CN212223633U - Electric climbing hanging basket for high-position small-space operation - Google Patents
Electric climbing hanging basket for high-position small-space operation Download PDFInfo
- Publication number
- CN212223633U CN212223633U CN202020813846.8U CN202020813846U CN212223633U CN 212223633 U CN212223633 U CN 212223633U CN 202020813846 U CN202020813846 U CN 202020813846U CN 212223633 U CN212223633 U CN 212223633U
- Authority
- CN
- China
- Prior art keywords
- hanging basket
- fixed
- steel plate
- space operation
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
An electric climbing hanging basket for high-position small-space operation relates to the field of civil engineering construction mechanical devices. For solving current electronic hanging flower basket that climbs is bulky, can't satisfy and use in less space, in bridge construction work progress, toward the condition that accompanies narrow and small space range construction, can't use electronic hanging flower basket that climbs, can only adopt large-scale crane operation, lead to work efficiency lower, the higher problem of cost. The hanging flower basket frame becomes "V" style of calligraphy form, and the both ends of bearing footboard are equipped with a hanging flower basket frame respectively, and the terminal surface fixed connection of the most advanced of hanging flower basket frame and bearing footboard, and the upper end of two hanging flower basket frames all is equipped with a fixed steel sheet, and the base fixed connection of angle steel and hoist engine is passed through to the upper surface of every fixed steel sheet, is equipped with two dead levers between two fixed plates, and two dead lever parallel arrangement are equipped with a plurality of bracing pieces between two dead levers. The utility model is suitable for a narrow and small space operation in civil engineering construction.
Description
Technical Field
The utility model relates to a civil engineering construction machinery device field, concretely relates to be used for electronic hanging flower basket that climbs of high-order little space operation.
Background
With the rapid development of road and bridge construction cause and economy and the enhancement of comprehensive national force in China, the construction materials, equipment and construction technology in China are rapidly developed. The continuous completion of high-tech bridge works, the construction of Chinese bridges is rapidly advancing. The method is a long-term construction target and task of the railway in China for realizing the railway crossing type development idea of rapidly expanding the transport capacity and rapidly improving the technical equipment level as a main line. Therefore, the bridge construction is often accompanied with the condition of narrow and small space range construction, the traditional construction process adopts large-scale equipment such as cranes for construction, often accompanied with a lot of deficiencies, because the narrow and small machinery of the construction range can not enter, the high altitude position small crane can not satisfy the construction, the adoption of a large-size crane improves the construction cost and may have the restriction conditions such as construction site, and especially when the bridge is constructed in an upper span or a lower crossing bridge, the condition of normal construction can not be satisfied.
In conclusion, the conventional electric climbing hanging basket is large in size and cannot be used in a small space, and in the bridge construction process, the electric climbing hanging basket cannot be used along with the situation of construction in a narrow space range, and only a large crane can be used for operation, so that the problems of low working efficiency and high cost are caused.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a solve present electronic hanging flower basket that climbs and be bulky, can't satisfy and use in less space, in bridge construction work progress, toward the condition that accompanies narrow and small space range construction, can't use electronic hanging flower basket that climbs, can only adopt large-scale crane operation, lead to work efficiency lower, the higher problem of cost, and provide one kind and be used for high-order little space operation electronic hanging flower basket and application method that climbs.
The utility model relates to an electric climbing hanging basket used for high-position small-space operation, which comprises two winches, two hanging basket frames, two fixed steel plates, a bearing pedal, angle steel, a support rod and two fixed rods;
the hanging basket frame is in a V-shaped shape, two ends of the bearing pedal are respectively provided with a hanging basket frame, the tip end of each hanging basket frame is fixedly connected with the end face of the bearing pedal, the upper ends of the two hanging basket frames are respectively provided with a fixed steel plate, the upper surface of each fixed steel plate is fixedly connected with the base of the winch through an angle steel, one end of each fixed steel plate is fixedly connected with one end of a fixed rod, the other end of each fixed rod is fixedly connected with one end of the other fixed steel plate, the other end of each fixed steel plate is fixedly connected with one end of the other fixed rod, the other end of the other fixed rod is fixedly connected with the other end of the other fixed steel plate, the two fixed rods are arranged in parallel, n support rods are arranged between the two fixed rods, n is a;
further, the fixed steel plate is a steel plate with the thickness of 12mm multiplied by 400mm multiplied by 300 mm;
furthermore, the angle steel is 5mm multiplied by 200 mm;
furthermore, the thickness of the bearing pedal is 15-25 mm;
furthermore, the thickness of the bearing pedal is 20 mm;
furthermore, the upper end of the hanging basket frame is connected with the bottom end of the fixed steel plate 3 in a welding mode;
furthermore, the number n of the supporting rods is more than or equal to 3 and less than or equal to 6;
further, when the electric climbing hanging basket is used, the electric climbing hanging basket is conveyed to a construction position to be in place, a power supply is switched on, and a socket (for an electric winch and drilling equipment) is arranged for debugging to ensure normal operation of the hanging basket, a winch hook of the hanging basket is lifted to the top of a frame pier through a steel wire rope, the hanging basket is reliably connected and fixed with an embedded part, the hanging basket is lifted to a stressed state, an operator carries a safety belt to enter the hanging basket in place, and meanwhile, a falling protector is lowered to be firmly connected with a safety belt buckle; drilling equipment is in place, a drainage pipeline and a pier body are connected by adopting an anchor ear and an expansion bolt, one anchor ear is arranged every 2m, the corner part is reinforced, a drilling machine drills a hole to perform expansion screw construction and is temporarily fixed with the anchor ear, and an electric climbing hanging basket performs drilling construction at the next position until the drilling is completed, wherein the length of one UPVC pipe is 6 m; a worker at the top of the frame pier lowers the UPVC pipe to the fixed position of the hoop through a rope, the electric hanging basket is lifted to the position of the hoop, the operator finely adjusts and fixes the UPVC pipe, and all the hoops within the length range of 6m of the UPVC pipe are sequentially fixed; the electric hanging basket descends to the next construction position, and the construction mode is repeated for construction; after one part is installed, the electric hanging basket is descended to the bridge floor of the T-shaped beam, and after the fixing position of the hanging basket at the top of the frame pier is adjusted, the hanging basket is lifted again for subsequent installation of the drainage pipeline; after the installation of a frame pier drainage pipeline is completed, the electric hanging basket descends to a T-shaped beam bridge floor, the falling protector is unfastened, the hanging basket fixing buckle is unfastened, and the hanging basket is carried to the next frame pier by workers for repeated construction to complete the installation of all the frame pier drainage pipelines.
Compared with the prior art, the utility model following beneficial effect has:
one, the utility model overcomes prior art's shortcoming adopts this kind of electronic hanging flower basket device that climbs, is applicable to and builds the less construction environment of bridge, avoids adopting traditional large-scale crane operation, improves work efficiency, and can used repeatedly, practices thrift the cost.
Second, the utility model overcomes prior art's shortcoming, utilize the application method of electronic hanging flower basket that climbs, when establishing the bridge, realize quick construction, improve work efficiency.
Thirdly, the utility model has simple structure, light and flexible structure, convenient use and can be used for various operations.
Drawings
Fig. 1 is a front view of an electric climbing basket for high-position small-space operation according to the present invention;
fig. 2 is a side view of an electric climbing basket for high-position small-space operation according to the present invention;
fig. 3 is a top view of the electric climbing hanging basket for high-position small space operation.
Detailed Description
The first embodiment is as follows: the embodiment is described with reference to fig. 1, fig. 2 and fig. 3, and the electric climbing cradle for high-position small-space operation in the embodiment comprises two winches 1, two cradle frames 2, two fixed steel plates 3, a bearing pedal 4, angle steel 5, a support rod 6 and two fixed rods 7;
the hanging basket frame 2 is in a V shape, two ends of the bearing pedal 4 are respectively provided with a hanging basket frame 2, the tip ends of the basket frames 2 are fixedly connected with the end face of the bearing pedal 4, the upper ends of the two basket frames 2 are respectively provided with a fixed steel plate 3, the upper surface of each fixed steel plate 3 is fixedly connected with the base of the winch 1 through an angle steel 5, one end of one fixed steel plate 3 is fixedly connected with one end of a fixed rod 7, the other end of one fixed rod 7 is fixedly connected with one end of the other fixed steel plate 3, the other end of one fixed steel plate 3 is fixedly connected with one end of the other fixed rod 7, the other end of the other fixed rod 7 is fixedly connected with the other end of the other fixed steel plate 3, the two fixing rods 7 are arranged in parallel, n supporting rods 6 are arranged between the two fixing rods 7, n is a positive integer, and each supporting rod 6 is perpendicular to the fixing rod 7;
according to the specific embodiment, the electric climbing hanging basket device is suitable for construction environments with small bridges, operation of a traditional large crane is avoided, working efficiency is improved, and cost is saved. The electric climbing hanging basket has the advantages of simple structure, easiness in processing, portability, flexibility, high applicability and capability of performing various operations, compared with the traditional construction, the electric climbing hanging basket is more convenient, concise and efficient, a plurality of hanging baskets can be processed for simultaneous construction when the workload is large, and the cost can be saved by repeated utilization;
when the electric climbing hanging basket is used, the electric climbing hanging basket is conveyed to a construction position to be in place, a power supply is switched on, a socket (for an electric winch and drilling equipment) is provided, debugging is carried out to ensure that the hanging basket normally runs, a winch 1 hook of the hanging basket is lifted to the top of a frame pier through a steel wire rope, the hanging basket is reliably connected and fixed with an embedded part, the hanging basket is lifted to a stressed state, an operator carries a safety belt to enter the hanging basket to be in place, and meanwhile, a falling protector is lowered to be firmly connected with a safety belt buckle; drilling equipment is in place, a drainage pipeline and a pier body are connected by adopting an anchor ear and an expansion bolt, one anchor ear is arranged every 2m, the corner part is reinforced, a drilling machine drills a hole to perform expansion screw construction and is temporarily fixed with the anchor ear, and an electric climbing hanging basket performs drilling construction at the next position until the drilling is completed, wherein the length of one UPVC pipe is 6 m; a worker at the top of the frame pier lowers the UPVC pipe to the fixed position of the hoop through a rope, the electric hanging basket is lifted to the position of the hoop, the operator finely adjusts and fixes the UPVC pipe, and all the hoops within the length range of 6m of the UPVC pipe are sequentially fixed; the electric hanging basket descends to the next construction position, and the construction mode is repeated for construction; after one part is installed, the electric hanging basket is descended to the bridge floor of the T-shaped beam, and after the fixing position of the hanging basket at the top of the frame pier is adjusted, the hanging basket is lifted again for subsequent installation of the drainage pipeline; after the installation of a frame pier drainage pipeline is completed, the electric hanging basket descends to a T-shaped beam bridge floor, the falling protector is unfastened, the hanging basket fixing buckle is unfastened, and the hanging basket is carried to the next frame pier by workers for repeated construction to complete the installation of all the frame pier drainage pipelines.
The second embodiment is as follows: the present embodiment is described with reference to fig. 2, and the present embodiment is a further limitation of the electric climbing cradle according to the first embodiment, and the electric climbing cradle for high-level small space operation according to the present embodiment is characterized in that the fixed steel plate 3 is a steel plate of 12mm × 400mm × 300 mm;
in the present embodiment, the steel plate having a thickness of 12mm and a fixed steel plate 3 of 12mm × 400mm × 300mm is used, and the stability of the hoist 1 is improved.
The third concrete implementation mode: the present embodiment is described with reference to fig. 1, and the present embodiment is a further limitation of the electric climbing gondola of the first embodiment, and the electric climbing gondola of the present embodiment is used for high-level small space operation, and the angle steel 5 is angle steel of 5mm × 5mm × 200 mm;
in the specific embodiment, the angle steel 5 is 5mm × 5mm × 200mm, the thickness is 5mm, and the supporting force is improved, so that the stability of the device is improved.
The fourth concrete implementation mode: the embodiment is described with reference to fig. 1 and 2, and the embodiment further defines the electric climbing basket of the first embodiment, and the electric climbing basket for high-position small space operation of the embodiment has the thickness of the bearing pedal 4 of 15 mm-25 mm;
in the specific embodiment, the thickness of the bearing pedal 4 is 15-25 mm, so that 2-3 people can be borne during use, and the working efficiency is improved.
The fifth concrete implementation mode: the present embodiment is described with reference to fig. 1 and 2, and is a further limitation of the electric climbing cradle described in the fourth embodiment, and the electric climbing cradle for high-level small space operation described in the present embodiment has a thickness of 20mm of the load-bearing pedal 4.
The sixth specific implementation mode: the present embodiment is described with reference to fig. 1 and 2, and is further limited to the electric climbing cradle according to the first embodiment, which is used for high-level small space operation, and the connection manner between the upper end of the cradle frame 2 and the bottom end of the fixed steel plate 3 is welding;
in the specific embodiment, the connection mode of the upper end of the hanging basket frame 2 and the bottom end of the fixed steel plate 3 is welding, so that the stability of the device is improved.
The seventh embodiment: the embodiment is described with reference to fig. 1 and 2, and the embodiment further defines the electric climbing basket according to the first embodiment, and the number n, 3 ≤ n ≤ 6 of the support rods 6 is used for high-position small-space operation.
Principle of operation
When the electric climbing hanging basket is used, the electric climbing hanging basket is conveyed to a construction position to be in place, a power supply is switched on, a socket (for an electric winch and drilling equipment) is provided, debugging is carried out to ensure that the hanging basket normally runs, a winch 1 hook of the hanging basket is lifted to the top of a frame pier through a steel wire rope, the hanging basket is reliably connected and fixed with an embedded part, the hanging basket is lifted to a stressed state, an operator carries a safety belt to enter the hanging basket to be in place, and meanwhile, a falling protector is lowered to be firmly connected with a safety belt buckle; drilling equipment is in place, a drainage pipeline and a pier body are connected by adopting an anchor ear and an expansion bolt, one anchor ear is arranged every 2m, the corner part is reinforced, a drilling machine drills a hole to perform expansion screw construction and is temporarily fixed with the anchor ear, and an electric climbing hanging basket performs drilling construction at the next position until the drilling is completed, wherein the length of one UPVC pipe is 6 m; a worker at the top of the frame pier lowers the UPVC pipe to the fixed position of the hoop through a rope, the electric hanging basket is lifted to the position of the hoop, the operator finely adjusts and fixes the UPVC pipe, and all the hoops within the length range of 6m of the UPVC pipe are sequentially fixed; the electric hanging basket descends to the next construction position, and the construction mode is repeated for construction; after one part is installed, the electric hanging basket is descended to the bridge floor of the T-shaped beam, and after the fixing position of the hanging basket at the top of the frame pier is adjusted, the hanging basket is lifted again for subsequent installation of the drainage pipeline; after the installation of a frame pier drainage pipeline is completed, the electric hanging basket descends to a T-shaped beam bridge floor, the falling protector is unfastened, the hanging basket fixing buckle is unfastened, and the hanging basket is carried to the next frame pier by workers for repeated construction to complete the installation of all the frame pier drainage pipelines.
Claims (7)
1. The utility model provides an electronic hanging flower basket that climbs that is used for high-order little space operation which characterized in that: comprises two winches (1), two hanging basket frames (2), two fixed steel plates (3), a bearing pedal (4), angle steel (5), a support rod (6) and two fixed rods (7);
the hanging basket frame (2) is in a V-shaped shape, two ends of the bearing pedal (4) are respectively provided with a hanging basket frame (2), the tip end of the hanging basket frame (2) is fixedly connected with the end face of the bearing pedal (4), the upper ends of the two hanging basket frames (2) are respectively provided with a fixed steel plate (3), the upper surface of each fixed steel plate (3) is fixedly connected with the base of the winch (1) through an angle steel (5), one end of one fixed steel plate (3) is fixedly connected with one end of one fixed rod (7), the other end of one fixed rod (7) is fixedly connected with one end of the other fixed steel plate (3), the other end of the other fixed steel plate (3) is fixedly connected with one end of the other fixed rod (7), the other end of the other fixed rod (7) is fixedly connected with the other end of the other fixed steel plate (3), and the two fixed rods (7) are arranged, n support rods (6) are arranged between the two fixing rods (7), n is a positive integer, and each support rod (6) is perpendicular to the fixing rod (7).
2. The electric climbing hanging basket for high-position small-space operation according to claim 1, characterized in that: the fixed steel plate (3) is a steel plate with the thickness of 12mm multiplied by 400mm multiplied by 300 mm.
3. The electric climbing hanging basket for high-position small-space operation according to claim 1, characterized in that: the angle steel (5) is 5mm multiplied by 200 mm.
4. The electric climbing hanging basket for high-position small-space operation according to claim 1, characterized in that: the thickness of the bearing pedal (4) is 15 mm-25 mm.
5. The electric climbing hanging basket for high-position small-space operation according to claim 4, characterized in that: the thickness of the bearing pedal (4) is 20 mm.
6. The electric climbing hanging basket for high-position small-space operation according to claim 1, characterized in that: the upper end of the hanging basket frame (2) is connected with the bottom end of the fixed steel plate (3) in a welding mode.
7. The electric climbing hanging basket for high-position small-space operation according to claim 1, characterized in that: the number n of the supporting rods (6) is more than or equal to 3 and less than or equal to 6.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020813846.8U CN212223633U (en) | 2020-05-15 | 2020-05-15 | Electric climbing hanging basket for high-position small-space operation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020813846.8U CN212223633U (en) | 2020-05-15 | 2020-05-15 | Electric climbing hanging basket for high-position small-space operation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212223633U true CN212223633U (en) | 2020-12-25 |
Family
ID=73926658
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020813846.8U Active CN212223633U (en) | 2020-05-15 | 2020-05-15 | Electric climbing hanging basket for high-position small-space operation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212223633U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111485499A (en) * | 2020-05-15 | 2020-08-04 | 中铁建大桥工程局集团第四工程有限公司 | Electric climbing hanging basket for high-position small-space operation and mounting method |
-
2020
- 2020-05-15 CN CN202020813846.8U patent/CN212223633U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111485499A (en) * | 2020-05-15 | 2020-08-04 | 中铁建大桥工程局集团第四工程有限公司 | Electric climbing hanging basket for high-position small-space operation and mounting method |
CN111485499B (en) * | 2020-05-15 | 2024-10-15 | 中铁建大桥工程局集团第四工程有限公司 | Electric climbing hanging basket for high-level small-space operation and mounting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102900021B (en) | Split mounting type bridge wet joint construction method | |
CN212223633U (en) | Electric climbing hanging basket for high-position small-space operation | |
CN204112242U (en) | A kind of Concrete Filled Steel-tube Truss Arch Bridge suspender replacement special tool boom system | |
CN210944509U (en) | Plate hoisting clamping part for building construction | |
CN206308702U (en) | A kind of portable basis of derrick crane | |
CN202450548U (en) | Adjustable support for fundament of construction elevator on basement top plate | |
CN111485499B (en) | Electric climbing hanging basket for high-level small-space operation and mounting method | |
CN216613706U (en) | Portable floor hoisting structure | |
CN213979839U (en) | Assembled I-shaped girder steel operation device that encorbelments that can have enough to meet need not wear wall | |
CN205294678U (en) | Hoist and mount of instrument formula and uninstallation device of large -scale truss structure | |
CN209780257U (en) | Steel structure high altitude construction device | |
CN211998435U (en) | Tool type aerated brick hopper | |
CN210914945U (en) | Hoisting device for upper structure of aluminum electrolytic cell | |
CN203781713U (en) | High slope support material transport device | |
CN111042538A (en) | Hoisting and mounting method of buckling restrained brace | |
CN210594893U (en) | Double-hook clamp for hoisting H-shaped steel beam | |
CN202467221U (en) | Power plant main workshop steel roof truss hoisting lifting device | |
CN202766094U (en) | Hoisting clamp for steel reinforcement cage | |
CN201458509U (en) | Combined hoisting tool for large-sized pipes | |
CN206636239U (en) | A hang mounting system for installing intermediate layer girder steel | |
CN205077876U (en) | Prestressed steel strand pulling machine and tensioning jack suspension device | |
CN206903178U (en) | Hoisting type elevator steel platform | |
CN215885996U (en) | F-shaped prefabricated T-beam template hoisting device | |
CN204530489U (en) | A kind of high pier creeping formwork hydraulic lifting apparatus | |
CN214460463U (en) | Bracket for supporting and installing foundation pit engineering steel pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |