CN208297161U - Construction soil sampling apparatus based on linkage drive technology - Google Patents
Construction soil sampling apparatus based on linkage drive technology Download PDFInfo
- Publication number
- CN208297161U CN208297161U CN201820665882.7U CN201820665882U CN208297161U CN 208297161 U CN208297161 U CN 208297161U CN 201820665882 U CN201820665882 U CN 201820665882U CN 208297161 U CN208297161 U CN 208297161U
- Authority
- CN
- China
- Prior art keywords
- sampling
- cavity
- connecting rod
- soil
- linkage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Sampling And Sample Adjustment (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The utility model discloses a kind of construction soil sampling apparatus based on linkage drive technology, including body, the left and right side bottom symmetrical of body is equipped with stable cavity, the inside of body is equipped with linkage chamber and sampling cavity, the bottom wall of inner cavity of sampling cavity is equipped with sampling hole, the soil sampler matched with sampling hole is equipped in sampling cavity, the bottom end of soil sampler is equipped with drill bit, the periphery bottom end of soil sampler is arranged with the position-limiting drum matched with sampling cavity, the top of soil sampler is fixedly connected with connecting rod, it the roof of the top perforation sampling cavity of connecting rod and links and chamber and is fixedly connected with turntable, connecting rod is equipped with graduation mark, the periphery of connecting rod is arranged with tuning drive gear;The utility model drives fixing anchor bar high-speed rotation by motor, so that fixing anchor bar is under the action of anchor head, go deep into soil layer, so that inside entire fixing anchor bar insertion soil, to stablize entire body, so that overall stability greatly improves, geotechnological work is taken convenient for soil sampler completion, greatly improves the accuracy of sampling.
Description
Technical field
The utility model relates to building engineering equipment technical field, specially a kind of building based on linkage drive technology is applied
Work soil sampling apparatus.
Background technique
Architectural engineering, refer to by construction to all kinds of building constructions and its affiliated facility and route matched with its, pipeline,
The installation activity of equipment is formed by engineering entity.Wherein " building construction ", which refers to, top cover, beam column, wall, basis and can
Inner space is formed, meets people's production, lives, learns, the engineering that public activity needs.
Civil engineering course teaching steering committee divides into civil engineering, architectural environment and energy source use engineering, discharge hydroscience
It is opened with engineering, architectural electricity and intelligence, architecture, urban and rural planning, Landscape, engineering management and project cost, real estate
Hair and management and 9 disciplines steering committees of estate management (the hereinafter referred to as specialized guidance committee), corresponding " institution of higher education
Bachelor degree catalogue " in building class, Building class, Management Science and Engineering class (part) and industrial and commercial administration class (part) 11 specially
Industry.
Architectural engineering is the planning carried out for newly-built, reconstruction or enlarging building construction and auxiliary construction facility, surveys
It the engineering entity and route matched with its, pipeline, equipment of every technical work and completion such as examines, design and constructs, be completed
Installing engineering.Also refer to the construction engineering of various houses, building, also known as building operation amount.This part investment must emerging work
Dynamic material, is just able to achieve by construction activities.
Wherein the construction engineering of " building construction " includes workshop, theater, hotel, shop, school, hospital and house etc.,
The dynamic material of necessary emerging work is extended in its newly-built, reconstruction, is just able to achieve by construction activities;" auxiliary construction facility " refers to and builds with house
Build matched water tower, shed for bicycle, pond etc.." installation of route, pipeline, equipment " refers to and building construction and its affiliated facility phase
The routes such as matched electrical, plumbing, HVAC, communication, intelligence, elevator, pipeline, equipment installation activity.
With the drive of rapid development and the accession to WTO of China market economy, construction industry is just from labor-intensive to technology
Intensity conversion, advanced technology and process equipment will be used largely, and the professional degree in many posies is higher and higher, with high content of technology
Post continue to bring out again, building enterprise needs producing and managing First Line not only by textbook education in large quantities, but also grasps skilled
Technology and the labour type talent for understanding management work.Although country implements economic adjustment from macroscopical total amount level, for those
Overall development lags behind the bottleneck industry of national economic development level, and country will increasing policy supports.
According to the statistical data of State Statistics Bureau, 2010-2011, Chinese architecture construction industry keeps fast-developing gesture
Head.Architectural engineering industry realizes 3565.11 hundred million yuan of income from sales within 2010, increases by 58.59% on a year-on-year basis;Total industrial output value is
3488.90 hundred million yuan, increasing by 99.86% on a year-on-year basis;385.20 hundred million yuan of total value are generated profit, increases by 99.86% on a year-on-year basis.
2011, although macroeconomic situation is uncertain, Real Estate Regulation was severe, and investment of railway construction slows down, by
Guarantee house construction accelerates and water conservancy construction investment speedup positive influence on both side, the direct pull need of three classes engineering machinery
Ask: concreting machinery, large excavator and loading machine then show as indirectly pulling for the demand of other types.Therefore,
Architectural engineering industry in China's still keeps faster speedup within 2011.2011, national architectural engineering industry total assets reached
4409.63 hundred million yuan, increasing by 28.61% on a year-on-year basis;Income from sales reaches 5180.92 hundred million yuan, more than 2010 whole year, increases by a year-on-year basis
33.88%.The huge infrastructure construction of China is still in fast-developing phase, urbanization, new countryside construction, railway, highway foundation
Facility, the lasting holding of public facility construction investment are high-order.China's security housing, high-speed rail, water conservancy construction year during " 12th Five-Year Plan "
It invests respectively up to 800,000,000,000 yuan, 700,000,000,000 yuan and 200,000,000,000 yuan, concreting machinery, earthmoving machinery etc. can substantially be driven to build work
The development of journey class.
Currently, needing to generally investigate the soil of construction ground before engineering construction, soil monitoring and soil measurement formula, data are used to
Judge the depth of ground and the weight of total building, be construction before it is especially important one work, it is necessary to outfit meet holostrome, etc.
The soil sample collector of amount and convenient requirement, existing soil sample collector is although of simple structure and low cost, still, time-consuming, take
Power, and stablize poor, sampling frequent the case where tilting, lead to soil sample inaccuracy, influences testing result.
Utility model content
The purpose of this utility model is to provide it is a kind of based on linkage drive technology construction soil sampling apparatus, with
Solve the problems mentioned above in the background art.
To achieve the above object, the utility model provides the following technical solutions:
A kind of construction soil sampling apparatus based on linkage drive technology, including body, the left and right side bottom of body
Portion is symmetrically arranged with stable cavity, and the inside of body is equipped with linkage chamber and sampling cavity, and linkage chamber is located at the top of stable cavity and sampling cavity,
Sampling cavity is located between two linkage chambers, and the bottom wall of inner cavity of sampling cavity is equipped with sampling hole, the axis of sampling cavity and the axis of sampling hole
Line is overlapped, and the soil sampler matched with sampling hole is equipped in sampling cavity, and the axis of sampling cavity is overlapped with the axis of soil sampler, takes soil
The bottom end of device is equipped with drill bit, and the periphery bottom end of soil sampler is arranged with the position-limiting drum matched with sampling cavity, soil sampler and limit
It is to be threadedly coupled between cylinder, for position-limiting drum inner sleeve on the internal chamber wall of sampling cavity, the top of soil sampler is fixedly connected with connecting rod, takes soil
The axis of device is overlapped with the axis of connecting rod, and the roof and linkage chamber of the top of connecting rod perforation sampling cavity and being fixedly connected turns
Disk, the axis of connecting rod are overlapped with the axis of turntable, are rotation connection between connecting rod and body, and connecting rod is equipped with scale
Line, the periphery of connecting rod are arranged with tuning drive gear, and tuning drive gear is ring structure, if the bottom end of tuning drive gear is uniformly equipped with
Heavenly Stems and Earthly Branches strut, tuning drive gear are fixedly connected on body by support rod, and the top end face of body bilateral symmetry is equipped with handle, and two
Handle sets up separately in the left and right sides of connecting rod.
As the further technical solution of the utility model, fixing anchor bar, the bottom end of fixing anchor bar are equipped in stable cavity
Penetrate through the bottom wall of stable cavity and be fixedly connected with anchor head, the top of fixing anchor bar perforation stable cavity and overhang link it is intracavitary, Gu
The top for determining anchor pole is fixedly connected with coupled wheel, and fixing anchor bar is rotatably connected on body by bearing, between two coupled wheels
It is connected by belt, the periphery bottom end of a fixing anchor bar is arranged with driven gear, the inner cavity of the stable cavity equipped with driven gear
Bottom wall is equipped with motor, and the motor shaft of motor is fixedly connected with shaft, and the top of shaft is fixedly connected with to be matched with driven gear
Driving gear.
As the further technical solution of the utility model, sampling cavity is cylindrical cavity.
As the further technical solution of the utility model, tuning drive gear is to select transparent material production.
As the further technical solution of the utility model, handle is U-shaped structure.
As the further technical solution of the utility model, Anti-slip cover is arranged on handle.
As the further technical solution of the utility model, Anti-slip cover is to select rubber material production.
Compared with prior art, the utility model drives fixing anchor bar high-speed rotation by motor, so that fixing anchor bar exists
Under the action of anchor head, go deep into soil layer, so that inside entire fixing anchor bar insertion soil, thus stablize entire body, so that
Overall stability greatly improves, and takes geotechnological work convenient for soil sampler completion, greatly improves the accuracy of sampling;Overall structure is simple,
Easy to operate, stability is high, and convenient for the progress of sampling operation, and sampling precision is high, and data are accurate, provide accurately for architectural engineering
Data support.
Detailed description of the invention
Fig. 1 is a kind of knot of the front view of the construction soil sampling apparatus based on linkage drive technology of the utility model
Structure schematic diagram;
Fig. 2 is a kind of knot of the top view of the construction soil sampling apparatus based on linkage drive technology of the utility model
Structure schematic diagram;
Fig. 3 is a kind of knot of the soil sampler of the construction soil sampling apparatus based on linkage drive technology of the utility model
Structure schematic diagram.
In figure: 1- body, 2- stable cavity, 3- fixing anchor bar, 31- anchor head, 4- bearing, 5- coupled wheel, 6- belt, 7- are driven
Gear, 8- driving gear, 9- shaft, 10- motor, 11- linkage chamber, 12- sampling cavity, 13- position-limiting drum, 14- soil sampler, 15- are bored
Head, 16- sampling hole, 17- connecting rod, 18- graduation mark, 19- turntable, 20- tuning drive gear, 21- support rod, 22- handle.
Specific embodiment
The technical solution of the patent is explained in further detail With reference to embodiment.
Please refer to Fig. 1~3, a kind of construction soil sampling apparatus based on linkage drive technology, including body 1, institute
The left and right side bottom symmetrical for stating body 1 is equipped with stable cavity 2, and the inside of body 1 is equipped with linkage chamber 11 and sampling cavity 12, described
Dynamic chamber 11 is located at the top of stable cavity 2 and sampling cavity 12, and the sampling cavity 12 is located between two linkage chambers 11, the stable cavity
Fixing anchor bar 3 is equipped in 2, the bottom end of the fixing anchor bar 3 penetrates through the bottom wall of stable cavity 2 and is fixedly connected with anchor head 31, fixed anchor
Bar 3 top perforation stable cavity 2 and overhang linkage chamber 11 in, the top of fixing anchor bar 3 is fixedly connected with coupled wheel 5, Gu
Determine anchor pole 3 to be rotatably connected on body 1 by bearing 4, be connected between two coupled wheels 5 by belt 6, a fixation
The periphery bottom end of anchor pole 3 is arranged with driven gear 7, and the bottom wall of inner cavity of the stable cavity 2 equipped with driven gear 7 is equipped with motor
10, the motor shaft of the motor 10 is fixedly connected with shaft 9, and the top of the shaft 9 is fixedly connected with to be matched with driven gear 7
Driving gear 8;The sampling cavity 12 is cylindrical cavity, and the bottom wall of inner cavity of sampling cavity 12 is equipped with sampling hole 16, the axis of sampling cavity 12
Line is overlapped with the axis of sampling hole 16, and the soil sampler 14 matched with sampling hole 16, the axis of sampling cavity 12 are equipped in sampling cavity 12
Line is overlapped with the axis of soil sampler 14, and the bottom end of the soil sampler 14 is equipped with drill bit 15, and the periphery bottom end of soil sampler 14 is arranged
There is the position-limiting drum 13 matched with sampling cavity 12, be to be threadedly coupled between soil sampler 14 and position-limiting drum 13, in the position-limiting drum 13
It covers on the internal chamber wall of sampling cavity 12, the top of the soil sampler 14 is fixedly connected with connecting rod 17, the axis of soil sampler 14 and company
The axis of extension bar 17 is overlapped, and the roof and linkage chamber 11 of the top perforation sampling cavity 12 of the connecting rod 17 and being fixedly connected turns
The axis of disk 19, connecting rod 17 is overlapped with the axis of turntable 19, is rotation connection, connecting rod 17 between connecting rod 17 and body 1
It is equipped with graduation mark 18, the periphery of connecting rod 17 is arranged with tuning drive gear 20, and the tuning drive gear 20 is ring structure, scale
Pointer 20 is to select transparent material production, and the bottom end of tuning drive gear 20 is uniformly equipped with several support rods 21, and tuning drive gear 20 is logical
It crosses support rod 21 to be fixedly connected on body 1, the top end face bilateral symmetry of the body 1 is equipped with handle 22, two handles
22 set up separately in the left and right sides of connecting rod 17, and handle 22 is U-shaped structure, and Anti-slip cover is arranged on handle 22, and the Anti-slip cover is
Select rubber material production.
When the utility model is used, by hand steered handle 22, stablize entire body 1, then driven and fixed by motor 10
3 high-speed rotation of anchor pole, so that fixing anchor bar 3 gos deep into soil layer under the action of anchor head 31, so that entire fixing anchor bar 3 is inserted
Enter inside soil, to stablize entire body 1, so that overall stability greatly improves, take geotechnological work convenient for the completion of soil sampler 14,
Greatly improve the accuracy of sampling;After body 1 is stablized, by manually rotating clockwise turntable 19, to drive soil sampler 14
Rotated on position-limiting drum 13, so that soil sampler 14 goes out sampling hole 16, go deep into soil layer, carry out soil sample, by graduation mark 18 with
The cooperation of tuning drive gear 20 can observe soil layer depth selection, intuitively convenient for the acquisition of data;It is inverse after the completion of taking geotechnique to make
Hour hands rotate turntable 19 and sampling work can be completed to promote soil sampler 14, and overall structure is simple, easy to operate, stability
Height, convenient for the progress of sampling operation, and sampling precision is high, and data are accurate, provides accurate data for architectural engineering and supports;In order to
The convenience that turntable 19 rotates is improved, can uniformly be equipped with several poke rods in the periphery of turntable 19, and cover on poke rod
Equipped with non-slip texture, so that the intensity of sampling work further decreases, the convenience of work is improved.
The preferred embodiment of the patent is described in detail above, but this patent is not limited to above-mentioned embodiment party
Formula within the knowledge of one of ordinary skill in the art can also be under the premise of not departing from this patent objective
Various changes can be made.
Claims (7)
1. the construction soil sampling apparatus based on linkage drive technology, which is characterized in that including body (1), body (1)
Left and right side bottom symmetrical is equipped with stable cavity (2), and the inside of body (1) is equipped with linkage chamber (11) and sampling cavity (12), and link chamber
(11) it is located at the top of stable cavity (2) and sampling cavity (12), sampling cavity (12) is located between two linkage chambers (11), sampling cavity
(12) bottom wall of inner cavity is equipped with sampling hole (16), and the axis of sampling cavity (12) is overlapped with the axis of sampling hole (16), sampling cavity
(12) soil sampler (14) matched with sampling hole (16), the axis of sampling cavity (12) and the axis weight of soil sampler (14) are equipped in
It closes, the bottom end of soil sampler (14) is equipped with drill bit (15), and the periphery bottom end of soil sampler (14) is arranged with to match with sampling cavity (12)
The position-limiting drum (13) of conjunction, is to be threadedly coupled between soil sampler (14) and position-limiting drum (13), and position-limiting drum (13) inner sleeve is in sampling cavity
(12) on internal chamber wall, the top of soil sampler (14) is fixedly connected connecting rod (17), the axis and connecting rod of soil sampler (14)
(17) axis is overlapped, and the top of connecting rod (17), which penetrates through the roof of sampling cavity (12) and links chamber (11) and be fixedly connected, to be turned
The axis of disk (19), connecting rod (17) is overlapped with the axis of turntable (19), is that rotation connects between connecting rod (17) and body (1)
It connects, connecting rod (17) is equipped with graduation mark (18), and the periphery of connecting rod (17) is arranged with tuning drive gear (20), tuning drive gear
It (20) is ring structure, the bottom end of tuning drive gear (20) is uniformly equipped with several support rods (21), and tuning drive gear (20) passes through branch
Strut (21) is fixedly connected on body (1), and the top end face bilateral symmetry of body (1) is equipped with handle (22), two handles (22)
Set up the left and right sides in connecting rod (17) separately.
2. the construction soil sampling apparatus according to claim 1 based on linkage drive technology, which is characterized in that steady
Determine to be equipped with fixing anchor bar (3) in chamber (2), the bottom end of fixing anchor bar (3) penetrates through the bottom wall of stable cavity (2) and is fixedly connected with anchor head
(31), top perforation stable cavity (2) of fixing anchor bar (3) and overhang in linkage chamber (11), the top of fixing anchor bar (3) is solid
Surely it is connected with coupled wheel (5), fixing anchor bar (3) is rotatably connected on body (1) by bearing (4), between two coupled wheels (5)
It is connected by belt (6), the periphery bottom end of a fixing anchor bar (3) is arranged with driven gear (7), is equipped with driven gear (7)
The bottom wall of inner cavity of stable cavity (2) is equipped with motor (10), and the motor shaft of motor (10) is fixedly connected shaft (9), the top of shaft (9)
End is fixedly connected with the driving gear (8) matched with driven gear (7).
3. the construction soil sampling apparatus according to claim 1 based on linkage drive technology, which is characterized in that take
Sample chamber (12) is cylindrical cavity.
4. the construction soil sampling apparatus according to claim 1 based on linkage drive technology, which is characterized in that carve
Degree pointer (20) is to select transparent material production.
5. the construction soil sampling apparatus according to claim 1 based on linkage drive technology, which is characterized in that mention
Hand (22) is U-shaped structure.
6. the construction soil sampling apparatus according to claim 5 based on linkage drive technology, which is characterized in that mention
Hand is arranged with Anti-slip cover on (22).
7. the construction soil sampling apparatus according to claim 6 based on linkage drive technology, which is characterized in that anti-
Sliding sleeve is to select rubber material production.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820665882.7U CN208297161U (en) | 2018-05-07 | 2018-05-07 | Construction soil sampling apparatus based on linkage drive technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820665882.7U CN208297161U (en) | 2018-05-07 | 2018-05-07 | Construction soil sampling apparatus based on linkage drive technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208297161U true CN208297161U (en) | 2018-12-28 |
Family
ID=64702985
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820665882.7U Expired - Fee Related CN208297161U (en) | 2018-05-07 | 2018-05-07 | Construction soil sampling apparatus based on linkage drive technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208297161U (en) |
-
2018
- 2018-05-07 CN CN201820665882.7U patent/CN208297161U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206503558U (en) | A kind of engineering geological investigation hand drill rig | |
CN207908195U (en) | A kind of device of portable soil sampling and moisture measurement | |
CN203965184U (en) | Built-in rotor segment soil sampler | |
CN206300806U (en) | Soil collecting device | |
CN108398290A (en) | A kind of construction soil sampling apparatus based on linkage drive technology | |
CN205936594U (en) | Three -dimensional geological data gathers portable equipment with transmission | |
CN206189376U (en) | Highway is soil sampling device for engineering | |
CN108930261B (en) | Civil engineering is with device of fetching earth fast | |
CN203455187U (en) | Rotary type soil sample collector | |
CN208297161U (en) | Construction soil sampling apparatus based on linkage drive technology | |
LU102449B1 (en) | A Stratified Sampling Device in Middle and Deep Soil | |
CN203310651U (en) | Portable rotary soil sample collector | |
CN208350411U (en) | Construction soil sampling apparatus based on U-shaped frame support technology | |
CN206540748U (en) | Multifunctional soft clay hollow cylinder sample sample preparation device | |
CN109060405A (en) | A kind of soil investigation sampling mid-deep strata soil layering sampler | |
CN211060883U (en) | Area measuring instrument for land planning design | |
CN209028213U (en) | A kind of cut and cover method deep basal pit inner lining concrete side wall integration automated watch-keeping facility | |
CN206583629U (en) | Soil sample collector and soil sampling apparatus | |
CN108398289A (en) | A kind of construction soil sampling apparatus based on U-shaped frame support technology | |
CN211877445U (en) | Hydraulic ring geological survey sampling equipment | |
CN201891410U (en) | Device capable of real-time recording of drill speed parameters of drilling machine | |
CN207300624U (en) | A kind of Geological Engineering sampler | |
CN106680055A (en) | Sample preparation device of multifunctional soft clay hollow cylindrical test sample and sample preparation method | |
CN209493933U (en) | A kind of mechanically decoupled ground device of civil engineering sampling | |
CN208366651U (en) | A kind of soil investigation sampling mid-deep strata soil layering sampler |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20191029 Address after: 314000 room 502B, building C9, Dahua city garden, Jiaxing Economic and Technological Development Zone, Zhejiang Province Patentee after: Jiaxing Hajin New Material Co., Ltd Address before: 317 200 No. 5, Shantou Zhu Group, Xiazhu Village, Chicheng Street, Tiantai County, Taizhou City, Zhejiang Province Patentee before: Zhu Youfu |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |