CN208815884U - A kind of elevator supporting standard regulating device - Google Patents
A kind of elevator supporting standard regulating device Download PDFInfo
- Publication number
- CN208815884U CN208815884U CN201821456803.8U CN201821456803U CN208815884U CN 208815884 U CN208815884 U CN 208815884U CN 201821456803 U CN201821456803 U CN 201821456803U CN 208815884 U CN208815884 U CN 208815884U
- Authority
- CN
- China
- Prior art keywords
- steel
- scaffolding
- steel pipe
- fastener
- grade iii
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000001105 regulatory effect Effects 0.000 title claims abstract description 15
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 175
- 239000010959 steel Substances 0.000 claims abstract description 175
- 230000000694 effects Effects 0.000 abstract description 4
- 238000000034 method Methods 0.000 description 8
- 238000005266 casting Methods 0.000 description 4
- 238000003466 welding Methods 0.000 description 4
- 230000007812 deficiency Effects 0.000 description 3
- 238000009415 formwork Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 235000001674 Agaricus brunnescens Nutrition 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Landscapes
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
The utility model discloses a kind of elevator supporting standard regulating devices, including the first I-steel, second I-steel, first scaffolding steel pipe, second scaffolding steel pipe, third scaffolding steel pipe, 4th scaffolding steel pipe and fastener, the outside of first I-steel is welded with the second I-steel in two sides up and down, the external top of second I-steel is welded with the first grade III steel, the external top of second I-steel is welded with the second grade III steel, first grade III steel passes through fastener and the 4th scaffolding steel pipe snapping, second grade III steel passes through fastener and third scaffolding steel pipe snapping, second grade III steel passes through fastener and the 4th scaffolding steel pipe snapping.The first I-steel, the second I-steel, the first grade III steel, third scaffolding steel pipe, the 4th scaffolding steel pipe, triangle groove and the fastener that the utility model passes through setting, solves higher cost, effect is unobvious, it is not possible to be recycled for a long time, not have good economic and social benefit.
Description
Technical field
The utility model relates to technical field of buildings, specially a kind of elevator supporting standard regulating device.
Background technique
With the development of society, especially scientific and technical progress, is greatly facilitated the development of social productive forces;Urbanization
The quickening of process and the high concentration of social dominance's resource, so that many cities need to carry more on limited soil
Population, and the material goods such as place are provided for its life and work, the building for thus having expedited the emergence of building trade are had to high-altitude
Develop with subterranean depth, many building are rised sheer from level ground like the mushrooms after rain.
In the building to tower into the clouds, elevator is the upper and lower important transportation vehicles of carrying;In architectural engineering, elevator
Supporting scaffold generally using setting up method for protecting support to pouring layer always from the first floor, this result in live scaffold use it is tight
The cumbersome of a large amount of rental charge and worker operation is wasted and then generated again while also resulting in that there are some potential safety problemss;
In existing elevator construction process, supporting standard regulating device is a kind of relatively conventional tool, existing supporting standard knot
Device has the following deficiencies: existing supporting standard regulating device, and in use, higher cost, effect is unobvious, it is not possible to
It is recycled for a long time, does not have good economic and social benefit.
Summary of the invention
In view of the deficiencies of the prior art, the utility model provides a kind of elevator supporting standard regulating device, solves into
This is higher, and effect is unobvious, it is not possible to be recycled for a long time, the deficiency without good economic and social benefit.
To achieve the above object, the utility model provides the following technical solutions:
A kind of elevator supporting standard regulating device, including the first I-steel, the second I-steel, the first scaffolding steel pipe,
Two scaffolding steel pipes, third scaffolding steel pipe, the 4th scaffolding steel pipe and fastener, the upper and lower two sides in the outside of first I-steel
Be welded with the second I-steel, the external top of second I-steel is welded with the first grade III steel, second I-steel it is outer
The second grade III steel is welded with above portion, lower section butting has the first scaffold steel outside first grade III steel and the second grade III steel
Lower section butting has the second scaffolding steel pipe outside pipe, first grade III steel and the second grade III steel, and first grade III steel passes through
Fastener and third scaffolding steel pipe snapping, first grade III steel is by fastener and the 4th scaffolding steel pipe snapping, and described second
Grade III steel passes through fastener and the 4th scaffolding steel pipe button by fastener and third scaffolding steel pipe snapping, second grade III steel
It connects.
First I-steel is internally provided with triangle groove.
The outside of the fastener is provided with screw rod, and the screw rod passes through arc frame and is threadedly coupled with nut.
It is rotatablely connected between the fastener by shaft.
The arc frame is rotatablely connected by pivot pin and fastener.
Positive beneficial effect: the utility model passes through the first I-steel of setting, the second I-steel, the first grade III steel, the
Three scaffolding steel pipes and fastener, in use, it is stronger by welding stability between the first I-steel and the second I-steel, it improves
The safety of device, the first grade III steel and the second scaffolding steel pipe improve the stability of device by being tied together, and first
Grade III steel and third scaffolding steel pipe snapping, the position between adjustable first grade III steel and third scaffolding steel pipe, fastener
Between be rotatablely connected by shaft, the rotation angle between adjustable fastener, fastener is threadedly coupled by screw rod with arc frame,
The stability of device, the damage of anti-locking apparatus, by the device tower crane before having tested wall column casting concrete every time can be improved
It is hung at the floor plate absolute altitude, blocks the floor plate with the triangle groove that is internally provided with of the first I-steel, then on it
Just to hoistway formwork.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the connection schematic diagram of third scaffolding steel pipe and the 4th scaffolding steel pipe in the utility model Fig. 1;
Fig. 3 is the side structure schematic view of the first I-steel in the utility model Fig. 1.
In figure: 1, the first I-steel;2, the second I-steel;3, the first grade III steel;4, the second grade III steel;5, the first scaffold
Steel pipe;6, the second scaffolding steel pipe;7, third scaffolding steel pipe;8, the 4th scaffolding steel pipe;9, triangle groove;10, fastener;
11, screw rod;12, arc frame;13, nut;14, pivot pin;15, shaft.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
It please refers to shown in Fig. 1-3, a kind of embodiment provided by the utility model;A kind of elevator supporting standard regulating device,
Including the first I-steel 1, the second I-steel 2, the first scaffolding steel pipe 5, the second scaffolding steel pipe 6, third scaffolding steel pipe 7,
The outside of 4th scaffolding steel pipe 8 and fastener 10, the first I-steel 1 is welded with the second I-steel 2, the first I-steel in two sides up and down
1 and second stronger by welding stability between I-steel 2, the safety of device is improved, is brought convenience to user, first
I-steel 1 is internally provided with triangle groove 9, and the device is hung to the layer with tower crane before having tested wall column casting concrete every time
At floor absolute altitude, the floor plate is blocked with the triangle groove 9 that is internally provided with of the first I-steel 1, then above it to electricity
Stair shaft template, the external top of the second I-steel 2 are welded with the first grade III steel 3, and the external top of the second I-steel 2 is welded with the
Two grade III steels 4, the first grade III steel 3 and 4 outside lower section butting of the second grade III steel have the first scaffolding steel pipe 5,3 He of the first grade III steel
Second grade III steel, 4 outside lower section butting has the second scaffolding steel pipe 6, and the first grade III steel 3 and the second scaffolding steel pipe 6 pass through butting
Together, the stability of device is improved, the first grade III steel 3 passes through fastener 10 and 7 snapping of third scaffolding steel pipe, the first three-level
7 snapping of steel 3 and third scaffolding steel pipe, the position between adjustable first grade III steel 3 and third scaffolding steel pipe 7, to making
User brings conveniently, and the first grade III steel 3 passes through fastener by 8 snapping of fastener 10 and the 4th scaffolding steel pipe, the second grade III steel 4
10 with 7 snapping of third scaffolding steel pipe, be rotatablely connected by shaft 15 between fastener 10, the rotation between adjustable fastener 10
Angle, for the second grade III steel 4 by 8 snapping of fastener 10 and the 4th scaffolding steel pipe, the outside of fastener 10 is provided with screw rod 11, screw rod
11 pass through arc frame 12 is threadedly coupled with nut 13, and fastener 10 is threadedly coupled by screw rod 11 with arc frame 12, and dress can be improved
The stability set, the damage of anti-locking apparatus, arc frame 12 are rotatablely connected by pivot pin 14 and fastener 10.
Working principle: when the utility model is run, pass through welding stability between the first I-steel 1 and the second I-steel 2
It is stronger, the safety of device, the first grade III steel 3 and the second scaffolding steel pipe 6 are improved by being tied together, and improve device
Stability, 7 snapping of the first grade III steel 3 and third scaffolding steel pipe, adjustable first grade III steel 3 and third scaffolding steel pipe
Position between 7 is rotatablely connected between fastener 10, the rotation angle between adjustable fastener 10, fastener 10 by shaft 15
It is threadedly coupled by screw rod 11 with arc frame 12, the stability of device can be improved, wall is being tested in the damage of anti-locking apparatus every time
The device is hung at the floor plate absolute altitude with tower crane before column casting concrete, is internally provided with triangle with the first I-steel 1
Groove 9 blocks the floor plate, then above it to hoistway formwork, installation cost is low, can be recycled.
Embodiment
A kind of elevator supporting standard regulating device, using materials such as common I-steel, round steel pipe, fastener, plain bars,
It is made into Fig. 1 such as and shows moulding.It is described in detail as follows:
The first step selects the I-steel and two root long degree 2900mm, 100* of two root long degree 1500mm, 100*68*4.5mm
Two short I-steel are welded on two root long I-steel by the I-steel of 68*4.5mm, while by the web of long I-steel one end
It is cut into a chamfer triangle, and welds four root long 10mm, diameter 20mm on the upside of the welding of short I-steel and long I-steel
Grade III steel, placed it in after first floor demoulding at first floor elevator, block first floor floor with the I-steel one end for having notch,
Two outer one end are then placed on left-right position in the middle part of the elevator shear wall of demoulding naturally.
Second step selects the scaffolding steel pipe and two root long 3000mm, Φ 50*3mm of two root long 4000mm, Φ 50*3mm
Scaffolding steel pipe fixes this four steel pipes on above-mentioned four short three-level reinforcing bars respectively, and binds jail with the reinforcing bar of four Φ 6
Gu.
Third step selects the scaffolding steel pipe and two root long 2000mm, Φ 50*3mm of two root long 1000mm, Φ 50*3mm
Scaffolding steel pipe, wherein the scaffolding steel pipe fastener fixing of a 1000mm is at the position 1000mm high of 4000mm upright bar,
The scaffolding steel pipe fastener fixing of an other 1000mm guarantees two 1000mm scaffolding steel pipes in 3000mm bottom of upright rod
In same level, then the scaffolding steel pipe of two 2000mm is separately fixed to the lower part of 1000mm horizon bar with fastener
?.
4th step selects the scaffolding steel pipe of two 2500mm, Φ 50*3mm, long with fastener fixing at two layers of absolute altitude
To arrangement.
5th step selects the scaffolding steel pipe of three 2000mm, Φ 50*3mm, respectively with fastener fixing in above-mentioned 2500mm
Scaffolding steel pipe on.
It uses: being hung to the device at the floor plate absolute altitude with tower crane before having tested wall column casting concrete every time, with having
The I-steel one end of notch blocks the floor plate, then above it to hoistway formwork.
It can to sum up obtain, first I-steel 1, second I-steel 2, first grade III steel 3, third of the utility model by setting
Scaffolding steel pipe 7, the 4th scaffolding steel pipe 8, triangle groove 9 and fastener 10, solve higher cost, and effect is unobvious, can not
To be recycled for a long time, do not have good economic and social benefit.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality
Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation
In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to
Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those
Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment
Intrinsic element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (5)
1. a kind of elevator supporting standard regulating device, including the first I-steel (1), the second I-steel (2), the first scaffolding steel pipe
(5), the second scaffolding steel pipe (6), third scaffolding steel pipe (7), the 4th scaffolding steel pipe (8) and fastener (10), feature exist
In: the outside of first I-steel (1) is welded with the second I-steel (2) two sides up and down, the outside of second I-steel (2)
Top is welded with the first grade III steel (3), and the external top of second I-steel (2) is welded with the second grade III steel (4), and described the
The external lower section butting of one grade III steel (3) and the second grade III steel (4) has the first scaffolding steel pipe (5), first grade III steel (3) and
The external lower section butting of second grade III steel (4) has the second scaffolding steel pipe (6), first grade III steel (3) by fastener (10) with
Third scaffolding steel pipe (7) snapping, first grade III steel (3) pass through fastener (10) and the 4th scaffolding steel pipe (8) snapping, institute
The second grade III steel (4) are stated by fastener (10) and third scaffolding steel pipe (7) snapping, second grade III steel (4) passes through fastener
(10) with the 4th scaffolding steel pipe (8) snapping.
2. a kind of elevator supporting standard regulating device according to claim 1, it is characterised in that: first I-steel
(1) be internally provided with triangle groove (9).
3. a kind of elevator supporting standard regulating device according to claim 1, it is characterised in that: outside the fastener (10)
Portion is provided with screw rod (11), and the screw rod (11) passes through arc frame (12) and is threadedly coupled with nut (13).
4. a kind of elevator supporting standard regulating device according to claim 1, it is characterised in that: between the fastener (10)
It is rotatablely connected by shaft (15).
5. a kind of elevator supporting standard regulating device according to claim 3, it is characterised in that: the arc frame (12) is logical
Pivot pin (14) and fastener (10) are crossed to be rotatablely connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821456803.8U CN208815884U (en) | 2018-09-06 | 2018-09-06 | A kind of elevator supporting standard regulating device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821456803.8U CN208815884U (en) | 2018-09-06 | 2018-09-06 | A kind of elevator supporting standard regulating device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208815884U true CN208815884U (en) | 2019-05-03 |
Family
ID=66276098
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821456803.8U Expired - Fee Related CN208815884U (en) | 2018-09-06 | 2018-09-06 | A kind of elevator supporting standard regulating device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208815884U (en) |
-
2018
- 2018-09-06 CN CN201821456803.8U patent/CN208815884U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201158933Y (en) | High-rise maintaining scaffold device with extruding structure | |
CN100537975C (en) | The job practices of inclined drawing steel truss high-supported formwork structure system | |
CN105089178B (en) | A kind of pre-splicing Standard formula building of prefabricated steel reinforced concrete shear walls | |
CN104453197A (en) | High-altitude large-cantilever concrete structure structural steel supporting platform | |
CN102704684B (en) | Construction method for high-strength shaping combined template of plank frame of shear wall | |
CN103276893A (en) | Novel composite structure for supporting rigid building template and construction method | |
CN206487087U (en) | A kind of scissor stairs of sectional | |
CN106930531A (en) | A kind of pull-up manomelia is encorbelmented the construction method of heavy frame | |
CN111809951A (en) | Prefabricated assembled water pool and assembling method | |
CN105155836A (en) | Aluminum alloy formwork for buildings and method for applying aluminum alloy formwork | |
CN208815884U (en) | A kind of elevator supporting standard regulating device | |
CN111236603B (en) | Comprehensive construction method for steel plate mesh overhanging scaffold | |
CN201158932Y (en) | Self-chucking platform especially for high-rise building elevator shaft formwork supports | |
CN203755171U (en) | Bridge back-pulling bearing construction support | |
CN203257070U (en) | Slippage frame operating platform for gallery daylighting roof curtain wall installation | |
CN205776400U (en) | A kind of for poured band of outer wall of basement structure | |
CN212802189U (en) | Assembly type disassembly-free template | |
CN201802063U (en) | Steel formwork used for building construction | |
CN111608376B (en) | Comprehensive construction method for shaping component | |
CN208415925U (en) | A kind of PVC column-form | |
CN111608377B (en) | Comprehensive construction method for building overhanging scaffold | |
CN204040457U (en) | Wood frame plastic formwork system | |
CN208202547U (en) | A kind of building climbing form system foldable shear support | |
CN207144161U (en) | Strengthening concrete Core Walls Structure and the structural system of concrete-filled rectangular steel tube Special-Shaped Column | |
CN206438749U (en) | Construction operation platform in turnover type elevator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190503 |