EP1111135A2 - Method of building viaducts - Google Patents

Method of building viaducts Download PDF

Info

Publication number
EP1111135A2
EP1111135A2 EP00126823A EP00126823A EP1111135A2 EP 1111135 A2 EP1111135 A2 EP 1111135A2 EP 00126823 A EP00126823 A EP 00126823A EP 00126823 A EP00126823 A EP 00126823A EP 1111135 A2 EP1111135 A2 EP 1111135A2
Authority
EP
European Patent Office
Prior art keywords
carrying
ashlar
horizontal
ledger
ashlars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP00126823A
Other languages
German (de)
French (fr)
Other versions
EP1111135A3 (en
Inventor
Francesco Paglini
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pontello SpA
Original Assignee
Pontello SpA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pontello SpA filed Critical Pontello SpA
Publication of EP1111135A2 publication Critical patent/EP1111135A2/en
Publication of EP1111135A3 publication Critical patent/EP1111135A3/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection

Definitions

  • the invention refers to a new method to build viaducts particularly those with big span and with substantial height on the valley bottom, that is to say for all the viaducts for which for some time the classic method of lagging and work cementation has been abandoned.
  • a building method has had development. Said method provides the realization of the horizontal carrying structure floor systems by assembling of prefabricated units.
  • a first method refers to a working with a push launching from an end, in which the ashlars are positioned and solidarized behind of an abutment and then they are pushed so making move the units on tracks placed on the head of the piers. This method has the problem that all the piers must already be made, it has the necessity to have room behind the abutment and it does not permit the scaffolding stopage for any reasons such for example in relation to possible interferences or for the presence of obstacles.
  • a second method refers to a positioning with launching truck providing a span truss equal to one or more spans and consequently much expensive.
  • the bigger problem is given to the necessity to never break off the progressive advancement of the positioning and to must have big room behind the abutment to mount and to dismount the truss.
  • the working times of the work are increased both in relation of the slowness of the truck translation velocity than in relation to the necessity to must mount and to must dismount the truss.
  • the invented method gives a solution to said disadvantages by a new launching method more adaptable and more quick and to be actuated by different sequences following described. 1) After to have ended the piers and the same are to the plan height by formwork, it is positioned the first ashlar from which going on in the working, this positioning can be made also at the same time on the different piers.
  • the invented method comprises three parts: a horizontal carrying structure, a vertical lifting ledger and a hooking beam.
  • the horizontal carrying structure consists of a level structure 1 formed by two structural steel work beams with cross bracings 2 on horizontal plane. Said horizontal structure goes on rails 3 fixed on the scaffolding slab by four motorized wheels 4 with safety block device 5.
  • the level structure moreover provides feet 6 acting like stabilizers to be lowered during the lifting phase of the ashlar.
  • the vertical lifting beam consists of a carrying ledger 7 sliding on jaws 8 to be fixed on the level structure 1 with motorized cargo winch 9 for lifting the ropes 10 having hanging sheaves 11 with blocks 12.
  • the hooking ledger consists of a carrying beam 13 equipped with hooks and with two subordinate beams which bring the ashlar with four pins realized with threaded bars 14.
  • the first three ashlars15, 16 and 17 are placed by a mobile crane.
  • the rails 3 are placed by fixing the same with passing means, then always with the mobile crane the horizontal carrying structure with level part 1 is placed.
  • Said part 1 puts on the rails by its set of wheels 4.
  • the vertical lifting beam with the carrying ledger 7 is placed equipped with cargo winches 9 and ropes 10, laying it on the jaws 8 of the level structure 1.
  • the ropes 10 are lowered with hanging by the blocks 12 the carrying beam 13.
  • the bars 14 the ashlar to be lifted is fixed and it is lifted acting by the motorized cargo winches 9.
  • the horizontal carrying structure is moved on the rails 3 till the necessary position.
  • the stabilizing feet 6 are lifted and the horizontal carrying structure is moved to the opposed halfspan so to go on with the equal simmetrical working.
  • the network structure 18 placed on the pier head permits the placing of the first three ashlars 15, 16 and 17 from which the whole building starts. Said first three ashlars are launched by a crane. Said network structure 18, after to have mounted the three ashlars, is dismounted from the pier head with the same crane used for placing the ashlars 15, 16 and 17.
  • Said three starting ashlars form a small room on which the rails 3 bringing the whole structure are placed. Moreover it is provided, connected to the end of the horizontal carrying structure with level part 1 a metallic stull 19 with two placing stages so to control the ashlar positioning and then make its jointing. In this stull the room is suitable to house the necessary materials, the tensioning jacks and our workers. Said metallic stull 19 to be moved by a crane to be in help of the working. Said crane can be the same used for the positioning of the first three ashlars 15, 16 and 17.
  • the invented method is illustrated in schematic and limitated view in the drawings of sheets 1, 2, 3, 4, 5, 6 and 7. In sheet 1 fig.
  • FIG. 1 is side view of the structures 1 and 7 with the ropes 10 and without the ashlar.
  • sheet 2 fig. 2 is plant view of the structures 1 and 7.
  • sheet 3 fig. 3 is side view in lifting position of the ashlar.
  • sheet 4 fig . 4 is transversal section view of an already jointed ashlar whereas another ashlar is in supporting phase hooked to the hooking beam 13.
  • sheet 5 fig.5 is perspective view of the horizontal structure with part 1 with on an end the stull 19 and the vertical structure with ledger 7 in lifting of the ashlar.
  • sheet 6 fig. 6 is perspective view of the horizontal carrying structure with part 1 and the vertical structure with ledger 7 with a hooked ashlar during the translation.
  • FIG. 7 is view in detail of the network structure 18 to be put onto the pier head for the positioning of the first three ashlars from which the building is started whereas onto the behind pier is showed the horizontal structure with part 1 during the working phase with the stull 19 connected to its end.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

The building method is actuated by a horizontal carrying structure, a vertical lifting ledger and a hooking beam. The horizontal carrying structure consists of a level structure (1) formed by two structural steel work beams with cross bracings (2) on horizontal plane. The horizontal structure goes on rails (3) fixed on the scaffolding slab by four motorized wheels (4) with safety block device (5). The level structure moreover provides feet (5) acting kike stabilizers to be lowered during the lifting phase of the ashlar. The vertical lifting beam consists of a carrying ledger (7) sliding on jaws (8) to be fixed on the level structure (1) with motorized cargo winch (9) for lifting the ropes (10) having hanging sheaves (11) with blocks (12). The hooking ledger consists of a carrying beam (13) equipped with hooks and with two subordinate beams which bring the ashlar with four pins realized with threaded bars (14).

Description

  • The invention refers to a new method to build viaducts particularly those with big span and with substantial height on the valley bottom, that is to say for all the viaducts for which for some time the classic method of lagging and work cementation has been abandoned. For these kinds of viaducts, already in the sixties, a building method has had development. Said method provides the realization of the horizontal carrying structure floor systems by assembling of prefabricated units.
  • This also in relation with the development of the pretensioning methods which permit the subsequent assembling and the solidari zing of separated units afterwards called "ashlar". In said methods of viaduct building is consequently become of foundamental importance the development of a method for the moving, the lifting and the positioning of the prefabricated unit that, in relation, forms the sector advancement.
  • All these workings are in the sector called "of launching".
  • Principally for these kinds of viaducts are to be considered two different working methods. A first method refers to a working with a push launching from an end, in which the ashlars are positioned and solidarized behind of an abutment and then they are pushed so making move the units on tracks placed on the head of the piers. This method has the problem that all the piers must already be made, it has the necessity to have room behind the abutment and it does not permit the scaffolding stopage for any reasons such for example in relation to possible interferences or for the presence of obstacles. A second method refers to a positioning with launching truck providing a span truss equal to one or more spans and consequently much expensive. Also in this method the bigger problem is given to the necessity to never break off the progressive advancement of the positioning and to must have big room behind the abutment to mount and to dismount the truss. As the consequence in said method the working times of the work are increased both in relation of the slowness of the truck translation velocity than in relation to the necessity to must mount and to must dismount the truss. The invented method gives a solution to said disadvantages by a new launching method more adaptable and more quick and to be actuated by different sequences following described. 1) After to have ended the piers and the same are to the plan height by formwork, it is positioned the first ashlar from which going on in the working, this positioning can be made also at the same time on the different piers. 2) On this first scaffolding unit the rails are put on which will move the apparatus for the ashlar lifting. 3) On the rail is put the sliding lifting apparatus with all its members, said apparatus is formed by a sole body and it does not request assembling working on the place. 4) The prefabricated ashlars are brought to the pier base, the sliding apparatus lets down the horizontal bar, blocks the ashlar, lifts it and places the same making to transfer it in the position under the already built floor system. When the horizontal bar has reached the assembling position, the ashlar is further lifted to put it in height with the part of floor system already realized. 5) During the lifting phase, so to ensure the stability so avoiding the carrying structure overturning, the same is fixed to the floor system slab already realized by two stabilizers acting like tie rod. 6) Placed in building line the ashlar, with the same still supports by the carrying structure, the joining of the ashlar to the already realized floor system is actuated, this joining obtained by the pretensioning of two music wire cables. 7) The building so goes on from the end of each pier and it must be actuated in symmetric way to the pier axis from which the two halfspans start. As a consequence of this, after to have end the ashlar launching on a halfspan, to not create an overturning-moment it must be necessary launched the ashlar of the opposed span and all the building must going on with this sequence. 8) The joining of the whole floor system, formed by the various halfspans realized as described, is made by means of casts realized in working by hanging a convention formwork at the two ends of the halfspans. 9) Ending the building the structure is removed. Making a comparison between the invented method as described and the previous used cited methods the following advantages are to be pointed out: a) rooms behind the abutments do not need for the mounting and the dismounting of the launching truck; b) the sequentiality in the execution of the whole floor system does not need, this means that part of no adjacent floor system can be realized such as, in case of different obstacles like presence of electric line, ditches, landslides or other, it is possible to pass over the building of the halfspans of the pier that at the moment cannot be built so permitting the no working clocking also in the obstacle presence, whereas with the current methods a such obstacle brings forcedly to block the workings; c) the invented method is to be actuated also with span of various width such it works with indipendent self-moving apparatuses; d) mounting and dismounting workings are not necessary such the apparatus consists of only three prearranged parts that are to be moved from a yard to another one; e) the used cargo winch is suitable for height above the valley bottom of about 80 metres and, in case of bigger height, in the invented method only the cargo winch must be changed whereasall the other structures remain the same; f) having more apparatuses it is possible at the same time to work starting from more piers and also with two shuttling on the same pier so reducing significantly the working time; g) a big saving on the building costs of the floor system is obtained such as there are not the big cost of labour for mounting and dismounting the structure and it is possible to have for the quick working rate a less impact of the labour on the launching operations. The invented method comprises three parts: a horizontal carrying structure, a vertical lifting ledger and a hooking beam. The horizontal carrying structure consists of a level structure 1 formed by two structural steel work beams with cross bracings 2 on horizontal plane. Said horizontal structure goes on rails 3 fixed on the scaffolding slab by four motorized wheels 4 with safety block device 5. The level structure moreover provides feet 6 acting like stabilizers to be lowered during the lifting phase of the ashlar. The vertical lifting beam consists of a carrying ledger 7 sliding on jaws 8 to be fixed on the level structure 1 with motorized cargo winch 9 for lifting the ropes 10 having hanging sheaves 11 with blocks 12. The hooking ledger consists of a carrying beam 13 equipped with hooks and with two subordinate beams which bring the ashlar with four pins realized with threaded bars 14.
  • For the working after to have mounted the network structure at the pier head the first three ashlars15, 16 and 17 are placed by a mobile crane. On said ashlars the rails 3 are placed by fixing the same with passing means, then always with the mobile crane the horizontal carrying structure with level part 1 is placed. Said part 1 puts on the rails by its set of wheels 4. Then the vertical lifting beam with the carrying ledger 7 is placed equipped with cargo winches 9 and ropes 10, laying it on the jaws 8 of the level structure 1. Then the ropes 10 are lowered with hanging by the blocks 12 the carrying beam 13. By the bars 14 the ashlar to be lifted is fixed and it is lifted acting by the motorized cargo winches 9. At this point the horizontal carrying structure is moved on the rails 3 till the necessary position.
  • Practically said position corresponds to the position of the last ashlar already jointed. During this hoisting phase the stabilizers 6 of the carrying horizontal structure are lowered so stabilizing the different parts. The vertical lifting beam with ledger 7, moving itself on jaws 8, is joltingly carried with hooked the ashlar till the position of the further lifting for the final placing. In this way the ashlar is brought to the final height to actuate the jointing by prestressing. Ending the jointing the threaded bars 14 are unhooked, the carrying beam 13 is lowered on the ground and the vertical lifting beam with ledger 7 is put again in the starting position barycentric with the set of wheels 4. The stabilizing feet 6 are lifted and the horizontal carrying structure is moved to the opposed halfspan so to go on with the equal simmetrical working. The network structure 18 placed on the pier head permits the placing of the first three ashlars 15, 16 and 17 from which the whole building starts. Said first three ashlars are launched by a crane. Said network structure 18, after to have mounted the three ashlars, is dismounted from the pier head with the same crane used for placing the ashlars 15, 16 and 17.
  • Said three starting ashlars form a small room on which the rails 3 bringing the whole structure are placed. Moreover it is provided, connected to the end of the horizontal carrying structure with level part 1 a metallic stull 19 with two placing stages so to control the ashlar positioning and then make its jointing. In this stull the room is suitable to house the necessary materials, the tensioning jacks and our workers. Said metallic stull 19 to be moved by a crane to be in help of the working. Said crane can be the same used for the positioning of the first three ashlars 15, 16 and 17. The invented method is illustrated in schematic and limitated view in the drawings of sheets 1, 2, 3, 4, 5, 6 and 7. In sheet 1 fig. 1 is side view of the structures 1 and 7 with the ropes 10 and without the ashlar. In sheet 2 fig. 2 is plant view of the structures 1 and 7. In sheet 3 fig. 3 is side view in lifting position of the ashlar. In sheet 4 fig . 4 is transversal section view of an already jointed ashlar whereas another ashlar is in supporting phase hooked to the hooking beam 13. In sheet 5 fig.5 is perspective view of the horizontal structure with part 1 with on an end the stull 19 and the vertical structure with ledger 7 in lifting of the ashlar. In sheet 6 fig. 6 is perspective view of the horizontal carrying structure with part 1 and the vertical structure with ledger 7 with a hooked ashlar during the translation. In sheet 7 fig. 7 is view in detail of the network structure 18 to be put onto the pier head for the positioning of the first three ashlars from which the building is started whereas onto the behind pier is showed the horizontal structure with part 1 during the working phase with the stull 19 connected to its end.

Claims (3)

  1. Method to build viaducts to be actuated by a horizontal carrying structure, a vertical lifting ledger and a hooking beam; characterized in that:
    the horizontal carrying structure consists of a level structure (I) formed by two structural stell work beams with cross bracings (2) on horizontal plane, said structure goes on rails (3) fixed on the scaffolding slab by four motorized wheels (4) with safety block device (5), said level structure moreover provides feet (6) acting like stabilizers to be lowered during the lifting phase of the ashlar;
    the vertical lifting beam consists of a carrying ledger (7) sliding on jaws (8) to be fixed on the level structure (1) with motorized cargo winch (9) for lifting the ropes (10) having hanging sheaves (11) with blocks (12);
    the hooking ledger consists of a carrying beam (13) equipped with hooks and with two subordinate beams which bring the ashlar with four pins realized with threaded bars (14);
    for the working after to have mounted the network structure at the pier head the first three ashlars (15, 16 and 17) are placed by a mobile crane, on said ashlars the rails (3) are placed by fixing the same with passing means then always with the mobile crane the horizontal carrying structure with level part (1) is placed, said part (1) puts on the rails by its set of wheels (4), then the vertical lifting beam with the carrying ledger (7) is placed equipped with cargo winches (9) and ropes (10) laying it on the jaws (8) of the level structure (1), then the ropes (10) are lowered with hanging by the blocks (12) the carrying beam (13), by the bars (14) the ashlar to be lifted is fixed and it is lifted acting by the motorized cargo winches (9), at this point the horizontal carrying structure is moved on the rails (3) till the necessary position, during this hoisting phase the stabilizers (6) of the carrying horizontal structure are lowered so stabilizing the different parts, the vertical lifting beams with ledger (7) moving itself on jaws ( ) is joltingly carried with hooked the ashlar till the position of the further lifting for the filing placing in this way the ashlar is brought to the final height to actuate the jointing by prestressing, ending the jointing the threaded bars (14) are unhooked, the carrying beam (13) is lowered on the ground in the starting position barycentric with the set of wheels (4), the stabilizing feet (6) are lifted and the horizontal carrying structure is moved to the opposed halfspan so to go on with the equal simmetrical working.
  2. Method to build viaducts, as per claim 1, characterized in that a network structure (18) placed on the pier head permits the placing of the first three ashlars (15, 16 and 17) from which the whole building starts, said first three ashlars are launched by a crane; said network structure (18) after to have mounted the three ashlars is dismounted from the pier head with the same crane used for placing the ashlars (15, 16 and 17), said three starting ashlars form a small room on which the rails (3) bringing the whole strcuture are placed.
  3. Method to build viaducts, as per claim 1, characterized in that connected to the end of the horizontal carrying structure with level part (1) a metallic stull (19) with two placing stages so to control the ashlar positioning and then make its jointing, in this stull the room is suitable to house the necessary materials, the tensioning jacks and four workers; said metallic stull (19) to be moved by a crane to be in help of the working.
EP00126823A 1999-12-23 2000-12-07 Method of building viaducts Withdrawn EP1111135A3 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
ITBO990704 1999-12-23
IT1999BO000704 IT1311372B1 (en) 1999-12-23 1999-12-23 SYSTEM FOR BUILDING VIADUCTS.

Publications (2)

Publication Number Publication Date
EP1111135A2 true EP1111135A2 (en) 2001-06-27
EP1111135A3 EP1111135A3 (en) 2003-03-19

Family

ID=11344433

Family Applications (1)

Application Number Title Priority Date Filing Date
EP00126823A Withdrawn EP1111135A3 (en) 1999-12-23 2000-12-07 Method of building viaducts

Country Status (2)

Country Link
EP (1) EP1111135A3 (en)
IT (1) IT1311372B1 (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182148A (en) * 2011-04-02 2011-09-14 天津天佳市政公路工程有限公司 Quick rollers for large bridge installation
CN103628409A (en) * 2013-11-08 2014-03-12 中天建设集团有限公司 Construction device for anti-collision wall of viaduct
JP2015113581A (en) * 2013-12-09 2015-06-22 株式会社横山基礎工事 Construction method of structure and support device
RU2560012C1 (en) * 2014-06-24 2015-08-20 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Device for lifting and installation of bridge units
EP3018255A1 (en) * 2014-10-27 2016-05-11 Rubrica Ingenieria Y Arquitectura, S.L. Cart for building a bridge board forward progressive
RU177385U1 (en) * 2017-08-03 2018-02-20 Виктор Никитович Коротин DEVICE FOR PRECISION MOUNTING SUSPENDED FOR FOUR POINTS OF STRUCTURES OF THE SPAN STRUCTURE OF THE BRIDGE
CN108100894A (en) * 2018-01-25 2018-06-01 中交第三航务工程局有限公司宁波分公司 The short tower crane equipment of low speed and system
JP2018091093A (en) * 2016-12-06 2018-06-14 三井住友建設株式会社 Bridge construction method
CN110644377A (en) * 2019-09-30 2020-01-03 中铁二院工程集团有限责任公司 Roller type beam body pushing construction device
CN110904841A (en) * 2019-11-07 2020-03-24 中铁大桥局集团有限公司 Bridge girder lifting method and system
CN117090147A (en) * 2023-10-19 2023-11-21 湖南省通盛工程有限公司 Small-radius curve section cross-pier steel beam suspension splicing device and construction method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356078A (en) * 2021-07-07 2021-09-07 甘肃路桥建设集团有限公司 Bridge pier column reinforcement rack

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1658602B1 (en) * 1967-08-12 1970-11-19 Hochtief Ag Hoch Tiefbauten Device for assembling the prefabricated components of a prestressed concrete bridge, each comprising a complete bridge section, in cantilevered cantilevered sections
DE2704033A1 (en) * 1977-02-01 1978-08-03 Beton & Monierbau Ag Staged multi-span reinforced concrete bridge erection - using supports carried through roadway edge cut=outs and fixed to pier
JPH1192082A (en) * 1997-09-24 1999-04-06 Kitagawa Iron Works Co Ltd Lifting device for construction of bridge beam
JPH11158817A (en) * 1997-11-26 1999-06-15 Nkk Corp Balancing erection construction for bridge at height and transferable slinging lifting device therefor

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1658602B1 (en) * 1967-08-12 1970-11-19 Hochtief Ag Hoch Tiefbauten Device for assembling the prefabricated components of a prestressed concrete bridge, each comprising a complete bridge section, in cantilevered cantilevered sections
DE2704033A1 (en) * 1977-02-01 1978-08-03 Beton & Monierbau Ag Staged multi-span reinforced concrete bridge erection - using supports carried through roadway edge cut=outs and fixed to pier
JPH1192082A (en) * 1997-09-24 1999-04-06 Kitagawa Iron Works Co Ltd Lifting device for construction of bridge beam
JPH11158817A (en) * 1997-11-26 1999-06-15 Nkk Corp Balancing erection construction for bridge at height and transferable slinging lifting device therefor

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
PATENT ABSTRACTS OF JAPAN vol. 1999, no. 09, 30 July 1999 (1999-07-30) -& JP 11 092082 A (KITAGAWA IRON WORKS CO LTD;KAJIMA CORP), 6 April 1999 (1999-04-06) *
PATENT ABSTRACTS OF JAPAN vol. 1999, no. 11, 30 September 1999 (1999-09-30) -& JP 11 158817 A (NKK CORP), 15 June 1999 (1999-06-15) *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182148A (en) * 2011-04-02 2011-09-14 天津天佳市政公路工程有限公司 Quick rollers for large bridge installation
CN103628409A (en) * 2013-11-08 2014-03-12 中天建设集团有限公司 Construction device for anti-collision wall of viaduct
JP2015113581A (en) * 2013-12-09 2015-06-22 株式会社横山基礎工事 Construction method of structure and support device
RU2560012C1 (en) * 2014-06-24 2015-08-20 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Device for lifting and installation of bridge units
EP3018255A1 (en) * 2014-10-27 2016-05-11 Rubrica Ingenieria Y Arquitectura, S.L. Cart for building a bridge board forward progressive
JP2018091093A (en) * 2016-12-06 2018-06-14 三井住友建設株式会社 Bridge construction method
RU177385U1 (en) * 2017-08-03 2018-02-20 Виктор Никитович Коротин DEVICE FOR PRECISION MOUNTING SUSPENDED FOR FOUR POINTS OF STRUCTURES OF THE SPAN STRUCTURE OF THE BRIDGE
CN108100894A (en) * 2018-01-25 2018-06-01 中交第三航务工程局有限公司宁波分公司 The short tower crane equipment of low speed and system
CN110644377A (en) * 2019-09-30 2020-01-03 中铁二院工程集团有限责任公司 Roller type beam body pushing construction device
CN110644377B (en) * 2019-09-30 2021-01-12 中铁二院工程集团有限责任公司 Roller type beam body pushing construction device
CN110904841A (en) * 2019-11-07 2020-03-24 中铁大桥局集团有限公司 Bridge girder lifting method and system
CN110904841B (en) * 2019-11-07 2021-08-10 中铁大桥局集团有限公司 Bridge girder lifting method and system
CN117090147A (en) * 2023-10-19 2023-11-21 湖南省通盛工程有限公司 Small-radius curve section cross-pier steel beam suspension splicing device and construction method
CN117090147B (en) * 2023-10-19 2023-12-26 湖南省通盛工程有限公司 Small-radius curve section cross-pier steel beam suspension splicing device and construction method

Also Published As

Publication number Publication date
EP1111135A3 (en) 2003-03-19
IT1311372B1 (en) 2002-03-12
ITBO990704A1 (en) 2001-06-23

Similar Documents

Publication Publication Date Title
JP3885584B2 (en) Construction method of composite truss bridge
US3550723A (en) Bridge scaffold
KR20140084107A (en) Self-Launching Movable Scaffolding System
EP1111135A2 (en) Method of building viaducts
US4768938A (en) Apparatus for pouring concrete slabs
US4492358A (en) Truss shoring system and apparatus therefor
JPH0841826A (en) Erection method of bridge and equipment thereof and main girder unit
JP4361775B2 (en) Bridge erection method and bridge erection device
JP3804883B2 (en) Concrete high structure construction apparatus and concrete oblique column construction method
JP3110985B2 (en) Construction method of column capital of overhang girder bridge
JP2539150B2 (en) Bridge erection equipment
US4921649A (en) Method for pouring concrete slabs
JP3197234B2 (en) Moving scaffold for floor slab assembly
JP3032477B2 (en) Moving scaffold for floor slab assembly
JP2552997B2 (en) Bridge girder construction method and its equipment
JPH0336362B2 (en)
JP3026544B2 (en) Method and apparatus for moving overhanging work vehicle
JP2000087314A (en) Method and device for construction of floor slab
JP7112146B1 (en) Mobile connection suspension scaffold and its usage
JPH11158817A (en) Balancing erection construction for bridge at height and transferable slinging lifting device therefor
JPS649403B2 (en)
RU2247805C2 (en) Method for assembling over-pier part of bridge span structure
JPS5847803A (en) Bridge crane
JPH05148817A (en) Construction of pc bridge
JPH07102524A (en) Method for building concrete cable-stayed bridge and form supporting truck using the same

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

AX Request for extension of the european patent

Free format text: AL;LT;LV;MK;RO;SI

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

AX Request for extension of the european patent

Extension state: AL LT LV MK RO SI

AKX Designation fees paid

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20030920