- wall
- anchor
- ground
- anchor muscle
- anchoring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model discloses a ground is wall anchor muscle protection architecture even, include: the anchor muscle row that the reinforcing cage in even wall, even wall in the ground and the relative both sides limit in even wall upper portion of ground formed the inline row by a plurality of anchor muscle, anchor muscle row form hold even wall super-grouted concrete's outer wall, and anchor muscle row is equipped with the protection device of anchor muscle, including corresponding the planking, the inner panel that set up in anchor muscle row both sides respectively and the anchor nail of connecting planking, inner panel. The utility model has the advantages that: the plate body of the protection structure is made of corrosion-resistant materials such as PE or PP, the anchoring ribs are isolated from the diaphragm wall super-poured concrete through the inner plate and the outer plate, the diaphragm wall super-poured concrete loses bond force on the diaphragm wall anchoring ribs, the aim that diaphragm wall super-poured concrete can be hung and removed without chiseling diaphragm wall super-poured concrete is achieved, the protection structure is simple to manufacture, and factory streamlined production is facilitated.
Description
Technical Field
The utility model belongs to the technical field of pier or subway station ground is wall sheet pile supporting construction even, especially relates to a ground is wall anchor muscle protection architecture even.
Background
The diaphragm wall is mainly applied to diaphragm wall sheet pile wharf structures and subway station supporting structures, the diaphragm wall concrete super-grouting height is generally about 0.5-0.8 m according to the diaphragm wall construction process, and diaphragm wall super-grouting concrete can wrap diaphragm wall anchoring ribs to form large holding force. Before the construction of the upper structure of the diaphragm wall, the diaphragm wall super-poured concrete and the bonding part of the anchoring ribs need to be peeled off, and then the diaphragm wall super-poured concrete is hung. The traditional construction method for stripping diaphragm wall super-poured concrete and anchoring ribs is manual air pick chiseling, and the method has the following defects: a. the anchoring ribs are easy to be damaged by meat biting, repeated bending and the like in the manual chiseling process, so that the bending resistance of the anchoring ribs is reduced; b. the traditional chiseling method needs a large amount of professional special work types, the chiseling efficiency of the diaphragm wall super-filled concrete is low, and the working procedure becomes a key factor for restricting the construction period; c. a large amount of noise and dust are generated in the process of chiseling the diaphragm wall super-filled concrete, so that the civil disturbance event and the environmental pollution are easy to occur, and the safe and civilized construction is not facilitated; the method is characterized in that the method is used for excavating the diaphragm wall super-irrigation concrete for a long time, workers are prone to pneumoconiosis and general vibration occupational diseases, the occupational health of the workers is influenced, and the method is contrary to the people-oriented idea of the country; d. the cost of the drilling personnel for the ground connecting wall super-filled concrete is high.
Disclosure of Invention
For solving the above-mentioned shortcoming, the utility model aims at providing a protect wall anchor muscle even with the ground, can avoid the ground even super-filled concrete of wall to wrap up in the bond of anchor muscle, reduce the ground even wall excavation back ground even the super-filled concrete of wall chiseling the construction process, solved traditional artifical chiseling and removed the ground even the super-filled concrete of wall and easily cause the protection architecture who destroys the difficult problem to the anchor muscle.
In order to achieve the above object, the utility model adopts the following technical scheme: a diaphragm wall anchoring bar protection structure, comprising: the anchor muscle row that the reinforcing cage in even wall, even wall in the ground and the relative both sides limit in even wall upper portion in the ground formed by a plurality of anchor muscle is arranged, the anchor muscle row forms the outer wall that holds even wall super-filled concrete, the anchor muscle row is equipped with the protection device of anchor muscle, the protection device of anchor muscle is including corresponding the planking, the inner panel that set up in anchor muscle row both sides respectively and the anchor nail of connecting planking, inner panel.
The outer plate and the inner plate are respectively and correspondingly provided with a plurality of grooves matched with the anchoring ribs, and the grooves on the outer plate and the inner plate mutually form anchoring holes for containing the anchoring ribs.
The cross section of each groove is semicircular, the two semicircular grooves form a circular anchoring hole, and the diameter of the circular anchoring hole is 2-5mm larger than that of the anchoring rib.
Two connecting anchors are arranged between the outer plate and the inner plate.
And oblique angles are arranged at the contact positions of the outer plate, the inner plate and the diaphragm wall.
The angle of the bevel is 30-45 degrees.
The utility model has the advantages that: the plate body of the protection structure is made of corrosion-resistant materials such as PE or PP, the anchoring ribs are isolated from the diaphragm wall super-poured concrete through the inner plate and the outer plate, the diaphragm wall super-poured concrete loses bond force on the diaphragm wall anchoring ribs, the aim that diaphragm wall super-poured concrete can be hung and removed without chiseling diaphragm wall super-poured concrete is achieved, the protection structure is simple to manufacture, and factory streamlined production is facilitated.
Drawings
FIG. 1 is a schematic view of the protective structure of the anchoring rib of the diaphragm wall of the present invention;
FIG. 2 is a schematic cross-sectional view of FIG. 1;
FIG. 3 is a schematic diagram of the removal of diaphragm wall super-filled concrete;
FIG. 4 is a schematic view of the protection structure of the anchoring rib of the diaphragm wall;
FIG. 4-1 is a schematic front view of an anchoring rib protection structure of the diaphragm wall;
FIG. 4-2 is a schematic side view of the protective structure of the anchoring rib of the diaphragm wall;
fig. 4-3 are schematic top views of the protective structure of the anchorage bar of the diaphragm wall.
In the figure:
1. outer plate 2, inner plate 3, anchor
4. Diaphragm wall reinforcement cage 5, diaphragm wall 6, diaphragm wall super-cast concrete
7. Anchor bar W1, outer plate face W2, outer plate rib
W3, outer plate groove W4, outer plate anchoring hole W5 and outer plate bevel
N1, inner plate surface N2, inner plate rib N3 and inner plate groove
N4, inner plate anchoring hole N5 and inner plate bevel
Detailed Description
The following describes the protection structure of the ground wall anchoring rib according to the present invention with reference to the accompanying drawings.
As shown in fig. 1 to 4, the utility model discloses a ground is wall anchor muscle protection architecture's design thought is that utilize anchor nail 3 to fix planking 1 and inner panel 2 on anchor muscle 7, realize keeping apart anchor muscle 7 and ground even wall super-grouted concrete 6, stop ground even wall super-grouted concrete 6 and wrap up in to anchor muscle 7's bond to realize ground even wall super-grouted concrete and exempt from the purpose that chiseling can hang and remove, improved the efficiency of construction under the circumstances of guaranteeing anchor muscle 7 not chiseling the in-process destruction by ground even wall super-grouted concrete 6, practiced thrift the cost of labor, be favorable to the environmental protection construction.
The local continuous wall anchoring rib protection structure comprises an outer plate 1, an inner plate 2 and an anchor 3; the outer plate 1 comprises an outer plate surface W1, an outer plate rib W2, an outer plate groove W3, an outer plate anchoring hole W4 and an outer plate bevel W5; the inner plate 2 comprises an inner plate surface N1, an inner plate rib N2, an inner plate groove N3, an inner plate anchoring hole N4 and an inner plate bevel N5.
The cross sections of the outer plate groove W3 and the inner plate groove N3 are semicircular, and the diameter of the outer plate groove W3 and the inner plate groove N3 is 2-5mm larger than that of the anchoring rib 7; in order not to influence the lifting of the concrete to the sediment in the concrete pouring process, the angles of the outer plate bevel angle W5 and the inner plate bevel angle N5 are preferably between 30 degrees and 45 degrees.
The utility model discloses a ground is wall anchor muscle protective structure function is realized like this:
1. after the ground-connected wall reinforcement cage 4 is manufactured, the outer plate 1 is placed on the outer side of the ground-connected wall reinforcement cage 4, the inner plate 2 is placed on the inner side of the ground-connected wall reinforcement cage 4, and the anchor bolts 3 connect the outer plate 1 and the inner plate 2 together through the outer plate anchoring holes W4 and the inner plate anchoring holes N4.
2. Planking 1 and inner panel 2 are by anchor 3 anchor back, and planking board rib W2 and inner panel board rib N2 contact, and including planking recess W3 and inner panel recess N3 wrapped up anchor muscle 7, finally protected even wall anchor muscle 7 with ground, avoided even wall super-filled concrete 6 to wrap up in the holding of anchor muscle 7, even wall anchor muscle protection architecture installation is accomplished.
3. Put the groove under the wall reinforcement cage 4 that will install even wall anchor muscle protection architecture, carry out even wall concrete pouring, after even wall concrete reaches excavation strength, with even wall super-filled concrete 6 excavate, demolish anchor nail 3 earlier, demolish planking 1 again, then hang even wall super-filled concrete 6 and remove, reduced even wall 5 excavation like this and even wall 6 chisel of even wall super-filled concrete and removed the construction process, solved traditional artifical chisel and removed even wall super-filled concrete 6 and easily caused the difficult problem of destruction to the anchor muscle.
The ground is wall anchor muscle protection architecture even notices following main points in the use:
1. the protective structure should have certain rigidity and strength to meet the requirements of field installation, hoisting and concrete pouring;
2. the protection structure should be far away from a fire source and a high-temperature area in the processes of storage, transportation and use, so as to prevent thermal deformation.
3. The influence of wind load on lifting must be considered when the ground is connected the wall steel reinforcement cage 4 and the ground is connected the wall anchor muscle protection architecture as whole and lifts by crane.
4. Avoid colliding with to ground even wall anchor muscle protection architecture at the in-process of lifting by crane of ground even wall steel reinforcement cage 4, prevent that ground even wall anchor muscle protection architecture from warping and losing the guard action.
Claims (6)
1. A diaphragm wall anchoring bar protection structure, comprising: ground is even steel reinforcement cage (4) in wall (5), ground even wall (5) and ground even wall (5) upper portion opposite sides limit by the anchor muscle row of a word arrangement that a plurality of anchor muscle (7) formed, anchor muscle row forms the outer wall that holds ground even wall super-filled concrete (6), characterized by: the anchor rib row is provided with a protection device of an anchor rib (7), and the protection device of the anchor rib (7) comprises an outer plate (1) and an inner plate (2) which are correspondingly arranged on two sides of the anchor rib row respectively and an anchor nail (3) for connecting the outer plate and the inner plate.
2. The ground connection wall anchoring rib protection structure as claimed in claim 1, wherein: the anchor plate is characterized in that a plurality of grooves matched with the anchor ribs (7) are correspondingly arranged on the outer plate (1) and the inner plate (2) respectively, and the grooves in the outer plate (1) and the inner plate (2) form anchor holes for accommodating the anchor ribs (7) mutually.
3. The ground connection wall anchoring rib protection structure as claimed in claim 2, wherein: the cross section of each groove is semicircular, the two semicircular grooves form a circular anchoring hole, and the diameter of the circular anchoring hole is 2-5mm larger than that of the anchoring rib (7).
4. The ground-connecting wall anchoring bar protection structure according to claim 1 or 2, characterized in that: two connecting anchors (3) are arranged between the outer plate (1) and the inner plate (2).
5. The ground-connecting wall anchoring bar protection structure according to claim 1 or 2, characterized in that: the contact positions of the outer plate (1), the inner plate (2) and the ground connecting wall (5) are provided with oblique angles.
6. The underground diaphragm wall anchoring rib protection structure of claim 5, which is characterized in that: the angle of the bevel is 30-45 degrees.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921130457.9U CN210797531U (en) | 2019-07-18 | 2019-07-18 | Ground is wall anchor muscle protection architecture even |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921130457.9U CN210797531U (en) | 2019-07-18 | 2019-07-18 | Ground is wall anchor muscle protection architecture even |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210797531U true CN210797531U (en) | 2020-06-19 |
Family
ID=71241548
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921130457.9U Active CN210797531U (en) | 2019-07-18 | 2019-07-18 | Ground is wall anchor muscle protection architecture even |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210797531U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110295589A (en) * | 2019-07-18 | 2019-10-01 | 天津深基工程有限公司 | Ground-connecting-wall anchor rib protects structure |
-
2019
- 2019-07-18 CN CN201921130457.9U patent/CN210797531U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110295589A (en) * | 2019-07-18 | 2019-10-01 | 天津深基工程有限公司 | Ground-connecting-wall anchor rib protects structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110984004B (en) | Method for dismantling lower supporting structure of bridge | |
CN107419918A (en) | A kind of Historical Buildings periphery single-layer frame retains method for dismounting | |
CN203487803U (en) | Safety protection structure for elevator shaft construction | |
CN111271121A (en) | Shield tunnel segment dismantling construction method | |
CN210797531U (en) | Ground is wall anchor muscle protection architecture even | |
CN107142954B (en) | Steel hanging box lifting system for integral lifting and lifting method thereof | |
CN209585054U (en) | Be used for foundation ditch to speedily carry out rescue work emergent bracing fast | |
CN103615253B (en) | Shield cutter service work well suspension device and equipment | |
CN205348724U (en) | Detachable wire rope rings anchor structure of external scaffolding of encorbelmenting | |
CN211621598U (en) | A foundation ditch structure for hole passes steel pipe installation | |
CN203049577U (en) | Complete recovery type non-grouting anchor grasping anchor cable timbering structure | |
CN218029036U (en) | Protection structure for construction on inclined plate | |
CN216194967U (en) | Earth retaining structure for protecting existing tower column | |
JP5903877B2 (en) | Temporary deadline construction method for dam body | |
CN115653373A (en) | Double-spherical hinge support beam column anti-seismic structure system and construction method | |
CN205557785U (en) | A device that is used for tailing storehouse frame -type pumping shaft arch bar to install | |
CN212896438U (en) | Prefabricated assembled tower crane foundation safety protection component | |
CN110295589A (en) | Ground-connecting-wall anchor rib protects structure | |
CN212130145U (en) | Pile hole enclosing device for manual hole digging pile | |
CN204266111U (en) | Deep foundation ditch steel trestle | |
CN212670862U (en) | Open type wall connecting box | |
CN210766816U (en) | Supporting construction for exposing weak objects in high and steep rock slope excavation | |
CN110984003B (en) | Method for removing pier and bearing platform at lower part of river-crossing bridge | |
CN208380053U (en) | Tool-type elevator horizontal protective frame | |
CN202245789U (en) | Special typhoon prevention device for gantry crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |