DE4025355A1 - Construction of piers for bridge spanning river - by forming concrete foundation inside double walled shuttering - Google Patents

Construction of piers for bridge spanning river - by forming concrete foundation inside double walled shuttering

Info

Publication number
DE4025355A1
DE4025355A1 DE19904025355 DE4025355A DE4025355A1 DE 4025355 A1 DE4025355 A1 DE 4025355A1 DE 19904025355 DE19904025355 DE 19904025355 DE 4025355 A DE4025355 A DE 4025355A DE 4025355 A1 DE4025355 A1 DE 4025355A1
Authority
DE
Germany
Prior art keywords
foundation
river
bridge
river bed
screws
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE19904025355
Other languages
German (de)
Inventor
Des Erfinders Auf Nennung Verzicht
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LAMMERS ALBERT 4400 MUENSTER DE
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE19904025355 priority Critical patent/DE4025355A1/en
Publication of DE4025355A1 publication Critical patent/DE4025355A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/02Caissons able to be floated on water and to be lowered into water in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Foundations (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The piers supporting a bridge which spans a river are constructed in the following way. Oversize screws, arranged in a row at right angles to the direction of the flow of the river, are screwed into the river bed. These screws extend to a height above the water which is less than the height of the undersurface of the intended bridge. The pier foundation is then formed by means of double walled shuttering which is floated to the required position. The shuttering is then sunk to the river bed by filling the space between inner and outer walls with material excavated from the riverbed. The inner space is then filled with concrete to form the pier foundation. After the concrete has hardened, the pier is erected on the foundation. USE - Bridge building.

Description

Die Erfindung betrifft ein Verfahren mit Vorrichtung zum Bau von Brückenpfeilern in Fließgewässer.The invention relates to a method with a device for building Bridge piers in rivers.

Brücken müssen über Fließgewässer gebaut werden, heut und in Zu­ kunft. Bestehende Brücken müssen saniert werden, was zum nach­ träglichen Bau von Brückenpfeilern unter sanierungsbedürftige Brücken führen kann oder zu vorübergehender Errichtung von Be­ helfs-Brückenpfeilern für die Zeit der Sanierung. Das erfordert viel Zeit für die Vorplanung und Vorbereitung, da jedes Fließge­ wässer und jede Brücke zusammen ein individuelles Problem dar­ stellen, das nicht schematisch gelöst werden kann bis heute.Bridges must be built over rivers, today and in Zu coming. Existing bridges have to be renovated, which leads to the sluggish construction of bridge piers under renovation Can lead to bridges or to the temporary erection of Be helfs bridge pillars for the time of renovation. That requires plenty of time for pre-planning and preparation, as every Flgege water and each bridge together represent an individual problem that cannot be solved schematically to this day.

Eine schematische schnelle Lösung wäre aber bei plötzlich not­ wendig gewordener Sanierungsarbeit sehr von Vorteil und könnte die Zeit der Sanierung oder des Brückenbaues sehr verkürzen.A schematic quick solution would suddenly be needed agile renovation work very beneficial and could shorten the time of the renovation or the bridge construction.

Leider gibt es noch kein Schema für den Bau von Brückenpfei­ lern in Fließgewässer, denn die Fließgewässer gilt es zu erhal­ ten, andererseits sind Fließgewässer unberechenbar. Ein Wolken­ bruch stromaufwärts kann einen ruhigen Strom in einen reißenden und kaum zu bändigenden Strom verwandeln und das in sehr kurzer Zeit. Das kann Brückenbauer bedrängen und sie in Not bringen.Unfortunately, there is still no scheme for the construction of bridge pillars Learn in rivers, because the rivers have to be preserved On the other hand, rivers are unpredictable. A cloud break upstream can be a calm stream into a torrent and transform electricity that can hardly be tamed, in a very short time Time. This can press bridge builders and put them in need.

Es ist daher Aufgabe der Erfindung, ein Verfahren mit Vorrich­ tung aufzuzeigen, mit welchem Brückenpfeiler schematisch für fast jedes Fließgewässer geplant, vorbereitet und schnell in die Fließgewässer gebaut werden kann.It is therefore an object of the invention, a method with Vorrich to show which bridge pillar schematically for almost every river is planned, prepared and quickly into the Rivers can be built.

Die gestellte Aufgabe wird erfindungsgemäß durch die Merkmale des Anspruchs 1 gelöst.The object is achieved by the features of claim 1 solved.

Unterhalb des bzw. der (zukünftigen) Brückenpfeiler und der Brücke, stromabwärts gesehen, werden eine oder mehrere Reihen überdimensionale Schrauben wie Bohrgestänge in den Flußunter­ grund gebohrt bzw. geschraubt, so tief, daß mit Sicherheit trotz aller Strömung sie immer fest stehen werden, z. B. 20 m tief. Sie überragen den Flußgrund ein Stück und vor ihnen wird Aushub aus dem Fluß aufgeschüttet und dadurch der Fluß ein wenig aufgestaut. Dies geschieht bis zu solcher Höhe, daß eine Doppelschalung in der Art eines Schiffes vom Ufer ins Wasser gelassen werden kann und auf dem Wasser an den Ort geschwommen werden kann, an welcher der Brückenpfeiler stehen soll. Die Doppelschalung ist dafür schwimmfähig. Ist die Doppelschalung am Ort des zukünfti­ gen Brückenpfeilers fixiert, so wird Aushub aus dem Fluß zwi­ schen die äußere Wandung der Doppelschalung und ihre innere Wan­ dung geschüttet. Zuvor wurde an dieser Stelle im Flußbett eine Vertiefung ausgehoben, in welche die Schalung jetzt durch das Ge­ wicht des eingefüllten Flußaushubs in den äußeren Hohlraum ver­ sinkt bis an den Rand des Wasserspiegels. Jetzt wird das Füllma­ terial für das Fundament des Brückenpfeilers auf dem Gewässer herangefahren und der innere Hohlraum der Doppelschalung damit gefüllt als zukünftiges Fundament.Below the (future) bridge pier and the Bridge, seen downstream, become one or more rows oversized screws like drill pipes in the river bottom drilled or screwed to the bottom, so deep that with certainty despite of all currents they will always be fixed, e.g. B. 20 m deep. they protrude a little from the river bed and excavation is carried out in front of them heaped up on the river and thereby the river a little dammed up. This happens up to such a height that a double formwork in like a ship can be launched into the water from the shore and can be floated on the water to the place  which of the bridge pillars should stand. The double formwork is for floating. Is the double formwork at the location of the future fixed to the bridge pier, so excavation from the river is between the outer wall of the double formwork and its inner wall poured dung. Previously, a was in the river bed at this point Excavated in which the formwork is now by Ge weight of the filled river excavation in the outer cavity ver sinks to the edge of the water level. Now the filling measure material for the foundation of the bridge pier on the water moved up and the inner cavity of the double formwork filled as a future foundation.

Dieses Fundament hat aber Aussparungen bzw. Löcher, welche für das Einschrauben von überdimensionalen Schrauben dienen, die nach dem Aushärten des Fundamentes eingeschraubt werden und das Fundament unbeweglich auf den Platz fixieren. Aus dem Fundament ragt die Armierung für den Aufbau des Brückenpfeilers. Diese Ar­ mierung kann auch durch die überdimensionalen Schrauben gebil­ det werden, indem man sie entsprechend weit aus dem Fundament herausragen läßt.But this foundation has cutouts or holes, which for the screwing in of oversized screws that serve be screwed in after the foundation has hardened and that Fix the foundation immovably on the place. From the foundation the reinforcement protrudes for the construction of the bridge pier. This ar The oversized screws can also be used for lubrication be removed by moving them far enough from the foundation protrudes.

Die das Wasser aufstauende Reihe überdimensionaler Schrauben wird jetzt in den Flußgrund geschraubt bis zu solcher Tiefe, daß im Bereich der Brücke ein Niveauausgleich stattfindet in der Art, daß dadurch unterhalb der Brücke zwischen den Brückenpfeilern die Fließgeschwindigkeit des Wassers zumindest am Grunde des Flusses stark gebremst wird.The row of oversized screws that block the water is now screwed into the riverbed to such a depth that A level compensation takes place in the area of the bridge in such a way that the below the bridge between the bridge piers Flow speed of the water at least at the bottom of the river is heavily braked.

Die schwimmfähige Schalung wird aus genormten Teilen mittels Dichtungen wasserdicht zusammengebaut an Land und nach Aushärten des Fundamentes über dem Flußgrund an den Seiten des Fundamentes wieder abgebaut für erneute Benutzung.The floating formwork is made from standardized parts Seals assembled watertight on land and after curing of the foundation over the river bed on the sides of the foundation dismantled again for reuse.

Die überdimensionalen Schrauben sind hohl und werden nach dem Ein­ schrauben mit Beton gefüllt. Soweit diese über das Fundament ins Freie ragen, werden diese überstehenden Teile abgeschraubt oder sonstwie entfernt.The oversized screws are hollow and become after the one screws filled with concrete. As far as this about the foundation ins If they protrude freely, these protruding parts are unscrewed or otherwise removed.

Brückenpfeiler können jetzt in kürzester Zeit gebaut werden.Bridge piers can now be built in no time.

Claims (5)

1. Verfahren und Vorrichtung für den Bau von Brückenpfeilern in Fließgewässer, dadurch gekennzeichnet, daß
unterhalb mit Abstand von der (zukünftigen) Flußüberbrückung überdimensionale Schrauben in ein oder mehr Reihen quer zur Fließrichtung des Flusses in den Flußgrund geschraubt werden und mit Aushub davor und dazwischen über den Flußgrund hinausragen und das Fließgewässer aufstauen,
das Fundament für den Brückenpfeiler vom Ufer innerhalb der ent­ standenen Tiefwasserzone als schwimmfähige, doppelwandige Scha­ lung ins Wasser gelassen und an den Ort des zukünftigen Brücken­ pfeilers geschwommen wird
und der Hohlraum zwischen der äußeren und inneren Wand der dop­ pelwandigen Schalung mit Aushub vom Flußbett gefüllt wird und mit dem Flußbett-Aushub gefüllt in die vorbereitete Flußvertie­ fung versinkt,
danach der innere Hohlraum innerhalb der inneren Schalungswand mit dem Material (Beton) des zukünftigen Fundaments gefüllt wird und in belassene Aussparungen (Löcher) des Fundaments nach Aushärten des Fundaments überdimensionale Schrauben geschraubt werden in die Tiefe des Flußuntergrundes und der Brückenpfeiler dann auf das Fundament gegossen bzw. aufgebaut wird mit den aus dem Fundament herausragenden Armierungen,
danach die das Wasser zusammen mit dem Aushub aufstauenden über­ dimensionalen Schrauben in den Flußgrund weiter hineingeschraubt werden bis zur Höhe des Flußgrundes oberhalb der Brückenpfeiler in der Art eines Niveauausgleiches.
1. The method and device for the construction of bridge piers in flowing waters, characterized in that
underneath, with distance from the (future) river bridging, oversized screws are screwed into the river bed in one or more rows transversely to the direction of flow of the river and with excavation in front of and in between they protrude over the river bed and build up the river,
the foundation for the bridge pillar is let into the water as a floating, double-walled formwork from the bank within the deep-water zone that has been created and is floated to the location of the future bridge pillar
and the cavity between the outer and inner walls of the double-walled formwork is filled with excavation from the river bed and filled with the river bed excavation sinks into the prepared river depression,
Then the inner cavity within the inner formwork wall is filled with the material (concrete) of the future foundation and oversized screws are screwed into the left recesses (holes) of the foundation after the foundation has hardened is built with the reinforcements protruding from the foundation,
afterwards the water, together with the excavation, is screwed into the river bed by means of dimensional screws up to the height of the river bed above the bridge piers in the manner of level compensation.
2. Verfahren und Vorrichtung nach Anspruch 1, dadurch gekennzeich­ net, daß die schwimmfähige Schalung aus genormten Teilen mit Dichtungen zusammengesetzt ist und oberhalb des Flußgrundes nach Aushärten des Fundamentes wieder abgebaut wird.2. The method and device according to claim 1, characterized net that the floating formwork made of standardized parts with seals is composed and above the river bed after curing the foundation is dismantled again. 3. Verfahren und Vorrichtung nach Anspruch 1 und 2, dadurch ge­ kennzeichnet, daß die überdimensionalen Schrauben für die Verschraubung des Fun­ damentes im Flußgrund hohl sind und ausgegossen werden mit z. B. Beton. 3. The method and device according to claim 1 and 2, characterized ge indicates that the oversized screws for screwing the Fun dameses in the river bottom are hollow and are poured out with z. B. Concrete.   4. Verfahren und Vorrichtung nach Anspruch 1 bis 3, dadurch ge­ kennzeichnet, daß
die überdimensionalen Schrauben durch das Fundament in den Unter­ grund des Flußbettes reichen und über das Fundament ragen statt Armierungen, die Brückenpfeiler stützen von innen.
4. The method and device according to claim 1 to 3, characterized in that
the oversized screws extend through the foundation into the underground of the river bed and protrude above the foundation instead of reinforcements, the bridge piers support from the inside.
5. Verfahren und Vorrichtung nach Anspruch 1-4, dadurch gekenn­ zeichnet, daß der über das Fundament außerhalb der Brückenpfeiler reichende Teil der das Fundament am Untergrund haltenden überdimensiona­ len Schrauben abnehmbar bzw. abschraubbar ist.5. The method and device according to claim 1-4, characterized records that the one reaching over the foundation outside the bridge pillars Part of the oversize that holds the foundation on the ground len screws can be removed or unscrewed.
DE19904025355 1990-08-10 1990-08-10 Construction of piers for bridge spanning river - by forming concrete foundation inside double walled shuttering Withdrawn DE4025355A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19904025355 DE4025355A1 (en) 1990-08-10 1990-08-10 Construction of piers for bridge spanning river - by forming concrete foundation inside double walled shuttering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19904025355 DE4025355A1 (en) 1990-08-10 1990-08-10 Construction of piers for bridge spanning river - by forming concrete foundation inside double walled shuttering

Publications (1)

Publication Number Publication Date
DE4025355A1 true DE4025355A1 (en) 1991-05-02

Family

ID=6411992

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19904025355 Withdrawn DE4025355A1 (en) 1990-08-10 1990-08-10 Construction of piers for bridge spanning river - by forming concrete foundation inside double walled shuttering

Country Status (1)

Country Link
DE (1) DE4025355A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102010006458A1 (en) * 2010-02-01 2011-09-22 Ed. Züblin Aktiengesellschaft Method and installation arrangement with a flat foundation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102010006458A1 (en) * 2010-02-01 2011-09-22 Ed. Züblin Aktiengesellschaft Method and installation arrangement with a flat foundation

Similar Documents

Publication Publication Date Title
DE69635549T2 (en) METHOD AND DEVICE FOR ESTABLISHING ENDLESS UNDERGROUND WALLS
DE2434200C3 (en) Process for the production of underground cavities
WO2019122118A1 (en) Polygonal strutting system with node points for bracing foundation pits
DE112022001701T5 (en) Basket-shaped, large-span swallow-style steel box arch bridge with specially shaped arch ribs and its rapid construction method
DE2332725A1 (en) METHOD AND DEVICE FOR THE MANUFACTURING OF CONCRETE STRUCTURES IN WATER
DE2403988A1 (en) PROCEDURE FOR MAKING OR STABILIZING A FOUNDATION USING STAKES EXTENDING THE GROUND
DE69804834T2 (en) ARCH BAUTRÄGER STRUCTURE
DE2330061C2 (en) Method and cover plate for making a concrete foundation under water
CH610966A5 (en) Rock or slope revetment and method of constructing it
DE4025355A1 (en) Construction of piers for bridge spanning river - by forming concrete foundation inside double walled shuttering
DE4219078C2 (en) Device for lowering a foundation part of a building into an excavation pit filled with groundwater
DE1634027B2 (en) BREAKERS
EP1426495A2 (en) Method and device for the construction of a tunnel or a trench
DE102010006458A1 (en) Method and installation arrangement with a flat foundation
EP0514559B1 (en) Transfer of building load via a steelmember, to the ground, by use of a special ramhead
EP1707685A2 (en) Foundation for a high water barrier
DE3338652C2 (en) Method for constructing an underwater tunnel
DE2754577A1 (en) Conveyor installation method - by excavating for foundations, then casting in whilst support members are held up in position
DE1634531A1 (en) Process for the production of retaining walls using prefabricated concrete walls
AT317092B (en) Process for the production of a trough arranged in the ground below the groundwater level and for this purpose prefabricated reinforced concrete girders for their production
EP0056422A1 (en) Process and falsework for constructing bridges of reinforced concrete
CH245930A (en) Pressed concrete construction process for the production of building structures under water.
DE3716750A1 (en) Method of constructing and sinking foundation structures
DE1915091A1 (en) Method and device for the production of channels using the diaphragm wall method
AT388008B (en) Method of constructing a retaining dam for a river power plant, and retaining dam produced by the method

Legal Events

Date Code Title Description
OAV Applicant agreed to the publication of the unexamined application as to paragraph 31 lit. 2 z1
8122 Nonbinding interest in granting licenses declared
8127 New person/name/address of the applicant

Owner name: LAMMERS, ALBERT, 4400 MUENSTER, DE

8133 Disposal/non-payment of the application fee