CN208814490U - A kind of novel drainage ditch cover plate hanging apparatus - Google Patents

A kind of novel drainage ditch cover plate hanging apparatus Download PDF

Info

Publication number
CN208814490U
CN208814490U CN201821308854.6U CN201821308854U CN208814490U CN 208814490 U CN208814490 U CN 208814490U CN 201821308854 U CN201821308854 U CN 201821308854U CN 208814490 U CN208814490 U CN 208814490U
Authority
CN
China
Prior art keywords
cover plate
cover board
drainage ditch
main beam
hanging apparatus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821308854.6U
Other languages
Chinese (zh)
Inventor
钟远帆
李泽
张云
肖超
鲁重
王治群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCFEB Civil Engineering Co Ltd
Original Assignee
CCFEB Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCFEB Civil Engineering Co Ltd filed Critical CCFEB Civil Engineering Co Ltd
Priority to CN201821308854.6U priority Critical patent/CN208814490U/en
Application granted granted Critical
Publication of CN208814490U publication Critical patent/CN208814490U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of novel drainage ditch cover plate hanging apparatus, comprising: skeleton framework, the skeleton framework include a main beam, the more secondary beams being uniformly fixed on above main beam, two hanging rings for being symmetricly set on main beam both ends;Bandlet is lifted by crane, the lifting bandlet is connect with two hanging rings in skeleton framework;And cover plate connecting device, the cover plate connecting device are symmetricly set on the both ends of secondary beam, the cover plate connecting device includes the cover board suspension hook for connecting with the precast reinforced hanging ring of cover board, and one end connect the wirerope that the other end is connect with cover board suspension hook with time beam end.Utility model device can increase handling amount when crane lifting cover board, the effect of preferably to play crane, greatly improve lifting efficiency, and keep the pile of prefabricated cover board more neat.

Description

A kind of novel drainage ditch cover plate hanging apparatus
Technical field
The utility model belongs to municipal works technical field, and in particular to a kind of novel drainage ditch cover plate hanging apparatus.
Background technique
In municipal works, roadbed two sides gutter is both needed to overlay cover board, since each piece of prefabricated cover board is from prefabricated to peace Dress needs to lift 3 times (prefabricated-centralized maintenance storage-entrucking-installation), and crane pendulum arm angle in hoisting process is big, but every The prefabricated cover board of block only has 200kg, can not play crane effect, causes crane equipment utilization rate to substantially reduce, while also increasing Cost of labor is added.
Utility model content
In view of the above-mentioned problems, the utility model provides a kind of novel drainage ditch cover plate hanging apparatus, sturdy construction is steady Gu it is durable, handling amount when crane lifting cover board can be increased, the effect of preferably to play crane, greatly improve lifting efficiency.
The utility model is achieved through the following technical solutions.
A kind of novel drainage ditch cover plate hanging apparatus, characterized by comprising:
Skeleton framework, the skeleton framework include a main beam, more be uniformly fixed on secondary beams above main beam, right Claim two hanging rings that main beam both ends are set;
Bandlet is lifted by crane, the lifting bandlet is connect with two hanging rings in skeleton framework;
Cover plate connecting device, the cover plate connecting device are symmetricly set on the both ends of secondary beam, the cover plate connecting device packet The cover board suspension hook for connecting with the precast reinforced hanging ring of cover board is included, one end connect the other end with time beam end and connect with cover board suspension hook Wirerope.
As optimal technical scheme, the main beam, secondary beam are channel steel.
As optimal technical scheme, the secondary beam is welded and fixed with main beam.
As optimal technical scheme, the hanging ring and cover board suspension hook are made of round steel.
As optimal technical scheme, the wirerope is made up using carbon steel or steel alloy of cold drawing or cold rolling.
As optimal technical scheme, it is welded and fixed between the more secondary beams using lacing wire.
As optimal technical scheme, it is provided with screw hole on the secondary beam, the spiral shell with screw hole cooperation is offered on the main beam Bolt sliding slot;The secondary beam passes through screw hole, bolt sliding slot and main beam bolt by bolt and fixes.
As optimal technical scheme, the length of the bolt sliding slot is 5~15cm.
The utility model has the beneficial effects that handling amount when utility model device can increase crane lifting cover board, with more The effect of performance crane got well, lifting efficiency is greatly improved, and keep the pile of prefabricated cover board more neat.
Detailed description of the invention
Fig. 1 is the main view of the utility model hanging apparatus;
Fig. 2 is the top view of the utility model hanging apparatus;
Fig. 3 is the left view of the utility model hanging apparatus;
Fig. 4 is the top view of the preferred embodiment in the utility model hanging apparatus;
Fig. 5 is the top view of main beam in the preferred embodiment in the utility model hanging apparatus;
Fig. 6 is the left view of main beam in the preferred embodiment in the utility model hanging apparatus;
The meaning respectively marked in above-mentioned figure:
1- skeleton framework, 11- main beam, 12- secondary beam, 13- hanging ring, 14- lacing wire, 15- bolt sliding slot, 16- bolt, 17- Screw hole;
2- lifts by crane bandlet;
3- cover plate connecting device, 31- wirerope, 32- cover board suspension hook;
The precast reinforced hanging ring of 4- cover board;
5- cover board.
Specific embodiment
Other than objects, features and advantages described above, there are also other purposes, feature and excellent for the utility model Point.Below with reference to Figure of description, the utility model is described in further detail.What is constituted part of this application is attached Figure is used to provide a further understanding of the present invention, and the illustrative embodiments and their description of the utility model are for explaining this Utility model does not constitute improper limits to the present invention.
Embodiment
A kind of novel drainage ditch cover plate hanging apparatus, please refers to Fig. 1, Fig. 2, Fig. 3, comprising:
Skeleton framework 1, skeleton framework 1 include a main beam 11, the more secondary beams being uniformly fixed on above main beam 11 12, two hanging rings 13 at 11 both ends of main beam are symmetricly set on;It in actual use, can be according to construction requirement, in main beam On 11 be arranged two, three, four, or more root secondary beam 12, the present embodiment Fig. 1, Fig. 2 illustrate only secondary beam 12 be four when Situation;
Bandlet 2 is lifted by crane, lifting bandlet 2 is connect with two hanging rings 13 in skeleton framework 1;
Cover plate connecting device 3, cover plate connecting device 3 are symmetricly set on the both ends of secondary beam 12, and cover plate connecting device 3 includes using In the cover board suspension hook 32 connecting with the precast reinforced hanging ring 4 of cover board, one end connect the other end and cover board suspension hook 32 with 12 end of secondary beam The wirerope 31 of connection;
Referring to Fig. 1, the specific operation process of the utility model lifting cover board is as follows:
1, cover board spacing as required, it is regularly arranged it is prefabricated after the completion of, it is first that crane is in place, then will lifting bandlet 4 with The suspension hook of crane connects, then is transported to the present apparatus at the prefabricated cover board for needing handling by crane;
2, cover board suspension hook 32 connect to (two cover boards at 12 both ends of a usual secondary beam are hung with the precast reinforced hanging ring 4 of cover board Hook 32 is connect with the precast reinforced hanging ring 4 of two cover boards preset on one piece of cover board, i.e. a secondary beam 12, which can correspond to, slings one piece of lid Plate, as described in Figure 1, when four secondary beams 12 are arranged on main beam 11, the present apparatus can once lift four pieces of cover boards), and inspection is No loosening is commanded by department's rope work and is lifted by crane after being completely embedded;
3, when cover board is hoisted to the upper end of designated position by crane, cover board is slowly transferred, when cover board is apart from ground When 50cm~100cm, cap locations are finely tuned by worker, makes the decentralization that cover board is accurate, stable, unclamps cover board suspension hook after the completion of decentralization 32, that is, complete entire hoisting process.
For convenient for materials, further, main beam 11, secondary beam 12 are channel steel.
It is fastened to guarantee to connect between secondary beam 12 and main beam 11, makes 1 stabilized structure of skeleton framework, further, secondary beam 12 are welded and fixed with main beam 11.
Further, hanging ring and cover board suspension hook are made of round steel.
Further, wirerope is made up using carbon steel or steel alloy of cold drawing or cold rolling.
To make 1 stabilized structure of skeleton framework, further, Fig. 1, Fig. 2, Fig. 3 is please referred to, is used between more secondary beams 12 Lacing wire 14 is welded and fixed.
In order to which the lifting for alloing utility model device to be applicable in different dimensions cover boards further please refers to figure 4, Fig. 5, Fig. 6 are provided with screw hole 17 on secondary beam 12, and the bolt sliding slot 15 cooperated with screw hole 17 is offered on the main beam 11;Institute It states secondary beam 12 and screw hole 17, bolt sliding slot 15 and the bolt fixation of main beam 11 is passed through by bolt 16;In this way, different when needing to lift by crane It, can be by adjusting position of the bolt 16 in bolt sliding slot 15, to adjust between more secondary beams 12 when the cover board of dimensions Spacing, in addition can also flexibly dismantle secondary beam 12, the radical of secondary beam 12 be adjusted, to match the size of cover board.
Further, the length of bolt sliding slot 15 is preferably 5~15cm.

Claims (8)

1. a kind of novel drainage ditch cover plate hanging apparatus, characterized by comprising:
Skeleton framework (1), the skeleton framework (1) are uniformly fixed on main beam (11) including a main beam (11), more The secondary beam (12) of side, two hanging rings (13) for being symmetricly set on main beam (11) both ends;
It lifts by crane bandlet (2), lifting bandlet (2) connect with two hanging rings (13) in skeleton framework (1);And
Cover plate connecting device (3), the cover plate connecting device (3) are symmetricly set on the both ends of secondary beam (12), the cover board connection Device (3) includes the cover board suspension hook (32) for connecting with the precast reinforced hanging ring of cover board (4), and one end is connect with secondary beam (12) end The wirerope (31) that the other end is connect with cover board suspension hook (32).
2. a kind of novel drainage ditch cover plate hanging apparatus as described in claim 1, it is characterised in that the main beam (11), secondary Beam (12) is channel steel.
3. a kind of novel drainage ditch cover plate hanging apparatus as described in claim 1, it is characterised in that the secondary beam (12) and master Crossbeam (11) is welded and fixed.
4. a kind of novel drainage ditch cover plate hanging apparatus as described in claim 1, it is characterised in that the hanging ring (13) and lid Plate suspension hook (32) is made of round steel.
5. a kind of novel drainage ditch cover plate hanging apparatus as described in claim 1, it is characterised in that the wirerope (31) is adopted It is made up with carbon steel or steel alloy of cold drawing or cold rolling.
6. a kind of novel drainage ditch cover plate hanging apparatus as described in Claims 1 to 5 is any, it is characterised in that described more times It is welded and fixed between beam (12) using lacing wire (14).
7. a kind of novel drainage ditch cover plate hanging apparatus as described in claim 1, it is characterised in that opened on the secondary beam (12) Have screw hole (17), the bolt sliding slot (15) with screw hole (17) cooperation is offered on the main beam (11);The secondary beam (12) is logical Bolt (16) are crossed to fix across screw hole (17), bolt sliding slot (15) and main beam (11) bolt.
8. a kind of novel drainage ditch cover plate hanging apparatus as claimed in claim 7, it is characterised in that the bolt sliding slot (15) Length be 5~15cm.
CN201821308854.6U 2018-08-14 2018-08-14 A kind of novel drainage ditch cover plate hanging apparatus Active CN208814490U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821308854.6U CN208814490U (en) 2018-08-14 2018-08-14 A kind of novel drainage ditch cover plate hanging apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821308854.6U CN208814490U (en) 2018-08-14 2018-08-14 A kind of novel drainage ditch cover plate hanging apparatus

Publications (1)

Publication Number Publication Date
CN208814490U true CN208814490U (en) 2019-05-03

Family

ID=66273510

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821308854.6U Active CN208814490U (en) 2018-08-14 2018-08-14 A kind of novel drainage ditch cover plate hanging apparatus

Country Status (1)

Country Link
CN (1) CN208814490U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110104535A (en) * 2019-05-20 2019-08-09 中铁六局集团有限公司 Concrte sleeper townhouse hanging apparatus

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110104535A (en) * 2019-05-20 2019-08-09 中铁六局集团有限公司 Concrte sleeper townhouse hanging apparatus

Similar Documents

Publication Publication Date Title
CN202717501U (en) Pile foundation reinforcement cage lifting ring
CN109095343A (en) Assembled hanger
CN203173684U (en) Component for hoisting reinforcement cage
CN210914946U (en) Lifting appliance with sling tensioning device
CN208814490U (en) A kind of novel drainage ditch cover plate hanging apparatus
CN207331426U (en) A kind of double box steel concrete binder bowstring arch bridges of railway
CN203998604U (en) The be threaded vertical reinforcement erecting equipment of form of employing
CN207030735U (en) Prefabricated balcony lifts servicing unit
CN202988556U (en) Special lifting appliance for angle-steel type frame body
CN208948679U (en) Assembled hanger
CN206625585U (en) A kind of carrying pole device of purlin installation
CN103803397B (en) A kind of suspender for installed vertical rolling mill universal axle and using method
CN212924074U (en) Non-embedded multifunctional lifting appliance for precast concrete beam
CN209493211U (en) A kind of assembled architecture Prefabricated element slings
CN211846839U (en) Prefabricated post hoist device
CN108331335A (en) A kind of pre-splicing separation type hydraulic of steel and wood composite is from climbing support
CN203754232U (en) Simple steel rail lifting tool
CN207633773U (en) A kind of glomeration building prefabricated construction reinforcing bar guiding tube dismounting system
CN207986495U (en) A kind of Bridge High-pier main reinforcement hanging apparatus
CN207434839U (en) A kind of impeller hub suspender installs carrying device
CN209065269U (en) A kind of roof purline modularization installation combined tools
CN205976550U (en) Cluster hangs instrument of girder steel
CN202785257U (en) Control device used for hoisting and positioning steel reinforcement cage of manual hole digging piles
CN204848024U (en) Girder steel hoist device for construction
CN206127859U (en) Portable construction operation platform of drilled pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant