EP1568821B1 - Railroad concrete ballast construction system and method - Google Patents
Railroad concrete ballast construction system and method Download PDFInfo
- Publication number
- EP1568821B1 EP1568821B1 EP05001314A EP05001314A EP1568821B1 EP 1568821 B1 EP1568821 B1 EP 1568821B1 EP 05001314 A EP05001314 A EP 05001314A EP 05001314 A EP05001314 A EP 05001314A EP 1568821 B1 EP1568821 B1 EP 1568821B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- rail
- concrete
- slab
- ballast
- constructed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Not-in-force
Links
Images
Classifications
-
- D—TEXTILES; PAPER
- D05—SEWING; EMBROIDERING; TUFTING
- D05C—EMBROIDERING; TUFTING
- D05C3/00—General types of embroidering machines
- D05C3/02—General types of embroidering machines with vertical needles
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/002—Ballastless track, e.g. concrete slab trackway, or with asphalt layers
- E01B1/004—Ballastless track, e.g. concrete slab trackway, or with asphalt layers with prefabricated elements embedded in fresh concrete or asphalt
-
- D—TEXTILES; PAPER
- D05—SEWING; EMBROIDERING; TUFTING
- D05C—EMBROIDERING; TUFTING
- D05C13/00—Auxiliary devices incorporated in embroidering machines, not otherwise provided for; Ancillary apparatus for use with embroidering machines
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/002—Ballastless track, e.g. concrete slab trackway, or with asphalt layers
- E01B1/007—Ballastless track, e.g. concrete slab trackway, or with asphalt layers with interlocking means to withstand horizontal forces
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/06—Height or lateral adjustment means or positioning means for slabs, sleepers or rails
Definitions
- the present invention relates to a railroad concrete ballast construction system and method capable of exchanging a certain section of a gravel ballast track with a new concrete ballast track even when a train currently runs on a railroad, and in particular to a railroad concrete ballast construction system and method capable of constructing a concrete ballast at a certain section of a gravel ballast having no gravel and rail tie for exchanging a certain section of a gravel ballast with a new concrete ballast in a state that a train currently runs on a railroad, curing and disassembling a structure adapted to fix a rail for a stable operation of a train for thereby effectively finishing an exchanging work.
- the ballast has been used for widely distributing a weight transferred through a rail and rail tie, and transferring to a ground, resulting in a reduction of the weight.
- the ballast is capable of preventing a rail tie movement occurring due to a contraction and elongation of a rail by a temperature change based on a ballast resistance force for thereby absorbing a vibration of a train and enhancing an absorbing effect.
- the gravel ballast includes a rail 1 that supports train wheels, a rail tie 2 that is formed of a concrete rail tie or a wooden rail tie for transferring a weight or impact from the rail 1 to the ground when a train runs on a rail road, a gravel ballast 3 that is provided between the ground and the rail tie 2 for thereby absorbing the weight transferred thereto, and a clamp 5 of which one end is engaged with a fixture 4 fixed at the rail tie 2, an intermediate portion supports a flange 1 a of the rail 1, and the other end supports the fixture 4 wherein the clamp 5 is designed with three support points in an E-shape.
- the above gravel ballast has an advantage of uniformly distributing the weight transferred through the rail 1 when the train runs to the ground.
- the gravels of the gravel ballast 3 may be broken and worn away, thus producing small gravel pieces.
- the function of the ballast is significantly decreased and the safety factor of the train operation is decreased, thereby causing an accident.
- a railroad concrete ballast construction system with the features of claim 1, comprising a concrete rail tie slab in which a mounting part formed at both sides is engaged at a certain section having no gravel and rail tie on a gravel ballast track by a certain fixture; a rail support unit that is detachably installed between opposite slabs, and supports a vertical weight applied to a rail when a train runs, and supports the rail on the ground for thereby preventing the rail from being sagged; a gauge tie rod of which both ends are fixed at a rail support upper plate and an intermediate portion is flexible, for thereby preventing an elongation of the rail when a concrete of the slab is constructed; a gauge strut of which both ends are fixed at an inner surface of a body of the rail and an intermediate portion is flexible, for thereby preventing a contraction of the rail when a concrete of the slab is constructed; a horizontal support member that is installed outside the rail to be on the same line as the gauge strut, and supports an outer surface of the body of the
- receiving groove is formed at an outer surface of the slab so that the rail support unit is disassembled from the slab and is pulled out in an outer direction after the concrete is cured.
- the concrete rail tie slab includes a mounting part that is protruded from the left and right sides of an upper surface of the slab in opposite directions wherein the rail is mounted thereon; an engaging part that is engaged with an engaging hole formed at the left and right sides of the mounting part and has a certain elastic force capable of supporting a flange of the inner and outer sides of the rail; and an assistant engaging part that is engaged with a through hole formed at the slab in an outer direction of the mounting part and is embedded when a concrete is constructed for thereby enhancing an engaging force of the slab.
- the concrete rail tie slab is formed of a steel-reinforced concrete structure of which a tensional force is reinforced using steel bars embedded.
- a railroad rail concrete ballast construction method comprising the steps of removing gravels and rail ties from the ground and the rail in a certain section of a gravel ballast track; engaging a concrete rail tie slab at a lower side of a flange of the rail using a certain fixture; supporting the rail on the ground using a rail support unit installed between the opposite slabs for thereby preventing a sagging of the rail by supporting a vertical weight applied to the rail when a trains runs on the railroad; preventing an elongation of the rail using a gauge tie rod of which both ends are fixed at a rail support upper plate, when a concrete is constructed; preventing a contraction of the rail using a gauge strut of which both ends are fixed at an inner surface of a body of the rail, when a concrete of the slab is constructed; maintaining a horizontal state of the rail, when a concrete of the slab is constructed, by a horizontal support member installed outside the rail to be the same line as the gauge strut; fixing the slab on the ground
- a railroad concrete ballast construction system includes a concrete rail tie slab 20 in which a mounting unit 21 is engaged at a rail 10 by a certain fixture in a certain section of a gravel ballast track having no gravel and rail tie wherein a train can run on a railroad; and a rail support unit 30 that is installed so that it is disassembled between the opposite slabs 20 and is designed to support a vertical weight applied to the rail 10 when the train runs and the weight of the rail 10 at the ground for thereby preventing the rail 10 from being sagged.
- the rail support unit 30 may be preferably formed of a hydraulic jack, a screw jack, a rack jack, etc.
- the concrete rail tie slab 20 may be preferably formed of a reinforced concrete (RC) of which a tensional force is reinforced by an embedded reinforcing bar (not shown).
- RC reinforced concrete
- a horizontal support member 60 that is installed outside the rail 10 to be on the same line with the gauge strut 50 and supports an outer side of the body 11 of the rail 10 for thereby maintaining a horizontal state of the rail when the concrete of the slab 20 is constructed; and a concrete ballast 70 that fixes the slab 20 on the ground based on the concrete constructed between the ground and the slab 20 through an inlet 22 formed at the slab 20.
- the concrete rail tie slab 20 includes a mounting part 21 that is protruded from the left and right sides of the upper surface of the slab 20 in opposite directions wherein the rail 10 is mounted thereon; an engaging part 25 that is engaged to an engaging hole formed at the left and right sides of the mounting part 21 and has an elastic force and is fixed by an engaging bolt B supporting a flange 12 at the inner and outer sides of the rail 10; and an assistant engaging part 27 that is engaged with a through hole 26 formed at the slab 20 at the outer side of the mounting part 21 for thereby enhancing an engaging force of the slab 20 when the concrete is constructed.
- a receiving groove 23 is formed at an outer surface of the slab 20 so that the rail support part 30 is disassembled from the slab 20 in an outer direction after the concrete is cured.
- reference numeral 90 represents an anti-vibration member that is installed at the lower side of the flange 20 of the rail 10 for thereby absorbing impacts and vibrations
- 100 represents a driving motor for driving a pair of levers 103 and 104 when a driving shaft 102 is rotated for thereby preventing the rail 10 from being sagged by a support part 101.
- the gravels and rail ties are removed from the ground and the rail 10 in a certain section of the gravel ballast track on which the train can run in a step S100.
- the rail 10 in the section having no gravel and rail tie is installed with a certain gap from the ground.
- the concrete rail tie slab 20 is engaged to a lower side of the flange 12 of the rail 10 using a certain fixture in a step S200.
- the slab 20 is moved by a certain lifting equipment such as a crane, etc. and is inserted between the rail 10 and the ground.
- the rail 10 On the ground, the rail 10 is supported by the rail support unit 30 installed between the opposite slabs 20 for thereby preventing the rail 10 from being sagged by supporting a vertical weight applied to the rail 10 when the train runs during a working time in a step S300.
- the rail support unit 30 may be formed of a hydraulic jack, a screw jack, etc.
- the method for driving the rail support unit 30 and supporting the rail 10 is a known art, so that the detailed description thereon will be omitted.
