Polyvalent module for building wire gabion walls Download PDFInfo
- Publication number
- EP1641981B1 EP1641981B1 EP04739903A EP04739903A EP1641981B1 EP 1641981 B1 EP1641981 B1 EP 1641981B1 EP 04739903 A EP04739903 A EP 04739903A EP 04739903 A EP04739903 A EP 04739903A EP 1641981 B1 EP1641981 B1 EP 1641981B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- cross
- pyramid
- wire
- tube
- wire ropes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Not-in-force
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0208—Gabions
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Revetment (AREA)
- Input Circuits Of Receivers And Coupling Of Receivers And Audio Equipment (AREA)
- Piezo-Electric Or Mechanical Vibrators, Or Delay Or Filter Circuits (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Thermistors And Varistors (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Networks Using Active Elements (AREA)
Abstract
Description
Es sind Befestigungsarbeiten und Eindämmungsarbeiten unter der Bezeichnung "Drahtschotterverhau" bekannt welche entlang der Ufer von Flüssen oder entlang von Küsten ausgeführt werden um ein über die Ufer Treten der Flüsse und die Erosion der Küsten zu verhindern. Diese Drahtschotterverhaue haben meist prismatische Form, sind aus Gitter aus verzinktem Stahldraht hergestellt und mit Steinen oder Schotter gefüllt. Für den Schutz der Küsten und für die Erstellung von parallel als auch quer (Buhnen) zur Küste verlaufenden Befestigungen, seltener für Banketts bei begrenzter Wassertiefe, werden prismatische kastenförmige Körbe aus verzinktem Stahldraht verwendet welche mit einer Hülle aus Kunststoff überzogen sind, mit quer verlaufenden aussteifenden Zwischenwänden ausgestattet sind und mit großen Steinen gefüllt werden.There are fortification and containment works known as "ballast gravel" which are carried along the banks of rivers or along coasts to prevent overflowing the rivers and erosion of the coasts. This wire ballast Verhaue have mostly prismatic shape, are made of grids made of galvanized steel wire and filled with stones or gravel. For the protection of the coasts and for the creation of parallel and transverse (groynes) coastal fortifications, more rarely banquets with limited depth, prismatic box-shaped baskets of galvanized steel wire are used, which are covered with a plastic sheath, with transverse stiffening Partitions are equipped and filled with large stones.
Die Erstellung dieser Drahtschotterverhaue bringt beachtliche Probleme mit sich, sei es in der Verlegungsphase, insbesondere beim Verlegen der ersten Lage der Drahtschotterkästen welche der Wirkung des strömenden Wassers ausgesetzt sind und oft auf unregelmäßigem Untergrund verlegt werden, welcher dauernd der Erosion ausgesetzt ist, als auch während der folgenden abschließenden Phasen, während der Ausbesserungsarbeiten und/oder den nachträglichen Erhöhungsarbeiten.The creation of this wire ballast entails considerable problems, be it in the laying phase, in particular when laying the first layer of wire ballast boxes which are exposed to the action of the flowing water and often laid on irregular ground, which is constantly exposed to erosion, as well as during the following final stages, during the repair work and / or the subsequent enhancement work.
Die bekannten Drahtschotterkästen haben im Verhältnis zu der, der Strömung ausgesetzten, Oberfläche ein bescheidenes Gewicht und können in der Praxis nicht im strömenden Wasser verlegt werden weil sie vom Wasserstrom, bzw. vom Wellengang verstellt würden. Wegen der relativ bescheidenen Ausmaße müssen die bekannten Drahtschotterkästen zum Großteil von Hand oder immerhin mittels Arbeitskräften gefüllt werden welche Gefahren ausgesetzt sind und gezwungen sind mit Stiefeln ausgerüstet im Wasser zu arbeiten. Weiters ist die Gitterstruktur der besagten Drahtschotterkästen wenig stabil so dass es bereits beim Verlegen dieser oder beim Beginn des Fültens, leicht zu übermäßigen Verformungen kommt welche das Verlegen der übergeordneten Drahtschotterkästen in Frage stellen oder erschweren.The known wire ballast boxes have in relation to the surface exposed to the flow of a modest weight and can not be installed in the flowing water in practice because they would be adjusted by the water flow, or from the swell. Because of the relatively modest dimensions of the known Drahtschotterkästen must be largely by hand or at least by means Workers exposed to hazards and forced to work equipped with boots in the water. Furthermore, the lattice structure of said wire ballast boxes is not very stable, so that even when laying this or at the beginning of the filling, easily excessive deformations occur which make the laying of the parent wire ballast boxes in question or difficult.
Aus der
Aus der
Die Erfindung stellt sich die Aufgabe ein polyvalentes Modul für die Erstellung von Drahtschotterverhauen zu schaffen welches leicht montierbar und transportierbar ist, welches geeignet ist diesen Strukturen eine beachtenswerte Formstabilität während der Verlegung zu verleihen, während anschließend beim Füllen oder beim Auftreten von Belastungen, um Brüche zu verhindern, eine begrenzte Anpassung der Struktur möglich ist, wobei diese ein derartiges Verhältnis zwischen Gewicht und der, dem Wasserstrom ausgesetzten, Oberfläche aufweist welches ein sicheres und definitives Verlegen auch in bewegten Gewässern und/oder auf prekärem Untergrund ermöglicht.The object of the invention is to provide a polyvalent module for the creation of wire ballast scrapers which is easy to assemble and transport, which is suitable for giving these structures a remarkable dimensional stability during installation, and subsequently for fracturing during filling or when loads occur prevent a limited adaptation of the structure is possible, which has such a relationship between weight and the surface exposed to the flow of water, which allows a safe and definitive installation even in moving waters and / or on precarious ground.
Zur Lösung dieser Aufgabe schlägt die Erfindung die Nutzung eines polyvalenten Moduls mit gelenkiger pyramidenförmiger Struktur vor welche als Verstärkung für die Gitterstruktur der einzelnen Drahtschotterkästen wirkt die ihrerseits verschiedenartig zusammenbaubar sind und für Drahtschotterverhaue verschiedener Form einsetzbar sind.To solve this problem, the invention proposes the use of a polyvalent module with articulated pyramidal structure before which acts as a reinforcement for the lattice structure of the individual wire ballast boxes which in turn are variously assemble and can be used for Drahtschotterverhaue different form.
Die Erfindung schlägt den Einsatz einer Struktur vor welche an sich als Lawinenverbauungselement oder als Konsolidierungselement bekannt ist und immer mit dem Scheitel mittels Platten, Zugankern oder Ankerpfählen an Hängen verankert ist und mit einem Netz ausschließlich im Bereich der Pyramidengrundfläche ausgestattet ist und welche als Barriere, zwecks Zurückhalten der talwärts strömenden Schneemassen wirkt. Die bekannte Pyramidenstruktur besteht wesentlich aus einer Grundfläche welche von vier kreuzartig angeordneten Profilen gebildet wird welche am Ende eines Rohres oder eines Profils gelenkig festgelegt sind und aus Drahtseilen welche die äußeren Enden der vier kreuzartig angeordneten Profile verbinden indem sie einen quadratischen oder rechteckigen Umfang bestimmen; die selben Enden der kreuzförmig angeordneten Profile sind weiters durch Drahtseile mit dem freien Ende (Scheitel der Pyramide) des Profils oder Rohres verbunden welches die Position der Pyramidenhöhe einnimmt.The invention proposes the use of a structure which is known per se as an avalanche barrier element or as a consolidation element and is always anchored to the apex by means of plates, tie rods or anchor piles on slopes and is equipped with a network exclusively in the pyramid base area and which as a barrier, for the purpose Retention of the snow masses flowing downwards is effective. The well-known pyramid structure consists essentially of a base which is formed by four cross-shaped profiles which are articulated at the end of a pipe or a profile and made of wire ropes which the outer Connect ends of the four cross-shaped profiles by defining a square or rectangular circumference; the same ends of the cross-shaped profiles are further connected by wire cables with the free end (apex of the pyramid) of the profile or tube which occupies the position of the pyramid height.
Die gelenkige Pyramidenstruktur wird erfindungsgemäß als Grundmodul für die Erstellung verschiedener Verstärkungsstrukturen von Drahtschotterverhauen eingesetzt, wobei sie erfindungsgemäß als einzelnes Modul oder in Kombination mit mehreren Modulen oder Modulteilen die Halte- und Stützfunktion für einen Drahtschotterkasten oder eine Gitterstruktur welche aus mehreren Flächen besteht übernimmt und dabei auf gelenkige Weise eine zu starke Verformung der einzelnen Flächen und der Gesamtform des Drahtschotterverhaues verhindert und überdies als Ballast und als beachtliche Verstärkung der Befestigungsfront oder Befestigungsfronten des Drahtschotterverhaues wirkt.According to the invention, the articulated pyramid structure is used as the basic module for the creation of various reinforcing structures of wire ballast, wherein it assumes the holding and supporting function for a wire ballast box or a lattice structure consisting of several surfaces as a single module or in combination with a plurality of modules or module parts hinged way prevents excessive deformation of the individual surfaces and the overall shape of the wire ballast Verhaues and also acts as a ballast and as a considerable reinforcement of the mounting front or mounting fronts of Drahtschotterverhaues.
