AU2010268761A1 - Forming a shaft for an underground mine - Google Patents
Forming a shaft for an underground mine Download PDFInfo
- Publication number
- AU2010268761A1 AU2010268761A1 AU2010268761A AU2010268761A AU2010268761A1 AU 2010268761 A1 AU2010268761 A1 AU 2010268761A1 AU 2010268761 A AU2010268761 A AU 2010268761A AU 2010268761 A AU2010268761 A AU 2010268761A AU 2010268761 A1 AU2010268761 A1 AU 2010268761A1
- Authority
- AU
- Australia
- Prior art keywords
- shaft
- skip
- transfer station
- excavated material
- earth
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000000463 material Substances 0.000 claims abstract description 71
- 238000009412 basement excavation Methods 0.000 claims abstract description 15
- 238000003860 storage Methods 0.000 claims description 20
- 238000000034 method Methods 0.000 claims description 19
- 238000005520 cutting process Methods 0.000 claims description 13
- 230000037361 pathway Effects 0.000 claims description 8
- 230000015572 biosynthetic process Effects 0.000 claims description 7
- 238000009434 installation Methods 0.000 claims description 7
- 238000007599 discharging Methods 0.000 claims description 4
- 238000000151 deposition Methods 0.000 claims description 2
- 230000000737 periodic effect Effects 0.000 claims description 2
- 230000032258 transport Effects 0.000 description 10
- 238000009415 formwork Methods 0.000 description 5
- 238000005553 drilling Methods 0.000 description 4
- 238000005422 blasting Methods 0.000 description 3
- 230000003019 stabilising effect Effects 0.000 description 3
- 238000010276 construction Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000005507 spraying Methods 0.000 description 2
- 241000277284 Salvelinus fontinalis Species 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000004513 sizing Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 238000009423 ventilation Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D1/00—Sinking shafts
- E21D1/03—Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
- Earth Drilling (AREA)
- Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Piles And Underground Anchors (AREA)
Abstract
In forming a mine shaft for an underground mine, earth excavated by a boring machine (21) is transported upwardly by handling unit (22) to a transfer station (33) where it is transferred into skips 36 which are raised and lowered along skip guides 38 within the shaft hole (19) for transport of the excavated material to an earth surface region. Transfer station (33) is moved downwardly as excavation progresses.
Description
WO 2011/000037 PCT/AU2010/000820 FORMING A SHAFT FOR AN UNDERGROUND MINE Field of the Invention This invention relates to the formation of shafts for 5 underground mines. It has particular but not exclusive application to the formation of a mine shaft through which to provide access to underground mining activity and extraction of mined material after the mine shaft has been formed but it may also have application to the formation 10 of shafts for other purposes such as for use as ventilation shafts for underground mines. Background of the Invention Modern large block cave mines require a significant time 15 to develop and a very significant early investment. Both of these factors make their financial success in terms of net present value extremely sensitive to the speed at which they can be brought on stream. Deep cave mines require shaft access and the development of this shaft 20 access forms the initial part of the mine development and therefore is directly on the project critical path i.e. until the initial shafts are completed no other underground development activity can be commenced. 25 Traditional shaft sinking operations are carried out by drilling and blasting to excavate material to form a hole and removing the excavated material by a mucking system by which the excavated material is picked up and deposited in kibbles which are hoisted to the surface on cables run to 30 head gear and a winder installed at the surface of the mine. This mucking operation requires skilled operators and is inherently dangerous to miners required to guide and operate equipment at the bottom of the shaft as it is being formed. Moreover, the speed at which the excavated 35 material can be removed is limited by the need to cease operations for drilling and blasting, the difficulty of loading variable sized material into the kibbles and the WO 2011/000037 PCT/AU2010/000820 -2 limited speed at which the kibbles can be hoisted and lowered as they tend to move about on the very long lengths of cable as sinking progresses. 5 There have been proposals to increase the speed at which sinking can progress by using earth boring machinery. For example, United States patent 3,965,995 of Sugden which discloses a proposal to use a cutter wheel which rotates about a horizontal tubular support, where the cutting are 10 directed into the tubular support to be received by an endless bucket which carries them up to a discharge station. Another example is United States patent 4,589,502 of Salter et al which discloses a proposal to use a shaft sinking apparatus which employs an earth 15 boring machine having a rotary cutting head and a bucket conveyor for carrying cuttings to a feed bin installed on the boring machine from which the cuttings can be fed into a skip which is lifted by a crane to the ground surface. However, these prior art proposals still involve the 20 direct filling of kibbles, buckets or skips and the operational speed and capacity from such systems is thus limited by having such filling devices on station, ie if there is no filling device at the discharge station for such earth boring machinery, the machines must temporarily 25 cease cutting until another filling device is available. The present invention enables development of a more robust and effective removal system which allows the continued supply of excavated material to continue from such machines even if filling devices are not on station. 30 Summary of the Invention According to the invention there is provided a method of removing excavated material from a mine shaft during formation of the mine shaft for an underground mine, 35 comprising; transporting excavated material upwardly on a substantially continuous basis from an excavation region WO 2011/000037 PCT/AU2010/000820 -3 of the shaft to a transfer station above the excavation region; depositing the transported excavated material into at least one storage bin located at the transfer 5 station; intermittently discharging excavated material from the storage bin into a skip moveable up and down along a skip guide within the shaft to deposit a discrete load of excavated material into the skip; 10 hoisting the skip upwardly through the shaft to an earth surface region; discharging the load of excavated material from the skip at said surface region and lowering the skip back to the transfer station to receive a further discrete load 15 of excavated material from the storage bin; and moving the transfer station and storage bin periodically downwardly within the shaft as excavation proceeds. 20 The storage bin may be one of a plurality of such bins at the transfer station and the skip may be one of a like plurality of skips lowered and hoisted through the hole on guides to receive and transport material from the bins. More specifically, there may be a pair of storage bins at 25 the transfer station and a pair of skips moveable up and down within the shaft along adjacent pathways sequentially to receive discrete loads of excavated material and to transport those loads to the earth surface region for discharge at the earth surface region and then to return 30 downwardly to the transfer station. The skips may be constrained by respective skip guides to move along pathways disposed within a side segment of the shaft having a cross-sectional area which is less than 50% 35 of the cross-sectional area of the shaft.
WO 2011/000037 PCT/AU2010/000820 -4 The excavated material may be transported to the transfer station by a conveyor associated with the transfer station. 5 The conveyor may have a vertically moveable lower end which is moved downwardly through a limited distance as excavation proceeds before moving the transfer station. The periodic movement of the transfer station may be in 10 response to installation of shaft lining extensions below the transfer station. The invention further provides a method of forming a mine shaft for an underground mine, comprising: 15 excavating earth to form a hole extending downwardly from an earth surface region; and removing excavated material from the shaft by the above defined method. 20 The excavation of earth may be performed by an earth boring machine comprising a rotary cutting head. The hole may be lined progressively with a shaft lining incorporating a guide for the or each skip by installation 25 of successive lining and skip guide extensions below the transfer station so as to extend the lining and the skip guide for the or each extension of lining in advance of skip movements downwardly along the extensions. 30 The invention further provides apparatus for removing excavated material from a mine shaft during formation of the shaft, comprising: an extendible conveyor for transporting excavated material upwardly from an excavation region to a transfer 35 station; WO 2011/000037 PCT/AU2010/000820 -5 at least one storage bin located at the transfer station to receive excavated material from an upper part of the conveyor; and a skip moveable up and down on a skip guide 5 within the shaft intermittently to receive discrete loads of excavated material from the storage bin at the transfer station and transport that material to an earth surface region for discharge at the surface region. 10 The invention also extends to apparatus for forming a mine shaft for an underground mine, comprising: an excavator for excavating earth to form a hole extending downwardly from an earth surface region; and an apparatus as defined above for removing earth 15 excavated by the excavator. Brief Description of the Drawings In order that the invention may be more fully explained, one particular embodiment will be described in detail with 20 reference to the accompanying drawings in which: Figure 1 illustrates a shaft sinking system constructed and operated in accordance with the present invention; 25 Figure 2 is a vertical cross-section through the shaft sinking system; Figure 3 is a vertical cross-section through an upper part of the system; 30 Figures 4 and 5 are horizontal cross-sections through the upper part of the system; and Figures 6 and 7 illustrate the construction of a pair of 35 skips and skip guides incorporated in the system.
WO 2011/000037 PCT/AU2010/000820 -6 Detailed Description of the Preferred Embodiment The drawings illustrate a mine shaft boring apparatus denoted generally as 20 located in a shaft hole 19. This apparatus comprises a boring machine 21 and an excavated 5 material handling unit 22 disposed above the boring machine and operable to receive excavated material from the boring machine and to transfer it to skips for transport to ground level and discharge at ground level to appropriate conveying equipment or other transport for 10 disposal. Earth boring machine 21 has a rotary cutting head 23 fitted with cutters 25 and is mounted at the lower end of a main machine frame 26. The cutter head is rotatable 15 about a vertical axis so that the machine is operable to bore a generally cylindrically shaped hole. Bucket conveyors 45, 46 transport the excavated material from the cutter head upwardly to the material handling unit 22 disposed above the boring machine. 20 The main machine frame 26 can be stabilised or locked into position within the bored hole by operation of hydraulically actuated stabilising jacks 27, 28 which operate upper and lower grippers 29, 30 to grip the 25 sidewalls of the shaft to stabilise the position of the boring machine in the shaft. The boring machine can be advanced downwardly by incremental advancement of the main frame 26 by operation of the stabilising jacks 27, 28 and grippers 29, 30 in known fashion. 30 Material handling unit 22 comprises a galloway or main frame 31 formed by a series of platforms or decks 31a interconnected by circumferentially spaced vertical studs 32. 35 Galloway 31 may be lowered into the shaft on cables and is supported independently of boring machine 21.
WO 2011/000037 PCT/AU2010/000820 -7 Material handling unit 22 comprises a material transfer station 33 including a pair of storage bins in the form of hoppers 34 mounted side by side on galloway 31. The 5 galloway also supports a bucket conveyor 46 which transports excavated material from boring machine 21 upwardly through the shaft to a location above the transfer station from which it discharges the excavated material onto discharge ramps 35 and into the bins 34. 10 Conveyor 46 is operated while cutter head 23 is cutting to feed the excavated material into the bins and the material is discharged sequentially from the bins into a pair of skips 36 hoisted on cables 40 from ground level and fitted with wheels 37 which run on vertical guides 38 fitted to 15 the shaft in the manner to be described below. Skips 36 may be arc gate bottom dump skips as shown in Figures 6 and 7. The top and bottom of each skip is fitted with two sets of wheels 37 to run on three sides of 20 the respective vertical guides 38. Each skip is also fitted with open channel runners 50 lined with wear blocks to run along the guide. Skips 36 are operated in tandem so that as one skip is 25 hoisted from the transfer station 33 to ground level, the other skip is lowered to the loading station. When a skip 36 reaches the loading station the bottom floor of the respective bin 34 is moved to discharge material stored in the bin through discharge opening 39 into the skip. The 30 contents of the bin empties quickly to discharge a predetermined discrete load of material into the skip and the bottom door of the bin is closed. Each bin has sufficient capacity to accumulate material from conveyor 46 as the skip is hoisted to the surface, its contents 35 discharged by opening the bottom arc gate and the skip relowered to the loading station to receive another discrete load of material.
WO 2011/000037 PCT/AU2010/000820 -8 Skips 36 are formed as long rectangular containers which are disposed so as to extend vertically along a side section or segment 52 of the shaft. This section of the 5 shaft, which occupies considerably less than 50% of the shaft cross-section may be divided from the remainder of the shaft space by steel formwork carrying the skip guides 38 and set into a shaft lining 42 installed within the shaft as boring progresses. Typically the maximum width 10 side segment 52 of the shaft may be no more than about one third of the shaft diameter. As shown in Figures 2 and 3, the shaft may be fitted with air ducts 43 and a delivery bucket or lift 44 for delivery 15 of men and materials to the decks of galloway 34 and the mainframe of the boring machine, a central region 51 of the shaft remaining available as a heave lift compartment. Because skips 36 are constrained to run on guides which 20 are firmly anchored to the shaft lining through the formwork 41 they can be of very robust construction and can be raised and lowered along the guides and within the protective formwork much more rapidly than the receptacles previously used for transmitting excavated material to the 25 surface. The lining 42 may be formed of concrete and to enable progressive extension of the lining and the guides for the skips the shaft lining and skip guides may be extended by installation of successive lining and skip guide extensions below the transfer station 33 while 30 material is being conveyed and transferred in advance of movements of the skips into the extensions of the lining as shaft sinking proceeds. As shaft boring operations proceed the boring machine may 35 be advanced in successive increments by alternate operation of the stabilising jacks 27, 28 to allow the machine to move down the hole. The bottom end of conveyor WO 2011/000037 PCT/AU2010/000820 -9 is vertically extensible by movement of a bottom loop 46a of the conveyor with compensating movement of an upper loop 46b to allow continued transport of excavated material by the conveyor to the transfer station and 5 discharge into hoppers 34 without moving the transfer station as the cutter head of the boring machine and the conveyor 45 moves through a limited distance. During this time, an extension of the shaft lining 42 (not shown) can be installed below the transfer station, more 10 specifically, on the platforms or decks immediately below the lowermost positions of the skips 36 in the lining installation zone 90 during the then current material transfer and hoisting operations. 15 The lining may be installed by spraying concrete directly onto the bored hole through a slick line extending from the surface and supplying concrete through a distributor to one or more, typically two, manually operated application hoses. Alternatively, the concrete can be 20 poured into formwork instead of being sprayed or the lining can be assembled from precast components and attached to the wall by bolting or other convenient means. Extensions of the skip guides and skip guide formwork can then be installed so as to be firmly anchored to the 25 lining. The unit 22 can then be lowered so that the loading station is lowered and the skips 36 allowed to run onto the extended guides within the extended lining. If the lining is applied in wet form to the bore hole by spraying or other means, sufficient time will need to be 30 allowed for the concrete to cure before the loading station is lowered. As the transfer station is supported independently of the boring machine it can be moved in incremental steps or 35 substantially continuous movements which may or may not match the movements of the boring machine. Typically such WO 2011/000037 PCT/AU2010/000820 - 10 movements will be in response to the need to reposition to do another extension of the shaft lining. The invention enables the development of a material 5 transfer and hoisting system as the hole progresses using skips which can be robust and can be hoisted and lowered more rapidly than kibbles and other unguided receptacles. The illustrated system is capable of moving excavated material at a rate equal to that required for removal of 10 material in an operating mine. The capacity will depend on the size of the hoist at the surface and the depth of the shaft but a typical installation should be capable of moving at least 4,500 tonnes of excavated material per day. Accordingly, the transfer station and skip hoisting 15 equipment as installed during the shaft sinking operation may be left in position and subsequently used for retrieving material from a subsequently developed operating mine. 20 The illustrated system has been advanced by way of example only and it could be modified considerably including various skip guide arrangements. Various kinds of boring machines could be used in an apparatus or method in accordance with the invention. Such boring machines could 25 use various types of cutters or may employ hydraulic or other types of excavation. The excavation may alternatively be carried out by drilling and low energy blasting operations for example by drilling small closely spaced holes filled with low energy charges. The 30 excavated material may be picked up for transport to the transfer station by any appropriate means such as by water slurry transport. It would also be possible to install a material sizing unit on the excavator to crush or otherwise size the excavated material to a condition 35 suitable for loading onto the bottom end of the conveyor transporting it to the transfer station.
WO 2011/000037 PCT/AU2010/000820 - 11 It is to be understood that these and many other modifications and variations may be made without departing from the scope of the invention and the appended claims.
Claims (23)
1. A method of removing excavated material from a mine shaft during formation of the mine shaft for an 5 underground mine, comprising; transporting excavated material upwardly on a substantially continuously basis from an excavation region of the shaft to a transfer station above the excavation region; 10 depositing the transported excavated material into at least one storage bin located at the transfer station; intermittently discharging excavated material from the storage bin into a skip moveable up and down 15 along a skip guide within the shaft to deposit a discrete load of excavated material into the skip; hoisting the skip upwardly through the shaft to an earth surface region; discharging the load of excavated material from 20 the skip at said surface region and lowering the skip back to the transfer station to receive a further discrete load of excavated material from the storage bin; and moving the transfer station and storage bin periodically downwardly within the shaft as excavation 25 proceeds.
2. A method as claimed in claim 1, wherein the storage bin is one of a plurality of such bins at the transfer station and the skip is one of a like plurality 30 of skips lowered and hoisted through the hole to receive and transport material from the bins.
3. A method as claimed in claim 2 wherein there is a pair of storage bins at the transfer station and a pair of 35 skips moveable up and down within the shaft along adjacent pathways sequentially to receive loads of excavated material and to transport those loads to the earth surface WO 2011/000037 PCT/AU2010/000820 - 13 region for discharge at the earth surface region and then to return downwardly to the transfer station.
4. A method as claimed in claim 2 or claim 3, 5 wherein the skips are constrained to said pathways by moving along vertical guides within the shaft.
5. A method as claimed in claim 4, wherein the skips are constrained by respective skip guides to move along 10 pathways disposed within a side segment of the shaft having a cross-sectional area which is less than 50% of the cross-sectional area of the shaft.
6. A method as claimed in any one of the preceding 15 claims, wherein the excavated material is transported to the transfer station by a conveyor associated with the transfer station.
7. A method as claimed in claim 6 wherein the 20 conveyor has a vertically moveable lower end which is moved downwardly through a limited distance as excavation proceeds before moving the transfer station.
8. A method as claimed in any one of the preceding 25 claims wherein the periodic moment of the transfer station is in response to installation of shaft lining extensions below the transfer station.
9. A method of forming a mine shaft for an 30 underground mine, comprising: excavating earth to form a hole extending downwardly from an earth surface region; and removing excavated material from the shaft by a method as claimed in any one of claims 1 to 8. 35 WO 2011/000037 PCT/AU2010/000820 - 14
10. A method as claimed in claim 9, wherein the excavation of earth is performed by an earth boring machine. 5
11. A method as claimed in claim 10 wherein the earth boring machine comprises a rotary cutting head.
12. A method as claimed in claim 11 wherein the rotary cutting head has a series of cutter elements 10 rotated about a horizontal axis to excavate material from the earth.
13. A method as claimed in claim 12 wherein the cutter head is rotated about a vertical axis so as to bore 15 a generally cylindrical hole.
14. A method as claimed in any one of the preceding claims wherein the hole is lined progressively with a shaft lining incorporating a guide for the or each skip by 20 installation of successive lining and skip guide extensions below the transfer station so as to extend the lining and the skip guide for the or each extension of lining in advance of skip movements downwardly along the extensions. 25
15. Apparatus for removing excavated material from a mine shaft during formation of the shaft, comprising: a conveyor for transporting excavated material upwardly from an excavation region to a transfer station; 30 at least one storage bin located at the transfer station to receive excavated material from an upper part of the conveyor; and a skip moveable up and down on a skip guide within the shaft intermittently to receive discrete loads 35 of excavated material from the storage bin at the transfer station and transport that material to an earth surface region for discharge at the surface region. WO 2011/000037 PCT/AU2010/000820 - 15
16. Apparatus as claimed in claim 15 wherein the storage bin is one of a plurality of such bins at the transfer station and the skip is one of a like plurality 5 of skips moveable up within the shaft along adjacent pathways to in turn receive excavated material from a respective storage bin and transport that material to the surface region for discharge at the surface region. 10
17. Apparatus as claimed in claim 16 wherein there is a pair of storage bins and a pair of said skips.
18. Apparatus as claimed in claim 15 or claim 16 wherein the skips are constrained to said pathways by 15 vertical skip guides within the shaft.
19. Apparatus as claimed in claim 17 wherein the skip pathways are disposed within a side segment of the shaft having a cross-sectional area less than 50% of the cross 20 sectional area of the shaft.
20. Apparatus for forming a mine shaft for an underground mine, comprising: an excavator for excavating earth to form a hole 25 extending downwardly from an earth surface region; and an apparatus as claimed in any one of claims 15 to 19 for removing earth excavated by the excavator.
21. Apparatus as claimed in claim 20 wherein the 30 excavator comprises a rotary cutting head.
22. Apparatus as claimed in claim 21 wherein the rotary cutting head has a series of earth cutters rotatable about a generally horizontal axis. 35 WO 2011/000037 PCT/AU2010/000820 - 16
23. Apparatus as claimed in claim 21 or claim 22 wherein the cutting head is rotatable about a vertical axis so as to form a generally cylindrical hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU2010268761A AU2010268761B2 (en) | 2009-06-30 | 2010-06-30 | Forming a shaft for an underground mine |
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU2009903054A AU2009903054A0 (en) | 2009-06-30 | Forming a shaft for an underground mine | |
AU2009903054 | 2009-06-30 | ||
PCT/AU2010/000820 WO2011000037A1 (en) | 2009-06-30 | 2010-06-30 | Forming a shaft for an underground mine |
AU2010268761A AU2010268761B2 (en) | 2009-06-30 | 2010-06-30 | Forming a shaft for an underground mine |
Publications (2)
Publication Number | Publication Date |
---|---|
AU2010268761A1 true AU2010268761A1 (en) | 2012-01-19 |
AU2010268761B2 AU2010268761B2 (en) | 2012-07-26 |
Family
ID=43410362
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
AU2010268761A Active AU2010268761B2 (en) | 2009-06-30 | 2010-06-30 | Forming a shaft for an underground mine |
Country Status (12)
Country | Link |
---|---|
EP (1) | EP2449214B1 (en) |
CN (1) | CN102472101B (en) |
AU (1) | AU2010268761B2 (en) |
BR (1) | BRPI1014138B1 (en) |
CA (1) | CA2765758C (en) |
CL (1) | CL2011003356A1 (en) |
DE (2) | DE10793425T8 (en) |
EA (1) | EA021979B1 (en) |
MX (1) | MX2012000112A (en) |
PE (1) | PE20121376A1 (en) |
PL (1) | PL2449214T3 (en) |
WO (1) | WO2011000037A1 (en) |
Families Citing this family (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103046931B (en) * | 2012-12-03 | 2015-01-14 | 云南建工水利水电建设有限公司 | Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode |
AU2014253678B2 (en) * | 2013-04-16 | 2017-10-12 | Technological Resources Pty. Limited | A method of moving a component or a material to and within a level of a shaft boring system |
DE112014002722T5 (en) | 2013-06-07 | 2016-03-03 | Technological Resources Pty. Limited | Funding Hype fall protection |
AU2014277625B9 (en) | 2013-06-07 | 2018-04-26 | Technological Resources Pty. Limited | Guide system |
WO2015024069A1 (en) | 2013-08-23 | 2015-02-26 | Technological Resources Pty. Limited | Skip and crosshead |
CN103821519B (en) * | 2013-11-14 | 2017-05-24 | 北京中煤矿山工程有限公司 | Integrated propulsion and tangential fore bearing support structure |
WO2015124728A2 (en) * | 2014-02-21 | 2015-08-27 | China Railway Engineering Equipment Group Co., Ltd (Creg) | Shaft installation system with a multi-purpose service column |
CN103924977B (en) * | 2014-02-27 | 2016-01-06 | 中铁工程装备集团有限公司 | Center stand column tunneling boring shaft drilling machine |
WO2018055549A1 (en) * | 2016-09-21 | 2018-03-29 | Master Sinkers (Pty) Ltd | Shaft enlargement arrangement for a boring system |
US11014762B1 (en) | 2017-09-11 | 2021-05-25 | Grass Skirt Oilfield Consulting Inc. | Apparatus, systems and methods for weighing and distributing drill cuttings in an enclosed cuttings skip |
US10732020B1 (en) | 2017-09-11 | 2020-08-04 | Grass Skirt Oilfield Consulting Inc. | Apparatus systems, and methods for determining cuttings level or volume in an enclosed cuttings skip |
RU2685365C1 (en) * | 2018-08-28 | 2019-04-17 | Общество с ограниченной ответственностью "Скуратовский опытно-экспериментальный завод" | Method of mine shaft construction and a shaft-penetrating combine |
CN113482623B (en) * | 2021-06-28 | 2024-02-02 | 山西工程技术学院 | Vertical shaft shield machine and cutterhead system thereof |
Family Cites Families (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1608290B2 (en) | 1968-03-15 | 1976-12-09 | Westfälische Berggewerkschaftskasse, 4630 Bochum; Schachtbau Thyssen GmbH, 4330 Mülheim | DEVICE FOR BUMPING SHAFTS WITH AT LEAST ONE PICK UP THE PILE ON THE MANHOLE SOLE AND A LOADING DEVICE CONSISTING OF A GRAPPLE, AND WITH A BUCKET CONVEYOR |
US3965995A (en) * | 1975-03-06 | 1976-06-29 | The Robbins Company | Machine for boring a large diameter blind hole |
US4589502A (en) * | 1984-05-04 | 1986-05-20 | Cementation Company Of America, Incorporated | Earth boring apparatus |
US4646853A (en) * | 1984-07-31 | 1987-03-03 | The Robbins Company | Shaft boring machine and method |
US5112111A (en) * | 1990-12-10 | 1992-05-12 | Addington Resources, Inc. | Apparatus and method for continuous mining |
CN1036674C (en) * | 1993-01-15 | 1997-12-10 | 山西矿业学院 | Apparatus for sinking shaft and its job practice |
CN2300726Y (en) * | 1997-05-19 | 1998-12-16 | 王家喜 | Vertical lifting conveyer |
JP4486766B2 (en) * | 2001-06-19 | 2010-06-23 | 株式会社大林組 | Vertical hole drilling rig |
CN1525043A (en) * | 2003-02-24 | 2004-09-01 | 蔡德彬 | Cycle type vertical shaft drilling and digging equipment and construction method thereof |
WO2005049966A1 (en) * | 2003-11-20 | 2005-06-02 | J.S. Redpath Limited | Earth boring apparatus for sinking shafts and method of excavating a shaft |
JP5285152B2 (en) * | 2008-07-31 | 2013-09-11 | ヘーレンクネヒト アーゲー | Method of excavating vertical shaft and excavating machine |
-
2010
- 2010-06-30 DE DE10793425T patent/DE10793425T8/en active Active
- 2010-06-30 AU AU2010268761A patent/AU2010268761B2/en active Active
- 2010-06-30 CN CN201080029789.3A patent/CN102472101B/en active Active
- 2010-06-30 EA EA201270083A patent/EA021979B1/en not_active IP Right Cessation
- 2010-06-30 DE DE202010017762U patent/DE202010017762U1/en not_active Expired - Lifetime
- 2010-06-30 MX MX2012000112A patent/MX2012000112A/en active IP Right Grant
- 2010-06-30 PE PE2011002185A patent/PE20121376A1/en active IP Right Grant
- 2010-06-30 CA CA2765758A patent/CA2765758C/en active Active
- 2010-06-30 BR BRPI1014138-3A patent/BRPI1014138B1/en active IP Right Grant
- 2010-06-30 EP EP10793425.9A patent/EP2449214B1/en active Active
- 2010-06-30 PL PL10793425T patent/PL2449214T3/en unknown
- 2010-06-30 WO PCT/AU2010/000820 patent/WO2011000037A1/en active Application Filing
-
2011
- 2011-12-29 CL CL2011003356A patent/CL2011003356A1/en unknown
Also Published As
Publication number | Publication date |
---|---|
PE20121376A1 (en) | 2012-10-15 |
DE10793425T1 (en) | 2012-11-08 |
MX2012000112A (en) | 2012-02-29 |
BRPI1014138A2 (en) | 2019-04-09 |
BRPI1014138B1 (en) | 2019-11-05 |
PL2449214T3 (en) | 2021-08-23 |
CN102472101B (en) | 2014-03-12 |
AU2010268761B2 (en) | 2012-07-26 |
EP2449214B1 (en) | 2020-12-30 |
EP2449214A1 (en) | 2012-05-09 |
CA2765758C (en) | 2013-04-02 |
EP2449214A4 (en) | 2013-01-23 |
DE10793425T8 (en) | 2013-04-25 |
CA2765758A1 (en) | 2011-01-06 |
CN102472101A (en) | 2012-05-23 |
EA021979B1 (en) | 2015-10-30 |
DE202010017762U1 (en) | 2012-07-17 |
EA201270083A1 (en) | 2012-06-29 |
CL2011003356A1 (en) | 2012-06-22 |
WO2011000037A1 (en) | 2011-01-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2765758C (en) | Forming a shaft for an underground mine | |
US8591151B2 (en) | Forming a shaft for an underground mine | |
CA2765714C (en) | Underground mining | |
CA2883015C (en) | A system for the reduction in applied energy, improved efficiencies and reduced costs in open pit mining | |
US4353796A (en) | Apparatus for digging and transporting soil and sand, stones and rocks, minerals and the like | |
AU2015100065A4 (en) | A System for the Reduction in Applied Energy, Improved Efficiencies and Reduced Costs in Open Pit Mining | |
CN209780954U (en) | Coal face end triangular space filling device | |
WO1985004916A1 (en) | Excavation apparatus | |
Krauze et al. | Mechanized shaft sinking system | |
CN115341904A (en) | Mine air shaft tunneling method | |
CN112811210A (en) | Intelligent driving, loading and slag storage bin | |
Thomson | Pipejacking equipment: line, drive pit, top side | |
JPS62148795A (en) | Method and maching for excavating vertical pit | |
CZ20012628A3 (en) | Sinking machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FGA | Letters patent sealed or granted (standard patent) |