CN111809951A - Prefabricated assembled water pool and assembling method - Google Patents

Prefabricated assembled water pool and assembling method Download PDF

Info

Publication number
CN111809951A
CN111809951A CN202010832927.7A CN202010832927A CN111809951A CN 111809951 A CN111809951 A CN 111809951A CN 202010832927 A CN202010832927 A CN 202010832927A CN 111809951 A CN111809951 A CN 111809951A
Authority
CN
China
Prior art keywords
prefabricated
component
water pool
vertical plate
shaped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010832927.7A
Other languages
Chinese (zh)
Inventor
文华
邓淞尹
张祎
庞腾
汪思思
谭树成
郭小燕
徐斌
席茜
吴学宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest University of Science and Technology
Original Assignee
Southwest University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest University of Science and Technology filed Critical Southwest University of Science and Technology
Priority to CN202010832927.7A priority Critical patent/CN111809951A/en
Publication of CN111809951A publication Critical patent/CN111809951A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H7/00Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
    • E04H7/02Containers for fluids or gases; Supports therefor
    • E04H7/18Containers for fluids or gases; Supports therefor mainly of concrete, e.g. reinforced concrete, or other stone-like material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/64Insulation or other protection; Elements or use of specified material therefor for making damp-proof; Protection against corrosion
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a prefabricated assembled water pool and an assembling method, and belongs to the field of liquid storage pools. The prefabricated assembled water pool comprises a water pool bottom plate and prefabricated components arranged on the water pool bottom plate, wherein the prefabricated components comprise a plurality of groups of L-shaped components arranged on the water pool bottom plate and vertical plate type components arranged between the transversely adjacent L-shaped components, and connecting bolts are arranged between the L-shaped components and the vertical plate type components; meanwhile, the invention improves the construction efficiency of the pre-drilling engineering and solves the problem of short construction period of the pre-drilling engineering for a long time.

Description

Prefabricated assembled water pool and assembling method
Technical Field
The invention relates to the field of liquid storage tanks, in particular to a prefabricated assembled water tank and an assembling method.
Background
Abundant shale gas resources make the shale gas exploitation task urgent in China, the shale gas exploitation task is urgent at present, and the pre-drilling engineering becomes an important bottleneck problem restricting shale gas exploitation. The traditional process of the pre-drilling engineering, namely the traditional process of masonry or concrete, has more working procedures, more work types and machines and equipment, longer construction period and can not meet the task requirement of shale gas exploitation. The cast-in-place water tank is large in size, procedures such as concrete pouring and maintenance are multiple on a well site, multiple operation working faces are crossed, the water tank pouring slows down the overall construction progress, and meanwhile, because waste liquid containing acid, alkali and oil stains needs to be stored in the water tank, if the construction period is shortened, the water tank engineering quality cannot be guaranteed. In addition, the rain fall in the Yu district is longer and the rainfall is great, and traditional construction maintenance time is longer and the construction progress is influenced by the rainfall greatly.
In addition, in recent years, the construction of sponge cities is greatly promoted by the nation, and the water storage tank is taken as an important ring of a rainwater circulation system, so that the positive effects of solving and avoiding rainwater flood peaks, realizing rainwater recycling, avoiding pollution of initial rainwater to a discharged water body and the like are achieved. However, the problems of large amount of construction waste, noise disturbing residents in the construction process, long maintenance period and the like in the traditional cast-in-place or masonry construction in the city become the difficulties for propelling the sponge city.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides a prefabricated assembled water pool and an assembling method, and the specific technical scheme is as follows:
the utility model provides a prefabricated assembled pond, includes the pond bottom plate and sets up the prefabricated component on the pond bottom plate, the prefabricated component is including setting up multiunit L type component on the pond bottom plate, setting up the floor formula component between horizontal adjacent L type component and setting up the connecting bolt between L type component and floor formula component, L type component all is equipped with the connecting hole with the avris of floor formula component, connecting bolt's both ends are connected with the connecting hole respectively.
The prefabricated components are manufactured in factories, compared with cast-in-place construction, the prefabricated components have controllable product quality and high dimensional precision, and compared with the traditional cast-in-place construction, the factory production is not influenced by natural environments such as severe weather, the construction period is more controllable, the working procedures are more simplified, and the production efficiency is far higher than that of manual operation. In addition, most of the prefabricated part construction in the invention adopts dry construction, water and electricity are saved, the construction is environment-friendly and energy-saving, and compared with the traditional construction, the prefabricated part can be used after being assembled without maintenance, and the maintenance time cost is saved; simultaneously, the L-shaped component and the vertical plate type component are combined for use, so that the liquid storage amount of the assembled water pool can be increased according to actual conditions, and different use requirements can be met.
Preferably, the connecting bolt is arranged between the vertically adjacent L-shaped components, and the connecting bolt is also arranged between the vertically adjacent vertical plate type components.
Preferably, the inner side of the corner of the L-shaped member is provided with a construction rib.
The structural ribs are used for improving the strength of the L-shaped component, the strength of corners of the L-shaped component is enhanced, and the strength of the whole L-shaped component is further enhanced.
Preferably, the top sides of the L-shaped member and the vertical plate type member are provided with hanging points.
The lifting points arranged on the top sides of the L-shaped member and the vertical plate type member are convenient for workers to lift the L-shaped member and the vertical plate type member, and the installation direction of the L-shaped member and the vertical plate type member is adjusted.
Preferably, a filling pad is arranged between the vertically adjacent L-shaped components, and the filling pad is also arranged between the vertically adjacent vertical plate type components.
In the invention, after a layer of prefabricated parts is installed, workers need to lay a layer of filling pad above the prefabricated parts so as to ensure the connection tightness of the prefabricated parts and be used for leveling and waterproofing the prefabricated parts. After the filling pad is laid, a worker screws a connecting bolt for connecting the upper prefabricated member and the lower prefabricated member into the reserved hole of the L-shaped member, and then hoists the prefabricated member on the next layer until the hoisting is finished.
The assembling method of the prefabricated assembled water pool sequentially comprises the following steps:
s1: processing an L-shaped component and a vertical plate type component according to design requirements;
s2: leveling and paying off on site, and determining the hoisting positions of an L-shaped component and a vertical plate component in the assembled water pool;
s3: hoisting the L-shaped member and the vertical plate type member, and mounting the prefabricated assembly type pool;
s4: mounting and fastening connecting bolts on the L-shaped component and the vertical plate type component;
s5: installing temporary support rods on the front side and the back side of the vertical plate type component, and removing the temporary support rods after the prefabricated assembled water pool is installed;
s6: and (4) performing waterproof and anticorrosive treatment on the prefabricated assembled water pool.
Preferably, in step S2, four standard axis control piles for each pool are set based on the coordinates, four control axes of the pool are defined by a theodolite, the intersection points of the axes are set as control points, the longitudinal and transverse axes of the L-shaped member, the inner side line of the L-shaped member, and the node line are sequentially drawn out based on the control axes and the control horizontal line, and the member position line and the number are marked.
Preferably, in the step S5, the fastening of the connecting bolt is performed in two times, the first initial tightening value is 45-55% of the standard axial force, and the second final tightening value is 45-55% of the standard axial force.
