6 shown in FIG. With a thicker line is in the Figure 2 a route 10 has now been drawn in and set by an actuating unit 12 while using switches W1 to W6. For this reason, the second display elements 6 have also been drawn in as a shining light bulb symbol. This signals that the associated switch for the set travel path 10 is claimed. Thus, for example, the shunting personnel working in the track area 8 is reliably signaled that when one of the switches W1 to W6 is adjusted, the currently set travel path 10 is no longer guaranteed (safe). It is therefore at the discretion of the shunting staff whether a possible turnout should take place.

Nachdem die Stelleinheit 12 einen Fahrweg anfordert, kann eine ebenfalls in die Stelleinheit 12 integrierte Prüfeinheit die aktuellen Lagen der für den Fahrweg erforderlichen Weichen prüfen. Während dieser Prüfdauer können die zweiten Anzeigeelemente der entsprechenden Weichen bereits zum Blinken gebracht werden. Ist die Prüfung abgeschlossen und sind alle Weichen in die für diesen Fahrweg erforderlichen Weichenlagen gebracht worden, leuchten die entsprechenden zweiten Anzeigeelemente 6 dauerhaft auf. Erst wenn der Fahrweg 10 wieder aufgelöst werden kann, können die zweiten Anzeigeelemente 6 wieder in den Blinkbetrieb gehen, um zu signalisieren, dass die entsprechende Weiche nicht mehr für einen eingestellten Fahrweg in Anspruch genommen wird. Mit einer unterschiedlichen Blinkfrequenz kann auch noch signalisiert werden, ob sich die zugehörige Weiche in der Phase des einzustellenden oder aufzulösenden Fahrwegs 10 befindet.After the actuating unit 12 requests a route, a test unit likewise integrated in the actuating unit 12 can check the current positions of the switches required for the route. During this test period, the second display elements of the corresponding switches can already be made to flash. When the test is complete and all switches have been brought into the switch positions required for this route, the corresponding second display elements 6 light up permanently. Only when the route 10 can be broken again can the second display elements 6 again start flashing to signal that the corresponding switch is no longer used for a set route. A different flashing frequency can also be used to signal whether the associated switch is in the phase of the route 10 to be set or to be released.

Claims (6)

  1. Method for operating a confined track section (8) with a number of points (W, W1 to W6) arranged therein, comprising the steps:
    a) setting of a route (10) utilising the points (W1 to W6) integrated into the route (10) and a predetermined point position for the points (W1 to W6) of this route (10);
    b) checking the current position of the points (W1 to W6) integrated into the route (10) and if necessary, adjusting the points (W1 to W6) into the point position predetermined for this route (10);
    c) displaying the point position by way of first signalling elements in each case at each of the points (W1 to W6) integrated into the route (8), and
    characterised by
    d) optical and/or acoustic signalling by way of second signalling elements at each of the points (W1 to W6) integrated into the route (10), such that the points (W1 to W6) are used for a set route (10).
  2. Method according to claim 1, characterised in that at each of the points (W1 to W6) integrated into the route (10), signals are emitted optically and/or acoustically by way of the second signalling elements, such that the points (W1 to W6) are to be used for a route (10) to be set.
  3. Method according to claim 1 or 2, characterised in that at each of the points (W1 to W6) integrated into the route (10), signals are emitted optically and/or acoustically by way of the second signalling elements, such that the points (W1 to W6) for the set route (10) are no longer to be used and thus the route (10) can be cancelled.
  4. System for operating a confined track section (8) with a number of points arranged therein (W, W1 to W6), comprising:
    a) an actuating device (12) for setting a route (10) using the points (W1 to W6) integrated into the route (10) and a predefined point position for the points (W1 to W6) of this route (10);
    b) a testing device (12) for checking the current position of the points (W1 to W6) integrated into the route (10) and if necessary adjusting the points (W1 to W6) into the predefined point positions for this route (10) by way of the actuating device (12);
    c) first signalling elements (2a, 2b) for displaying the point position in each case at each of the points (W, W1 to W6) integrated into the route (10); and
    characterised by
    d) second signalling elements (6) for optical and/or acoustic signalling at each of the points (W, W1 to W6) integrated into the route (10), such that the points (W, W1 to W6) are used for a set route (10).
  5. System according to claim 4, characterised in that at each of the points (W, W1 to W6) integrated into the route (10) optical and/or acoustic signals can be emitted with the second signalling elements (6), such that the points (W, W1 to W6) are to be used for a route (10) to be set.
  6. System according to claim 4 or 5, characterised in that at each of the points (W, W1 to W6) integrated into the route (10) optical and/or acoustic signals can be emitted with the second signalling elements (6), such that the points (W, W1 to W6) are no longer to be used for the set route (10) and thus the route (10) can be cancelled.
EP16156826.6A 2016-02-23 2016-02-23 Method and system for operating a confined track section with a number of points assembled therein Revoked EP3210847B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
EP16156826.6A EP3210847B1 (en) 2016-02-23 2016-02-23 Method and system for operating a confined track section with a number of points assembled therein

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EP16156826.6A EP3210847B1 (en) 2016-02-23 2016-02-23 Method and system for operating a confined track section with a number of points assembled therein

Publications (2)

Publication Number Publication Date
EP3210847A1 EP3210847A1 (en) 2017-08-30
EP3210847B1 true EP3210847B1 (en) 2020-02-05

Family

ID=55442664

Family Applications (1)

Application Number Title Priority Date Filing Date
EP16156826.6A Revoked EP3210847B1 (en) 2016-02-23 2016-02-23 Method and system for operating a confined track section with a number of points assembled therein

Country Status (1)

Country Link
EP (1) EP3210847B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2020296131A1 (en) * 2019-06-21 2022-02-17 Harsco Technologies LLC Systems for railroad switch position detection
CN112550372B (en) * 2020-11-16 2023-01-06 卡斯柯信号有限公司 Method for automatically changing traffic route and turning back during interrupted operation based on operation diagram

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3502115A1 (en) 1985-01-23 1986-07-24 Verkehrsbetriebe Peine-Salzgitter Gmbh, 3320 Salzgitter Control device for centralised signal box
DE19824562A1 (en) 1997-06-06 1998-12-10 Tiefenbach Gmbh Points position signalling device
DE19905916A1 (en) 1998-02-14 1999-08-19 Tiefenbach Gmbh Railway points control system
DE10161369A1 (en) 2000-12-15 2002-06-20 Tiefenbach Gmbh Points controller for railway tracks has input device for issuing points control commands, blocking circuit for selective output of blocking or release command for selectable points
DE102012200394A1 (en) 2012-01-12 2013-07-18 Siemens Aktiengesellschaft Method and control device for controlling a Weichelage- and Ordnungsmelders associated with a switch

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB201104009D0 (en) * 2011-03-09 2011-04-20 Sharing Alfred Indication system for railways and roads

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3502115A1 (en) 1985-01-23 1986-07-24 Verkehrsbetriebe Peine-Salzgitter Gmbh, 3320 Salzgitter Control device for centralised signal box
DE19824562A1 (en) 1997-06-06 1998-12-10 Tiefenbach Gmbh Points position signalling device
DE19905916A1 (en) 1998-02-14 1999-08-19 Tiefenbach Gmbh Railway points control system
DE10161369A1 (en) 2000-12-15 2002-06-20 Tiefenbach Gmbh Points controller for railway tracks has input device for issuing points control commands, blocking circuit for selective output of blocking or release command for selectable points
DE102012200394A1 (en) 2012-01-12 2013-07-18 Siemens Aktiengesellschaft Method and control device for controlling a Weichelage- and Ordnungsmelders associated with a switch

Non-Patent Citations (15)

* Cited by examiner, † Cited by third party
Title
ANONYMOUS: "Die Elektrisch ortsbediente Weiche EOW S7", SIEMENS AG, March 2010 (2010-03-01), pages 1 - 4, XP007920749
ANONYMOUS: "Elektrisch ortsbediente Weichen, wahlweise stellwerksbedient", VPS - VERKEHRSBETRIEBE PEINE-SALZGITTER GMBH, October 1992 (1992-10-01), XP055748416
ANONYMOUS: "Micro Computer - Elektrisch Ortsgestellte Weiche", PINTSCH TIEFENBACH, February 2013 (2013-02-01), XP055748429
ANONYMOUS: "PINTSCH TIEFENBACH Mikro Computer - Elektrisch Ortsgestellte Weiche. TMC-EOW", PINTSCH TIEFENBACH GMBH, February 2013 (2013-02-01), XP055750875
ANONYMOUS: "Weichenlage- und Ordnungsmelder", TIEFENBACH GMBH, December 1999 (1999-12-01), pages 1 - 2, XP055748436
ANONYMOUS: "Weichenlage und Ordnungsmelder. WLM", PINTSCH TIEFENBACH GMBH, February 2013 (2013-02-01), XP055750874
FENNER, WOLFGANG ET AL.: "Verkehrssicherungstechnik", 1998, PUBLICIS, Erlangen, article "Aufgabenstellung und Forderungen", XP055750882
GUTFREUND, LUTZ ET AL.: "Rangierstellwerk - Erneuerung im größten Automobilwerk Europa s unter rollendem Rad", SIGNAL & DRAHT, vol. 107, March 2015 (2015-03-01), pages 6 - 10, XP055748372
KLÖTERS, GEORG ET AL.: "Vom Läutewerk zur digitalen Bahnübergangsakustik", SIGNAL & DRAHT, vol. 104, October 2012 (2012-10-01), pages 35 - 38, XP001578000
LPA: "EOW -Weichen auf der Lübecker Hafenbahn", LPA - LÜBECK PORT AUTHORITY, 2003, pages 1 - 15, XP055748381, Retrieved from the Internet <URL:https://bekanntmachungen.luebeck.de/dokumente/d/550/inline>
LUTZ GUTFREUND ET AL.: "Rangierstellwerk - Erneuerung im größten Automobilwerk Euro- pas unter rollendem Rad", SIGNAL + DRAHT, vol. 107, March 2015 (2015-03-01), pages 6 - 10, XP055748372
PEISER, STEFAN: "Effizienter Technikeinsatz mit EOW und Rangierstellwerken", EL- EISENBAHNINGENIEUR, April 2015 (2015-04-01), pages 34 - 37, XP055748365
STEFAH PEISER: "TMC-EOW - Systemlosung fur einfache betriebliche Verhaltnisse (Teil 2)", SIGNAL + DRAHT, vol. 93, December 2001 (2001-12-01), pages 38 - 43, XP055748407
STEFAN PEISER: "Effizienter Technikeinsatz mit EOW und Rangierstellwerken", EI - EISENBAHNINGENIEUR, April 2015 (2015-04-01), pages 34 - 37, XP055748365, Retrieved from the Internet <URL:https://pintsch.net/wp-content/uploads/fachartikel-034_037_peiser.pdf>
STEFAN PEISER: "TMC-EOW - Systemlösung für einfache betriebliche Verhältnisse", SIGNAL + DRAHT, vol. 93, no. 12, November 2001 (2001-11-01), pages 38 - 43, XP055748395

Also Published As

Publication number Publication date
EP3210847A1 (en) 2017-08-30

Similar Documents

Publication Publication Date Title
EP1552997B1 (en) Train management system with change of the train control system
EP3400160A1 (en) Railway-technical installations and method for operating a railway-technical installation
EP3210847B1 (en) Method and system for operating a confined track section with a number of points assembled therein
EP1607300A2 (en) Train Control Method
DE19828878A1 (en) Data traffic reduction method for railway operation
DE102016203694A1 (en) Railway installation and method for operating a railway installation
DE102012217814A1 (en) Slow driving of a railway line
EP0988207B1 (en) Device for controlling level crossings
DE102011054422A1 (en) Protection system for intermittent protection of rail vehicle i.e. train, has signal detection unit transferring determined driving road information to data balise to transmit information as further information to rail vehicle
DE19825257A1 (en) Control device for rail vehicles in track system
DE19907466C1 (en) Train sequence safety method for rail network allows second train to enter occupied track section with safety distance between successive trains maintained to prevent collision
WO1998007609A1 (en) Process and device for control and monitoring a traffic control system
DE102004042979A1 (en) System for the safe operation of track-bound trains on tracks
EP2143614B1 (en) Method and device for secured notification that a section of track is available
EP0792230B1 (en) Process for the braking of vehicles at halts in the target shooting manner
DE1919468C3 (en) Installation in railway systems with level crossings on the same rails
DE4429403C2 (en) Process for treating overlapping slipping paths
EP3480078B1 (en) Light signal and method for displaying signal terms for a traffic route
DE102004062987A1 (en) Train controlling and securing method, involves blocking virtual blocks after clearing following train for other trains and issuing dis-positive drive assignment by host computer or dispatcher that is connected via cellular radio network
DE10002908A1 (en) Procedure for securing distances of trains
DE2329825C3 (en) Arrangement at signaling boards of signal boxes
DE2819785C2 (en) Device for train control
DE19958784A1 (en) Device for setting light signal to safety stop when railway vehicle passes has signal-safety track switching arrangements that trigger stop setting of associated light signal when vehicle passes
DE1455390C (en) Device for creating routes in railway signal boxes
DE19522585A1 (en) Railway signal box track occupation monitoring fault prevention

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20180119

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

RAP1 Party data changed (applicant data changed or rights of an application transferred)

Owner name: SIEMENS MOBILITY AG

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20191018

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 1229698

Country of ref document: AT

Kind code of ref document: T

Effective date: 20200215

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 502016008604

Country of ref document: DE

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: SIEMENS SCHWEIZ AG, CH

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20200205

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200628

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200505

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200505

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200605

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200506

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

REG Reference to a national code

Ref country code: DE

Ref legal event code: R026

Ref document number: 502016008604

Country of ref document: DE

Ref country code: BE

Ref legal event code: MM

Effective date: 20200229

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200223

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

PLBI Opposition filed

Free format text: ORIGINAL CODE: 0009260

PLBI Opposition filed

Free format text: ORIGINAL CODE: 0009260

PLAX Notice of opposition and request to file observation + time limit sent

Free format text: ORIGINAL CODE: EPIDOSNOBS2

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

26 Opposition filed

Opponent name: PINTSCH GMBH

Effective date: 20201028

TPAC Observations filed by third parties

Free format text: ORIGINAL CODE: EPIDOSNTIPA

26 Opposition filed

Opponent name: DEUTSCHE BAHN AG

Effective date: 20201029

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200405

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200223

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200229

PLBG Opposition deemed not to have been filed

Free format text: ORIGINAL CODE: 0009274

PLBB Reply of patent proprietor to notice(s) of opposition received

Free format text: ORIGINAL CODE: EPIDOSNOBS3

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20200505

26D Opposition deemed not to have been filed

Opponent name: PINTSCH GMBH

Effective date: 20201129

PLAY Examination report in opposition despatched + time limit

Free format text: ORIGINAL CODE: EPIDOSNORE2

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200505

PLBC Reply to examination report in opposition received

Free format text: ORIGINAL CODE: EPIDOSNORE3

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 20220110

Year of fee payment: 7

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200205

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20220419

Year of fee payment: 7

RDAF Communication despatched that patent is revoked

Free format text: ORIGINAL CODE: EPIDOSNREV1

REG Reference to a national code

Ref country code: DE

Ref legal event code: R103

Ref document number: 502016008604

Country of ref document: DE

Ref country code: DE

Ref legal event code: R064

Ref document number: 502016008604

Country of ref document: DE

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20220509

Year of fee payment: 7

RDAG Patent revoked

Free format text: ORIGINAL CODE: 0009271

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: PATENT REVOKED

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: FI

Ref legal event code: MGE

27W Patent revoked

Effective date: 20220828

REG Reference to a national code

Ref country code: AT

Ref legal event code: MA03

Ref document number: 1229698

Country of ref document: AT

Kind code of ref document: T

Effective date: 20220828