Bei Verlegen mehrerer Pyramidenstrukturen mit seitlich anliegenden Grundflächen und am Boden aufliegenden Scheiteln welche entweder an einem einzigen Punkt vereint sind oder konvergieren, ist die Möglichkeit gegeben vieleckige oder halbvieleckige Drahtschotterverhaue zu erstellen, bzw. Abschnitte mit vieleckiger Anordnung zu erstellen und zwar mit der Möglichkeit die Scheitel mit gleichen Abständen, entsprechend einer Seitenlänge der Grundfläche, anzuordnen um so einen geradlinigen Verlauf der Struktur zu erhalten oder mit den Scheiteln mit größerem Abstand als die genannte Seitenlänge, um so einen konkaven vieleckigen Verlauf der Befestigungsstruktur zu erhalten. In diesen letzten Fällen werden die Freiräume zwischen den Scheiteln vorteilhafterweise von weiteren Drahtschotterkästen mit oder ohne entgegengesetzt ausgerichteter Pyramidenstruktur besetzt. Erfindungsgemäß kann an jeder der genannten Pyramidenstrukturen ein Gitter zwecks Zusammenhalten der Steine angebracht werden, dieses ist innerhalb der kreuzförmig verlaufenden Profile und innerhalb oder auch außerhalb der Drahtseile, welche die äußeren Enden der genannten Profile der Grundfläche mit dem Scheitel verbinden, angebracht wobei die Möglichkeit besteht, nach erfolgtem Füllen, einen pyramidenförmigen Drahtschotterkasten oder, bei nach oben sich erstreckenden Gittern im Bereich der Scheitel, einen zwickelförmigen Drahtschotterkasten, zu bilden. Im Falle einer derart gebildeten Serie von Drahtschotterkästen mit beabstandeten Scheiteln, können die freien Zwischenräume ihrerseits mit Steinen, mit oder ohne Einsatz von Gittern, aufgefüllt werden. Natürlich wird die Befestigungsfront eines derart erstellten Drahtschotterverhaues, im Falle einer Ufer- oder Küstenbefestigung, von den Strukturen der Grundflächen der Pyramiden gebildet während bei Bodenkonsolidierungen diese Front die Terrassierung oder Sperre bildet welche durch den, eventuell auf einer am Hang erzeugten Abstufung, angelegten Drahtschotterverhau verankert ist.When laying several pyramidal structures with laterally adjacent bases and lying on the ground vertices which are either united at a single point or converge, the possibility is given to create polygonal or halbvieleckige Drahtschotterverhaue, or sections with polygonal arrangement to create and with the possibility of the vertices to arrange at equal intervals, corresponding to a side length of the base so as to obtain a rectilinear course of the structure or with the vertices at a greater distance than the said side length so as to obtain a concave polygonal course of the mounting structure. In these latter cases, the spaces between the vertices are advantageously occupied by further wire ballast boxes with or without oppositely oriented pyramidal structure. According to the invention, a grid may be attached to each of said pyramidal structures to hold the stones together, which is inside the cross-shaped profiles and inside or outside the wire ropes connecting the outer ends of said base profiles to the apex, the said Possibility, after completion of filling, a pyramidal wire ballast box or, in upwardly extending grids in the region of the vertex, a gore-shaped wire ballast box to form. In the case of such a series of wire ballast boxes with spaced vertexes, the free spaces in turn may be filled with stones, with or without the use of gratings. Of course, the attachment front of such created Drahtschotterverhaues, in the case of a shore or coastal fortification, formed by the structures of the bases of the pyramids while ground consolidations this front the terracing or barrier forms which anchored by the, possibly on a slope generated gradation, applied Drahtschotterverhau is.
Die erfindungsgemäßen Pyramidenstrukturen sind einfach in der Herstellung und montagefreundlich, sie ermöglichen eventuell eine Vormontage und den anschließenden Transport an die Einsatzstelle eventuell mittels Helikopter, dies ist auch im Falle von bereits mit Gitter ausgestatteten Pyramidenstrukturen möglich. Im Falle einer Verlegung in Wasser wirkt die Pyramidenstruktur als Ballast und verhindert dass der Drahtschotterkasten von der Wasserströmung abgetrieben wird.The pyramid structures according to the invention are easy to manufacture and easy to install, they possibly allow pre-assembly and subsequent transport to the site, possibly by helicopter, this is also possible in the case of already equipped with grid pyramid structures. In the case of laying in water, the pyramid structure acts as ballast and prevents the wire ballast box from being driven off by the water flow.
Erfindungsgemäß ermöglicht das beschriebene Modul eine Erweiterung indem am Scheitel also am Ende des Rohres oder des Profils welches sich entsprechend der Pyramidenhöhe erstreckt eine zweite kreuzförmige Struktur vorgesehen ist welche jener an der Pyramidengrundfläche entspricht und gleich dieser aus vier gelenkig, am zweiten Ende des genannten Rohres oder Profils, festgelegten Profilen besteht. In diesem Fall können, bezüglich der Längserstreckung des Verbindungsrohres oder -profils, zwischen den beiden kreuzförmigen Strukturen, die Profilenden jeder Kreuzanordnung mittels Drahtseile mit dem entgegengesetzten Ende des Verbindungsrohres oder -profils verbunden werden wodurch eine Struktur für einen prismatischen Drahtschotterkasten entsteht, wobei das Verbindungsrohr oder -profil entsprechend der Längsachse des Prismas verläuft. Erfindungsgemäß kann jedoch die Befestigung der Drahtseile welche an den äußeren Enden der kreuzförmig angeordneten Profile befestigt sind, auch an einem Punkt im Mittelbereich oder außerhalb der Mitte der Längserstreckung des Rohres oder des Profils oder an zwei getrennten beabstandeten Punkten befestigt werden. Der prismatische Drahtschotterkasten wird in diesem Fall aus Gitter gebildet welche innerhalb der beiden Kreuzanordnungen und innerhalb oder außerhalb der Drahtseile, welche die entsprechenden äußeren Enden der kreuzförmig angeordneten Profile der Pyramidenstrukturen welche durch ein Rohr oder Profil verbundenen sind, angebracht sind und die Längskanten des Prismas definieren.According to the invention described module allows an extension by at the apex so at the end of the tube or the profile which extends corresponding to the pyramid height, a second cross-shaped structure is provided which corresponds to that on the pyramid base and the same of four articulated, at the second end of said tube or Profils, specified profiles exists. In this case, with respect to the longitudinal extent of the connection pipe or profile, between the two cross-shaped structures, the profile ends of each cross assembly can be connected by wire ropes to the opposite end of the connection pipe or profile creating a structure for a prismatic wire ballast box, wherein the connection pipe or Profile runs along the longitudinal axis of the prism. According to the invention, however, the attachment of the wire ropes which are attached to the outer ends of the cross-shaped profiles are also attached at a point in the central region or outside the center of the longitudinal extent of the tube or the profile or at two separate spaced points. The prismatic wire ballast box in this case is formed of grids which are mounted within the two cross arrangements and inside or outside the wire ropes, which are the respective outer ends of the cross-shaped profiles of the pyramid structures which are connected by a pipe or profile and define the longitudinal edges of the prism ,
Der Drahtschotterverhau welcher erfindungsgemäß erstellt wird bietet sich an durch Aufsetzen von, sich senkrecht erstreckenden, Rohren oder Profilen im Bereich der Kreuzanordnungen der zusammengesetzten Pyramidenstrukturen, einen weiteren Drahtschotterkasten zu schaffen welcher an den vier senkrechten Kanten von den genannten aufgesetzten Rohren oder Profilen zusammen mit eventuellen dazwischen angebrachten Verbindungs- oder/und Verwindungsdrahtseilen, gestützt wird.The Drahtschotterverhau which is created according to the invention is offered by placing, extending vertically, tubes or profiles in the region of the cross arrangements of the composite pyramid structures to provide another wire ballast box which at the four vertical edges of said patch tubes or profiles together with any in between attached connecting and / or twisting wire ropes, is supported.
Erfindungsgemäß kann, zwecks Verstärkung der Drahtschotterkästen in Eck- oder Endbereichen, z.B. am Ende von Buhnen, auch das Gitter welche die Außenfläche am Ende des Verhaues bildet, mit einer Pyramidenstruktur ausgestattet werden wobei das Verbindungsrohr oder -profil welches sich entsprechend der Pyramidenhöhe erstreckt, mit dem Verbindungsrohr- oder -profil welches die beiden Kreuzanordnungen verbindet oder mit einem anderen Strukturelement, verbunden werden kann.According to the invention, in order to reinforce the wire ballast boxes in corner or end areas, e.g. At the end of groynes, also the grid which forms the outer surface at the end of the Verhaues be equipped with a pyramidal structure, wherein the connecting pipe or profile which extends according to the pyramid height, with the Verbindungsrohr- or profile which connects the two cross-arrangements or with a other structural element, can be connected.
Wegen der inneren Pyramidenstruktur welche geeignet ist in gelenkiger Art die Form des Drahtschotterkastens zu stützen, können die derart erstellten Drahtschotterverhaue vollständig mit mechanischen Mitteln gefüllt werden.Because of the internal pyramid structure which is suitable for supporting the shape of the wire ballast box in an articulated manner, the wire ballast structures thus created can be completely filled with mechanical means.
Die Erfindung schließt nicht aus, dass im Falle prismatischer Strukturen die Verbindungsdrahtseile, zwischen den äußeren Enden der kreuzförmig angeordneten Profile und dem Verbindungsrohr oder -profil zwischen den beiden Kreuzanordnungen, von Drahtseilen ersetzt werden können welche die genannten Enden der Profile einer Kreuzanordnung mit jenen der entgegengesetzten Kreuzanordnung verbinden, wobei sie zueinander parallel und den Längskanten des Prismas entsprechend verlaufen, oder den Diagonalen der Außenflächen des Prismas entsprechend, bzw. den Raumdiagonalen entsprechend verlaufen und sich überschneiden.The invention does not exclude that in the case of prismatic structures, the connecting wire ropes, between the outer ends of the cross-shaped arranged profiles and the connecting tube or profile between the two cross assemblies, can be replaced by wire cables which connect said ends of the profiles of a cross assembly with those of the opposite cross arrangement, wherein they are parallel to each other and the longitudinal edges of the prism corresponding, or the diagonal of the outer surfaces Corresponding to the prism, or the space diagonals accordingly and overlap.
Gemäß einer Weiterentwicklung des Erfindungsgedankens kann, insbesondere ein würfelförmiger aber auch ein prismatischer Drahtschotterkasten an allen Außenflächen mit einer gelenkigen Kreuzanordnung ausgestattet sein wobei die Rohre oder Profile welche mit dem gelenkigen Verbindungsteil ausgestattet sind im zentralen Bereich des geometrischen Körpers verbunden sind. Diese Lösung ermöglicht die Erstellung einer Stützstruktur bei welcher nur die äußeren Enden der kreuzförmig angeordneten Profile, welche den Ecken des geometrischen Körpers entsprechen, unter sich verbunden sind. Weiters ermöglicht diese Struktur die vollständige oder teilweise Rückgewinnung der Strukturelemente, ohne Entleerung des derart erstellten Drahtschotterkorbes, durch Lösen der Befestigungen an den äußeren Enden der kreuzförmig angeordneten Profile, durch Umlegen der Profile nach außen nach Art eines umgekehrten Schirmes und durch eventuelles Lösen der Gitter und Ausziehen der Verbindungsrohre oder Verbindungsprofile falls diese kreuzartig angeordnet sind ohne unter sich verbunden zu sein.According to a further development of the inventive concept, in particular a cube-shaped but also a prismatic wire ballast box can be equipped with an articulated cross arrangement on all outer surfaces, the tubes or profiles which are equipped with the articulated connection part being connected in the central region of the geometric body. This solution makes it possible to create a support structure in which only the outer ends of the cross-shaped profiles, which correspond to the corners of the geometric body, are connected to each other. Furthermore, this structure allows the complete or partial recovery of the structural elements, without emptying the thus created wire ballast cage, by loosening the fasteners at the outer ends of the cross-shaped profiles, by turning the profiles outward in the manner of a reverse umbrella and possibly loosening the grid and Extracting the connecting pipes or connecting profiles if they are arranged like a cross without being connected to each other.
Die Erfindung wird anschließend anhand einiger, in den beigelegten Zeichnungen schematisch dargestellter, vorzuziehender Ausführungsbeispiele polyvalenter erfindungsgemäßer Module für die Erstellung von Drahtschotterverhauen näher erklärt, weiters sind in den Zeichnungen unterschiedliche Kombinationen der Module gezeigt.The invention will be explained in more detail with reference to some, in the attached drawings schematically illustrated, preferred embodiments of polyvalent inventive modules for the creation of Drahtschotterverhauen closer, further different combinations of the modules are shown in the drawings.
Die Fig. 1 ist eine perspektivische Darstellung einer bekannten Pyramidenstruktur welche als Lawinenverbauungselement mit am Boden verankertem Scheitel installiert ist.Fig. 1 is a perspective view of a known pyramid structure which is installed as an avalanche barrier element with vertex anchored to the ground.
Die Fig. 1a zeigt in Seitenansicht das Detail der gelenkigen Festlegung zwischen den kreuzförmig angeordneten Profilen welche die Grundfläche der in Fig. 1 gezeigten Pyramidenstruktur bilden und des Rohr- oder Profilendes welches mit dem entgegengesetzten Ende den Scheitel der Pyramide bildet.Fig. 1a shows a side view of the detail of the articulation between the cross-shaped profiles which form the base of the pyramidal structure shown in Fig. 1 and the pipe or profile end which forms the apex of the pyramid with the opposite end.
Die Fig. 2 zeigt schematisch eine erfindungsgemäße Stützstruktur für einen prismatischen Drahtschotterkasten welche aus dem Zusammenbau zweier pyramidenförmiger Module gebildet wird, wobei der Scheitel jeder der Pyramiden dem Gelenk an der Grundfläche der entsprechenden zusammengebauten Pyramide entspricht.Fig. 2 shows schematically a support structure according to the invention for a prismatic wire ballast box which is formed from the assembly of two pyramidal modules, wherein the apex of each of the pyramids corresponds to the joint at the base of the corresponding assembled pyramid.
Die Fig. 2a zeigt schematisch in Draufsicht die Errichtung eines Drahtschotterverhaues mittels mehrerer in Fig. 2 gezeigter Module welche unter sich ausgerichtet sind.Fig. 2a shows schematically in plan view the construction of a Drahtschotterverhaues means of several shown in Fig. 2 modules which are aligned among themselves.
Die Fig. 3 zeigt schematisch eine erfindungsgemäße Stützstruktur für einen prismatischen Drahtschotterkasten welche durch den Zusammenbau zweier Pyramidenmodule entstanden ist, die Scheitel der Pyramiden befinden sich am Mittelpunkt am Verbindungsrohr oder -profil der zwei Grundflächen der zusammengebauten Pyramiden.Fig. 3 shows schematically a support structure according to the invention for a prismatic wire ballast box which is formed by the assembly of two pyramid modules, the apex of the pyramids are located at the midpoint on the connecting pipe or profile of the two bases of the assembled pyramids.
Die Fig. 4 zeigt schematisch in Draufsicht einen vieleckig verlaufenden Drahtschotterverhau in Draufsicht welcher aus erfindungsgemäßen Modulen zusammengesetzt ist.Fig. 4 shows schematically in plan view a polygonal Drahtschotterverhau in plan view which is composed of modules according to the invention.
Die Fig. 5 zeigt schematisch in perspektivischer Darstellung die Schaffung eines würfelförmigen Drahtschotterkastens dessen Hülle von vier Pyramidenelementen verstärkt ist wobei die Kreuzanordnungen die vier seitlichen Flächen des Würfels abdecken und die Verbindungsrohre oder-profile untereinander innen im Zentrum des Würfel verbunden sind.Fig. 5 shows schematically in perspective the creation of a cube-shaped wire ballast box whose shell is reinforced by four pyramidal elements, wherein the cross-arrangements of the four lateral faces of the cube Cover and the connecting tubes or profiles are interconnected inside in the center of the cube.
Die Fig. 5a zeigt schematisch in Draufsicht die Erstellung eines Drahtschotterverhaues mittels mehrerer in Fig. 2 gezeigter Module wobei die Stirnfläche des Drahtschotterkastens am Ende der Struktur durch ein drittes Pyramidenelement verstärkt ist.5a shows schematically in plan view the creation of a Drahtschotterverhaues means of several shown in Fig. 2 modules wherein the end face of the wire ballast box is reinforced at the end of the structure by a third pyramid element.
Die Fig. 6 zeigt in Vorderansicht einen gefüllten erfindungsgemäß verstärkten, prismatischen Drahtschotterkasten welcher oberhalb mit einer Aufbaustruktur mit umlaufendem Gitter versehen ist um von oben weiter mit Steine gefüllt werden zu können.6 shows a front view of a filled according to the invention reinforced, prismatic wire ballast box which is provided above with a body structure with encircling grid to be filled from above with stones.
Die Pyramidenstruktur welche das Grundmodul (Fig. 1, 1a) für die Verstärkung und Stützung eines Drahtschotterkastens bildet, besteht wesentlich aus einem Rohr oder Profil 3 welches an einem der Enden ein Verbindungsteil 2 aufweist an welchem die Enden der kreuzförmig angeordneten Profile 1 gelenkig festgelegt sind. Dazu sind z.B. die Flansche 1a welche an einem der Enden des Profils 1 vorstehen mit einer durchgehenden Bohrung 1 b versehen um mittels Zapfen oder Bolzen 4 an einem Verbindungselement 2 welches entsprechende Bohrungen aufweist festgelegt zu werden. Die äußeren Enden der Profile 1 sind durch ein Drahtseile 6 verbunden um die Grundfläche der Pyramide zu bilden, diese äußeren Enden sind weiters mittels Drahtseile 5 mit dem Scheitel der Pyramidenstruktur verbunden welcher durch das freie Ende des Rohres oder Profils 3 gebildet wird während am anderen Ende das Verbindungselement 2 vorgesehen ist.The pyramidal structure which forms the basic module (FIG. 1, 1a) for the reinforcement and support of a wire ballast box essentially consists of a tube or
Erfindungsgemäß kann jedoch auch das freie Ende dieses Rohres oder Profils 3 mit einem Verbindungselement 2 versehen sein an welchem weitere kreuzförmig angeordnete und gelenkig festgelegte Profile 1, spiegelbildlich zu jenen am entgegengesetzten Ende, vorgesehenen sind. In diesem Fall erhält man eine Struktur aus einer Doppelpyramide wobei die Drahtseile 5 welche an den äußeren Enden der kreuzförmig angeordneten Profile 1 befestigt sind, am zweiten Ende am Verbindungselement 2 der gegenüberliegenden Kreuzanordnung (Fig. 2) befestigt sind. Die äußeren Enden der Profile 1 der beiden Kreuzanordnungen können weiters unter sich über Drahtseile 7 verbunden sein ohne auszuschließen dass diese Drahtseile sich überkreuzen. Die Gitter welche den Drahtschotterkasten bilden sind an den Kreuzanordnungen der Profile 1 innenliegend angeordnet während die Gitter welche den Rest der Abwicklung des Drahtschotterkastens bilden innerhalb oder außerhalb an den Drahtseilen 7, welche die Längskanten des Kastens definieren, befestigt sind.According to the invention, however, the free end of this tube or
Gemäß einer Weiterentwicklung des Erfindungsgedankens können die Drahtseile 5 welche die äußeren Enden der Profile 1 mit dem Rohr oder Profil 3, bzw. mit den Verbindungselementen 2 im Mittelbereich der Längserstreckung des Rohres oder Profils 3, oder an zwei beabstandeten Punkten, verbunden sein; die Verankerung der Drahtseile 5 einer Kreuzanordnung kann dabei am näheren oder am entfernteren Punkt erfolgen wobei in diesem letzteren Fall eine Überschneidung zwischen den Drahtseilen 5 stattfindet.According to a further development of the inventive idea, the
Die prismatische Struktur eines durch das pyramidenförmige erfindungsgemäße Modul verstärkten Drahtschotterkorbes kann auch an einer (Fig. 5a) oder an mehreren (Fig. 5) weiteren Flächen verstärkt werden indem ein weiteres Pyramidenelement vorgesehen wird dessen Rohr oder Profil 3, unter Bildung eines Winkels von 90°, am Verbindungsrohr oder -profil 3 welches die beiden Kreuzanordnungen der Stützstruktur verbindet oder an einem anderen Element der pyramidenförmigen Struktur festgelegt wird.The prismatic structure of a wire ballast basket reinforced by the pyramidal module according to the invention can also be reinforced on one (Fig. 5a) or on several (Fig. 5) further surfaces by providing another pyramidal element whose tube or
Eine besondere Ausführung der Stützstruktur für einen Drahtschotterkasten welcher vorzugsweise die Form eines Würfels hat (Fig. 5), ohne jedoch eine prismatische Form auszuschließen, entsteht dadurch dass an den vier Seitenflächen des Würfels und eventuell auch an der Grundfläche und der oberen Fläche je eine aus Profilen 1 gebildete Kreuzanordnung samt den entsprechenden Verbindungselementen 2 und dem Verbindungsrohr 3, welches eventuell mit jenem des zweiten oder des dritten Paares von Kreuzanordnungen verbunden ist, vorgesehen ist. Diese Struktur bietet auch den Vorteil, dass durch gegenseitiges Festlegen der entsprechenden äußeren Enden der kreuzförmig angeordneten Profile 1 die gesamte Struktur stabil wird wobei die Kreuzanordnungen mit umlaufenden Drahtseilen 6 versehen sind. Eine derartige Struktur macht die vollständige oder teilweise Rückgewinnung der Elemente möglich indem die Festlegungen an den äußeren Enden der kreuzförmig angeordneten Profile 1 gelöst werden, indem diese, infolge Loslösen von den Gittern 11, wie ein umgekehrter Schirm umgelegt werden und indem die Verbindungsrohre oder Verbindungsprofile 3 vorzugsweise nach oben, durch das lockere überlagerte Material hindurchgezogen werden.A particular embodiment of the support structure for a wire ballast box, which preferably has the shape of a cube (FIG. 5), but without precluding a prismatic shape, arises from the fact that on each of the four side surfaces of the cube and possibly also on the base surface and the upper surface Profiles 1 formed cross assembly together with the
Die Erfindung schließt jedoch nicht aus einfache Pyramidenelemente für die Erstellung von z.B. vieleckig verlaufenden Drahtschotterverhauen (Fig. 4) einzusetzen, in diesem Fall kann jedes einzelne Pyramidenelement mit einem Metallgitter versehen werden oder es können mehrere Pyramidenelemente so verbunden werden dass eine zusammengesetzte, z.B. vieleckige Struktur entsteht, welche mit einem Metallgitter ausgestattet wird.However, the invention does not exclude simple pyramidal elements for the creation of e.g. In this case, each individual pyramidal element may be provided with a metal grid, or several pyramidal elements may be connected such that a composite, e.g. polygonal structure is created, which is equipped with a metal grid.
Das Pyramidenelement und die aus zwei oder mehreren Pyramidenelementen zusammengesetzten Strukturen können mit vertikalen Strukturelementen 9 (Fig. 6) ausgestattet werden welche an den oberen Eckbereichen der Struktur über die obere Fläche des Drahtschotterkastens emporragen um an den oberen Enden 9a mit Drahtseilen 9b und eventuellen diagonalen Drahtseilen 9c verbunden zu werden und mit einem Gitter 10 zwecks Ausbildung einer weiteren Drahtschotterzelle für die Erhöhung des Verhaues auszustatten.The pyramidal element and the structures composed of two or more pyramidal elements may be provided with vertical structural elements 9 (Figure 6) which protrude above the top surface of the wire ballast box at the top corner regions of the structure around the
Natürlich können die Gitter 10, 11 welche den Drahtschotterkasten bilden verschiedener Art sein und eventuell in mehr Schichten überlagert sein, weiters können für die einzelnen Flächen eines Drahtschotterkastens eigene Gitter eingesetzt werden welche an den Kanten unter sich und/oder an Drahtseilen oder an anderen Strukturelementen der Stützmodule befestigt werden.Of course, the
Claims (4)
- A polyvalent module for building gabion walls, wherein the module is pyramid-shaped, comprises four first section bars (1) arranged in a cross shape which form the base of the pyramid and are applied in a jointed fashion to a connecting element (2) which is fixed to the end of a second section bar or tube (3) extending in conformity with the height of the pyramid, wherein the outer ends of these first section bars (1) arranged in a cross shape are joined to each other by first wire ropes (6), wherein these same ends are joined by second wire ropes (5) to the free end of the tube or second section bar (3) or to a point distant from the connecting element (2) on the tube or second section bar (3), wherein the module also comprises at least one grille-style element (11), wherein the grille-style element or grille-style elements (11) are applied to the pyramid to create a wire net container, and wherein the grille-style elements (11) are applied internally relative to the first section bars (1) arranged in a cross shape and forming the base of the pyramid and internally or externally relative to two adjacent second wire ropes (5) which form the lateral edges of the pyramid.
- The module according to claim 1, wherein, in order to form a second cross-shaped arrangement of the first section bars (1), the tube or second section bar (3) also has a connecting element (2) at the other end, for the jointed fixing of other first section bars (1) arranged in a cross shape, wherein other second wire ropes (5) join the outer ends of these first section bars (1) of the second cross-shaped arrangement fixed at both ends of the tube or second section bar (3) to the opposite end of the tube or second section bar (3) or to the connecting element (2) on this end, wherein the outer ends of the first section bars (1) of both cross-shaped arrangements distanced from one another are joined by third wire ropes (7) parallel and/or if necessary intersecting and wherein additional grille-style elements (10, 11) forming the wire net container are fixed inside the two cross-shaped arrangements and outside or inside the wire ropes (7) which form the longitudinal edges and the diagonals of the lateral surfaces of the prismatic structure.
- The module according to claim 2, wherein the third wire ropes (7) which join the outer ends of the first section bars (1) of one cross-shaped arrangement to those of the opposite cross-shaped arrangement are positioned according to the diagonals of the prismatic structure.
- The module according to claim 2, wherein the wire ropes (5) which join the outer ends of the first section bars (1) of the two cross-shaped arrangements to the tube or second section bar (3), relatively to their longitudinal extension, are fixed centrally at a single point or away from the centre or at two points which are distant from each other and more precisely with the possibility of fixing to the point closest to the cross-shaped arrangement or furthest from it where the second wire ropes (5) intersect.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
IT000033A ITBZ20030033A1 (en) | 2003-06-18 | 2003-06-18 | MULTI-PURPOSE MODULE FOR THE CREATION OF GABBIONATE STRUCTURES |
PCT/EP2004/006433 WO2004111351A1 (en) | 2003-06-18 | 2004-06-15 | Polyvalent module for building wire gabion walls |
Publications (2)
Publication Number | Publication Date |
---|---|
EP1641981A1 EP1641981A1 (en) | 2006-04-05 |
EP1641981B1 true EP1641981B1 (en) | 2008-01-16 |
Family
ID=33548850
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP04739903A Not-in-force EP1641981B1 (en) | 2003-06-18 | 2004-06-15 | Polyvalent module for building wire gabion walls |
Country Status (6)
Country | Link |
---|---|
EP (1) | EP1641981B1 (en) |
AT (1) | ATE384170T1 (en) |
DE (1) | DE502004005971D1 (en) |
ES (1) | ES2299840T3 (en) |
IT (1) | ITBZ20030033A1 (en) |
WO (1) | WO2004111351A1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR3134124A1 (en) * | 2022-03-30 | 2023-10-06 | Sbj & Co Sa | Retaining structure and corresponding retaining device |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2500864A1 (en) * | 1980-12-19 | 1982-09-03 | Zimmermann Eugene | Steel bracing for connecting and reinforcing metal gabions - has three dimensional frame for steadying gabion walls during filling |
IT1284463B1 (en) * | 1996-07-03 | 1998-05-21 | Valsella Meccanotecnica Spa | QUICK INSTALLATION MODULAR PROTECTION SYSTEM |
-
2003
- 2003-06-18 IT IT000033A patent/ITBZ20030033A1/en unknown
-
2004
- 2004-06-15 WO PCT/EP2004/006433 patent/WO2004111351A1/en active IP Right Grant
- 2004-06-15 DE DE502004005971T patent/DE502004005971D1/en not_active Expired - Fee Related
- 2004-06-15 EP EP04739903A patent/EP1641981B1/en not_active Not-in-force
- 2004-06-15 AT AT04739903T patent/ATE384170T1/en active
- 2004-06-15 ES ES04739903T patent/ES2299840T3/en active Active
Also Published As
Publication number | Publication date |
---|---|
ATE384170T1 (en) | 2008-02-15 |
ES2299840T3 (en) | 2008-06-01 |
ITBZ20030033A1 (en) | 2004-12-19 |
DE502004005971D1 (en) | 2008-03-06 |
WO2004111351A1 (en) | 2004-12-23 |
EP1641981A1 (en) | 2006-04-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE4030885A1 (en) | METHOD AND ELEMENT FOR THE PRODUCTION OF STRUCTURES FOR TAKING UP TERRAIN AREA | |
EP4148186A1 (en) | Foundation for a wind turbine | |
EP2912238B1 (en) | Wall element for building in prefabricated construction | |
EP0828897B1 (en) | Avalanche breaking-up element with an umbrella-shaped structure and net | |
EP0202552B1 (en) | Tridimensional unit made of mesh panels | |
EP3183401B1 (en) | Concrete construction of modular design | |
DE69813809T2 (en) | HEDGE WALL SYSTEM | |
DE4208964A1 (en) | Steep bank supporting structure | |
DE3719523A1 (en) | Foundation or protection element | |
DE102005014025A1 (en) | Steel framework tower e.g. for wind power plants, has tower powerplant having pyramid tapered shape and in corner areas steel supporting tubes of lower anchorage up to upper part are provided | |
EP1641981B1 (en) | Polyvalent module for building wire gabion walls | |
DE3103849A1 (en) | Securing structure for steep slopes and walls in which vegetation can grow | |
EP2535463A1 (en) | Modular pre-fabricated retaining wall, concrete retaining wall comprising same and method for erecting the retaining wall | |
EP2292846B1 (en) | Gabion assembly | |
CH651095A5 (en) | REINFORCEMENT ELEMENT FOR TRANSMITTING LATERAL FORCES IN PANEL-LIKE SUPPORT LINKS, e.g. FLAT CEILINGS. | |
DE3833414A1 (en) | Noise protection wall consisting of grid mats | |
EP1418276A2 (en) | Dike element | |
EP1131498A1 (en) | Support wall system | |
EP1898005B1 (en) | Gabion element for constructing supporting walls or similar | |
AT304833B (en) | Triangular structural element, method of manufacturing a tower structure and tower structure from such structural elements | |
DE4409538A1 (en) | Device for constructing slopes, preferably in which plants can be grown | |
AT372733B (en) | CONSTRUCTION SKELETON FROM LOAD-BEARING PRE-FABRICATED ELEMENTS | |
DE8612622U1 (en) | Room element made of lattice mats | |
EP4222320A1 (en) | Foundation for a wind turbine | |
DE102020109352A1 (en) | Support arrangement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20051214 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LI LU MC NL PL PT RO SE SI SK TR |
|
17Q | First examination report despatched |
Effective date: 20060703 |
|
DAX | Request for extension of the european patent (deleted) | ||
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
GRAC | Information related to communication of intention to grant a patent modified |
Free format text: ORIGINAL CODE: EPIDOSCIGR1 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LI LU MC NL PL PT RO SE SI SK TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D Free format text: NOT ENGLISH |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: LANGUAGE OF EP DOCUMENT: GERMAN |
|
REF | Corresponds to: |
Ref document number: 502004005971 Country of ref document: DE Date of ref document: 20080306 Kind code of ref document: P |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: NV Representative=s name: BUGNION S.A. |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 2299840 Country of ref document: ES Kind code of ref document: T3 |
|
NLV1 | Nl: lapsed or annulled due to failure to fulfill the requirements of art. 29p and 29m of the patents act | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 |
|
GBV | Gb: ep patent (uk) treated as always having been void in accordance with gb section 77(7)/1977 [no translation filed] | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080416 |
|
ET | Fr: translation filed | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080616 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FD4D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 Ref country code: IE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080416 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 |
|
26N | No opposition filed |
Effective date: 20081017 |
|
BERE | Be: lapsed |
Owner name: LASAR SRL Effective date: 20080630 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20080630 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20080630 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20090101 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080717 Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20080615 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080116 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080417 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 20120629 Year of fee payment: 9 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20120626 Year of fee payment: 9 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20120712 Year of fee payment: 9 Ref country code: ES Payment date: 20120709 Year of fee payment: 9 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 20120619 Year of fee payment: 9 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MM01 Ref document number: 384170 Country of ref document: AT Kind code of ref document: T Effective date: 20130615 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20140228 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130630 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130630 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130615 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130701 Ref country code: AT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130615 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FD2A Effective date: 20140707 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130616 |