EP1568821B1 - Railroad concrete ballast construction system and method - Google Patents

Railroad concrete ballast construction system and method Download PDF

Info

Publication number
EP1568821B1
EP1568821B1 EP05001314A EP05001314A EP1568821B1 EP 1568821 B1 EP1568821 B1 EP 1568821B1 EP 05001314 A EP05001314 A EP 05001314A EP 05001314 A EP05001314 A EP 05001314A EP 1568821 B1 EP1568821 B1 EP 1568821B1
Authority
EP
European Patent Office
Prior art keywords
rail
concrete
slab
ballast
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Not-in-force
Application number
EP05001314A
Other languages
German (de)
French (fr)
Other versions
EP1568821A2 (en
EP1568821A3 (en
Inventor
Sang Jin Kim
Sung Min Chung
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEOUL METRO
Original Assignee
Seoul Metro
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seoul Metro filed Critical Seoul Metro
Publication of EP1568821A2 publication Critical patent/EP1568821A2/en
Publication of EP1568821A3 publication Critical patent/EP1568821A3/en
Application granted granted Critical
Publication of EP1568821B1 publication Critical patent/EP1568821B1/en
Not-in-force legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • DTEXTILES; PAPER
    • D05SEWING; EMBROIDERING; TUFTING
    • D05CEMBROIDERING; TUFTING
    • D05C3/00General types of embroidering machines
    • D05C3/02General types of embroidering machines with vertical needles
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • E01B1/004Ballastless track, e.g. concrete slab trackway, or with asphalt layers with prefabricated elements embedded in fresh concrete or asphalt
    • DTEXTILES; PAPER
    • D05SEWING; EMBROIDERING; TUFTING
    • D05CEMBROIDERING; TUFTING
    • D05C13/00Auxiliary devices incorporated in embroidering machines, not otherwise provided for; Ancillary apparatus for use with embroidering machines
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • E01B1/007Ballastless track, e.g. concrete slab trackway, or with asphalt layers with interlocking means to withstand horizontal forces
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/06Height or lateral adjustment means or positioning means for slabs, sleepers or rails

Definitions

  • the present invention relates to a railroad concrete ballast construction system and method capable of exchanging a certain section of a gravel ballast track with a new concrete ballast track even when a train currently runs on a railroad, and in particular to a railroad concrete ballast construction system and method capable of constructing a concrete ballast at a certain section of a gravel ballast having no gravel and rail tie for exchanging a certain section of a gravel ballast with a new concrete ballast in a state that a train currently runs on a railroad, curing and disassembling a structure adapted to fix a rail for a stable operation of a train for thereby effectively finishing an exchanging work.
  • the ballast has been used for widely distributing a weight transferred through a rail and rail tie, and transferring to a ground, resulting in a reduction of the weight.
  • the ballast is capable of preventing a rail tie movement occurring due to a contraction and elongation of a rail by a temperature change based on a ballast resistance force for thereby absorbing a vibration of a train and enhancing an absorbing effect.
  • the gravel ballast includes a rail 1 that supports train wheels, a rail tie 2 that is formed of a concrete rail tie or a wooden rail tie for transferring a weight or impact from the rail 1 to the ground when a train runs on a rail road, a gravel ballast 3 that is provided between the ground and the rail tie 2 for thereby absorbing the weight transferred thereto, and a clamp 5 of which one end is engaged with a fixture 4 fixed at the rail tie 2, an intermediate portion supports a flange 1 a of the rail 1, and the other end supports the fixture 4 wherein the clamp 5 is designed with three support points in an E-shape.
  • the above gravel ballast has an advantage of uniformly distributing the weight transferred through the rail 1 when the train runs to the ground.
  • the gravels of the gravel ballast 3 may be broken and worn away, thus producing small gravel pieces.
  • the function of the ballast is significantly decreased and the safety factor of the train operation is decreased, thereby causing an accident.
  • a railroad concrete ballast construction system with the features of claim 1, comprising a concrete rail tie slab in which a mounting part formed at both sides is engaged at a certain section having no gravel and rail tie on a gravel ballast track by a certain fixture; a rail support unit that is detachably installed between opposite slabs, and supports a vertical weight applied to a rail when a train runs, and supports the rail on the ground for thereby preventing the rail from being sagged; a gauge tie rod of which both ends are fixed at a rail support upper plate and an intermediate portion is flexible, for thereby preventing an elongation of the rail when a concrete of the slab is constructed; a gauge strut of which both ends are fixed at an inner surface of a body of the rail and an intermediate portion is flexible, for thereby preventing a contraction of the rail when a concrete of the slab is constructed; a horizontal support member that is installed outside the rail to be on the same line as the gauge strut, and supports an outer surface of the body of the
  • receiving groove is formed at an outer surface of the slab so that the rail support unit is disassembled from the slab and is pulled out in an outer direction after the concrete is cured.
  • the concrete rail tie slab includes a mounting part that is protruded from the left and right sides of an upper surface of the slab in opposite directions wherein the rail is mounted thereon; an engaging part that is engaged with an engaging hole formed at the left and right sides of the mounting part and has a certain elastic force capable of supporting a flange of the inner and outer sides of the rail; and an assistant engaging part that is engaged with a through hole formed at the slab in an outer direction of the mounting part and is embedded when a concrete is constructed for thereby enhancing an engaging force of the slab.
  • the concrete rail tie slab is formed of a steel-reinforced concrete structure of which a tensional force is reinforced using steel bars embedded.
  • a railroad rail concrete ballast construction method comprising the steps of removing gravels and rail ties from the ground and the rail in a certain section of a gravel ballast track; engaging a concrete rail tie slab at a lower side of a flange of the rail using a certain fixture; supporting the rail on the ground using a rail support unit installed between the opposite slabs for thereby preventing a sagging of the rail by supporting a vertical weight applied to the rail when a trains runs on the railroad; preventing an elongation of the rail using a gauge tie rod of which both ends are fixed at a rail support upper plate, when a concrete is constructed; preventing a contraction of the rail using a gauge strut of which both ends are fixed at an inner surface of a body of the rail, when a concrete of the slab is constructed; maintaining a horizontal state of the rail, when a concrete of the slab is constructed, by a horizontal support member installed outside the rail to be the same line as the gauge strut; fixing the slab on the ground
  • a railroad concrete ballast construction system includes a concrete rail tie slab 20 in which a mounting unit 21 is engaged at a rail 10 by a certain fixture in a certain section of a gravel ballast track having no gravel and rail tie wherein a train can run on a railroad; and a rail support unit 30 that is installed so that it is disassembled between the opposite slabs 20 and is designed to support a vertical weight applied to the rail 10 when the train runs and the weight of the rail 10 at the ground for thereby preventing the rail 10 from being sagged.
  • the rail support unit 30 may be preferably formed of a hydraulic jack, a screw jack, a rack jack, etc.
  • the concrete rail tie slab 20 may be preferably formed of a reinforced concrete (RC) of which a tensional force is reinforced by an embedded reinforcing bar (not shown).
  • RC reinforced concrete
  • a horizontal support member 60 that is installed outside the rail 10 to be on the same line with the gauge strut 50 and supports an outer side of the body 11 of the rail 10 for thereby maintaining a horizontal state of the rail when the concrete of the slab 20 is constructed; and a concrete ballast 70 that fixes the slab 20 on the ground based on the concrete constructed between the ground and the slab 20 through an inlet 22 formed at the slab 20.
  • the concrete rail tie slab 20 includes a mounting part 21 that is protruded from the left and right sides of the upper surface of the slab 20 in opposite directions wherein the rail 10 is mounted thereon; an engaging part 25 that is engaged to an engaging hole formed at the left and right sides of the mounting part 21 and has an elastic force and is fixed by an engaging bolt B supporting a flange 12 at the inner and outer sides of the rail 10; and an assistant engaging part 27 that is engaged with a through hole 26 formed at the slab 20 at the outer side of the mounting part 21 for thereby enhancing an engaging force of the slab 20 when the concrete is constructed.
  • a receiving groove 23 is formed at an outer surface of the slab 20 so that the rail support part 30 is disassembled from the slab 20 in an outer direction after the concrete is cured.
  • reference numeral 90 represents an anti-vibration member that is installed at the lower side of the flange 20 of the rail 10 for thereby absorbing impacts and vibrations
  • 100 represents a driving motor for driving a pair of levers 103 and 104 when a driving shaft 102 is rotated for thereby preventing the rail 10 from being sagged by a support part 101.
  • the gravels and rail ties are removed from the ground and the rail 10 in a certain section of the gravel ballast track on which the train can run in a step S100.
  • the rail 10 in the section having no gravel and rail tie is installed with a certain gap from the ground.
  • the concrete rail tie slab 20 is engaged to a lower side of the flange 12 of the rail 10 using a certain fixture in a step S200.
  • the slab 20 is moved by a certain lifting equipment such as a crane, etc. and is inserted between the rail 10 and the ground.
  • the rail 10 On the ground, the rail 10 is supported by the rail support unit 30 installed between the opposite slabs 20 for thereby preventing the rail 10 from being sagged by supporting a vertical weight applied to the rail 10 when the train runs during a working time in a step S300.
  • the rail support unit 30 may be formed of a hydraulic jack, a screw jack, etc.
  • the method for driving the rail support unit 30 and supporting the rail 10 is a known art, so that the detailed description thereon will be omitted.
  • a mold 200 is installed around the rail support unit 30 for thereby preventing the concrete from being inputted into the surrounding portions of the rail support unit 30 when constructing the concrete.
  • the portions corresponding to the mold 200 is finished with cement after the concrete is cured.
  • the gauge tie rod 40 of which both ends are fixedly supported by the rail support upper plate 80 and an intermediate part is flexible is adapted to prevent the rail 10 from being elongated when the concrete of the slab 20 is constructed in a step S400.
  • the gauge strut 50 of which both ends are fixedly supported by the rail support upper plate 80 and an intermediate portion is flexible is adapted to prevent the rail 10 from being sagged when the concrete is constructed in a step S500.
  • the horizontal support member 60 that is installed outside the rail 10 to be at the same line with the gauge strut 50 wherein an intermediate portion of the same is flexible is adapted to maintain a horizontal state of the rail 10 when the concrete of the slab 20 is constructed in a step S600.
  • the concrete supplied between the ground and the slab 20 through the inlet 22 formed at the center of the slab 20 constructs the slab 20 on the ground in a step S700. At this time, the concrete is constructed with a certain height including the height of the slab 20 for thereby enhancing a support force.
  • the rail support unit 30, the gauge tie rod 40, the gauge strut 50 and the horizontal support member 60 are disassembled from the rail 10 after the concrete ballast 70 is cured (generally after 3 ⁇ 5 days) in a step S800.
  • the rail 10 is supported by a plurality of the rail support part 30 in a state that the rail tie and gravel are removed from the lower side of the rail 10, it is possible to prevent the rail 10 from being sagged wherein the rail 10 is sagged due to a vertical weight from the rail 10 when the train runs.
  • the slab 20 is designed to prevent the rail 10 from being sagged by the tie rod 40 when the concrete is constructed, and the strut 50 is designed to prevent the rail 10 from being contracted, and the horizontal support member 60 is designed to maintain a horizontal state of the rail.
  • the railroad concrete ballast construction system according to the present invention has the following advantages.
  • the gravel ballast can be exchanged with a concrete ballast during the operation of the train, any inconvenience is not provided to train passenger.
  • the work for exchanging the gravel ballast with a concrete ballast can be performed during a day time, resulting in a better work environment. Therefore, work time is significantly decreased, and workers have less workload.

Abstract

The railroad concrete ballast construction system and method are disclosed, which are capable of constructing a concrete ballast (70) at a certain section of a gravel ballast having no gravel and rail tie (20) for exchanging a certain section of a gravel ballast (3) with a new concrete ballast (70) in a state that a train currently runs on a railroad, curing and disassembling a structure adapted to fix a rail for a stable operation of a train for thereby effectively finishing an exchanging work. The railroad concrete ballast construction system includes a concrete rail tie slab engaged at a rail (10) of a certain section having no gravels and rail ties in a gravel ballast, a rail support unit (30) for supporting a vertical weight applied to the rail during an operation of the train and preventing a sagging of the rail, a gauge tie rod (40) for preventing an elongation of the rail when a concrete of the slab is constructed, a gauge strut (50) for preventing a contraction of the rail when a concrete of the slab is constructed, a horizontal support member (60) for maintaining a horizontal state of the rail when a concrete of the slab is constructed, and a concrete ballast for constructing the slab on the ground using a concrete supplied through an inlet formed at the slab.

Description

    BACKGROUND OF THE INVENTION 1. Field of the Invention
  • The present invention relates to a railroad concrete ballast construction system and method capable of exchanging a certain section of a gravel ballast track with a new concrete ballast track even when a train currently runs on a railroad, and in particular to a railroad concrete ballast construction system and method capable of constructing a concrete ballast at a certain section of a gravel ballast having no gravel and rail tie for exchanging a certain section of a gravel ballast with a new concrete ballast in a state that a train currently runs on a railroad, curing and disassembling a structure adapted to fix a rail for a stable operation of a train for thereby effectively finishing an exchanging work.
  • 2. Description of the Background Art
  • Generally, the ballast has been used for widely distributing a weight transferred through a rail and rail tie, and transferring to a ground, resulting in a reduction of the weight. In addition, the ballast is capable of preventing a rail tie movement occurring due to a contraction and elongation of a rail by a temperature change based on a ballast resistance force for thereby absorbing a vibration of a train and enhancing an absorbing effect.
  • In addition, a drainage operation is enhanced in cooperation with the ballast, and it is possible to effectively prevent the growth of weeds. Therefore, the gravels that have the above functions and are easily obtained, have been widely used as a material of the ballast.
  • As shown in Figure 1, the gravel ballast includes a rail 1 that supports train wheels, a rail tie 2 that is formed of a concrete rail tie or a wooden rail tie for transferring a weight or impact from the rail 1 to the ground when a train runs on a rail road, a gravel ballast 3 that is provided between the ground and the rail tie 2 for thereby absorbing the weight transferred thereto, and a clamp 5 of which one end is engaged with a fixture 4 fixed at the rail tie 2, an intermediate portion supports a flange 1 a of the rail 1, and the other end supports the fixture 4 wherein the clamp 5 is designed with three support points in an E-shape.
  • The above gravel ballast has an advantage of uniformly distributing the weight transferred through the rail 1 when the train runs to the ground. However, the gravels of the gravel ballast 3 may be broken and worn away, thus producing small gravel pieces. In this case, the function of the ballast is significantly decreased and the safety factor of the train operation is decreased, thereby causing an accident.
  • In the case that the gravels of the gravel ballast 3 are disappeared and broken into small gravels, the absorbing effect becomes decreased, and it is needed to continuously refill the gravels into the gravel ballast 3. Therefore, additional workers and time are needed, so that a maintenance cost is increased. In this case, it is impossible to perform the work for filling the gravels into the gravel ballast 3 when the train runs.
  • Recently, in order to overcome the above problems, a concrete ballast has been constructed. And also the gravel ballast is now exchanging with a concrete ballast.
  • However, in order to exchange the gravel ballast with a concrete ballast, it is needed to stop the running of the train. In this case, many conveniences are caused to passenger. In addition, an exchanging work is performed during a nighttime in which the operation of the train is stopped. In this case, workers have too much workload due to a bad work environment. As a result, workability is decreased.
    Document DE-19903702 A1 , which is regarded as the closest prior art, describes a railroad construction system and discloses all the features of the preamble of claim 1.
  • SUMMARY OF THE INVENTION
  • Accordingly, it is an object of the present invention to provide a railroad concrete ballast construction system and method capable of enhancing a workability efficiency in such a manner that a certain section of a gravel ballast is exchanged with a concrete ballast when a train currently runs on a railroad.
  • It is another object of the present invention to provide a railroad concrete ballast construction system and method capable of significantly reducing a workload of a worker in such a manner that an exchanging work can be performed during a night without causing any convenience with respect to a train passenger by exchanging a gravel ballast with a concrete ballast when a train runs on a railroad.
  • To achieve the above objects, there is provided a railroad concrete ballast construction system with the features of claim 1, comprising a concrete rail tie slab in which a mounting part formed at both sides is engaged at a certain section having no gravel and rail tie on a gravel ballast track by a certain fixture; a rail support unit that is detachably installed between opposite slabs, and supports a vertical weight applied to a rail when a train runs, and supports the rail on the ground for thereby preventing the rail from being sagged; a gauge tie rod of which both ends are fixed at a rail support upper plate and an intermediate portion is flexible, for thereby preventing an elongation of the rail when a concrete of the slab is constructed; a gauge strut of which both ends are fixed at an inner surface of a body of the rail and an intermediate portion is flexible, for thereby preventing a contraction of the rail when a concrete of the slab is constructed; a horizontal support member that is installed outside the rail to be on the same line as the gauge strut, and supports an outer surface of the body of the rail and maintains a horizontal state of the rail when a concrete of the slab is constructed; and a concrete ballast that fixes the slab on the ground in cooperation with the concrete constructed between the ground and the slab through an inlet formed at the slab.
  • In the present invention, receiving groove is formed at an outer surface of the slab so that the rail support unit is disassembled from the slab and is pulled out in an outer direction after the concrete is cured.
  • The concrete rail tie slab includes a mounting part that is protruded from the left and right sides of an upper surface of the slab in opposite directions wherein the rail is mounted thereon; an engaging part that is engaged with an engaging hole formed at the left and right sides of the mounting part and has a certain elastic force capable of supporting a flange of the inner and outer sides of the rail; and an assistant engaging part that is engaged with a through hole formed at the slab in an outer direction of the mounting part and is embedded when a concrete is constructed for thereby enhancing an engaging force of the slab.
  • The concrete rail tie slab is formed of a steel-reinforced concrete structure of which a tensional force is reinforced using steel bars embedded.
  • To achieve the above objects, there is provided a railroad rail concrete ballast construction method, comprising the steps of removing gravels and rail ties from the ground and the rail in a certain section of a gravel ballast track; engaging a concrete rail tie slab at a lower side of a flange of the rail using a certain fixture; supporting the rail on the ground using a rail support unit installed between the opposite slabs for thereby preventing a sagging of the rail by supporting a vertical weight applied to the rail when a trains runs on the railroad; preventing an elongation of the rail using a gauge tie rod of which both ends are fixed at a rail support upper plate, when a concrete is constructed; preventing a contraction of the rail using a gauge strut of which both ends are fixed at an inner surface of a body of the rail, when a concrete of the slab is constructed; maintaining a horizontal state of the rail, when a concrete of the slab is constructed, by a horizontal support member installed outside the rail to be the same line as the gauge strut; fixing the slab on the ground using a concrete constructed between the ground and the slab through an inlet formed at the slab; and disassembling the rail support unit, the gauge tie rod, the gauge strut and the horizontal support member after the concrete is cured.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • The present invention will become better understood with reference to the accompanying drawings which are given only by way of illustration and thus are not limitative of the present invention, wherein;
    • Figure 1 is a cross sectional view illustrating a gravel ballast of a conventional railroad;
    • Figure 2 is a schematic plan view illustrating a railroad concrete ballast construction system according to the present invention;
    • Figure 3 is a schematic view illustrating a state that a gravel and rail tie are removed, and a rail is supported in a certain section of a gravel ballast in which a railroad concrete ballast construction system according to the present invention is adapted;
    • Figure 4 is a schematic view illustrating a state that a concrete rail tie slab is installed at a lower side of a rail according to the present invention;
    • Figure 5 is a schematic view illustrating a state that a concrete is constructed between the ground and a slab of Figure 4;
    • Figure 6 is a cross sectional view illustrating a slab according to the present invention; and
    • Figure 7 is a flow chart of a work process of a railroad concrete ballast construction system according to the present invention.
    DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
  • As shown in Figures 2 through 6, a railroad concrete ballast construction system according to the present invention includes a concrete rail tie slab 20 in which a mounting unit 21 is engaged at a rail 10 by a certain fixture in a certain section of a gravel ballast track having no gravel and rail tie wherein a train can run on a railroad; and a rail support unit 30 that is installed so that it is disassembled between the opposite slabs 20 and is designed to support a vertical weight applied to the rail 10 when the train runs and the weight of the rail 10 at the ground for thereby preventing the rail 10 from being sagged.
  • The rail support unit 30 may be preferably formed of a hydraulic jack, a screw jack, a rack jack, etc.
  • The concrete rail tie slab 20 may be preferably formed of a reinforced concrete (RC) of which a tensional force is reinforced by an embedded reinforcing bar (not shown).
  • In addition, there are further provided a gauge tie rod 40 of which both ends are fixed to an upper plate 80 and an intermediate part is flexible so that it is possible to prevent the rail 10 from being elongated when concrete is constructed or a train runs; and a gauge strut 50 of which both ends are fixed to an inner surface of a body 11 of the rail 109 and an intermediate portion is flexible for thereby preventing the rail from being contracted when the concrete of the slab 20 is constructed.
  • There are further provided a horizontal support member 60 that is installed outside the rail 10 to be on the same line with the gauge strut 50 and supports an outer side of the body 11 of the rail 10 for thereby maintaining a horizontal state of the rail when the concrete of the slab 20 is constructed; and a concrete ballast 70 that fixes the slab 20 on the ground based on the concrete constructed between the ground and the slab 20 through an inlet 22 formed at the slab 20.
  • Here, the concrete rail tie slab 20 includes a mounting part 21 that is protruded from the left and right sides of the upper surface of the slab 20 in opposite directions wherein the rail 10 is mounted thereon; an engaging part 25 that is engaged to an engaging hole formed at the left and right sides of the mounting part 21 and has an elastic force and is fixed by an engaging bolt B supporting a flange 12 at the inner and outer sides of the rail 10; and an assistant engaging part 27 that is engaged with a through hole 26 formed at the slab 20 at the outer side of the mounting part 21 for thereby enhancing an engaging force of the slab 20 when the concrete is constructed.
  • A receiving groove 23 is formed at an outer surface of the slab 20 so that the rail support part 30 is disassembled from the slab 20 in an outer direction after the concrete is cured.
  • In the drawing, reference numeral 90 represents an anti-vibration member that is installed at the lower side of the flange 20 of the rail 10 for thereby absorbing impacts and vibrations, and 100 represents a driving motor for driving a pair of levers 103 and 104 when a driving shaft 102 is rotated for thereby preventing the rail 10 from being sagged by a support part 101.
  • The operation of the railroad concrete ballast construction system according to the present invention will be described.
  • As shown in Figure 7, the gravels and rail ties are removed from the ground and the rail 10 in a certain section of the gravel ballast track on which the train can run in a step S100. At this time, the rail 10 in the section having no gravel and rail tie is installed with a certain gap from the ground.
  • As shown in Figure 3, the concrete rail tie slab 20 is engaged to a lower side of the flange 12 of the rail 10 using a certain fixture in a step S200. The slab 20 is moved by a certain lifting equipment such as a crane, etc. and is inserted between the rail 10 and the ground.
  • On the ground, the rail 10 is supported by the rail support unit 30 installed between the opposite slabs 20 for thereby preventing the rail 10 from being sagged by supporting a vertical weight applied to the rail 10 when the train runs during a working time in a step S300.
  • At this time, the rail support unit 30 may be formed of a hydraulic jack, a screw jack, etc. The method for driving the rail support unit 30 and supporting the rail 10 is a known art, so that the detailed description thereon will be omitted.
  • A mold 200 is installed around the rail support unit 30 for thereby preventing the concrete from being inputted into the surrounding portions of the rail support unit 30 when constructing the concrete. The portions corresponding to the mold 200 is finished with cement after the concrete is cured.
  • Here, the gauge tie rod 40 of which both ends are fixedly supported by the rail support upper plate 80 and an intermediate part is flexible is adapted to prevent the rail 10 from being elongated when the concrete of the slab 20 is constructed in a step S400.
  • The gauge strut 50 of which both ends are fixedly supported by the rail support upper plate 80 and an intermediate portion is flexible is adapted to prevent the rail 10 from being sagged when the concrete is constructed in a step S500.
  • The horizontal support member 60 that is installed outside the rail 10 to be at the same line with the gauge strut 50 wherein an intermediate portion of the same is flexible is adapted to maintain a horizontal state of the rail 10 when the concrete of the slab 20 is constructed in a step S600.
  • The concrete supplied between the ground and the slab 20 through the inlet 22 formed at the center of the slab 20 constructs the slab 20 on the ground in a step S700. At this time, the concrete is constructed with a certain height including the height of the slab 20 for thereby enhancing a support force.
  • The rail support unit 30, the gauge tie rod 40, the gauge strut 50 and the horizontal support member 60 are disassembled from the rail 10 after the concrete ballast 70 is cured (generally after 3~5 days) in a step S800.
  • As described above, in the case that the work for exchanging a part of the gravel ballast with a concrete ballast is performed, since the rail 10 is supported by a plurality of the rail support part 30 in a state that the rail tie and gravel are removed from the lower side of the rail 10, it is possible to prevent the rail 10 from being sagged wherein the rail 10 is sagged due to a vertical weight from the rail 10 when the train runs.
  • In addition, the slab 20 is designed to prevent the rail 10 from being sagged by the tie rod 40 when the concrete is constructed, and the strut 50 is designed to prevent the rail 10 from being contracted, and the horizontal support member 60 is designed to maintain a horizontal state of the rail.
  • Therefore, in the present invention, it is possible to prevent the sagging and contraction of the rail 10 at a certain section even when the train runs during the working time for thereby continuously performing the gravel ballast exchanging work, so that it is possible to significantly enhance the workability.
  • As described above, the railroad concrete ballast construction system according to the present invention has the following advantages.
  • In the present invention, it is possible to continuously perform a work for exchanging a certain section of the gravel ballast with a concrete ballast even when the train runs on the railroad for thereby enhancing a workability.
  • In addition, in the present invention, since the gravel ballast can be exchanged with a concrete ballast during the operation of the train, any inconvenience is not provided to train passenger. The work for exchanging the gravel ballast with a concrete ballast can be performed during a day time, resulting in a better work environment. Therefore, work time is significantly decreased, and workers have less workload.
  • As the present invention may be embodied in several forms without departing from the spirit or essential characteristics thereof, it should also be understood that the above-described examples are not limited by any of the details of the foregoing description, unless otherwise specified, but rather should be construed within the scope as defined in the appended claims, and therefore all changes and modifications that fall within the meets and bounds of the claims, are intended to be embraced by the appended claims.

Claims (5)

  1. A railroad concrete ballast construction system, comprising:
    a concrete rail tie slab (20) in which a mounting part (21) formed at both sides is engaged at a certain section having no gravel and rail tie on a gravel ballast track by a certain fixing means (25);
    a rail support (30) unit that is detachably installed between opposite slabs, and supports a vertical weight applied to a rail when a train runs, and supports the rail (10) on the ground for thereby preventing the rail from being sagged;
    a horizontal support member (60) that is installed outside the rail, and supports an outer surface of the body of the rail and maintains a horizontal state of the rail when a concrete of the slab is constructed;
    and a concrete ballast (70) that fixes the slab on the ground in cooperation with the concrete constructed between the ground and the slab through an inlet (22) formed at the slab; characterised in that it further comprises
    a gauge tie rod (40) of which both ends are fixed at a rail support upper plate (80) and an intermediate portion is flexible, for thereby preventing an elongation of the rail when a concrete of the slab (70) is constructed;
    a gauge strut (50), installed on the same line as the horizontal support member, of which both ends are fixed at an inner surface of a body of the rail (11) and an intermediate portion is flexible, for thereby preventing a contraction of the rail (10) when a concrete of the slab is constructed.
  2. The system of claim 1, wherein a receiving groove (23) is formed at an outer surface of the slab (20) so that the rail support unit (30) is disassembled from the slab and is pulled out in an outer direction after the concrete is cured.
  3. The system of either claim 1 or claim 2, wherein said concrete rail tie slab (20) includes:
    a mounting part (21) that is protruded from the left and right sides of an upper surface of the slab in opposite directions wherein the rail is mounted thereon;
    an engaging part (25) that is engaged with an engaging hole formed at the left and right sides of the mounting part and has a certain elastic force capable of supporting a flange of the inner and outer sides of the rail; and
    an assistant engaging part (27) that is engaged with a through hole (26) formed at the slab in an outer direction of the mounting part and is embedded when a concrete is constructed for thereby enhancing an engaging force of the slab.
  4. The system of either claim 1 or claim 2, wherein said concrete rail tie slab (20) is formed of a steel-reinforced concrete structure of which a tensional force is reinforced using steel bars embedded.
  5. A railroad rail concrete ballast construction method, comprising:
    removing gravels (3) and rail ties (2) from the ground and the rail in a certain section of a gravel ballast track;
    engaging a concrete rail tie slab (20) at a lower side of a flange (12) of the rail (10) using a certain fixing means (25);
    supporting the rail on the ground using a rail support (30) unit installed between the opposite slabs for thereby preventing a sagging of the rail by supporting a vertical weight applied to the rail when a trains runs on the railroad;
    preventing an elongation of the rail using a gauge tie rod (40) of which both ends are fixed at a rail support upper plate (80), when a concrete (70) is constructed;
    preventing a contraction of the rail using a gauge strut (50) of which both ends are fixed at an inner surface of a body of the rail (11), when a concrete of the slab (20) is constructed;
    maintaining a horizontal state of the rail, when a concrete of the slab is constructed, by a horizontal support member (60) installed outside the rail to be the same line as the gauge strut;
    fixing the slab (20) on the ground using a concrete (70) constructed between the ground and the slab through an inlet (22) formed at the slab (20); and
    disassembling the rail support unit (30), the gauge tie rod (40), the gauge strut (50) and the horizontal support member (60) after the concrete (70) is cured.
EP05001314A 2004-02-24 2005-01-24 Railroad concrete ballast construction system and method Not-in-force EP1568821B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR2004012205 2004-02-24
KR1020040012205A KR100595429B1 (en) 2004-02-24 2004-02-24 Concrete sleeper for structure of rail

Publications (3)

Publication Number Publication Date
EP1568821A2 EP1568821A2 (en) 2005-08-31
EP1568821A3 EP1568821A3 (en) 2006-11-02
EP1568821B1 true EP1568821B1 (en) 2008-03-19

Family

ID=34747934

Family Applications (1)

Application Number Title Priority Date Filing Date
EP05001314A Not-in-force EP1568821B1 (en) 2004-02-24 2005-01-24 Railroad concrete ballast construction system and method

Country Status (4)

Country Link
EP (1) EP1568821B1 (en)
KR (1) KR100595429B1 (en)
AT (1) ATE389747T1 (en)
DE (1) DE602005005372T2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100744175B1 (en) * 2005-12-07 2007-08-02 한국철도기술연구원 Precast concrete slab on ballast track and concrete ballast laying system and method using it
EP2206831B1 (en) * 2009-01-13 2014-11-05 Knape Gruppe Holding GmbH Device and method for lifting and aligning rails
KR101052906B1 (en) * 2010-12-02 2011-07-29 삼표이앤씨 주식회사 Precast slab track system and method constructing the same
KR101439527B1 (en) * 2012-08-20 2014-09-15 영중산업 주식회사 Rail supporter for installing rail assembly of concrete railroad
CN103334350B (en) * 2013-07-16 2015-08-12 中国铁道科学研究院铁道建筑研究所 A kind of prestressed reinforced concrete tie, track plates thread rolling scale helix rib steel wire
KR101660212B1 (en) 2016-06-15 2016-10-10 이국현 Assembling method of mounting module for railway
KR102091735B1 (en) 2018-03-05 2020-03-20 한국철도기술연구원 Fast-hardening track for improving resistance performance against vertical deform and horizontal deform, and construction method for the same
KR102196373B1 (en) 2020-04-07 2020-12-29 황윤태 Rail construction method using precast slab panel

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2691484B1 (en) * 1992-05-22 1994-07-29 Vanotti Gerard METHOD OF CONSTRUCTING A RAILWAY IN CONCRETE.
DE4437826A1 (en) * 1993-10-18 1996-04-18 Betonwerk Rethwisch Gmbh Roadbed for railway using noise reducing elements and no ballast
DE19903702A1 (en) * 1999-01-30 2000-08-03 Bahnbau Wels Gmbh Wels Device for height and side alignment and / or support of the rails of a track
ES2211386T3 (en) * 1999-02-08 2004-07-16 Hochtief Aktiengesellschaft PROCEDURE FOR THE MANUFACTURE OF A RAILWAY WITHOUT BASKET.
KR20030065897A (en) * 2002-02-01 2003-08-09 주식회사 에이브이티 Structure of concrete ballast track and construction method thereof
KR100446310B1 (en) * 2002-11-07 2004-08-30 (주)신성엔지니어링 Apparatus for preventing cross movement of railroad track

Also Published As

Publication number Publication date
DE602005005372T2 (en) 2008-07-17
KR100595429B1 (en) 2006-07-03
DE602005005372D1 (en) 2008-04-30
KR20050087018A (en) 2005-08-31
EP1568821A2 (en) 2005-08-31
ATE389747T1 (en) 2008-04-15
EP1568821A3 (en) 2006-11-02

Similar Documents

Publication Publication Date Title
EP1568821B1 (en) Railroad concrete ballast construction system and method
KR100808212B1 (en) The bridge upper structure pulling up for which construction bent for bridge upper structure pulling up and this were used
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
CN1807757A (en) Pre-assembled plate consisting of armoured concrete
JP6837343B2 (en) Floor slab replacement method for synthetic girders
KR100891961B1 (en) The construction infrastructure the use road the martial art as a matter of bridge of the bridge which is old in the railroad or the railroad respects the induction event a method of construction which shifts the bridge and the system
JP5184311B2 (en) Steel structure construction method
CA2194794A1 (en) Substructure for a rail vehicle track
KR100355091B1 (en) Method for reinforcing resistance force of a bridge using a prefabricated bracket
JP6074378B2 (en) Expansion device replacement method and temporary lining plate structure
KR100454405B1 (en) Method for changing steel bridge of supporting rail into concreat bridge
KR100454406B1 (en) Method and apparatus for changing steel bridge of supporting rail into concrete bridge using temporary bent
KR100449231B1 (en) temporaty bridge using prestressed compuond double girder and method for building the temporary bridge
JP4934779B2 (en) Boarding / exit structure and boarding / exiting method
KR20020082728A (en) Process and frame for substituting steel girder of a railway bridge for concrete slab
CN209891074U (en) Cast-in-place reinforced concrete guardrail slip form system
KR20100109471A (en) H shaped tie for railroad and mold for making thereof
CN210151571U (en) Prefabricated guardrail mounting and positioning device
KR100638578B1 (en) Method for carrying out replacement of an upper structure of a railway bridge
JP2007169950A (en) Expansion body for bridge, and bridge expansion structure using the same
KR101996601B1 (en) Mono-block for improving metrology and method of the same
KR20060082970A (en) Crane for replacement of a girdir of a railway bridge and method for replacement of the girdir using the same
JP3814286B2 (en) Formwork support structure
KR101756965B1 (en) Height adjusting type maintanable rail track construction method and maintanance method using the same
JP2020186614A (en) Precast floor slab connection part structure and connection part construction method

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20050124

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU MC NL PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA HR LV MK YU

RAP1 Party data changed (applicant data changed or rights of an application transferred)

Owner name: SEOUL METRO

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU MC NL PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA HR LV MK YU

AKX Designation fees paid

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU MC NL PL PT RO SE SI SK TR

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU MC NL PL PT RO SE SI SK TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REF Corresponds to:

Ref document number: 602005005372

Country of ref document: DE

Date of ref document: 20080430

Kind code of ref document: P

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

NLV1 Nl: lapsed or annulled due to failure to fulfill the requirements of art. 29p and 29m of the patents act
PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080826

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080619

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080630

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080719

EN Fr: translation not filed
PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

26N No opposition filed

Effective date: 20081222

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080619

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090131

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20090124

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090131

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090131

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090124

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090126

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080620

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090124

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080920

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080319

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20090109

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20190214

Year of fee payment: 15

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602005005372

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200801