CN105464456A - Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter - Google Patents
Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter Download PDFInfo
- Publication number
- CN105464456A CN105464456A CN201511019924.7A CN201511019924A CN105464456A CN 105464456 A CN105464456 A CN 105464456A CN 201511019924 A CN201511019924 A CN 201511019924A CN 105464456 A CN105464456 A CN 105464456A
- Authority
- CN
- China
- Prior art keywords
- tower
- tower body
- helicopter
- arm
- body sections
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
- E04H12/342—Arrangements for stacking tower sections on top of each other
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Suspension Of Electric Lines Or Cables (AREA)
- Electric Cable Installation (AREA)
Abstract
The invention provides a method and lifting sling for assembling an extra-high voltage transmission iron tower through a helicopter. The method for assembling the extra-high voltage transmission iron tower through the helicopter comprises the following steps that 1, the helicopter hoists and fixes an iron tower leg section of the extra-high voltage transmission iron tower to a predetermined area; 2, the helicopter hoists and fixes an iron tower body of the extra-high voltage transmission iron tower to the iron tower leg section; 3, the helicopter hoists and fixes outside cross arms of the extra-high voltage transmission iron tower to the two sides of the iron tower body. According to the method and lifting sling for assembling the extra-high voltage transmission iron tower through the helicopter, the difficulties in a extra-high voltage construction peak season are solved, and the difficulties of difficult construction in special areas are further solved. By means of a success of assembling the extra-high voltage transmission iron tower through the helicopter, the construction technology of applying the helicopter to hoist an iron tower is pushed to a higher level, the range of types of hoisted towers is enlarged, and the demonstration effect and social influence both have great significance.
Description
Technical field
The present invention relates to UHV transmission apparatus field, particularly a kind ofly go straight up to the method that unit founds UHV transmission steel tower, or a kind of suspender used when going straight up to unit and founding UHV transmission steel tower.
Background technology
More than 1000kV extra high voltage line steel pipe sections tower has tower Duan Chong, the feature that frame construction physical dimension is large.Show according to data from investigation, at present, only there is the case history adopting Mi-26 hoisting large-size TV transmission tower in Russia, there is no the data of other types lifting extra-high voltage tower.In the face of extra-high voltage project Large scale construction; helicopter has become the important selection solving the outstanding problems such as the extreme construction difficult problem of engineering construction, response environment protection, construction safety, duration pressure, advances the strengthened research of helicopter in extra-high voltage project is built very necessary.
Summary of the invention
In order to solve the problem of UHV transmission tower erection difficulty, the invention provides and a kind ofly go straight up to method and the suspender that unit founds UHV transmission steel tower, this is gone straight up to unit and founds the method for UHV transmission steel tower and suspender and solve extra-high voltage and build the difficult problem that peak period faces, and also solves a difficult problem for Special zone difficulty construction.
The technical solution adopted for the present invention to solve the technical problems is:
Go straight up to the method that unit founds UHV transmission steel tower, comprise the following steps:
Step 1, helicopter this is gone straight up to unit stand UHV transmission steel tower tower leg section lifting be fixed on the predetermined area;
Step 2, helicopter this is gone straight up to unit stand UHV transmission steel tower tower body lifting be fixed in this tower leg section;
This is gone straight up to the both sides that this tower body is fixed in outside cross-arm lifting that unit founds UHV transmission steel tower by step 3, helicopter.
Go straight up to the suspender used when unit founds UHV transmission steel tower, this suspender is the suspender used in above-mentioned steps 1, and this suspender comprises the gusset, shoulder pole frame and the multiple Chain block that connect successively from the top down.
The invention has the beneficial effects as follows, this is gone straight up to unit and founds the method for UHV transmission steel tower and suspender and solve extra-high voltage and build the difficult problem that peak period faces, and also solves a difficult problem for Special zone difficulty construction.This is gone straight up to the construction technology of success to application helicopter steel tower that unit founds UHV transmission steel tower and pushes higher level to and expand lifting tower scope, and its demonstration effect and social influence all have great significance.
Accompanying drawing explanation
The Figure of description forming a application's part is used to provide a further understanding of the present invention, and schematic description and description of the present invention, for explaining the present invention, does not form inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is the front view of going straight up to the UHV transmission steel tower that unit has stood.
Fig. 2 is the schematic diagram of a helicopter complete tower leg.
Schematic diagram when Fig. 3 is helicopter complete No. 23 tower body sections.
Fig. 4 is the top view of hanger.
Fig. 5 is the front view of hook.
Fig. 6 is the front view that helicopter laterally docks the state one when assembling outside cross-arm.
Fig. 7 is the front view that helicopter laterally docks the state two when assembling outside cross-arm.
Fig. 8 is the front view that helicopter laterally docks the state three when assembling outside cross-arm.
Fig. 9 is the front view that helicopter laterally docks the state four when assembling outside cross-arm.
Figure 10 is the front view that helicopter laterally docks the state five when assembling outside cross-arm.
Reference numeral in figure: 5, No. 5 tower body sections; 6, No. 6 tower body sections; 7, No. 7 tower body sections; 8, No. 8 tower body sections; 9, No. 9 tower body sections; 10, No. 10 tower body sections; 11, No. 11 tower body sections; 12, No. 12 tower body sections; 13, No. 13 tower body sections; 17, No. 17 tower body sections; 23, No. 23 tower body sections; 24, No. 24 tower body sections; 26, tower leg section;
30, suspender; 31, gusset; 32, shoulder pole frame; 33, Chain block; 34, lifting bolt; 35, bracing wire;
40, complete tower leg; 41, tower leg; 42, lower tower body unit; 43, temporary guy;
50, outside cross-arm; 51, hanger; 52, upper main material; 53, link up with; 54, nearside cross-arm; 55, upper steel pipe; 56, insertion rod; 57, clamping groove plate; 58, V-way.
Detailed description of the invention
It should be noted that, when not conflicting, the embodiment in the application and the feature in embodiment can combine mutually.Below with reference to the accompanying drawings and describe the present invention in detail in conjunction with the embodiments.
Go straight up to the method that unit founds UHV transmission steel tower, comprise the following steps:
Step 1, helicopter this is gone straight up to unit stand UHV transmission steel tower tower leg section lifting be fixed on the predetermined area;
Step 2, helicopter this is gone straight up to unit stand UHV transmission steel tower tower body lifting be fixed in this tower leg section;
This is gone straight up to the both sides that this tower body is fixed in outside cross-arm lifting that unit founds UHV transmission steel tower by step 3, helicopter;
This goes straight up to UHV transmission steel tower that unit stood as shown in Figure 1.
In the present embodiment, this is gone straight up to the tower leg section that unit founds UHV transmission steel tower and contains four tower legs 41, in order to improve lifting efficiency, in step 1, tower body section (i.e. No. 24 tower body sections 24) bottom in this tower body is equally divided into and four tower legs 41, four lower tower body unit 42 one to one, four tower legs 41 and four lower tower body unit 42 (i.e. No. 24 tower body sections 24 1/4th) are made to connect one to one into four complete tower legs (40), complete tower leg 40 lifting can be fixed on the predetermined area by this helicopter at every turn like this, by repeatedly back and forth this helicopter complete the lifting of this tower leg section 26 and No. 24 tower body sections 24.Namely this helicopter is when completing lifting tower leg section 26, tower body section bottom in tower leg section 26 and this tower body can be completed lifting simultaneously.Preferably, the size and shape of each complete tower leg 40 is identical, and the weight of each complete tower leg 40 is 7 tons ~ 8 tons.
In the present embodiment, in step 1, complete tower leg 40 lifting is fixed on the predetermined area and is comprised the following steps by this helicopter:
Step 1.1, this helicopter are taken a complete tower leg 40 and are flown to this predetermined area;
Step 1.2, this helicopter are taken this complete tower leg 40 and are hovered to this overhead, predetermined area, this helicopter is commanded to decline, when this complete tower leg 40 drops to this predetermined area, the temporary guy of colligation on this complete tower leg 40 is untied, this complete tower leg 40 is pulled to ready position and tentatively connects;
Step 1.3, push-and-pull or crowbar mode is adopted to make the lower margin flange eyelet of complete tower leg 40 lower end aim at stone bolt on this predetermined area, this helicopter continues to decline, and makes complete tower leg 40 fall to penetrating this stone bolt by the outer gear guide rail that this predetermined area is arranged;
Step 1.4, complete tower leg 40 in place safe after, carry out temporary fixed to complete tower leg 40, as shown in Figure 2.
Concrete, complete tower leg 40 lifting is fixed on the predetermined area and is comprised the following steps by this helicopter:
Helicopter is flown to above the hanging piece of stock ground, and slowly drop to work clasp joint near the ground, constructor hangs hanging piece.
Step 1.1, commander's helicopter rise, and take hanging piece and fly to construction point (i.e. tower position);
Step 1.2, helicopter take hang hanging piece to overhead, tower position hovering, by ground control's helicopter falling head, to hanging piece close to base surface time, the temporary guy of colligation on hanging piece is untied by constructor, is pulled to bracing wire off-the-shelf with ground and is tentatively connected;
Step 1.3, constructor adopt push-and-pull or crowbar mode (crowbar can penetrate perforate on flange strength plate) to rotate tower leg principal post, make lower margin flange eyelet alignedly foot bolt, notify that helicopter declines by ground, flight side person in charge, the section of hanging, by the outer gear guide rail that basis is arranged, falls to penetrating stone bolt;
Step 1.4, tower leg in place safe after, temporary guy 43 fixes rapidly by constructor;
Step 1.5, helicopter disengagement work hook, return to stock ground;
Step 1.6, repeat four times by above-mentioned steps 1.1 to step 1.5, complete after 4 complete tower legs 40 lift, constructor Deng Ta completes overall package work.
The points for attention of step 1:
1, tower leg section is when stock ground is assembled, and place should be smooth.Behaviour is flat for tower section each fulcrum instrument, and ground erection bolt is fastening intact, ensures that the distortion of tower section principal post is less and conforms with the regulations.
2, this programme gives preliminary suspension centre rope length, and actual suspension centre rope length is determined by real model experiment, by test, construction operation guiding book determines that length performs.Real model experiment is taked crane to debug and is hung vertical center of gravity, determine a rope length, and checks that column foot flange stiffener is screwed into impact to nut, carries out with regard to bit test.
3, answer the good temporary guy of lay, connect tackle pulley, in order to Fast Installation bracing wire; Hand fit's operation should be trained in advance, completes tower leg lifting operation at the appointed time to meet; After 1/4 tower leg section is hung and stood, adjustment bracing wire makes central connection point outwards be reserved with 100mm ~ 200mm gap, during to avoid installing with hypomere, extension occurs and touches phenomenon.
4, during the assembling of stock ground, at the upper end installation in position guide rail of No. 24 tower body sections 24.Flange in the bottom eyelet and corresponding stone bolt will carry out obvious mark.
5, tower position construction point should draw layout plan, and arranges the putting position and the artificial each facility installed of mending material according to figure.
In the present embodiment, the tower body of this UHV transmission steel tower contains multiple tower body section, and in step 2, this helicopter lifts each tower body section successively according to being obedient to from bottom to top, and this helicopter comprises the following steps when a lifting tower body section:
Step 2.1, this helicopter are taken this tower body section and are hovered to this overhead, predetermined area, this helicopter is commanded to decline, make the limit rope of the lower end of this tower body section enclose frame and enter position to be connected upper rall, continue to fall to making this tower body section through this guide rail landing in the alignment pin on the flange at this position to be connected, make the eyelet accurate contraposition on the flange eyelet of the lower end of this tower body section and the flange at this position to be connected, as shown in Figure 3.
Concrete, in step 2, this helicopter comprises the following steps when a lifting tower body section (only to install No. 23 tower body sections 23):
Helicopter is flown to above the hanging piece of stock ground, and slowly drop to work clasp joint near the ground, constructor hangs hanging piece;
Step 2.1, the section of hanging are after construction point and overhead are flown in stock ground, slowly drop to tower leg section overhead, make the limit rope of No. 23 tower body sections 23 enclose guide rail that frame enters No. 24 tower body section 24 tops is coordinated by flight teacher and ground control, in the alignment pin of the section of hanging that falls again on the flange of guide rail landing to 24 tower body section 24, lower flange eyelet accurate contraposition in order;
Step 2.2, after ground control's suspension centre rope comes off, helicopter returns to stock ground;
Step 2.3, polishing rod member and bolt, flat mouth physical dimension in measurement, checks the section of hanging deformation;
Step 2.4, measure whole tower inclination conditions, errorless rear fastening bolt;
Step 2.5, dismounting auxiliary part and device.
Step 2.6, by above-mentioned steps 2.1 to step 2.5 repeatedly, until complete the assembly working of tower body entirety.
The points for attention of step 2:
1, the section of hanging is after the assembling of stock ground, and slinging with crane checks that whether each portion size is accurate, checks that after checking it slings, the deflection of tower section conforms with the regulations.
2, after tower section completes lifting by interior guide rail autofitting, the artificial upper timely erection bolt of tower; Timely installation loss of weight rod member, removes reinforcing bar.
3, as there is bolt hole decentraction phenomenon in tower section rear stub in place, can use to have a look at punching and penetrate the good bolt hole of concentric situation, coordinates hand hammer by artificial hammering, make tower section progressively return, then in empty bolt hole, penetrate bolt, finally extract again and have a look at punching, replace having a look at punching with bolt.
In the present embodiment, the tower body of this UHV transmission steel tower contains multiple tower body section, it is tower body section bottom in this tower body that the plurality of tower body section comprises No. 5 tower body sections 5, No. 6 tower body sections 6, No. 7 tower body sections 7, No. 8 tower body sections 8, No. 9 tower body sections 9, No. 10 tower body sections 10, No. 11 tower body sections 11, No. 12 tower body sections 12, No. 13 tower body sections 13, No. 17 tower body sections 17, No. 23 tower body sections 23 of connecting successively from the top down and No. 24 tower body sections 24, No. 24 tower body sections 24; No. 5 tower body sections 5, No. 7 tower body sections 8, No. 9 tower body sections 9, No. 10 tower body sections 10, No. 11 tower body sections 11, No. 12 tower body sections 12, No. 13 tower body sections 13, No. 17 tower body sections 17 and No. 23 tower body sections 23 adopt vertical assembled; No. 6 tower body sections 6, No. 8 tower body sections 8, complete tower leg 40 and this cross-arms adopt horizontal assembling.
Vertical assembled is introduced: when tower sheet assemble on ground, two main materials hang on chock by distribution, and auxiliary material to make inside tower sheet upward after assembling.Sling to tower section height with the two panels tower material that ground has been assembled by crane respectively during lifting, and the main material lower end of tower sheet is overlapped with the ground place of printing adjust tower material angle of inclination with tricing line control tower sheet angle of inclination, utilize the temporary ground anchor on ground that bracing wire is set tower sheet is firmly stable, the slow loose hook of crane.When noting lifting by crane, tower sheet should not leave ground.Utilize the auxiliary material in crane auxiliary installation side, after tower section has been assembled, measure the related datas such as root is opened, inclination.
Horizontal assembling is introduced: assembled on ground by side tower sheet, installs side wedge, need to set temporary guy and carry out firmly, prevent the tower section run-off the straight organized after installing wedge with crane is auxiliary.Another sheet offside tower sheet assembled on ground is sling with crane and has been organized tower section with ground and be connected.After tower section has been assembled, measure the related datas such as root is opened, inclination.
In the step 3 of the present embodiment, outside cross-arm 50 described in helicopter comprises can following steps:
Step 3.1, two hangers 51 are arranged on one to one the end to be connected of two upper main materials 52 of cross-arm 50 outside this, two hooks 53 are arranged on one to one the position to be connected, outer end of two upper steel pipes 55 of the nearside cross-arm 54 outside tower body, hanger 51 is containing the insertion rod 56 arranged in the horizontal direction, hook 53 is containing clamping groove plate 57 and V-way 58, on clamping groove plate 57 containing opening towards hook-type notch, the installation site demand fulfillment of hanger 51 and hook 53 is when insertion rod 56 to be inserted into downwards along V-way 58 in the hook-type notch of clamping groove plate 57 and to rotate cross-arm 50 outside this, outside this, the end to be connected of two of cross-arm 50 upper main materials 52 can correspondingly connect with the position to be connected, outer end of two upper steel pipes 55 of nearside cross-arm 54, as shown in Figure 4 and Figure 5,
Step 3.2, with helicopter, the outside cross-arm 50 of traverse is suspended to the top of nearside cross-arm 54, this helicopter is when suspending in midair, the end to be connected of the upper main materials 52 in two of cross-arm 50, outside is positioned at the top of the end to be connected of main material under two of outside cross-arm 50, cross-arm 50 outside this is made to decline again, until insertion rod 56 is inserted in the hook-type notch of clamping groove plate 57 downwards along V-way 58 downwards, as shown in Figure 6 and Figure 7;
Step 3.3, continue to transfer cross-arm 50 outside this, make outside cross-arm 50 with insertion rod 56 for axle rotates, connect until the end to be connected of main material is corresponding with the position to be connected, outer end of two lower steel pipes of nearside cross-arm 54 under two of outside cross-arm 50, the end to be connected of two of outside cross-arm 50 upper main materials 52 connects with the position to be connected, outer end of two upper steel pipes 55 of nearside cross-arm 54 is also corresponding simultaneously, as shown in Fig. 8 to Figure 10, then outside cross-arm 50 and nearside cross-arm 54 are bolted fixing.
Step 3.4, by above-mentioned steps 3.1 to step 3.3 repeatedly, until the assembly working completing outside cross-arm 50.
Introduce below and a kind ofly go straight up to the suspender used when unit founds UHV transmission steel tower, this suspender is the suspender 30 used in step 1, namely this helicopter lifts described tower leg by suspender 30, this suspender 30 comprises the gusset 31, shoulder pole frame 32 and the multiple Chain block 33 that connect successively from the top down, certainly, this helicopter can pass through this suspender 30 erection tower figure and outside cross-arm 50.
In the present embodiment, gusset 31 is provided with two lifting bolts 34, and the circular head of lifting bolt 34 upward.Gusset 31 is in annular.Along the circumference of gusset 31, between the inner circle and cylindrical of gusset 31, be provided with multiple through hole, the axis of this through hole and the axis being parallel of gusset 31.Lifting bolt 34 is connected and fixed by this through hole and gusset 31.On the surface of gusset 31, be provided with a stiffener between two adjacent these through holes, this stiffener is arranged along the radial direction of gusset 31.The external diameter of gusset 31 is about 1000mm, and the internal diameter of gusset 31 is about 840mm, and the weight of gusset 31 is about 100kg, and acting as of gusset 31 prevents from reversing.
In the present embodiment, connected by four bracing wires 35 between gusset 31 and shoulder pole frame 32.Gusset 31 is connected with helicopter by two lifting ropes, and the rated load of bracing wire 35 is 80kN ~ 120kN.Shoulder pole frame 32 is rectangular, and shoulder pole frame 32 is formed by connecting by four crossbeams and two cant beams, and the bottom of shoulder pole frame 32 is connected with four Chain blocks 33, and the rated load of Chain block 33 is 25kN ~ 40kN.Shoulder pole frame 32 is connected with by hanging piece by Chain block 33.
The above, be only specific embodiments of the invention, can not limit the scope that invention implements with it, so the displacement of its equivalent assemblies, or the equivalent variations done according to scope of patent protection of the present invention and modification, all still should belong to the category that this patent is contained.In addition, the technical characteristic in the present invention and all can using by independent assortment between technical characteristic, between technical characteristic and technical scheme, between technical scheme and technical scheme.
Claims (10)
1. go straight up to the method that unit founds UHV transmission steel tower, it is characterized in that, described in go straight up to the method that unit founds UHV transmission steel tower and comprise the following steps:
Step 1, helicopter this is gone straight up to unit stand UHV transmission steel tower tower leg section lifting be fixed on the predetermined area;
Step 2, helicopter this is gone straight up to unit stand UHV transmission steel tower tower body lifting be fixed in this tower leg section;
This is gone straight up to the both sides that this tower body is fixed in outside cross-arm lifting that unit founds UHV transmission steel tower by step 3, helicopter.
2. according to claim 1ly go straight up to the method that unit founds UHV transmission steel tower, it is characterized in that, in step 1, this helicopter lifts described tower leg by suspender (30), and this suspender (30) comprises the gusset (31), shoulder pole frame (32) and the multiple Chain block (33) that connect successively from the top down.
3. according to claim 1ly go straight up to the method that unit founds UHV transmission steel tower, it is characterized in that, this is gone straight up to the tower leg section that unit founds UHV transmission steel tower and contains four tower legs (41), in step 1, tower body section bottom in this tower body is divided into and four tower legs (41), four lower tower body unit (42) one to one, four tower legs (41) are made to connect one to one into four complete tower legs (40) with four lower tower body unit (42), complete tower leg (40) lifting is fixed on the predetermined area by this helicopter at every turn, by repeatedly back and forth this helicopter complete the lifting of this tower leg section.
4. according to claim 3ly go straight up to the method that unit founds UHV transmission steel tower, it is characterized in that, the size and shape of each complete tower leg (40) is identical, and the weight of each complete tower leg (40) is 7 tons ~ 8 tons.
5. according to claim 3ly go straight up to the method that unit founds UHV transmission steel tower, it is characterized in that, in step 1, complete tower leg (40) lifting is fixed on the predetermined area and is comprised the following steps by this helicopter:
Step 1.1, this helicopter are taken a complete tower leg (40) and are flown to this predetermined area;
Step 1.2, this helicopter are taken this complete tower leg (40) and are hovered to this overhead, predetermined area, this helicopter is commanded to decline, when this complete tower leg (40) drops to this predetermined area, the temporary guy of colligation on this complete tower leg (40) is untied, this complete tower leg (40) is pulled to ready position and tentatively connects;
Step 1.3, push-and-pull or crowbar mode is adopted to make the lower margin flange eyelet of complete tower leg (40) lower end aim at stone bolt on this predetermined area, this helicopter continues to decline, make complete tower leg (40) by the outer gear guide rail that this predetermined area is arranged, fall to penetrating this stone bolt;
Step 1.4, complete tower leg (40) in place safe after, carry out temporary fixed to complete tower leg (40).
6. according to claim 1ly go straight up to the method that unit founds UHV transmission steel tower, it is characterized in that, the tower body of this UHV transmission steel tower contains multiple tower body section, in step 2, this helicopter lifts each tower body section successively according to being obedient to from bottom to top, and this helicopter comprises the following steps when a lifting tower body section:
Step 2.1, this helicopter are taken this tower body section and are hovered to this overhead, predetermined area, this helicopter is commanded to decline, make the limit rope of the lower end of this tower body section enclose frame and enter position to be connected upper rall, continue to fall to making this tower body section through this guide rail landing in the alignment pin on the flange at this position to be connected, make the eyelet accurate contraposition on the flange eyelet of the lower end of this tower body section and the flange at this position to be connected.
7. according to claim 3ly go straight up to the method that unit founds UHV transmission steel tower, it is characterized in that, the tower body of this UHV transmission steel tower contains multiple tower body section, the plurality of tower body section comprises No. 5 tower body sections (5) connected successively from the top down, No. 6 tower body sections (6), No. 7 tower body sections (7), No. 8 tower body sections (8), No. 9 tower body sections (9), No. 10 tower body sections (10), No. 11 tower body sections (11), No. 12 tower body sections (12), No. 13 tower body sections (13), No. 17 tower body sections (17), No. 23 tower body sections (23) and No. 24 tower body sections (24), No. 24 tower body sections (24) are tower body section bottom in this tower body,
No. 5 tower body sections (5), No. 7 tower body sections (8), No. 9 tower body sections (9), No. 10 tower body sections (10), No. 11 tower body sections (11), No. 12 tower body sections (12), No. 13 tower body sections (13), No. 17 tower body sections (17) and No. 23 tower body sections (23) adopt vertical assembled;
No. 6 tower body sections (6), No. 8 tower body sections (8), complete tower leg (40) and this cross-arms adopt horizontal assembling.
8. according to claim 1ly go straight up to the method that unit founds UHV transmission steel tower, it is characterized in that, in step 3, described in helicopter, outside cross-arm (50) comprises lower step:
Step 3.1, two hangers (51) are arranged on one to one the end to be connected of two upper main materials (52) of cross-arm outside this (50), two hooks (53) are arranged on one to one the position to be connected, outer end of two upper steel pipes (55) of the nearside cross-arm (54) outside tower body, hanger (51) is containing the insertion rod (56) arranged in the horizontal direction, hook (53) is containing clamping groove plate (57) and V-way (58), clamping groove plate (57) upper containing opening towards hook-type notch, the installation site demand fulfillment of hanger (51) and hook (53) is when insertion rod (56) to be inserted into downwards in the hook-type notch of clamping groove plate (57) along V-way (58) and to rotate cross-arm outside this (50), outside this, the end to be connected of two of cross-arm (50) upper main materials (52) can correspondingly connect with the position to be connected, outer end of two upper steel pipes (55) of nearside cross-arm (54),
Step 3.2, with helicopter, the outside cross-arm (50) of traverse is suspended to the top of nearside cross-arm (54), this helicopter is when suspending in midair, the end to be connected of the upper main materials (52) of outside cross-arm (50) two is positioned at the top of the end to be connected of main material under two of outside cross-arm (50), cross-arm outside this (50) is made to decline again, until insertion rod (56) is inserted in the hook-type notch of clamping groove plate (57) downwards along V-way (58) downwards;
Step 3.3, continue to transfer cross-arm outside this (50), make outside cross-arm (50) with insertion rod (56) for axle rotates, until the end to be connected of main material and the position to be connected, outer end of two lower steel pipes of nearside cross-arm (54) is corresponding connects under two of outside cross-arm (50), the end to be connected of two of outside cross-arm (50) upper main materials (52) and two of nearside cross-arm (54) go up that the position to be connected, outer end of steel pipes (55) is also corresponding to be connected simultaneously.
9. go straight up to the suspender used when unit founds UHV transmission steel tower for one kind, it is characterized in that, this suspender is the suspender (30) used in the step 1 of claim 1, and this suspender (30) comprises the gusset (31), shoulder pole frame (32) and the multiple Chain block (33) that connect successively from the top down.
10. according to claim 9ly go straight up to the suspender used when unit founds UHV transmission steel tower, it is characterized in that, gusset (31) is provided with two lifting bolts (34), connected by four bracing wires (35) between gusset (31) and shoulder pole frame (32), shoulder pole frame (32) is rectangular, and the bottom of shoulder pole frame (32) is connected with four Chain blocks (33).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201511019924.7A CN105464456B (en) | 2015-12-30 | 2015-12-30 | Go straight up to method and suspender that unit founds UHV transmission steel tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201511019924.7A CN105464456B (en) | 2015-12-30 | 2015-12-30 | Go straight up to method and suspender that unit founds UHV transmission steel tower |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105464456A true CN105464456A (en) | 2016-04-06 |
CN105464456B CN105464456B (en) | 2017-09-01 |
Family
ID=55602570
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201511019924.7A Active CN105464456B (en) | 2015-12-30 | 2015-12-30 | Go straight up to method and suspender that unit founds UHV transmission steel tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105464456B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108374595A (en) * | 2018-01-26 | 2018-08-07 | 中国电力科学研究院有限公司 | A kind of assembled staggered floor cross-arm tangent tower and its vertical tower method |
CN109779380A (en) * | 2019-01-23 | 2019-05-21 | 浙江省送变电工程有限公司 | Laterally docking assembles the quick tightening device of angle steel tower and group tower method to helicopter |
CN109850762A (en) * | 2019-03-29 | 2019-06-07 | 南京铁道职业技术学院 | A kind of electric power hanging apparatus |
CN112302350A (en) * | 2019-07-26 | 2021-02-02 | 璧典寒 | Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower |
CN114278146A (en) * | 2021-12-28 | 2022-04-05 | 国网天津市电力公司建设分公司 | Robot intelligent tower assembling construction method for high-voltage transmission iron tower |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4189892A (en) * | 1977-07-19 | 1980-02-26 | Erickson Air Crane Co. | Angle guide apparatus |
JP3947542B2 (en) * | 2005-03-25 | 2007-07-25 | 関西電力株式会社 | Steel tower lifting and dismantling method and tower receiving bracket for the method |
JP4099491B2 (en) * | 2005-05-16 | 2008-06-11 | 関西電力株式会社 | Steel tower assembly method and work jig by helicopter |
CN102064493A (en) * | 2010-11-02 | 2011-05-18 | 北京交通大学 | Method for paying off overhead transmission line by unmanned helicopter |
CN102108801A (en) * | 2011-01-17 | 2011-06-29 | 中国电力科学研究院 | Guide rail system for use on end part of cross arms of helicopter-assembled power transmission line iron tower |
JP4755479B2 (en) * | 2005-10-12 | 2011-08-24 | 株式会社エフテック | Tower dismantling method by helicopter |
CN102310862A (en) * | 2010-07-09 | 2012-01-11 | 侯卫平 | Low-altitude and high-speed rail, namely, integral regional low-altitude and high-speed traffic transportation equipment and method |
CN202131824U (en) * | 2010-12-21 | 2012-02-01 | 国家电网公司直流建设分公司 | Serial guide rail used for helicopter assembly transmission line iron tower |
CN102561788A (en) * | 2010-12-21 | 2012-07-11 | 国家电网公司直流建设分公司 | Guide track series for helicopter assemblage power transmission line iron tower |
US8375650B2 (en) * | 2009-10-09 | 2013-02-19 | International Towers, Inc. | Rapid deployable structure for remote installation |
CN103031978A (en) * | 2012-12-12 | 2013-04-10 | 中国电力科学研究院 | Installation assisting system for erection of power transmission line iron tower and erection method for iron tower |
CN104278874A (en) * | 2013-07-06 | 2015-01-14 | 湖北省电力公司黄冈供电公司 | Method for assembling iron tower through high-voltage power transmission lines |
-
2015
- 2015-12-30 CN CN201511019924.7A patent/CN105464456B/en active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4189892A (en) * | 1977-07-19 | 1980-02-26 | Erickson Air Crane Co. | Angle guide apparatus |
JP3947542B2 (en) * | 2005-03-25 | 2007-07-25 | 関西電力株式会社 | Steel tower lifting and dismantling method and tower receiving bracket for the method |
JP4099491B2 (en) * | 2005-05-16 | 2008-06-11 | 関西電力株式会社 | Steel tower assembly method and work jig by helicopter |
JP4755479B2 (en) * | 2005-10-12 | 2011-08-24 | 株式会社エフテック | Tower dismantling method by helicopter |
US8375650B2 (en) * | 2009-10-09 | 2013-02-19 | International Towers, Inc. | Rapid deployable structure for remote installation |
CN102310862A (en) * | 2010-07-09 | 2012-01-11 | 侯卫平 | Low-altitude and high-speed rail, namely, integral regional low-altitude and high-speed traffic transportation equipment and method |
CN102064493A (en) * | 2010-11-02 | 2011-05-18 | 北京交通大学 | Method for paying off overhead transmission line by unmanned helicopter |
CN202131824U (en) * | 2010-12-21 | 2012-02-01 | 国家电网公司直流建设分公司 | Serial guide rail used for helicopter assembly transmission line iron tower |
CN102561788A (en) * | 2010-12-21 | 2012-07-11 | 国家电网公司直流建设分公司 | Guide track series for helicopter assemblage power transmission line iron tower |
CN102108801A (en) * | 2011-01-17 | 2011-06-29 | 中国电力科学研究院 | Guide rail system for use on end part of cross arms of helicopter-assembled power transmission line iron tower |
CN103031978A (en) * | 2012-12-12 | 2013-04-10 | 中国电力科学研究院 | Installation assisting system for erection of power transmission line iron tower and erection method for iron tower |
CN104278874A (en) * | 2013-07-06 | 2015-01-14 | 湖北省电力公司黄冈供电公司 | Method for assembling iron tower through high-voltage power transmission lines |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108374595A (en) * | 2018-01-26 | 2018-08-07 | 中国电力科学研究院有限公司 | A kind of assembled staggered floor cross-arm tangent tower and its vertical tower method |
CN109779380A (en) * | 2019-01-23 | 2019-05-21 | 浙江省送变电工程有限公司 | Laterally docking assembles the quick tightening device of angle steel tower and group tower method to helicopter |
CN109850762A (en) * | 2019-03-29 | 2019-06-07 | 南京铁道职业技术学院 | A kind of electric power hanging apparatus |
CN112302350A (en) * | 2019-07-26 | 2021-02-02 | 璧典寒 | Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower |
CN114278146A (en) * | 2021-12-28 | 2022-04-05 | 国网天津市电力公司建设分公司 | Robot intelligent tower assembling construction method for high-voltage transmission iron tower |
Also Published As
Publication number | Publication date |
---|---|
CN105464456B (en) | 2017-09-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105464456A (en) | Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter | |
CN101434366B (en) | Hoisting tool and hoisting method for column component | |
CN101537976B (en) | Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof | |
CN104480930B (en) | A kind of filling pile cage of reinforcement hangs fixing construction method | |
CN106012852B (en) | Support integrally falls frame construction method | |
CN206692235U (en) | A kind of steel structure dome lifts by crane erecting device | |
CN106703420A (en) | Large-span ball joint spherical wire frame cluster rocker hoisting construction method | |
CN207294093U (en) | A kind of large span steel truss integral lifting apparatus | |
CN210193173U (en) | Large-scale H shaped steel stand hoist and mount hoist that breaks off relations fast | |
CN202658590U (en) | Integral assembled drilling platform | |
CN205429566U (en) | Crossing structure | |
CN104989111B (en) | Steel construction high level construction method for hanging | |
CN100494576C (en) | Method for setting up box-type bridge body maintain engineering box outer hanging falsework | |
CN203625889U (en) | Hanging cage structure for large-diameter hole drilling cast pile reinforcement cage hanging | |
CN109826082B (en) | Construction method for installing decorative structure in multi-tower combined space of cable-stayed bridge | |
CN103132702A (en) | Longspan pipe truss pulling bar lifting and overhead rotating emplacing construction method | |
CN205243147U (en) | Hoist that uses during special high -tension transmission iron tower of helicopter assemblage | |
CN103979442B (en) | The method of 6400 tons of Hydraulic double-type crane lifting cost tropsch reactors | |
CN103556626A (en) | Hanging structure for hoisting large-diameter hole drilling filling pile steel bar cage | |
CN218027231U (en) | Simple device for lowering bottom basket of hanging basket | |
CN210505201U (en) | Equipment for hoisting reinforcing steel bars in batches | |
CN110040632A (en) | A kind of segmental hoisting construction method of large span section steel beam | |
CN208265608U (en) | Large-tonnage hoisting device for reinforcement cage | |
CN104085832A (en) | Flexible component lifting device and lifting method thereof | |
CN203625891U (en) | Hanging structure for large-diameter hole drilling cast pile reinforcement cage hanging |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 100031 No. 86 West Chang'an Avenue, Beijing, Xicheng District Patentee after: STATE GRID CORPORATION OF CHINA Patentee after: State Grid Power Space Technology Co.,Ltd. Address before: 100031 No. 86 West Chang'an Avenue, Beijing, Xicheng District Patentee before: State Grid Corporation of China Patentee before: SGCC GENERAL AVIATION Co.,Ltd. |