- a mold 200 is installed around the rail support unit 30 for thereby preventing the concrete from being inputted into the surrounding portions of the rail support unit 30 when constructing the concrete.
- the portions corresponding to the mold 200 is finished with cement after the concrete is cured.
- the gauge tie rod 40 of which both ends are fixedly supported by the rail support upper plate 80 and an intermediate part is flexible is adapted to prevent the rail 10 from being elongated when the concrete of the slab 20 is constructed in a step S400.
- the gauge strut 50 of which both ends are fixedly supported by the rail support upper plate 80 and an intermediate portion is flexible is adapted to prevent the rail 10 from being sagged when the concrete is constructed in a step S500.
- the horizontal support member 60 that is installed outside the rail 10 to be at the same line with the gauge strut 50 wherein an intermediate portion of the same is flexible is adapted to maintain a horizontal state of the rail 10 when the concrete of the slab 20 is constructed in a step S600.
- the concrete supplied between the ground and the slab 20 through the inlet 22 formed at the center of the slab 20 constructs the slab 20 on the ground in a step S700. At this time, the concrete is constructed with a certain height including the height of the slab 20 for thereby enhancing a support force.
- the rail support unit 30, the gauge tie rod 40, the gauge strut 50 and the horizontal support member 60 are disassembled from the rail 10 after the concrete ballast 70 is cured (generally after 3 ⁇ 5 days) in a step S800.
- the rail 10 is supported by a plurality of the rail support part 30 in a state that the rail tie and gravel are removed from the lower side of the rail 10, it is possible to prevent the rail 10 from being sagged wherein the rail 10 is sagged due to a vertical weight from the rail 10 when the train runs.
- the slab 20 is designed to prevent the rail 10 from being sagged by the tie rod 40 when the concrete is constructed, and the strut 50 is designed to prevent the rail 10 from being contracted, and the horizontal support member 60 is designed to maintain a horizontal state of the rail.
- the railroad concrete ballast construction system according to the present invention has the following advantages.
- the gravel ballast can be exchanged with a concrete ballast during the operation of the train, any inconvenience is not provided to train passenger.
- the work for exchanging the gravel ballast with a concrete ballast can be performed during a day time, resulting in a better work environment. Therefore, work time is significantly decreased, and workers have less workload.
Abstract
Description
- The present invention relates to a railroad concrete ballast construction system and method capable of exchanging a certain section of a gravel ballast track with a new concrete ballast track even when a train currently runs on a railroad, and in particular to a railroad concrete ballast construction system and method capable of constructing a concrete ballast at a certain section of a gravel ballast having no gravel and rail tie for exchanging a certain section of a gravel ballast with a new concrete ballast in a state that a train currently runs on a railroad, curing and disassembling a structure adapted to fix a rail for a stable operation of a train for thereby effectively finishing an exchanging work.
- Generally, the ballast has been used for widely distributing a weight transferred through a rail and rail tie, and transferring to a ground, resulting in a reduction of the weight. In addition, the ballast is capable of preventing a rail tie movement occurring due to a contraction and elongation of a rail by a temperature change based on a ballast resistance force for thereby absorbing a vibration of a train and enhancing an absorbing effect.
- In addition, a drainage operation is enhanced in cooperation with the ballast, and it is possible to effectively prevent the growth of weeds. Therefore, the gravels that have the above functions and are easily obtained, have been widely used as a material of the ballast.
- As shown in
Figure 1 , the gravel ballast includes arail 1 that supports train wheels, arail tie 2 that is formed of a concrete rail tie or a wooden rail tie for transferring a weight or impact from therail 1 to the ground when a train runs on a rail road, agravel ballast 3 that is provided between the ground and therail tie 2 for thereby absorbing the weight transferred thereto, and aclamp 5 of which one end is engaged with afixture 4 fixed at therail tie 2, an intermediate portion supports aflange 1 a of therail 1, and the other end supports thefixture 4 wherein theclamp 5 is designed with three support points in an E-shape. - The above gravel ballast has an advantage of uniformly distributing the weight transferred through the
rail 1 when the train runs to the ground. However, the gravels of thegravel ballast 3 may be broken and worn away, thus producing small gravel pieces. In this case, the function of the ballast is significantly decreased and the safety factor of the train operation is decreased, thereby causing an accident. - In the case that the gravels of the
gravel ballast 3 are disappeared and broken into small gravels, the absorbing effect becomes decreased, and it is needed to continuously refill the gravels into thegravel ballast 3. Therefore, additional workers and time are needed, so that a maintenance cost is increased. In this case, it is impossible to perform the work for filling the gravels into thegravel ballast 3 when the train runs. - Recently, in order to overcome the above problems, a concrete ballast has been constructed. And also the gravel ballast is now exchanging with a concrete ballast.
- However, in order to exchange the gravel ballast with a concrete ballast, it is needed to stop the running of the train. In this case, many conveniences are caused to passenger. In addition, an exchanging work is performed during a nighttime in which the operation of the train is stopped. In this case, workers have too much workload due to a bad work environment. As a result, workability is decreased.
DocumentDE-19903702 A1 , which is regarded as the closest prior art, describes a railroad construction system and discloses all the features of the preamble ofclaim 1. - Accordingly, it is an object of the present invention to provide a railroad concrete ballast construction system and method capable of enhancing a workability efficiency in such a manner that a certain section of a gravel ballast is exchanged with a concrete ballast when a train currently runs on a railroad.
- It is another object of the present invention to provide a railroad concrete ballast construction system and method capable of significantly reducing a workload of a worker in such a manner that an exchanging work can be performed during a night without causing any convenience with respect to a train passenger by exchanging a gravel ballast with a concrete ballast when a train runs on a railroad.
- To achieve the above objects, there is provided a railroad concrete ballast construction system with the features of
claim 1, comprising a concrete rail tie slab in which a mounting part formed at both sides is engaged at a certain section having no gravel and rail tie on a gravel ballast track by a certain fixture; a rail support unit that is detachably installed between opposite slabs, and supports a vertical weight applied to a rail when a train runs, and supports the rail on the ground for thereby preventing the rail from being sagged; a gauge tie rod of which both ends are fixed at a rail support upper plate and an intermediate portion is flexible, for thereby preventing an elongation of the rail when a concrete of the slab is constructed; a gauge strut of which both ends are fixed at an inner surface of a body of the rail and an intermediate portion is flexible, for thereby preventing a contraction of the rail when a concrete of the slab is constructed; a horizontal support member that is installed outside the rail to be on the same line as the gauge strut, and supports an outer surface of the body of the rail and maintains a horizontal state of the rail when a concrete of the slab is constructed; and a concrete ballast that fixes the slab on the ground in cooperation with the concrete constructed between the ground and the slab through an inlet formed at the slab. - In the present invention, receiving groove is formed at an outer surface of the slab so that the rail support unit is disassembled from the slab and is pulled out in an outer direction after the concrete is cured.
- The concrete rail tie slab includes a mounting part that is protruded from the left and right sides of an upper surface of the slab in opposite directions wherein the rail is mounted thereon; an engaging part that is engaged with an engaging hole formed at the left and right sides of the mounting part and has a certain elastic force capable of supporting a flange of the inner and outer sides of the rail; and an assistant engaging part that is engaged with a through hole formed at the slab in an outer direction of the mounting part and is embedded when a concrete is constructed for thereby enhancing an engaging force of the slab.
- The concrete rail tie slab is formed of a steel-reinforced concrete structure of which a tensional force is reinforced using steel bars embedded.
- To achieve the above objects, there is provided a railroad rail concrete ballast construction method, comprising the steps of removing gravels and rail ties from the ground and the rail in a certain section of a gravel ballast track; engaging a concrete rail tie slab at a lower side of a flange of the rail using a certain fixture; supporting the rail on the ground using a rail support unit installed between the opposite slabs for thereby preventing a sagging of the rail by supporting a vertical weight applied to the rail when a trains runs on the railroad; preventing an elongation of the rail using a gauge tie rod of which both ends are fixed at a rail support upper plate, when a concrete is constructed; preventing a contraction of the rail using a gauge strut of which both ends are fixed at an inner surface of a body of the rail, when a concrete of the slab is constructed; maintaining a horizontal state of the rail, when a concrete of the slab is constructed, by a horizontal support member installed outside the rail to be the same line as the gauge strut; fixing the slab on the ground using a concrete constructed between the ground and the slab through an inlet formed at the slab; and disassembling the rail support unit, the gauge tie rod, the gauge strut and the horizontal support member after the concrete is cured.
- The present invention will become better understood with reference to the accompanying drawings which are given only by way of illustration and thus are not limitative of the present invention, wherein;
-
Figure 1 is a cross sectional view illustrating a gravel ballast of a conventional railroad; -
Figure 2 is a schematic plan view illustrating a railroad concrete ballast construction system according to the present invention; -
Figure 3 is a schematic view illustrating a state that a gravel and rail tie are removed, and a rail is supported in a certain section of a gravel ballast in which a railroad concrete ballast construction system according to the present invention is adapted; -
Figure 4 is a schematic view illustrating a state that a concrete rail tie slab is installed at a lower side of a rail according to the present invention; -
Figure 5 is a schematic view illustrating a state that a concrete is constructed between the ground and a slab ofFigure 4 ; -
Figure 6 is a cross sectional view illustrating a slab according to the present invention; and -
Figure 7 is a flow chart of a work process of a railroad concrete ballast construction system according to the present invention. - As shown in
Figures 2 through 6 , a railroad concrete ballast construction system according to the present invention includes a concreterail tie slab 20 in which amounting unit 21 is engaged at arail 10 by a certain fixture in a certain section of a gravel ballast track having no gravel and rail tie wherein a train can run on a railroad; and arail support unit 30 that is installed so that it is disassembled between theopposite slabs 20 and is designed to support a vertical weight applied to therail 10 when the train runs and the weight of therail 10 at the ground for thereby preventing therail 10 from being sagged. - The
rail support unit 30 may be preferably formed of a hydraulic jack, a screw jack, a rack jack, etc. - The concrete
rail tie slab 20 may be preferably formed of a reinforced concrete (RC) of which a tensional force is reinforced by an embedded reinforcing bar (not shown). - In addition, there are further provided a
gauge tie rod 40 of which both ends are fixed to anupper plate 80 and an intermediate part is flexible so that it is possible to prevent therail 10 from being elongated when concrete is constructed or a train runs; and agauge strut 50 of which both ends are fixed to an inner surface of abody 11 of the rail 109 and an intermediate portion is flexible for thereby preventing the rail from being contracted when the concrete of theslab 20 is constructed. - There are further provided a
horizontal support member 60 that is installed outside therail 10 to be on the same line with thegauge strut 50 and supports an outer side of thebody 11 of therail 10 for thereby maintaining a horizontal state of the rail when the concrete of theslab 20 is constructed; and aconcrete ballast 70 that fixes theslab 20 on the ground based on the concrete constructed between the ground and theslab 20 through aninlet 22 formed at theslab 20. - Here, the concrete
rail tie slab 20 includes amounting part 21 that is protruded from the left and right sides of the upper surface of theslab 20 in opposite directions wherein therail 10 is mounted thereon; anengaging part 25 that is engaged to an engaging hole formed at the left and right sides of themounting part 21 and has an elastic force and is fixed by an engaging bolt B supporting aflange 12 at the inner and outer sides of therail 10; and anassistant engaging part 27 that is engaged with athrough hole 26 formed at theslab 20 at the outer side of themounting part 21 for thereby enhancing an engaging force of theslab 20 when the concrete is constructed. - A receiving
groove 23 is formed at an outer surface of theslab 20 so that therail support part 30 is disassembled from theslab 20 in an outer direction after the concrete is cured. - In the drawing,
reference numeral 90 represents an anti-vibration member that is installed at the lower side of theflange 20 of therail 10 for thereby absorbing impacts and vibrations, and 100 represents a driving motor for driving a pair oflevers driving shaft 102 is rotated for thereby preventing therail 10 from being sagged by asupport part 101. - The operation of the railroad concrete ballast construction system according to the present invention will be described.
- As shown in
Figure 7 , the gravels and rail ties are removed from the ground and therail 10 in a certain section of the gravel ballast track on which the train can run in a step S100. At this time, therail 10 in the section having no gravel and rail tie is installed with a certain gap from the ground. - As shown in
Figure 3 , the concreterail tie slab 20 is engaged to a lower side of theflange 12 of therail 10 using a certain fixture in a step S200. Theslab 20 is moved by a certain lifting equipment such as a crane, etc. and is inserted between therail 10 and the ground. - On the ground, the
rail 10 is supported by therail support unit 30 installed between theopposite slabs 20 for thereby preventing therail 10 from being sagged by supporting a vertical weight applied to therail 10 when the train runs during a working time in a step S300. - At this time, the
rail support unit 30 may be formed of a hydraulic jack, a screw jack, etc. The method for driving therail support unit 30 and supporting therail 10 is a known art, so that the detailed description thereon will be omitted. - A
mold 200 is installed around therail support unit 30 for thereby preventing the concrete from being inputted into the surrounding portions of therail support unit 30 when constructing the concrete. The portions corresponding to themold 200 is finished with cement after the concrete is cured. - Here, the
gauge tie rod 40 of which both ends are fixedly supported by the rail supportupper plate 80 and an intermediate part is flexible is adapted to prevent therail 10 from being elongated when the concrete of theslab 20 is constructed in a step S400. - The
gauge strut 50 of which both ends are fixedly supported by the rail supportupper plate 80 and an intermediate portion is flexible is adapted to prevent therail 10 from being sagged when the concrete is constructed in a step S500. - The
horizontal support member 60 that is installed outside therail 10 to be at the same line with thegauge strut 50 wherein an intermediate portion of the same is flexible is adapted to maintain a horizontal state of therail 10 when the concrete of theslab 20 is constructed in a step S600. - The concrete supplied between the ground and the
slab 20 through theinlet 22 formed at the center of theslab 20 constructs theslab 20 on the ground in a step S700. At this time, the concrete is constructed with a certain height including the height of theslab 20 for thereby enhancing a support force. - The
rail support unit 30, thegauge tie rod 40, thegauge strut 50 and thehorizontal support member 60 are disassembled from therail 10 after theconcrete ballast 70 is cured (generally after 3~5 days) in a step S800. - As described above, in the case that the work for exchanging a part of the gravel ballast with a concrete ballast is performed, since the
rail 10 is supported by a plurality of therail support part 30 in a state that the rail tie and gravel are removed from the lower side of therail 10, it is possible to prevent therail 10 from being sagged wherein therail 10 is sagged due to a vertical weight from therail 10 when the train runs. - In addition, the
slab 20 is designed to prevent therail 10 from being sagged by thetie rod 40 when the concrete is constructed, and thestrut 50 is designed to prevent therail 10 from being contracted, and thehorizontal support member 60 is designed to maintain a horizontal state of the rail. - Therefore, in the present invention, it is possible to prevent the sagging and contraction of the
rail 10 at a certain section even when the train runs during the working time for thereby continuously performing the gravel ballast exchanging work, so that it is possible to significantly enhance the workability. - As described above, the railroad concrete ballast construction system according to the present invention has the following advantages.
- In the present invention, it is possible to continuously perform a work for exchanging a certain section of the gravel ballast with a concrete ballast even when the train runs on the railroad for thereby enhancing a workability.
- In addition, in the present invention, since the gravel ballast can be exchanged with a concrete ballast during the operation of the train, any inconvenience is not provided to train passenger. The work for exchanging the gravel ballast with a concrete ballast can be performed during a day time, resulting in a better work environment. Therefore, work time is significantly decreased, and workers have less workload.
- As the present invention may be embodied in several forms without departing from the spirit or essential characteristics thereof, it should also be understood that the above-described examples are not limited by any of the details of the foregoing description, unless otherwise specified, but rather should be construed within the scope as defined in the appended claims, and therefore all changes and modifications that fall within the meets and bounds of the claims, are intended to be embraced by the appended claims.
Claims (5)
- A railroad concrete ballast construction system, comprising:a concrete rail tie slab (20) in which a mounting part (21) formed at both sides is engaged at a certain section having no gravel and rail tie on a gravel ballast track by a certain fixing means (25);a rail support (30) unit that is detachably installed between opposite slabs, and supports a vertical weight applied to a rail when a train runs, and supports the rail (10) on the ground for thereby preventing the rail from being sagged;a horizontal support member (60) that is installed outside the rail, and supports an outer surface of the body of the rail and maintains a horizontal state of the rail when a concrete of the slab is constructed;and a concrete ballast (70) that fixes the slab on the ground in cooperation with the concrete constructed between the ground and the slab through an inlet (22) formed at the slab; characterised in that it further comprisesa gauge tie rod (40) of which both ends are fixed at a rail support upper plate (80) and an intermediate portion is flexible, for thereby preventing an elongation of the rail when a concrete of the slab (70) is constructed;a gauge strut (50), installed on the same line as the horizontal support member, of which both ends are fixed at an inner surface of a body of the rail (11) and an intermediate portion is flexible, for thereby preventing a contraction of the rail (10) when a concrete of the slab is constructed.
- The system of claim 1, wherein a receiving groove (23) is formed at an outer surface of the slab (20) so that the rail support unit (30) is disassembled from the slab and is pulled out in an outer direction after the concrete is cured.
- The system of either claim 1 or claim 2, wherein said concrete rail tie slab (20) includes:a mounting part (21) that is protruded from the left and right sides of an upper surface of the slab in opposite directions wherein the rail is mounted thereon;an engaging part (25) that is engaged with an engaging hole formed at the left and right sides of the mounting part and has a certain elastic force capable of supporting a flange of the inner and outer sides of the rail; andan assistant engaging part (27) that is engaged with a through hole (26) formed at the slab in an outer direction of the mounting part and is embedded when a concrete is constructed for thereby enhancing an engaging force of the slab.
- The system of either claim 1 or claim 2, wherein said concrete rail tie slab (20) is formed of a steel-reinforced concrete structure of which a tensional force is reinforced using steel bars embedded.
- A railroad rail concrete ballast construction method, comprising:removing gravels (3) and rail ties (2) from the ground and the rail in a certain section of a gravel ballast track;engaging a concrete rail tie slab (20) at a lower side of a flange (12) of the rail (10) using a certain fixing means (25);supporting the rail on the ground using a rail support (30) unit installed between the opposite slabs for thereby preventing a sagging of the rail by supporting a vertical weight applied to the rail when a trains runs on the railroad;preventing an elongation of the rail using a gauge tie rod (40) of which both ends are fixed at a rail support upper plate (80), when a concrete (70) is constructed;preventing a contraction of the rail using a gauge strut (50) of which both ends are fixed at an inner surface of a body of the rail (11), when a concrete of the slab (20) is constructed;maintaining a horizontal state of the rail, when a concrete of the slab is constructed, by a horizontal support member (60) installed outside the rail to be the same line as the gauge strut;fixing the slab (20) on the ground using a concrete (70) constructed between the ground and the slab through an inlet (22) formed at the slab (20); anddisassembling the rail support unit (30), the gauge tie rod (40), the gauge strut (50) and the horizontal support member (60) after the concrete (70) is cured.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR2004012205 | 2004-02-24 | ||
KR1020040012205A KR100595429B1 (en) | 2004-02-24 | 2004-02-24 | Concrete sleeper for structure of rail |
Publications (3)
Publication Number | Publication Date |
---|---|
EP1568821A2 EP1568821A2 (en) | 2005-08-31 |
EP1568821A3 EP1568821A3 (en) | 2006-11-02 |
EP1568821B1 true EP1568821B1 (en) | 2008-03-19 |
Family
ID=34747934
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP05001314A Not-in-force EP1568821B1 (en) | 2004-02-24 | 2005-01-24 | Railroad concrete ballast construction system and method |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP1568821B1 (en) |
KR (1) | KR100595429B1 (en) |
AT (1) | ATE389747T1 (en) |
DE (1) | DE602005005372T2 (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100744175B1 (en) * | 2005-12-07 | 2007-08-02 | 한국철도기술연구원 | Precast concrete slab on ballast track and concrete ballast laying system and method using it |
EP2206831B1 (en) * | 2009-01-13 | 2014-11-05 | Knape Gruppe Holding GmbH | Device and method for lifting and aligning rails |
KR101052906B1 (en) * | 2010-12-02 | 2011-07-29 | 삼표이앤씨 주식회사 | Precast slab track system and method constructing the same |
KR101439527B1 (en) * | 2012-08-20 | 2014-09-15 | 영중산업 주식회사 | Rail supporter for installing rail assembly of concrete railroad |
CN103334350B (en) * | 2013-07-16 | 2015-08-12 | 中国铁道科学研究院铁道建筑研究所 | A kind of prestressed reinforced concrete tie, track plates thread rolling scale helix rib steel wire |
KR101660212B1 (en) | 2016-06-15 | 2016-10-10 | 이국현 | Assembling method of mounting module for railway |
KR102091735B1 (en) | 2018-03-05 | 2020-03-20 | 한국철도기술연구원 | Fast-hardening track for improving resistance performance against vertical deform and horizontal deform, and construction method for the same |
KR102196373B1 (en) | 2020-04-07 | 2020-12-29 | 황윤태 | Rail construction method using precast slab panel |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2691484B1 (en) * | 1992-05-22 | 1994-07-29 | Vanotti Gerard | METHOD OF CONSTRUCTING A RAILWAY IN CONCRETE. |
DE4437826A1 (en) * | 1993-10-18 | 1996-04-18 | Betonwerk Rethwisch Gmbh | Roadbed for railway using noise reducing elements and no ballast |
DE19903702A1 (en) * | 1999-01-30 | 2000-08-03 | Bahnbau Wels Gmbh Wels | Device for height and side alignment and / or support of the rails of a track |
ES2211386T3 (en) * | 1999-02-08 | 2004-07-16 | Hochtief Aktiengesellschaft | PROCEDURE FOR THE MANUFACTURE OF A RAILWAY WITHOUT BASKET. |
KR20030065897A (en) * | 2002-02-01 | 2003-08-09 | 주식회사 에이브이티 | Structure of concrete ballast track and construction method thereof |
KR100446310B1 (en) * | 2002-11-07 | 2004-08-30 | (주)신성엔지니어링 | Apparatus for preventing cross movement of railroad track |
-
2004
- 2004-02-24 KR KR1020040012205A patent/KR100595429B1/en active IP Right Grant
-
2005
- 2005-01-24 DE DE602005005372T patent/DE602005005372T2/en active Active
- 2005-01-24 EP EP05001314A patent/EP1568821B1/en not_active Not-in-force
- 2005-01-24 AT AT05001314T patent/ATE389747T1/en not_active IP Right Cessation
Also Published As
Publication number | Publication date |
---|---|
DE602005005372T2 (en) | 2008-07-17 |
KR100595429B1 (en) | 2006-07-03 |
DE602005005372D1 (en) | 2008-04-30 |
KR20050087018A (en) | 2005-08-31 |
EP1568821A2 (en) | 2005-08-31 |
ATE389747T1 (en) | 2008-04-15 |
EP1568821A3 (en) | 2006-11-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1568821B1 (en) | Railroad concrete ballast construction system and method | |
KR100808212B1 (en) | The bridge upper structure pulling up for which construction bent for bridge upper structure pulling up and this were used | |
JP5266291B2 (en) | Construction method of bridge deck and joint structure of precast deck | |
CN1807757A (en) | Pre-assembled plate consisting of armoured concrete | |
JP6837343B2 (en) | Floor slab replacement method for synthetic girders | |
KR100891961B1 (en) | The construction infrastructure the use road the martial art as a matter of bridge of the bridge which is old in the railroad or the railroad respects the induction event a method of construction which shifts the bridge and the system | |
JP5184311B2 (en) | Steel structure construction method | |
CA2194794A1 (en) | Substructure for a rail vehicle track | |
KR100355091B1 (en) | Method for reinforcing resistance force of a bridge using a prefabricated bracket | |
JP6074378B2 (en) | Expansion device replacement method and temporary lining plate structure | |
KR100454405B1 (en) | Method for changing steel bridge of supporting rail into concreat bridge | |
KR100454406B1 (en) | Method and apparatus for changing steel bridge of supporting rail into concrete bridge using temporary bent | |
KR100449231B1 (en) | temporaty bridge using prestressed compuond double girder and method for building the temporary bridge | |
JP4934779B2 (en) | Boarding / exit structure and boarding / exiting method | |
KR20020082728A (en) | Process and frame for substituting steel girder of a railway bridge for concrete slab | |
CN209891074U (en) | Cast-in-place reinforced concrete guardrail slip form system | |
KR20100109471A (en) | H shaped tie for railroad and mold for making thereof | |
CN210151571U (en) | Prefabricated guardrail mounting and positioning device | |
KR100638578B1 (en) | Method for carrying out replacement of an upper structure of a railway bridge | |
JP2007169950A (en) | Expansion body for bridge, and bridge expansion structure using the same | |
KR101996601B1 (en) | Mono-block for improving metrology and method of the same | |
KR20060082970A (en) | Crane for replacement of a girdir of a railway bridge and method for replacement of the girdir using the same | |
JP3814286B2 (en) | Formwork support structure | |
KR101756965B1 (en) | Height adjusting type maintanable rail track construction method and maintanance method using the same | |
JP2020186614A (en) | Precast floor slab connection part structure and connection part construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20050124 |
|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU MC NL PL PT RO SE SI SK TR |
|
AX | Request for extension of the european patent |
Extension state: AL BA HR LV MK YU |
|
RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: SEOUL METRO |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU MC NL PL PT RO SE SI SK TR |
|
AX | Request for extension of the european patent |
Extension state: AL BA HR LV MK YU |
|
AKX | Designation fees paid |
Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU MC NL PL PT RO SE SI SK TR |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU MC NL PL PT RO SE SI SK TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REF | Corresponds to: |
Ref document number: 602005005372 Country of ref document: DE Date of ref document: 20080430 Kind code of ref document: P |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 |
|
NLV1 | Nl: lapsed or annulled due to failure to fulfill the requirements of art. 29p and 29m of the patents act | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080826 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080619 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080630 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080719 |
|
EN | Fr: translation not filed | ||
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 |
|
26N | No opposition filed |
Effective date: 20081222 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080619 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20090131 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20090124 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20090131 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20090131 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20090124 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20090126 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080620 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20090124 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080920 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20080319 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20090109 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20190214 Year of fee payment: 15 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602005005372 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200801 |