CN102704684B - Construction method for high-strength shaping combined template of plank frame of shear wall - Google Patents

Construction method for high-strength shaping combined template of plank frame of shear wall Download PDF

Info

Publication number
CN102704684B
CN102704684B CN201210207235.9A CN201210207235A CN102704684B CN 102704684 B CN102704684 B CN 102704684B CN 201210207235 A CN201210207235 A CN 201210207235A CN 102704684 B CN102704684 B CN 102704684B
Authority
CN
China
Prior art keywords
formwork
wall
shaped
keel
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210207235.9A
Other languages
Chinese (zh)
Other versions
CN102704684A (en
Inventor
陈明伟
洪文聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN LONGCHENG CONSTRUCTION GROUP Co Ltd
Original Assignee
FUJIAN LONGCHENG CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN LONGCHENG CONSTRUCTION GROUP Co Ltd filed Critical FUJIAN LONGCHENG CONSTRUCTION GROUP Co Ltd
Priority to CN201210207235.9A priority Critical patent/CN102704684B/en
Publication of CN102704684A publication Critical patent/CN102704684A/en
Application granted granted Critical
Publication of CN102704684B publication Critical patent/CN102704684B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明公开了一种剪力墙木框定型组合模板的施工方法,包括下述步骤:一、模板设计与配置;二、测量放线;三、安装准备;四、定型模板安装;五、拆模、清理、堆放。本发明采用组合定型模板进行施工,并通过水平龙骨对模板进行加固,可以减少混凝土的截面偏差,且可提高混凝土施工质量及混凝土外观质量,同时可材料降低损耗、降低劳动强度,节约成本。

The invention discloses a construction method for a shear wall wooden frame stereotyped composite template, comprising the following steps: 1. template design and configuration; 2. measurement and setting out; 3. installation preparation; Mold, clean, stack. The present invention adopts a combined shaped formwork for construction, and reinforces the formwork with a horizontal keel, which can reduce the cross-section deviation of concrete, improve the concrete construction quality and concrete appearance quality, reduce material loss, reduce labor intensity, and save costs.

Description

剪力墙木框高强定型组合模板施工方法Construction method of high-strength shaped composite formwork with wooden frame of shear wall

技术领域 technical field

本发明涉及建筑施工的技术领域,尤指一种剪力墙木框高强定型组合模板施工方法。 The invention relates to the technical field of building construction, in particular to a construction method for a shear wall wooden frame high-strength shaped composite formwork.

背景技术 Background technique

现浇钢筋混凝土剪力墙结构是当前高层建筑的主要结构型式,随着社会建筑施工水平的不断提高,设计要求剪力墙结构达到清水混凝土标准日益普遍。目前钢筋混凝土剪力墙的施工大多数还是采用普通木模板进行施工,每层施工都需要重新配模,不但造成材料浪费,模板的周转次数少,而且劳动强度大、工作效率低,将增加工时,增加成本。 The cast-in-place reinforced concrete shear wall structure is the main structural type of high-rise buildings at present. With the continuous improvement of the construction level of social buildings, it is increasingly common for the design to require the shear wall structure to meet the fair-faced concrete standard. At present, most of the construction of reinforced concrete shear walls is carried out with ordinary wooden formwork, and each layer of construction needs to be re-formulated, which not only causes waste of materials, but also has less turnover times of formwork, and has high labor intensity and low work efficiency, which will increase working hours. ,increase cost.

此外,目前的施工方法,楼层过渡处易出现错台,且模板的拼接不严密,尤其是混凝土边角以及细部结构不精细,混凝土浇筑截面易出现偏差,因此工程质量及混凝土外观质量都不易保证。 In addition, with the current construction method, it is easy to have wrong platform at the transition of the floor, and the splicing of the formwork is not tight, especially the concrete corner and detail structure are not fine, and the concrete pouring section is prone to deviation, so the quality of the project and the quality of the appearance of the concrete are not easy to guarantee .

发明内容 Contents of the invention

本发明所要解决的技术问题在于提供一种剪力墙木框高强定型组合模板施工方法,采用组合定型模板进行剪力墙的施工,可以减少混凝土的截面偏差,且可提高混凝土施工质量及混凝土外观质量,同时可材料降低损耗、降低劳动强度,节约成本。 The technical problem to be solved by the present invention is to provide a construction method of high-strength shaped composite formwork for a shear wall wooden frame, which can reduce the cross-sectional deviation of concrete and improve the quality of concrete construction and the appearance of concrete At the same time, it can reduce material loss, reduce labor intensity, and save costs.

为解决上述技术问题,本发明的技术解决方案是: For solving the problems of the technologies described above, the technical solution of the present invention is:

一种剪力墙木框定型组合模板的施工方法,包括下述步骤: A construction method for a shear wall wooden frame stereotyped composite formwork, comprising the following steps:

一、模板设计与配置:采用定型模板,并通过龙骨进行加固; 1. Formwork design and configuration: use the finalized formwork and reinforce it through the keel;

1)设计 1) design

a、根据施工图纸设计不同规格的定型模板,确定非标准模板的使用位置、尺寸,并绘制模板拼装图、大样图; a. According to the construction drawings, design templates of different specifications, determine the use position and size of non-standard templates, and draw template assembly diagrams and large-scale drawings;

所述的定型模板面板、两条横肋及若干竖肋;两条横肋分别置于面板的上下两端,竖肋以一定间距竖向设置并与横肋相抵住,横、竖肋与面板采用螺钉固定; The stereotyped formwork panel, two transverse ribs and several vertical ribs; the two transverse ribs are respectively placed at the upper and lower ends of the panel, and the vertical ribs are vertically arranged at a certain interval and resist the transverse ribs, and the horizontal and vertical ribs are connected to the panel Fix with screws;

b、根据刚度要求确定龙骨尺寸、间距,并确定螺栓规格、间距; b. Determine the keel size and spacing according to the stiffness requirements, and determine the bolt specifications and spacing;

龙骨用于定型模板的加固,该龙骨采用双拼方钢管,并通过若干穿墙螺栓从两根方钢管中间穿过,通过锁具与穿墙螺栓连接; The keel is used to reinforce the shaped formwork. The keel is made of double square steel pipes, and passes through the middle of the two square steel pipes through several wall bolts, and is connected with the wall bolts through locks;

2)配置 2) Configuration

根据上述设计方案,统计各种规格模板的数量,进行各定型模板的制作,并对每块模板进行编号,之后进行分类堆放; According to the above design plan, count the number of templates of various specifications, make each finalized template, and number each template, and then classify and stack them;

二、测量放线:弹好柱墙身位置线及支模控制线,并弹好门窗洞口位置线,测量并画出标高线。 2. Measure and set out the line: play the position line of the column wall and the control line of the formwork, and play the position line of the door and window openings, measure and draw the elevation line.

三、安装准备: 3. Installation preparation:

1)确定墙身钢筋骨架绑扎是否完毕,是否已安装预埋管线、接线盒、电箱,并已通过各分项工程的隐检工作; 1) Determine whether the binding of the steel skeleton on the wall is completed, whether the embedded pipelines, junction boxes, and electrical boxes have been installed, and have passed the hidden inspection of each sub-project;

2)将定型模板表面水泥浆等杂物清理干净,并在模板与混凝土接触面涂刷好脱模剂,把清理完毕并涂刷过脱模剂的模板搬运到相应位置; 2) Clean up the cement slurry and other debris on the surface of the shaped formwork, and apply a release agent on the contact surface between the formwork and the concrete, and move the formwork that has been cleaned and painted with the release agent to the corresponding position;

四、定型模板安装: 4. Installation of stereotyped formwork:

1)组合定型模板的安装原则为:“先横墙,后纵墙”;“先外墙,后内墙”;“先小板块模,后大板块模,大板块模压住小板块模”; 1) The installation principle of the combination stereotyped formwork is: "first the horizontal wall, then the vertical wall"; "first the outer wall, then the inner wall"; "first the small plate formwork, then the large plate formwork, the large plate formwork presses the small plate formwork" ;

2)定型模板底座及外墙三角架安装 2) Shaped formwork base and external wall tripod installation

a、底座安装:在模板下口与地面接触面粘贴海绵条,再于墙根钉木方条进行找平; a. Base installation: Paste sponge strips on the contact surface between the lower opening of the formwork and the ground, and then nail wooden square strips at the root of the wall for leveling;

b、外墙三脚架安装:将外墙的外侧定型模板下口伸至下层墙顶以下一定距离;并采用外墙三角架支撑和加固外墙外侧的定型模板; b. External wall tripod installation: Extend the lower opening of the external shaped formwork of the external wall to a certain distance below the top of the lower wall; and use the external wall tripod to support and reinforce the external shaped formwork of the external wall;

3)内外墙组合定型模板就位 3) The combination of internal and external walls and the finalized formwork are in place

a、外墙定型模板安装:利用塔吊把外墙外侧定型模板架设在外墙三角架上并临时固定,并将所述的穿墙螺栓一端固定于该外侧墙模板上;之后将外墙内侧定型模板架立在墙模底座上,立好后用穿墙螺栓与已立好外侧墙模定位加固; a. Installation of external wall shaped formwork: use a tower crane to erect the outer wall shaped formwork on the outer wall tripod and temporarily fix it, and fix one end of the wall-through bolt on the outer wall formwork; then install the outer wall inner shaped formwork Stand on the base of the wall formwork, and then use the through-wall bolts to position and reinforce the outside wall formwork that has been erected;

b、内墙定型模板安装:利用人工把内墙一侧组合定型模板架立在墙体钢筋骨架的一侧墙模底座上,单侧拼接完成后穿入所述的穿墙螺栓,并做好临时固定;钢筋骨架的另一侧组合定型模板同样架立在墙模底座上,立好后与已立好的原有一侧墙模穿墙螺栓连接定位加固; b. Installation of the shaped formwork for the inner wall: manually erect the combined shaped formwork on one side of the inner wall on the wall formwork base on one side of the steel reinforcement skeleton of the wall. Temporary fixation; the other side of the steel skeleton is also erected on the base of the wall formwork, and then connected with the wall bolts on the original side of the wall formwork that have been erected for positioning and reinforcement;

c、两侧墙模螺栓锁紧后,采用锁具进行主龙骨方钢管加固; c. After the wall formwork bolts on both sides are locked, locks are used to reinforce the main keel square steel pipe;

d、有楼面洞口一侧的模板安装同外墙外侧模板,将孔洞边一侧模板下口伸至下层墙顶以下下一定距离,洞口两侧模板采用可伸缩碳钢钢管对撑以控制洞口尺寸; d. The formwork on the side of the floor opening is installed with the formwork on the outside of the outer wall. The lower opening of the formwork on the side of the hole is extended to a certain distance below the top of the lower wall. The formwork on both sides of the opening is supported by telescopic carbon steel pipes to control the opening. size;

4)阴阳角结构组合定型模板的安装 4) Installation of yin and yang angle structure combined shaping formwork

对于结构阳角部位,采用铁锁链连接龙骨方钢管,将墙体两端阳角部位整体拉接紧固; For the external corners of the structure, iron chains are used to connect the keel square steel pipes, and the external corners at both ends of the wall are integrally pulled and fastened;

对于结构阴角部位,将一侧龙骨方钢管伸至转角处另一侧模板面板上,另一侧龙骨方钢管抵在前一侧龙骨方钢管上; For the inner corner of the structure, extend the keel square steel pipe on one side to the formwork panel on the other side of the corner, and the other keel square steel pipe against the front keel square steel pipe;

5)模板位置校正、垂直度调整并固定 5) Template position correction, verticality adjustment and fixation

定型墙模就位后,用可伸缩碳钢钢管抵住龙骨支撑于楼面稳定墙体两侧模板;之后采用吊线锤方法吊磁力线坠挂铅垂线,量测定型模板上、下口控制线距离,通过调整墙体两侧的碳钢钢管长度来修正模板垂直度; After the shaped wall formwork is in place, use the telescopic carbon steel pipe to support the keel and support the formwork on both sides of the floor to stabilize the wall; then use the pendant hammer method to hang the magnetic line of force and hang the plumb line, and measure the upper and lower control lines of the shaped formwork The verticality of the formwork is corrected by adjusting the length of the carbon steel pipes on both sides of the wall;

五、拆模、清理、堆放:当混凝土浇筑完成后,对定型模板进行拆除;拆模时,按支模的逆顺序进行,注意保护现浇面板,尽量利用大模板自重脱落,严禁强行砸撬模板;若自重脱模困难,则采用撬棍轻撬模板下口;拆除后的模板各种安装小配件应集中堆放。 5. Form removal, cleaning, and stacking: After the concrete pouring is completed, remove the shaped formwork; when removing the formwork, follow the reverse order of the formwork support, pay attention to protecting the cast-in-place panel, try to use the large formwork to fall off by its own weight, and forcibly smashing and prying is strictly prohibited Formwork; if it is difficult to remove the formwork by its own weight, use a crowbar to lightly pry the lower opening of the formwork; after dismantling, various installation accessories of the formwork should be stacked together.

所述定型模板的面板采用胶合板,横肋与竖肋均采用木方楞。 The panel of the shaped formwork is made of plywood, and the transverse ribs and vertical ribs are all made of square corrugated wood.

所述的穿墙螺栓包括穿墙螺杆、螺于该穿墙螺杆两端的扩大头螺母,该扩大头螺母外端设有螺柱,该螺柱与一螺母锁具螺固,该螺母锁具内端设有扩大头,外端设有至少一个锁孔。 The wall-through bolt includes a wall-through screw and an enlarged head nut screwed at both ends of the wall-through screw. The outer end of the enlarged head nut is provided with a stud, which is screwed with a nut lock, and the inner end of the nut lock is provided with a stud. There is an enlarged head, and the outer end is provided with at least one keyhole.

所述的锁具为插销式锁具,包括固定板及插销,该固定板上设有穿孔;在锁固龙骨时,将所述螺母锁具的外端从固定板上的穿孔穿过,之后将所述插销从固定板的外侧插于螺母锁具上的其中一个锁孔内。 The lock is a bolt-type lock, including a fixed plate and a bolt, and the fixed plate is provided with a perforation; when locking the keel, the outer end of the nut lock is passed through the perforation on the fixed plate, and then the The latch is inserted into one of the locking holes on the nut lockset from the outside of the fixing plate.

