CN210914945U - Hoisting device for upper structure of aluminum electrolytic cell - Google Patents
Hoisting device for upper structure of aluminum electrolytic cell Download PDFInfo
- Publication number
- CN210914945U CN210914945U CN201921433950.8U CN201921433950U CN210914945U CN 210914945 U CN210914945 U CN 210914945U CN 201921433950 U CN201921433950 U CN 201921433950U CN 210914945 U CN210914945 U CN 210914945U
- Authority
- CN
- China
- Prior art keywords
- workpiece
- mounting hole
- electrolytic cell
- aluminum electrolytic
- hoisting device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Electrolytic Production Of Metals (AREA)
Abstract
Description
技术领域technical field
本实用新型设计建筑施工领域,尤其是一种铝电解槽上部结构吊装装置。The utility model is designed in the field of building construction, in particular to a hoisting device for the upper structure of an aluminum electrolytic cell.
背景技术Background technique
在铝电解槽技改和检修施工过程中需要将上部T型梁的整体吊装,并且吊装频率较高。In the process of technical renovation and maintenance of the aluminum electrolytic cell, it is necessary to hoist the upper T-beam as a whole, and the hoisting frequency is high.
目前常用的吊装施工方法需要制作横梁扁担,横梁扁担穿过大梁窗口进行吊装。横梁扁担笨重、转运安装繁琐,安装过程中需要天车配合,需要人力较多。铝电解槽检修一般与甲方生产同时进行,在安装和拆卸横梁扁担时需要等候天车造成人员设备的窝工,影响施工进度。At present, the commonly used hoisting construction method needs to make a cross beam pole, and the cross beam pole is hoisted through the girder window. The cross-beam pole is cumbersome, and the transfer and installation are cumbersome. During the installation process, it requires the cooperation of the crane and requires a lot of manpower. The maintenance of the aluminum electrolytic cell is generally carried out at the same time as Party A's production. When installing and dismantling the beam and pole, it is necessary to wait for the crane to cause the squatting of personnel and equipment, which will affect the construction progress.
寻找一种施工简单不依靠天车配合,施工速度相对较快且相对安全的吊装装置是急需解决的问题。It is an urgent problem to find a hoisting device that is simple in construction and does not rely on the cooperation of the crane, and the construction speed is relatively fast and relatively safe.
实用新型内容Utility model content
为解决上述技术问题,本实用新型提出一种安装方便,操作简单的铝电解槽上部结构吊装装置。In order to solve the above-mentioned technical problems, the utility model proposes a hoisting device for the upper structure of an aluminum electrolytic cell, which is convenient to install and simple to operate.
本实用新型采用如下技术方案:The utility model adopts the following technical solutions:
一种铝电解槽上部结构吊装装置,包括吊具,卡具,吊具为长形箱体结构,吊具的两端设置有吊耳,吊具的中部设置有销子;卡具是由工件一和工件二组成的分体式结构,工件一为L型钢板,工件一上设置有螺栓安装孔,工件二为L型钢板,工件二上设置有与铝电解槽上部T型梁的翼板相配合的安装缝,工件二上设置有卡具安装孔。A hoisting device for the upper structure of an aluminum electrolytic cell, comprising a hoist and a clamp, the hoist is a long box structure, the two ends of the hoist are provided with lifting ears, and the middle of the hoist is provided with a pin; A split structure composed of the first and the second workpiece. The first workpiece is an L-shaped steel plate, and the first workpiece is provided with bolt mounting holes. The second workpiece is an L-shaped steel plate. A fixture installation hole is arranged on the second workpiece for the matching installation seam.
与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the present utility model are:
本实用新型的卡具为组合是单片安装,结构简单,拆装方便,而且能够多次循环利用,卡具的安装不用依靠天车的配合,降低了安装难度;单片式结构有利于保证施工人员的施工安全。The clamp of the utility model is assembled in a single piece, with simple structure, convenient disassembly and assembly, and can be recycled for many times. The installation of the clamp does not depend on the cooperation of the crane, which reduces the difficulty of installation; Construction safety of construction workers.
与现有技术相比,本实用新型采用的优选方案是:Compared with the prior art, the preferred scheme adopted by the present utility model is:
工件二由c部和d部组成,安装缝设置在c部和d部连接位置,c部的一端对应工件一的螺栓安装孔一设置有螺栓安装孔二。The second workpiece is composed of a c part and a d part, the installation seam is arranged at the connection position of the c part and the d part, and one end of the c part corresponds to the
卡环安装孔内设置有卡环。A snap ring is arranged in the snap ring mounting hole.
一组卡具由两个工件一和一个工件二组成。A set of fixtures consists of two workpieces one and one workpiece two.
附图说明Description of drawings
图1为本实用新型的结构示意图;Fig. 1 is the structural representation of the utility model;
图2为工件一的结构示意图;Fig. 2 is the structural representation of workpiece one;
图3为工件二的结构示意图;Fig. 3 is the structural representation of workpiece two;
图4为工件一和工件二相配合的结构示意图;Fig. 4 is the structural representation that workpiece one and workpiece two are matched;
图中:铝电解槽1;T型梁2;翼板201;吊具3;吊耳4;钢丝绳5;销子6;卡具7;工件一701;工件二702;卡环8;螺栓安装孔一9;螺栓安装孔二10;卡环安装孔11;安装缝12;螺栓13。In the figure: aluminum
具体实施方式Detailed ways
以下结合附图和具体实施方式对本实用新型进一步说明。The present invention will be further described below with reference to the accompanying drawings and specific embodiments.
参见附图:See attached image:
一种铝电解槽上部结构吊装装置,由吊具3和卡具7组成,吊具3为长形箱体结构,吊具3的两端对称设置有吊耳4,吊具3的中部对称设置有两个销子6。A hoisting device for the upper structure of an aluminum electrolytic cell, which is composed of a
一组卡具7由两个工件一701和一个工件二702组成,工件一701为L型钢板,工件一701由a部和b部组成,a部上设置有四个螺栓安装孔一9,两个工件一701之间螺栓13固定连接。A set of
工件二702为倒置的L型钢板,工件二702由c部和d部组成,c部和d部的连接处横向开设有一条安装缝12,铝电解槽1上方的T型梁2的翼板201正好顶进安装缝12内,工件二702的上方设置有卡环安装孔11,卡环安装孔11内设置有卡环8,安装缝12的宽度需要根据施工现场T型梁2的翼板201确定。The
工件一701和工件二702在应用时,先将工件二702垂直于翼板201放置,然后将T型梁2内侧翼板201沿安装缝12顶进,使安装缝12与翼板201的上下表面紧密接触,将两个工件一701置于T型梁2的外侧,且两个工件一701分别置于工件二702的两侧并关于工件二702对称设置(如图4所示),然后将两个工件一701b部的承托面分别顶在T型梁2外侧翼板201的下表面上,将工件二702上的螺栓安装孔二10分别与两个工件一701上的螺栓安装孔一9对齐,并通过螺栓13将工件二702和两个工件一701固定连接为一体;将用于吊装的钢丝绳5穿过卡环8,钢丝绳5的两端分别设置有环扣,两个环扣分别挂在吊具3中部的两个销子6上。When the
一种铝电解槽上部结构吊装的施工方法,按如下步骤进行:A construction method for hoisting the upper structure of an aluminum electrolytic cell is carried out according to the following steps:
(1)根据铝电解槽1上方T型梁2的翼板201尺寸制作卡具7和吊具3;(1) According to the size of the
(2)将卡具7安装在铝电解槽1上部的翼板201上:工件二702垂直于翼板201放置,然后将T型梁2内侧翼板201沿安装缝5顶进,将两个工件一701置于T型梁2的外侧,且两个工件一701分别置于工件二702的两侧并关于工件二702对称设置,然后将两个工件一701b部的承托面分别顶在T型梁2外侧翼板201的下表面上,将工件二702上的螺栓安装孔二10分别与两个工件一701上的螺栓安装孔一9对齐,并通过螺栓13将工件二702和两个工件一701固定连接为一体。(2) Install the
(3)将卡环8安装至卡环安装孔11内,在卡环8内安装钢丝绳5,等待吊装。(3) Install the
(4)两台天车联动作业,同时将吊具3吊至铝电解槽1上方,将钢丝绳5固定在吊具3的销子6上,开始吊装。(4) The two cranes are linked together, and the
以上仅为本实用新型的具体实施方式,但对本实用新型的保护并不局限于此,所有涉及本技术领域技术人员提出的对本技术方案技术特征提出的等效的变化或替换,都涵盖在实用新型的保护范围之内。The above are only specific embodiments of the present utility model, but the protection of the present utility model is not limited to this, and all the equivalent changes or replacements proposed by those skilled in the art to the technical features of the technical solution are included in the utility model. within the scope of the new protection.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201921433950.8U CN210914945U (en) | 2019-08-30 | 2019-08-30 | Hoisting device for upper structure of aluminum electrolytic cell |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201921433950.8U CN210914945U (en) | 2019-08-30 | 2019-08-30 | Hoisting device for upper structure of aluminum electrolytic cell |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN210914945U true CN210914945U (en) | 2020-07-03 |
Family
ID=71345526
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201921433950.8U Active CN210914945U (en) | 2019-08-30 | 2019-08-30 | Hoisting device for upper structure of aluminum electrolytic cell |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN210914945U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110422751A (en) * | 2019-08-30 | 2019-11-08 | 中国二十二冶集团有限公司 | Aluminum electrolytic cell superstructure hoisting device and its construction method |
-
2019
- 2019-08-30 CN CN201921433950.8U patent/CN210914945U/en active Active
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110422751A (en) * | 2019-08-30 | 2019-11-08 | 中国二十二冶集团有限公司 | Aluminum electrolytic cell superstructure hoisting device and its construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN210914945U (en) | Hoisting device for upper structure of aluminum electrolytic cell | |
| CN219546511U (en) | Hydropower station electric hoist track installation dismounting device | |
| WO2022111218A1 (en) | Pile casing hoisting arm | |
| CN218371219U (en) | PCCP pipeline handling frock | |
| CN216038140U (en) | Assembly type house PC hoisting stair structure | |
| CN222273900U (en) | A steel plate lifting tool | |
| CN201857209U (en) | Special lifting tool provided with wheel hub of diversion cover | |
| CN209507399U (en) | Be applied to prefab stable form hoist of sling cart | |
| CN209127874U (en) | A kind of concurrent lifting device | |
| CN219603041U (en) | Lifting appliance for steel bar truss floor support plate | |
| CN212832351U (en) | Hoisting tool for installing reactor supporting beam | |
| CN210457169U (en) | Novel lifting appliance suitable for lifting all sections of steel trussed beams of suspension bridge | |
| CN209815490U (en) | Hoisting device for rotor magnetic pole in hydraulic generator pit | |
| CN205590168U (en) | Overturning lifting device | |
| CN204569127U (en) | Steel upright post hoisting jig | |
| CN207276043U (en) | A kind of large component lifts positioning auxiliary device | |
| CN211521339U (en) | Hoisting device for hanging and releasing steel wire rope | |
| CN210505204U (en) | A type of steel lifting device | |
| CN110422751A (en) | Aluminum electrolytic cell superstructure hoisting device and its construction method | |
| CN210914967U (en) | A reinforced concrete pipe hoisting device | |
| CN203497976U (en) | High-altitude installation clamping device for large electric hoists | |
| CN107100369A (en) | A kind of interim crossbeam construction method | |
| CN209427982U (en) | A kind of large-scale mixed turbine water pilot bearing and main shaft seal special hanger for hoisting | |
| CN203333153U (en) | Detachable hoisting appliance for chord member of large-scale truss | |
| CN113417269A (en) | Method for mounting rib plate of combined beam structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |