EA021979B1 - Forming a shaft for an underground mine - Google Patents

Forming a shaft for an underground mine Download PDF

Info

Publication number
EA021979B1
EA021979B1 EA201270083A EA201270083A EA021979B1 EA 021979 B1 EA021979 B1 EA 021979B1 EA 201270083 A EA201270083 A EA 201270083A EA 201270083 A EA201270083 A EA 201270083A EA 021979 B1 EA021979 B1 EA 021979B1
Authority
EA
Eurasian Patent Office
Prior art keywords
shaft
mine
station
rock
excavated rock
Prior art date
Application number
EA201270083A
Other languages
Russian (ru)
Other versions
EA201270083A1 (en
Inventor
Роки Линн Уэбб
Моррис Джеймс Медд
Райан Джордж Гоф
Джон Николас Де Ла Вернь
Энди Роберт Фирн
Фредрик Кристофер Делаббио
Original Assignee
Текнолоджикал Ресорсиз Пти. Лимитед
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU2009903054A external-priority patent/AU2009903054A0/en
Application filed by Текнолоджикал Ресорсиз Пти. Лимитед filed Critical Текнолоджикал Ресорсиз Пти. Лимитед
Publication of EA201270083A1 publication Critical patent/EA201270083A1/en
Publication of EA021979B1 publication Critical patent/EA021979B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/03Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Earth Drilling (AREA)
  • Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

In forming a mine shaft for an underground mine, earth excavated by a boring machine (21) is transported upwardly by handling unit (22) to a transfer station (33) where it is transferred into skips (36) which are raised and lowered along skip guides (38) within the shaft hole (19) for transport of the excavated material to an earth surface region. Transfer station (33) is moved downwardly as excavation progresses.

Description

Настоящее изобретение относится к созданию стволов шахт для подземных рудников. Изобретение имеет конкретное, но не исключительное применение для создания ствола шахты рудника, через который создают доступ к действующим забоям и извлекают добытый материал после создания ствола шахты рудника, но может также применяться для создания стволов шахт другого назначения, таких как вентиляционные стволы для подземных рудников.The present invention relates to the creation of mine shafts for underground mines. The invention has a specific, but not exclusive application for creating a mine shaft, through which access to active faces is obtained and material extracted after creating a mine shaft, but can also be used to create mine shafts for other purposes, such as ventilation shafts for underground mines.

Предпосылки изобретенияBACKGROUND OF THE INVENTION

Claims (23)

1. Способ удаления вынутой породы из ствола шахты во время создания ствола шахты для подземного рудника, содержащий следующие стадии:1. A method of removing excavated rock from a mine shaft while creating a mine shaft for an underground mine, comprising the following steps: транспортировка вынутой породы вверх, по существу, непрерывно из зоны выемки ствола шахты на станцию перегрузки над зоной выемки;transporting the excavated rock upward substantially continuously from the recess area of the shaft of the mine to the transshipment station above the recess zone; размещение транспортируемой вынутой породы по меньшей мере в одном накопительном бункере, установленном на станции перегрузки так, что транспортируемая вынутая порода временно хранится в бункерах для увеличения статических дискретных грузов породы;placing the transported excavated rock in at least one storage hopper installed at the transshipment station so that the transported excavated rock is temporarily stored in silos to increase the static discrete loads of the rock; циклическая выгрузка дискретного груза вынутой породы из множества накопительных бункеров в аналогичное множество скипов, каждый из которых связан с каждым из накопительных бункеров и способен перемещаться вверх и вниз вдоль направляющих скипов в стволе шахты;cyclic unloading of discrete cargo of excavated rock from multiple storage bins into a similar set of skips, each of which is connected to each of the storage bins and is able to move up and down along the guide skips in the shaft of the mine; циклический подъем каждого скипа после приема дискретного груза вынутой породы из соответствующего связанного с ним бункера в зону поверхности земли, выгрузка вынутой породы из скипа в зоне поверхности земли и спуск скипа обратно на станцию перегрузки для приема следующего дискретного груза вынутой породы из соответствующего бункера;cyclic lifting of each skip after receiving a discrete cargo of excavated rock from the corresponding bunker connected to it to the earth's surface zone, unloading the removed rock from the skip in the earth's surface zone and lowering the skip back to the transshipment station to receive the next discrete cargo of excavated rock from the corresponding hopper; периодическая перестановка станции перегрузки и накопительных бункеров на последовательно перемещаемые вниз рабочие места при продолжении выемки.periodic relocation of the transshipment station and storage bins to sequentially moving down jobs with continued excavation. 2. Способ по п.1, в котором используется пара накопительных бункеров на станции перегрузки и пара скипов, перемещающихся вверх и вниз в стволе шахты вдоль смежных путей для поочередного приема дискретных грузов вынутой породы и их транспортировки в зону поверхности земли для выгрузки в зоне на поверхности земли и возвращения вниз на станцию перегрузки.2. The method according to claim 1, in which a pair of storage bins is used at the transshipment station and a pair of skips moving up and down in the shaft of the mine along adjacent tracks for alternately receiving discrete loads of excavated rock and transporting them to the surface of the earth for unloading in the zone of ground surface and return down to the transshipment station. 3. Способ по п.1 или 2, в котором скипы связаны вертикальными направляющими для перемещения вдоль путей, расположенных в боковом участке ствола шахты, имеющем площадь сечения, составляющую менее 50% площади сечения ствола шахты.3. The method according to claim 1 or 2, in which the skips are connected by vertical guides for moving along paths located in a side section of the shaft of the shaft having a cross-sectional area of less than 50% of the cross-sectional area of the shaft of the shaft. 4. Способ по любому из пп.1-3, в котором вынутую породу транспортируют на станцию перегрузки конвейером, связанным со станцией перегрузки.4. The method according to any one of claims 1 to 3, in which the excavated rock is transported to the transshipment station by a conveyor associated with the transshipment station. 5. Способ по п.4, в котором конвейер имеет вертикально перемещающийся нижний конец, который перемещается вниз на ограниченное расстояние с продолжением выемки между периодическими перестановками станции перегрузки.5. The method according to claim 4, in which the conveyor has a vertically moving lower end, which moves down a limited distance with the continuation of the recess between the periodic permutations of the reloading station. - 4 021979- 4 021979 6. Способ по любому из пп.1-5, в котором периодические перестановки станции перегрузки выполняют при установке удлинений крепи ствола шахты под станцией перегрузки.6. The method according to any one of claims 1 to 5, in which the periodic rearrangement of the transshipment station is performed by installing extensions of the mine shaft support under the transshipment station. 7. Способ создания ствола шахты для подземного рудника, содержащий следующие стадии: выемка грунта для создания ствола, проходящего вниз от зоны поверхности земли; удаление вынутой породы из ствола шахты способом по любому из пп.1-6.7. A method of creating a mine shaft for an underground mine, comprising the following stages: excavation to create a shaft extending downward from the surface zone of the earth; removal of excavated rock from the shaft of the mine by the method according to any one of claims 1 to 6. 8. Способ по п.7, в котором выемку грунта выполняют буровой проходческой машиной.8. The method according to claim 7, in which the excavation is performed by a drilling tunneling machine. 9. Способ по п.8, в котором буровая проходческая машина содержит роторную врубовую головку.9. The method according to claim 8, in which the drilling sinking machine contains a rotary cutting head. 10. Способ по п.9, в котором роторная врубовая головка имеет ряд режущих элементов, вращающихся вокруг горизонтальной оси для выемки породы из земли.10. The method according to claim 9, in which the rotary cutting head has a number of cutting elements rotating around a horizontal axis for excavating the rock from the ground. 11. Способ по п.10, в котором врубовая головка вращается вокруг вертикальной оси для бурения, в общем, цилиндрического ствола.11. The method according to claim 10, in which the cutting head rotates around a vertical axis for drilling a generally cylindrical shaft. 12. Способ по любому из пп.7-11, в котором ствол крепят поступательно крепью ствола шахты, включающей в себя скиповые направляющие, для установки последовательного удлинения крепи и скиповых направляющих под станцией перегрузки для удлинения крепи и скиповых направляющих перед перестановкой вниз станции перегрузки.12. The method according to any one of claims 7 to 11, in which the trunk is progressively attached to the shaft of the shaft, including skip guides for sequentially extending the supports and skip guides under the overload station to extend the supports and skip guides before moving down the transshipment station. 13. Способ по любому из предыдущих пунктов, в котором вынутую породу перемещают вверх из зоны выемки посредством конвейера, работающего, когда врубовая головка врезается для подачи вынутой породы в бункеры.13. The method according to any one of the preceding paragraphs, in which the excavated rock is moved upward from the excavation zone by means of a conveyor operating when the cutting head cuts in to feed the excavated rock into the silos. 14. Устройство для осуществления способа удаления вынутой породы из ствола шахты рудника во время создания ствола шахты по любому из пп.1-13, содержащее конвейер для транспортировки вынутой породы вверх из зоны выемки на станцию перегрузки, множество накопительных бункеров, установленных на станции перегрузки для приема вынутой породы с верхней части конвейера так, что транспортируемая вынутая порода временно хранится в бункерах для увеличения статических дискретных грузов вынутой породой, и аналогичное множество скипов, каждый из которых связан с каждым из накопительных бункеров и способен перемещаться вверх и вниз на его направляющей в стволе шахты для цикличного приема дискретного груза вынутой породы из соответствующего одного из бункеров на станции перегрузки для его транспортировки в зону поверхности земли, выгрузки в зоне поверхности земли и возврата на станцию перегрузки для приема следующего груза вынутой породы.14. A device for implementing a method for removing excavated rock from a mine shaft while creating a mine shaft according to any one of claims 1 to 13, comprising a conveyor for transporting the excavated rock upward from the excavation zone to the transshipment station, a plurality of storage bins installed at the transshipment station for receiving excavated rock from the top of the conveyor so that the transported excavated rock is temporarily stored in silos to increase static discrete loads by the removed rock, and a similar set of skips, each of which x is associated with each of the storage bins and is able to move up and down on its guide in the shaft of the shaft for cyclical reception of discrete cargo of excavated rock from the corresponding one of the bunkers at the transshipment station for its transportation to the earth's surface zone, unloading in the earth's surface zone and return to transshipment station for receiving the next cargo of excavated rock. 15. Устройство по п.14, которое содержит пару накопительных бункеров и пару скипов.15. The device according to 14, which contains a pair of storage bins and a pair of skips. 16. Устройство по п.14 или 15, в котором скипы связаны их направляющими для перемещения вдоль путей, расположенных в боковом участке ствола шахты, имеющем площадь сечения, составляющую менее 50% площади сечения ствола шахты.16. The device according to 14 or 15, in which the skips are connected by their guides to move along paths located in the lateral section of the shaft of the shaft having a cross-sectional area of less than 50% of the cross-sectional area of the shaft of the shaft. 17. Устройство по любому из пп.14-16, в котором накопительные бункеры расположены на опорной раме, выполненной с возможностью периодической перестановки рамы и накопительных бункеров последовательно с перемещением вниз места работы.17. The device according to any one of paragraphs.14-16, in which the storage bins are located on a support frame made with the possibility of periodically rearranging the frame and storage bins in series with moving down the workplace. 18. Система для создания ствола шахты для подземного рудника, содержащая экскаватор для выемки грунта для создания ствола, проходящего вниз от зоны поверхности земли, и устройство по любому из пп.14-17 для удаления грунта, вынутого экскаватором.18. A system for creating a mine shaft for an underground mine, comprising an excavator for excavating the soil to create a shaft extending downward from a surface zone of the earth, and a device according to any one of claims 14-17 for removing soil excavated by an excavator. 19. Система по п.18, в которой экскаватор содержит роторную врубовую головку.19. The system of claim 18, wherein the excavator comprises a rotary cutting head. 20. Система по п.19, в которой роторная врубовая головка имеет ряд режущих грунт элементов, вращающихся вокруг, в общем, горизонтальной оси.20. The system according to claim 19, in which the rotary cutting head has a number of soil-cutting elements rotating around a generally horizontal axis. 21. Система по п.19 или 20, в которой врубовая головка является вращающейся вокруг вертикальной оси для образования, в общем, цилиндрического ствола.21. The system according to claim 19 or 20, in which the cutting head is rotating around a vertical axis to form a generally cylindrical barrel. 22. Система по любому из пп.18-21, в которой экскаватор выполнен с возможностью перемещения вниз в стволе шахты рудника независимо от станции перегрузки и конвейер имеет вертикально перемещающийся нижний конец, который перемещается вниз на ограниченное расстояние с продолжением приема вынутой породы во время перемещения вниз экскаватора относительно накопительной станции.22. The system according to any one of paragraphs 18-21, in which the excavator is arranged to move downward in the mine shaft of the mine independently of the transfer station and the conveyor has a vertically moving lower end that moves downward to a limited distance while continuing to receive the excavated rock during movement down excavator relative to the storage station. 23. Система по любому из пп.18-22, в которой станцию перегрузки располагают на надшахтном копре, а надшахтный копер спускают в шахту рудника на тросах и поддерживают независимо от буровой проходческой машины 21.23. The system according to any one of claims 18 to 22, wherein the transshipment station is located on the mine head, and the mine head is lowered into the mine shaft with cables and is supported independently of the drilling machine 21.
EA201270083A 2009-06-30 2010-06-30 Forming a shaft for an underground mine EA021979B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
AU2009903054A AU2009903054A0 (en) 2009-06-30 Forming a shaft for an underground mine
PCT/AU2010/000820 WO2011000037A1 (en) 2009-06-30 2010-06-30 Forming a shaft for an underground mine

Publications (2)

Publication Number Publication Date
EA201270083A1 EA201270083A1 (en) 2012-06-29
EA021979B1 true EA021979B1 (en) 2015-10-30

Family

ID=43410362

Family Applications (1)

Application Number Title Priority Date Filing Date
EA201270083A EA021979B1 (en) 2009-06-30 2010-06-30 Forming a shaft for an underground mine

Country Status (12)

Country Link
EP (1) EP2449214B1 (en)
CN (1) CN102472101B (en)
AU (1) AU2010268761B2 (en)
BR (1) BRPI1014138B1 (en)
CA (1) CA2765758C (en)
CL (1) CL2011003356A1 (en)
DE (2) DE10793425T8 (en)
EA (1) EA021979B1 (en)
MX (1) MX2012000112A (en)
PE (1) PE20121376A1 (en)
PL (1) PL2449214T3 (en)
WO (1) WO2011000037A1 (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046931B (en) * 2012-12-03 2015-01-14 云南建工水利水电建设有限公司 Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
AU2014253678B2 (en) * 2013-04-16 2017-10-12 Technological Resources Pty. Limited A method of moving a component or a material to and within a level of a shaft boring system
DE112014002722T5 (en) 2013-06-07 2016-03-03 Technological Resources Pty. Limited Funding Hype fall protection
AU2014277625B9 (en) 2013-06-07 2018-04-26 Technological Resources Pty. Limited Guide system
WO2015024069A1 (en) 2013-08-23 2015-02-26 Technological Resources Pty. Limited Skip and crosshead
CN103821519B (en) * 2013-11-14 2017-05-24 北京中煤矿山工程有限公司 Integrated propulsion and tangential fore bearing support structure
WO2015124728A2 (en) * 2014-02-21 2015-08-27 China Railway Engineering Equipment Group Co., Ltd (Creg) Shaft installation system with a multi-purpose service column
CN103924977B (en) * 2014-02-27 2016-01-06 中铁工程装备集团有限公司 Center stand column tunneling boring shaft drilling machine
WO2018055549A1 (en) * 2016-09-21 2018-03-29 Master Sinkers (Pty) Ltd Shaft enlargement arrangement for a boring system
US11014762B1 (en) 2017-09-11 2021-05-25 Grass Skirt Oilfield Consulting Inc. Apparatus, systems and methods for weighing and distributing drill cuttings in an enclosed cuttings skip
US10732020B1 (en) 2017-09-11 2020-08-04 Grass Skirt Oilfield Consulting Inc. Apparatus systems, and methods for determining cuttings level or volume in an enclosed cuttings skip
RU2685365C1 (en) * 2018-08-28 2019-04-17 Общество с ограниченной ответственностью "Скуратовский опытно-экспериментальный завод" Method of mine shaft construction and a shaft-penetrating combine
CN113482623B (en) * 2021-06-28 2024-02-02 山西工程技术学院 Vertical shaft shield machine and cutterhead system thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3965995A (en) * 1975-03-06 1976-06-29 The Robbins Company Machine for boring a large diameter blind hole
GB2158129A (en) * 1984-05-04 1985-11-06 Cementation Company Of America Earth boring apparatus
US4646853A (en) * 1984-07-31 1987-03-03 The Robbins Company Shaft boring machine and method
WO2005049966A1 (en) * 2003-11-20 2005-06-02 J.S. Redpath Limited Earth boring apparatus for sinking shafts and method of excavating a shaft
WO2010012290A1 (en) * 2008-07-31 2010-02-04 Herrenknecht Ag Method for introducing a vertical shaft and shaft driving machine

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1608290B2 (en) 1968-03-15 1976-12-09 Westfälische Berggewerkschaftskasse, 4630 Bochum; Schachtbau Thyssen GmbH, 4330 Mülheim DEVICE FOR BUMPING SHAFTS WITH AT LEAST ONE PICK UP THE PILE ON THE MANHOLE SOLE AND A LOADING DEVICE CONSISTING OF A GRAPPLE, AND WITH A BUCKET CONVEYOR
US5112111A (en) * 1990-12-10 1992-05-12 Addington Resources, Inc. Apparatus and method for continuous mining
CN1036674C (en) * 1993-01-15 1997-12-10 山西矿业学院 Apparatus for sinking shaft and its job practice
CN2300726Y (en) * 1997-05-19 1998-12-16 王家喜 Vertical lifting conveyer
JP4486766B2 (en) * 2001-06-19 2010-06-23 株式会社大林組 Vertical hole drilling rig
CN1525043A (en) * 2003-02-24 2004-09-01 蔡德彬 Cycle type vertical shaft drilling and digging equipment and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3965995A (en) * 1975-03-06 1976-06-29 The Robbins Company Machine for boring a large diameter blind hole
GB2158129A (en) * 1984-05-04 1985-11-06 Cementation Company Of America Earth boring apparatus
US4646853A (en) * 1984-07-31 1987-03-03 The Robbins Company Shaft boring machine and method
WO2005049966A1 (en) * 2003-11-20 2005-06-02 J.S. Redpath Limited Earth boring apparatus for sinking shafts and method of excavating a shaft
WO2010012290A1 (en) * 2008-07-31 2010-02-04 Herrenknecht Ag Method for introducing a vertical shaft and shaft driving machine

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
DOUGLAS, A. et al., Sinking Contractor's Close Out Presentation on Completion of South Deep Shafts, The South African Institute of Mining and Metallurgy, The Third South African Conference on Base Metals, c2005, [retrieved on 2 August 2010]. Retrieved from the Internet , See fig. 4, page 458 *

Also Published As

Publication number Publication date
PE20121376A1 (en) 2012-10-15
DE10793425T1 (en) 2012-11-08
AU2010268761A1 (en) 2012-01-19
MX2012000112A (en) 2012-02-29
BRPI1014138A2 (en) 2019-04-09
BRPI1014138B1 (en) 2019-11-05
PL2449214T3 (en) 2021-08-23
CN102472101B (en) 2014-03-12
AU2010268761B2 (en) 2012-07-26
EP2449214B1 (en) 2020-12-30
EP2449214A1 (en) 2012-05-09
CA2765758C (en) 2013-04-02
EP2449214A4 (en) 2013-01-23
DE10793425T8 (en) 2013-04-25
CA2765758A1 (en) 2011-01-06
CN102472101A (en) 2012-05-23
DE202010017762U1 (en) 2012-07-17
EA201270083A1 (en) 2012-06-29
CL2011003356A1 (en) 2012-06-22
WO2011000037A1 (en) 2011-01-06

Similar Documents

Publication Publication Date Title
EA021979B1 (en) Forming a shaft for an underground mine
CN104405437B (en) A kind of solid filling with combine the hybrid working face mining method of adopting
EA025603B1 (en) Underground mining
US8591151B2 (en) Forming a shaft for an underground mine
JP6527056B2 (en) EXPORT SYSTEM AND EXPORT METHOD OF EXCAVATOR
CN105401951B (en) The double rock gangways in colliery share discharge refuse method and system
CN110454219B (en) Full-gangue underground automatic filling device and method
CN105565130A (en) Coal mine vertical shaft combined hoisting system
CN204726935U (en) Raw material silo
CN110284883A (en) Recovery method is filled by a kind of row of adopting, open coal mine end side
CN104564139B (en) Sold stowing system and placement method
CN202628170U (en) Movable self-loading type waste rock bin mechanism
JP2002371792A (en) Device for conveying muck excavated from inclined shaft
AU2014100343A4 (en) A System for the Reduction in Applied Energy, Improved Efficiencies and Reduced Costs in Open Pit Mining
JP7162687B2 (en) Muddy transport system and tunnel excavation method
CN204643194U (en) A kind of closed bedding plant
CN204822720U (en) Even raw materials warehouse of windrow
CN109538204B (en) Mechanized continuous production method for mineral aggregate
CN218062383U (en) Anchoring machine is transported in tunnelling
CN113738438B (en) Integrated green mining method for coal pillar recovery and gangue filling
CN113847088B (en) Waste rock backfill conveying device for coal mine goaf
CN204979957U (en) Three -layer platform raw materials warehouse has
CN110863829A (en) Method for mining steeply inclined coal seam by fully-mechanized excavating machine
CN116677379A (en) Mineral exploitation method and mineral exploitation system
CN115341904A (en) Mine air shaft tunneling method

Legal Events

Date Code Title Description
MM4A Lapse of a eurasian patent due to non-payment of renewal fees within the time limit in the following designated state(s)

Designated state(s): AM AZ BY KZ KG MD TJ TM