CN214219987U CN202023066173.3U CN202023066173U CN214219987U CN 214219987 U CN214219987 U CN 214219987U CN 202023066173 U CN202023066173 U CN 202023066173U CN 214219987 U CN214219987 U CN 214219987U
Authority
CN
China
Prior art keywords
embedded
sleeve
jib
connecting device
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023066173.3U
Other languages
Chinese (zh)
Inventor
夏儒懂
黄路遥
石绍鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202023066173.3U priority Critical patent/CN214219987U/en
Application granted granted Critical
Publication of CN214219987U publication Critical patent/CN214219987U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides a jib connecting device, including embedded bar and the embedded sleeve of connection on embedded bar, be equipped with the connecting portion that are used for connecting the jib in the embedded sleeve. The utility model discloses a set up pre-buried sleeve, and set up the connecting portion of connecting the jib in pre-buried sleeve, be convenient for in the construction of the fire-fighting equipment and the ventilation system in later stage, connect the jib in pre-buried sleeve, not only avoided drilling to lead to the damage of structure floor and the possibility of destroying the pre-buried pipeline, still avoided causing later stage infiltration, and construction convenience, swift, can practice thrift the time limit for a project, reduce with the construction influence of other work types little; the embedded steel bars are connected with the embedded sleeves, so that the embedded sleeves are anchored more firmly; through setting up pre-buried fixed steel sheet, be convenient for with this connecting device location installation on concrete placement template to it is pre-buried firm to ensure jib connecting device.

Description

Suspender connecting device
Technical Field
The utility model relates to a building technical field especially relates to a jib connecting device.
Background
Nowadays, pouring fire-fighting facilities and ventilation system engineering are prevalent in China's construction industry, and the application is relatively common, and the suspender is connected by inserting expansion bolts into the rear drill holes in the construction process. Due to the fact that the rear-mounted drill holes are adopted, damage to the first pair of structural floors, particularly drilling holes in the floors of wading rooms, easily causes drilling cracks on the floors, and causes later-stage water seepage; the second post-drilled hole may cause damage to the pipeline of the pre-buried floor, which affects the laying of the cable.
SUMMERY OF THE UTILITY MODEL
To foretell technical problem, the utility model provides a jib connecting device for the structure of connecting the jib among the solution prior art causes the problem of later stage infiltration easily.
In order to achieve the above purpose, the technical solution of the present invention is realized as follows:
the utility model provides a jib connecting device, includes embedded bar and the embedded sleeve of connection on embedded bar, is equipped with the connecting portion that are used for connecting the jib in the embedded sleeve.
Further, the connecting portion is an internal thread hole, and the internal thread hole is matched with the external thread of the suspender.
Furthermore, the embedded steel bars are L-shaped steel bars, and one side of each L-shaped steel bar is fixedly connected with the embedded sleeve in a welding mode.
Furthermore, the number of the embedded steel bars is at least two, and the embedded steel bars are symmetrically connected to the embedded sleeve.
Furthermore, an embedded fixed steel plate is connected to the embedded sleeve.
Further, the embedded fixed steel plate is sleeved on the embedded sleeve.
Furthermore, the embedded fixed steel plate is provided with embedded steel nails in a penetrating way.
The utility model has the advantages that: the utility model discloses a set up pre-buried sleeve to set up the connecting portion of connecting the jib in pre-buried sleeve, be convenient for in the setting construction of fire-fighting equipment and ventilation system in later stage, connect the jib in pre-buried sleeve, not only avoided drilling to lead to the damage of structure floor and the possibility of destroying pre-buried pipeline, still avoided causing later stage infiltration, and construction convenience, swift, can practice thrift the time limit for a project, and reduce with the construction influence of other worker types little; the embedded steel bars are connected with the embedded sleeves, so that the embedded sleeves are anchored more firmly; through setting up pre-buried fixed steel sheet, be convenient for with this connecting device location installation on concrete placement template to it is pre-buried firm to ensure jib connecting device.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a rear view of FIG. 1;
fig. 3 is a side view of the outer form of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without any creative effort belong to the protection scope of the present invention.
As shown in fig. 1-fig. 3, a suspender connecting device, including embedded bar 1 and embedded sleeve 2 of connection on embedded bar 1, be equipped with the connecting portion that are used for connecting jib 5 in embedded sleeve 2. The corresponding hanger rods 5 and the matched embedded sleeves 2 are selected according to the pipe diameters of the spraying or air pipe, and the length of the embedded sleeves 2 is cut according to the thickness of the protective layer on the upper portion of the floor slab. Embedded steel bar 1 is the angle with embedded sleeve 2 and is connected, in this embodiment, embedded steel bar 1 is connected with embedded sleeve 2 is perpendicular, make embedded sleeve 2 anchored more firm, through set up the connecting portion of connecting jib 5 in embedded sleeve 2, be convenient for in the fire-fighting equipment in later stage and ventilation system's the setting construction, connect jib 5 in embedded sleeve 2, not only avoided drilling to lead to the damage of structure floor and the possibility of destroying the embedded pipeline, still avoid causing the later stage infiltration, and construction convenience, swiftly, can practice thrift the time limit for a project and can reduce the construction influence with other types of industry little.
Further, as shown in fig. 2, in this embodiment, the connection portion is an internal thread hole, and the internal thread hole is matched with the external thread of the suspension rod 5, so that the connection is convenient and the reliability is high through threaded connection.
Further, as shown in fig. 1, the embedded steel bars 1 are L-shaped steel bars, one side of each L-shaped steel bar is fixedly connected with the embedded sleeve 2, the connection area between the embedded steel bars 1 and the embedded sleeve 2 is increased, and the firmness and stability are increased.
Further, as shown in fig. 3, embedded steel bars 1 are provided with at least two, and embedded steel bars 1 are symmetrically connected to the side of embedded sleeve 2, and in this embodiment, two embedded steel bars 1 are provided, and two embedded steel bars are symmetrically welded and connected to two sides of embedded sleeve 2.
Further, as shown in fig. 1, the pre-buried sleeve 2 is connected with a pre-buried fixing steel plate 4, so that the pre-buried stability of the suspender connecting device is ensured.
Further, as shown in fig. 1, the embedded fixing steel plate 4 is sleeved on the embedded sleeve 2, so that the internal thread hole of the embedded sleeve 2 is exposed to facilitate screwing the suspender. In addition, in the concrete pouring process, the ports of the embedded sleeves 2 are plugged by adhesive tapes, so that the embedded sleeves 2 are prevented from being plugged by pouring concrete.
Further, as shown in fig. 1, the embedded steel nails 3 penetrate through the embedded fixed steel plates 4, so that the connecting device can be conveniently positioned and installed on a concrete pouring template, the concrete pouring process is well tracked, construction collision is prevented from falling down, and the concrete is timely centered.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. The utility model provides a jib connecting device, its characterized in that includes embedded bar (1) and connects embedded sleeve (2) on embedded bar (1), is equipped with the connecting portion that are used for connecting jib (5) in embedded sleeve (2).
2. Boom attachment according to claim 1, characterized in that the attachment part is an internally threaded hole which cooperates with an external thread of the boom (5).
3. The boom connecting device as claimed in claim 1 or 2, wherein the embedded steel bar (1) is an L-shaped steel bar, and one side of the L-shaped steel bar is fixedly connected with the embedded sleeve (2) by welding.
4. The boom connecting device as claimed in claim 3, wherein there are at least two embedded bars (1), and the embedded bars (1) are symmetrically connected to the embedded sleeve (2).
5. Boom connection according to claim 1, 2 or 4, c h a r a c t e r i z e d in that a pre-embedded fixing steel plate (4) is connected to the pre-embedded sleeve (2).
6. The boom connecting device as claimed in claim 5, wherein the pre-embedded fixed steel plate (4) is sleeved on the pre-embedded sleeve (2).
7. The boom connecting device as claimed in claim 6, wherein the pre-embedded steel nails (3) are arranged on the pre-embedded fixed steel plate (4) in a penetrating way.
CN202023066173.3U 2020-12-18 2020-12-18 Suspender connecting device Active CN214219987U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023066173.3U CN214219987U (en) 2020-12-18 2020-12-18 Suspender connecting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023066173.3U CN214219987U (en) 2020-12-18 2020-12-18 Suspender connecting device

Publications (1)

Publication Number Publication Date
CN214219987U true CN214219987U (en) 2021-09-17

Family

ID=77703258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023066173.3U Active CN214219987U (en) 2020-12-18 2020-12-18 Suspender connecting device

Country Status (1)

Country Link
CN (1) CN214219987U (en)

Similar Documents

Publication Publication Date Title
CN103161313B (en) Connection method of main reinforcement of constructional column of infilled wall and framed girder
CN111236416A (en) Prefabricated reinforced concrete structure house and installation method thereof
CN214219987U (en) Suspender connecting device
WO2020103351A1 (en) Bailey support system applied to crossed protection of complicated pipe cable and construction method therefor
CN206345617U (en) Building tower crane attachment device is received in a kind of
CN110112681B (en) Modular cable hoist and mount lays auxiliary device
CN102605945B (en) Manufacturing method of big wood formwork
CN212376009U (en) Prefabricated assembled reinforced concrete structure house
CN211369529U (en) A template for expansion joint department
CN212670862U (en) Open type wall connecting box
CN210797531U (en) Ground is wall anchor muscle protection architecture even
CN105888055A (en) External wall panel installation node
CN112942777A (en) Ultrahigh-layer periphery protection cyclic telescopic detachable cantilever structure and mounting method
CN207392189U (en) A kind of assembled sealing up screw reinforces one side formwork structure
CN207228643U (en) A kind of new cover to reinforcement fixture
CN217106161U (en) Assembled building aluminum mould board strutting arrangement
CN210032125U (en) Accurate positioning device for tower crane attached through-wall bolt
CN210736046U (en) Temporary access passage of tower crane
CN205046829U (en) Shaped steel draws wire rope turnover formula anchor to one side
CN113738139A (en) Corridor embedded-hanging type turnover vertical face protection tool and construction method thereof
CN216196520U (en) I-steel positioning and clamping device
CN218292762U (en) Pre-buried screw even wall spare
CN214423970U (en) Adjustable corner wall connecting piece structure
CN210152266U (en) Wall pre-embedding fixing device
CN215055559U (en) Roof steel beam installation protection structure of electronic factory building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant