Prefabricated assembled reinforced concrete structure house Download PDFInfo
- Publication number
- CN212376009U CN212376009U CN202020336162.3U CN202020336162U CN212376009U CN 212376009 U CN212376009 U CN 212376009U CN 202020336162 U CN202020336162 U CN 202020336162U CN 212376009 U CN212376009 U CN 212376009U
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- wallboard
- floor
- prefabricated wallboard
- reinforced concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Panels For Use In Building Construction (AREA)
Abstract
The utility model discloses a prefabricated assembled reinforced concrete structure house, including the foundatin plate, the top of foundatin plate is equipped with prefabricated wallboard, and back inserting stirrup preformed hole and the built-in fitting of lifting by crane have been seted up respectively at the top of prefabricated wallboard, the wallboard connection embedded groove has been seted up to the side of prefabricated wallboard, and the front of prefabricated wallboard is equipped with preformed hole and supports buried bolt in advance respectively, the bottom of prefabricated wallboard is equipped with floor connection built-in fitting, the top of prefabricated wallboard is equipped with prefabricated floor, all be equipped with the spread groove around the prefabricated wallboard, be equipped with the connecting piece in the spread groove, the connecting piece is used for the direct or indirect connection of two adjacent prefabricated wallboards. The utility model discloses a prefabricated wallboard and prefabricated floor all accomplish at the mill's prefabrication, and the job site only need hoist prefabricated component, easy and simple to handle, quick, and a whole set of nodal connection method construction is simple, and the node atress is reasonable, and the stability in house is good, can satisfy diversified demand.
Description
Technical Field
The utility model relates to the technical field of building, specifically be a prefabricated assembled reinforced concrete structure house.
Background
The building refers to an asset formed by artificial construction, belongs to the category of fixed assets, and comprises two categories of houses and constructions, wherein the houses refer to engineering buildings for people to live, work, study, produce, manage, entertain, store articles and perform other social activities. The prefabricated reinforced concrete structure house is different from a building, and the building refers to engineering buildings except a house, such as enclosing walls, roads, dams, wells, tunnels, water towers, bridges, chimneys and the like.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a prefabricated assembled reinforced concrete structure house to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a prefabricated reinforced concrete structure house, includes the foundatin plate, the top of foundatin plate is equipped with prefabricated wallboard, the top of prefabricated wallboard is equipped with prefabricated floor, all be equipped with the spread groove around the prefabricated wallboard, be equipped with the connecting piece in the spread groove, prefabricated floor's top is equipped with the back and inserts the stirrup.
Preferably, the connecting member is used for direct or indirect connection of two adjacent prefabricated wall panels or connection of a prefabricated wall panel and a prefabricated floor slab.
Preferably, the top of the prefabricated wallboard is respectively provided with a rear stirrup preformed hole and a hoisting embedded part, and the side surface of the prefabricated wallboard is provided with a wallboard connecting embedded groove.
Preferably, the front of the prefabricated wall board is respectively provided with a reserved electric hole and a supporting embedded bolt, and the bottom of the prefabricated wall board is provided with a floor slab connecting embedded part.
Compared with the prior art, the beneficial effects of the utility model are as follows:
the utility model discloses a prefabricated wallboard and prefabricated floor all accomplish at the mill's prefabrication, and the job site only need hoist prefabricated component, easy and simple to handle, quick, and a whole set of nodal connection method construction is simple, and the node atress is reasonable, and the holistic stability in house is good, and is safe in utilization, can satisfy diversified demand.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a horizontal sectional view of the prefabricated wall panel of the present invention;
figure 3 is the utility model discloses the side elevation of prefabricated wallboard picture.
In the figure: the prefabricated wallboard comprises a foundation plate 1, a prefabricated wallboard 2, a rear stirrup preformed hole 21, a hoisting embedded part 22, a wallboard connecting embedded groove 23, a reserved electric hole 24, a supporting embedded bolt 25, a floor connecting embedded part 26, a prefabricated floor 3, a connecting groove 4, a connecting part 5 and a rear stirrup 6.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The first embodiment is as follows:
referring to fig. 1 to 3, a prefabricated assembly type reinforced concrete structure house includes a foundation plate 1, the top of the foundation plate 1 is provided with a prefabricated wall plate 2, the top of the prefabricated wall plate 2 is respectively provided with a rear stirrup preformed hole 21 and a lifting embedded part 22, the side surface of the prefabricated wall plate 2 is provided with a wall plate connecting embedded groove 23, the front surface of the prefabricated wall plate 2 is respectively provided with a reserved electric hole 24 and a supporting embedded bolt 25, the bottom of the prefabricated wall board 2 is provided with a floor slab connecting embedded part 26, the top of the prefabricated wall board 2 is provided with a prefabricated floor slab 3, the periphery of each prefabricated wall panel 2 is provided with connecting grooves 4, connecting pieces 5 are arranged in the connecting grooves 4, the connecting pieces 5 are used for directly or indirectly connecting two adjacent prefabricated wall panels 2, or the prefabricated wall plate 2 is connected with the prefabricated floor slab 3, and the top of the prefabricated floor slab 3 is provided with a rear stirrup 6.
In this embodiment, the prefabricated concrete wall panel is constructed in the following manner:
1. the both sides of prefabricated wallboard 2 reserve logical long spread groove 4 when prefabricated, are convenient for adopt to lead to long special shaped steel to carry out the connection between the prefabricated wallboard 2.
2. The upper portion of prefabricated wallboard 2 is through the spread groove 4 of reserving, is convenient for adopt special shaped steel to carry out being connected between prefabricated wallboard 2 and the prefabricated floor 3.
3. The lower part of prefabricated wallboard 2 is convenient for adopt special shaped steel to carry out the fixed between prefabricated wallboard 2 and foundatin plate 1 or prefabricated floor 3 through the spread groove 4 of reserving.
The installation method of the prefabricated building comprises the following steps:
1. lay prefabricated wallboard 2 in proper order, fixed prefabricated wallboard 2 bottom and foundatin plate 1's connection.
2. And after the connecting pieces 5 of the prefabricated wall boards 2 are sequentially placed, the bonding agent is poured into the joints.
3. After the prefabricated floor slab 3 is placed in sequence, the prefabricated floor slab 3 and the prefabricated wall slab 2 are installed to connect the stirrups.
4. And (3) pouring adhesive into the joint of the prefabricated floor slab 3 and the prefabricated wall plate 2.
The prefabricated concrete structure house node connecting method comprises the following steps:
(1) connection form of adjacent prefabricated wall panels 2:
a. the end parts of the adjacent prefabricated wall boards 2 are vertically connected by adopting rigid connection, the end parts of the prefabricated wall boards 2 are fixed by reserving connecting grooves 4 and special section steel, and then cement-based bonding materials are poured into the connecting grooves to form integral rigid joints.
b. Adjacent prefabricated wallboard 2's lug connection adopts flexonics, and is fixed through pre-buried special shaped steel and the high strength bolt in prefabricated wallboard 2's junction reservation spread groove 4, forms flexible node, can make prefabricated wallboard 2Z direction unidirectional movement in the space coordinate system.
c. The indirect connection of the adjacent prefabricated inner wallboards adopts the rigid connection of the prefabricated connecting beams to connect the two prefabricated wallboards 2, and the special prefabricated section steel at the end part of the prefabricated connecting beams and the embedded parts on the upper parts of the prefabricated wallboards 2 are fixed by high-strength bolts to form rigid joints.
(2) Prefabricated wallboard 2 and prefabricated floor 3 or the connected form of foundatin plate 1:
a. the bottom of the prefabricated inner wallboard is flexibly connected with a floor slab or a foundation, and is fixed through special section steel and high-strength bolts in the reserved groove at the bottom of the prefabricated wallboard 2 to form a flexible joint, so that the prefabricated wallboard 2 can move in two directions of an X, Y shaft in a horizontal coordinate system.
b. The bottom of the prefabricated external wall panel is flexibly hinged with the floor slab or the foundation, and the prefabricated external wall panel is fixed by special section steel and high-strength bolts in the reserved groove at the bottom of the prefabricated wall panel 2 to form a flexible joint, so that the prefabricated wall panel 2 can move in one direction in the X-axis or Y-axis direction in a horizontal coordinate system.
c. The upper part of the prefabricated wall panel 2 is rigidly connected with the floor slab, stirrups are inserted into the reserved holes of the prefabricated wall panel 2 and the prefabricated floor slab 3 for fixing, and then cement-based bonding materials are poured into the holes to form an integral rigid joint.
(3) The connection form of the precast floor slab 3 and the precast floor slab 3 is as follows:
the connection of adjacent prefabricated floor slabs 3 adopts rigid connection, connecting grooves 4 and special section steel are reserved at the end parts of the prefabricated floor slabs 3 for fixing, and then cement-based bonding materials are poured to form integral rigid joints.
The utility model discloses a prefabricated wallboard 2 and prefabricated floor 3 all accomplish at the mill's prefabrication, and the job site only need hoist prefabricated component, easy and simple to handle, quick, and a whole set of nodal connection method construction is simple, and the node atress is reasonable, and the holistic stability in house is good, and is safe in utilization, can satisfy diversified demand.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (4)
1. The utility model provides a prefabricated assembled reinforced concrete structure house, includes foundatin plate (1), its characterized in that: the top of foundatin plate (1) is equipped with prefabricated wallboard (2), the top of prefabricated wallboard (2) is equipped with prefabricated floor (3), all be equipped with spread groove (4) around prefabricated wallboard (2), be equipped with connecting piece (5) in spread groove (4), the top of prefabricated floor (3) is equipped with back and inserts stirrup (6).
2. A prefabricated assembled reinforced concrete structural house according to claim 1, wherein: the connecting piece (5) is used for directly or indirectly connecting two adjacent prefabricated wall boards (2) or connecting the prefabricated wall boards (2) and the prefabricated floor slabs (3).
3. A prefabricated assembled reinforced concrete structural house according to claim 1, wherein: the prefabricated wall panel is characterized in that a rear stirrup preformed hole (21) and a hoisting embedded part (22) are respectively formed in the top of the prefabricated wall panel (2), and a wall panel connecting embedded groove (23) is formed in the side surface of the prefabricated wall panel (2).
4. A prefabricated assembled reinforced concrete structural house according to claim 1, wherein: the front of prefabricated wallboard (2) is equipped with reserved electric hole (24) and supports pre-buried bolt (25) respectively, the bottom of prefabricated wallboard (2) is equipped with floor connection built-in fitting (26).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020336162.3U CN212376009U (en) | 2020-03-17 | 2020-03-17 | Prefabricated assembled reinforced concrete structure house |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020336162.3U CN212376009U (en) | 2020-03-17 | 2020-03-17 | Prefabricated assembled reinforced concrete structure house |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212376009U true CN212376009U (en) | 2021-01-19 |
Family
ID=74158318
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020336162.3U Active CN212376009U (en) | 2020-03-17 | 2020-03-17 | Prefabricated assembled reinforced concrete structure house |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212376009U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113006269A (en) * | 2021-03-05 | 2021-06-22 | 兰州有色冶金设计研究院有限公司 | Construction method of sandwich earth wall house structure system |
-
2020
- 2020-03-17 CN CN202020336162.3U patent/CN212376009U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113006269A (en) * | 2021-03-05 | 2021-06-22 | 兰州有色冶金设计研究院有限公司 | Construction method of sandwich earth wall house structure system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201217898Y (en) | Concrete prefabricated stairs | |
CN107401217B (en) | A kind of beamless hollow floor-chamber concrete-filled steel tube shear wall combined structure system and method | |
CN105569355B (en) | It is a kind of to include the assembly method of prefabricated components modularization house | |
CN107355077A (en) | A kind of basement barricade single side formwork reinforcing device and method | |
CN111236416A (en) | Prefabricated reinforced concrete structure house and installation method thereof | |
CN103924710A (en) | Steel plate welding node structure of low-layer assembly type composite wall house | |
CN103993679A (en) | Bolt connecting joint structure of low-rise fabricated composite wall house | |
CN109403545B (en) | High-assembly-rate steel pipe concrete frame structure system and connection method | |
CN105275089A (en) | Fully-prefabricated cold-formed steel house modular unit and assembly connection method | |
CN110439291B (en) | Assembly type production construction method suitable for low-rise building | |
CN103741970A (en) | Assembled machining shed for building construction and manufacture and installation method thereof | |
CN212376009U (en) | Prefabricated assembled reinforced concrete structure house | |
CN212376010U (en) | Assembled concrete house structure | |
CN215106121U (en) | One-way superimposed sheet piece department joint construction | |
CN206737200U (en) | A kind of assembled arthitecutral structure system | |
CN214531068U (en) | Assembled steel structure house | |
CN106760059A (en) | A kind of assembled arthitecutral structure system | |
CN207122021U (en) | Assembled bolt connection concrete-filled steel tube shear wall | |
CN115977278A (en) | Assembled light steel combined truss supported steel wire mesh frame mortar-perlite-polyphenyl composite shear wall and manufacturing method thereof | |
CN214364235U (en) | Assembled steel sheet compound shear wall body structure | |
CN215802289U (en) | Module connecting system for lightweight concrete modular integrated structure | |
CN206769199U (en) | After wear formula post stretching vertical prestressing cast-in-place concrete rod structure | |
CN103993672A (en) | Tenon type connecting joint structure of low-rise fabricated composite wall house | |
CN210421398U (en) | Assembled house system | |
CN112227580A (en) | Steel pipe truss prestressed hollow superimposed sheet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||