EP0514559B1 - Transfer of building load via a steelmember, to the ground, by use of a special ramhead - Google Patents
Transfer of building load via a steelmember, to the ground, by use of a special ramhead Download PDFInfo
- Publication number
- EP0514559B1 EP0514559B1 EP91108024A EP91108024A EP0514559B1 EP 0514559 B1 EP0514559 B1 EP 0514559B1 EP 91108024 A EP91108024 A EP 91108024A EP 91108024 A EP91108024 A EP 91108024A EP 0514559 B1 EP0514559 B1 EP 0514559B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- concrete
- course
- crushed
- stone
- excavated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
Definitions
- an area (a) is excavated approximately two meters deep; now several trenches, approximately 1.20 meters wide and two to three meters deep (depending on the nature of the soil) are dug (b); (Fig. 1) on the bottom of a gravel layer is introduced.
- a layer of concrete is then placed on top of this and then a layer of gravel, which is compacted again with the fall bear.
- the steel girders are integrated into a reinforced base plate that extends to the top of the terrain.
- Figure 1 shows the construction measure according to the invention.
- an area (a) is excavated approximately two meters deep; now several trenches, approximately 1.20 meters wide and two to three meters deep (depending on the nature of the soil) are dug (b); a layer of gravel is placed on the bottom of the gravel.
- a layer of concrete is then placed on top of this and then a layer of gravel, which is compacted again with the fall bear.
- the strong horizontal compression creates an unimaginable thrust in the direction of the tower, which prevents the tower from moving in the direction of the fall.
- the steel beams fully absorb the load from above. The load is distributed over a large area.
- the concrete beams which are under great tension, ensure that the steel beams have a load capacity that goes far beyond the requirements.
- the fields between the concrete beams are compacted by driving in ballast so that the very high load-bearing capacity of the construction is increased even further.
- slots are made in the foundation at the level of the slab, into which concrete and iron penetrate when the slab is cast. This relieves the steel beams considerably and creates an even stronger connection between the tower and the reinforced concrete slab.
- This foundation system is, of course, also suitable for buildings that sit evenly (Cologne Cathedral).
- the system can also be used for non-load-bearing building ground, since every building ground, even the worst, can be compacted into a load-bearing element.
Abstract
Description
In Neigungsrichtung eines Turmes wird eine Fläche (a) ca. zwei Meter tief ausgehoben;
nun werden mehrere Gräben, ca. 1,20 Meter breit und zwei bis drei Meter tief (je nach Bodenbeschaffenheit) ausgehoben (b); (Fig. 1) auf deren Boden wird eine Schotterschicht eingebracht.In the direction of inclination of a tower, an area (a) is excavated approximately two meters deep;
now several trenches, approximately 1.20 meters wide and two to three meters deep (depending on the nature of the soil) are dug (b); (Fig. 1) on the bottom of a gravel layer is introduced.
Dieselbe wird mit dem Fallbär solange in den Untergrund gerammt, bis die Verdichtung so stark ist, daß sich der Schotter beginnt zu Staub zu zermahlen. Damit ist nahezu die Tragfähigkeit von gewachsenem Fels erreicht.The same is rammed into the ground with the fall bear until the compaction is so strong that the ballast begins to grind to dust. This means that the load capacity of grown rock is almost reached.
Nun wird eine Fertigbetonschicht aufgebracht; auf diese kommt wiederum eine Schotterschicht, die wieder mit dem Fallbär in die Betonschicht eingerammt wird.Now a precast concrete layer is applied; on top of this comes a layer of gravel, which is then rammed into the concrete layer with the fall bear.
Darauf wird wieder eine Betonschicht und darauf wieder eine Schotterschicht, die wieder mit dem Fallbär verdichtet wird, aufgebracht.A layer of concrete is then placed on top of this and then a layer of gravel, which is compacted again with the fall bear.
Das wird solange wiederholt, bis der Graben mit dem stehengebliebenem Land eine Ebene bildet.This is repeated until the trench forms a level with the land that has remained.
Auf diesen Betonkörper (b) werden nun Stahlträger in beliebiger Anzahl und Stärke gelegt und mit dem einen Ende in das Fundament des Turmes einbetoniert (c).Steel beams of any number and strength are now placed on this concrete body (b) and one end is concreted into the foundation of the tower (c).
Um eine tragende Einheit zu erhalten, werden die Stahlträger in eine armierte Bodenplatte eingebunden, die bis zu Geländeoberkante reicht.To obtain a load-bearing unit, the steel girders are integrated into a reinforced base plate that extends to the top of the terrain.
Nachdem der schiefe Turm von Pisa immer schiefer wird, also umzufallen droht, habe ich mich entschlossen, mit Hilfe meiner Erfindung "Fallbär" Patenturkunde Nr. 1 634 348 vom 08.12.1967 des Deutschen Patentamtes und einem von mir entwickeltem Gründungssystems, den Turm vor dem Verfall zu bewahren! Diese Aufgabe wird erfindungsgemäß durch den Merkmalen des Anspruchs gelöst wobei FR-A-2079 884, welche als nächstliegender Stand der Technik zu betrachten ist, ein Bauverfahren beschreibt, entsprechend dem Oberbegriff des Patentanspruches.Since the leaning tower of Pisa is always leaning, so it threatens to topple over, I decided with the help of my invention "Fallbär" patent certificate No. 1 634 348 from 08.12.1967 of the German Patent Office and a foundation system developed by me, the tower in front of the To preserve decay! This object is achieved according to the invention by the features of the claim, wherein FR-A-2079 884, which is the closest prior art, describes a construction method according to the preamble of the claim.
Figur 1 stellt die erfindungsgemäße Baumaßnahme dar.Figure 1 shows the construction measure according to the invention.
Dazu sind folgende Arbeitsgänge notwendig, die als Patentansprüche angemeldet sind.The following operations are necessary for this, which are registered as patent claims.
In Neigungsrichtung des Turmes wird eine Fläche (a) ca. zwei Meter tief ausgehoben;
nun werden mehrere Gräben, ca. 1,20 Meter breit und zwei bis drei Meter tief (je nach Bodenbeschaffenheit) ausgehoben (b);
auf deren Boden wird eine Schotterschicht eingebracht.In the direction of inclination of the tower, an area (a) is excavated approximately two meters deep;
now several trenches, approximately 1.20 meters wide and two to three meters deep (depending on the nature of the soil) are dug (b);
a layer of gravel is placed on the bottom of the gravel.
Dieselbe wird mit dem Fallbär solange in den Untergrund gerammt, bis die Verdichtung so stark ist, daß sich der Schotter beginnt zu Staub zu zermahlen. Damit ist nahezu die Tragfähigkeit von gewaschsenem Fels erreicht.The same is rammed into the ground with the fall bear until the compaction is so strong that the ballast begins to grind to dust. This almost reaches the load-bearing capacity of washed rock.
Nun wird eine Fertigbetonschicht aufgebracht auf diese kommt wiederum eine Schotterschicht, die wieder mit dem Fallbär in die Betonschicht eingerammt wird.Now a ready-mixed concrete layer is applied to this, in turn there is a layer of gravel, which is rammed into the concrete layer again with the fall bear.
Darauf wird wieder eine Betonschicht und darauf wieder eine Schotterschicht, die wieder mit dem Fallbär verdichtet wird, aufgebracht.A layer of concrete is then placed on top of this and then a layer of gravel, which is compacted again with the fall bear.
Mit diesem System ist es möglich, ohne den Turm zu gefährden, ein unter unvorstellbarer Spannung stehendes Schottergerüst, welches sich mit dem Fertigbeton verbindet, herzustellen.With this system, it is possible, without endangering the tower, to create an unimaginably stressed ballast scaffold that connects to the prefabricated concrete.
Auf diesen Betonkörper (b) werden nun Stahlträger in beliebiger Anzahl und Stärke gelegt und mit dem einen Ende in das Fundament des Turmes einbetoniert (c). Damit das Baumaterial des Turmes nicht beschädigt wird, werden oberhalb und unterhalb der Stahlträger Stahlplatten eingelegt. Zwischen die obere Platte und dem Träger wird ein Flachstahlkeil angebracht. Nach Abbinden des Betons kann damit dann die notwendige Spannung erzeugt werden.Steel beams of any number and strength are now placed on this concrete body (b) and one end is concreted into the foundation of the tower (c). So that the building material of the tower is not damaged, steel plates are inserted above and below the steel beams. A flat steel wedge is placed between the top plate and the beam. After the concrete has set, the necessary tension can then be generated.
Nun wird über das Ganze eine starke armierte Betonplatte gegossen, welche die Stahlträger einbindet und das Ganze zusammen mit den Betonträgern (b) eine tragende Einheit bildet.Now a strong, reinforced concrete slab is poured over the whole, which ties in the steel girders and forms a load-bearing unit together with the concrete girders (b).
Durch die starke horizontale Verdichtung entsteht in Richtung Turm eine unvorstellbare Schubwirkung, welche verhindert, daß sich der Turm in Fallrichtung verschieben kann. Die Last von oben wird von den Stahlträgern voll aufgefangen. Die Last wird auf eine große Fläche verteilt. Die unter großer Spannung stehenden Betonträger sichern den Stahlträgern eine weit über die Erfordernisse hinausgehende Tragkraft. Die Betonplatte, verbunden mit den Betonträgern, umfaßt den Turm und läßt ihn keinen Millimeter seitwärts abtriften.The strong horizontal compression creates an unimaginable thrust in the direction of the tower, which prevents the tower from moving in the direction of the fall. The steel beams fully absorb the load from above. The load is distributed over a large area. The concrete beams, which are under great tension, ensure that the steel beams have a load capacity that goes far beyond the requirements. The concrete slab, connected to the concrete girders, surrounds the tower and does not allow it to drift sideways.
Um die Tragkraft der Stahlbetonplatte weiter zu erhöhen, werden die Felder zwischen den Betonbalken durch Einrammen von Schotter so verdichtet, daß die sehr hohe Tragfestigkeit der Konstruktion noch weiter erhöht wird. Um die Tragfähigkeit der Platte direkt auf den Turm zu übertragen, werden in Höhe der Platte Schlitze in das Fundament eingeschlagen, in welche beim Verguß der Platte Beton und Eisen eindringen. Dadurch werden die Stahlträger erheblich entlastet und eine noch sträkere Verbindung zwischen Turm und der Stahlbetonplatte hergestellt.In order to further increase the load-bearing capacity of the reinforced concrete slab, the fields between the concrete beams are compacted by driving in ballast so that the very high load-bearing capacity of the construction is increased even further. To transfer the load-bearing capacity of the slab directly to the tower, slots are made in the foundation at the level of the slab, into which concrete and iron penetrate when the slab is cast. This relieves the steel beams considerably and creates an even stronger connection between the tower and the reinforced concrete slab.
Dieses Gründungssystem ist natürlich auch für Bauwerke geeignet, welche sich gleichmäßig setzen (Kölner Dom).This foundation system is, of course, also suitable for buildings that sit evenly (Cologne Cathedral).
Desgleichen ist das System auch für nichttragenden Baugrund zu verwenden, da jeder Baugrund, auch der schlechteste, zu einem tragenden Element verdichtet werden kann.Likewise, the system can also be used for non-load-bearing building ground, since every building ground, even the worst, can be compacted into a load-bearing element.
Claims (10)
- An area of approx. 2.00 m is excavated in line with the inclination of the structures; the amount of soil to be excavated depends on the load cut.
- Several ditches of approx. 1.20 m width and 2.00 to 3.00 m depth, depending on the nature of the soil, are excavated in the cutting area.
- A crushed-stone course is placed onto the bottom of these ditches.
- These crushed-stone courses are compacted with a tamper and rammed into the subsoil until the stability of the layer is comparable to that of natural rock.
- The next step to perform is to introduce a local concrete layer.
- Steps 3,4 and 5 are continued until the layer of the courses is level with the upper border of the ditch.
- Steel girders are placed onto these ditches; their number and size being chosen upon requirements. They must be end-anchored in the foundation of the leaning structure to be held.
- To obtain the highest possible load distribution, steel plates are encased in the foundation concrete.
- Before the concrete between the steel girder and the steel plate starts setting, a steel bar wedge is driven into the concrete to make sure that the required tension is reached.
- The final step is to embed the steel girder in an armoured bottom plate. The plate's upper end has to be level with the surrounding area such as to be able to support the load.
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE59104810T DE59104810D1 (en) | 1991-05-17 | 1991-05-17 | Transfer of the load of a building via steel girders to the surrounding area through the use of a special fall bear. |
AT91108024T ATE119227T1 (en) | 1991-05-17 | 1991-05-17 | TRANSFER OF THE LOAD OF A BUILDING VIA STEEL BEAMS TO THE SURROUNDING AREA BY USING A SPECIAL FALL BEAR. |
EP91108024A EP0514559B1 (en) | 1991-05-17 | 1991-05-17 | Transfer of building load via a steelmember, to the ground, by use of a special ramhead |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP91108024A EP0514559B1 (en) | 1991-05-17 | 1991-05-17 | Transfer of building load via a steelmember, to the ground, by use of a special ramhead |
Publications (2)
Publication Number | Publication Date |
---|---|
EP0514559A1 EP0514559A1 (en) | 1992-11-25 |
EP0514559B1 true EP0514559B1 (en) | 1995-03-01 |
Family
ID=8206736
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP91108024A Expired - Lifetime EP0514559B1 (en) | 1991-05-17 | 1991-05-17 | Transfer of building load via a steelmember, to the ground, by use of a special ramhead |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP0514559B1 (en) |
AT (1) | ATE119227T1 (en) |
DE (1) | DE59104810D1 (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6505998B1 (en) | 1997-08-20 | 2003-01-14 | Global Innovations, Inc. | Ground treatment |
GB2403964B (en) * | 2003-07-18 | 2006-09-27 | Roxbury Ltd | Ground improvement |
US8740501B2 (en) | 2009-06-24 | 2014-06-03 | Geopier Foundation Company, Inc. | Apparatus and method for ground improvement |
US9915050B2 (en) | 2009-06-24 | 2018-03-13 | Geopier Foundation Company, Inc. | Apparatus and method for ground improvement |
MA33383B1 (en) | 2009-06-24 | 2012-06-01 | Geopier Found Co Inc | APPARATUS AND METHOD FOR SOIL IMPROVEMENT |
US8328470B2 (en) * | 2009-06-24 | 2012-12-11 | Geopier Foundation Company, Inc. | Apparatus and method for ground improvement |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3741083A (en) * | 1970-08-26 | 1973-06-26 | V Shakhlin | Compaction device for loose materials or concrete |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1634348C3 (en) * | 1967-12-08 | 1973-10-04 | Kurt 8580 Bayreuth Ellmer | Fallbear for compacting gravel, sand or the like |
FR2079884A5 (en) * | 1970-02-16 | 1971-11-12 | Carlo Di Spirito | |
NL8701654A (en) * | 1987-07-14 | 1989-02-01 | Ballast Nedam Groep Nv | METHOD AND APPARATUS FOR COMPACTING SOIL |
-
1991
- 1991-05-17 AT AT91108024T patent/ATE119227T1/en not_active IP Right Cessation
- 1991-05-17 DE DE59104810T patent/DE59104810D1/en not_active Expired - Fee Related
- 1991-05-17 EP EP91108024A patent/EP0514559B1/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3741083A (en) * | 1970-08-26 | 1973-06-26 | V Shakhlin | Compaction device for loose materials or concrete |
Also Published As
Publication number | Publication date |
---|---|
EP0514559A1 (en) | 1992-11-25 |
DE59104810D1 (en) | 1995-04-06 |
ATE119227T1 (en) | 1995-03-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3195312A (en) | Method for erecting precast retaining wall | |
EP0146592A1 (en) | Prestressed component retaining wall system | |
EP0514559B1 (en) | Transfer of building load via a steelmember, to the ground, by use of a special ramhead | |
US5537788A (en) | System and method for widening a highway and supporting a sound wall | |
DE19930701A1 (en) | Tub construction for an underpass of a traffic route | |
US5123777A (en) | Construction elements | |
AT505789A2 (en) | BARRIER WITH GLUED TRIANGES | |
DE102005013993B3 (en) | Foundation for a flood protection | |
US6877290B2 (en) | Building block | |
DE4440787A1 (en) | Prefabricated support for use on weak or unstable ground | |
KR20020024027A (en) | The length adjustable lagging and its using method of braced wall construction | |
JPH01146020A (en) | Foundation structure by banking and its construction | |
CN1204714A (en) | Method for forming retaining wall | |
DE102005013994B4 (en) | Device for the concentrated introduction of force into unreinforced diaphragm walls in the ground | |
KR20020025856A (en) | Prevention of approach slab settlement by applying non-com paction abutment backfilling method | |
JPH08209704A (en) | Construction of banking | |
DE1634531A1 (en) | Process for the production of retaining walls using prefabricated concrete walls | |
JPH0978613A (en) | Precast interlocking block member | |
JPS5996320A (en) | Improvement of soft ground | |
KR920008713B1 (en) | Construction method and block for prefabricated retaining wall | |
JP3593752B2 (en) | Retaining wall structure and built flat land structure or built road structure on steep slopes | |
Zumrawi et al. | Mechanically Stabilized Earth with Steel Reinforcement | |
RU2202678C2 (en) | Mudflow conduit | |
DE2658890C2 (en) | Basin for settling suspended matter in water, as a filter basin, sludge basin, clarifier or the like | |
DE4445707A1 (en) | Economical removal of same level traffic surfaces |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE CH DE DK ES FR GB GR IT LI LU NL SE |
|
RBV | Designated contracting states (corrected) |
Designated state(s): AT DE ES FR IT |
|
17P | Request for examination filed |
Effective date: 19921223 |
|
17Q | First examination report despatched |
Effective date: 19940202 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT DE ES FR IT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRE;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED.SCRIBED TIME-LIMIT Effective date: 19950301 Ref country code: ES Free format text: THE PATENT HAS BEEN ANNULLED BY A DECISION OF A NATIONAL AUTHORITY Effective date: 19950301 Ref country code: FR Effective date: 19950301 |
|
REF | Corresponds to: |
Ref document number: 119227 Country of ref document: AT Date of ref document: 19950315 Kind code of ref document: T |
|
REF | Corresponds to: |
Ref document number: 59104810 Country of ref document: DE Date of ref document: 19950406 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Effective date: 19950517 |
|
EN | Fr: translation not filed | ||
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed | ||
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 19960924 Year of fee payment: 6 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19980203 |