CN204199271U - A kind of filling pile cage of reinforcement hangs fastening devices - Google Patents

A kind of filling pile cage of reinforcement hangs fastening devices Download PDF

Info

Publication number
CN204199271U
CN204199271U CN201420667151.8U CN201420667151U CN204199271U CN 204199271 U CN204199271 U CN 204199271U CN 201420667151 U CN201420667151 U CN 201420667151U CN 204199271 U CN204199271 U CN 204199271U
Authority
CN
China
Prior art keywords
seamless steel
steel pipe
cover hook
hook
iron
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420667151.8U
Other languages
Chinese (zh)
Inventor
王丽梅
余沛
孙旭平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Engineering Bureau Civil Engineering Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201420667151.8U priority Critical patent/CN204199271U/en
Application granted granted Critical
Publication of CN204199271U publication Critical patent/CN204199271U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of filling pile cage of reinforcement and hang fastening devices, it comprises and is laid on the ground sleeper of priming concrete pile hole casing top relative to both sides, described sleeper is erected with well shape support, described well shape Bracket setting one group of relative edge below adopts i iron, described i iron has multiple mounting limit hole, another group of well shape support relative edge adopts seamless steel pipe, cover hook hangs on seamless steel pipe through the through hole in a cover hook and arranges by each root seamless steel pipe, the bottom of described cover hook has hook, the top of described cover hook has handle, the two ends of two seamless steel pipes are fixedly connected with the mounting limit hole on i iron respectively by through the positioning bolt on seamless steel pipe.Adopt this appliance stand to make simple, link up with and regulate its position by handle, convenient and labor-saving like this.Do not use any machinery and auxiliary equipment.

Description

A kind of filling pile cage of reinforcement hangs fastening devices
Technical field
The utility model relates to and hangs fastening devices, particularly relates to a kind of filling pile cage of reinforcement and hangs fastening devices.
Background technology
In bridge construction, substructure pile foundation engineering is absolutely necessary, but hanging particularly for especially big reinforcing cage in pile foundation construction, required equipment, working space and technical difficulty are relatively excessive.Therefore more loaded down with trivial details with the setting method construction of conventional underwater grouting pile cages, difficulty is also unreasonable economically.
The patent of having authorized is learnt by retrieval:
1 application number is: the Chinese patent of CN201310206512.9 discloses " a kind of hoisting device for reinforcement cage ", this device comprises main lifting assembly and secondary lifting assembly, main lifting assembly forms primarily of wire rope, two first gin wheels and a lifting beam, lifting beam two ends connect one first gin wheel respectively, the wire rope that on two first gin wheels, cross-over connection one is isometric respectively, two wire rope symmetries are connected to the symmetrical both sides of reinforcing cage axial direction; Secondary lifting assembly forms primarily of wire rope, two second gin wheels and one the 3rd gin wheel, cross-over connection one wire rope on 3rd gin wheel, these wire rope two ends connect one second gin wheel respectively, cross-over connection one wire rope on each second gin wheel, these wire rope two ends are connected on 2 of described reinforcing cage the top.
2 application numbers are: the Chinese patent of CN201120172116.5 discloses " steel reinforcement cage lifting device " this device and includes an equalizer bar, equalizer bar is arranged in the middle of above reinforcing cage, its direction is parallel with reinforcing cage axis direction, the soffit two ends of equalizer bar are symmetrically arranged with two groups and fix wire rope, and respectively the two ends symmetry often organizing fixing wire rope is fixed on the both sides at the axial two ends of reinforcing cage, directly over the centre of equalizer bar, also be provided with pulley, through there being movable wire rope on pulley, and the two ends of movable wire rope symmetry is fixed on the upper surface of equalizer bar.
3 application numbers are: the Chinese patent of CN201220066562.2 discloses " a kind of hanger structure lifting by crane reinforcing cage ", comprise the main hook on loop wheel machine, shoulder pole girder, hoist cable, shoulder pole girder two ends arrange a pulley respectively, each pulley is wound with hoist cable, the two ends of hoist cable fasten the upper and lower two ends of reinforcing cage respectively by fastener, form two suspension centres; Shoulder pole girder upper end is provided with V-shaped suspension hook.
1-3 item patent mainly hoisting device for reinforcement cage, is not suitable for the fastening devices after rigging out.
4. application number is: the Chinese patent of CN201120308130.3 discloses " hanging installer for steel bar cage in drilled pile ", comprise aperture spacer bars and steel reinforcement cage hanging steel bar, aperture spacer bars is fixedly connected with by rope cramp with steel reinforcement cage hanging steel bar, the lower end of steel reinforcement cage hanging steel bar is provided with two limit pin holes, two limit pin holes form bayonet socket, and limit pin hole comprises nut and is fixed on the reinforcing bar of nut side.This patent mainly hanging installer for steel bar cage in drilled pile, when constructing at the scene, aperture spacer bars needs to be connected with ground fastening devices, and will employ machinery, and when affecting by construction area geographical environment, big machinery cannot enter.And rope cramp also easily ruptures.
Summary of the invention
The purpose of this utility model is the feature overcoming prior art, convenient and labor-saving, reusable edible, and economical rationality, not only increase labor productivity, and saved cost, a kind of filling pile cage of reinforcement saving the duration hangs fastening devices.
A kind of filling pile cage of reinforcement of the present utility model hangs fastening devices, it comprises and is laid on the ground sleeper of priming concrete pile hole casing top relative to both sides, described sleeper is erected with well shape support, described well shape Bracket setting one group of relative edge below adopts i iron, described i iron has multiple mounting limit hole, another group of well shape support relative edge adopts seamless steel pipe, cover hook hangs on seamless steel pipe through the through hole in a cover hook and arranges by each root seamless steel pipe, the bottom of described cover hook has hook, the top of described cover hook has handle, the two ends of two seamless steel pipes are fixedly connected with the mounting limit hole on i iron respectively by through the positioning bolt on seamless steel pipe.
The beneficial effect of the utility model device is:
Rack making is simple, large for grout pile footpath, reinforcing cage is long, during by construction area and lifting machine load limit, adopt this device to construct, make reinforcing cage hang on hook, two seamless steel pipes can regulate its spacing according to stake footpath size by positioning bolt, hook regulates its position by handle, convenient and labor-saving like this.Do not use any machinery and auxiliary equipment.
Accompanying drawing explanation
Fig. 1 is the scheme of installation that a kind of filling pile cage of reinforcement of the present utility model hangs fastening devices;
Fig. 2 is that a kind of filling pile cage of reinforcement of the present utility model hangs the i iron of fastening devices and the floor map of seamless steel pipe;
Fig. 3 adopts a kind of filling pile cage of reinforcement of the present utility model to hang fastening devices to carry out reinforcing cage and hang fixing schematic diagram;
Fig. 4 adopts a kind of filling pile cage of reinforcement of the present utility model to hang fastening devices to carry out final section reinforcing cage scheme of installation.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in detail.
A kind of filling pile cage of reinforcement of the present utility model as shown in drawings hangs fastening devices, it comprises and is laid on the ground sleeper 5 of priming concrete pile hole casing top relative to both sides, described sleeper is erected with well shape support, described well shape Bracket setting one group of relative edge below adopts i iron 3, described i iron has multiple mounting limit hole 7, another group of well shape support relative edge adopts seamless steel pipe 2, cover hook hangs on seamless steel pipe through the through hole in a cover hook and arranges by each root seamless steel pipe, the bottom of described cover hook has hook 4, the top of described cover hook has handle 1, the two ends of two seamless steel pipes are fixedly connected with the mounting limit hole on i iron respectively by through the positioning bolt on seamless steel pipe.
Adopt the construction method of this device as follows: (1) lays railway sleepers 5 on the ground of relative both sides, priming concrete pile hole casing 8 top, described sleeper is set up well shape support, well shape Bracket setting one group of relative edge below adopts i iron 3, described i iron 3 has multiple mounting limit hole 7, another group of well shape support relative edge adopts seamless steel pipe 2, cover hook hangs on seamless steel pipe 2 through the through hole in a cover hook by each root seamless steel pipe 2, the bottom of described cover hook has hook 4, and the top of described cover hook has handle 1; (2) distance adjusted between two seamless steel pipes 2 make two overlap hooks be in can link up with the reinforcing cage 9 hung position on, the two ends of two seamless steel pipes 2 are fixedly connected with the mounting limit hole 7 on i iron 3 respectively by through the positioning bolt on seamless steel pipe 2; (3) when the lower joint reinforcing cage 9 hung is in orifice position, the lower joint reinforcing cage 9 hung is hung on hook 4 temporary fixed, and then be welded and fixed on lower joint reinforcing cage 9 and save reinforcing cage, after having welded, reinforcing cage is hung by kart, extract hook 4, down install reinforcing cage is to assigned position, then upper joint reinforcing cage is hung over close to apical position with hook 4, carry out the welding of an other joint reinforcing cage again, circulate welding successively, until welded final section reinforcing cage, hang reinforcing cage by kart, extract hook 4; (4) suspension ring 6 that hook adopts round steel to make on hook 4, the threaded reinforcing bar of tool on final section reinforcing cage 9 is threaded with nigger 10, nigger upper end is threaded with suspension ring bottom, then the complete reinforcing cage of connection is hung onto design attitude, when concreting is complete, by torque spanner, nigger 10 is removed.

Claims (1)

1. a filling pile cage of reinforcement hangs fastening devices, it is characterized in that: it comprises and is laid on the ground sleeper of priming concrete pile hole casing top relative to both sides, described sleeper is erected with well shape support, described well shape Bracket setting one group of relative edge below adopts i iron, described i iron has multiple mounting limit hole, another group of well shape support relative edge adopts seamless steel pipe, cover hook hangs on seamless steel pipe through the through hole in a cover hook and arranges by each root seamless steel pipe, the bottom of described cover hook has hook, the top of described cover hook has handle, the two ends of two seamless steel pipes are fixedly connected with the mounting limit hole on i iron respectively by through the positioning bolt on seamless steel pipe.
CN201420667151.8U 2014-11-10 2014-11-10 A kind of filling pile cage of reinforcement hangs fastening devices Active CN204199271U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420667151.8U CN204199271U (en) 2014-11-10 2014-11-10 A kind of filling pile cage of reinforcement hangs fastening devices

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420667151.8U CN204199271U (en) 2014-11-10 2014-11-10 A kind of filling pile cage of reinforcement hangs fastening devices

Publications (1)

Publication Number Publication Date
CN204199271U true CN204199271U (en) 2015-03-11

Family

ID=52657246

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420667151.8U Active CN204199271U (en) 2014-11-10 2014-11-10 A kind of filling pile cage of reinforcement hangs fastening devices

Country Status (1)

Country Link
CN (1) CN204199271U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105297711A (en) * 2015-11-25 2016-02-03 中国一冶集团有限公司 Reusable pile foundation steel reinforcement cage pile locating device and locating method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105297711A (en) * 2015-11-25 2016-02-03 中国一冶集团有限公司 Reusable pile foundation steel reinforcement cage pile locating device and locating method
CN105297711B (en) * 2015-11-25 2017-03-22 中国一冶集团有限公司 Reusable pile foundation steel reinforcement cage pile locating device and locating method

Similar Documents

Publication Publication Date Title
CN104480930B (en) A kind of filling pile cage of reinforcement hangs fixing construction method
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN207392772U (en) Cable-free wind rope steel stand alignment system
CN205429566U (en) Crossing structure
CN202658590U (en) Integral assembled drilling platform
CN204434116U (en) A kind of hanging device for interior courtyard lifting pipeline
CN105464456A (en) Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter
CN208168317U (en) A kind of lower extension platform of high-altitude construction
CN202483154U (en) High bearing capacity suspending scaffold
CN102561689B (en) Construction method for cantilever lifting scaffold
CN203877731U (en) Hoisting and dragging device used in PHC (Pre-stress High-strength Concrete) pipe pile construction site
CN204199271U (en) A kind of filling pile cage of reinforcement hangs fastening devices
CN104499706A (en) Elevator well template platform and construction method thereof
CN203794505U (en) Internal climbing steel beam conveying device of internal climbing movable arm tower crane
CN203461720U (en) Simple cantilever hoisting machine
CN202785257U (en) Control device used for hoisting and positioning steel reinforcement cage of manual hole digging piles
CN202988556U (en) Special lifting appliance for angle-steel type frame body
CN205575534U (en) Lattice formula groined type support body lifting means
CN202785255U (en) Turnover hoisting tool for reinforced concrete pipe joint
CN201873949U (en) Bride prestress stretch-draw trolley
CN203782575U (en) Stay cable hanging and tension construction device
CN104746860A (en) Water tank air cast-in-place method for inclined-pulling formwork of inverted cone water tower
JP5421805B2 (en) Suspension and pile bracket
CN205132926U (en) Special well word hoist of hydroelectric set tail water ell
CN204980822U (en) Whole hoist of superimposed sheet

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20180914

Granted publication date: 20150311

PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20190618

Granted publication date: 20150311