The invention has the following beneficial effects:
(1) the assembled component is high in quality: compared with cast-in-place construction, the prefabricated part is manufactured in a factory, the product quality is controllable, and the dimensional accuracy is high;
(2) the construction efficiency is high: compared with the traditional cast-in-place construction, the method has the advantages that the factory production is not influenced by natural environments such as severe weather, the construction period is more controllable, the working procedures are more simplified, and the production efficiency is far higher than that of manual operation;
(3) and (3) dry construction: the construction of the prefabricated part is mostly carried out by a dry method, so that water and electricity are saved, and the method is environment-friendly and energy-saving;
(4) no maintenance period: compared with the traditional construction, the prefabricated part disclosed by the invention can be used after being assembled without maintenance, so that the maintenance time cost is saved;
(5) the size is flexible: according to the invention, the L-shaped component and the vertical plate type component are combined for use, so that the liquid storage amount of the assembled water pool can be increased according to actual conditions, and different use requirements can be met;
(6) and (3) seepage resistance and corrosion resistance: the invention can perform anti-seepage treatment on the L-shaped member and the vertical plate type member and can store waste liquid containing acid, alkali and oil stains.
(7) Green and environment-friendly: the prefabricated part is produced industrially, the construction waste on the construction site is reduced, the phenomena of dust flying and noise buzzing in the construction process are avoided, and green construction is realized.
(8) The design is reasonable: the invention is formed by combining L-shaped prefabricated components, has good stability, does not need additional support, reduces the construction risk and reduces the construction difficulty.
The prefabricated assembled water pool in the invention absorbs the advantages of the assembled construction technology, forms the modular, standardized and large-scale production technology and the standardized assembly process technology, shortens the construction period to the maximum extent, improves the construction efficiency, protects the ecological environment and reduces the noise pollution of the construction site under the condition of meeting certain strength, durability and stability; meanwhile, the invention improves the construction efficiency of the pre-drilling engineering, solves the problem of short construction period of the pre-drilling engineering for a long time, and provides powerful support for improving the drilling speed; the method has great practical significance for promoting the construction of sponge cities, efficiently constructing and accelerating the realization of scientific management of urban rainfall floods.
Drawings
FIG. 1 is a schematic view of a first structure of the present invention;
FIG. 2 is a second schematic structural diagram of the present invention;
FIG. 3 is a top view of FIG. 1;
FIG. 4 is an enlarged view of a portion of the connecting bolt of the present invention;
FIG. 5 is a schematic structural view of an L-shaped member according to the present invention;
FIG. 6 is a schematic structural view of a riser member according to the present invention;
FIG. 7 is a schematic drawing of a leveling line according to the present invention.
Detailed Description
The principles and features of this invention are described below in conjunction with the following drawings, which are set forth by way of illustration only and are not intended to limit the scope of the invention.
Examples
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. The components of embodiments of the present invention generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations.
Thus, the following detailed description of the embodiments of the present invention, presented in the figures, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus once an item is defined in one figure, it is not further defined and explained by advocate in subsequent figures.
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "communicating," "connected," and "connected" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Some embodiments of the invention are described in detail below with reference to the accompanying drawings. The embodiments described below and the features of the embodiments can be combined with each other without conflict.
Referring to fig. 1 to 7, the prefabricated assembly type sink of the present invention includes a sink base plate 1 serving as a support installation body and prefabricated parts 2 provided on the sink base plate 1, and the prefabricated assembly type sink is formed by splicing the sink base plate 1 with the prefabricated parts 2. The prefabricated part 2 and the pool bottom plate 1 are manufactured in a factory, and compared with cast-in-place construction, the product quality is controllable, and the dimensional accuracy is high; compared with the traditional cast-in-place construction, the invention has the advantages that the factory production is not influenced by the natural environment such as severe weather, the construction period is more controllable, the working procedures are more simplified, and the production efficiency is far higher than that of manual operation. In addition, the prefabricated member 2 can be used after being assembled without maintenance in the splicing process, so that the time cost of concrete maintenance is saved.
Referring to fig. 1 to 2, the prefabricated part 2 comprises L-shaped members 21 arranged at the top end of the pool bottom plate 1 and vertical plate-type members 22 arranged between the transversely adjacent L-shaped members 21, wherein the L-shaped members 21 have the thickness of 200mm, the width of 2200mm and the side width of 2200 mm; the floor member 22 has a thickness of 200mm, a width of 1200mm, and a side width of 2200 mm. The height of the prefabricated assembled type pool in this embodiment is 2400mm, so the height of the prefabricated part 2 of the L-shaped member 21 and the rising plate member 22 is set to 1200 mm. The height of the prefabricated part 2 of the L-shaped member 21 and the riser member 22 may be set to 2400mm or the like in other embodiments.
Referring to fig. 4 to 5, the inner side of the corner of the L-shaped member 21 is provided with a structural rib 5 for improving the strength of the L-shaped member 21, and two ends of the structural rib 5 are respectively fixedly connected with two sides of the L-shaped member 21, so that the strength of the corner of the L-shaped member 21 is enhanced, and the strength of the whole L-shaped member 21 is further enhanced. Meanwhile, the top sides of the L-shaped member 21 and the vertical plate member 22 are both provided with the lifting points 6, and the lifting points 6 arranged on the top sides of the L-shaped member 21 and the vertical plate member 22 are convenient for workers to lift the L-shaped member 21 and the vertical plate member 22, and the installation direction of the L-shaped member 21 and the vertical plate member 22 is adjusted. In the embodiment, 2M 24 hoisting points 6 are arranged on the top side of each L-shaped member 21, and two sides of each L-shaped member 21 are respectively 1; each vertical plate type member 22 is provided with 2M 24 hoisting points 6, 4M 24 bolts connected with a support frame, and the front and back of each vertical plate type member 22 are two; in the process of hoisting the L-shaped member 21 and the floor member 22, the hoisting point 6 is mainly used for connecting the member and a hook hanger, and after hoisting is completed, the hanger is unscrewed from the hoisting point 6.
Referring to fig. 1 to 3, a connecting bolt 3 for fixedly connecting the L-shaped member 21 and the vertical plate member 22 is disposed between the L-shaped member 21 and the vertical plate member 22, connecting holes 4 are disposed on both sides of the L-shaped member 21 and the vertical plate member 22, and both ends of the connecting bolt 3 are respectively connected to the connecting holes 4. Meanwhile, the connecting bolts 3 are arranged between the vertically adjacent L-shaped components 21, and the connecting bolts 3 are also arranged between the vertically adjacent vertical plate type components 22. The connecting bolt 3 is screwed into a pre-embedded hoisting nut on the surface of an installed component in advance before the next prefabricated component 2 is hoisted, the next prefabricated component 2 is hoisted to the position close to the installation position by using a crane, when the components stop swinging, when the interval between an upper prefabricated L-shaped component 21 and a lower prefabricated L-shaped component 21 is about 10cm, a screw rod is used for aligning holes, and the bolt is prevented from being forcibly penetrated in operation. If the screw can not be inserted, the hoisted gourd is used for leveling, and the screw can be ensured to be aligned with the hole. The connecting piece is fastened after the member is in place, the installed connecting bolts 3 are high-strength bolts, connecting pairs of high-strength bolts, nuts and washers in the same batch are required to be selected according to design specifications, and the bolts, the nuts and the washers in one batch can not be used in a mixed mode with the bolts in other batches.
And filling pads 7 are arranged between the vertically adjacent L-shaped components 21, and the filling pads 7 are also arranged between the vertically adjacent vertical plate type components 22. In the invention, after a layer of prefabricated parts 2 is installed, workers need to lay a layer of filling pad 7 above the prefabricated parts 2 to ensure the connection tightness of the prefabricated parts 2 and use the prefabricated parts 2 for leveling and waterproofing. After the filling pad 7 is laid, a worker screws the connecting bolt 3 for connecting the upper prefabricated component 2 and the lower prefabricated component 2 into the reserved hole of the L-shaped component 21, and then hoists the prefabricated component 2 on the next layer until the hoisting is finished.
Referring to fig. 1 to 7, the assembling method of the prefabricated assembled type pool in the present invention sequentially comprises the following steps:
s1: the L-shaped member 21 and the vertical plate member 22 are processed according to design requirements, the prefabricated member 2 is divided into two specifications of the L-shaped member 21, namely PC1 model and the vertical plate member 22, namely PC2 model, wherein the thickness of the PC1 model L-shaped member 21 is 200mm, the width is 2200mm, the side width is 2200mm, the thickness of the PC2 model vertical plate member 22 is 200mm, the width is 1200mm, and the side width is 2200mm, therefore, the height of the prefabricated water pool in the embodiment is 2400mm, so the height of the prefabricated member 2 of the L-shaped member 21 and the vertical plate member 22 is 1200 mm.
2M 24 hoisting points 6 are arranged on each L-shaped member 21, two sides of each L-shaped member are respectively 1, and 2M 24 hoisting points 6 are arranged on each vertical plate type member 22; in the process of hoisting the L-shaped member 21 and the vertical plate member 22, the hoisting point 6 is mainly used for connecting the member and a lifting hook hanger, after hoisting is finished, the hanger is screwed out from the hoisting point 6, and then bolts for connecting the upper member and the lower member are screwed. Meanwhile, 2 connections are reserved on two sides of the L-shaped and vertical plate type prefabricated components 2 along the height direction and are used for horizontally and fixedly connecting the same-layer prefabricated components 2 and installing connecting bolts 3. The bottom of the L-shaped component 21 is reserved with 2 holes, the two sides of each L-shaped component are respectively 1, and the L-shaped component is used for being fixedly connected with the lower layer of the prefabricated component 2 and installing the connecting bolts 3, and the bottom of the vertical plate type component 22 is reserved with 1 connecting hole 4, and the L-shaped component is used for being fixedly connected with the lower layer of the prefabricated component 2 and installing the connecting bolts 3.
S2: leveling and paying off on site, and determining the hoisting positions of the L-shaped component 2 and the vertical plate component 22 of the assembled water pool; the invention adopts 'inner-approximation' paying off, namely, four standard axes of each square well are arranged according to coordinates, two control piles are arranged in the directions of the longitudinal axis and the transverse axis respectively, four control axes of a building are determined by a theodolite, and the intersection points of the axes are used as control points. The worker sequentially releases the longitudinal axis and the transverse axis of the L-shaped member 21, the inner side line and the node line of the L-shaped member 21 according to the control axis and the control horizontal line, and marks the position line and the serial number of the prefabricated member 2; the axis pay-off deviation must not exceed 2 mm. However, when the paying-off of the constructor encounters continuous deviation, the adjustment from one axis in the middle of the building to two sides is considered.
S3: hoisting the L-shaped member 2 and the vertical plate type member 22, and installing the assembled water pool; because the inner diameter of the prefabricated assembled water pool in the embodiment is 4000mm multiplied by 4000mm, the outer diameter is 4400mm multiplied by 4400mm, and the height is 2400 mm; the prefabricated member is formed by hoisting and splicing 8L-shaped members 21 in 2 layers, wherein 8 PC1 types, namely 8 prefabricated members 2 on the first layer are assembled by adopting the same method after the prefabricated members 2 on the second layer are installed, the adjacent L-shaped members 21 are mechanically connected by adopting a phi 24 connecting bolt 3, and gaps between the adjacent L-shaped members 21 are filled by using assembly type special sealant.
When the size of the prefabricated assembled water pool in the embodiment is expanded to 6200mm multiplied by 6200mm as the minimum inner diameter, 6600mm multiplied by 6600mm as the minimum outer diameter and 2400mm as the minimum height, the invention needs to adopt the L-shaped member 21 and the vertical plate type member 22 to be combined and assembled so as to achieve the size standard of the combined and assembled water pool. The prefabricated assembled water pool is formed by hoisting and splicing 8L-shaped components 21 and 8 vertical plate type components 22 in 2 layers, wherein 8 PC1 models and 8 PC2 models and 8 PC1 components and a PC2 component are mechanically connected by a phi 24 connecting bolt 3, and gaps between adjacent prefabricated components 2 are filled with special prefabricated sealant.
Before hoisting, a worker buckles a hoisting chain or a chain block, a pulling rope and a steel wire rope on a hoisting point 6 of an L-shaped member 21, wherein the hoisting chain and the steel wire rope are used for fixing the L-shaped member 21 and a hoisting tool, the hoisting chain also has the function of leveling the L-shaped member 21 in the hoisting process, and the pulling rope is used for adjusting the direction and the position of the L-shaped member 21 in the hoisting process; after the first L-shaped member 21 is placed on the foundation cushion layer, the supporting end seats are installed at the embedded M24 bolts of the vertical plate type member 22 in advance, and temporary supporting frames on the front surface and the back surface of the vertical plate type member 22 are installed after positioning, so that the stability of the vertical plate member is maintained.
When hoisting the L-shaped member 2, the worker fastens the pull ropes on two sides above the L-shaped member 21 according to the measured central shaft and side line, and adjusts the direction and the position of the L-shaped member 21 by using the pull ropes in the process of hoisting and slowly falling so as to enable the L-shaped member 21 to be approximately in place. When the first layer is 3-5 cm away from the ground, a worker needs to use a level detector to perform horizontal calibration, if the first layer is not horizontal, the worker can use a lifting chain or a chain block to adjust so that the component is horizontal, and the first layer can slowly fall in place behind the component; the L-shaped component 21 on the second layer is arranged at the position with the vertical distance of about 10cm, a connecting screw rod needs to be used for aligning holes, if the L-shaped component cannot penetrate through the holes, the hand chain block for hoisting is used for leveling, and the L-shaped component can slowly fall into place when the connecting screw rod enters the holes. When the condition that the leveling cannot be achieved in the hoisting and mounting process occurs, angle steel and a gasket are used for leveling, and the installation of each layer of components can be ensured to be level and smooth.
S4: the L-shaped member 21 and the upright plate member 22 are fastened by attaching the connecting bolt 3 thereto;
s4-1: mounting the connecting bolt 3;
the connecting bolt 3 should be screwed into the pre-embedded hoisting nut on the surface of the installed prefabricated part 2 in advance before the next prefabricated part 2 is hoisted, the next prefabricated part 2 is hoisted to the position near the installation position by using a crane, and when the swinging of the members stops, when the upper L-shaped member 21 and the lower L-shaped member 21 are spaced by about 10cm, the screw rod hole alignment is carried out. The connecting bolt 3 is strictly prohibited to be forcibly penetrated in the operation process; if the hole can not be penetrated, the hoisted gourd is used for leveling, and the hole can be aligned when the connecting screw rod can align the hole. After the prefabricated part 2 is in place, the fastening of the connecting bolts 3 is started. The connecting bolt 3 is a high-strength bolt, and the connecting pairs of the high-strength bolt, the nut and the washer in the same batch are selected according to design rules; one batch of bolts, nuts and washers cannot be used in combination with other batches of bolts.
After a layer of prefabricated parts 2 is installed, a layer of filling pad 7 needs to be laid above the prefabricated parts 2 by workers to ensure the connection tightness of the prefabricated parts 2 and be used for leveling and waterproofing the prefabricated parts 2. After the filling pad 7 is laid, a worker screws the connecting bolt 3 for connecting the upper prefabricated component 2 and the lower prefabricated component 2 into the reserved hole of the L-shaped component 21, and then hoists the prefabricated component 2 on the next layer until the hoisting is finished.
S4-2: fastening the connecting bolt 3;
the fastening of the connecting bolt 3 in the present invention is divided into initial screwing and final screwing. In the initial screwing, when the number of the connecting bolts 3 is large, a part of the axial force of the bolt fastened first is consumed to overcome the deformation, and the axial force of the bolt fastened first 3 is reduced by the distribution of the axial force after the bolts 3 are fastened around the bolt. Therefore, in order to minimize the influence of the fastening bolt 3 during the fastening process, measures are taken to minimize the mutual influence, and it is specified that the fastening is performed at least twice in the high-strength bolt fastening. The first fastening is called initial screwing, and the initial screwing axial force is generally up to 50% of the standard axial force. The final tightening is the final tightening of the installed connecting bolt 3, which is called final tightening. The final axial force value is targeted at the standard axial force and should meet the design requirements. Considering creep of the high-strength connecting bolt 3 and loss of the pretensioning force at the time of final tightening, the final tightening is generally 5% to 10% of the design pretensioning force according to the test.
S5: installing temporary support rods on the front and back sides of the vertical plate type member 22, and removing the temporary support rods after the pool is installed;
after the single vertical plate type member 22 is fixed by the connecting bolts 3, temporary supporting rods are installed on the front and back sides of the vertical plate type member 22 to ensure that the vertical plate type member 22 is stable and does not have the risk of collapse, then the connecting bolts 3 for connecting the L-shaped member 21 and the vertical plate type member 22 are connected, and after the single prefabricated assembled water pool is completely installed, all the temporary supporting rods on the two sides of the vertical plate type member 22 can be detached.
S6: performing waterproof and anticorrosive treatment on the prefabricated assembled water pool;
the waterproof and antiseptic treatment in the embodiment comprises two schemes:
scheme 1: before waterproof and anticorrosion treatment is carried out on the prefabricated assembled water pool, materials and tools such as SPU waterproof paint, polyurethane coating cloth, a waterproof blanket, impermeable cloth, a blower and the like which are needed to be used in construction are prepared; and then cleaning the construction surface, checking and removing sundries in the prefabricated assembled water pool, particularly thoroughly cleaning sundries such as sharp stones, tree roots and the like, wherein the base surface of the prefabricated assembled water pool cannot have local concave-convex phenomenon, and the anti-seepage material is prevented from being punctured. The paving workers need to wear the soft-sole shoes to prevent materials such as coating cloth, anti-seepage pad cloth and the like from being damaged.
After the prefabricated assembly type water pool is cleaned, the connecting holes 4 in the prefabricated parts 2 need to be plugged by cement concrete, so that the connecting bolts 3 in the prefabricated parts 2 are prevented from being corroded. The waterproof coating material is required to be coated 3 times during construction, and the upturning height of the waterproof coating around the prefabricated assembled water pool along the pool wall is not less than 250 mm; after each layer of construction is finished, the protection is strictly carried out, and people are not allowed to step on the floor. After the waterproof coating is air-dried, the materials such as the waterproof blanket and the like need to be subjected to appearance inspection before being laid, and the found defects such as mechanical damage, holes, breakage and the like are recorded and repaired. Before the waterproof material is cut, relevant sizes of the waterproof material are measured, and the waterproof material is cut according to actual conditions, wherein the lapping width of seams between films in film laying is not less than 150 mm. And artificial wrinkles are avoided in the laying process, and the artificial wrinkles are tensioned and paved as much as possible when the temperature is low. After the laying is finished, backfilling the working area outside the prefabricated assembly type water pool, wherein the filling compactness is not less than 94%, and each layer is not higher than 50cm by adopting layered rolling.
Scheme 2: before waterproof and anticorrosion treatment is carried out on the prefabricated assembly type water pool, materials and tools such as a sealant, a glue gun, a brush, a waterproof adhesive tape butyl adhesive tape and the like which are needed in construction are prepared; and then cleaning the construction surface, wherein dust, adsorbed oil, moisture, rust, cement floating slurry and other substances which are unfavorable for the sealant bonding exist at the joint of the assembly type building, so that the performance of the sealant is influenced and the sealant needs to be removed. The treated substrate surface should be clean, dry, clean, and uniform in texture.
After a construction surface is cleaned, filling sealant, and filling the sealant into a sealant gun, wherein the diameter of a glue nozzle of the sealant gun for filling the sealant is smaller than the width of a glue injection joint, the glue nozzle is extended to the bottom of the joint during glue application, glue injection is slow, continuous and uniform, the joint is ensured to be filled with the sealant, and bubbles or cavities are prevented from being generated when the glue nozzle moves too fast; at the crossing seams and edges, special care is taken to prevent air bubbles from forming during filling.
And after the sealing structure adhesive is air-dried, the waterproof adhesive tape can be pasted, construction with water can not be carried out during pasting, and the adhesive tape is kept to be smoothly pasted. The corner of the seam of the prefabricated assembled water pool is emphasized, and after a layer of waterproof adhesive tape is adhered, the edges of two sides of the waterproof adhesive tape are adhered. After the prefabricated parts 2 of the prefabricated assembled water pool are installed, the connecting holes 4 in the prefabricated parts 2 need to be sealed by cement concrete, so that the connecting bolts 3 in the prefabricated parts 2 are prevented from being corroded.
The prefabricated components are manufactured in factories, compared with cast-in-place construction, the prefabricated components have controllable product quality and high dimensional precision, and compared with the traditional cast-in-place construction, the factory production is not influenced by natural environments such as severe weather, the construction period is more controllable, the working procedures are more simplified, and the production efficiency is far higher than that of manual operation. The construction of the prefabricated parts is mostly carried out by a dry method, water and electricity are saved, the prefabricated parts are environment-friendly and energy-saving, and compared with the traditional construction, the prefabricated parts can be used after being assembled without maintenance, and the maintenance time cost is saved; meanwhile, the L-shaped component and the vertical plate type component are combined for use, so that the liquid storage amount of the assembled water pool can be increased according to actual conditions, and different use requirements can be met; the anti-seepage treatment method disclosed by the invention is used for carrying out anti-seepage treatment on the L-shaped member and the vertical plate type member, waste liquid containing acid, alkali and oil stains can be stored, the prefabricated member is industrially produced, the construction waste on a construction site is reduced, the phenomena of dust flying and noise buzzing in the construction process are avoided, and the green construction is realized.
The prefabricated assembled water pool absorbs the advantages of the assembled construction technology, forms the modular, standardized and large-scale production technology and the standardized assembly process technology, shortens the construction period to the maximum extent, improves the construction efficiency, protects the ecological environment and reduces the noise pollution of the construction site under the condition of meeting certain strength, durability and stability; meanwhile, the invention improves the construction efficiency of the pre-drilling engineering, solves the problem of short construction period of the pre-drilling engineering for a long time, and provides powerful support for improving the drilling speed; the method has great practical significance for promoting the construction of sponge cities, efficiently constructing and accelerating the realization of scientific management of urban rainfall floods.
It is to be noted that, in this document, the terms "comprises", "comprising" or any other variation thereof are intended to cover a non-exclusive inclusion, so that an article or apparatus including a series of elements includes not only those elements but also other elements not explicitly listed or inherent to such article or apparatus. Without further limitation, an element defined by the phrase "comprising … …" does not exclude the presence of additional like elements in the article or device comprising the element.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (8)

1. The utility model provides a prefabricated assembled pond, its characterized in that includes pond bottom plate (1) and prefabricated component (2) of setting on pond bottom plate (1), prefabricated component (2) is including setting up multiunit L type component (21) on pond bottom plate (1), setting up riser formula component (22) between horizontal adjacent L type component (21) and setting up connecting bolt (3) between L type component (21) and riser formula component (22), L type component (21) all are equipped with connecting hole (4) with the avris of riser formula component (22), the both ends of connecting bolt (3) are connected with connecting hole (4) respectively.
2. The prefabricated water pool of claim 1, wherein the connecting bolts (3) are arranged between the vertically adjacent L-shaped members (21), and the connecting bolts (3) are also arranged between the vertically adjacent vertical plate members (22).
3. Prefabricated water pool according to claim 1, characterized in that the inside of the corners of the L-shaped members (21) are provided with construction ribs (5).
4. Prefabricated water pool according to any of claims 1 to 3, wherein the top sides of the L-shaped members (21) and the riser members (22) are provided with lifting points (6).
5. Prefabricated water pool according to any of claims 1 to 3, wherein filling mats (7) are provided between vertically adjacent L-shaped members (21) and filling mats (7) are also provided between vertically adjacent riser members (22).
6. The assembling method of the prefabricated assembled water pool is characterized by sequentially comprising the following steps of:
s1: processing an L-shaped component (21) and a vertical plate component (22) according to design requirements;
s2: leveling and paying off on site, and determining the hoisting positions of an L-shaped component (21) and a vertical plate component (22) in the assembled water pool;
s3: hoisting the L-shaped member (21) and the vertical plate type member (22) and installing the prefabricated assembled water pool;
s4: mounting and fastening a connecting bolt (3) on the L-shaped member (21) and the vertical plate member (22);
s5: temporary support rods are arranged on the front side and the back side of the vertical plate type component (22), and the temporary support rods are removed after the prefabricated assembly type pool is installed;
s6: and (4) performing waterproof and anticorrosive treatment on the prefabricated assembled water pool.
7. The assembling method of the prefabricated assembled type pool, according to the claim 6, wherein in the step S2, four standard axis control piles of each pool are set according to the coordinates, four control axes of the pool are determined by theodolite, the intersection points of the axes are used as control points, then the longitudinal and transverse axes of the L-shaped member (2), the inner side line and the node line of the L-shaped member (2) are sequentially discharged according to the control axes and the control horizontal line, and the member position line and the member number are marked.
8. The assembling method of the prefabricated assembled type water pool according to claim 7, wherein the fastening of the connecting bolt (3) in the step S5 is divided into two times of fastening, the first time of screwing up the axial force value reaches 45% -55% of the standard axial force, and the second time of screwing up the axial force value reaches the standard axial force.
CN202010832927.7A 2020-08-18 2020-08-18 Prefabricated assembled water pool and assembling method Pending CN111809951A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010832927.7A CN111809951A (en) 2020-08-18 2020-08-18 Prefabricated assembled water pool and assembling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010832927.7A CN111809951A (en) 2020-08-18 2020-08-18 Prefabricated assembled water pool and assembling method

Publications (1)

Publication Number Publication Date
CN111809951A true CN111809951A (en) 2020-10-23

Family

ID=72859160

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010832927.7A Pending CN111809951A (en) 2020-08-18 2020-08-18 Prefabricated assembled water pool and assembling method

Country Status (1)

Country Link
CN (1) CN111809951A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112746765A (en) * 2020-12-29 2021-05-04 河北华友文化遗产保护股份有限公司 Rapid construction method for fire pool
CN114592739A (en) * 2022-03-22 2022-06-07 辽宁省城乡市政工程集团有限责任公司 Semi-assembly type ultra-deep superposed water storage tank and construction process
CN115126319A (en) * 2022-06-30 2022-09-30 湖北宇辉智能科技有限公司 Prefabricated assembled plate combined rectangular pool and manufacturing and mounting method
PL441833A1 (en) * 2022-07-25 2024-01-29 Politechnika Rzeszowska im. Ignacego Łukasiewicza Connector for prefabricated elements of a cylindrical tank and method of connecting prefabricated elements of cylindrical tank using this joint

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112746765A (en) * 2020-12-29 2021-05-04 河北华友文化遗产保护股份有限公司 Rapid construction method for fire pool
CN114592739A (en) * 2022-03-22 2022-06-07 辽宁省城乡市政工程集团有限责任公司 Semi-assembly type ultra-deep superposed water storage tank and construction process
CN114592739B (en) * 2022-03-22 2024-04-26 辽宁省城乡市政工程集团有限责任公司 Semi-assembled ultra-deep superposed water storage tank and construction process
CN115126319A (en) * 2022-06-30 2022-09-30 湖北宇辉智能科技有限公司 Prefabricated assembled plate combined rectangular pool and manufacturing and mounting method
CN115126319B (en) * 2022-06-30 2023-12-12 湖北宇辉智能科技有限公司 Prefabricated assembled plate combined rectangular water tank and manufacturing and mounting method
PL441833A1 (en) * 2022-07-25 2024-01-29 Politechnika Rzeszowska im. Ignacego Łukasiewicza Connector for prefabricated elements of a cylindrical tank and method of connecting prefabricated elements of cylindrical tank using this joint

Similar Documents

Publication Publication Date Title
CN111809951A (en) Prefabricated assembled water pool and assembling method
WO2021253808A1 (en) Building technique for low-carbon society in high-technology era
CN110805257B (en) Flower basket overhanging type section steel bearing beam structure and construction method
CN100473790C (en) Tower crane foundation for construction and manufacturing method thereof
CN104594387A (en) Improved post-pouring strip advanced water-stopping construction method
CN105926765B (en) The regular polygon of falling umbrella steel structure module and its installation method
CN111926910A (en) Installation method of fabricated building
CN203514814U (en) Overhead building putting-up machine
CN108915107B (en) Construction method of EPS inorganic infiltration insulation board
CN102251537A (en) Construction method for installing block slurry of sizing block by equipment
CN101029524A (en) Mosaic tile built-in fitting, external-wall thermal-insulating structure and its construction
CN204263314U (en) Multifunction combined adjustable type T plate template system
CN105672664A (en) Integral heat insulation wallboard building system
CN107190889A (en) The integrated wall of steel frame lightweight sandwich boards and its construction method
CN113882562A (en) Construction method of special-shaped double-sided wood grain fair-faced concrete wall
CN113958138A (en) Green formwork system construction method
CN111305399A (en) Basement outer wall post-cast strip system and construction method thereof
US4096675A (en) Split-slab house construction
CN212453863U (en) Prefabricated assembled pond
CN111576878A (en) Construction process for quick-release system of aluminum alloy template
CN216665090U (en) Automatic spraying and health preserving system for basement shear wall
CN206174293U (en) Prefabricated constructional column
CN1047425C (en) Attaching process for colour facing concrete board
CN115247508A (en) Construction method of large-scale tank body structure of sewage treatment station
CN210395868U (en) Reinforcing steel bar split heads

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination