CN208039631U - 一种框架柱纵向钢筋定位装置 - Google Patents

一种框架柱纵向钢筋定位装置 Download PDF

Info

Publication number
CN208039631U
CN208039631U CN201820458439.2U CN201820458439U CN208039631U CN 208039631 U CN208039631 U CN 208039631U CN 201820458439 U CN201820458439 U CN 201820458439U CN 208039631 U CN208039631 U CN 208039631U
Authority
CN
China
Prior art keywords
iron plate
longitudinal reinforcement
frame column
positioning
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820458439.2U
Other languages
English (en)
Inventor
李迥
邱荣昌
方宝兔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUNYOUNG CONSTRUCTION GROUP CO Ltd
Original Assignee
SUNYOUNG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUNYOUNG CONSTRUCTION GROUP CO Ltd filed Critical SUNYOUNG CONSTRUCTION GROUP CO Ltd
Priority to CN201820458439.2U priority Critical patent/CN208039631U/zh
Application granted granted Critical
Publication of CN208039631U publication Critical patent/CN208039631U/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

一种框架柱纵向钢筋定位装置,由带内方孔的纵向钢筋定位铁板、铁板固定件组成,其中带内方孔的纵向钢筋定位铁板的铁板条中心线四角点及中心线上均匀分布的钢筋定位圆孔,圆孔外边到铁板边沿距离满足钢筋保护层厚度要求,铁板固定件一端与铁板焊接连接,另一端有定位用的圆孔;框架柱钢筋绑扎好并完成支模后,将本装置的套在框架柱纵筋的上方,让纵筋穿过钢筋定位圆孔,然后调节纵向钢筋定位铁板位置同设计定位一致,通过铁板固定件的另一端定位孔将装置固定在模板上,从而实现框架柱纵向钢筋位置满足设计要求。

Description

一种框架柱纵向钢筋定位装置
技术领域
本实用新型涉及到建筑施工领域内的一种框架柱纵向钢筋定位装置,主要适用于工业与民用建筑结构中框架柱纵向钢筋安装与混凝土浇筑施工时柱顶纵筋定位。
背景技术
目前房屋建筑工程的框架结构的钢筋绑扎时大多采用手工绑扎,由于采用手工绑扎因人的差异性,易出现绑扎间距差异,纵向钢筋的水平和竖向位置不能满足设计要求。另外由于纵向钢筋缺乏定位装置固定,在混凝土浇筑过程中由于混凝土流动产生的侧向推力及混凝土浇筑过程浇捣人员碰触钢筋等原因导致框架柱纵钢筋移位,从而造成纵筋位置偏差超出规范要求与保护层厚度不能满足设计和规范要求,特别是目前装配式建筑兴起,所有的装配式构件大多都不是从首层开始全装配式,而是一到二层采用现浇,三层及以上采用预制构件,这里存在现浇与预制的转换过渡,如果转换层的现浇框架柱纵筋出现位置偏差将造成首层预制的柱对位不准,安装困难,这成了目前框架结构和框架剪力墙结构等施工的质量通病,很难避免,困搅着施工技术与管理人员。
发明内容
为了解决目前钢筋混凝土结构中的框架柱施工质量通病,从确保框架柱纵筋位置及其保护层厚度,方便上层预制框架柱安装出发,我们设计出了一种框架柱纵向钢筋定位装置,由带内方孔的纵向钢筋定位铁板、铁板固定件组成,其中带内方孔的纵向钢筋定位铁板的铁板条中心线四角点及中心线上均匀分布的钢筋定位圆孔,圆孔外边到铁板边沿距离满足钢筋保护层厚度要求,铁板固定件一端与铁板焊接连接,另一端有定位用的圆孔;框架柱钢筋绑扎好并完成支模后,将本装置的套在框架柱纵筋的上方,让纵筋穿过钢筋定位圆孔,然后调节纵向钢筋定位铁板位置同设计定位一致,通过铁板固定件的另一端定位孔将装置固定在模板上,从而实现框架柱纵向钢筋位置满足设计要求。
附图说明
下面结合附图对本实用新型做进一步说明。
图1装置横剖面图
图中1.带内方孔的纵向钢筋定位铁板 2. 铁板条带 3.钢筋定位圆孔 4.铁板固定件 5.定位孔;
具体实施方式
1、工厂内根据框架柱的设计尺寸选择同样大小的铁板,为减轻定位铁板的重量,铁板中心锯成方形孔,锯方形孔的大小确保锯后剩下的铁板条带的宽度满足钢筋定位孔开凿的要求;
2、根据框架柱中纵向钢筋设计位置进行钢筋定位孔的开孔,确保钢筋定位圆孔的圆心与框架柱纵筋中心在同一位置;
3、钢筋定位圆孔完成后,选择楔形铁板,并在楔形铁板一端开孔,制作四个铁板固定件;
4、将四个楔形铁板开孔端的另一端焊接固定到铁板条中间这样框架柱纵向钢筋定位装置制作完成;
5、框架柱钢筋绑扎好并完成支模后,将本装置的套在框架柱纵筋的上方,让纵筋穿过钢筋定位圆孔;
6、调节纵向钢筋定位铁板位置同设计定位一致,通过铁板固定件的另一端定位孔将装置固定在模板上,从而实现框架柱纵向钢筋位置满足设计要求。

Claims (1)

1.一种框架柱纵向钢筋定位装置,由带内方孔的纵向钢筋定位铁板、铁板固定件组成,其中带内方孔的纵向钢筋定位铁板的铁板条中心线四角点及中心线上均匀分布的钢筋定位圆孔,圆孔外边到铁板边沿距离满足钢筋保护层厚度要求,铁板固定件一端与铁板焊接连接,另一端有定位用的圆孔;框架柱钢筋绑扎好并完成支模后,将本装置的套在框架柱纵筋的上方,让纵筋穿过钢筋定位圆孔,然后调节纵向钢筋定位铁板位置同设计定位一致,通过铁板固定件的另一端定位孔将装置固定在模板上,从而实现框架柱纵向钢筋位置满足设计要求。
CN201820458439.2U 2018-04-03 2018-04-03 一种框架柱纵向钢筋定位装置 Expired - Fee Related CN208039631U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820458439.2U CN208039631U (zh) 2018-04-03 2018-04-03 一种框架柱纵向钢筋定位装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820458439.2U CN208039631U (zh) 2018-04-03 2018-04-03 一种框架柱纵向钢筋定位装置

Publications (1)

Publication Number Publication Date
CN208039631U true CN208039631U (zh) 2018-11-02

Family

ID=63945596

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820458439.2U Expired - Fee Related CN208039631U (zh) 2018-04-03 2018-04-03 一种框架柱纵向钢筋定位装置

Country Status (1)

Country Link
CN (1) CN208039631U (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109849178A (zh) * 2019-01-24 2019-06-07 五冶集团上海有限公司 一种装配式建筑钢筋固定件
CN110685442A (zh) * 2019-08-26 2020-01-14 锦萧建筑科技有限公司 装配式建筑基础柱钢筋控制装置
CN111101655A (zh) * 2019-12-19 2020-05-05 中建一局集团第三建筑有限公司 一种钢筋定位装置及其施工方法
CN111502309A (zh) * 2020-05-21 2020-08-07 中国建筑第五工程局有限公司 一种钢筋定位片和钢筋定位装置

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109849178A (zh) * 2019-01-24 2019-06-07 五冶集团上海有限公司 一种装配式建筑钢筋固定件
CN110685442A (zh) * 2019-08-26 2020-01-14 锦萧建筑科技有限公司 装配式建筑基础柱钢筋控制装置
CN111101655A (zh) * 2019-12-19 2020-05-05 中建一局集团第三建筑有限公司 一种钢筋定位装置及其施工方法
CN111101655B (zh) * 2019-12-19 2021-07-30 中建一局集团第三建筑有限公司 一种钢筋定位装置及其施工方法
CN111502309A (zh) * 2020-05-21 2020-08-07 中国建筑第五工程局有限公司 一种钢筋定位片和钢筋定位装置
CN111502309B (zh) * 2020-05-21 2024-05-10 中国建筑第五工程局有限公司 一种钢筋定位片和钢筋定位装置

Similar Documents

Publication Publication Date Title
CN208039631U (zh) 一种框架柱纵向钢筋定位装置
CN108149825B (zh) 一种用于装配式建筑的预制板、预制板与梁的连接方式及施工方法
CN105507470B (zh) 一种周边叠合整体装配式楼板及其施工方法
WO2015184476A1 (en) Precast concrete falsework bubbledeck element and process of manufacturing thereof
CN104294920B (zh) 一种u形钢混凝土组合梁与异形钢管混凝土柱的节点组件及制备方法
CN108708273A (zh) 一种分块式桥面板湿接缝连接形式
CN209585431U (zh) 框架柱模壳及免模板钢筋混凝土柱
JP2010242390A (ja) 鉄骨ブレースを有する柱・梁の接合部の接合方法とその構造
CN105113781B (zh) 一种悬挑架梁侧全预埋安装搭设装置
CN104153463B (zh) 装配整体式框架体系及其施工方法
CN103835440A (zh) 外包钢丝网水泥砂浆板-混凝土组合承重矩形柱及作法
CN207048152U (zh) 叠合梁与叠合板连接系统
CN105839851B (zh) 采用分段连接形成的预制框架柱的施工方法
RU73891U1 (ru) Плитная железобетонная конструкция
KR200408399Y1 (ko) 투명 데크 플레이트를 이용한 슬라브 시공 구조
CN204899041U (zh) 板筋上下保护层控制马凳
CN102561383B (zh) 塔吊底座安装方法
CN207582978U (zh) 一种楼板厚度控制装置
CN106760189B (zh) 高层建筑结构转换梁施工方法
CN102535684A (zh) 防平面外倒塌填充墙
CN203008239U (zh) 钢筋保护层垫块
CN208415101U (zh) 开孔板式索-塔连接结构
DE1941662A1 (de) Decken- und Dachkonstruktion
CN205502340U (zh) 一种周边叠合整体装配式楼板
CN206053310U (zh) 一种可调节的模板支架

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181102