所述的外墙三角架包括三角固定架,在三角固定架的上方设有支撑横板,该支撑横板的外侧向上延伸有一凸沿,该凸沿上安装有一螺旋紧固件,所述三角固定架的内侧设有竖向槽,该竖向槽处设有一滑动片,该滑动片上设有孔。 The tripod on the outer wall includes a tripod, and a support horizontal plate is arranged above the tripod. The outer side of the support cross plate extends upwards with a convex edge, and a screw fastener is installed on the convex edge. The triangle The inner side of the fixed frame is provided with a vertical groove, and a sliding sheet is arranged at the vertical groove, and a hole is arranged on the sliding sheet.

采用上述方案后,本发明具有如下特点: After adopting the above scheme, the present invention has the following characteristics:

1.本发明采用组合定型木模板进行施工,并配合水平龙骨进行加固,较其它体系木模板整体性更好,材质强度、刚度更大,大大减少混凝土浇筑截面偏差,提高混凝土质量及观感。 1. The present invention uses a combination of shaped wooden formwork for construction and is reinforced with horizontal keels. Compared with other systems of wooden formwork, it has better integrity, greater material strength and rigidity, greatly reduces the deviation of the concrete pouring section, and improves the quality and appearance of concrete.

2.通过使用定型化和标准化模板,制作及拼装简单方便,易于装拆,加快了施工进度,提高劳动效率,节约劳动力成本,更能满足标准化施工的要求。 2. Through the use of stereotyped and standardized formwork, the production and assembly are simple and convenient, easy to assemble and disassemble, speed up the construction progress, improve labor efficiency, save labor costs, and better meet the requirements of standardized construction.

3.本发明的组合定型木模板采用局部整体工具式拼装,并采用多种专门设计的配件安装加固,对于混凝土边角以及细部结构施工更精细,模板拼接严密,更有利于工程质量的提高。同时增加了模板的周转次数,节约模板材料成本。 3. The combined and shaped wooden formwork of the present invention is assembled in the form of partial integral tools, and is installed and reinforced by a variety of specially designed accessories. The construction of concrete corners and detailed structures is more precise, and the formwork is tightly spliced, which is more conducive to the improvement of project quality. At the same time, the turnover times of the formwork are increased, and the cost of formwork materials is saved.

4.组合定型木模板易于分类编号,可提高人工搬运效率,减少塔吊用量,降低机械成本,同时也降低调运过程的安全风险。 4. The combined and shaped wooden formwork is easy to classify and number, which can improve the efficiency of manual handling, reduce the amount of tower cranes, reduce the cost of machinery, and also reduce the safety risk of the transportation process.

附图说明 Description of drawings

图1是本发明的施工工艺流程图; Fig. 1 is a construction process flow chart of the present invention;

图2A是本发明所述定型模板的平面示意图; Fig. 2A is a schematic plan view of the sizing template of the present invention;

图2B是本发明所述定型模板螺钉连接处的剖面图; Fig. 2B is a cross-sectional view of the screw connection of the shaped template according to the present invention;

图3是本发明所述模板龙骨加固安装示意图; Fig. 3 is the schematic diagram of the formwork keel reinforcement installation of the present invention;

图3A是图3中A-A剖视图; Fig. 3 A is A-A sectional view among Fig. 3;

图4是本发明所述穿墙螺栓的结构示意图; Fig. 4 is the structural representation of wall-through bolt described in the present invention;

图5是本发明所述插销式锁具的结构示意图; Fig. 5 is a structural schematic diagram of the bolt type lockset of the present invention;

图6是本发明方木底座构造图; Fig. 6 is a structural diagram of a square wooden base of the present invention;

图7是本发明所述外墙三脚架安装构造图; Fig. 7 is a diagram of the installation structure of the tripod on the outer wall of the present invention;

图7A是本发明所述外墙三脚架的结构示意图; Fig. 7A is a schematic structural view of the tripod on the outer wall of the present invention;

图8A是本发明阳角结构处组合模板的安装示意图; Fig. 8A is a schematic diagram of the installation of the combined formwork at the male corner structure of the present invention;

图8B是本发明阴角结构处组合模板的安装示意图; Fig. 8B is a schematic diagram of the installation of the combined template at the internal corner structure of the present invention;

图9是本发明模板固定示意图。 Fig. 9 is a schematic diagram of template fixing in the present invention.

具体实施方式 Detailed ways

下面结合附图和具体实施例对本发明作进一步详述。 The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

本发明所揭示的是一种剪力墙木框定型组合模板的施工方法,如图1所示,包括下述步骤: What the present invention discloses is a kind of construction method of shear wall wooden frame stereotyped combination formwork, as shown in Figure 1, comprises the following steps:

一、模板设计与配置 1. Template design and configuration

本施工方法采用定型模板,并通过龙骨进行加固。因此在施工前需对模板及龙骨进行设计及配置。 This construction method adopts shaped templates and reinforces them through keels. Therefore, it is necessary to design and configure the formwork and keel before construction.

1)设计 1) design

a、根据施工图纸设计不同规格的定型模板,确定非标准模板的使用位置、尺寸,并绘制模板拼装图、大样图。 a. According to the construction drawings, design templates of different specifications, determine the use position and size of non-standard templates, and draw template assembly diagrams and large-scale drawings.

本施工方法采用的定型模板1的结构如图2A及图2B所示,其包括面板11、两条横肋12及若干竖肋13。所述面板11可以采用一定厚度的胶合板,横肋与竖肋均可以采用一定尺寸的木方楞。两条横肋12分别置于胶合面板11的上下两端,竖肋13以一定间距竖向设置并与横肋12相抵住,横、竖肋12、13与胶合面板11采用螺钉14牢固组成成定型模板1结构。 The structure of the shaped template 1 adopted in this construction method is shown in FIG. 2A and FIG. 2B , which includes a panel 11 , two transverse ribs 12 and several vertical ribs 13 . The panel 11 can be plywood with a certain thickness, and both the transverse ribs and the vertical ribs can be wooden corrugated with a certain size. Two transverse ribs 12 are respectively placed on the upper and lower ends of the glued panel 11, and the vertical ribs 13 are vertically arranged at a certain distance and resist the transverse ribs 12, and the transverse and vertical ribs 12, 13 and the glued panel 11 are firmly formed by screws 14 stereotypes template1 structure.

b、根据刚度要求确定龙骨尺寸、间距,并确定螺栓规格、间距。 b. Determine the keel size and spacing according to the stiffness requirements, and determine the bolt specifications and spacing.

龙骨用于定型模板的加固,该龙骨2可以采用一定尺寸的双拼方钢管(配合图3及图3A),并通过若干穿墙螺栓3从两根方钢管中间穿过,通过锁具与穿墙螺栓3牢固连接,从而锁紧并定位定型模板1。所述的穿墙螺栓3可以是专门设计的结构,其不但可以固定定型模板1,还可以定位两侧模板之间的距离,以保证混凝土的厚度。该穿墙螺栓3的结构如图4所示,其包括穿墙螺杆31、螺于该穿墙螺杆31两端的扩大头螺母32,该扩大头螺母32外端设有螺柱33,该螺柱33与一螺母锁具34螺固,该螺母锁具34内端设有扩大头35,外端设有至少一个锁孔36。 The keel is used for the reinforcement of the shaped formwork. The keel 2 can be a double square steel pipe of a certain size (cooperate with Figure 3 and Figure 3A), and pass through the middle of the two square steel pipes through a number of wall bolts 3, and pass through the lock and the wall. The bolts 3 are firmly connected, thereby locking and positioning the shaping template 1 . The wall-through bolt 3 can be a specially designed structure, which can not only fix the shaped template 1, but also position the distance between the templates on both sides to ensure the thickness of the concrete. The structure of this wall-through bolt 3 is shown in Figure 4, and it comprises wall-through screw rod 31, the expansion head nut 32 that is screwed on this wall-through screw rod 31 two ends, and this expansion head nut 32 outer end is provided with stud 33, and this stud stud 33 is screwed with a nut lock 34, the inner end of the nut lock 34 is provided with an enlarged head 35, and the outer end is provided with at least one lock hole 36.

所述的锁具可以为插销式锁具4,该插销式锁具4也是专门设计的结构,如图5所示,其包括固定板41及插销42,该固定板41上设有穿孔43。在锁固龙骨2时,将所述螺母锁具34的外端从固定板41上的穿孔43穿过,之后将所述插销42从固定板41的外侧插于螺母锁具34上的其中一个锁孔36内,从而令固定板41的内侧抵于龙骨2上,将龙骨2固定,进而加固定型模板1。 The lock can be a bolt-type lock 4, which is also a specially designed structure, as shown in FIG. When locking the keel 2, pass the outer end of the nut lock 34 through the perforation 43 on the fixing plate 41, and then insert the latch 42 into one of the lock holes on the nut lock 34 from the outside of the fixing plate 41 36, so that the inner side of the fixing plate 41 is against the keel 2, the keel 2 is fixed, and then the fixed formwork 1 is added.

2)配置 2) Configuration

根据上述设计方案,统计各种规格模板的数量,进行各定型模板的制作,并对每块模板进行编号,之后进行分类堆放。 According to the above design plan, the number of templates of various specifications is counted, each template is made, and each template is numbered, and then classified and stacked.

二、测量放线 2. Measurement and release

弹好柱墙身位置线及支模控制线,支模控制线离墙边线距离一般为500mm。并弹好门窗洞口位置线,测量并画出标高线。 Play the position line of the column wall and the control line of the formwork. The distance between the control line of the formwork and the edge of the wall is generally 500mm. And play the position line of the door and window opening, measure and draw the elevation line.

三、安装准备 3. Installation preparation

1)确定墙身钢筋骨架5(配合图6、7所示)绑扎是否完毕,是否已安装预埋管线、接线盒、电箱,并已通过各分项工程的隐检工作。 1) Determine whether the wall reinforcement frame 5 (as shown in Figures 6 and 7) has been bound, whether the embedded pipelines, junction boxes, and electrical boxes have been installed, and have passed the hidden inspection of each sub-project.

2)将定型模板表面水泥浆等杂物清理干净,并在模板与混凝土接触面涂刷好脱模剂。把清理完毕并涂刷过脱模剂的模板搬运到相应位置。 2) Clean up the cement slurry and other debris on the surface of the shaped formwork, and apply a release agent on the contact surface between the formwork and the concrete. Move the template that has been cleaned and painted with release agent to the corresponding location.

四、定型模板安装 4. Installation of stereotyped formwork

1)组合定型模板的安装原则可以为:通常按照“先横墙,后纵墙”;“先外墙,后内墙”;“先小板块模,后大板块模,大板块模压住小板块模”的三项要领进行安装作业。 1) The installation principle of the combination stereotyped formwork can be as follows: usually follow "horizontal wall first, then vertical wall"; "outer wall first, then inner wall"; The three essentials of "block formwork" are used for installation work.

2)定型模板底座及外墙三角架安装 2) Shaped formwork base and external wall tripod installation

a、底座6安装:配合图6所示,为了防止楼面不平而导致墙模底部漏浆,出现“烂根”现象,根据放样的墙位置线,在模板下口与地面接触面可以粘贴一定宽度的海绵条61,再于墙根钉木方条62进行找平。 a. Installation of the base 6: As shown in Figure 6, in order to prevent the floor from being uneven and cause the bottom of the wall formwork to leak slurry and cause "rotten roots" phenomenon, according to the wall position line of the stakeout, a certain amount can be pasted on the contact surface between the lower opening of the formwork and the ground. The sponge strip 61 of width is leveled at the root of the wall nailing wooden square bar 62 again.

b、外墙三脚架安装:配合图7所示,为了解决外墙楼层过渡错台弊端,将外墙的外侧定型模板下口伸至下层墙顶以下一定距离。并采用外墙三角架7支撑和加固外墙外侧的定型模板1。为了施工的方便,可以采用专门设计的外墙三角架7,并利用下层剪力墙体上的穿墙螺栓孔洞固定该外墙三脚架7。所述的外墙三角架7的结构如图7A所示,其包括三角固定架71,在三角固定架71的上方设有支撑横板72,该支撑横板72的外侧向上延伸有一凸沿73,该凸沿73上安装有一螺旋紧固件74,所述三角固定架71的内侧设有竖向槽75,该竖向槽75处设有一滑动片76,该滑动片76上设有孔77。先将穿墙螺杆31及扩大头螺母32固定在墙上(下层剪力墙体上的穿墙螺栓孔洞内),再将三角固定架71上的滑动片76上的孔77与扩大头螺母32上的螺柱连接,调整至所需的水平位置后,用外侧螺母锁具34旋紧使外墙三角架7牢固附于墙体上。 b. Installation of tripod on the exterior wall: As shown in Figure 7, in order to solve the disadvantages of the staggered transition between the floors of the exterior wall, extend the lower opening of the external shaping formwork of the exterior wall to a certain distance below the top of the lower wall. And the external wall tripod 7 is used to support and reinforce the shaped formwork 1 on the outside of the external wall. For the convenience of construction, a specially designed outer wall tripod 7 can be used, and the outer wall tripod 7 can be fixed by utilizing the through-wall bolt holes on the lower shear wall. The structure of the tripod 7 on the outer wall is shown in Figure 7A, which includes a tripod 71, and a support horizontal plate 72 is provided above the tripod 71, and a convex edge 73 extends upwards from the outside of the support cross plate 72. , a helical fastener 74 is installed on the protruding edge 73, a vertical groove 75 is provided on the inner side of the tripod mount 71, a sliding piece 76 is arranged at the vertical groove 75, and a hole 77 is arranged on the sliding piece 76. . First fix the wall-through screw rod 31 and the expansion head nut 32 on the wall (in the wall-through bolt hole on the lower floor shear wall), and then connect the hole 77 on the sliding piece 76 on the triangle fixing frame 71 with the expansion head nut 32 After being adjusted to the required horizontal position, the studs on the top are connected, and the outer wall tripod 7 is firmly attached to the body of wall by tightening the outer nut lockset 34.

3)内外墙组合定型模板就位 3) The combination of internal and external walls and the finalized formwork are in place

a、外墙定型模板安装:配合图7所示,利用塔吊把外墙外侧定型模板1架设在外墙三角架7上,并将螺旋紧固件74顶紧模板以做好临时固定。并将所述的穿墙螺栓3一端固定于该外侧墙模板上。之后将外墙内侧定型模板1架立在墙模底座6上,立好后用穿墙螺栓3与已立好外侧墙模定位加固,两侧的扩大头螺母32之间的距离可以定位两侧模板之间的距离,从而保证剪力墙的厚度。 a. Installation of external wall shaped formwork: As shown in Figure 7, use a tower crane to erect external wall external shaped formwork 1 on the external wall tripod 7, and tighten the formwork with screw fasteners 74 for temporary fixation. And one end of the wall-through bolt 3 is fixed on the outer wall template. Afterwards, set up the inside sizing formwork 1 of the outer wall on the wall formwork base 6, and then use the through-wall bolts 3 to position and reinforce the outside wall formwork that has been established, and the distance between the enlarged head nuts 32 on both sides can be positioned on both sides. The distance between the templates ensures the thickness of the shear wall.

b、内墙定型模板安装:配合图6所示,利用人工把内墙一侧组合定型模板1架立在墙体钢筋骨架5的一侧墙模底座6上,单侧拼接完成后穿入所述的穿墙螺栓3,并做好临时固定。钢筋骨架5的另一侧组合定型模板1同样架立在墙模底座6上,立好后与已立好的原有一侧墙模穿墙螺栓3连接,外侧用螺母锁具34锁紧,定位加固。 b. Installation of interior wall shaping formwork: As shown in Figure 6, manually erect the combined shaping formwork 1 on one side of the interior wall on the wall formwork base 6 on one side of the wall reinforcement skeleton 5, and penetrate into the place after the one-side splicing is completed. The above-mentioned wall-through bolt 3, and do a good job of temporary fixation. The other side of the steel bar skeleton 5 is also set up on the wall formwork base 6. After being erected, it is connected with the wall-through bolts 3 on the original side of the wall formwork. The outer side is locked with a nut lock 34 for positioning and reinforcement. .

c、两侧墙模螺栓锁紧后,采用插销式锁具4进行主龙骨方钢管加固。混凝土浇筑后产生的侧压力可以通过板面结构传给横向的龙骨2,由穿墙螺栓3约束内外板面结构受力,以保证模板的强度和刚度。 c. After the wall formwork bolts on both sides are locked, use the bolt-type lock 4 to reinforce the main keel square steel pipe. The lateral pressure generated after concrete pouring can be transmitted to the horizontal keel 2 through the slab structure, and the internal and external slab structures are restrained by the through-wall bolts 3 to ensure the strength and rigidity of the formwork.

d、有楼面洞口一侧的模板安装同外墙外侧模板(为解决楼层孔洞边墙体过渡错台弊端,将孔洞边一侧模板下口伸至下层墙顶以下下一定距离,洞口两侧模板可以采用可伸缩碳钢钢管对撑以控制洞口尺寸。 d. The formwork on the side of the floor opening is installed with the formwork on the outside of the outer wall (in order to solve the disadvantages of the transition of the wall at the side of the floor hole, the lower opening of the formwork on the side of the hole is extended to a certain distance below the top of the lower wall, and the two sides of the opening The template can be braced by telescopic carbon steel pipes to control the size of the opening.

4)阴阳角结构组合定型模板的安装 4) Installation of yin and yang angle structure combined shaping formwork

如图8A所示,对于结构阳角部位,采用铁锁链8连接龙骨2方钢管,将墙体两端阳角部位整体拉接紧固,以确保龙骨加固牢靠。 As shown in Figure 8A, for the external corners of the structure, iron chains 8 are used to connect the two square steel pipes of the keel, and the external corners at both ends of the wall are integrally pulled and fastened to ensure that the keel is firmly reinforced.

如图8B所示,对于结构阴角部位,将一侧龙骨方钢管伸至转角处另一侧模板面板11上,另一侧龙骨方钢管抵在前一侧龙骨方钢管上,以确保阴角拼接位置不变形。 As shown in Figure 8B, for the inner corner of the structure, extend the square steel pipe on one side to the formwork panel 11 on the other side of the corner, and the square steel pipe on the other side against the square steel pipe on the front side to ensure the inner corner The stitching position is not deformed.

5)模板位置校正、垂直度调整并固定 5) Template position correction, verticality adjustment and fixation

如图9所示,定型墙模就位后,用可伸缩碳钢钢管9抵住龙骨2支撑于楼面稳定墙体两侧模板。之后采用吊线锤方法吊磁力线坠挂铅垂线,量测定型模板上、下口控制线距离,通过调整墙体两侧的碳钢钢管长度来修正模板垂直度。 As shown in Figure 9, after the shaped wall formwork is in place, use a telescopic carbon steel steel pipe 9 to support the keel 2 and support the formwork on both sides of the floor to stabilize the wall. Afterwards, use the pendant hammer method to hang the magnetic line of force and hang the plumb line, measure the distance between the upper and lower control lines of the formwork, and correct the verticality of the formwork by adjusting the length of the carbon steel pipes on both sides of the wall.

五、拆模、清理、堆放 Five, demoulding, cleaning, stacking

当混凝土浇筑完成后,对定型模板进行拆除。一般要遵循下述原则: After the concrete pouring is completed, the formwork is removed. Generally follow the following principles:

1)严格掌握拆模强度,常温施工时不得低于1.0MPa,冬季施工时不得低于受冻临界强度,并保证拆模时墙体不粘模、不缺角、不裂缝。剪力墙内墙拆模强度应达到1.2MPa,外墙拆模强度应达到7.5MPa。 1) Strictly control the strength of formwork removal. It must not be lower than 1.0MPa during normal temperature construction, and it must not be lower than the critical strength of freezing during winter construction, and ensure that the wall does not stick to the formwork, no corners, and no cracks during formwork removal. The formwork removal strength of the inner wall of the shear wall should reach 1.2MPa, and the formwork removal strength of the outer wall should reach 7.5MPa.

2)剪力墙拆模时,按支模的逆顺序进行,注意保护现浇面板,尽量利用大模板自重脱落,严禁强行砸撬模板;若自重脱模困难,则采用撬棍轻撬模板下口;拆模过程必须有专人指挥;拆除后的模板各种安装小配件应集中堆放,防止丢失。 2) When removing the formwork of the shear wall, proceed in the reverse order of supporting the formwork, pay attention to protecting the cast-in-place panel, try to use the large formwork to fall off by its own weight, and forcibly smashing the formwork is strictly prohibited; if it is difficult to remove the formwork by its own weight, use a crowbar to lightly pry the formwork down The demolition process must be directed by a special person; the various installation accessories of the demolished formwork should be stacked together to prevent loss.

3)拆卸后用铲刀及时清理模板表面,经检查合格后再涂刷脱模剂堆放整齐备用。 3) After disassembly, use a spatula to clean the surface of the template in time, and after passing the inspection, apply the release agent and stack it neatly for future use.

采用上述施工方法,具有下述经济效益: Using the above construction method has the following economic benefits:

1.模板及木楞周转次数多 1. There are many turnover times of formwork and corrugated

组合定型木模板成型后不需再进行模板的配模,没有再次配模的材料浪费,横竖肋固定在模板上与模板一起周转,没有再次拆装的材料损耗,减少了拆装的铁钉打孔,达到增加模板及木楞周转次数的目的。组合定型模板与普通模板相比如下表。 After the combined shaped wooden formwork is formed, there is no need to match the formwork, and there is no material waste for re-matching the formwork. The horizontal and vertical ribs are fixed on the formwork and rotate together with the formwork. There is no material loss for disassembly and assembly again, and the iron nailing for disassembly and assembly is reduced. holes, to increase the turnover times of formwork and flute. The combined stereotype template is compared with the common template as shown in the table below.

2.操作工效高 2. High operating efficiency

对于散支散拆类墙体支模方式而言,组合定型模板安装、拆卸具有方便快捷等优点,工人可以利用电动锁具对螺栓进行快速模板加固,大大减少了工人的劳动量,降低了工人的劳动强度。 For the wall formwork support method of loose support and dismantling, the installation and disassembly of the combined formwork has the advantages of convenience and quickness. Workers can use electric locks to quickly reinforce the formwork with bolts, which greatly reduces the labor load of workers and reduces the labor costs of workers. Labor intensity.

3.节约混凝土装饰材料、人工费用和工期 3. Save concrete decoration materials, labor costs and construction period

1)组合定型模板体系,结构墙面出模后可达到清水效果,清水墙一次成型,可达到中级抹灰标准,可不做任何装饰。从质量上杜绝了室内墙面抹灰空鼓、裂缝的通病;从施工成本上分析,节约了水泥、砂的原材耗用,以及抹灰用工;同时还节省了因抹灰工程质量通病而引起的维修工作量和维修费用。 1) Combined and shaped formwork system, the structural wall surface can achieve the effect of clear water after the mold is released, and the clear water wall can be formed at one time to meet the intermediate plastering standard without any decoration. In terms of quality, the common problems of plastering hollows and cracks on indoor walls have been eliminated; from the analysis of construction costs, the consumption of raw materials such as cement and sand, and labor for plastering have been saved; The maintenance workload and maintenance costs caused.

2)从工期上分析,采用组合定型模板对于工程主体施工阶段的工期变化不大,但室内装修阶段的工时可以缩短,节约了总工期。 2) From the analysis of the construction period, the use of combined stereotyped formwork has little change in the construction period of the main body of the project, but the working hours of the interior decoration stage can be shortened, saving the total construction period.

4.综合效益 4. Comprehensive benefits

1)从建筑观感质量而言,清水混凝土极具装饰效果。在模板拆除后,表面非常光滑,棱角分明,无需任何外墙装饰,只是在表面涂一层或两层透明的保护剂即可,显得十分自然。 1) In terms of architectural perception and quality, fair-faced concrete has a very decorative effect. After the formwork is removed, the surface is very smooth with sharp edges and corners, without any external wall decoration, just apply one or two layers of transparent protective agent on the surface, which looks very natural.

2)从结构利用率而言,省去结构抹灰面,房间内净尺寸可以增加3cm~5cm,增加室内有效使用面积。 2) In terms of structural utilization, the net size of the room can be increased by 3cm to 5cm by omitting the plastering surface of the structure, increasing the effective indoor area.

3)从设计安全而言,清水墙省去抹灰,楼体自重减轻,地震作用力相应减弱,结构抗震能力增强,更安全。 3) From the perspective of design safety, plastering is omitted on the dry wall, the weight of the building is reduced, the seismic force is correspondingly weakened, and the seismic capacity of the structure is enhanced, making it safer.

以上所述,仅为本发明的较佳实施例而已,并非用来限定本发明实施的范围。故但凡依本发明的权利要求和说明书所做的变化或修饰,皆应属于本发明专利涵盖的范围之内。 The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the implementation scope of the present invention. Therefore, all changes or modifications made according to the claims and description of the present invention shall fall within the scope covered by the patent of the present invention.

Claims (5)

1.一种剪力墙木框定型组合模板的施工方法,其特征在于:包括下述步骤: 1. a construction method of a shear wall wooden frame stereotyped combination formwork, is characterized in that: comprise the following steps: 一、模板设计与配置:采用定型模板,并通过龙骨进行加固; 1. Formwork design and configuration: use the finalized formwork and reinforce it through the keel; 1)设计 1) design a、根据施工图纸设计不同规格的定型模板,确定非标准模板的使用位置、尺寸,并绘制模板拼装图、大样图; a. According to the construction drawings, design templates of different specifications, determine the use position and size of non-standard templates, and draw template assembly diagrams and large-scale drawings; 所述的定型模板面板、两条横肋及若干竖肋;两条横肋分别置于面板的上下两端,竖肋以一定间距竖向设置并与横肋相抵住,横、竖肋与面板采用螺钉固定; The stereotyped formwork panel, two transverse ribs and several vertical ribs; the two transverse ribs are respectively placed at the upper and lower ends of the panel, and the vertical ribs are vertically arranged at a certain interval and resist the transverse ribs, and the horizontal and vertical ribs are connected to the panel Fix with screws; b、根据刚度要求确定龙骨尺寸、间距,并确定螺栓规格、间距; b. Determine the keel size and spacing according to the stiffness requirements, and determine the bolt specifications and spacing; 龙骨用于定型模板的加固,该龙骨采用双拼方钢管,并通过若干穿墙螺栓从两根方钢管中间穿过,通过锁具与穿墙螺栓连接; The keel is used to reinforce the shaped formwork. The keel is made of double square steel pipes, and passes through the middle of the two square steel pipes through several wall bolts, and is connected with the wall bolts through locks; 2)配置 2) Configuration 根据上述设计方案,统计各种规格模板的数量,进行各定型模板的制作,并对每块模板进行编号,之后进行分类堆放; According to the above design plan, count the number of templates of various specifications, make each finalized template, and number each template, and then classify and stack them; 二、测量放线:弹好柱墙身位置线及支模控制线,并弹好门窗洞口位置线,测量并画出标高线; 2. Measure and set out the line: snap the position line of the column wall and the control line of the formwork, and snap the position line of the door and window openings, measure and draw the elevation line; 三、安装准备: 3. Installation preparation: 1)确定墙身钢筋骨架绑扎是否完毕,是否已安装预埋管线、接线盒、电箱,并已通过各分项工程的隐检工作; 1) Determine whether the binding of the steel skeleton on the wall is completed, whether the embedded pipelines, junction boxes, and electrical boxes have been installed, and have passed the hidden inspection of each sub-project; 2)将定型模板表面水泥浆杂物清理干净,并在模板与混凝土接触面涂刷好脱模剂,把清理完毕并涂刷过脱模剂的模板搬运到相应位置; 2) Clean up the cement slurry debris on the surface of the shaped formwork, and apply a release agent on the contact surface between the formwork and the concrete, and move the formwork that has been cleaned and painted with the release agent to the corresponding position; 四、定型模板安装: 4. Installation of stereotyped formwork: 1)组合定型模板的安装原则为:“先横墙,后纵墙”;“先外墙,后内墙”;“先小板块模,后大板块模,大板块模压住小板块模”; 1) The installation principle of the combination stereotyped formwork is: "first the horizontal wall, then the vertical wall"; "first the outer wall, then the inner wall"; "first the small plate formwork, then the large plate formwork, the large plate formwork presses the small plate formwork" ; 2)定型模板底座及外墙三角架安装 2) The base of the finalized formwork and the installation of the tripod on the outer wall a、底座安装:在模板下口与地面接触面粘贴海绵条,再于墙根钉木方条进行找平; a. Base installation: Paste sponge strips on the contact surface between the lower opening of the formwork and the ground, and then nail wooden square strips at the root of the wall for leveling; b、外墙三脚架安装:将外墙的外侧定型模板下口伸至下层墙顶以下一定距离;并采用外墙三角架支撑和加固外墙外侧的定型模板; b. External wall tripod installation: Extend the lower opening of the external shaped formwork of the external wall to a certain distance below the top of the lower wall; and use the external wall tripod to support and reinforce the external shaped formwork of the external wall; 3)内外墙组合定型模板就位 3) The combination of internal and external walls and the finalized formwork are in place a、外墙定型模板安装:利用塔吊把外墙外侧定型模板架设在外墙三角架上并临时固定,并将所述的穿墙螺栓一端固定于该外侧墙模板上;之后将外墙内侧定型模板架立在墙模底座上,立好后用穿墙螺栓与已立好外侧墙模定位加固; a. Installation of external wall shaped formwork: use a tower crane to erect the outer wall shaped formwork on the outer wall tripod and temporarily fix it, and fix one end of the wall-through bolt on the outer wall formwork; then install the outer wall inner shaped formwork Stand on the base of the wall formwork, and then use the through-wall bolts to position and reinforce the outside wall formwork that has been erected; b、内墙定型模板安装:利用人工把内墙一侧组合定型模板架立在墙体钢筋骨架的一侧墙模底座上,单侧拼接完成后穿入所述的穿墙螺栓,并做好临时固定;钢筋骨架的另一侧组合定型模板同样架立在墙模底座上,立好后与已立好的原有一侧墙模穿墙螺栓连接定位加固; b. Installation of the shaped formwork for the inner wall: manually erect the combined shaped formwork on one side of the inner wall on the wall formwork base on one side of the steel reinforcement skeleton of the wall. Temporary fixation; the other side of the steel skeleton is also erected on the base of the wall formwork, and then connected with the wall bolts on the original side of the wall formwork that have been erected for positioning and reinforcement; c、两侧墙模螺栓锁紧后,采用锁具进行主龙骨方钢管加固; c. After the wall formwork bolts on both sides are locked, locks are used to reinforce the main keel square steel pipe; d、有楼面洞口一侧的模板安装同外墙外侧模板,将孔洞边一侧模板下口伸至下层墙顶以下一定距离,洞口两侧模板采用可伸缩碳钢钢管对撑以控制洞口尺寸; d. The formwork on the side of the floor opening is installed with the formwork on the outside of the outer wall, and the lower opening of the formwork on the side of the hole is extended to a certain distance below the top of the lower wall. The formwork on both sides of the opening is supported by telescopic carbon steel pipes to control the size of the opening ; 4)阴阳角结构组合定型模板的安装 4) Installation of yin and yang angle structure combined shaping formwork 对于结构阳角部位,采用铁锁链连接龙骨方钢管,将墙体两端阳角部位整体拉接紧固; For the external corners of the structure, iron chains are used to connect the keel square steel pipes, and the external corners at both ends of the wall are integrally pulled and fastened; 对于结构阴角部位,将一侧龙骨方钢管伸至转角处另一侧模板面板上,另一侧龙骨方钢管抵在前一侧龙骨方钢管上; For the inner corner of the structure, extend the keel square steel pipe on one side to the formwork panel on the other side of the corner, and the other keel square steel pipe against the front keel square steel pipe; 5)模板位置校正、垂直度调整并固定 5) Template position correction, verticality adjustment and fixation 定型墙模就位后,用可伸缩碳钢钢管抵住龙骨支撑于楼面稳定墙体两侧模板;之后采用吊线锤方法吊磁力线坠挂铅垂线,量测定型模板上、下口控制线距离,通过调整墙体两侧的碳钢钢管长度来修正模板垂直度; After the shaped wall formwork is in place, use the telescopic carbon steel pipe to support the keel and support the formwork on both sides of the floor to stabilize the wall; then use the pendant hammer method to hang the magnetic line of force and hang the plumb line, and measure the upper and lower control lines of the shaped formwork The verticality of the formwork is corrected by adjusting the length of the carbon steel pipes on both sides of the wall; 五、拆模、清理、堆放:当混凝土浇筑完成后,对定型模板进行拆除;拆模时,按支模的逆顺序进行,注意保护现浇面板,尽量利用大模板自重脱落,严禁强行砸撬模板;若自重脱模困难,则采用撬棍轻撬模板下口;拆除后的模板各种安装小配件应集中堆放。 5. Form removal, cleaning, and stacking: After the concrete pouring is completed, remove the shaped formwork; when removing the formwork, follow the reverse order of the formwork support, pay attention to protecting the cast-in-place panel, try to use the large formwork to fall off by its own weight, and forcibly smashing and prying is strictly prohibited Formwork; if it is difficult to remove the formwork by its own weight, use a crowbar to lightly pry the lower opening of the formwork; after dismantling, various installation accessories of the formwork should be stacked together. 2.根据权利要求1所述的剪力墙木框定型组合模板的施工方法,其特征在于:所述定型模板的面板采用胶合板,横肋与竖肋均采用木方楞。 2. The construction method of the shear wall wooden frame shaped combined formwork according to claim 1, characterized in that: the panel of the shaped formwork adopts plywood, and the transverse ribs and vertical ribs all adopt wooden square corrugated. 3.根据权利要求1所述的剪力墙木框定型组合模板的施工方法,其特征在于:所述的穿墙螺栓包括穿墙螺杆、螺于该穿墙螺杆两端的扩大头螺母,该扩大头螺母外端设有螺柱,该螺柱与一螺母锁具螺固,该螺母锁具内端设有扩大头,外端设有至少一个锁孔。 3. The construction method of the shear wall wooden frame stereotyped combined formwork according to claim 1, characterized in that: the wall-through bolts include wall-through screw rods, and enlarged head nuts screwed on both ends of the wall-through screw rod, the enlarged head nuts The outer end of the head nut is provided with a stud, and the stud is screwed with a nut lock, the inner end of the nut lock is provided with an enlarged head, and the outer end is provided with at least one lock hole. 4.根据权利要求3所述的剪力墙木框定型组合模板的施工方法,其特征在于:所述的锁具为插销式锁具,包括固定板及插销,该固定板上设有穿孔;在锁固龙骨时,将所述螺母锁具的外端从固定板上的穿孔穿过,之后将所述插销从固定板的外侧插于螺母锁具上的其中一个锁孔内。 4. The construction method of the shear wall wooden frame stereotyped combination formwork according to claim 3, characterized in that: the lock is a bolt-type lock, comprising a fixing plate and a bolt, and the fixing plate is provided with a perforation; When fixing the keel, the outer end of the nut lock is passed through the perforation on the fixing plate, and then the latch is inserted into one of the lock holes on the nut lock from the outside of the fixing plate. 5.根据权利要求1-4之一所述的剪力墙木框定型组合模板的施工方法,其特征在于:所述的外墙三角架包括三角固定架,在三角固定架的上方设有支撑横板,该支撑横板的外侧向上延伸有一凸沿,该凸沿上安装有一螺旋紧固件,所述三角固定架的内侧设有竖向槽,该竖向槽处设有一滑动片,该滑动片上设有孔。 5. The construction method of the shear wall wooden frame stereotyped combination formwork according to any one of claims 1-4, characterized in that: the tripod on the outer wall includes a tripod, and a support is provided above the tripod A horizontal plate, the outer side of the support horizontal plate extends upwards with a convex edge, a screw fastener is installed on the convex edge, a vertical groove is provided on the inner side of the triangle fixing frame, and a sliding piece is provided at the vertical groove. The sliding sheet is provided with holes.
CN201210207235.9A 2012-06-21 2012-06-21 Construction method for high-strength shaping combined template of plank frame of shear wall Expired - Fee Related CN102704684B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210207235.9A CN102704684B (en) 2012-06-21 2012-06-21 Construction method for high-strength shaping combined template of plank frame of shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210207235.9A CN102704684B (en) 2012-06-21 2012-06-21 Construction method for high-strength shaping combined template of plank frame of shear wall

Publications (2)

Publication Number Publication Date
CN102704684A CN102704684A (en) 2012-10-03
CN102704684B true CN102704684B (en) 2015-01-07

Family

ID=46897713

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210207235.9A Expired - Fee Related CN102704684B (en) 2012-06-21 2012-06-21 Construction method for high-strength shaping combined template of plank frame of shear wall

Country Status (1)

Country Link
CN (1) CN102704684B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103206088B (en) * 2013-04-18 2015-10-28 南通卓强建设集团有限公司 Parts of shear wall structure wall, slab integral pouring construction method
CN103498454A (en) * 2013-10-15 2014-01-08 国家电网公司 Underwater construction process of water inlet/outlet of lower storage reservoir
CN105275198B (en) * 2014-07-02 2018-03-06 中国华冶科工集团有限公司 A kind of shear-wall strengthening formwork structure and its construction method
CN104153579B (en) * 2014-08-26 2016-03-09 中国建筑第八工程局有限公司 A kind of formwork for placing structure of non-standard layers structure and construction method
CN106013158A (en) * 2016-06-07 2016-10-12 中国十七冶集团有限公司 Aluminum alloy formwork one-edge formwork-supporting device
CN106320693A (en) * 2016-08-31 2017-01-11 沈阳欣荣基建筑工程有限公司 Construction method of plastic formwork system
CN113944319A (en) * 2021-09-29 2022-01-18 中国化学工程第六建设有限公司 Novel shaping combined template for wall column and construction method thereof
CN113898179A (en) * 2021-11-16 2022-01-07 启东建筑集团有限公司 Construction method of whole plate single-side-edge lock hole formwork supporting system of shear wall structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03293445A (en) * 1990-04-11 1991-12-25 Shimizu Corp Construction method of building structure
JP2000328700A (en) * 1999-05-21 2000-11-28 Odakyu Construction Co Ltd Methods for reinforcing concrete structures
CN1986989A (en) * 2006-11-27 2007-06-27 青岛建设集团公司 Three dimension arch steel concrete structure formwork and construction method
CN101397844A (en) * 2008-09-25 2009-04-01 陕西省第三建筑工程公司 Construction method of special section steel concrete composite structure inclined wall mould base engineering

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03293445A (en) * 1990-04-11 1991-12-25 Shimizu Corp Construction method of building structure
JP2000328700A (en) * 1999-05-21 2000-11-28 Odakyu Construction Co Ltd Methods for reinforcing concrete structures
CN1986989A (en) * 2006-11-27 2007-06-27 青岛建设集团公司 Three dimension arch steel concrete structure formwork and construction method
CN101397844A (en) * 2008-09-25 2009-04-01 陕西省第三建筑工程公司 Construction method of special section steel concrete composite structure inclined wall mould base engineering

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
曲昭嘉等.定型组合模板施工要点.《建筑工程构造与施工手册》.中国建筑工业出版社,2009,第552-556页. *
浅谈定型组合模板在施工中的应用;岳江彦;《价值工程》;20101031(第10期);第110页 *
编委会.概述.《模板工快速入门》.北京理工大学出版社,2009,第21-27页、第30-31页. *

Also Published As

Publication number Publication date
CN102704684A (en) 2012-10-03

Similar Documents

Publication Publication Date Title
CN103615110B (en) Random oblique netted nine-squares beam Hyperbolic Roof construction method
CN102704684A (en) Construction method for high-strength shaping combined template of plank frame of shear wall
CN101892743B (en) Construction method of permanent housing
CN103911951A (en) Special formwork for bridge integrated cast-in-situ anti-collision barrier and hanging plate and construction method thereof
CN203429641U (en) Single-side supporting formwork reinforcing structure system for building construction
CN202787974U (en) Closed framework structure used for stair construction
CN104196231A (en) Concrete floor aluminum alloy template and construction method thereof
CN204781452U (en) Section bar and possess framework of this section bar
CN212534738U (en) Truss Floor Slab
CN113482312A (en) Guide type double-layer structure elevator shaft operating platform and construction method based on platform
CN116480133A (en) Formwork support system and method for fair-faced concrete construction with Gaussian curved surfaces in the coastal environment
CN110439257A (en) A kind of high turnover rate fashioned iron of sectional-film coating plywood light-type template system construction method
CN105155836A (en) Aluminum alloy formwork for buildings and method for applying aluminum alloy formwork
CN210342693U (en) Outer wall integration composite insulation board consolidates support
CN104674997A (en) Supporting structure of archaized wood structure building roof and construction method thereof
CN104727446A (en) Construction method of large aluminum alloy formwork at settlement joint
CN103225394B (en) Big wood template construction method of indoor constructional engineering shear wall
CN110258890A (en) A construction method for a broken-line exterior wall and roof connected concrete structure
CN202509762U (en) Cast-in-place concrete structure profile steel secondary edge and wood plastic composite framework support device
CN105275198B (en) A kind of shear-wall strengthening formwork structure and its construction method
CN204059940U (en) A kind of concrete floor aluminum alloy mould plate
CN103485538A (en) Construction method of energy-saving insulation waterproof wood-trussed roof system
CN203947493U (en) Assembling type device for detecting manhole
CN106193578B (en) It is a kind of that modular system and construction technology are matched somebody with somebody based on groove type quarter bend
CN204728688U (en) A kind of combined template for architecture

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150107